BHBE – G8 System Impact Study PREPARED ON BEHALF OF THE COMMON USE SYSTEM BY BLACK HILLS CORPORATION TRANSMISSION PLANNING 1. Executive Summary An Interconnection System Impact Study (SIS) was performed by Black Hills Corporation under the guidance of the Common Use System (CUS) Joint Open Access Transmission Tariff Large Generator Interconnection Procedures (LGIP) for the Interconnection Customer to construct and interconnect an 80.5 MW wind farm in western South Dakota. The proposed project consists of thirty-five (35) 2.3 MW Siemens wind turbine generators and will connect to the CUS 230 kV transmission system at a point along the existing Lange to Lookout 230 kV line near Sturgis, SD. The purpose of the study was to: • Analyze the steady state and short circuit conditions for the project • Evaluate transient stability performance • Determine any upgrades to the transmission system that would be required to mitigate any adverse impacts that the proposed project could pose on the reliability and operating characteristics of the transmission system. Steady State Analysis Steady-state voltage and thermal analysis examined system performance without the proposed project in order to establish a baseline for comparison. System performance was re-evaluated with the project in place and compared with the baseline performance to demonstrate the impact of the project on local transmission reliability. The analysis determined that no steady-state criteria were violated as a result of the interconnection. It also showed that the reactive requirements have been met for this project. Stability Analysis Stability analysis evaluated the impact of the proposed project on transmission system performance for both heavy summer and light winter load conditions. The stability analysis identified the project’s impacts on the transmission system following several different disturbances. Stability analysis results showed that no transient stability criteria were violated as a result of the proposed interconnection and verified the project’s Low Voltage Ride-Through (LVRT) capability was in accordance with current NERC/WECC LVRT requirements. Short Circuit Analysis Short circuit analysis was performed in the Feasibility Study (FS) to asses the impact the proposed project would have on the fault current levels and breaker duty in the area. No adverse results were found during the FS for the original interconnection request of 120 MW, as such the impacts were assumed to be less for the smaller request of 80.5 MW and so the short circuit analysis was not performed for the SIS. Conclusions The System Impact Study identified no network upgrades, beyond those required to interconnect the project, to accommodate the 80.5 MW wind project. Network facilities required to interconnect the project are a new three position ring bus intersecting the Lange to Lookout 230 kV line at an estimated cost of $2,300,000. Also, fiber communications would need to be installed on the Lange to Lookout 230 kV line at an estimated cost of $2,000,000 for a total estimated cost of $4,300,000. Estimated time of construction for Network Upgrades is approximately eighteen (18) months from execution of an Interconnection Agreement and receipt of funds. All facilities and equipment beyond the Point of Interconnection station take-off structure will be the sole responsibility of the Interconnection Customer. All new facilities and equipment required to interconnect the project within the substation are considered Network Upgrades and will be funded by the Interconnection Customer but owned by BHP. Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery. 2. Background 2.1. Tariff Black Hills Power (BHP), Basin Electric Power Cooperative (Basin), and Powder River Energy Corporation (PRECorp) own and operate 230 kV transmission facilities in Wyoming and South Dakota which are governed by a FERC approved Joint Open Access Transmission Tariff (Joint Tariff) and commonly referred to as the Common Use System (CUS). Black Hills Power acts as the Tariff Administrator of the Joint Tariff and, as such, is responsible for evaluating and studying all large generator interconnection requests made on the CUS. 2.2. Study Objective The primary objective of the study was to determine whether the proposed interconnection had any adverse impacts on the reliability, stability or operating characteristics of the Bulk Electric System (BES). Comprehensive steady-state and “worst-case” stability performance was evaluated. 2.3. Project Description The project consists of thirty-five (35) 2.3 MW Siemens wind turbine generators, producing up to 80.5 MW total. The project was studied as both a network resource and an energy resource, interconnecting the existing Lange to Lookout 230 kV line. 3. Base Case Development 3.1. Base Case Origin and Year The proposed interconnection is scheduled for the end of the fourth quarter of 2010. The base case originated from the Western Electricity Coordinating Council (WECC). The base case chosen was the 2011 HS1B1P. The case was examined for accuracy and updated. 