PROJECT SUBMITTAL REQUIREMENTS

advertisement
PROJECT SUBMITTAL REQUIREMENTS
11-28-2012
REV 4
8-5-2013 Addendum 1
(p. 2 only)
10-21-2015 Addendum 2
(p. 2 only)
10-30-2015 Addendum 3
(p. 3 only)
PART 1: SUBMITTAL REQUIREMENTS
PART 2: CAD STANDARDS
PART 3: SPACE INVENTORY –
ROOM NUMBER ASSIGNMENT STANDARDS
EXHIBITS
DRAWINGS
CHANGE LOG
For further information, contact:
Facilities Information Resources
Facilities & Services
University of Illinois at Urbana-Champaign
117 Physical Plant Service Building, MC-821
1501 South Oak Street
Champaign, IL 61820
217-333-0923
FandSFIRE@uillinois.edu
www.fs.uiuc.edu/planning/planresources/planresources.cfm
PROJECT SUBMITTAL REQUIREMENTS
PART 1: SUBMITTAL REQUIREMENTS
A line in the margin indicates a change from the previous version. See Change Log for details.
A. Introduction: This document provides clarification of timing, formats, and recipients for
select submittals required by contract. “Exhibit A: Submittal Requirements & Space Inventory
Checklist” is available for use by the Professional Services Consultant (PSC) and the
University for compliance with these Requirements.
B. Related Standards:
1. Space Inventory – Room Number Assignment Standards
2. CAD Standards
C. Definitions:
1. As-Built Drawings – Bid or construction drawings marked up by contractors as work
commences on a project, that reflect as-built conditions in the field.
2. Record Drawings – The final set of drawings created for a project that incorporates
contractor as-builts, including addenda, change orders, supplemental instructions,
field orders and represents conditions as completed in the field.
3. Substantial Completion – The “effective” date on the University “Certificate of
Substantial Completion,” which begins the one year warranty period.
4. Closeout – The end of the one year warranty period, when warranty walk-through
and Quality Assurance Checklists have been complete, and when the project is
“Closed” in the University’s capital project financial services system.
D. Submittals Required: The following submittals are required by the University:
1. Project Manual (with any addenda)
2. Drawings (with any supporting files)
3. Other Submittals as required by Contract.
E. Phase Submittals Required: Submittals are required for the Design and Construction
Phases as applicable per the Professional Services Agreement. Submittals for the Bid
through Close-out Phases are required for all projects.
1.
2.
3.
4.
5.
6.
7.
SCHEMATIC DESIGN
DESIGN DEVELOPMENT
CONSTRUCTION – 50% REVIEW
CONSTRUCTION – 95% REVIEW
BID
SUBSTANTIAL COMPLETION
CLOSE-OUT
PROJECT SUBMITTAL REQUIREMENTS
1
PART 1: SUBMITTAL REQUIREMENTS
11-28-12 REV 4
F. Submittal Delivery and Format Requirements:
1. All submittals shall be accompanied by a Transmittal Form such as one commonly
accepted in the Construction Industry, and including (but not limited to):
a. University Project Number
b. Project Title as appears in PRZM (or as approved by the Board of Trustees)
c. Project Phase
2. For all Phases except Substantial Completion and Close-Out, submittals shall be
delivered as follows by the PSC to:
a. Project Manager:
115 PPSB (MC-800), Facilities & Services, University of Illinois, 1501 S. Oak St.,
Champaign, IL 61820
One (1) Project Manual with any addenda, and one (1) half-size set of Drawings
b. Assoc. Director Code Compliance and Fire Safety: Craig Grant
115 PPSB (MC-800), Facilities & Services, University of Illinois, 1501 S. Oak St.,
Champaign, IL 61820
One (1) Project Manual with any addenda, and one (1) half-size set of Drawings
c.
Quality Assurance: Design
Alaina
Davis
& Construction
Submittal Receiving
117 PPSB (MC-800), Facilities & Services, University of Illinois, 1501 S. Oak St.,
148
Champaign, IL 61820
i. Schematic Design through Construction - 100%:
Two (2) Project Manuals, one (1) full-size set of Drawings, one
(1) half-size set of Drawings, and one (1) electronic set of both
the Project Manual and the Drawings.
ii. Bid:
one (2)
(1)
Three (3) Project Manuals, three (3) Addenda (if any), two
two (2)
full-size set of Drawings, one
(1) half-size set of Drawings, and
one (1) electronic set of the Project Manual, Drawings and
Addenda.
Technology
Services
Plant Design Brian Cockerham
d. CITES
Plant
Design:
2434 DCL (MC-256), CITES Plant Design, University of Illinois, 1304 W.
Springfield Ave., Urbana, IL 61801
One (1) Project Manual with any addenda, and one (1) full-size set of Drawings
e. CITES Classroom and Conference Media Engineering: Jeffery Martin
95 Bevier Hall (MC-187), CITES CCME, University of Illinois, 905 S Goodwin
Ave., Urbana, IL 61801
One (1) Project Manual with any addenda, and one (1) full-size set of Drawings
f.
Project Department:
________________________________________________________________
One (1) Project Manual with any addenda, and one (1)
-size set of Drawings
(deferred maintenance projects require half-size sets)
g. Project College:
________________________________________________________________
One (1) Project Manual with any addenda, and one (1)
-size set of Drawings
h. Note: Additional submittals may be required for specific design projects. Please
contact the Project Manager prior to generating document submittals. (For
example: Fire Department Informational Plan Review Set in Schematic Design
Phase and/or a Schematic Design set to Planner if Board of Trustees Design
Approval is requested).
PROJECT SUBMITTAL REQUIREMENTS
2
PART 1: SUBMITTAL REQUIREMENTS
11-28-12 REV 4
3. At no later than 90 days past date of Certificate of Substantial Completion, submit to:
& Construction
Submittal Receiving
a. Quality Assurance: Design
Alaina
Davis
117 PPSB (MC-800), Facilities & Services, University of Illinois, 1501 S. Oak St.,
148
Champaign, IL 61820
One (1) Record Project Manual (with Addenda incorporated)
One (1) full-size set of Record Drawings (with As-Built mark-ups incorporated)
One (1) electronic set of both the Project Manual and the Drawings
b. Project Department/College:
_____ copies of Record Project Manual (with Addenda incorporated)
_____ copies of ___-size set of Record Drawings (with As-Built mark-ups incorporated)
_____ copies of electronic set of both the Project Manual and the Drawings
G. Project Manual Requirements: The following information shall be in all submittals:
1. Contents: The Project Manual cover shall contain:
a.
b.
c.
d.
e.
Project Title as appears in PRZM (or as approved by the Board of Trustees)
University Project Number
Building Name and Number or Utility Name
Project Phase
If used, University logo in compliance with the Illinois Identity Standards, Graphic
Standards Manual, Campus Logo Guidelines
2. Paper Format: The Project Manual shall be:
a. Bound (no ACCO-style bare metal fasteners, staples, or post bindings)
b. Split into multiple volumes if more than 300 pages double-sided or over 1.5” thick
3. Electronic Format: Files shall be:
a. In Microsoft Word (.doc) format compatible with the currently supported version
(Word 2010 or earlier)
b. One (1) set of pdf files (one section per file), searchable
c. Submitted on CD or DVD
d. Submitted one project per CD or DVD
e. Uncompressed
f. In one folder titled “Project Manual,” and two subfolders titled “pdf” and “Word.”
There shall not be any further subfolders within the “pdf” and “Word” folders
except to denote multiple volumes in accordance with the hardcopy set.
g. Named by specification section number
PROJECT SUBMITTAL REQUIREMENTS
3
PART 1: SUBMITTAL REQUIREMENTS
11-28-12 REV 4
H. Drawing Requirements: These documents shall be:
1. Contents: Drawing title blocks shall contain, but are not limited to:
a.
b.
c.
d.
Project Title as appears in PRZM (or as approved by the Board of Trustees)
University Project Number
Building Name and Number, or Utility Name
Project Phase (Note: a “Record Drawing” stamp on the cover sheet is not
acceptable. Each drawing shall have the Phase indicated in the Revision block.)
e. Drawing Title
f. Drawing Number. Use the following table to assign appropriate Discipline
Designator (required). (Table is in preferred sheet order.)
Discipline
Designator
G
C
L
A
S
FP
P
H
V
HV
TC
E
T
AV
ASB
LBP
HZ
_D
EQP
Discipline
Description
General
Civil (Survey Mapping, Utilities, Soil Borings, Geotechnical, Irrigation)
Landscape
Architectural (including Interiors)
Structural
Fire Protection
Plumbing
Heating
Ventilation
Mechanical (use for smaller projects only)
Temperature Control
Electrical
Telecommunications
Audio/Visual
Asbestos
Lead Paint
Hazardous Materials (other)
Demolition (added after the respective Discipline Designator)
Equipment
g. Revision Number, Date, and Description (Note: a “Record Drawing” stamp on
the cover sheet is not acceptable. Each drawing should have the Phase
indicated in the Revision block.)
h. If used, University logo in compliance with the Illinois Identity Standards, Graphic
Standards Manual, Campus Logo Guidelines
2. Paper Format: Drawings shall be:
a. Bound (sets shall not be submitted loose) (no single corner staples or bare metal
ACCO-style fasteners)
b. In volumes of no more than 100 sheets per volume
c. In compliance with the CAD Standards
PROJECT SUBMITTAL REQUIREMENTS
4
PART 1: SUBMITTAL REQUIREMENTS
11-28-12 REV 4
3. Electronic Format: Files shall be:
a. 1 set of unbound CAD drawings in .dwg format compatible with the currently
supported version (AutoCAD 2012 or earlier), packaged with eTransmit or Packn-go, using the “Place all files in one folder” Transmittal Option
b. 1 set of pdf drawings (one drawing per file), searchable, and rotated to the
correct orientation
c. Uncompressed
d. In one folder titled “Drawings,” and two subfolders titled, “CAD” and “pdf.” There
shall not be any further subfolders with the “CAD” and “pdf” folders except to
denote multiple volumes in accordance with the paper set.
e. In compliance with the CAD Standards
f. Submitted on CD or DVD (no ftp site or e-mail)
g. Submitted one project per CD or DVD
h. Files shall be named by drawing number(s), with no additional prefixes or
suffixes. CAD files with multiple layout tabs shall have the tabs named the same
as the drawing contained on the tab (e.g. A-1, A-2). The only exception to this is
the addition of a numeric prefix that allows the files to sort in the same order as
the paper drawing set.
examples: G1.pdf
001_G1.pdf
C100-C104.dwg
003_C100-C104.dwg
Note: for CAD drawings, represent drawing range – do not list all drawings found in the file
i.
Extraneous objects beyond the drawing extents in “model space” shall be
removed.
j. Blocks shall not be exploded.
k. Drawings shall be purged.
l. Drawings shall be zoomed out to display entire sheet or model.
m. Non-pertinent reference (x-refs) files shall be removed from the drawing file.
n. All necessary files shall be included with the CAD file, including, but not limited
to, xrefs, fonts, hatch, line types, and plot styles (.ctb, .pcs and .stb).
I.
Electronic Media (CD-Rom or DVD) Label Requirements: Labels shall contain:
a.
b.
c.
d.
e.
f.
g.
University Project Number, Name and CDB Number (if applicable)
University Building Number and Name
University Project Manager
Consultant Name and Contact Information
Project Phase
Content Description (e.g.: “Project Manual”, “Project Drawings”, etc.)
Date of Submittal Documents (i.e. dates of drawings or project manuals – not the
date the CD or DVD was created)
h. Date CD or DVD Created
J. Validation of Deliverables: The University reserves the right to request a new submittal at
the consultant’s expense if the documents submitted are not in compliance with the Project
Submittal Requirement Standards, Space Inventory - Room Number Assignment Standards,
and CAD Standards.
PROJECT SUBMITTAL REQUIREMENTS
5
PART 1: SUBMITTAL REQUIREMENTS
11-28-12 REV 4
PROJECT SUBMITTAL REQUIREMENTS
PART 2: CAD STANDARDS
CHAPTER I: UTILIZING THE CAD STANDARDS
A. Introduction: This chapter describes how to conform to the CAD Standards, the purpose,
guidelines, and related procedures.
B. Related Documents:
1. Exhibit B, CAD Standard Master Layer List
C. References:
1. United States National CAD Standard Guidelines Version 3.1
D. Purpose: Provide for a common medium of information exchange. In fact, the true power
and potential of CAD is the ability to re-use and share the information contained within the
CAD document. The key to realizing this potential is common organizing principles–standards
for the production and dissemination of CAD information. The standard organization of files,
layers and entities, as well as standardized software applications is essential for effective
work and communication. Standards are necessary to ensure that:
1. CAD drawings and data created in one phase (e.g., design) are readily usable in
subsequent phases (e.g., facility management).
2. Drawings and data are applicable for their intended use.
3. Drawings and data are compatible with the available CAD equipment and software.
4. Drawings and data created for one project or project discipline, are compatible with
those created for others.
5. Drawings and data can be transferred and integrated with other applications, such as
facility management.
6. Drawings and data created in one department of the University are consistent with
those developed by the other departments.
7. The compatibility of the University CAD drawings and data with pertinent national,
international and industry standards is maintained.
E. Guidelines: To ensure that the University of Illinois and its Consultants conform to the
broader scope of the proposed National CAD Standard, sponsored by the National Institute of
Building Sciences (NIBS) CADD Council, these Standards incorporate recommended
guidelines from the following:
1. United States National CAD Standard Guidelines Version 3.1
F. Comprehensive Facilities Management Strategy: The University of Illinois has multiple
information management systems that require data be specifically formatted for compatibility.
This document sets performance standards for CAD data delivered to the University. The
University does not intend to influence the methods or means of practice of outside
Consultants. Consultants may use any CAD system to develop construction documents for
PROJECT SUBMITTAL REQUIREMENTS
6
Error! Reference source not found.
11-28-12 REV 4
the University, as long as the delivered data conforms to the current University CAD
Standards.
Commitment: The University is committed, however, to enforcing the standards of
information delivery that ensure predictability and the ability to easily reuse information. As a
result, these CAD Standards will be included as part of the Professional Services Consultant
Requirements: Project Submittal Requirements.
H. Scope: This data specification covers all Construction Documents prepared by or on behalf
of the University. CAD drawings shall be provided for all Projects, regardless of size. The
deliverables described in this manual shall be provided for each sheet that is issued for
construction in a Project and shall include all supporting data files that are used to produce
the finished sheets. If additional electronic design drawings or 3D models are provided, it is
the responsibility of the Consultant to initiate discussion with the Chief Engineering
Draftsman, Planning Resources to determine an acceptable format for those deliverables.
I.
Application: Anyone who is going to prepare CAD data for the University, including
University staff, Contractors, and Consultants, shall read and become familiar with this
document before proceeding with any work. (The term "Consultant" used in this manual
refers to the person or organization who is preparing the CAD data, whether the person or
organization is part of the University or not.)
J. Basic CAD Software Requirements: The designated CAD software for the University is
Autodesk’s AutoCAD. All CAD files are required to be delivered in AutoCAD’s .dwg file
format.
