Production Approval Procedures Manual Version 3.0: July 2011 CASADOC 79 Production Approval Procedures Manual This is an internal CASA policy manual. It contains guidance material intended to assist CASA officers and delegates in carrying out their regulatory responsibilities and may be made available to the public for information purposes only. Since this is an uncontrolled version of the manual which will not be updated by CASA, it should not be relied upon for any regulatory purpose. The current manual can be viewed at any time via CASA's website at "www.casa.gov.au". You should always refer to the applicable provisions of the Civil Aviation Act, Civil Aviation Regulations and the Civil Aviation Orders, rather than this manual, to ascertain the requirements of, and the obligations imposed by or under, the civil aviation legislation. Version 3.0: July 2011 Production Approval Procedures Manual Table of Contents Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Table of Contents Table of Contents ........................................................................................................................ i List of Effective Pages ............................................................................................................... v List of Abbreviations ................................................................................................................. vi Preface ....................................................................................................................................... vi 1. Introduction to Production Approval Procedures ..........................................................1-1 1.1 About this Manual ..................................................................................................1-1 1.1.1 Manual Sponsorship ....................................................................................1-1 1.1.2 Review of this Manual ..................................................................................1-1 1.1.3 Purpose and Scope of the Manual ...............................................................1-2 1.2 Regulatory Framework ...........................................................................................1-3 1.2.1 Background..................................................................................................1-3 1.2.2 Legislative Basis ..........................................................................................1-4 1.3 Responsibility for Production Approval ...............................................................1-6 1.3.1 Staff Responsibilities....................................................................................1-6 1.4 Production Approval Process ...............................................................................1-7 1.4.1 Production Approval Flowchart ....................................................................1-7 1.5 Processing Inquiries and Applications for Production Approvals ....................1-8 1.5.1 Advice Provided by CASA for General Enquiries .........................................1-8 1.5.2 Administrative Processing of an Application ................................................1-9 1.5.3 Technical Processing of an Application .....................................................1-10 1.6 Production Control Board (PCB).........................................................................1-12 1.6.1 Production Control Board Description ........................................................1-12 1.6.2 PCB Membership .......................................................................................1-12 1.6.3 PCB Member Responsibilities ...................................................................1-12 1.6.4 Conduct of the PCB ...................................................................................1-13 1.6.5 PCB Records .............................................................................................1-15 1.6.6 Administration of Production Approvals Granted .......................................1-16 2. Assessment and Issue of Approvals...............................................................................2-1 2.1 Approved Production Inspection System—Production under a TC Only .........2-1 2.1.1 Applicability – Production under Certificate Only .........................................2-1 i Production Approval Procedures Manual Table of Contents Approved by Executive Manager, Aviation Safety Standards 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 2.1.7 Version 3.0: July 2011 Responsibility...............................................................................................2-1 Procedure for PIS Issue ...............................................................................2-1 Production Inspection System (PIS) Board ..................................................2-4 TC Holder's/TC Licensee's Responsibility under CASR Part 21, Subpart F .....................................................................................................2-5 PIS Holder’s Facility Location ......................................................................2-7 Assessment of an Applicant’s Suppliers ......................................................2-7 2.2 Production Certificate (PC) Only ...........................................................................2-8 2.2.1 Applicability – Production Certificate ............................................................2-8 2.2.2 One-off PC ...................................................................................................2-9 2.2.3 Responsibility for PCs ..................................................................................2-9 2.2.4 Advising the