P546 (Rev. 04-2015) 15_00221 British Columbia Service Entrance Requirements for Single Family Residential Buildings TELUS Communications Inc. is responsible for providing and installing the network wiring to the property, and the owner/developer is responsible for providing a suitable pathway (trench, conduit, aerial support etc.) as stipulated by TELUS Communications Inc. from the property line to the building Service Provider Demarcation Point (SPDP). FIGURE 1A - Typical Single Family Residence Electrical utility mast and Weatherhead (Note 2) Electrical utility service Telephone Weatherhead (Note 3) Telephone attachments Telephone drop to building 300 mm (12") Separation (in all directions) (Note 1) Aerial Service – If the drop wire crosses a street or lane to reach the house, . the minimum placing clearance is 5.3 m (17.4') above the crown of the road. If the minimum road clearance cannot be maintained, a clearance pole will be requested by TELUS to be installed. This will provide the minimum required CSA clearance in all weather conditions. So, if your house is a low ranch style, to ensure adequate road clearance it may be necessary to place a mast. Telephone drop wire may attach to the same mast as electrical utility. If this is done, a minimum of a 300 mm (12") separation must be kept between electrical utility and TELUS wires. 35 mm (1-1/4") Conduit Communication drops (wires) Preferred installation method Alternate aerial routes 35 mm (1-1/4") Conduit Jack (Note 5) CATV only distribution box TELUS only box For aerial service, the following materials, available at electrical suppliers, are required: Weatherhead, EMT (metal) or PVC (plastic) with UV inhibitor conduit, pull string and a plastic Network Interface Box (NIB) (in-wall or surface mounted). A conduit size of 35 mm (1-1/4") minimum allows for placing of TELUS and CATV service wire to the building. Please contact your local CATV representative for their requirements. 1.3 m (4'- 3") above finished grade See underground service below If the conduit is to support the drop wire from the pole then a minimum of 53 mm (2") HDG iron pipe must be used. FIGURE 2 - Exterior Flush Mounted Network Interface Box (NIB) and Demarcation Boxes Grounding – TELUS recommends that a No. 6 AWG green insulated ground wire be provided from (and connected to) the power service ground to the NIB. This is the maximum size conductor required by the Canadian Electrical Code (CEC) and therefore ensures that grounding will be adequate to accommodate future growth of the communication installation. Please note that the minimum size of ground wire that TELUS will accept is a No.10 AWG green insulated ground wire. See Canadian Electrical Code Section 60-704. The grounding conductor placed in the NIB should then be directly connected to the grounding conductor of the building’s consumer service. As the next (least recommended) alternative, the NIB grounding conductor may be attached to the power service electrical equipment enclosures (if allowed by the electrical inspector). Where the power grounding conductor is run within a metal conduit, the NIB grounding conductor should be bonded to that conduit. . Aerial Option Remove cap and place conduit access path See instructions provided with box Weatherhead CATV Enclosure Property line NIB NIB Single Family Home Garage Pipe adapter access Telephone to CATV 6.5 m (21.3') max. height to service attachment point TELUS NIB 1 - 53 mm (2") This ground wire should be as short as possible, as a guideline it should be less than 6 m (20'), with as few bends as practical (sweep bends only). It must be permanent and, where needed, guarded from mechanical injury. An approved connector should be used for all connections. Notes: Inside wire (customer owned) Underground conduit TELUS demarcation point and protector (Note 4) 2 - 53 mm (2") Entrance conduits supplied/installed by developer 1. A minimum 300 mm (12") clearance must be maintained in all directions between TELUS wires and electrical utility wires. 2. TELUS wires may be attached to the electrical utility mast for support below the electrical utility wires – 300 mm (12") clearance. 3. Electrical utility wires cannot be attached to the TELUS mast for support in order to meet CEC clearance requirements. 4. TELUS’ policy is to place the protector/demarcation blocks on the first building on which the drop or entrance cable attaches, except, when no service is required at the first building and the entrance cable conduit is continuous to the second building. 5. On single family homes all wires placed beyond the demarcation point (termination point of the entrance cable or drop) is classifed as inside wire and is the responsibility of the owner. FIGURE 3 - Exterior Surface Mounted Network Interface Box (NIB) 6.