K. CAD Application Software: CAD application software packages operate on top of, or in
conjunction with, the basic CAD software to extend its capabilities. The extensions enhance
design, drafting and modeling productivity and link non-graphic attribute data to the graphic
entities. All CAD application packages used by the University, or its Consultants, which
modify or create CAD layers or other entities shall comply with these Standards.
L. Inquiries about the CAD Standards: These Standards will be most effective for the
University and most usable for Consultants if there is communication between Consultants,
the Owner’s Representative and the Chief Engineering Draftsman, Planning Resources.
Consultants should ask questions about the CAD Standards before beginning work.
Concerns regarding the impact of the CAD standards on a particular Project shall be
discussed with the Owner’s Representative and the Chief Engineering Draftsman, Planning
Resources.
Consultants’ questions are valuable because they help the University understand the realworld conditions of each Project’s design and construction process. Questions will raise
issues that will result in better CAD Standards.
M. Requests for Improving the CAD Standards: The content of this manual is intended to be
neither static nor all-inclusive. Suggestions for improvements are encouraged so that
subsequent updates reflect the needs of the University. Submit requests, as well as any
pertinent new information, to the Chief Engineering Draftsman, Planning Resources.
PROJECT SUBMITTAL REQUIREMENTS
7
Error! Reference source not found.
11-28-12 REV 4
CHAPTER II: TECHNICAL REQUIREMENTS FOR CAD STANDARDS
A. Introduction: The organization and format of the CAD deliverables shall support the
requirements of the University Project for design, construction, bidding and archiving. The
deliverable shall also readily support the integration of information into other University facility
management systems with minimal additional effort.
B. Drawing Setup: This chapter describes how to organize and set up CAD drawings for the
University. Consultants shall obtain prior approval from the Owner’s Representative and
Chief Engineering Draftsman, Planning Resources for any exceptions to the drawing set up
Standards. Consultants shall submit documentation that shows the files affected and how
they deviate from the Standards.
1. Drawing Units: Architectural CAD files shall be drawn using architectural (feet and
inches). Civil engineering CAD files shall be drawn using decimal (feet and
hundredths). No metric equivalents. NO METRIC EQUIVALENTS.
2. Drawing Accuracy: All CAD drawings shall be drafted using precision input
employing the most accurate source material available. For all drawing entities, zero
tolerance is required, all lines meet at intersections, straight lines are straight, blocks
are inserted properly without overlap, etc.
Consultants are responsible for the accuracy of all CAD drawings delivered to the
University, regardless of the accuracy of CAD drawings of previous projects furnished
by the University as a convenience to the consultant.
3. Drawing Scale: Objects created in model space shall be drawn at 1:1 scale
(e.g. a 100-foot wall will be drawn to 100 feet and a 36-inch column will be drawn to
36 inches).
The following types of CAD models may be drawn to any scale: schedules, riser
diagrams, schematic diagrams and single line diagrams.
4. Drawing Origin and Registration: The origins of CAD files shall be defined at
coordinates 0, 0, 0. This is typically the lower left corner of the building. For nonrectilinear buildings a logical origin point shall be established. The model shall be
oriented so North is either to the top (^) or left (<) on the drawing document.
The origin point shall remain consistent between all CAD files in a Project. This is
critical for correct registration of different CAD files when referenced together,
aligning the various views of the facility. Registration of electronic data shall be
maintained so the information will be usable in future applications.
a. Exception: Civil engineering CAD files (Topographic-Site Surveys, Building
Site Plans, Utility Site Plans etc.) shall use true geographic coordinates for
their origins. Horizontal Datum shall be based upon Illinois State Coordinate
System East Zone North American Datum of 1983 ( 2011) “NAD 1983
ILLINOIS STATE PLANE, EAST ZONE” and North American Vertical
Datum 1988, “NAVD 1988”.
5. Graphic Representation of Entities
a. Curved Entities: Circles, arcs and ellipses shall be created as individual
entities, not of line segments.
PROJECT SUBMITTAL REQUIREMENTS
8
Error! Reference source not found.
11-28-12 REV 4
b. Entity Properties: Entity properties such as color, line weight, and linetype
shall be set BYLAYER, for purposes of clarity.
Line weight and color affect the use of CAD data in different ways. Line
weight typically is most effective when working with plotted CAD files. Plots,
or reproductions of plots, are typically monochrome. Utilizing line weights
can be an effective means of communicating important information about the
facility and the design Project.
Color is most useful when displaying the CAD data on a computer screen.
Colors allow users to readily identify systems and unique types of
information.
Consultants shall select line weights and colors that promote effective use of
the CAD data, in both plotted and electronic formats.
6. Line Type Scale: Line type scale shall be set so that each line type is recognizable,
easily identified, and distinguishable to individuals who are working in the CAD files
and in final plotted output.
7. Text Requirements
a. The text height requirement for all University of Illinois Cad files shall be 1/10
of an inch minimum.
b. Text shall be all upper case, except for cases where symbols require lower
case letters.
c. Text shall be placed in the CAD file with enough space around it, to allow for
legibility when the CAD file is plotted and reproduced.
d. Text placed at an angle shall be readable from bottom or right edge of the
plotted sheet. Typically text shall be place at 0 or 90 degrees.
e. Text placed along (aligned above or below) an object at an angle other than
0 or 90 degrees is acceptable.
8. Dimension Requirements
a. Associative dimensions shall be used.
b. Dimension style names shall be consistent between CAD files within a
Project.
9. Blocks: Any graphic entity that occurs repeatedly in drawings shall be made into a
block. Insertion points for blocks shall be consistent with its placement in the
drawing. Use a logical insertion point (center of circle, bottom left corner of object,
etc.). Keep names simple and descriptive. AutoCAD block names shall be unique
within each Project. Nested blocks contain more than one block definition. Nested
blocks are permitted but should be avoided whenever possible. Blocks shall conform
to the United States National CAD Standard Guidelines Version 3.1.
PROJECT SUBMITTAL REQUIREMENTS
9
Error! Reference source not found.
11-28-12 REV 4
10. Hatching: Do not use polylines with increased width as a replacement for poché or
hatching.
11. Xref (External Reference) Files: Xrefs may be used to subdivide a large CAD
drawing into several smaller, more efficient drawings. The use of this procedure will
reduce drawing size, increase performance, improve operator efficiency and make
coordination of disciplines easier. Xrefs may also be used to split a drawing by
disciplines. There shall be no specific drive or directory references associated with
the xrefs. All xrefs shall reside in the same directory as the drawing files.
C. Layers: The University has adopted the CAD layer naming convention published by the
United States National CAD Standard Version 3.1. Consultants shall follow this layer naming
system when producing CAD files for the Project.
Layer names and assignments are shown in Exhibit 00100-1, CAD Standard Master Layer
List. The layer table categorizes layers by discipline, and by type of information. This table
also shows several items for each layer, as follows: a complete listing of all layer names, a
detailed definition for each layer, and the presentation graphics associated with each layer,
including color, and line type.
Consultants who wish to use additional layers shall submit a list of proposed layer names to
the Chief Engineering Draftsman, Planning Resources.
1. Layer Format: The University’s layer guidelines are organized as a hierarchy. The
convention utilizes a scheme of naming layers with four field groups. The four groups
are discipline code, major group, minor group and status field:
Discipline
Code
Major Group
Minor Group
-
-
Status Field
-
2. Discipline Code: The Discipline Code is a two-character field with the second
character either a hyphen or a user-defined modifier. The defined codes are the
same for both layers and file names. Table 1 shows the letters that shall be used for
the first character of the discipline code.
Code
Discipline
A
Architectural
C
Civil
E
Electrical
F
Fire Protection
G
General
H
Heating
HZ
I
PROJECT SUBMITTAL REQUIREMENTS
Hazardous Materials
Interiors
10
Error! Reference source not found.
11-28-12 REV 4
L
Landscape
M
Mechanical
P
Plumbing
S
Structural
T
Telecommunications
V
Ventilation
Table 1: CAD layer discipline codes
3. Major Group: Major groups are a four-character field used to identify the building
system. Major groups are typically grouped with specific discipline codes. For
example, a drawing might contain the following layers:
a. A-WALL Walls
b. A-DOOR Doors
c. C-PKNG Parking Lots
4. Minor Group: Minor groups add an additional set of information to the layer names.
It is an optional, four-character field that further differentiates major groups into types
of information. For example, A-WALL-PRHT indicates architecture, new, wall, partial
height.
5. User-Definable Fields: The minor group field can be defined by the user, allowing
additional layers to be added to accommodate special Project requirements. This
shall only be done if a defined layer does not apply to a Project. Some examples of
layers using a user-defined minor group field are as follows:
a.
b.
c.
d.
e.
A-DOOR-METL Metal doors
A-WALL-STRC Walls to structure
A-FURN-PNL1 Furniture panels from manufacturer 1
A-FURN-PNL2 Furniture panels from manufacturer 2
Common Layers Used in All Files
6. Annotation Layers: Annotation comprises text, dimensions, sheet borders, detail
references, and other elements on CAD drawings that do not represent physical
aspects of a building. Annotation is designated by the major group "ANNO." See
University of Illinois Standard Layers List Exhibit B, CAD Standard Master Layer List
for examples of annotation layers.
7. Status layers: The status field is an optional, four-character field that designates the
phase of construction and status of the elements. This field is optional and is only
needed when phases of work need to be differentiated.
The status field is always placed as the last field of the layer name. In a simple layer
name such as A-WALL, the status field would be the third field, A-WALL-DEMO. In a
more detailed layer name, the status field would be the fourth field, A-WALL-INTRDEMO. See University of Illinois Standard Layers List Exhibit B, CAD Standard
Master Layer List for status field designators.
D. Preparing Drawings for Submittal: Refer to Part 1: Submittal Requirements, Section H:
Drawing Requirements.
PROJECT SUBMITTAL REQUIREMENTS
11
Error! Reference source not found.
11-28-12 REV 4
PROJECT SUBMITTAL REQUIREMENTS
PART 3: SPACE INVENTORY - ROOM NUMBER ASSIGNMENT STANDARDS
A. Introduction: This document provides guidance for establishing a consistent and intuitive
room numbering system within University buildings.
B. Related Documents and Standards:
1.
2.
3.
4.
Drawing 00100-1, Space Inventory - Room Number System
Drawing 00100-2, Space Inventory - Actual Room Use Assignments
Drawing 00100-3, Space Inventory - Area Polylines
CAD Standards
C. References:
1. Postsecondary Education Facilities Inventory and Classification Manual
D. Purpose: Allow better navigation of the buildings on campus for students, staff, maintenance
personnel, and emergency personnel. Ensure room numbers conform to the University’s
Space Inventory database structure.
F. Room Numbering Guidelines:
2. Room number layout shall begin at the main entrance of the building proceeding in a
clock-wise direction.
3. Odd room numbers and even room numbers shall be placed on opposite sides of the
corridor. (Example: Odd room number 1015 shall be across the corridor from even
room number 1016). Proceeding clock-wise from the main entrance, even room
numbers shall be assigned to rooms on the left side of the corridor, odd room
numbers shall be assigned to rooms on the right side of the corridor.
4. Vertical similarity shall be maintained between floors of the building. Special
consideration shall be given to restrooms and mechanical areas.
5. Room numbers shall be assigned in accordance with the ranges listed below for each
floor of the building.
a.
b.
c.
d.
e.
Basement: 1 – 999
Ground Floor / First Floor: 1000 – 1999
Second Floor: 2000 – 2999
Third Floor: 3000 – 3999
Fourth Floor: 4000 – 4999 etc.
6. Planning: Omitting room numbers from the sequence in a room numbering system
will allow availability of room numbers for future room remodels.
7. Primary Room Numbers: Rooms that can be accessed from a corridor shall be
assigned a primary room number (Example: 1000, 1001, or 1002). See Drawing
00100-1.
PROJECT SUBMITTAL REQUIREMENTS
12
PART 3: SPACE INVENTORY – ROOM
NUMBER ASSIGNMENT STANDARDS
11-28-12 REV 4
8. Alpha Suffix Room Numbers: Rooms that can be accessed only from a room with
a primary room number shall be assigned an alpha suffix room number. Example:
1000A, 1000B, or 1000C. See Drawing 00100-1.
9. Alpha-Numeric Suffix Room Numbers: Rooms that can be accessed only from a
room with an alpha suffix room number shall be assigned an alpha-numeric suffix
room number. Example: 1000A1, 1000A2, or 1000A3. See Drawing 00100-1.
10. C-Prefix Room Numbers: Circulation area spaces shall be assigned a C-Prefix
room number. Corridors, vestibules, unfurnished commons areas, and elevator lobby
areas are examples of circulation area spaces. Example: C1000, C1050, and
C1100. See Drawing 00100-1.
11. ELEV-Prefix Room Numbers: Elevators shall be assigned an ELEV prefix room
number. Each elevator in a building shall be assigned only one ELEV-prefix room
number. Example: ELEV1, ELEV2, or ELEV3. See Drawing 00100-1.
12. STAIR-Prefix Room Numbers: Stairwells shall be assigned a STAIR prefix room
number. Each stairwell in a building shall be assigned only one STAIR-prefix room
number. Example: STAIR1, STAIR2, or STAIR3. See Drawing 00100-1.
13. Exceptions to Standards: Consultant shall contact the Coordinator of Records
Management for approval of any exceptions to the A / E Requirements Space
Inventory – Room Number Assignment Standards.
F. Room Use: All rooms in a room number system shall be assigned an Actual Room Use
Code and Name, in accordance with the Postsecondary Education Facilities Inventory and
Classification Manual standards for room usages – see Table 1: Actual Room Uses below.
See Drawing 00100-2.
1. Postsecondary Education Facilities Inventory & Classification Manual: This
manual may be ordered free of charge from the U.S. Department of Education.
However, only one manual per customer. Ordering information below:
U.S. DEPARTMENT OF EDUCATION
1-877-4ED-PUBS, 1-877-433-7827
P.O. BOX 1398
JESSUP, MD 20794-1398
http://www.edpubs.org
2. Assignable Space: According to the Postsecondary Education Facilities Inventory
and Classification Manual, the definition for Assignable Space is “The sum of all
areas on all floors of a building assigned to or available for assignment to, an
occupant or for specific use”.
3. Non-Assignable Space: According to the Postsecondary Education Facilities
Inventory and Classification Manual, the definition for Non-Assignable Space is “The
sum of all areas on all floors of a building not available for assignment to an occupant
or for specific use, but necessary for the general operation of a building”.