Applicant................................................................................2-10 2.2.5 Preliminary Assessment Procedures .........................................................2-11 2.2.6 Testing Aircraft, Engines and Propellers ....................................................2-19 2.2.7 PC Holder's Location(s) .............................................................................2-19 2.2.8 Assessment of an Applicant’s Suppliers ....................................................2-19 2.2.9 Summary of Distribution of Production Certification Documents................2-20 2.2.10 Final Costing ..............................................................................................2-20 2.3 Australian Parts Manufacturer Approval Only ...................................................2-21 2.3.1 Applicability of Australian Parts Manufacturer Approval.............................2-21 2.3.2 Responsibility for Australian Parts Manufacturer Approval ........................2-21 2.3.3 Lodgement of an Application for an APMA ................................................2-22 2.3.4 CASA Engineering Assessment ................................................................2-22 2.3.5 FIS Assessment .........................................................................................2-28 2.3.6 APMA Approval .........................................................................................2-29 2.4 Australian Technical Standard Order Authorisation (ATSOA) Only ................2-32 2.4.1 Applicability – ATSOA ................................................................................2-32 2.4.2 Advising the Applicant................................................................................2-32 2.4.3 Lodgement of an Application .....................................................................2-33 2.4.4 ATSOA Issue Procedure............................................................................2-33 2.4.5 ATSOA Holder's Facility Location ..............................................................2-36 2.4.6 Approval of Materials and Processes.........................................................2-36 3. Assessment of an Applicant's Quality Systems for Manufacture ................................3-1 3.1 ii General Principles ..................................................................................................3-1 Production Approval Procedures Manual Table of Contents Approved by Executive Manager, Aviation Safety Standards 3.1.1 Version 3.0: July 2011 General Principles........................................................................................3-1 3.2 Assessment of an Applicant’s Suppliers .............................................................3-3 3.2.1 Assessment of an Applicant’s Suppliers ......................................................3-3 3.3 Quality System Assessment..................................................................................3-5 3.3.1 Stage 1 Quality System Assessment—Desk-top Review ............................3-5 3.3.2 Stage 2 Quality System Assessment – Quality System Evaluation ...........3-24 3.3.3 Stage 3 Quality System Assessment—Manufacturer's Corrective Action .........................................................................................................3-25 3.3.4 Manufacturer’s Service Documentation .....................................................3-25 3.3.5 Service Difficulty Reports ...........................................................................3-25 3.3.6 Reporting of Failures, Malfunctions and Defects during Manufacture ........3-26 3.3.7 Supplier Quality Control .............................................................................3-26 3.3.8 Engineering Drawings ................................................................................3-27 3.3.9 Use of CASA Form 1/Form 917 Authorised Release Certificate ................3-27 3.3.10 Use of CASA Form 1/Form 917 for Unapproved Parts ..............................3-28 3.3.11 Export Airworthiness Approvals .................................................................3-28 4. Inspections ........................................................................................................................4-1 4.1 Conformity Inspections .........................................................................................4-1 4.1.1 Introduction to Conformity Inspections .........................................................4-1 4.1.2 Conformity Inspections ................................................................................4-1 4.1.3 First Article Inspection..................................................................................4-4 4.1.4 Materials ......................................................................................................4-5 4.1.5 Processes Conformity ..................................................................................4-6 4.1.6 Automated Production Processes ................................................................4-7 4.1.7 Non-destructive Inspection (NDI) Method Evaluation ..................................4-8 4.1.8 Critical and Major Characteristics ................................................................4-8 4.1.9 Workmanship ...............................................................................................4-9 4.1.10 Adequacy of Drawings and Related Change Records .................................4-9 4.1.11 Adequacy of Inspection Records .................................................................4-9 4.1.12 Material Review Action ................................................................................4-9 4.1.13 Software.....................................................................................................4-10 