LONGITUDINAL INDUCTION VOLTAGE MEASUREMENT ON COMMUNICATION CABLES RUNNING PARALLEL TO OVERHEAD LINES IEEE PES Transmission and Distribution Conference_ Chicago April 2008 Dean Sharafi Introduction Electro-magnetic field is created as a result of current passing through the conductor. This field induces a voltage on adjacent conductors depending on: • • • • Distance Angle Screening Bonding. 1 Power Engineer's Considerations Safety Compliance with standards Commissioning Tests Collaboration of power and communication industries Standards International Telecommunication Union Normal Conditions • Accessible by public, 60V r.m.s • Accessible by technicians, 150V r.m.s Fault Conditions • 430V r.m.s • Probability of faults • Protection clearance time 2 LFI Voltage Limits Description LFI Volta ge Limit A High Reliability line with protective equipment that would clear an earth fault within 0.35 secs 1500 Vrms B High Reliability line with protective equipment that would clear an earth fault in, from 0.35 secs to 0.5 secs 1000 Vrms C Line not classed as a High Reliability as protective equipment would not clear an earth fault within 0.5 secs 430 Vrms All Normal operating conditions where the cable can be accessed by technicians 150 Vrms All Normal operating conditions where the cable can be accessed by the public 60 Vrms LINE CATE GOR Y LFI Hazards Hazards to humans (Physiology and probabilistic Analysis) Voltage stress on Telecom Cables Damage to equipment 3 Human Effects Current Magnitude Current path, H-H, H-F Duration Instant of occurrence during heart cycle Body impedance Individual sensitivity Frequency Fault Conditions Earth faults • Zero sequence current in earth-wires information needed during the design stage: • Phase conductor, earth-wire conductor and tower impedances, • Tower dimensions and spanning distances, • Fault currents at the substation, • Mutual impedances between • phase conductors and communication cables, • earth-wire conductor and communication cables 4 Induced Voltage Difference between voltage induced faulted phase conductor and earth-wire. V = CLiK by • where: V = induced longitudinal voltage [V] • C = mutual impedance per unit length [ohm/km] • L = length of exposure (between o/h line and communication cable) [km] • i = fault current [A] • K = shielding factor {K=1 for no shielding} Mutual Impedance C = 2πf log e (1 + 6 × 10 5 ρ ) × 10 − 4 d2 f ohm/km d = geometric separation between earth return circuits in meters ρ = earth resistivity in ohm-meter f = system frequency in Hz 5 Mitigation Measures Increasing shielding pairs in communication cables, Latent shielding for the communication cables via gas-filled protectors, Additional shielding conductor parallel to the power lines/cables, Fiber optic interface Reducing the fault level. Commissioning Tests Injection in the overhead line and measuring the induced voltages. Not practical to inject high currents Scaled to maximum fault current assuming system linearity. At or close to system frequency (50 Hz in Australia), Existence of background noise “standing voltages”. 6 Test Difficulties Inject higher currents and varying the frequency as much away from system frequency as possible. Difficulty in adjusting generators to operate in a range, which they are not primarily designed for • • • • • Phase Angle Meters Double Beam Oscilloscopes Selective Voltmeters Chart Recorders Spike Transient Voltmeters Test Difficulties Heavy equipment logistic difficulties Great amount of manpower Time required for performing tests Test in a large area 7 New Concept Primary test equipment capable of generating voltages and currents at various frequencies and connectable to GPS devices. Current injection is made with various frequencies, and induced voltage is measured simultaneously with the same applied frequency. The results are then extrapolated to show the response of the system for 50Hz frequency. Test Difficulty Difficulty is that in some occasions the injection location is far away from the location where induced voltages have to be measured. 8 Solution Two primary test units, Global positioning system synchronising devices Simultaneous initiation of two sets located at different locations. Test Set-up 9 Test Method Injection unit at injection location, Measuring unit measures the induced voltages at measuring point. Measurement with same injected frequency Two devices synchronised by GPS synchronising clocks. Test Method Off system frequency injection Interpolation of values measured from 30 Hz and 70 Hz injection. Extrapolated to maximum fault current Checked against allowable limits. 10 Case Study On Friday July 15 2005, Western Power performed the measurement of longitudinal voltage induction for the new Thornlie Railway Line Extension on behalf of Public Transport Authority of Western Australia. Design Assumptions A previous report had determined that induction depending on soil resistivity was: • 7.8V – 8.6V under normal train operation, • 166V – 204V under traction fault conditions. • Both values within allowable range 11 Test Results With injection current of 50A Voltage rise for two measurements were 1.02 and 1.05v Extrapolated to a calculated fault level of 4000A, which was 83V. Test Benefits Eliminating need for heavy equipment. More accurate and meaningful results by filtering out system frequency noise. Answer to the problem of testing in a large area. 12 Noise Filtration Voltage (V) Induction Voltage Vs Frequency For 50A Current Injection 2 1.5 1 0.5 0 0 10 20 30 40 50 60 70 80 90 10 0 Frequency (Hz) Induction Voltage Vs Frequency For 50A Current Injection Test Configuration 13 2 950 2.905 2.860 2.815 2.770 2.725 2.680 2.635 2.590 2.545 2.500 2.455 2.410 2.365 2.320 2.275 2.230 2.185 2.140 2.095 2.050 2.005 1.960 1.915 1.870 1.825 1.780 1.735 1.690 1.645 1.600 1.555 1.510 1.465 1.420 1.375 1.330 1.285 1.240 Ref km separation (m) Line Separation High Voltage Overhead Line Separation Com. Cable Line Separation 45 40 35 30 25 20 15 10 5 0 Km reference 14 Thank You for Your Attention! Any Questions? 15