PROJECT SUBMITTAL REQUIREMENTS
13
PART 3: SPACE INVENTORY – ROOM
NUMBER ASSIGNMENT STANDARDS
11-28-12 REV 4
100 SERIES - CLASSROOM FACILITIES
110
115
Classroom
Classroom Service
200 SERIES - LABORATORY FACILITIES
210
215
220
225
250
255
Class Laboratory
Class Laboratory Service
Open Laboratory
Open Laboratory Service
Non-Class Laboratory
Non-Class Lab Service
300 SERIES - OFFICE FACILITIES
310
315
350
355
Office
Office Service
Conference Room
Conference Room Service
400 SERIES - STUDY FACILITIES
410
420
430
440
455
Study Room
Stack
Open Stack Study Room
Processing Room
Study Service
500 SERIES - SPECIAL USE FACILITIES
510
515
520
523
525
530
535
540
545
550
555
570
575
580
585
590
Armory
Armory Service
Athletic/Physical Ed
Ath. Fac. Spectator Seat
Athletic/P.E. Service
Media Production
Media Production Service
Clinic (Non-Health Prof.)
Clinic Service (Non-Hlth)
Demonstration
Demonstration Service
Animal Quarters
Animal Quarters Service
Greenhouse
Greenhouse Service
Other
600 SERIES - GENERAL USE FACILITIES
610
615
620
625
630
635
PROJECT SUBMITTAL REQUIREMENTS
Assembly
Assembly Service
Exhibition
Exhibition Service
Food Facilities
Food Facilities Service
14
PART 3: SPACE INVENTORY – ROOM
NUMBER ASSIGNMENT STANDARDS
11-28-12 REV 4
650
655
660
665
670
675
680
685
Lounge
Lounge Service
Merchandising
Merchandising Service
Recreation
Recreation Service
Meeting Room
Meeting Room Service
700 SERIES - SUPPORT FACILITIES
710
720
725
730
735
740
745
750
755
760
765
780
Central Comp./Telecom
Shop
Shop Service
Central Storage
Central Storage Service
Vehicle Storage
Vehicle Storage Service
Central Service
Central Services Support
Hazardous Materials
Hazardous Materials Serv.
Unit Storage
800 SERIES - HEALTH CARE FACILITIES
810
820
830
840
850
860
870
880
895
Patient Bedroom
Patient Bath
Nurse Station
Surgery
Treatment/Examination
Diagnostic Service Lab.
Central Supplies
Public Waiting
Staff On-Call Fac. Serv.
900 SERIES - RESIDENTIAL FACILITIES
910
919
920
935
950
955
970
999
Sleep/Study w/o toilet/bath
Toilet/Bath
Sleep/Study w/ toilet/bath
Sleep/Study Service
Apartment
Apartment Service
House
Quasi Space
000 SERIES - UNCLASSIFIED FACILITIES
050
060
070
PROJECT SUBMITTAL REQUIREMENTS
Inactive Area
Alteration or Conversion Area
Unfinished Area
15
PART 3: SPACE INVENTORY – ROOM
NUMBER ASSIGNMENT STANDARDS
11-28-12 REV 4
NON-ASSIGNABLE AREA
WWW
W01
W02
W03
W04
W05
W06
W07
XXX
X01
X02
X03
X04
YYY
Y01
Y02
Y03
Y04
Circulation Area
Bridge/Tunnel
Elevator
Escalator
Loading Dock
Lobby
Public Corridor
Stairway
Custodial Area
Custodial Supply Closet
Janitor Room
Public Rest Room
Trash Room
Mechanical Area
Central Utility Plant
Fuel Room
Shaft
Utility/Mechanical Space
STRUCTURAL AREA
ZZZ
Structural Area
Table 1: Actual Room Uses
G. Identification Devices: All rooms in the space inventory room number system (including,
corridors, elevators, janitor closets, mechanical rooms, restrooms, stairwells, vestibules, etc.)
shall receive an identification device.
1. The identification device shall display the room number assigned to that room in the
space inventory room number system. (Example: room number assignment ELEV1
shall be displayed as “ELEV1” ).
2. Identification devices shall conform to the “U.I.U.C Facility Standards, Division 10 –
Specialties, Section 10440 – Identifying Devices”.
H. Drawing Requirements: Space Inventory data shall be added to CAD files in accordance
with the University’s “CAD Standards Section”. See CAD Standard Master Layer List, Exhibit
B, and Space Inventory – Room Number Assignment Standards, Drawings 00100-1, 001002, and 00100-3.
I.
Conformance to Room Number Assignment Standards: The Room Numbering Systems
delivered to the University by Consultants shall comply with the University “Space Inventory Room Number Assignment Standards” in effect during the current Project.
PROJECT SUBMITTAL REQUIREMENTS
16
PART 3: SPACE INVENTORY – ROOM
NUMBER ASSIGNMENT STANDARDS
11-28-12 REV 4
The University requires sample submittals at key milestones during development of the room
numbering system in accordance with the Professional Services Consultant Contract.
Sample submittals are not intended to be a burden on the Consultant, and typically will
involve a very limited number of drawings. The University requires digital media submittals,
as a minimum, be provided at the first and final submittal milestones.
Providing digital media at the first submittal milestone will allow the University to verify the
room numbering system being used by the Consultant conforms to the University’s Space
Inventory - Room Number Assignment Standards and can be readily used in the University’s
Space Inventory database.
PROJECT SUBMITTAL REQUIREMENTS
17
PART 3: SPACE INVENTORY – ROOM
NUMBER ASSIGNMENT STANDARDS
11-28-12 REV 4
EXHIBITS
EXHIBIT A: SUBMITTAL REQUIREMENTS & SPACE INVENTORY
CHECKLIST
EXHIBIT B: CAD STANDARD MASTER LAYER LIST
PROJECT SUBMITTAL REQUIREMENTS
18
EXHIBITS
11-28-12 REV 4
Exhibit A: Submittal Requirements & Space Inventory Checklist
Project
Phase
Project Manager
Review Date

Compliant with
o CAD Standards (see separate CAD Standards Checklist)1
o Space Inventory – Room Number Assignment Standards
 Room Number Systems2
 Actual Room Use Assignments3
 Area Polylines4

Transmittal Form (including, but not limited to:)5
o University Project Number
o University Project Name as approved by Board of Trustees
o Phase

CD-Rom or DVD6
o Label
 University Project – Name, Number and CDB Number (if applicable)
 University Building – Name, Number
 University Project Manager
 Consultant – Name, Contact Information
 Phase
 Content Description (e.g. Project Manual and Project Drawings)
 Date of Submittal Documents
 Date Submitted
o Files
 One project per CD or DVD
 Uncompressed files
 Folder structure:
Drawings
Project Manual
CAD
Word
pdf
pdf
 All sheets submitted in hard copy are submitted in e-copy

Review Copies Delivered to:7
o Project Manager – 1 half-size
o Code Compliance Officer – 1 half-size
o Quality Assurance – 1 full-size, 1 half-size, e-copy (all with manuals)
 At Bid – 2 full-size, 1 half-size, e-copy (all with manuals)
o CITES Plant Design – 1 full-size
o CITES Classroom & Conference Media Engineering – 1 full-size
o Project Department – 1 full-size (if Deferred Maint. Project submit half-size)
o Project College – 1 ____-size
o Other __________________________________________ - 1 ____-size
1
Project Submittal Requirements: Section B
Space Inventory – Room Number Assignment Standards: Section E, and Drawing 00100-1
3
Space Inventory – Room Number Assignment Standards: Section F, and Drawing 00100-2
4
Space Inventory – Room Number Assignment Standards: Section H, and Drawing 00100-3
5
Project Submittal Requirements: Section F1
6
Project Submittal Requirements: Section I
7
Project Submittal Requirements: Section F
2
PROJECT SUBMITTAL REQUIREMENTS
19
EXHIBIT A
11-28-12 REV 4

Close-Out8
o Quality Assurance:
 1 paper copy of both Drawings (full-size) and Project Manual
 1 electronic sets of both Drawings and Project Manual
o Project Department/College:
 ____ number of ____-size paper Drawings and Project Manuals
 ____ number of electronic sets of both Drawings and Project Manuals

Project Manual9
o Cover
 Project Title as appears in PRZM, or approved by Board of Trustees
 UIUC Project Number
 Building Name and Number OR
 Utility Name
 Phase
 Logo in compliance with Campus Identity Standards
o Paper Copy
 Bound (no ACCO-style bare metal fasteners, staples, or post bindings)
 Split if over 300 pages or over 1.5” thick
o E-copy
 MS Word
 Uncompressed
 Files named by spec section
 pdf

Drawings 10
o Title Block
 Project Title as appears in PRZM, or as approved by Board of Trustees
 UIUC Project Number
 Building Name and Number or Utility Name
 Phase
 Drafting Person’s Initials
 Reviewer’s Initials
 Drawing Title
 Drawing Number
 Revision Number, Date, and Description
 Logo in compliance with Campus Identity Standards
o Paper Copy
 Complies with CAD Standards
 Bound (no single corner staples)
 Volumes no more than 100 sheets
o E-copy
 Complies with CAD Standards
 1 set unbound CAD drawings – eTransmit or Pack-n-go, “Place all files in one folder”
Transmittal Option
 1 set pdf (1 drawing per file, searchable, rotated to correct direction)
 Uncompressed
 Drawing files named by sheet number(s) (if multiple layout tabbed cad files are
submitted, tabs named same as drawing number)
No file prefixes or suffixes, except to help sort files per paper set
e.g.
G-1.dwg
may be named
001_G-1.dwg
C100-C104.dwg
may be named
003_C100-C104.dwg
 Remove extraneous objects, purge, zoom to display sheet or model, remove nonpertinent files, do not explode blocks.
 Include all necessary associated files (e.g. fonts, plot styles).
8
Project Submittal Requirements: Section F3
Project Submittal Requirements: Section G
10
Project Submittal Requirements: Section H
9
PROJECT SUBMITTAL REQUIREMENTS
20
EXHIBIT A
11-28-12 REV 4
EXHIBIT B: CAD STANDARD MASTER LAYER LIST
General Information
Annotation Layers
Key Plans, Schedules, Legends &
Misc
Layer Name
*-ANNO-TEXT
*-ANNO-REDL
*-ANNO-SYMB
*-ANNO-LEGN
*-ANNO-DIMS
*-ANNO-TTLB
*-ANNO-NOTE
*-ANNO-NPLT
*-ANNO-KEYN
*-ANNO-REVS
*-ANNO-XREF
*-ANNO-GRID
Line
Type
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Color #
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Cross - hatching, poch'e
Identification tags
Elevation (vertical surfaces in 3D)
Read - me layer, not to be plotted
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
New work
Existing to remain
Demolition
Future work
Abandoned
Temporary work
Items to be moved
Relocated items
Not in contract
Phase numbers (1-9)
*Note: The status field may also occur as the fourth
field, following a minor group.
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
One-line line work identification - annotation
One-line line work - fine ( 0.000 - 0.009 )
One-line line work - thin ( 0.010 - 0.019 )
One-line line work - medium ( 0.020 - 0.029 )
One-line line work - wide ( 0.030 - 0.039 )
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Layer Description
Text
Redline
Symbols
Legends and schedules
Dimensions
Border and title block
Notes
Construction lines, nonplotting information
Key notes
Revisions
Reference files
Grid Index
*Note: Annotation layer names may be appended
with a four-character sheet name designator when
needed.
Common Modifiers
*-****-PATT
*-****-IDEN
*-****-ELEV
X-RDME
Status Field Modifiers
*-****-NEWW
*-****-EXST
*-****-DEMO
*-****-FUTR
*-****-ABND
*-****-TEMP
*-****-MOVE
*-****-RELO
*-****-NICN
*-****-PHS1-9
One-Line Diagram Layers
Line Work
*-1LIN-LWRK-IDEN
*-1LIN-LWRK-FINE
*-1LIN-LWRK-THIN
*-1LIN-LWRK-MEDM
*-1LIN-LWRK-WIDE
PROJECT SUBMITTAL REQUIREMENTS
21
EXHIBIT B
11-28-12 REV4
*-1LIN-LWRK-EXWD
Devices
*-1LIN-DEVC-IDEN
*-1LIN-DEVC-FINE
*-1LIN-DEVC-THIN
*-1LIN-DEVC-MEDM
*-1LIN-DEVC-WIDE
*-1LIN-DEVC-EXWD
One-line line work - extra wide ( 0.040 -
)
Varies
Varies
One-line devices identification - annotation
One-line devices - fine ( 0.000 - 0.009 )
One-line devices - thin ( 0.010 - 0.019 )
One-line devices - medium ( 0.020 - 0.029 )
One-line devices - wide ( 0.030 - 0.039 )
One-line devices - extra wide ( 0.040 )
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Riser diagram line work identification - annotation
Riser diagram line work - fine ( 0.000 - 0.009 )
Riser diagram line work - thin ( 0.010 - 0.019 )
Riser diagram line work - medium ( 0.020 - 0.029 )
Riser diagram line work - wide ( 0.030 - 0.039 )
Riser diagram line work - extra wide ( 0.040 )
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Detail accessories
Detail concrete masonry unit (CMU) outline (no
patterning)
Detail concrete
Detail covers and fittings
Detail devices (e.g. valves, meters, pump stations
etc.)
Detail witness/extension lines, dimension
arrowheads/dots/slashes, dimension text
Detail earth
Detail fasteners
Detail fencing
Detail fill
Detail finished grade
Detail fittings (e.g. tees, crosses, reducers etc.)
Detail general features (miscellaneous items
including details within the detail)
Detail junctions (e.g. manholes, pedestals,
handholes etc.)
Detail non-plotting - construction lines, reference
targets, area calculations, review comments
Detail joint materials (e.g. felt), vapor barrier, other
Detail model
Detail piping
Detail miscellaneous patterning
Detail pavement
Detail reinforcement rebar, welded wire mesh
Detail special features
Detail steel structure wide flange shapes, plates,
open web joists, decking, bolts, nails
Detail structural metal
Detail reference bubbles, match lines and break
lines
Detail shaded line work
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Riser Diagram Layers
*-RISR-LWRK-IDEN
*-RISR-LWRK-FINE
*-RISR-LWRK-THIN
*-RISR-LWRK-MEDM
*-RISR-LWRK-WIDE
*-RISR-LWRK-EXWD
Detail Layers
*-DETL-ACCS
*-DETL-CMUW
*-DETL-CONC
*-DETL-COVR
*-DETL-DEVC
*-DETL-DIMS
*-DETL-ERTH
*-DETL-FAST
*-DETL-FENC
*-DETL-FILL
*-DETL-FNGR
*-DETL-FTTG
*-DETL-GENF
*-DETL-JUNC
*-DETL-NPLT
*-DETL-MISC
*-DETL-MODL
*-DETL-PIPE
*-DETL-PATT
*-DETL-PAVE
*-DETL-REIN
*-DETL-SPCF
*-DETL-STLS
*-DETL-STRC
*-DETL-SYMB
*-DETL-SHDE
PROJECT SUBMITTAL REQUIREMENTS
22
EXHIBIT B
11-28-12 REV4
*-DETL-TANK
Detail tanks
Detail title text, text and associated leader lines and
arrowheads, notes
Detail border and title block
Detail weld symbols
Detail wood outline (no patterning)
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Line
Type
Color
#
Architectural area - Exterior and Interior Gross Area
each floor plan shall consist of two (2) separate closed
polylines. One (1) polyline shall be drawn around the
interior face of the exterior wall of the building. One (1)
polyline shall be drawn around the exterior face of the
exterior wall of the building - See Drawing 00100-3.
