U P C O M I N G C A P I TA L P R OJ E CT C O N S T R U CT I O N
IMPORTANT ANNOUNCEMENT
PROJECT DESCRIPTION
The existing 6" and 8" cast iron pipe (CIP) water mains along Alameda de las Pulgas between Cipriani Boulevard and
Arbor Avenue were installed in the mid-1950s and have experienced numerous water main breaks over the past several
years. The Mid-Peninsula Water District (MPWD) replaced a 320 LF section from Belle Monti Avenue to Coronet
Boulevard in recent years. The upcoming project will replace the remaining sections of water main between Cipriani
Boulevard and Arbor Avenue with new 8" ductile iron pipe (DIP), eliminating the 6" and 8" aged pipe along this road.
This project is identified among the highest priority projects within the MPWD’s Capital Improvement Program
developed in 2015 after extensive water hydraulic modeling of the entire MPWD system.
MPWD’s total estimated cost for this project is budgeted at $750,000, including engineering design, project management,
and construction. It will be funded with ratepayer revenues in Fiscal Years 2015/2016 and 2016/2017.
A community meeting will be hosted by the MPWD regarding this project on Tuesday, March 8, 2016, at 6:30 p.m.,
at the MPWD, 3 Dairy Lane, in Belmont. All ratepayers are invited to attend to learn more about the project and
interact with the project team.
CONSTRUCTION HIGHLIGHTS
■
■
■
■
Construction will start the week of June 13, 2016 and could last until the end of August 2016. During this period,
Alameda de las Pulgas between Arthur Avenue and Cipriani Boulevard will be CLOSED to through-way traffic,
Monday to Friday, from 9:00 a.m. to 3:00 p.m.
During construction hours, please be aware of heavy equipment, construction personnel, and increased noise levels.
There will be a few hours during the project that the water will be shut off (only between 9:00 a.m. and 3:00 p.m. on
a week day) in order to connect the new water main. Per MPWD policy, we will notify impacted residents about any
water shut-off at least 48 hours prior to doing so.
There will be DETOURS available during the construction, including the following options:
•
•
•
•
•
Cipriani Boulevard to Ralston Avenue
Arbor Avenue to Notre Dame Avenue to Alameda de las Pulgas
Notre Dame Avenue to Arbor Avenue to Alameda de las Pulgas
Arthur Avenue to Coronet Boulevard to Notre Dame Avenue
Notre Dame Avenue to Monroe Avenue to Alameda de las Pulgas
For further information, questions, or concerns, please contact
MPWD Operations Manager, Mr. Rene Ramirez during MPWD business hours at:
Produced with eco-friendly printing and paper.
continued on other side
650.591.8941
3 Dairy Ln., Belmont, CA 94002 • www.MidPeninsulaWater.org
IMPORTANT
ALAMEDA DE LAS PULGAS
WATER MAIN REPLACEMENT
■
■
Sanitation services (garbage/recycling/green waste) pickup times will be changed for certain areas to 6:00 a.m. Prior
to start of the construction, an updated sanitation services schedule will be distributed to impacted customers.
During construction hours of 9:00 a.m. to 3:00 p.m. the contractor will try to accommodate customers’ access to
their properties if needed. However, please be advised that vehicular access may not be available depending upon the
stage of construction. Vehicle parking outside the construction area will be designated if access is needed during
construction hours.
■
Parking will not be allowed in the construction zone. “No Parking” signs will be placed in the construction zone.
■
Emergency vehicles will always have access during construction as necessary.
■
An MPWD Operations Inspector will be onsite at all times during construction.
SERVICE AREA FOR WATER MAIN REPLACEMENT
Road closures are subject to change. Expect 15 minutes delay and one-way traffic control on certain intersections.