4.1.14 Conformity Inspections of Test Articles ......................................................4-10 4.1.15 Structural Test Articles – Aircraft ...............................................................4-11 4.1.16 Flight Test Articles—Aircraft ......................................................................4-11 4.1.17 Endurance Test Articles—Engines and Propellers ....................................4-11 iii Production Approval Procedures Manual Table of Contents Approved by Executive Manager, Aviation Safety Standards 4.2 Version 3.0: July 2011 Final Inspection and Flight Test ..........................................................................4-13 4.2.1 Applicability — Final Inspection and Production Flight Test.......................4-13 4.2.2 Preliminary Ground Inspection ...................................................................4-13 4.2.3 Final Ground Inspection .............................................................................4-13 4.2.4 Flight Inspection .........................................................................................4-14 5. Sample Letters ..................................................................................................................5-1 5.1 Introduction.............................................................................................................5-1 5.2 Sample CASA APMA Approval Letter...................................................................5-2 5.3 Sample CASA APMA Supplement without Licensing Agreement......................5-4 5.3.1 Sample CASA APMA Supplement (Design Approval) Test and Computation ................................................................................................5-4 5.4 Sample CASA APMA Supplement with Licensing Agreement ...........................5-5 5.4.1 Sample CASA APMA Supplement (Design Approval) Identicality ...............5-5 5.5 Sample APMA Supplement ....................................................................................5-6 5.6 Sample CASA APMA Design Rejection Letter .....................................................5-7 5.7 Sample ATSO Authorisation..................................................................................5-8 5.8 Sample PIS Approval Letter ................................................................................5-10 6. Definitions .........................................................................................................................6-1 Revision History .................................................................................................................. RH-1 Forms Form 724 Statement of Conformity Form 849 Production Approval—Application Form 882 Conformity Inspection Record Form 883 Production Approval Assessment Control Document Form 1248 Request for Conformity Inspection (Note: The above forms are only those available to the industry/public via the CASA Website. Forms and templates used internally are available to CASA staff only, via CASAconnect, and are not listed here.) iv Production Approval Procedures Manual List of Effective Pages Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 List of Effective Pages No. of Pages Version Date of Issue All 3.0 07/2011 Cover and verso 2 3.0 07/2011 Table of Contents List of Effective Pages and Abbreviations and Preface 12 3.0 07/2011 1. Introduction to Production Approval Procedures 16 3.0 07/2011 2. Assessment and Issue of Approvals 38 3.0 07/2011 3. Assessments 28 3.0 07/2011 4. Inspections 14 3.0 07/2011 5. Sample Letters 12 3.0 07/2011 6. Definitions 4 3.0 07/2011 2 3.0 07/2011 Part All pages Revision History v Production Approval Procedures Manual List of Abbreviations Approved by Executive Manager, Aviation Safety Standards List of Abbreviations Abbreviations AC AD APMA ARC ARN ASCD ATSOA AWE CoA ESS FIS FITCOM IPC MI MRB NAA PAH PA PC PCB PIS PLR PO RMU SB SDR STC TC Preface vi Advisory Circular Airworthiness Directive Australian Parts Manufacturer Approval Authorised Release Certificate Aviation Reference Number Aviation Safety Compliance Division Australian Technical Standard Order Authorisation Airworthiness Engineer Certificate of Airworthiness Engineering Support Section Fabrication Inspection System Fabrication in the Course of Maintenance Illustrated Parts Catalogue Manufacturing Inspector Materials Review Board National Airworthiness Authority Production Approval Holder Production Approval Production Certificate Production Certification Board Production Inspection System Production Limitation Record Project Officer Record Management Unit Service Bulletin Service Difficulty Report Supplementary Type Certificate Type Certificate Version 3.0: July 2011 Production Approval Procedures Manual Preface Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Foreword As a Commonwealth government authority, CASA must ensure that its decision-making processes are effective, fair, timely, transparent, consistent, properly documented and otherwise in accordance with the requirements of the law. Most of the regulatory decisions CASA makes are such that conformity with authoritative policy and established procedures will be conducive to the achievement of these outcomes. From time to time, however, decision-makers will encounter situations in which the strict application of policy, in the making of a decision involving the exercise of discretion, would not be appropriate. Indeed, in some cases, the inflexible application of policy may itself be unlawful. This preface and the following Introduction, explains the way in which the policy and processes set out in this manual are to be used by all CASA’s personnel when making decisions in the performance of their functions, the exercise of their powers and