Continuous
3
Architectural area - Room Interior Area One (1)
closed polyline shall be drawn around the interior face
of the walls for each individual room on a floor. See
Drawing 00100-3.
Continuous
2
Architectural area - Room Numbers shall be assigned
according to the University's “Space Inventory - Room
Number Assignment Standards". See Drawing 00100-1
- annotation
Continuous
4
Continuous
Continuous
Varies
Varies
Varies
Varies
Varies
4
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
*-DETL-TEXT
*-DETL-TTLB
*-DETL-WELD
*-DETL-WOOD
Architectural
Layer Name
Layer Description
Architectural Layers
A-AREA-GROS
A-AREA-RM
A-AREA-RMID
A-AREA-RUID
A-AREA-PATT
A-CLNG
A-CLNG-ACCS
A-CLNG-CONT
A-CLNG-GRID
A-CLNG-OPEN
A-CLNG-PATT
A-CLNG-TEES
A-CLNG-SUSP
A-COLS-ENCL
A-DOOR
A-DOOR-ELEV
A-DOOR-FULL
A-DOOR-IDEN
A-DOOR-PRHT
A-DOOR-SYMB
A-ELEV
Architectural area - Actual Room Use Identifications
shall be acquired according to the University's “Space
Inventory - Room Number Assignment Standards".
See Drawing 00100-2. - annotation
Architectural area cross hatching
Architectural ceiling information
Architectural ceiling access
Architectural ceiling control joints
Architectural ceiling grid
Architectural ceiling / roof penetrations
Architectural ceiling patterns (e.g. gypsum, plaster,
user defined)
Architectural ceiling main tees
Architectural ceiling suspended: ceiling mounted
specialities (e.g. clocks, fans, etc.)
Architectural column enclosures / fire protection
Architectural doors
Architectural doors: 3D views
Architectural doors full-height (to ceiling) door: swing
and leaf
Architectural doors door number, hardware group, etc.
- annotation
Architectural doors partial-height door: swing and leaf
Architectural doors miscellaneous symbols (e.g.
overhead, bifold, pocket, etc.)
Architectural elevations interior and exterior
PROJECT SUBMITTAL REQUIREMENTS
23
EXHIBIT B
11-28-12 REV4
A-ELEV-CASE
A-ELEV-OTLN
A-ELEV-FIXT
A-ELEV-FNSH
*-****-ABND
A-ELEV-IDEN
A-ELEV-PATT
A-ELEV-PFIXT
A-ELEV-SIGN
A-EQPM
A-EQPM-ACCS
A-EQPM-CLNG
A-EQPM-ELEV
A-EQPM-FIXD
A-EQPM-IDEN
A-EQPM-MOVE
A-EQPM-NICN
A-FLOR
A-FLOR-CASE
A-FLOR-EVTR
A-FLOR-FIXT
A-FLOR-HRAL
A-FLOR-IDEN
A-FLOR-LEVL
A-FLOR-OTLN
A-FLOR-OVHD
A-FLOR-PATT
A-FLOR-PFIX
A-FLOR-RAIS
A-FLOR-RISR
A-FLOR-SIGN
A-FLOR-SPCL
A-FLOR-STRS
A-FLOR-TPTN
A-FLOR-WDWK
A-FURN
A-FURN-CHAR
A-FURN-ELEV
A-FURN-FILE
A-FURN-FREE
A-FURN-IDEN
A-FURN-PATT
A-FURN-PLNT
Architectural elevations wall-mounted casework
Architectural elevations building outlines
Architectural elevations miscellaneous fixtures
Architectural elevations finishes, woodwork, trim
Abandoned
Architectural elevations component identification
numbers - annotation
Architectural elevations textures and hatch patterns
Architectural elevations plumbing fixtures
Architectural elevations signage
Architectural equipment
Architectural equipment access
Architectural equipment ceiling-mounted or suspended
Architectural equipment surfaces: 3D views
Architectural equipment fixed (non-moveable)
Architectural equipment identification numbers
Architectural equipment moveable
Architectural equipment not in contract
Architectural floor information
Architectural floor casework (manufacture cabinets)
Architectural floor elevator cars and equipment
Architectural floor mounted/free standing
miscellaneous fixtures (not including toilet fixtures)
Architectural floor stair and balcony handrails, guard
rails (except handicap grab bars)
Architectural floor targets, notes etc - annotation
Architectural floor level changes, ramps, pits,
depressions, breaks in construction
Architectural floor or building outline
Architectural floor overhead items (skylights, overhangs
---- usually dashed line)
Architectural floor paving, tile, carpet patterns
Architectural floor plumbing fixtures
Architectural floor: raised
Architectural floor stair risers
Architectural floor signage
Architectural floor specialties (toilet room accessories floor mounted only, display cases)
Architectural floor stair treads, escalators, ladders
Architectural floor toilet partitions and handicap grab
bars
Architectural floor woodwork (field-built cabinets and
counters)
Architectural furniture
Architectural furniture chairs and other seating
Architectural furniture elevations: 3D views
Architectural furniture file cabinets
Architectural furniture: freestanding (desks, credenzas,
etc.)
Architectural furniture numbers
Architectural furniture finish patterns
Architectural furniture plants
PROJECT SUBMITTAL REQUIREMENTS
24
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
EXHIBIT B
11-28-12 REV4
A-FURN-PNLS
A-FURN-POWR
A-FURN-STOR
A-FURN-WKSF
A-GLAZ
A-GLAZ-ELEV
A-GLAZ-FULL
A-GLAZ-IDEN
A-GLAZ-PRHT
A-GLAZ-SILL
A-ROOF
A-ROOF-CRTS
A-ROOF-DRNS
A-ROOF-EDGE
A-ROOF-EXPN
A-ROOF-HRAL
A-ROOF-LEVL
A-ROOF-OTLN
A-ROOF-PATT
A-ROOF-SPCL
A-ROOF-STRS
A-ROOF-WALK
A-WALL
A-WALL-CAVI
A-WALL-CNTR
A-WALL-CWMG
A-WALL-ELEV
A-WALL-EXTR
A-WALL-FIRE
A-WALL-HEAD
A-WALL-IDEN
A-WALL-INTR
A-WALL-JAMB
A-WALL-MOVE
A-WALL-PATT
A-WALL-PRHT
Architectural furniture system panels
Architectural furniture system ---- power designations
Architectural furniture system storage components
Architectural furniture system work surface
components
Architectural glazing windows, window walls, curtain
walls, glazed partitions
Architectural glazing and mullions --- elevation views
Architectural glazing full-height glazed walls and
partitions
Architectural glazing window number
Architectural glazing windows and partial-height glazed
partitions
Architectural glazing windowsills
Architectural roof
Architectural roof cricketts flow arrows flow info
Architectural roof drains
Architectural roof internal gutters
Architectual roof expansion joints
Architectural roof stair handrails, nosings, guardrails
Architectural roof level changes
Architectural roof outline
Architectural roof surfaces patterns, hatching
Architectural roof specialities, accessories, access
hatches
Architectural roof stair risers / treads, ladders
Architectural roof walkways
Architectural wall
Architectural wall: cavity lines
Architectural wall: centerlines
Architectural wall: curtain, mullions, & glass
Architectural wall surfaces: 3D views
Architectural wall: exterior full height
Architectural wall: fire wall designators (patterning)
Architectural wall Door and window headers (appear on
reflected ceiling plans)
Architectural wall identification / type text or tags annotation
Architectural wall: interior full height
Door and window jambs (do not appear on reflected
ceiling plans)
Architectural wall: moveable partitions
Wall insulation, hatching and fill
Partial-height walls (do not appear on reflected ceiling
plans)
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Electrical Layers
E-LITE
E-LITE-SPCL
E-LITE-EMER
E-LITE-EXIT
E-LITE-CLNG
Lighting
Special lighting
Emergency lighting
Exit lighting
Ceiling - mounted lighting
PROJECT SUBMITTAL REQUIREMENTS
25
EXHIBIT B
11-28-12 REV4
E-LITE-WALL
E-LITE-FLOR
E-LITE-OTLN
E-LITE-NUMB
E-LITE-ROOF
E-LITE-SITE
E-LITE-SWCH
E-LITE-CIRC
E-LITE-IDEN
E-LITE-JBOX
E-POWR
E-POWR-WALL
E-POWR-CLNG
E-POWR-PANL
E-POWR-EQPM
E-POWR-SWBD
E-POWR-CIRC
E-POWR-URAC
E-POWR-UCPT
E-POWR-CABL
E-POWR-FEED
E-POWR-BUSW
E-POWR-NUMB
E-POWR-IDEN
E-POWR-SITE
E-POWR-ROOF
E-POWR-OTLN
E-POWR-JBOX
E-CTRL
E-CTRL-DEVC
E-CTRL-WIRE
E-GRND
E-GRND-CIRC
E-GRND-REFR
E-GRND-EQUI
E-GRND-DIAG
E-AUXL
E-LTNG
E-FIRE
E-COMM
E-DATA
E-SOUN
E-TVAN
E-CCTV
E-NURS
E-SERT
E-PGNG
E-DICT
E-BELL
E-CLOK
E-ALRM
E-INTC
Wall - mounted lighting
Floor - mounted lighting
Lighting outline for background (optional)
Lighting circuit numbers
Roof lighting
Site lighting (see also civil group)
Lighting ---- switches
Lighting circuits
Luminaire identification and text
Junction box
Power
Power wall outlets and receptacles
Power ---- ceiling receptacles and devices
Power panels
Power equipment
Power switchboards
Power circuits
Underfloor raceways
Under - carpet wiring
Cable trays
Feeders
Busways
Power circuits numbers
Power identification, text
Site power (see also civil group)
Roof power
Power outline for backgrounds
Junction box
Electric control systems
Control system devices
Control system wiring
Ground system
Ground system circuits
Reference ground system
Equipotential ground system
Ground system diagam
Auxiliary systems
Lighting protection system
Fire alarm, fire extinguishers
Telephone, communication outlets
Data outlets
Sound / PA system
TV antenna system
Closed - circuit TV
Nurse call system
Security
Paging system
Central dictation system
Bell system
Clock system
Miscellaneous alarm system
Intercom system
PROJECT SUBMITTAL REQUIREMENTS
26
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
EXHIBIT B
11-28-12 REV4
E-LEGN
E-1LIN
E-RISR
E-SITE
E-SITE-LITE
E-SITE-UNDR
E-SITE-POLE
E-SITE-OVHD
Legend of symbols
One - line diagrams
Riser diagram
Site electrical substations, poles
Site lighting
Underground electrical lines
Electric poles
Overhead lines
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
F-CO2S
CO2 system
Varies
Varies
F-CO2S-PIPE
CO2 sprinkler piping
Varies
Varies
F-CO2S-EQPM
F-HALN
F-HALN-EQPM
F-HALN-PIPE
F-IGAS
F-IGAS-EQPM
F-IGAS-PIPE
F-SPRN
F-SPRN-CLHD
F-SPRN-OTHD
F-SPRN-PIPE
F-SPRN-STAN
F-STAN
F-PROT
F-PROT-EQPM
F-PROT-ALRM
F-PROT-SMOK
CO2 equipment
Halon
Halon equipment
Halon piping
Inert gas
Inert gas equipment
Inert gas piping
Fire protections sprinkler system
Sprinkler head ---- ceiling
Sprinkler head ---- other
Sprinkler piping
Sprinkler system standpipe
Fire protection standpipe system
Fire protection systems
Fire system equipment (fire hose cabinet extinguishers)
Fire alarm
Smoke detectors/heat sensors
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Floor plan ---- key plan
Site plan ---- key map
Access plan
Fire protection plan
Evacuation plan
Code compliance plan
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Floor plan
Site plan
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Fire Protection Layers
General Layers
G-PLAN
G-SITE
G-ACCS
G-FIRE
G-EVAC
G-CODE
Hazardous Layers
HZ-PLAN
HZ-SITE
Interior Layers
I-WALL-FULL
I-WALL-PRHT
I-WALL-MOVE
I-WALL-HEAD
Full - height walls, stair and shaft walls, walls to
structure
Partial - height walls (do not appear on reflected ceiling
plans)
Moveable partitions
Door and window headers (appear on reflected ceiling
plan)
PROJECT SUBMITTAL REQUIREMENTS
27
EXHIBIT B
11-28-12 REV4
I-WALL-JAMB
I-WALL-PATT
I-WALL-ELEV
I-WALL-FIRE
I-DOOR
I-DOOR-FULL
I-DOOR-PRHT
I-DOOR-IDEN
I-DOOR-ELEV
I-GLAZ
I-GLAZ-FULL
I-GLAZ-PRHT
I-GLAZ-SILL
I-GLAZ-IDEN
I-GLAZ-ELEV
I-FLOR
I-FLOR-OTLN
I-FLOR-LEVL
I-FLOR-STRS
I-FLOR-RISR
I-FLOR-HRAL
I-FLOR-EVTR
I-FLOR-TPTN
I-FLOR-SPCL
I-FLOR-WDWK
I-FLOR-CASE
I-FLOR-OVHD
I-FLOR-RAIS
I-FLOR-IDEN
I-FLOR-PATT
I-FLOR-PFIX
I-FLOR-FIXT
I-FLOR-SIGN
I-EQPM
I-EQPM-FIXD
I-EQPM-MOVE
I-EQPM-NICN
I-EQPM-ACCS
I-EQPM-IDEN
I-EQPM-ELEV
I-EQPM-CLNG
I-FURN
I-FURN-FREE
I-FURN-CHAR
I-FURN-FILE
I-FURN-PNLS
I-FURN-WKSF
I-FURN-STOR
Door and window jambs (do not appear on reflected
ceiling plans)
Wall insulation, hatching and fill
Wall surfaces: 3D views
Fire wall patterning
Doors
Full - height (to ceiling) door: swing and leaf
Partial - height door: swing and leaf
Door number, hardware group, etc.
Doors: 3D views
Glazing
Full - height glazed walls and partitions
Windows and partial - height glazed partitions
Windowsills
Window number
Glazing and mullions ---- elevation views
Floor information
Floor or building outline
Level changes, ramps, pits, depressions
Stairs treads, escalators, ladders
Stair risers
Stair and balcony handrails, guard rails
Elevator cars and equipment
Toliet partitions
Architectural specialties (toilet room accessories,
display cases)
Architectural woodwork (field - built cabinets and
counters)
Casework (manufactured cabinets)
Overhead items (skylights, overhangs ---- usually
dashed lines)
Raised floors
Room numbers, names, targets, etc.
Paving, tile, carpet patterns
Plumbing fixture
Miscellaneous fixtures
Signage
Equipment
Fixed equipment
Moveable equipment
Equipment not in contract
Equipment access
Equipment identification numbers
Equipment surfaces: 3D views
Ceiling - mounted or suspended equipment
Furniture
Furniture: freestanding (desks, credenzas, etc.)