3.2. Planned Projects The case was updated to include committed projects with in-service dates prior to the facility in-service date which were determined to have an impact on system performance as well as higher queued LGI requests. These projects included: • • • • • • Rapid City Voltage Support Project Wygen 3 The Hughes Transmission Project Dry Fork Station Donkey Creek-Pumpkin Butte-DJ area 230 kV line Teckla Voltage Support Project Should any one of the projects listed above not be complete prior to the proposed project in-service date, the interconnection project may be curtailed due to transmission prior outages or other emergency conditions. These curtailments and/or operating restrictions, if needed, will be developed and identified through operational studies as required. 3.3. Resource Assumptions 3.3.1. Network Resource To dispatch the wind generation as a Network Resource, the generation at Wygen I, Wygen II, Wygen III, and Neil Simpson II, were scaled down on a pro rata basis. 3.3.2. Energy Resource The wind generation was dispatched as an Energy Resource against generating facilities to the south. Specifically, this was accomplished by lowering the generation at the Laramie River Station. 3.4. Area Load 3.4.1. 2011 Heavy Summer The 2011 heavy summer load case was created by updating BHP, CLF&P, and Basin Electric loads to their 2011 peak forecast values 3.4.2. 2011 Light Winter The 2011 light winter load case was created by scaling the area load to 55% of 2011 peak summer forecast values. 3.5. Analytical Tools Power flow simulations were performed using PSS/E simulation software, version 30.3.3. Short-circuit analysis were performed using ASPEN OneLiner, version 10.12. 4. Steady State Analysis Methodology 4.1. Steady State Analysis Methodology To determine if the proposed project caused any adverse impacts to the reliability and operating characteristics of the CUS transmission system, it was evaluated using 2011 peak summer and light winter load levels. A baseline for comparison was established by comparing the voltage and thermal performance of the CUS without and with the proposed project in-service. 4.1.1. Voltage Limits Table 1 presents the voltage criteria used in the primary study area for the steadystate voltage assessment. Table 1: Steady State Voltage Limits Voltage Class 69 kV and Above Acceptable Voltage Range Pre-Contingency Post-Contingency 0.95 to 1.05 p.u. 0.90 to 1.10 p.u 4.1.2. Thermal Limits Normal thermal ratings shall not be violated under system intact conditions, and applicable emergency ratings shall not be exceeded under contingency conditions. Thermal loading on all transmission lines in the CUS are not allowed to exceed 100% of their normal rating. The CUS transmission lines do not have emergency ratings. Transformers are allowed to overload as outlined in Table 2. Table 2: Transformer Overloads Maximum Hours @ Overload ½ Hour 1 Hour 2 Hours Allowable Transformer Overload 153% 135% 120% 4.1.3. Solution Parameters Pre-contingency solution parameters allowed adjustment of load tap-changing (LTC) transformers, static VAR devices including switched shunt capacitors and reactors, and DC taps. Post-contingency solution parameters allowed for adjustment of DC taps and the Rapid City South capacitor only. Generator VAR limits were applied immediately and area interchange control was disabled for all solutions. A fixed-slope decoupled Newton solution method was implemented for all cases. Table 3 lists all of the prior outages and Table 4 lists all contingencies Table 3: Prior Outages List Prior Outage List Wyodak-Hughes 230 kV Lookout-Sturgis Wind 230 kV Lange-Rapid City South 230 kV West Hill-Osage 230 kV Osage-Wyodak 230 kV Yellow Creek-Lookout 230 kV Hughes-Lookout 230 kV Sturgis Wind-Lange 230 kV Rapid City South-West Hill 230 kV Osage-Yellow Creek 230 kV Wyodak-Donkey Creek 230 kV Table 4: Contingencies List Contingencies List (Lines are 230 kV unless noted) Ant Mine-Teckla Ant Mine-Yellow Cake Yellow Cake-Dave John Dave John-Larmie River Dave John-Stegall Wyodak-Osage Osage-Yellow Creek Wyodak-Hughes Wyodak-Donkey Creek Donkey Creek- Pmpkn Bt Teckla-Pmpkn Bt Dave John-Pmpkn Bt Wyodak-Carr Draw Buffalo-Carr Draw Buffalo-Sheridan Buffalo-Kaycee Dryfork-Carr Draw Dryfork-Huges Dryfork-Tongue River West Hill-Osage West Hill-Rapid City South West Hill-Stegall Larmie River-Stegall Lange-Rapid City South Reno-Teckla Reno-Donkey Creek Lookout-Yellow Creek Lookout-Hughes Dave John-Casper Casper-Riverton Dave John-Difficult Rapid City South-DC Tie Hughes-Osage 69 kV Sundance-Lange 69 kV Yellow Crk-Lange 69 kV Sundance-Yelow Crk 69 kV Lookout-Kirk 69 kV Lookout-Spfsh-YCrk 69 kV Pactola-YCrk 69 kV Custer-West Hill 69 kV Cmbl-4th-BF 69 kV Cambell-Lng-Tie 69 kV S Rapid-Cambell 69 kV BFrench-S Rapid 69 kV Wyodak Unit Wygen Unit Wygen II Unit NSS2 Unit BF Unit NSS1 Unit Lange Unit Osage #1 Unit Wyodak 70 Xfmr Wyodak 100 Xfmr Osage Xfmr Lange #1 Xfmr Lange #2 Xfmr Lookout #1 Xfmr Yellow Creek Xfmr West Hill Xfmr Hurghes Xfmr South Rapid Xfmr 5. Steady State Analysis Results 5.1. Heavy Summer Pre-Wind Results There were no criteria violations during the heavy summer pre-wind steady state analysis. 5.2. Heavy Summer Network Resource Results There were no criteria violations during the heavy summer network resource steady state analysis. 5.3. Heavy Summer Energy Resource Results There were no criteria violations during the heavy summer energy resource steady state analysis. 