the discharge of their duties. It also explains the processes to be followed if it appears that a departure from policy is necessary or appropriate. Mandatory Use of Policy and Procedure Manuals This manual is one of the set of manuals and other documents which comprise CASA’s authorised document set. The authorised document set contains the policy, processes and procedures with which CASA personnel are expected to comply when performing assigned tasks. All CASA personnel are required to have regard to the policies set out in this manual. Except as described in the Introduction, CASA decision-makers should not depart from these policies, processes and procedures. John F. McCormick Director of Aviation Safety vii Production Approval Procedures Manual Preface Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Introduction Regulatory Decision Making Where the legislation provides for one, and only one decision—the “correct” decision—is the only decision open to CASA. However, most of the decisions CASA makes involve the exercise of discretion. In such cases, there may well be more than one acceptable or correct decision. In these cases, the law requires that CASA makes the “preferable” decision, that is, the most appropriate decision, having regard to the overriding interests of safety and the obligation to be fair. In all such cases, CASA is bound to act in accordance with the applicable rules of administrative law. These rules govern how CASA arrives at the ‘preferable’ decision in any given case. Adherence to these rules is a requirement, not an option. Decisions and actions taken in contravention of these rules are unlawful, unenforceable, and in most cases invalid. CASA is legally accountable for the decisions it makes, and CASA decisionmakers are obliged to avoid the appearance, as much as the reality, of unlawful decisionmaking. Sound and lawful regulatory decision-making is generally governed by the 10 rules of administrative law summarised below. Adherence to these rules is essential to CASA’s obligations of accountability and good governance. 1. Natural Justice (Procedural Fairness) Hearing Rule. Persons affected by CASA’s decisions have a right to be heard. To be meaningful, the hearing rule normally requires that CASA provides persons with notice (usually in advance) that a particular decision is going to be taken, and the reasons for the decision CASA proposes to take. Without notice and a statement of reasons, there may be little point to providing a person with an opportunity to be heard. Rule Against Bias. Decision-makers should not have a personal or pecuniary interest in the outcome of their decisions. Neither may decision-makers prejudge (or pre-determine) matters in respect of which they are called upon to make a decision. 2. A decision-maker must not act for improper purposes. Even if the purposes for which a particular decision are lawful, the decision may only be taken for the purposes specifically authorised by the law under which the decision has been taken. 3. A decision-maker must not take any irrelevant considerations into account in coming to a decision. 4. A decision-maker must take all relevant considerations into account in coming to a decision. viii Production Approval Procedures Manual Preface Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Note: Applicable Policy is Always a Relevant Consideration. 5. A decision-maker must act on the basis of evidence, not mere supposition or speculation. 6. A decision-maker must not formulate requirements in vague or uncertain terms. 7. A decision-maker must not inflexibly apply policy (although departures from policy will normally need to be justified). 8. A decision-maker must not act under dictation (although this does not preclude adherence to formal directions, compliance with lawful conditions in relation to the process by which a decision is taken or the obligation to consult in the process of considering a decision). 9. A decision-maker must decide the matter within a reasonable time. 10. A decision maker must not act in a way that is manifestly unreasonable. A decision must not be so unreasonable that no reasonable person would make such a decision. Note: The meaning and application of these principles, and related considerations of administrative law, are covered more fully in the induction and orientation training undertaken by all CASA employees. Any questions in relation to these matters should be referred to the Legal Services Division. Departure from Authorised Policy Adherence to CASA’s authorised policies will almost always produce an appropriate decision. As said, however, from time to time there will be circumstances in which the strict application of policy may not result in the “preferable” decision. In these cases it may be appropriate (and possibly necessary) to depart from otherwise applicable policy. Any departure from policy must be justified in order to ensure that it: Is genuinely necessary in the interests of fairness Does not inappropriately compromise the need for consistent decision-making; and, of course Is not in conflict with the interests of safety. Without fettering a decision-maker’s discretion, it is therefore expected that appropriate consultation will occur before a decision is made that is not the product of the policies and processes set out in this manual. The prescribed consultation process is described below. ix Production Approval Procedures Manual Preface Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Consultation Process Decision-Maker’s Responsibilities When a decision-maker believes there is a need to depart from policy he or she is expected to consult with his or her direct supervisor. This process should be initiated in writing: Setting out the pertinent facts and circumstances Identifying the provisions of the policy normally applicable Stating why the application of that policy would not result in the making of the “preferable” decision in the circumstances to hand Specifying the approach the decision-maker believes is more likely to result in a “preferable” decision. Supervisor’s Responsibilities In considering a consultative referral, the decision-maker’s supervisor should: Advise the decision-maker as to whether his or her assessment of the relevant considerations appears to be complete and correct If, in the opinion of the supervisor, the circumstances do not warrant a departure from policy, provide the decision-maker with written advice and guidance as to how the decision might more properly be approached within the current policy framework Note: Reliance on relevant precedent is a sound basis on which to ground such an opinion. It may also be helpful to seek advice from peers, superiors and/or CASA’s Legal Services Division. If, in the opinion of the supervisor, a departure from policy is warranted, the supervisor should ensure the policy sponsor (normally the relevant Executive Manager) is advised of: i. The intention to depart from the otherwise applicable policy ii. The alternative approach the decision-maker will be taking to the matter. The supervisor should ensure that a full written record of these actions is made and maintained. x Production Approval Procedures Manual Preface Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Note: In no case may the terms of decision be dictated to a delegate authorised to exercise discretionary decision-making powers. If a decision-maker’s supervisor or the policy sponsor is not satisfied that the decision the decision-maker intends to make is the correct or preferable decision in all the circumstances, responsibility for that decision should be assumed by, or assigned to, another authorised delegate in accordance with appropriate processes and procedures. Policy Sponsor’s Responsibilities If the policy sponsor concurs in the proposed departure from policy, he or she should ensure the decision-maker is advised accordingly as soon as possible. If the policy sponsor does not believe the proposed departure from policy is warranted, he or she should: Advise the supervisor accordingly Assume responsibility for the decision Ensure that the decision-maker and any person affected by the decision (for which the policy sponsor has assumed responsibility) is advised accordingly Make the decision in a manner consistent with the applicable policy. The policy sponsor should ensure that a full written record of these actions is made and maintained. Nothing in these processes should be interpreted or applied so as to dictate the terms of the decision to be made by a decision-maker authorised to make discretionary decisions under the civil aviation legislation, or to delay unreasonably the making of such decisions. Revisions to Policies and Manuals As a result of experience in applying policies and procedures, users will form views as to accuracy, relevance and applicability of the content. CASA personnel are required to provide recommendations for revisions to policies and processes in this or any other manual should they become aware of shortcomings. In this way the policies and manuals will be continually improved and remain relevant to the tasks being undertaken. xi Production Approval Procedures Manual Preface Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Each policy and manual has a sponsor and recommendations for amendment are to be forwarded to the relevant individual for consideration. The revision process can be accessed via the link: http://casaconnect/manuals/doc_control/process.htm xii Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.1 About this Manual Approved by Executive Manager, Aviation Safety Standards 1. Version 3.0: July 2011 Introduction to Production Approval Procedures 1.1 About this Manual 1.1.1 Manual Sponsorship The Executive Sponsor of this manual is the Executive Manager Operations. The Technical Sponsor of this manual is the Team Leader Manufacturing (TLM). The Technical Sponsor is responsible for the integrity of the content of this manual and is the first approval authority for amendments to this Manual. The Executive Sponsor gives final approval of this manual and all its amendments. 1.1.2 Review of this Manual Production Approval Manual Review Team This Production Approval Procedures Manual will be reviewed as required and within at least 12 months of issue or review. The Production Approval Manual Review Team will comprise: ● Technical Sponsor/Chair – TLM Section ● Two Manufacturing Specialists ● Technical Support Officer. Recommending Changes to the Manual If any information in this manual needs to be amended or new information added, notify the technical sponsor. Use Form 476 Manual Amendment Request, when making suggestions, including additional sheets if necessary. Definitions See Section 6. Definitions 1-1 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.1 About this Manual Approved by Executive Manager, Aviation Safety Standards 1.1.3 Version 3.0: July 2011 Purpose and Scope of the Manual Purpose The purpose of this manual is to provide CASA staff with procedures for assessing applications for Production Approvals (PAs) under CASR Part 21 and for issuing those CASA approvals. CASR Part 21 Scope CASR Part 21 This manual applies to PAs under Part 21 including but not limited to the following: CASR Part 21. Subparts F, G, K, O, and Q ● Production under Type Certificate only (TC) (CASR Part 21 Subpart F) ● Production Certificate (PC) (CASR Part 21 Subpart G) ● Australian Parts Manufacturer Approval (APMA) (CASR Part 21 Subpart K) ● CASR Part 21.305 (A) ● Australian Technical Standard Order Authorisation (ATSOA) (CASR Part 21 Subpart O) Other approvals under CASR 21 Subpart K ■ 1-2 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.2 Regulatory Framework Approved by Executive Manager, Aviation Safety Standards 1.2 Regulatory Framework 1.2.1 Background Version 3.0: July 2011 An outline of the background to this manual is as follows: CASR Part 21 CAR 30 a. Version 1 of this manual was introduced in May 2000 to address manufacture under CASR Part 21 and for transition from previous approvals issued under regulation 30 of CAR 1988. ● ● CASR Part 21 CASR Part 21 provisions were developed with the intent of reflecting the corresponding provisions in US FAR Part 21, but only where these were appropriate to Australian requirements. The result has been regulations that harmonise with international best practice while at the same time meeting Australia's obligations as a contracting state to ICAO. b. Version 2.0 was introduced to clarify procedures in the light of experience gained since the introduction of CASR, (1998) Part 21. c. Version 2.1 was introduced in March 2010 to reflect CASA organisational changes, primarily the transfer of the Manufacturing Branch from the Standards Development and Future Technologies Branch to the Operations Division. Version 2.1 also introduced the concept of a Technical Sponsor, responsible for the integrity of the technical content of this manual. d. Version 3.0 is introduced to correct deficiencies in the manual. 1-3 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.2 Regulatory Framework Approved by Executive Manager, Aviation Safety Standards 1.2.2 Version 3.0: July 2011 Legislative Basis Civil Aviation Act 1988 Section 11 CAA 1988 CAR 1988 CASR 1998 Part 21 Australia, as a contracting state to ICAO, has an obligation to ensure that functions carried out in Australia are performed in accordance with international agreements. The Civil Aviation Act 1988 section 11 refers. CAR 1988 and CASR Part 21 are consistent with the provisions of the Act. Civil Aviation Act 1988 Section 31 and Civil Aviation Safety Regulations 1998 Part 201.4 CAA 31 Section 31 of the Act makes all decisions to refuse to grant, vary, suspend or cancel an approval appealable to the AAT. CASR 201.4 CASR Part 201.4 makes appealable any condition imposed on an approval, authorisation, authority, certificate or permit. Civil Aviation Act 1988 Section 97 If a fee is prescribed for the grant of an approval then the approval need not be granted until the fee is paid (section 97 of the Act). CAA 97 Civil Aviation Safety Regulations Part 1 CASR Part 1 Part 1 describes legislative links to other aviation legislation and practices. Civil Aviation Safety Regulations Part 21 Subpart A Subpart A defines the applicability of CASR Part 21, including provisions dealing with falsification of applications, suspension and cancellation actions and reporting of failures by production approval holders. CASR Part 21 Civil Aviation Safety Regulations Part 21 Subpart F CASR Part 21 Subpart F Subpart F prescribes the requirements for approval of production under a TC only. It contains the requirements for establishing a Production Inspection System (PIS) and a Materials Review Board (MRB). This approval does not provide the same degree of flexibility as a PC. Civil Aviation Safety Regulations Part 21 Subpart G CASR Part 21 Subpart G Subpart G prescribes the requirements for issue of a PC and the rules governing the production of aircraft, aircraft engines and propellers and certain parts. This approval requires the establishment of a PIS and a MRB.. 1-4 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.2 Regulatory Framework Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Civil Aviation Safety Regulations Part 21 Subpart K CASR Part 21. Subpart K, Subpart K prescribes the requirements for issue of an APMA. This approval requires the establishment of a Fabrication Inspection System (FIS). This approval is both a design and installation approval. Civil Aviation Safety Regulations Part 21 Subpart O CASR Part 21. Subpart O. Subpart O prescribes the requirements for issue of an ATSOA. This approval is both a design and production approval. Civil Aviation Safety Regulations Part 21 Subpart Q CASR Part 21. Subpart Q Subpart Q prescribes the requirements for part identification and marking. Civil Aviation Safety Regulations Part 201 CASR Part 201 Part 201 prescribes the appointment of Authorised Persons (AP). ■ 1-5 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.3 Responsibility for Production Approval Approved by Executive Manager, Aviation Safety Standards 1.3 Responsibility for Production Approval 1.3.1 Staff Responsibilities Version 3.0: July 2011 Executive Sponsor The Executive Sponsor has responsibility for the overall approval of this manual. Technical Sponsor The Technical Sponsor assumes technical responsibility for this manual and manages its development through to completion, or its amendment as and when required, in accordance with the Manual of Controlled Documents. Managers Managers ensure that CASA staff correctly implements the procedures in this manual. CASA Officers CASA officers are to: ● ● Adhere to the procedures in this manual Bring to the notice of the Technical Sponsor the need for amendments to the manual, in accordance with the instructions for Recommending Changes to the Manual (Form 476 Manual Amendment Request). CASA Project Officer The TLM Section appoints a PO for a particular production approval, who ensures that the production approval application is assessed effectively and that all aspects of the approval are complete and in accordance with this manual. When satisfied, the PO recommends the issue of the approval. ■ 1-6 