Chairs and other seating
File cabinets
Furniture system panels
Furniture system work surface components
Furniture system storage components
PROJECT SUBMITTAL REQUIREMENTS
28
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
EXHIBIT B
11-28-12 REV4
I-FURN-POWR
I-FURN-IDEN
I-FURN-PLNT
I-FURN-PATT
I-FURN-ELEV
I-CLNG
I-CLNG-GRID
I-CLNG-OPEN
I-CLNG-TEES
I-CLNG-SUSP
I-CLNG-PATT
I-CLNG-ACCS
I-LITE
I-COLS
I-HVAC-SDFF
I-HVAC-RDFF
I-GRID
I-AREA
I-AREA-PATT
I-AREA-IDEN
I-AREA-OCCP
I-ELEV
I-ELEV-FNSH
I-ELEV-CASE
I-ELEV-FIXT
I-ELEV-PFIXT
I-ELEV-SIGN
I-ELEV-PATT
I-ELEV-IDEN
I-SECT
I-SECT-MCUT
I-SECT-MBND
I-SECT-PATT
I-SECT-IDEN
I-DETL
I-DETL-MCUT
I-DETL-MBND
I-DETL-PATT
I-DETL-IDEN
Furniture system ---- power designations
Furniture numbers
Plants
Finish patterns
Furniture: 3D views
Ceiling information
Ceiling grid
Ceiling / roof penetrations
Main tees
Suspended elements
Ceiling patterns
Ceiling access
Light fixtures
Columns
Supply diffusers
Return air diffusers
Planning grid or column grid
Area calculation lines
Area cross hatching
Room numbers, tenant identifications, area calculation
Occupant or employee names
Interior and exterior elevations
Finishes, woodwork, trim
Wall - mounted casework
Miscellaneous fixtures
Plumbing fixtures in elevation
Signage
Textures and hatch patterns
Component identification numbers
Sections
Material cut by section
Material beyond section cut
Textures and hatch patterns
Component identification numbers
Details
Material cut by section
Material beyond section cut
Textures and hatch patterns
Component identification numbers
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Brine systems
Brine system equipment
Brine system piping
Prefabricated chimneys
Compressed air systems
Compressed air equipment
Compressed air piping
Process air equipment
Process air piping
Controls and instrumentation
Thermostats
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Mechanical Layers
M-BRIN
M-BRIN-EQPM
M-BRIN-PIPE
M-CHIM
M-CMPA
M-CMPA-CEQP
M-CMPA-CPIP
M-CMPA-PEQP
M-CMPA-PPIP
M-CONT
M-CONT-THER
PROJECT SUBMITTAL REQUIREMENTS
29
EXHIBIT B
11-28-12 REV4
M-CONT-WIRE
M-DUST
M-DUST-EQPM
M-DUST-DUCT
M-ELHT-EQPM
M-ENER
M-ENER-EQPM
M-ENER-WIRE
M-RCOV
M-RCOV-EQPM
M-RCOV-PIPE
M-FUME-EXHS
M-FUME-EQPM
M-EXHS
M-EXHS-EQPM
M-EXHS-DUCT
M-EXHS-RFEQ
M-FUEL
M-FUEL-GPRP
M-FUEL-GGEP
M-FUEL-OPRP
M-FUEL-OGEP
M-HVAC
M-HVAC-CDFF
M-HVAC-ODFF
M-HVAC-DUCT
M-HVAC-EQPM
M-HVAC-SDFF
M-HVAC-RDFF
M-HOTW
M-HOTW-EQPM
M-HOTW-PIPE
M-CWTR
M-CWTR-PIPE
M-CWTR-EQPM
M-MACH
M-MDGS
M-MDGS-EQPM
M-MDGS-PIPE
M-LGAS
M-LGAS-EQPM
M-LGAS-PIPE
M-NGAS
M-NGAS-EQPM
M-NGAS-PIPE
M-PROC
M-PROC-EQPM
M-PROC-PIPE
M-REFG
M-REFG-EQPM
M-REFG-PIPE
M-SPCL
Low voltage wiring
Dust and fume collection system
Dust and fume collection equipment
Dust and fume ductwork
Electric heat equipment
Energy management system
Energy management equipment
Energy management wiring
Energy recovery
Energy recovery equipment
Energy recovery piping
Fume hood exhaust system
Fume hoods
Exhaust system
Exhaust system equipment
Exhaust system ductwork
Rooftop exhaust equipment
Fuel system piping
Fuel gas process piping
Fuel gas general piping
Fuel oil process piping
Fuel oil general piping
HVAC system
HVAC ceiling diffusers
HVAC other diffusers
HVAC ductwork
HVAC equipment
Supply diffusers
Return air diffusers
Hot water heating system
Hot water equipment
Hot water piping
Chilled water system
Chilled water piping
Chilled water equipment
Machine shop equipment
Medical gas systems
Medical gas equipment
Medical gas piping
Laboratory gas systems
Laboratory gas equipment
Laboratory gas piping
Natural gas systems
Natural gas equipment
Natural gas piping
Process systems
Process equipment
Process piping
Refrigeration systems
Refrigeration equipment
Refrigeration piping
Special systems
PROJECT SUBMITTAL REQUIREMENTS
30
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
EXHIBIT B
11-28-12 REV4
M-SPCL-EQPM
M-SPCL-PIPE
M-STEM
M-STEM-CONP
M-STEM-EQPM
M-STEM-LPIP
M-STEM-HPIP
M-STEM-MPIP
M-TEST-EQPM
Special systems equipment
Special systems piping
Steam systems
Steam systems condensate piping
Steam systems equipment
Low pressure steam piping
High pressure steam piping
Medium pressure steam piping
Test equipment
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
P-ACID
P-ACID-PIPE
P-DOMW
P-DOMW-EQPM
P-DOMW-HPIP
P-DOMW-CPIP
P-DOMW-RISR
P-SANR
P-SANR-PIPE
P-SANR-FIXT
P-SANR-FLDR
P-SANR-RISR
P-SANR-EQPM
P-STRM
P-STRM-PIPE
P-STRM-RISR
P-STRM-RFDR
P-EQPM
P-FIXT
Acid, alkaline, oil waste systems
Acid, alkaline, oil waste piping
Domestic hot and cold water systems
Domestic hot and cold water equipment
Domestic hot water piping
Domestic cold water piping
Domestic hot and cold water risers
Sanitary drainage
Sanitary piping
Plumbing fixtures
Floor drains
Sanitary risers
Sanitary equipment
Storm drainage system
Storm drain piping
Storm drain risers
Roof drains
Plumbing miscellaneous equipment
Plumbing fixtures
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
S-BEAM
S-BEAM-CNTR
S-BRAC-LATL
S-BEAM-PRIM
S-BEAM-SCND
Structural beam
Structural beam centerlines
Structural bracing - lateral
Structural beam - primary (girders)
Structural beam - secondary (girders)
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
S-BRAC-SHEA
S-BRAC-VERT
S-COLS
S-COLS-CNTR
S-COLS-PRIM
S-COLS-SCND
Structural bracing - shear walls
Structural bracing - vertical
Structural columns
Structural columns centerlines
Structural columns - primary
Structural columns - secondary
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
S-DECK
S-DECK-FLOR
S-DECK-OPEN
S-DECK-ROOF
S-ELEV-IDEN
S-ELEV-OTLN
S-ELEV-PATT
S-ELEV-SIGN
S-EVTR-FRAM
S-FNDN
Structural deck
Structural deck - floor
Structural deck - openings and penetrations
Structural deck - roof
Structural elevation component identification numbers
Structural elevation building outlines
Structural elevation textures and hatch patterns
Structural elevation signage
Structural elevator framing
Structural foundation
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Plumbing Layers
PROJECT SUBMITTAL REQUIREMENTS
31
EXHIBIT B
11-28-12 REV4
S-FNDN-FTNG
S-FNDN-GRBM
S-FNDN-IDEN
S-FNDN-PILE
S-FNDN-RBAR
S-GRAD-ELEV
S-GRAD-FLOR
S-GRAT-ELEV
S-GRAT-FLOR
S-GRID
S-GRID-EXTR
S-GRID-INTR
S-GRID-DIMS
S-GRID-IDEN
S-JNTS-CNST
S-JNTS-CTRL
S-JOIS
S-JOIS-BRDG
S-JOIS-PRIM
S-JOIS-SCND
S-METL-MISC
S-SECT-IDEN
S-SECT-MBND
S-SECT-MCUT
S-SECT-PATT
S-SLAB
S-SLAB-EDGE
S-SLAB-JOIN
S-SLAB-RBAR
S-SPPT-MISC
S-STRS-JOIN
S-STRS-LADD
S-STRS-RBAR
S-TRUS-UNIT
S-WALL
S-WALL-CONC
S-WALL-LOAD
S-WALL-NONL
S-WALL-PCST
S-WALL-STUD
S-WELD-SYMB
Structural foundation footings
Structural foundation grade beams
Structural foundation component identification numbers
Structural foundation piles, drilled piers
Structural foundation reinforcing
Structural grading - elevated
Structural grading - floor
Structural grating - elevated (catwalks)
Structural grating - floor
Structural column grid
Structural column grid lines outside building
Structural column grid lines inside building
Structural column grid dimensions
Structural column grid identification tags
Structural joints - construction
Structural joints - control/expansion
Structural joist
Structural joist bridging
Structural joist - primary
Structural joist - secondary
Structural metal - miscellaneous
Structural section component identification numbers
Structural section - material beyond section cut
Structural section - material cut by section
Structural section textures and hatch patterns
Structural slab
Structural slab edge outline
Structural slab control joints
Structural slab reinforcing
Structural support miscellaneous fasteners, anchor
bolts
Structural stair control joints
Structural stair - ladders, ladder handrails, safety
guard, grab bars
Structural stair - reinforcing
Structural truss unit
Structural wall
Structural wall - concrete
Structural wall - load bearing concrete masonry unit
(CMU)
Structural wall - non-load bearing concrete masonry
unit (CMU)
Structural wall - precast
Structural wall - steel stud
Structural weld symbols
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Electrical equipment identifiers and leader lines
Electrical equipment physical outline of electrical
equipment (e.g. cabinets, enclosures, etc.)
Communication Junction boxes
Bell system identifier tags, symbol modifier and text
Bell system symbols
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Telecommunication Layers
T-ELEC-IDEN
T-ELEC-EQPM
T-COMM-JBOX
T-BELL-IDEN
T-BELL-SYST
PROJECT SUBMITTAL REQUIREMENTS
32
EXHIBIT B
11-28-12 REV4
T-DICT-IDEN
Dictation system identifier tags, symbol modifier and
text
Varies
Varies
T-DICT-SYST
Dictation system symbols
Varies
Varies
T-CLOK-IDEN
T-CLOK-SYST
T-ALRM-IDEN
T-ALRM-SYST
Clock system identifier tags, symbol modifier and text
Clock system symbols
Alarm system identifier tags, symbol modifier and text
Alarm system symbols
Nurse call system identifier tags, symbol modifier and
text
Nurse call system symbols
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
T-SECR-IDEN
T-SECR-SYST
T-COMM-COAX
Intercom / public address system symbols
Intercom / public address: paging system symbols
Fire alarm and detection system identifier tags, symbol
modifier and text
Fire alarm and detection system symbols
Energy management system identifier tags, symbol
modifier and text
Energy management system symbols
Security system identifier tags, symbol modifier and
text
Security system symbols
Wiring system coax cable
Varies
Varies
Varies
Varies
Varies
Varies
T-COMM-FIBR
T-COMM-IDEN
Wiring system fiber optics cable
Wiring system cable identifiers
Varies
Varies
Varies
Varies
T-COMM-MULT
T-COMM-TRAY
Wiring system multi-conductor cable
Wiring system cable trays and wireway symbols
Varies
Varies
Varies
Varies
T-NURS-IDEN
T-NURS-SYST
T-SOUN-IDEN
T-SOUN-SYST
T-PHON-IDEN
T-PHON-SYST
T-CATV-IDEN
T-CATV-TELE
T-CATV-TVAN
T-DATA-IDEN
T-DATA-SYST
T-INTC-IDEN
T-INTC-INPA
T-INTC-PGNG
T-FIRE-IDEN
T-FIRE-SYST
T-EMS-IDEN
T-EMS-SYST
Sound system identifier tags, symbol modifier and text
Sound system symbols
Phone system identifier tags, symbol modifier and text
Phone system symbols
Television system identifier tags, symbol modifier and
text
Television system symbols
Television system antenna system symbols
Data / LAN system identifier tags, symbol modifier and
text
Data / LAN system symbols
Intercom / public address system identifier tags, symbol
modifier and text
Civil - Data collected exterior of
the building
Layer Name
Layer Description
Buildings / Primary Structures
C-BLDG-IDEN
C-BLDG-OTLN
Building name and location number - annotation
Building footprint - exterior wall of the building
PROJECT SUBMITTAL REQUIREMENTS
33
Line
Type
Color
#
Continuous
Continuous
Varies
Varies
EXHIBIT B
11-28-12 REV4
C-BLDG-MINR
C-BLDG-UNDR
C-BLDG-PATT
C-BLDG-DETAIL
Alignments
C-ALGN-OBJT
C-ALGN-IDEN
Embankments
C-EMBK-CNTL
C-EMBK-EDGE
C-EMBK-IDEN
Property
C-PROP-BRNG
C-PROP-CONS
C-PROP-ESMT
C-PROP-LINE
C-PROP-PRVT
C-PROP-LTID
C-PROP-DETL
C-PROP-MONU
C-PROP-RECD
C-PROP-RCID
Site
C-SITE-SIGN
C-SITE-CMTY
C-SITE-BPTH
C-SITE-BRCK
C-SITE-WALK
C-SITE-WKID
C-SITE-FENC
C-SITE-FEID
C-SITE-PTNL
C-SITE-IDEN
C-SITE-MSTR
C-SITE-MSID
Survey
C-SURV-CTRL
C-SURV-CTID
C-SURV-LINE
C-SURV-IDEN
Building minor (bus-shelter, kiask, information
booth) curbs
Building structure underground
Building hatch pattern
Building exterior stairs, fire escapes, porches, and
canopies, loading docks attached to the building
Continuous
Hidden
Continuous
Varies
Varies
Varies
Continuous
Varies
Varies
Varies
Varies
Varies
Embankment centerline
Embankment edge and object lines
Embankment annotation
Varies
Varies
Continuous
Varies
Varies
Varies
Property bearings and distance - annotation
Property construction limits / controls
Property easements with annotation
Property lines with annotation
Property private
Property lot identification (ie: parcel number, lot
number etc.)
Property details with annotation (scaled views
depicting detailed areas of property)
Property monumentation (includes all monuments
found or set, witness corners)
Property record data (data aquired by other sources
- not as part of the field survey)
Property record data identification - annotation
Continuous
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Continuous
Varies
Continuous
Varies
Continuous
Varies
Continuous
Continuous
Varies
Varies
Continuous
Continuous
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Continuous
Varies
Varies
Varies
Continuous
Hidden
Continuous
Varies
Varies
Varies
Continuous
Varies
Continuous
Continuous
Varies
Varies
Varies
Varies
Varies
Varies
Alignments
Alignment annotation
Site signage with annotation (ie: building signs)
Site cemetery with annotation
Site bicycle path
Site bicycle rack
Site sidewalks, defined trails - crushed stone, peagravel, bark etc.
Site sidewalk material identification: crushed stone,
pea-gravel, bark etc. - annotation
Site fencing, chain-link, chain, wood rail, barbedwire, etc.
Site fencing type identification: chain-link, chain,
wood rail, barbed-wire etc. - annotation
Site pedestrian tunnel
Site identification notes - annotation
Site minor structure including misc impervious
features (example: concrete / asphalt pads etc.)
Site minor structure identification - annotation
Survey control point - permanent markers including
benchmarks, gps, brass-tablets, stone marker etc
Survey control point identification
Survey and control line
Survey and control line annotation
PROJECT SUBMITTAL REQUIREMENTS
34
EXHIBIT B
11-28-12 REV4
Topography
C-TOPO-BKLN
C-TOPO-BORE
C-TOPO-BOID
C-TOPO-CORD
C-TOPO-SPOT
C-TOPO-MAJR
C-TOPO-MAID
C-TOPO-MINR
C-TOPO-MIID
C-TOPO-SLOP
C-TOPO-SLID
C-TOPO-IDEN
Borrow Areas
C-BORW-LINE
C-BORW-IDEN
Topography break lines
Topography soil borings
Topography soil boring identificaion tags annotation
Topography coordinates
Topography spot elevations
Topography major contours
Topography major contour identification annotation
Topography minor contours
Topography minor contour identification annotation
Topography cut/fill slopes
Topography cut/fill slope identification - annotation
Topography identification notes - annotation
Borrow area outline
Borrow area identification - annotation
Varies
Continuous
Varies
Varies
Continuous
Continuous
Continuous
Varies
Varies
Varies
Varies
Varies
Continuous
Varies
Varies
Varies
Continuous
Continuous
Continuous
Continuous
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Continuous
200
Continuous
200
Continuous
200
Continuous
200
Continuous
Hidden
Center2
Center2
Center2
Center2
Continuous
200
253
200
200
200
200
200
Continuous
Continuous
200
200
Continuous
5
Continuous
5
Continuous
5
Continuous
5
Site Utility Systems
Chilled Water System
C-CWTR-JUNC
C-CWTR-JUID
C-CWTR-DEVC
C-CWTR-DVID
C-CWTR-FTTG
C-CWTR-ABND
C-CWTR-MSUP
C-CWTR-SSUP
C-CWTR-MRET
C-CWTR-SRET
C-CWTR-ANOD
C-CWTR-STID
C-CWTR-IDEN
Domestic Water System
C-DOMW-JUNC
C-DOMW-JUID
C-DOMW-DEVC
C-DOMW-DVID
C-DOMW-FTTG
Chilled water junction: vaults, manholes, handholes
and valve vaults (UIUC)
Chilled water junction identification: vaults,
manholes, handholes and valve vaults - annotation
(UIUC)
Chilled water devices: test boxes, storage tanks,
valves, meters, pumps, & regulators (UIUC)
Chilled water device identification: test boxes,
storage tanks, valves, meters, pumps, & regulators
(UIUC)
Chilled water fittings caps, crosses, reducers & tees
etc. (UIUC)
Chilled water pipe - abandoned (UIUC)
Chilled water pipe - supply main (UIUC)
Chilled water pipe - supply service (UIUC)
Chilled water pipe - return main (UIUC)
Chilled water pipe - return service (UIUC)
Chilled water anode test station (UIUC)
Chilled water station identification: anode annotation (UIUC)
Chilled water identification notes (UIUC)
Domestic water junction: vaults, manholes,
handholes, pump stations and valve vaults (UIUC)
Domestic water junction identification: vaults,
manholes, handholes, pump stations and valve
vaults - annotation (UIUC)
Domestic water devices: storage tanks, valves,
meters, & hydrants (UIUC)
Domestic water device identification: storage tanks,
valves, meters, & hydrants - annotation (UIUC)
Domestic water fittings caps, crosses, reducers &
tees etc. (UIUC)
PROJECT SUBMITTAL REQUIREMENTS
35
5
EXHIBIT B
11-28-12 REV4
C-DOMW-ABND
C-DOMW-MAIN
C-DOMW-SERV
C-DOMW-NPOT
C-DOMW-IDEN
Domestic water pipe - abandoned (UIUC)
Domestic water pipe - main (UIUC)
Domestic water pipe - service (UIUC)
Domestic water pipe - non-potable water (UIUC)
Domestic water identification notes - annotation
(UIUC)
Hidden
Continuous
Continuous
Continuous
253
5
5
5
Continuous
5
C-DOMW-OTHR-JUNC
Domestic water junction: vaults, manholes,
handholes, pump stations and valve vaults (owned
or maintained by others)
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Hidden
253
Continuous
7
Continuous
7
Continuous
7
Continuous
Continuous
7
C-ELEC-JUNC
Electrical junction: vaults, manholes, handholes,
junction boxes, pull boxes, pedestals & splices
(UIUC)
Continuous
1
C-ELEC-JUID
Electrical junction identification: vaults, manholes,
handholes, junction boxes, pull boxes, pedestals &
splices - annotation (UIUC)
Continuous
1
C-ELEC-DEVC
Electrical device: transformers, capacitors, voltage
regulators, motors, buses, generators, meters,
grounds & markers (UIUC)
Continuous
1
Continuous
Hidden
1
253
Divide2
Divide2
Divide2
1
1
1
Divide2
Divide2
Divide2
1
1
1
C-DOMW-OTHR-JUID
C-DOMW-OTHR-DEVC
C-DOMW-OTHR-DVID
C-DOMW-OTHR-FTTG
C-DOMW-OTHR-ABND
C-DOMW-OTHR-MAIN
C-DOMW-OTHR-SERV
C-DOMW-OTHR-NPOT
C-DOMW-OTHR-IDEN
Electrical Distribution System
C-ELEC-DVID
C-ELEC-ABND
C-EPRM-IDEN
C-EPRM-UNDR
C-EPRM-OVHD
C-ESCD-IDEN
C-ESCD-UNDR
C-ESCD-OVHD
Domestic water junction identification: vaults,
manholes, handholes, pump stations and valve
vaults - annotation (owned or maintained by others)
Domestic water devices: storage tanks, valves,
meters, & hydrants (owned or maintained by others)
Domestic water device identification: storage tanks,
valves, meters, & hydrants - annotation (owned or
maintained by others)
Domestic water fittings caps, crosses, reducers &
tees etc. (owned or maintained by others)
Domestic water pipe - abandoned (owned or
maintained by others)
Domestic water pipe - main (owned or maintained
by others)
Domestic water pipe - service (owned or maintained
by others)
Domestic water pipe - non-potable (owned or
maintained by others)
Domestic water identification notes - annotation
(owned or maintained by others)
Electrical device identification: transformers,
capacitors, voltage regulators, motors, buses,
generators, meters, grounds & markers - annotation
(UIUC)
Electrical cable - abandoned (UIUC)
Electrical cable - primary identification notes annotation (UIUC)
Electrical cable - primary underground (UIUC)
Electrical cable - primary overhead (UIUC)
Electrical cable - secondary identification notes annotation (UIUC)
Electrical cable - secondary underground (UIUC)
Electrical cable - secondary overhead (UIUC)
PROJECT SUBMITTAL REQUIREMENTS
36
EXHIBIT B
11-28-12 REV4
C-ESRV-IDEN
C-ESRV-UNDR
C-ELEC-DUCT
C-ELEC-SUBS
C-ELEC-DIST
C-ELEC-SWCH
C-ELEC-PDBL
C-ELEC-PRSR
C-ELEC-PTWR
C-ELEC-PSGL
C-ELEC-PDGY
C-ELEC-PSPN
C-ELEC-POID
C-ELEC-IDEN
Electrical cable - service identification notes annotation (UIUC)
Electrical cable - service underground (UIUC)
Electrical ductbanks (UIUC)
Electrical sub-stations (UIUC)
Electrical distribution centers (UIUC)
Electrical switches fuse cutouts, pole mounted
switches, circuit breakers, gang operated
disconnects, reclosers, cubicle switches (UIUC)
Electrical pole - double (UIUC)
Electrical pole - risers (UIUC)
Electrical pole - tower (UIUC)
Electrical pole - single (UIUC)
Electrical pole - down guy (UIUC)
Electrical pole - span guy wires (UIUC)
Electrical pole - identification tags - annotation
(UIUC)
Electrical identification notes - annotation (UIUC)
C-ELEC-OTHR-JUID
Electrical junction: vaults, manholes, handholes,
junction boxes, pull boxes, pedestals & splices
(owned or maintained by others)
Electrical junction identification: vaults, manholes,
handholes, junction boxes, pull boxes, pedestals &
splices - annotation (owned or maintained by
others)
C-ELEC-OTHR-DEVC
Electrical device: transformers, capacitors, voltage
regulators, motors, buses, generators, meters,
grounds & markers (owned or maintained by others)
C-ELEC-OTHR-JUNC
C-ELEC-OTHR-DVID
C-ELEC-OTHR-ABND
C-EPRM-OTHR-IDEN
C-EPRM-OTHR-UNDR
C-EPRM-OTHR-OVHD
C-ESCD-OTHR-IDEN
C-ESCD-OTHR-UNDR
C-ESCD-OTHR-OVHD
C-ESRV-OTHR-IDEN
C-ESRV-OTHR-UNDR
C-ELEC-OTHR-DUCT
Electrical device identification: transformers,
capacitors, voltage regulators, motors, buses,
generators, meters, grounds & markers - annotation
(owned or maintained by others)
Electrical cable - abandoned (owned or maintained
by others)
Electrical cable - primary identification notes annotation (owned or maintained by others)
Electrical cable - primary underground (owned or
maintained by others)
Electrical cable - primary overhead ( owned or
maintained by others)
Electrical cable - secondary identification notes annotation (owned or maintained by others)
Electrical cable - secondary underground (owned or
maintained by others)
Electrical cable - secondary overhead (owned or
maintained by others)
Electrical cable - service identification notes annotation ( owned or maintained by others)
Electrical cable - service underground ( owned or
maintained by others)
Electrical ductbanks (owned or maintained by
others)
PROJECT SUBMITTAL REQUIREMENTS
37
Divide2
Divide2
Divide2
Continuous
Continuous
1
1
1
1
1
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
1
1
1
1
1
1
1
Continuous
Continuous
1
1
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Hidden
253
Dashed
7
Dashed
7
Dashed
7
Dashed
7
Dashed
7
Dashed
7
Dashed
7
Dashed
7
Dashed
7
EXHIBIT B
11-28-12 REV4
C-ELEC-OTHR-SUBS
C-ELEC-OTHR-DIST
C-ELEC-OTHR-SWCH
C-ELEC-OTHR-PDBL
C-ELEC-OTHR-PRSR
C-ELEC-OTHR-PTWR
C-ELEC-OTHR-PSGL
C-ELEC-OTHR-PDGY
C-ELEC-OTHR-PSPN
C-ELEC-OTHR-POID
C-ELEC-OTHR-TGRD
C-ELEC-OTHR-IDEN
Energy Management System
(EMS)
C-EMS-JUNC
C-EMS-JUID
C-EMS-DEVC
C-EMS-DVID
C-EMS-ABND
C-EMS-OVHD
C-EMS-UNDR
C-EMS-DUCT
Fire Protection System
C-FIRE-JUNC
C-FIRE-JUID
C-FIRE-DEVC
Electrical sub-stations (owned or maintained by
others)
Electrical distribution centers (owned or maintained
by others)
Electrical switches fuse cutouts, pole mounted
switches, circuit breakers, gang operated
disconnects, reclosers, cubicle switches (owned or
maintained by others)
Electrical pole - double (owned or maintained by
others)
Electrical pole - risers (owned or maintained by
others)
Electrical pole - tower (owned or maintained by
others)
Electrical pole - single (owned or maintained by
others)
Electrical pole - down guy (owned or maintained by
others)
Electrical pole - span guy wires (owned or
maintained by others)
Electrical pole - identification tags - annotation
(owned or maintained by others)
Electrical tower ground wire (owned or maintained
by others
Electrical identification notes - annotation (owned or
maintained by others)
Energy management system junction: pull boxes,
manholes, handholes, pedestals, splices (UIUC)
Energy management system junction identification:
pull boxes, manholes, handholes, pedestals, splices
- annotation (UIUC)
Energy management system devices: field
interfaces, multiplexers, markers (UIUC)
Energy management system device identification:
field interfaces, multiplexers, markers - annotation
(UIUC)
Energy management system cable - abandoned
(UIUC)
Energy management system cable - overhead
(UIUC)
Energy management system cable - underground
(UIUC)
Energy management system ductbanks (UIUC)
Fire protection junction: vaults, manholes,
handholes, pump stations and valve vaults (UIUC)
Fire protection junction identification: vaults,
manholes, handholes, pump stations and valve
vaults - annotation (UIUC)
Fire protection devices: storage tanks, valves,
meters & hydrants (UIUC)
PROJECT SUBMITTAL REQUIREMENTS
38
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continous
7
Continuous
7
Continuous
1
Continuous
1
Continuous
1
Continuous
1
Hidden
253
Continuous
5
Continuous
Dashed
5
7
Continuous
5
Continuous
5
Continuous
5
EXHIBIT B
11-28-12 REV4
C-FIRE-IDEN
Fire protection device identification: storage tanks,
valves, hydrants, & meters - annotation (UIUC)
Fire protection fittings caps, crosses, reducers &
tees etc. (UIUC)
Fire protection pipe - abandoned (UIUC)
Fire protection pipe - main (UIUC)
Fire protection pipe - service (UIUC)
Fire protection identification notes - annotation
(UIUC)
C-FIRE-OTHR-JUNC
Fire protection junction: vaults, manholes,
handholes, pump stations and valve vaults (owned
or maintained by others)
C-FIRE-DVID
C-FIRE-FTTG
C-FIRE-ABND
C-FIRE-MAIN
C-FIRE-SERV
C-FIRE-OTHR-JUID
C-FIRE-OTHR-DEVC
Fire protection junction identification: vaults,
manholes, handholes, pump stations and valve
vaults - annotation (owned or maintained by others)
Fire protection devices: storage tanks, valves, valve
vaults, meters (owned or maintained by others)
Continuous
5
Continuous
Hidden
Continuous
Continuous
5
253
5
5
Continuous
5
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Hidden
253
Continuous
7
Fire protection device identification: storage tanks,
valves, meters - annotation (owned or maintained
by others)
Fire protection fittings caps, crosses, reducers &
tees etc. (owned or maintained by others)
Fire protection pipe - abandoned (owned or
maintained by others)
Fire protection pipe - main (owned or maintained by
others)
Fire protection pipe - service (owned or maintained
by others)
Fire protection identification notes - annotation
(owned or maintained by others)
Continuous
7
Continuous
7
C-FUEL-JUNC
Fuel system junction: hydrant fill points, vaults,
manholes, handholes, test boxes, vent vaults, valve
vaults, and hydrant control vaults and valves (UIUC)
Continuous
7
C-FUEL-JUID
Fuel system junction identification: hydrant fill
points, vaults, manholes, handholes, test boxes,
vent vaults, valve vaults, and hydrant control vaults
and valves - annotation (UIUC)
Continuous
7
C-FUEL-DEVC
Fuel system devices: air eliminators, filter strainers,
line vents, markers, meters, oil/water separators,
pumps, regulators, and tanks (UIUC)
Continuous
7
Continuous
7
Continuous
Hidden
Continuous
Continuous
Continuous
Continuous
Continuous
7
253
7
7
7
7
7
C-FIRE-OTHR-DVID
C-FIRE-OTHR-FTTG
C-FIRE-OTHR-ABND
C-FIRE-OTHR-MAIN
C-FIRE-OTHR-SERV
C-FIRE-OTHR-IDEN
Fuel System
C-FUEL-DVID
C-FUEL-FTTG
C-FUEL-ABND
C-FUEL-MAIN
C-FUEL-SERV
C-FUEL-DEFL
C-FUEL-ANOD
C-FUEL-BOOS
Fuel system device identification: air eliminators,
filter strainers, line vents, markers, meters, oil/water
separators, pumps, regulators, and tanks annotation (UIUC)
Fuel system fittings caps, crosses, reducers & tees
etc. (UIUC)
Fuel system pipe - abandoned (UIUC)
Fuel system pipe - main (UIUC)
Fuel system pipe - service (UIUC)
Fuel system pipe - defueling (UIUC)
Fuel system anode test station (UIUC)
Fuel system booster station (UIUC)
PROJECT SUBMITTAL REQUIREMENTS
39
EXHIBIT B
11-28-12 REV4
C-FUEL-REDC
C-FUEL-PUMP
C-FUEL-IDEN
Fuel system reducing station (UIUC)
Fuel system pumping station (UIUC)
Fuel system identification notes - annotation (UIUC)
C-FUEL-OTHR-JUID
Fuel system junction: hydrant fill points, vaults,
manholes, handholes, test boxes, vent vaults, valve
vaults, and hydrant control vaults and valves
(owned or maintained by others)
Fuel system junction identification: hydrant fill
points, vaults, manholes, handholes, test boxes,
vent vaults, valve vaults, and hydrant control vaults
and valves - annotation (owned or maintained by
others)
C-FUEL-OTHR-DEVC
Fuel system devices: air eliminators, filter strainers,
line vents, markers, meters, oil/water separators,
pumps, regulators, and tanks (owned or maintained
by others)
C-FUEL-OTHR-JUNC
C-FUEL-OTHR-DVID
C-FUEL-OTHR-FTTG
C-FUEL-OTHR-ABND
C-FUEL-OTHR-MAIN
C-FUEL-OTHR-SERV
C-FUEL-OTHR-DEFL
C-FUEL-OTHR-ANOD
C-FUEL-OTHR-BOOS
C-FUEL-OTHR-REDC
C-FUEL-OTHR-PUMP
C-FUEL-OTHR-IDEN
Lighting System
Fuel system device identification: air eliminators,
filter strainers, line vents, markers, meters, oil/water
separators, pumps, regulators, and tanks annotation (owned or maintained by others)
Fuel system fittings caps, crosses, reducers & tees
etc. (owned or maintained by others)
Fuel system pipe - abandoned (owned or
maintained by others)
Fuel system pipe - main (owned or maintained by
others)
Fuel system pipe - service (owned or maintained by
others)
Fuel system pipe - defueling (owned or maintained
by others)
Fuel system anode test station (owned or
maintained by others)
Fuel system booster station (owned or maintained
by others)
Fuel system reducing station (owned or maintained
by others)
Fuel system pumping station (owned or maintained
by others)
Fuel system identification notes - annotation (owned
or maintained by others)
C-LITE-JUID
C-LITE-FLOD
C-LITE-POLE
C-LITE-STRT
C-LITE-WALK
Lighting junctions: pull boxes, manholes,
handholes, pedestals, splices (UIUC)
Lighting junction identification: pull boxes,
manholes, handholes, pedestals, splices annotation (UIUC)
Lighting flood lights (UIUC)
Lighting pole mounted light (UIUC)
Lighting street lights (UIUC)
Lighting walkway lights (UIUC)
C-LITE-SWCH
C-LITE-ABND
Lighting switches fuse cutouts, pole mounted
switches, circuit breakers, gang operated
disconnects, reclosers, cubicle switches (UIUC)
Lighting cable - abandoned (UIUC)
C-LITE-JUNC
PROJECT SUBMITTAL REQUIREMENTS
40
Continuous
Continuous
Continuous
7
7
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Hidden
253
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
1
Continuous
Continuous
Continuous
Continuous
Continuous
1
1
1
1
1
Continuous
Hidden
1
253
EXHIBIT B
11-28-12 REV4
C-LITE-PRID
C-LITE-PRUN
C-LITE-PROH
C-LITE-SCID
C-LITE-SCUN
C-LITE-SCOH
C-LITE-SRID
C-LITE-SRUN
C-LITE-OTHR-JUNC
C-LITE-OTHR-JUID
C-LITE-OTHR-FLOD
C-LITE-OTHR-POLE
C-LITE-OTHR-STRT
C-LITE-OTHR-WALK
C-LITE-OTHR-SWCH
C-LITE-OTHR-ABND
C-LITE-OTHR-PRID
C-LITE-OTHR-PRUN
C-LITE-OTHR-PROH
C-LITE-OTHR-SCID
C-LITE-OTHR-SCUN
C-LITE-OTHR-SCOH
C-LITE-OTHR-SRID
C-LITE-OTHR-SRUN
Natural Gas Distribution
C-NGAS-JUNC
Lighting cable - primary identification notes annotation (UIUC)
Lighting cable - primary underground (UIUC)
Lighting cable - primary overhead (UIUC)
Lighting cable - secondary identification notes annotation (UIUC)
Lighting cable - secondary underground (UIUC)
Lighting cable - secondary overhead (UIUC)
Lighting cable - service identification notes annotation (UIUC)
Lighting cable - service underground (UIUC)
Lighting junctions: pull boxes, manholes,
handholes, pedestals, splices (owned or maintained
by others)
Lighting junction identification: pull boxes,
manholes, handholes, pedestals, splices annotation (owned or maintained by others)
Lighting flood lights (owned or maintained by
others)
Lighting pole mounted light (owned or maintained
by others)
Lighting street lights (owned or maintained by
others)
Lighting walkway lights (owned or maintained by
others)
Lighting switches fuse cutouts, pole mounted
switches, circuit breakers, gang operated
disconnects, reclosers, cubicle switches (owned or
maintained by others)
Lighting cable - abandoned (owned or maintained
by others)
Lighting cable - primary identification notes annotation (owned or maintained by others)
Lighting cable - primary underground (owned or
maintained by others)
Lighting cable - primary overhead (owned or
maintained by others)
Lighting cable - secondary identification notes annotation (owned or maintained by others)
Lighting cable - secondary underground (owned or
maintained by others)
Lighting cable - secondary overhead (owned or
maintained by others)
Lighting cable - service identification notes annotation (owned or maintained by others)
Lighting cable - service underground (owned or
maintained by others)
Natural gas junction: hydrant fill points, vaults,
manholes, handholes, test boxes, vent vaults, and
valve vaults (UIUC)
PROJECT SUBMITTAL REQUIREMENTS
41
Border2
Border2
Border2
1
1
1
Continuous
Border2
Border2
1
1
1
Continuous
Border2
1
1
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Continuous
7
Hidden
253
Dashed
7
Dashed
7
Dashed
7
Continuous
7
Dashed
7
Dashed
7
Continuous
7
Dashed
7
Continuous
52
EXHIBIT B
11-28-12 REV4
C-NGAS-JUID
C-NGAS-DEVC
Natural gas junction identification: hydrant fill points,
vaults, manholes, handholes, test boxes, vent
vaults, and valve vaults - annotation (UIUC)
Natural gas devices: vents, markers, meters,
pumps, regulators, tanks, taps, and valves (UIUC)
Continuous
52
Continuous
52
Continuous
Hidden
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
52
253
52
52
52
52
52
52
Continuous
Continuous
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
52
52
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
C-NGAS-STID
C-NGAS-IDEN
C-NGAS-CVNT
C-NGAS-WSGN
C-NGAS-LSTA
C-NGAS-TRAN-MAIN
C-NGAS-TRAN-ACAN
C-NGAS-TRAN-RWRE
C-NGAS-TRAN-RSTA
C-NGAS-TRAN-GSTA
C-GSLP-SERV
Natural gas device identification: vents, markers,
meters, pumps, regulators, tanks, taps, and valves annotation (UIUC)
Natural gas pipe - abandoned (UIUC)
Natural gas pipe - main (UIUC)
Natural gas pipe - service (UIUC)
Natural gas anode test station (UIUC)
Natural gas booster station (UIUC)
Natural gas reducing station (UIUC)
Natural gas pumping station (UIUC)
Natural gas station identification tags: anode test,
booster, reducing, pumping - annotation (UIUC)
Natural gas identification notes - annotation (UIUC)
Natural gas casing vent (UIUC)
Natural gas warning sign (UIUC)
Natural gas located station (UIUC)
Natural gas transmission main (UIUC)
Natural gas transmission anode canister (UIUC)
Natural gas transmission rectifier wire (UIUC)
Natural gas transmission rectifier station (UIUC)
Natural gas transmission gas station (UIUC)
LP Gas service (UIUC)
C-NGAS-OTHR-JUNC
Natural gas junction: hydrant fill points, vaults,
manholes, handholes, test boxes, vent vaults, and
valve vaults (owned or maintained by others)
Continuous
7
C-NGAS-OTHR-JUID
Natural gas junction identification: hydrant fill points,
vaults, manholes, handholes, test boxes, vent
vaults, and valve vaults - annotation (owned or
maintained by others)
Continuous
7
C-NGAS-OTHR-DEVC
Natural gas devices: vents, markers, meters,
pumps, regulators, tanks, taps, and valves (owned
or maintained by others)
Continuous
7
Continuous
7
Hidden
253
Dashed
7
Dashed
7
Continuous
7
Continuous
7
Continuous
7
C-NGAS-DVID
C-NGAS-ABND
C-NGAS-MAIN
C-NGAS-SERV
C-NGAS-ANOD
C-NGAS-BOOS
C-NGAS-REDC
C-NGAS-PUMP
C-NGAS-OTHR-DVID
C-NGAS-OTHR-ABND
C-NGAS-OTHR-MAIN
C-NGAS-OTHR-SERV
C-NGAS-OTHR-ANOD
C-NGAS-OTHR-BOOS
C-NGAS-OTHR-REDC
Natural gas device identification: vents, markers,
meters, pumps, regulators, tanks, taps, and valves annotation (owned or maintained by others)
Natural gas pipe - abandoned (owned or maintained
by others)
Natural gas pipe - main (owned or maintained by
others)
Natural gas pipe - service (owned or maintained by
others)
Natural gas anode test station (owned or
maintained by others)
Natural gas booster station (owned or maintained
by others)
Natural gas reducing station (owned or maintained
by others)
PROJECT SUBMITTAL REQUIREMENTS
42
EXHIBIT B
11-28-12 REV4
C-NGAS-OTHR-PUMP
C-NGAS-OTHR-STID
C-NGAS-OTHR-IDEN
Steam Distribution System
C-STEA-JUNC
C-STEA-JUID
C-STEA-DEVC
C-STEA-DVID
C-STEA-ABND
C-STEA-STNL
C-STEA-TUNL
C-STEA-TRAP
C-STEA-UGEC
C-STEA-LP
C-STEA-UP
C-STEA-HP
C-STEA-CR
C-STEA-PR
C-STEA-VR
C-STEA-IDEN
Sanitary Sewer System
C-SSWR-JUNC
C-SSWR-JUID
C-SSWR-DEVC
C-SSWR-DVID
C-SSWR-GSYM
C-SSWR-UGEC
C-SSWR-ABND
C-SSWR-MAIN
C-SSWR-SERV
C-SSWR-FRCM
C-SSWR-SEPT
C-SSWR-ARRW
C-SSWR-IDEN
C-SSWR-AGEC
Natural gas pumping station (owned or maintained
by others)
Continuous
7
Continuous
7
Continuous
7
Continuous
211
Continuous
211
Hidden
Phantom2
Phantom2
Varies
Varies
Center2
Center2
Center2
Center2
Center2
Center2
Continuous
253
211
211
Varies
Varies
211
211
211
211
211
211
211
Continuous
3
Continuous
3
Continuous
3
Continuous
3
Sanitary sewer graphic symbol
Continuous
3
Sanitary sewer underground enclosure
Sanitary sewer pipe - abandoned (UIUC)
Sanitary sewer pipe - main (UIUC)
Sanitary sewer pipe - service (UIUC)
Sanitary sewer pipe - forcemain (UIUC)
Sanitary sewer septic systems (UIUC)
Sanitary sewer direction of flow arrows (UIUC)
Sanitary sewer identification notes - annotation
(UIUC)
Continuous
Hidden
DashDot2
DashDot2
Hidden
DashDot2
Continuous
3
253
3
3
3
3
3
Continuous
3
Sanitary sewer above ground enclosure
Continuous
3
Natural gas station identification tags: anode test,
booster, reducing, & pumping - annotation (owned
or maintained by others)
Natural gas identification notes - annotation (owned
or maintained by others)
Steam distribution junction: vaults and manholes
(UIUC)
Steam distribution junction identification: vaults and
manholes (UIUC)
Steam distribution devices vaults, traps, condensate
pumps (UIUC)
Steam distribution device identification tags: vaults,
traps, condensate pumps - annotation (UIUC)
Steam distribution abandoned tunnels, piping
(UIUC)
Steam distribution shallow tunnel (UIUC)
Steam distribution tunnel (UIUC)
Steam distribution trap (UIUC)
Steam distribution underground enclosure (UIUC)
Steam distribution: low pressure piping (UIUC)
Steam distribution: utility pressure piping (UIUC)
Steam distribution: high pressure piping (UIUC)
Steam distribution: condensate return piping (UIUC)
Steam distribution: pressure return (UIUC)
Steam distribution: vacuum return (UIUC)
Steam distribution identification notes (UIUC)
Sanitary sewer junction: manholes and lift-stations
(UIUC)
Sanitary sewer junction identification: manholes and
lift-stations - annotation (UIUC)
Sanitary sewer devices: cleanouts and air-release
valves (UIUC)
Sanitary sewer device identification: cleanouts and