5.4. Light Winter Pre-Wind Results There were no criteria results during the light winter pre-wind steady state analysis. 5.5. Light Winter Network Resource Results There were no criteria violations during the light winter network resource steady state analysis. 5.6. Light Winter Energy Resource Results There were no criteria violations during the light winter energy resource steady state analysis. 5.7. Reactive Requirements The reactive requirements for this project have been met. 6. Stability Analysis Methodology 6.1. Stability Analysis Methodology The objective of stability analysis is to analyze the impact of the project on transient stability performance of the power system for various disturbances. Stability simulations were conducted with and without the proposed interconnection for both 2011 heavy summer and 2011 light winter load level scenarios to confirm performance with respect to applicable criteria. 6.1.1. Stability Performance Criteria The disturbance performance criteria for this study requires that the transient low voltage swing shall not be lower than 0.70 p.u. at any load or non-load bus and the system shall exhibit positive damping following any contingency. Table W-1 of the TPL-(001 thru 004)-WECC-1-CR-System Performance Criteria states that for a NERC Category B contingency, the frequency at a load bus must not dip below 59.6 HZ for more than 6 cycles, but this requirement was applied to all contingencies to simplify the presentation of the results. 6.1.2. Low Voltage Ride-Through Criteria The current NERC/WECC Low Voltage Ride-Through (LVRT) Standard requires generators to remain in-service for 3-phase faults with normal clearing (4-9 cycles) and single line-to-ground faults with delayed clearing that result in a GSU high side voltage of 0.15 per unit or greater 6.2. Stability Fault Descriptions Each dispatch scenario for the 2011 heavy summer and 2011 light winter load cases were simulated with various 3-phase faults applied. Table 5 lists the faults that were simulated. In addition to system intact fault analysis, the prior outages listed in Table 3 were also simulated with the various 3-phase faults. Table 5: Stability Analysis Fault Description Fault Description 3 PH Bus Fault Cleared Element New Tap 230 New Tap-Lookout 230 Line New Tap 230 New Tap-Lange 230 Line Lookout 230 Lookout-Hughes 230 Line Lookout 230 Lookout-Yellow Creek 230 Line Lange 230 Lange-South Rapid 230 Line South Rapid 230 South Rapid-West Hill 230 Line Teckla 230 Teckla-Wind Star 230 Line West Hill 230 West Hill-Osage 230 Line West Hill 230 West Hill-Stegall 230 Line Wyodak 230 Wyodak-Carr Draw 230 Line Wyodak 230 Wyodak-Donkey Creek 230 Line Wyodak 230 Wyodak-Hughes 230 Line Wyodak 230 Wyodak-Osage 230 Line Fault Duration 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 4.25 Cycles 7. Stability Analysis Results There were no stability performance criteria violations observed on the transmission system as a result of the interconnection of the proposed project. All post-contingent voltage dips remained well above the established limit and rotor angle oscillations were positively damped. Additionally, there were no frequency excursions below the 59.6 HZ limit for a period of 6 cycles or more at any of the monitored buses. The faults simulated at the New Tap 230 kV bus confirmed the LVRT capability of the Siemens 2.3 MW and exhibited performance that met NERC/WECC LVRT requirements. 8. Short Circuit Analysis A short circuit analysis was performed as part of the Feasibility Study for the 120 MW project, which exhibited no adverse impacts on the BES. The size of the project has since been reduced to 80.5 MW and the impacts are assumed to be reduced as well. Therefore the short circuit analysis was not performed as part of the SIS. 9. Conclusions This report describes the power flow and stability studies performed to determine the impacts of interconnecting a new 80.5 MW wind plant which intersects the existing Lange to Lookout 230 kV line. The interconnection project as studied is comprised of thirty-five (35) 2.3 MW Siemens wind turbine generators. There were no negative impacts to the transmission system as a result of the proposed interconnection and the reactive requirements have been met for this project. Customerfunded Network Upgrades required for interconnection to the existing Lange to Lookout 230 kV line are listed in Table 6. Table 6: POI Estimated Costs Customer-funded Network Upgrades 3 Position Ring Bus Construct a new 3 position ring bus to interconnect with BHP’s transmission system OPGW Install OPGW between Lange and Lookout 230 kV substations (estimate includes outage costs) Estimated Total Cost Estimated Time Frame $2,300,000 $2,000,000 $4,300,000 18 Months Estimated time of construction for Network Upgrades is approximately eighteen (18) months from execution of an Interconnection Agreement and receipt of funds. All facilities and equipment beyond the Point of Interconnection station take-off structure will be the sole responsibility of the Interconnection Customer. All new facilities and equipment required to interconnect the project within the substation are considered Network Upgrades and will be funded by the Interconnection Customer but owned by BHP. Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery.