Legend Insulation zone Air tightness barrier (note: this can also act as a vapour control layer) Blue text Guidance on thermal continuity Red text Guidance on air tightness Rigid insulation / plasterboard composite Values used in psi calculations Material -values used in calculations (W/mK) Plasterboard Insulation (generic) Plywood sheathing Brick outer leaf Mineral wool insulation Concrete block (dense) protected 0.21 0.04 0.13 0.77 0.044 1.13 Concrete block (lightweight, high strength) 0.19 Timber frame Concrete floor beam Concrete screed Render (cement/sand) Gypsum plaster (1000kg/m3) 0.13 2.3 1.15 1.0 0.4 Concrete roof tiles EPDM membrane Timber battens Timber flooring Chipboard Floor joists Aluminium Steel Stainless steel Glass Sarking felt Insulation board 1.5 0.25 0.13 0.13 0.13 0.13 160 50 17 1 0.23 0.022 Timber batten / service void (option) Vapour control layer Structural timber frame General guidance notes Alternative constructions Insulation Sheathing board Breather membrane Wall ties Cavity 1. The rigid insulation / plasterboard construction can be replaced other finishes but this will require that thicker insulation is used in the wall. Ensure that the thermal conductivity of this insulation is equal or less than that used in the cavity of the timber frame, to prevent interstitial condensation problems. 2. Different constructions can be used to provide an outer leaf but check that there is sufficient ventilation provision to prevent moisture from being trapped within the wall. Sealing membrane junctions Outer leaf (brick shown) 3. All membranes should be taped, stapled or bedded in adhesive as identified by manufacturer. Repair all tears in membranes before commencing next stage of work. Psi-value calculations This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Isometric cut-away view 4. For details of all thermal conductivity values of materials used in the psi-value calculations, see Appendix B of the Introduction. Detail 3.00 Thermal continuity checklist Air tightness checklist Ventilation gap equivalent to 5mm minimum continuous opening at ridge is required where the roof pitch is 1. Ensure that insulation layers in roof are fitted perpendicularly, to cover junctions 2. Ensure that roof insulation fully laps timber frame insulation 3. Install cavity barrier at the top of the wall. 1. Check that any air tightness barrier used in the wall overlaps and is robustly joined to the barrier in the ceiling more than 10m Proprietary cross flow ventilator to maintain minimum 25mm air gap Timber batten to provide fixing for plasterboard sheet Vapour control layer in wall and ceiling Ventilation gap equivalent to 10mm minimum continuous opening is required where or ventilation gap equivalent to 25mm minimum continuous opening is required where Cavity barrier giving 30 minute fire resistance - ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. Design advice Minimising condensation risk Insulation between the studs must be tightly fitted leaving no gaps 20x38mm timber battens / services void (optional) Composite rigid insulation / plasterboard 1. Check ventilation paths are clear before installing insulation above the ceiling Thermal Resistance of insulation used in details: Note: See detail numbers 3.02 and 3.21 for other junctions using this roof construction This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0464W/mK Pitched Roof: Ventilated Roofspace - Eaves Detail 3.01 Thermal continuity checklist Air tightness checklist 1. Ensure that insulation layers in roof are fitted perpendicularly, to cover junctions 2. Ensure that roof insulation butts against the timber sheathing in the wall 3. Install cavity barrier at the top of the wall. 1. Check that any air tightness barrier used in the wall overlaps and is robustly joined to the barrier in the ceiling Loft insulation continued up to outer face of the rigid sheathing Full depth dwang required to secure roof bracing at a level above the rafter ties. Alternative batten and bracing details can also be used Cavity barrier giving 30 minute fire resistance ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material Timber runner to provide fixing for plasterboard sheet Design advice Minimising condensation risk Cavity ventilator Vapour control layer in wall and ceiling Insulation between the studs must be tightly fitted leaving no gaps 1. Check ventilation paths are clear before installing insulation above the ceiling Thermal Resistance of insulation used in details: Note: See detail numbers 3.01 and 3.21 for other junctions using this roof construction HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.1006W/mK Pitched Roof: Ventilated Roofspace - Gable Detail 3.02 Thermal continuity checklist Minimum 50mm ventilation path over insulation 1. Ensure that insulation is fitted tightly within the timber frame 2. Ensure that insulation layers in roof are fitted perpendicularly to cover junctions 3. Install cavity barrier at the top of the wall. Air tightness checklist 1. Check that any air tightness barrier used in the wall overlaps with the barrier in the ceiling Masonry built up between ladder legs Cavity ventilator Design advice Cavity barrier giving 30 minute fire resistance ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material Minimising condensation risk Where two insulation types are used together see supplementary guidance Timber runner to provide fixing for plasterboard sheets Note: this construction is typically used where there are habitable rooms within the roof construction HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. Vapour control layer in wall and ceiling Insulation between the studs must be tightly fitted leaving no gaps 1. Check ventilation paths are clear before installing insulation above the ceiling Thermal Resistance of insulation used in details: Note: See detail numbers 3.04, 3.05 and 3.22 for other junctions using this roof construction This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0472W/mK Pitched Roof: Ventilated Rafter Void - Gable Detail 3.03 Thermal continuity checklist 1. Ensure that insulation layers in roof are fitted perpendicularly, to cover junctions 2. Ensure that roof insulation overlaps with the top of the timber frame wall, with minimum 50mm overlap at the narrowest point 3. Install cavity barrier at the top of the wall Air tightness checklist Ventilation gap equivalent to 5mm minimum continuous opening is required at ridge to batten space 1. Check that any air tightness barrier used in the wall overlaps with the barrier in the ceiling Rigid insulation used as sarking. Insulation to be vapour permeable Vapour permeable membrane (with a vapour resistance of not more than 0.6MN.s/g) Lap roof and wall insulation minimum 150mm thickness at narrowest point Proprietary over fascia ventilator Ventilation to batten void Alternative position for plasterboard ceiling Timber batten to provide fixing for plasterboard sheets Vapour control layer in wall and ceiling Cavity barrier giving 30 minute fire resistance - ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material Insulation between the studs must be tightly fitted leaving no gaps Note: this construction is typically used where there are habitable rooms within the roof construction HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. Design advice Minimising condensation risk 1. Check ventilation paths are clear before installing insulation above the ceiling Thermal Resistance of insulation used in details: Note: See detail numbers 3.03, 3.05 and 3.22 for other junctions using this roof construction This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0284W/mK Pitched Roof: Ventilated Batten Void (warm roof) - Eaves Detail 3.04 Thermal continuity checklist 1. Ensure that insulation layers are fitted perpendicularly, to cover junctions 2. Ensure that roof insulation fully laps timber frame insulation 3. Install cavity barrier at the top of the wall. Air tightness checklist Note: this construction is typically used where there are habitable rooms within the roof construction 1. Check that any air tightness barrier used in the wall overlaps with the barrier in the ceiling Minimum 50mm ventilation path over insulation Vapour permeable membrane (with a vapour resistance of not more than 0.25 MN.s/g) Design advice Minimising condensation risk Compressible filler Cavity ventilator Cavity barrier giving 30 minute fire resistance ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material Where two insulation types are used together see supplementary guidance Timber runner to provide fixing for plasterboard sheets Vapour control layer in wall and ceiling Insulation between the studs must be tightly fitted leaving no gaps HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. 1. Check ventilation paths are clear before installing insulation above the ceiling Thermal Resistance of insulation used in details: Note: See detail numbers 3.03, 3.04 and 3.22 for other junctions using this roof construction This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0431W/mK Pitched Roof: Ventilated Batten Void (warm roof) - Gable Detail 3.05 Thermal continuity checklist 1. Ensure that insulation layers in roof are fitted perpendicularly, to cover junctions 2. Ensure that roof insulation fully laps timber frame insulation 3. Install cavity barrier at the top of the wall. Air tightness checklist 1. Check that any air tightness barrier used in the wall overlaps with the barrier in the ceiling Vapour control layer turned up edge of roof insulation, lapped with roof waterproofing layer and sealed Eaves - fix full height blocking piece and tightly fit insulation into void and under deck Membrane roof construction Verge - tightly fit insulation into void over wall and under deck (not shown) Design advice Vapour control layer in ceiling Compressible filler Cavity ventilator Cavity barrier giving 30 minute fire resistance ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material Timber batten to be provided to cover over junction between plasterboard sheets Vapour control layer in wall Insulation between the studs must be tightly fitted leaving no gaps Minimising condensation risk 1. Check ventilation paths are clear before installing insulation above the ceiling 2. A vapour barrier is required at ceiling level, to prevent moisture from entering into the roof construction 3. The option shown here includes a vapour control layer and insulation as part of a membrane roof construction. Similar details could be used for a profiled metal decking roof but consult with manufacturer regarding ventilation requirements. Thermal Resistance of insulation used in details: HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0536W/mK Timber Flat Roof Detail 3.06 Thermal continuity checklist Air tightness checklist 1. Ensure that insulation layers in roof are fitted perpendicularly, to cover junctions 2. Ensure that roof insulation butts against the timber wall sheathing with a minimum of 50mm overlap at narrowest point 3. Install cavity barrier at the top of the wall 1. Check that any air tightness barrier used in the wall overlaps with the barrier in the ceiling Compressible filler Roofing membrane to be taken minimum 150mm above finished roof level Tightly fit compressible insulant between the wall studs above the level of the roof deck Vapour control layer turned up edge of roof insulation, lapped with breather membrane from cavity wall Vapour control layer Design advice Minimising condensation risk Cavity barrier giving 30 minute fire resistance ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material Vapour control layer in wall and ceiling Insulation between the studs must be tightly fitted leaving no gaps 1. Check ventilation paths are clear before installing insulation above the ceiling 2. A vapour barrier is required at ceiling level, to prevent moisture from entering into the roof construction 3. The option shown here includes a vapour control layer and insulation as part of a membrane roof construction. Similar details could be used for a profiled metal decking roof but consult with manufacturer regarding ventilation requirements. Thermal Resistance of insulation used in details: HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0299W/mK Timber Flat Roof with Parapet Detail 3.07 Thermal continuity checklist Air tightness checklist 1. Check that there is no debris in the cavity 2. Install cavity barrier around opening 1. Install window to overlap with outer leaf of wall finish. Alternative: If window lines through with the bottom of the opening in the external finish, some means of preventing a direct line of air infiltration will be required 2. Install air tightness seal between the inside face of the window and the structural finish of the window opening Insulation between the studs must be tightly fitted leaving no gaps Cavity tray with minimum upstand of 140mm and stop ends Use approved lintol details from timber frame supplier 30 minute fire resisting proprietary insulating cavity barrier with integral DPC Vapour control layer Design advice Minimising condensation risk 1. Alternative internal finish at window reveal - use insulation backed plasterboard Compressible fill Weep Hole Thermal Resistance of insulation used in details: Sealant at window frame If position of window head is lower than or level with the underside of the lintol, a larger compressible filler will be required to stop up a potential air infiltration route HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. Psi value = 0.121W/mK Insulate the window reveal Air tightness tape Sealant to back of frame This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Lintel at Window Head Detail 3.08 Thermal continuity checklist 1. Check that there is no debris in the cavity 2. Install cavity barrier around opening Air tightness checklist 1. Install window to overlap with outer leaf of wall finish. Alternative: If window lines through with the bottom of the opening in the external finish, some means of preventing a direct line of air infiltration will be required 2. Install air tightness seal between the inside face of the window and the structural finish of the window opening 30 minute fire resisting cavity barrier with integral DPC Sealant at window frame Air tightness tape and sealant to back of frame Insulate the window reveal Vapour control layer in wall Jamb detail Compressible filler between window and cill Solid cill acts as cavity closer. If pressed cill is used, a 30 minute fire rated thermally insulated cavity closer will be requied Design advice Air tightness tape and sealant to back of frame Insulate the window reveal Minimising condensation risk 1. Alternative internal finish at window reveal - use insulation backed plasterboard Thermal Resistance of insulation used in details: DPC lapped behind cill and below window Vapour control layer in wall Insulation between the studs must be tightly fitted leaving no gaps Cill detail HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. Psi value (jamb)=0.0328W/mK Psi value (cill) = 0.0934W/mK This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Windows and Doors - Jambs and Cills Detail 3.09 Thermal continuity checklist Air tightness checklist 1. Use a lightweight loadbearing concrete block where the wall abuts the concrete slab to minimise thermal bridging 2. Use a perimeter strip of insulation where the concrete slab abuts the concrete blockwork wall 1. Ensure that any air tightness barrier used in the wall overlaps onto the floor slab Vapour control layer in wall Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant Vapour control layer below timber floor finish External ground level Design advice Minimising condensation risk Damp proof membrane above or below slab 20mm strip of perimeter insulation with thermal conductivity ( value) not exceeding 0.025 W/mK around slab and any screed 1. Check that concrete slab is level and clear of debris before fitting the insulation at floor level 2. If a screed finish is used instead of a timber floor, use a strip of perimeter insulation with a minimum R value of Alternative detail 3. Using lightweight blockwork (e.g. with value of 0.19W/mK) to improve the thermal performance at the junction where the external wall and ground floor constructions meet will change the psi value Thermal Resistance of insulation used in details: HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.1145W/mK Ground Bearing Floor: Insulation Above Slab Detail 3.10 Thermal continuity checklist Air tightness checklist 1. Use a lightweight loadbearing concrete block where the wall abuts the concrete slab to minimise thermal bridging 2. Use a perimeter strip of insulation where the concrete slab abuts the concrete blockwork wall Vapour control layer in wall 1. Check that any air tightness barrier used in the wall overlaps onto the floor slab Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant External ground level Design advice Minimising condensation risk Damp proof membrane 50mm strip of perimeter insulation with thermal conductivity ( value) not exceeding 0.025 W/mK around slab and any screed 1. If a screed finish is used instead of a timber floor, use a strip of perimeter insulation with a minimum R value of Alternative detail 2. Using lightweight blockwork (e.g. with value of 0.19W/mK) to improve the thermal performance at the junction where the external wall and ground floor constructions meet will change the psi value Thermal Resistance of insulation used in details: HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.1733W/mK Ground Bearing Floor: Insulation Below Slab Detail 3.11 Thermal continuity checklist Air tightness checklist Vapour control layer in wall 1. Ensure that floor insulation butts against the insulation in the external wall Add timber batten to cover the floor/wall junction. Use air tightness tape at junction of air barrier in wall and floor. Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant 1. Check that any air tightness barrier used in the wall overlaps with the barrier in the floor Air tightness barrier below timber floor finish Insulation directly under flooring supported on netting draped over joists and stapled at required depths External ground level Solum Damp proof membrane Design advice Minimising condensation risk 1. Check that all ventilation paths are clear before installing the floor insulation Sub floor ventilation should be per run of external wall or Alternative detail 2. Using lightweight blockwork (e.g. with value of 0.19W/mK) to improve thermal performance at the junction where the external wall and ground floor constructions meet will change the psi value 3. If there are concerns about damaging the air tightness membrane in the floor finish during construction, an additional services void can be created using timber battens on top of the floor joists Thermal Resistance of insulation used in details: HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0423W/mK Timber Suspended Ground Floor Detail 3.12 Thermal continuity checklist Air tightness checklist Cavity barriers giving 30 minute fire resistance - ensure cavity barriers are not breeched by inappropriate insulation material in the timber frame 1. Check that there is no debris in the cavity 2. Install cavity barrier at junction of wall 1. Check that any air tightness barrier used in the internal wall overlaps with the barrier in the external wall Vapour control layer in wall Design advice Minimising condensation risk 1. Check that insulation is fitted between timber studs at corner junctions Thermal Resistance of insulation used in details: For more information on acoustic details see guidance in Section 5 of the Technical Standards Plan view HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0725W/mK Separating Wall Detail 3.13 Thermal continuity checklist Air tightness checklist 1. Check that there is no debris in the cavity 2. Install cavity barrier in line with floor construction 1. Check that any air tightness barrier used in the external wall overlaps with the barrier in the floor Vapour control layer in wall Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant Cavity ventilator Cavity barrier giving 30 minute fire resistance ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material Design advice Vapour control layer in wall Insulation between the studs must be tightly fitted leaving no gaps Minimising condensation risk 1. Check that insulation is tightly fixed to the timber studs adjacent to the floor junction, leaving no gaps Thermal Resistance of insulation used in details: Separating floors to comply with Section 2: Fire and Section 5: Noise HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0353W/mK Timber Separating Floor Detail 3.14 Thermal continuity checklist Air tightness checklist 1. Check that there is no debris in the cavity 2. Install cavity barrier as necessary 1. Check that any air tightness barrier used in the external wall overlaps with the barrier in the floor Vapour control layer in wall Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant Install air tightness barrier around joists, then lap membrane from walls over it and tape junction Design advice Vapour control layer in wall Insulation between the studs must be tightly fitted, leaving no gaps Minimising condensation risk 1. Check that insulation is tightly fixed to the timber studs adjacent to the floor junction, leaving no gaps Thermal Resistance of insulation used in details: HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0574W/mK Intermediate Floor / External Wall Detail 3.15 Thermal continuity checklist Air tightness checklist Vapour contol layer in wall 1. Ensure that insulation is tightly fitted between the timber floor joists 2. Install cavity barrier as necessary Use air tightness tape at junction of air barrier in wall and floor. Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant Air tightness barrier below timber floor finish 1. Check that any air tightness barrier used in the internal wall overlaps with the barrier in the floor Insulation directly under flooring supported on netting draped over joists and stapled at required depths Damp proof membrane Solum Design advice Minimising condensation risk Sub floor ventilation should be per run of external wall or 1. Check that all ventilation paths are clear before installing the floor insulation Alternative Detail 2. Lightweight thermal blockwork can be used in the separating wall to improve the thermal performance but this will also reduce the acoustic performance of the wall. If this alternative is used then additional elements will be required to meet Section 5 of the Technical Standards. Thermal Resistance of insulation used in details: HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0713W/mK Ground Floor/Separating Wall Junction- timber suspended floor Detail 3.16 Thermal continuity checklist 1. Ensure that insulation is tightly fitted against the separating floor Air tightness checklist Vapour control layer in wall 1. Check that any air tightness barrier used in the internal wall overlaps onto the floor slab Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant Design advice Minimising condensation risk 1. If a screed finish is used instead of a timber floor, use a strip of perimeter insulation with a minimum R value of Damp proof membrane Lightweight loadbearing concrete blockwork to minimise thermal bridging Alternative Detail 2. Heavyweight thermal blockwork can be used in the separating wall below slab level but this will reduce the thermal performance of this junction. Additional construction elements may be required along with lightweight blockwork in order to meet the acoustic requirements of Section 5 of the the Technical Standards Thermal Resistance of insulation used in details: HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.2765W/mK Concrete Ground Floor/ Separating Wall: Insulation Below Slab Detail 3.17 Thermal continuity checklist Air tightness checklist 1. Ensure that insulation is tightly fitted against the separating floor 1. Check that any air tightness barrier used in the internal wall overlaps onto the floor slab Vapour control layer in wall Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant Seal air tightness membrane to floor slab Vapour barrier in floor Design advice Minimising condensation risk Damp proof membrane 1. Check that concrete slab is level and clear of debris before fitting the insulation at floor level 2. If a screed finish is used instead of a timber floor, use a strip of perimeter insulation with a minimum R value of Alternative Detail 3. Lightweight thermal blockwork can be used in the separating wall to improve the thermal performance but this will also reduce the acoustic performance of the wall. If this alternative is used then additional elements will be required to meet Section 5 of the Technical Standards. HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Thermal Resistance of insulation used in details: Timber Frame Psi value = 0.0146W/mK Concrete Ground Floor/ Separating Wall: Insulation Above Slab Detail 3.18 Thermal continuity checklist Air tightness checklist 1. Ensure that insulation is tightly fitted 1. Check that any air tightness barrier used in the internal wall overlaps with the barrier in the floor Alternative: Ensure that a continuous air tightness barrier from the wall wraps around the end of the floor construction, leaving no gaps Vapour control layer in wall Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant Vapour control layer below timber floor finish Cavity barrier Design advice Vapour control layer in ceiling Minimising condensation risk See general guidance notes Vapour control layer in wall Thermal Resistance of insulation used in details: Insulation between the studs must be tightly fitted Separating floors require additional layers and components to comply with Section 2: Fire and Section 5: Noise HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0241W/mK Separating Floor / Wall Junction Detail 3.19 Thermal continuity checklist Air tightness checklist 1. Ensure that insulation is tightly fitted 1. Check that any air tightness barrier used in the internal wall overlaps with the barrier in the floor Alternative: Ensure that a continuous air tightness barrier from the wall wraps around the end of the floor construction, leaving no gaps Vapour control layer in wall Seal between the wall and floor membrane with a flexible sealant or seal the gap between skirting board and floor using a flexible sealant Cavity barrier Design advice Install air tightness barrier around joists, then lap membrane from walls over it and tape junction Vapour control layer in wall Insulation between the studs must be tightly fitted HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. Minimising condensation risk s See general guidance notes Thermal Resistance of insulation used in details: This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0333W/mK Intermediate Floor Detail 3.20 Thermal continuity checklist Air tightness checklist 1. Install a cavity barrier at the top of the wall 2. Ensure that insulation layers in the roof are fitted perpendicularly, to cover junctions 1. Check that there are no gaps between the top of the masonry and the underside of the roof 2. Check that the air tightness barrier in the wall overlaps with the barrier in the ceiling Cavity barrier giving 30 minute fire resistance ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material Where two insulation types are used together see supplementary guidance Design advice Minimising condensation risk 1. Check ventilation paths are clear before installing insulation above the ceiling Thermal Resistance of insulation used in details: Cavity barrier is used in line with ceiling insulation to prevent thermal bypass.Use dense insulation or proprietary cavity barrier in sleeve Separating walls require additional layers and components to comply with Section 2: Fire and Section 5: Noise HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. Vapour control layer in wall and ceiling Note: See detail numbers 3.01 and 3.02 for other junctions using this roof construction Insulation between the studs must be tightly fitted This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0132W/mK Pitched Roof: Cold Roof / Separating Wall junction Detail 3.21 Thermal continuity checklist Air tightness checklist Minimum 50mm ventilation path over insulation 1. Install a cavity barrier at the top of the wall 2. Ensure that insulation layers in the roof are fitted perpendicularly, to cover junctions Cavity barrier giving 30 minute fire resistance ensure cavity barrier is not breeched by inappropriate rigid sheathing insulation material 1. Check that there are no gaps between the top of the masonry and the underside of the roof 2. Check that the air tightness barrier in the wall overlaps with the barrier in the ceiling Where two insulation types are used together see supplementary guidance Vapour control layer in wall and ceiling Insulation between the studs must be tightly fitted Design advice Minimising condensation risk 1. Check ventilation paths are clear before installing insulation above the ceiling Thermal Resistance of insulation used in details: Separating walls require additional layers and components to comply with Section 2: Fire and Section 5: Noise HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. Note: this construction is typically used where there are habitable rooms within the roof construction Note: See detail numbers 3.03, 3.04 and 3.05 for other junctions using this roof construction This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0481W/mK Pitched Roof: Ventilated Batten Void / Separating Wall Junction Detail 3.22 Thermal continuity checklist Air tightness checklist 1. Check that there is no debris in the cavity 2. Install cavity barrier 1. Ensure that any air tightness barrier used in the external wall overlaps at the corner Cavity barrier giving 30 minute fire resistance - ensure cavity barrier is not breeched by inappropriate insulation material Insulation between the studs must be tightly fitted leaving no gaps Design advice Minimising condensation risk Vapour control layer 1. Check that insulation is tightly fixed to the timber studs at the corner junction, leaving no gaps Thermal Resistance of insulation used in details: Plan view HEAT 2.7 software image of isotherms through junction detail. For illustrative purposes only. This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reduction of unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculation provided the principles outlined and any identified component specification are followed. Timber Frame Psi value = 0.0179W/mK Wall Junction Detail 3.23