“Flexible or Rigid conduit” (complete with string) to be placed in the stud wall or concrete slab from the NIB to the inside wire Star Configuration inside the home supplied and installed by the owner/builder. 27 mm (1") conduit for TELUS “only” or 35 mm (1-1/4") for “shared” TELUS and CATV. 7. The inside wiring should be done in a “Star Configuration” where the individual set runs from each telephone jack and TV location collect at a common location within the home. Page 1 of 3 Aerial Option 35 mm (1-1/4") PVC or 53 mm (2") rigid steel mast “ Flexible or Rigid conduit” in the stud wall or concrete slab from the NIB to the inside wire Star Configuration inside the home 76 mm ( 3") ± 12.7 mm (1/2") 76 mm ( 3") ± 12.7 mm (1/2") TELUS installed protectors (NID) Ground bar for No.6 AWG green ground wire Underground Option 27 mm (1") or 53 mm (2") PVC 27 mm (1") for No.6 AWG green insulated ground, TELUS cable Mobile Home on Private Property Mobile home owners are required to provide: FIGURE 1B - Mobile Home on Private Property (BC) Notes: 1. For aerial service, a Class 6 treated pole shall be provided adjacent to the mobile home at the point of service entry. The treated pole shall set 1.22 m (4') into the ground no more than 610 mm (2') from the mobile unit. Drop wire (Note 1) For single mobile homes on private property For minimum clearance over public and private property, see telus.com/bics 2. For underground service, a 2 m (6.5') treated post measuring 100 mm X 100 mm (4" X 4") shall be set 0.7 m (28") into the ground with 1.3 m (4'- 3") ± 200 mm (8") above the final grade is required. The building owner is required to supply a No.6 AWG green insulated ground wire to the NIB. Demarcation point (NIB) Underground option Underground Service Figure 4A – 1 FIGURE 4A -Typical Section Thru Trench Property line Figure 4B – 2A 53 mm (2") PVC-DB2 300 mm (12") radius bend or 90° 53 mm (2") PVC J-bend (may be either DB2 duct or schedule 40). 450 mm (18") Minimum or same depth as 6A electrical utility Figure 4B – 3 The owner/builder is to make the physical connection at the TELUS specified point-of-connection. Figure 4A – 4 5 TELUS conduit must be on the property line side of the trench with 300 mm (12") separation from electrical utility conduit. No crossover of TELUS conduit and electrical utility is permitted. Electrical The minimum cover above conduit to 450 mm (18") or the same utility conduit depth as electrical utility. Figure 4A – 6 All material used for back-filling must be select fill, clear of all rocks and sharp stones unless otherwise specified. Figure 4A – 6A Native fill free of rock larger than 150 mm (6"). Stud Figure 4B – 7A Owner/builder to provide drain in 90° bend into drain rock, by Knockout perforating the bend on the bottom side. for aerial Figure 4B – 8 No installation can have more than two 90° or equivalent bends connection (2 X 45° = 1 X 90°) without the use of a pull box. Pull boxes or L-bends must not be used in place of a bend. An additional pull box is required if the maximum pulling length of 60 m (200') through two 90° (300 mm (12") radius) is exceeded or if the maximum pulling length of 90 m (300') on a straight pull is exceeded. 300 mm (12") Minimum CATV TELUS NIB 10 7 1.3 m (4'- 3") above finished grade 11 Base plate Figure 4B – 14 The owner/builder to provide and install a non-metallic “Flexible or Rigid conduit” (complete with string) in the stud wall or concrete slab from the NIB to the inside wire Star Configuration inside the home. 27 mm (1") conduit for TELUS “only” or 35 mm (1-1/4") for “shared” TELUS and CATV. NOTE: All materials supplied by owner/developer are available at electrical supply outlets. TELUS service box 12 Finished floor The exposed 53 mm (2") orange conduit may be reduced to 27 mm (1") grey conduit above the finished grade level. Do not glue the coupler reducer to the 53 mm (2") conduit, as access to the larger conduit may be required in the future. Page 2 of 3 4 14 Figure 4B – 13 All above requirements are subject to local building inspector’s approval. 200 mm (8") Exterior finish Sheathing Caulk Figure 4B – 10 Owner/builder to provide and install the plastic in-wall or surface Network Interface Box (NIB). Figure 4B – 12 Depending upon foundation type and local bylaws, conduit can be attached to exterior (All exposed PVC conduit must have UV inhibitors). 1 100 mm (4") FIGURE 4B - Typical Section Thru Trench (In-Wall) Extend conduit 1.3 m (4'- 3") above the final grade into NIB. Pull string to be 3 mm (1/3") braided nylon cord. Figure 4B – 11 Owner/builder to ensure that TELUS and electrical utility conduit exit the concrete at minimum 300 mm (12") separation. 