air-release valves - annotation (UIUC)
PROJECT SUBMITTAL REQUIREMENTS
43
EXHIBIT B
11-28-12 REV4
C-SSWR-OTHR-JUNC
C-SSWR-OTHR-JUID
C-SSWR-OTHR-DEVC
C-SSWR-OTHR-DVID
C-SSWR-OTHR-UGEC
C-SSWR-OTHR-ABND
C-SSWR-OTHR-MAIN
C-SSWR-OTHR-SERV
C-SSWR-OTHR-SEPT
C-SSWR-OTHR-FRCM
C-SSWR-OTHR-ARRW
C-SSWR-OTHR-IDEN
Storm Drainage System
C-STRM-JUNC
C-STRM-JUID
C-STRM-DEVC
C-STRM-DVID
C-STRM-GSYM
C-STRM-ABND
C-STRM-MAIN
C-STRM-SERV
C-STRM-UDRN
C-STRM-FRCM
C-STRM-ARRW
C-STRM-POND
C-STRM-DTCH
C-STRM-EROS
C-STRM-IDEN
Sanitary sewer junction: manholes and lift-stations
(owned or maintained by others)
Continuous
7
Sanitary sewer junction identification: manholes and
lift-stations - annotation (owned or maintained by
others)
Sanitary sewer devices: cleanouts and air-release
valves (owned or maintained by others)
Continuous
7
Continuous
7
Sanitary sewer device identification: cleanouts and
air-release valves - annotation (owned or
maintained by others)
Continuous
7
Continuous
7
Hidden
253
Dashed
7
Dashed
7
Dashed
7
Hidden
7
Sanitary sewer underground enclosure (owned or
maintained by others)
Sanitary sewer pipe - abandoned (owned or
maintained by others)
Sanitary sewer pipe - main (owned or maintained by
others)
Sanitary sewer pipe - service (owned or maintained
by others)
Sanitary sewer septic systems (owned or
maintained by others)
Sanitary sewer forcemain (owned or maintained by
others)
Sanitary sewer direction of flow arrows (owned or
maintained by others)
Sanitary sewer identification notes - annotation
(owned or maintained by others)
Continuous
7
Continuous
7
Storm drainage junction: manholes, curb inlets,
catch basins, drainage inlets, and storm drains
(UIUC)
Continuous
70
Continuous
70
Continuous
70
Continuous
70
Continuous
Hidden
Hidden
Hidden
Hidden
Hidden
Continuous
70
253
70
70
70
70
70
Continuous
Varies
Continuous
Varies
Continuous
Varies
Continuous
Varies
Storm drainage junction identification: manholes,
curb inlets, catch basins, drainage inlets, and storm
drains - annotation (UIUC)
Storm drainage devices: headwalls, cleanouts,
downspouts, culverts and air-release valves (UIUC)
Storm drainage device identification: headwalls,
cleanouts, downspouts, culverts and air-release
valves (UIUC)
Storm sewer graphic symbol
Storm drainage pipe - abandoned (UIUC)
Storm drainage pipe - main (UIUC)
Storm drainage pipe - service (UIUC)
Storm drainage pipe - underdrain (UIUC)
Storm drainage pipe - forcemain (UIUC)
Storm drainage direction of flow arrows (UIUC)
Storm drainage detention basins, retention basins
with annotation (UIUC)
Storm drainage swales / ditches with annotation
(UIUC)
Storm drainage erosion control with annotation
(UIUC)
Storm drainage identification notes - annotation
(UIUC)
PROJECT SUBMITTAL REQUIREMENTS
44
EXHIBIT B
11-28-12 REV4
C-STRM-OTHR-JUNC
Storm drainage junction: manholes, curb inlets,
catch basins, drainage inlets, and storm drains
(owned or maintained by others)
Continuous
7
C-STRM-OTHR-JUID
Storm drainage junction identification: manholes,
curb inlets, catch basins, drainage inlets, and storm
drains - annotation (owned or maintained by others)
Continuous
7
C-STRM-OTHR-DEVC
Storm drainage devices: headwalls, cleanouts,
downspouts, culverts and air-release valves (owned
or maintained by others)
Continuous
7
Continuous
7
Hidden
7
Hidden
7
Hidden
7
Hidden
7
Hidden
7
Continuous
7
Continuous
Continuous
7
7
Continuous
7
Continuous
7
Hidden
253
Telecommunication system tower
Telecommunication system conduit - main (UIUC)
Telecommunication system conduit - service (UIUC)
Telecommunication system cable - direct burried
(UIUC)
Telecommunication system fiber optic (UIUC)
Telecommunication system identification notes annotation (UIUC)
Continuous
Continuous
Continuous
7
7
7
Continuous
Continuous
7
7
Continuous
7
Road bridge
Transportation road flowline curb
Transportation road top back of curb
Transportation road rights-of-way, with markers
Transportation road centerlines
Transportation road centerline identification annotation
Continuous
Continuous
Continuous
Continuous
Continuous
Varies
Varies
Varies
Varies
Varies
Continuous
Varies
C-STRM-OTHR-DVID
C-STRM-OTHR-ABND
C-STRM-OTHR-MAIN
C-STRM-OTHR-SERV
C-STRM-OTHR-UDRN
C-STRM-OTHR-FRCM
C-STRM-OTHR-ARRW
C-STRM-OTHR-IDEN
Telecommunications System
C-TELE-JUNC
C-TELE-JUID
C-TELE-ABND
C-TELE-TOWR
C-TELE-MAIN
C-TELE-SERV
C-TELE-DBRY
C-TELE-FIBR
C-TELE-IDEN
Storm drainage device identification: headwalls,
cleanouts, downspouts, culverts and air-release
valves (owned or maintained by others)
Storm drainage pipe - abandoned (owned or
maintained by others)
Storm drainage pipe - main (owned or maintained
by others)
Storm drainage pipe - service (owned or maintained
by others)
Storm drainage pipe - underdrain (owned or
maintained by others)
Storm drainage pipe - forcemain (owned or
maintained by others)
Storm drainage direction of flow arrows (owned or
maintained by others)
Storm drainage identification notes - annotation
(owned or maintained by others)
Telecommunication system junction: vaults,
manholes, handholes, junction boxes, pull boxes,
pedestals & splices (UIUC)
Telecommunication system junction identification:
vaults, manholes, handholes, junction boxes, pull
boxes, pedestals and splices (UIUC)
Telecommunication system conduit, cable, fiber
optics - abandoned (UIUC)
Site Transportation System
Road System
C-ROAD-BRDG
C-ROAD-FLCB
C-ROAD-TBCB
C-ROAD-RWAY
C-ROAD-CNTR
C-ROAD-CNID
PROJECT SUBMITTAL REQUIREMENTS
45
EXHIBIT B
11-28-12 REV4
C-ROAD-GARD
C-ROAD-IDEN
C-ROAD-PVID
C-ROAD-SIGN
C-ROAD-MINR
Parking System
C-PKNG-CARS
C-PKNG-CNID
C-PKNG-CNTR
C-PKNG-CURB
C-PKNG-DRAN
C-PKNG-SPID
C-PKNG-IDEN
C-PKNG-SIGN
C-PKNG-PVMK
Railroad System
C-RAIL-CNID
C-RAIL-CNTR
C-RAIL-BRDG
C-RAIL-RAIL
C-RAIL-SIGN
Transportation road guardrails
Transportation road identification - annotation
Transportation road pavement type identification annotation
Transportation road signage with annotation
Transportation minor roads (crushed stone, dirt, oil
and chip) not defined by curbs
Continuous
Continuous
Varies
Varies
Continuous
Continuous
Varies
Varies
Continuous
Varies
Parking lot graphic illustration of cars
Parking lot centerline identification - annotation
Parking lot centerlines
Parking lot curbs, parking bumpers, islands
Parking lot drainage slope indications
Parking lot space identification - annotation
Parking lot identification - annotation
Parking lot signage with annotation
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Parking lot pavement markings (space stripes,
handicapped symbols, Right/Left/Straight turn
arrows etc.)
Continuous
Varies
Railroad centerline identification - annotation
Railroad centerline
Railroad bridge structure
Railroad rails
Railroad signage with annotation
Varies
Center
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Landscape plant trees & hedge rows
Landscape plant trees identification tags: decidous,
coniferous and hedge rows etc. - annotation
Landscape plant ground covers and vines
Landscape plant rock, bark, and other Landscape
beds, planters
Landscape plant lawn areas
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Site Landscaping
Plants
L-PLNT-TREE
L-PLNT-TRID
L-PLNT-GRND
L-PLNT-BEDS
L-PLNT-TURF
Irrigation System
L-IRRIG-JUNC
L-IRRIG-JUID
L-IRRIG-DEVC
L-IRRIG-DVID
L-IRRIG-ABND
L-IRRIG-MAIN
L-IRRIG-SERV
Structures
L-SITE-WALL
L-SITE-STEP
L-SITE-DECK
Landscape irrigation system junction: manholes,
vaults, and valve vault (UIUC)
Landscape irrigation system junction identification:
manholes, vaults, and valve vault - annotation
(UIUC)
Landscape irrigation system devices: valves,
meters, sprinkler heads and hydrants (UIUC)
Landscape irrigation system device identification:
valves, meters, sprinkler heads and hydrants
(UIUC)
Landscape irrigation system pipe - abandoned
(UIUC)
Landscape irrigation system pipe - main (UIUC)
Landscape irrigation system pipe - service (UIUC)
Varies
Varies
Hidden
Varies
Varies
253
Varies
Varies
Landscape site retaining walls
Landscape site steps (not attached to buildings)
Landscape site decks
Varies
Varies
Varies
Varies
Varies
Varies
PROJECT SUBMITTAL REQUIREMENTS
46
EXHIBIT B
11-28-12 REV4
L-SITE-BRDG
L-SITE-POOL
L-SITE-SPRT
L-SITE-PLAY
L-SITE-STRC
Hydroseeding
L-HYDR-IDEN
L-HYDR-GENL
L-HYDR-SEED
L-HYDR-SODS
L-HYDR-SPRG
L-HYDR-SDSD
L-HYDR-SDSG
L-HYDR-SSSG
Turfing
L-TURF-IDEN
L-TURF-MLCH
Seeding
L-SEED-IDEN
L-SEED-SDSD
L-SEED-SSSG
L-SEED-SDSG
L-SEED-SODS
L-SEED-GENL
Landscape site bridges
Landscape site pools and spas
Landscape site sports fields
Landscape site play structures
Landscape site structures for ecstatic purposes
(brick columns, concrete benches, statues, etc.)
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Hydroseeding annotation
Hydroseeding
Hydroseeding seed
Hydroseeding sod
Hydroseeding sprigs
Hydroseeding seed and sod
Hydroseeding seed and sprig
Hydroseeding seed, sod, and sprig
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Turfing annotation
Turfing mulch outlines
Varies
Varies
Varies
Varies
Seeding annotation
Seeding seed and sod
Seeding seed, sod, and sprig
Seeding seed and sprig
Seeding sod
Seeding seed
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
Varies
PROJECT SUBMITTAL REQUIREMENTS
47
EXHIBIT B
11-28-12 REV4
DRAWINGS
DRAWING 00100-1: SPACE INVENTORY – ROOM NUMBERING
SYSTEM
DRAWING 00100-2: SPACE INVENTORY – ACTUAL ROOM USE
ASSIGNED
DRAWING 00100-3: SPACE INVENTORY – AREA POLYLINES
PROJECT SUBMITTAL REQUIREMENTS
48
DRAWINGS
11-28-12 REV 4
PROJECT SUBMITTAL REQUIREMENTS
49
DRAWINGS
11-28-12 REV 4
PROJECT SUBMITTAL REQUIREMENTS
50
DRAWINGS
11-28-12 REV 4
PROJECT SUBMITTAL REQUIREMENTS
51
DRAWINGS
11-28-12 REV 4
CHANGE LOG
Revision
#
4
Date
11-28-12
3
1-19-11
Change(s) Made
Part 1, E, 5 – removed
Part 1, G, 2, a – added “staples, or post bindings”
Part 1, F, 3 – remove (O&M copies and warranties covered in Project Manual)
Part 1, F, 4, b (now 3b) – added option for Department/College to specify #/size of copies
Part 1, G, 3, a – changed “Word 2003” to “Word 2010 or earlier”
Part 1, G, 3, b – added “, searchable”
Part 1, G, 3, f – added “and two subfolders titled “pdf” and “Word.” There shall not be
any further subfolders within the “pdf” and “Word” folders except to denote multiple
volumes in accordance with the hardcopy set.”
Part 1, H, 1, f – added Discipline Designator requirements
Part 1, H, 2, a – added “(no single corner staples or bare metal ACCO-style fasteners)”
Part 1, H, 3, a – changed “AutoCAD 2006” to “AutoCAD 2012 or earlier”
Part 1, H, 3, b – added “searchable, and”
Part 1, H, 3, h – corrected typo “C100-C1-4.dwg” to “C100-C104.dwg”
Part 2, Chapter II, B, 1 – added “No Metric Equivalents”
Part 2, Chapter II, B, 4, a – changed 1986 to 2011
Part 2, Chapter II, C, 2 – Removed Geotechnical, Civil Works, Equipment, Process,
Resource, Other Disciplines, Contractor/Shop Drawings, Operations. Added HZ –
Hazardous Materials. Changed Discipline Codes H to Heating, and V to Ventilation.
Exhibit A, Project Manual, E-copy – corrected typo omission – added “pdf”
Exhibit B – Removed Annotation Layers: Q-OTLN, Q-POWR, Q-PIPE, R-****-OTLN,
R-****-DETL, R-****-PATT, R-****-ANNO. Added: *-ANNO-GRID, C-PROP-PRVT,
C-SITE-BRCK, C-ELEC-OTHR-TGRD, C-NGAS-CVNT, C-NGAS-WSGN, C-NGASLSTA, C-NGAS-TRAN-MAIN, C-NGAS-TRAN-ACAN, C-NGAS-TRAN-RWRE, CNGAS-TRAN-RSTA, C-NGAS-TRAN-GSTA, C-GSLP-SERV, C-STEA-TRAP, CSTEA-UGEC, C-SSWR-GSYM, C-SSWR-UGEC, C-SSWR-AGEC, C-SSWR-OTHRUGEC, C-STRM-GSYM, C-TELE-TOWR, L-PLNT-SHRB. Changed H-PLAN to HZPLAN and H-SITE to HZ-SITE; and added “kiosk” to C-BLDG-MINR.
Part 1, A – added clarification of document purpose
Part 1, D – deleted items 3 through 9.
Part 1, F, 2 – clarified department in item d, and moved “Class Tech” from item g to a new
item e.
Part 1, H, 3, b – added “rotated to the correct direction”
Part 1, H, 3 – struck item h
Part 1, H, 3, i (now item h) – added clarification for multi-sheet CAD files
Part 1, H, 3 – added items I, j, k, l
Part 1, I – added item h
Part 2, Chapter II, B, 1 – added “No metric equivalents.”
Part 2, Chapter II, B, 4 – added “The model shall be oriented so North is either to the top (^)
or left (<) on the drawing document.”
Part 2, Chapter II, B, 4, a – updated required version of Illinois State Plan Coordinate
System.
Part 2, Chapter II, B – added item 11
Part 2, Chapter II – added item D
Exhibits – made changes in checklist to reflect above changes
Change Log – added “Change Log”
PROJECT SUBMITTAL REQUIREMENTS
52
CHANGE LOG
11-28-12 REV 4
Download