Status of ELENA Fast Deflectors A. Prost, TE/ABT/SE 17/11/2015 A. Prost 1 Fast deflectors Elena ring Assembly of 2 fast deflectors in 2015. 2 horizontal-left [1,2] 3 4 6 7 1 5 TL Assembly of 5 fast deflectors in 2016. 8 3 TL horizontal-right [3,4,6] 2 TL vertical-up [7.8] 2 9 Spares Assembly of 2 spare fast deflectors in 2016. 1 TL horizontal-right [5] 1 TL horizontal-left [9] 17/11/2015 A. Prost 2 Part procurements status 1 Item Parts Quantity Done 2016 1 Vacuum vessel 9 9 0 2 Electrode 20 20 0 3 Electrode support parts 18 18 0 4 Insulator 44 24 20 5 Feedthrough 20 20 spare 6 Support plate 9 3 6 2 3 4 5 17/11/2015 6 A. Prost 3 2015 2 Elena Fast Deflectors: • • • • • • • Leak test of vessel done, Pre-assembly and electrodes aligned ok after bake out, Electrical DC test done, NEG coating and activation done (vessel only), Final assembly week 47 - 48, Vacuum acceptance tests week 48 - 49, Elena installation week 50 - 51. 17/11/2015 A. Prost 4 2016 7 TL Fast Deflectors: • • • • • • • • Support plate assembly procurement, Insulator and spare feedtrough procurement, Vacuum firing, Assembly, Leak test, NEG coating (to be confirmed), Bake out, Acceptance tests. 17/11/2015 A. Prost 5 Resources Fast Deflector requested budget: • • 522 kCHF (99264) Committed up to now: • • 270 kCHF for material and services (TTE) Expected for 2016: • 56 kCHF 17/11/2015 A. Prost 6 Conclusions • • • • • • 2 fast deflectors assembled and acceptance tested by TE/VSC by end of 2015. Prototype assembly for HV pulse test (ABT/EC). Test HV DC done. Ready for installation in ELENA ring for the end of 2015. Ready for installation in TL 09/2016. Spare parts to be ordered at the end of project. 17/11/2015 A. Prost 7