4 6 Figure 4A – 5 Figure 4B – 9 27 mm (1") schedule 40 PVC duct recommended NIB The owner/builder is responsible for supplying all material and civil work (to TELUS specifications) on private property. Figure 4B – 2 All duct material will be orange in colour. (53 mm (2") PVC-DB2 conduit; 53 mm (2") PVC-DB2 coupler) Figure 4B – 7 Post (Note 2) Finished grade Property line 450 mm (18") 2 Minimum 13 2A 1-53 mm (2") PVC DB2 duct 7A 750 mm (30") Minimum A Network Interface Box (NIB) provided by the owner/builder is required for aerial or underground service. TELUS will install protection and demarcation devices inside the NIB. At least one inside wire run must extend into the NIB where it can be attached to the demarcation device. Placed by developer or TELUS 9 Coupling 3 Placed by builder/owner 8 Wiring to Inside Star Configuration Outdoor Network Interface Box (NIB) to Inside Star Configuration ■ FIGURE 5A - Star Configuration Attached Garage The owner/builder to provide and install a non-metallic “Flexible or Rigid conduit” (complete with string) in the stud wall or concrete slab from the NIB to the inside wire Star Configuration inside the home. Conduit is the preferred option and if conduit is not installed, additional services to the home owner may not be possible. ■ V CAT5e Voice D CAT5e Data T CAT5e TV Coax 27 mm (1") conduit for TELUS “only” or 32 mm (1-1/4") for “shared” TELUS and CATV. ■ T When using rigid conduit a maximum of four sweeping 90 degree bends V or a total of 360 degrees is allowable. ■ Extend the pull string from the 27 mm (1") conduit in the NIB to the centre of the Star Configuration inside the home. V T T V D (See Figure 5B) (See Figure 4B) V D CATV TELUS NIB When NOT placing the conduit, pre-wire 2 CAT5e cables along with a single Bend Insensitive Fibre (BIF) (ITU-T-G657 compliant, indoor or outdoor rated) from the Network Interface Box (NIB) on the outside of the house to the inside wire Star Configuration or Multi-media Enclosure inside the home. ■ D Central Wiring Location to be located in heated environment and NOT opening into the garage Flexible or Rigid conduit in the stud wall or concrete slab Service conduit Pre-wire Outlets to Inside Star Configuration (Multimedia Enclosure or Backboard Area) ■ ■ ■ The inside wiring should be done in a “star configuration” where the individual set runs from each telephone jack and TV location collect at a common location within the home (See Figure 5A and 5B). The centre of the star is to be in a heated environment where there is - Owner/builder to provide a Flexible or Rigid conduit from Service Entry conduit to a common Central Wiring Location. - The centre of the star is to be in a heated environment where there is no risk of the ambient air temperature falling below 0° (zero) Celsius. - Coax (CATV) and Cat5e will home run back to a common Central Wiring Location. no risk of the ambient air temperature falling below 0º (zero) Celsius. A garage is NOT a suitable location. Owner/builder will provide one (1) duplex 15A non-switched power FIGURE 5B - Star Configuration receptacle dedicated to home networking communication and entertainment equipment, installed inside the multimedia enclosure. (The use of a Multimedia enclosure or Smart panel is not mandatory although it is strongly recommended.) ■ To Wall Outlets is to be located within 450 mm (18") of the star location for the home networking, communication and entertainment equipment installed at this location. ■ (Backside of Box) Total space required for the mounting of the Fibre Equipment and Multimedia enclosure will be a minimum of 600 mm (24") X 900 mm (36"). ■ Owner/builder will provide patch panels for Voice/Data/Coax. ■ ■ - If a multimedia enclosure is not used, a duplex receptacle All individual set runs are to be terminated at both ends (wall outlets and patch panels). Preferred Multi-media enclosure to have minimum inside dimension of 30" H x 14" W x 3.5"D and be Wi-Fi friendly (Primex P3000 or equivalent suggested) Central Wiring Location to be located in a heated environment and NOT opening into the garage. CATV TELUS NIB Entrance conduit from Property Line 27 mm (1") Flexible or Rigid conduit for TELUS only 35 mm (1-1/4") Flexible or Rigid conduit for TELUS and CATV Reference CSA CEC CATV PVC EMT All CAT5e Voice All CAT5e Data All CAT5e TV All Coax Canadian Standards Association Canadian Electrical Code Community Antenna Television Polyvinyl Compound Electrical Metal Tubing HDG UV DB2 NIB High Density Gauge Ultra Violet Direct Buried Type 2 Conduit Network Interface Box Please call 310-2255 for more information about products and services offered by TELUS or visit telus.com/bics TELUS and the TELUS logo are trademarks of TELUS Corporation, used under licence. © 2015 TELUS. 15_00221-P546 Page 3 of 3