Two-part superstructure made entirely of steel Svinesund, link SUPERSTRUCTURE One bridge - looks like two The superstructure of the bridge consists of two box beams made of steel. The two halves of the superstructures will be joined by a cross-member at each bridge support. Bridge sections 24 metres long and five metres wide will be delivered from the workshop. They will be made of steel plate, which is 12-40 mm thick and has been reinforced with longitudinal profiles. Two sections will be welded together to produce a 10metre-wide deck. Over each bridge support, two decks will be joined together via a cross-member to produce a section 28 metres wide and 24 metres long. The cross-members are steel boxes, eight metres wide and three metres high. They will be anchored in place by powerful cables that will be fixed to clamping struts inside the bridge supports – and thereby unite the superstructure with the supports. In the arch section, the decks will be assembled on either side of the arch. The two halves of the superstructure will be tight sidewise to the arch with cables without an additional cross-girder, so that the arch will rise between the carriageways without visible disturbances. Large and strong but looks light To reinforce the impression of lightness, the superstructure narrows “aslant” towards the outer edge. The wide intermediate space between the decks lets through sun, light and precipitation and makes the bridge less dominant from the underside. Slightly curved to the west Each deck will have its own connection to the ground and the abutments will act as the transition between the bridge and the ground. The decks on the southern side are about 360 metres. On the northern side, their length varies, 68 metres and 75 metres, and the abutment is split. The arch section of the superstructure is 188 m. The road and the bridge on the Swedish side curve, so motorists from the south will have a wonderful view of the entire bridge. Inspection points Interior lighting and the opportunity to walk along the whole of the bridge beam and transverse bulkheads will make inspections easy in the future. Correct relative humidity simplifies maintenance The interior will not be painted. A dehumidifying system will keep the relative humidity at a level that prevents corrosion. Substructure made of reinforced concrete The intermediate supports are simple, rectangular concrete columns. As a result of the ground conditions, their width and height vary, but their dimensions increase towards the base. The abutments take over the outer shape of the superstructure to continue its slender impression. The abutments and intermediate supports will be equipped with doors, interior stairs, lighting and so on to enable future inspections. Vägverket Region Väst SE 405 33 Göteborg, Sweden +46 31 63 50 00 www.vv.se Statens Vegvesen Region Øst Postboks 1010 Skurva, NO 2605 Lillehammer, Norway +47 69 24 35 00 www.vegvesen.no Norwegian Public Roads Administration Decks launched over supports in Sweden... Stepwise launch on southern side On the southern side, the decks will be launched; in other words, they will be pushed out in stages over the bridge supports. A launching station with auxiliary supports, hydraulic installations and so on will be build behind the abutment. This station is about 100 metres long so that three sections can be assembled and launched simultaneously to reduce the number of launching stages. The bridge piers will be reinforced with auxiliary steel structures which will brace the superstructure. Hydraulic jacks will push out the decks, 0.5 metres at a time. They will move easily on sliding bearings made of teflon on the auxiliary supports. At the very front, there is what is known as a launching nose. This is a 35-metre steel structure that compensates for the deflection of the deck. After each launching stage, the bridge will be fixed in place provisionally. The launching level is about 0.50 metres above the final superstructure level. When the entire structure is in its final position, it will be lowered and fixed in place. The decks will be launched to a point behind support 5. Launching is expected to be completed in the spring of 2004. ... and lifted into place by a crane in Norway The individual sections of the superstructure will be transported by truck to the assembly point on the Norwegian side. They will be placed on a fixed scaffold and welded together directly in their final position. This will require far more auxiliary supports to brace the decks during assembly than will be needed on the Swedish side. Accessibility in parts of the site is very poor and sites will therefore be constructed for the 500-tonne cranes that will be needed for handling and assembly of all segments. Temporary harbour at the site The superstructure will be constructed in Germany in sections measuring 24 x 5 metres and weighing around 80 tonnes. They will be transported by sea from Rostock to a provisional harbour in a small bay on the Swedish side. They will then be unloaded using a gigantic trailer, which will drive out on a barge to the ship via a gangway on pontoons. The barge measures 60 x 15 metres and will be anchored to the rocks and pontoons. Arch section hoisted into place in the arch Assembling the arch section The superstructure that will be suspended in the arch will be installed last. Five sections will be welded into one section, measuring 127 x 28 m, in Halden harbour. From there, the welded section will be transported by sea to the bridge site. Using temporary lifting devices inside the arch, this section will be hoisted up and connected to the cables in the arch. These cables follow the shape of the arch and the distance between them increases towards the attachment points in the cross-member. At supports 6 and 7, the beginning and end of the arch section, the last sections will be braced and attached to the arch using prestressing cables. The cable entries in the arch will be extra large in order to accommodate both the permanent bridge cables and the wires that will lift the arch section. When the assembly work is completed, these wires will be cut. When the wires are spun, a spinning agent (zinc paste) is added and, in combination with the profiled wires, this makes the structure completely watertight. So no extra sheath is needed around the cable. This is advantageous from an inspection angle and important in terms of aesthetics and the desire to keep the dimensions as small as possible. Detailed work Once the superstructure has been completed, work will begin on insulation, surfacing and final painting, together with the assembly of balustrades and transparent noise-reduction screens. FACTS SUPERSTRUCTURE Bridge cables with minimal dimensions The cables have a diameter of 90 mm and are of what is known as the locked coil type. The coil has a core made up of a number of 5 mm seamless steel wires. Around the core, there are several layers of wires with profiled cross-sections that lock into one another. Both types of wire are galvanised. Total length of bridge 704 m Steel 7,430 tonnes Cables in arch section 6x2 cables 14.5 m-27 m long Width of bridge, total 28.2 m Vertical clearance, approx. 55 m SPAN 247 m TOTAL LENGTH OF BRIDGE 704 M SUPPORT WALL ABUTMENT BRIDGE SUPPORTS SUPERSTRUCTURE CROSS-MEMBERS ACCESS BRIDGE SWEDEN, 363 m ABUTMENT ARCH SECTION, 188 m SUPPORT WALL ACCESS BRIDGE NORWAY, 128 M/142 M The superstructure consists of two separate decks which will be joined at the bridge supports and cables in the arch section. There is a space of eight metres between the bridges.