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.4 Production Approval Process Approved by Executive Manager, Aviation Safety Standards 1.4 Production Approval Process 1.4.1 Production Approval Flowchart Version 3.0: July 2011 Initial advice to applicant PACS Receive application Set-up project file Acknowledge Application Notifies Manufacturing Conduct onsite evaluation/ audit of QMS TSO Reviews application for completeness Does applicant follow approved procedures? Assigned Project Officer No Notify applicant to take corrective action Yes Is this the facility's first approval? Is PC board involved? No No Yes Convene PC board Yes Establish PC board if the application is for a PC Yes Is there a major change in the facility's procedures? No Has applicant met all requirements? No Notify applicant to take corrective action Yes Review data for compliance Issue the approval Do procedures comply? No Notify applicant to revise procedures Complete files and enter approval details on CASA database Yes ■ 1-7 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.5 Processing Inquiries and Applications for Production Approvals Approved by Executive Manager, Aviation Safety Standards 1.5 Processing Inquiries and Applications for Production Approvals 1.5.1 Advice Provided by CASA for General Enquiries AC 21.14, 21.16, 21.20, 21.27, 21.601 Version 3.0: July 2011 When people make enquiries about Production Approvals, provide them with relevant advice and request that they read the appropriate Advisory Circular (AC) for the particular approval, including: ● AC 21.14 Production Certificates ● AC 21.16 Australian Parts Manufacturer Approval ● AC 21.20 Production Under Type Certificate Only ● AC 21.27 Manufacturing Approval — Overview. ● AC 21.601 ATSOA Should the person wish to proceed, advice that a formal written application to CASA is required before the application can be processed. Enquirers must be advised that cost recovery procedures are applicable. Regardless of which production approval is sought, it should be stressed to the applicant that it is the applicant’s responsibility to demonstrate conforming products and parts. It is a CASA responsibility to find that conforming parts have been demonstrated as a basis for issue of the approval sought. A non-conformed proof-of-concept product is not a basis for CASA assessment and subsequent approval. The CASA officer should advise the applicant of the advantages of obtaining a PC. The advantages of being a PC holder, compared to production under a TC only, include the following: ● ● ● CASR 21.325 ● No requirement to submit a Statement of Conformity (Form 724) to CASA, for each conformed product Reduced CASA involvement, relative to conformity inspections An Authorised Person within the approved Production Inspection System (PIS) will be able to issue airworthiness certificates and approvals for completed products without reliance on CASA inspections The issue of export approvals for small aircraft without assembly or flight test (CASR 21.325). ■ 1-8 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.5 Processing Inquiries and Applications for Production Approvals Approved by Executive Manager, Aviation Safety Standards 1.5.2 Version 3.0: July 2011 Administrative Processing of an Application Administrative Procedures by Permission Application Centres (PAC) 1. All production approval applications are received by PAC on Form 849 Production Approval Application. Once all relevant data has been received, PAC will send a draft cost estimate to TLM for completion. 2. Once the applicant has paid the required fees, PAC will create a task which is assigned to the TLM. Once the task is accepted by TLM, PAC manages the application as required, in accordance with their procedures. 3. When the task is completed, TLM or the appointed PO will advise PAC of completion and will provide an adjusted costing. 4. PAC will advise the applicant of the actual cost and recover additional cost or provide a reimbursement to the applicant. ■ 1-9 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.5 Processing Inquiries and Applications for Production Approvals Approved by Executive Manager, Aviation Safety Standards 1.5.3 Version 3.0: July 2011 Technical Processing of an Application Team Leader Manufacturing (TLM) The TLM Section monitors the progress of the application. If it becomes evident that the application will not be processed within the normal timeframe, he will ensure that the applicant is notified accordingly. The TLM appoints a PO for each task and updates the work flow management system to reflect the appointed PO. The TLM issues approvals that are not within the delegation of the Manufacturing Inspectors (MI). The TLM is the design approval authority for design submitted in support of production approval except for design for Type Certificate and Supplementary Type Certificate. Project Officer (PO) The PO: 1. Completes the required completion dates in the work flow management system and accepts the task for Manufacturing Section 2. Checks that Form 849 Production Approval Application and covering letter are complete and on the Document Management System 3. Checks the regulatory AIRS database for any current enforcement actions pending or proceeding in relation to the applicant or whether any exclusion periods have been imposed. Refer any of these to the Office of Legal Services for advice, if needed 4. If a Production Control Board (PCB) is required, pre-PCB (CASA) and pre-PCB (applicant) meetings may now be convened (refer to 1.6.1 Production Control Board Description), to prepare both CASA officers involved in the assessment and the applicant for the requirements of the assessment. (A PCB is required for Class 1 items, and may be required for other items, depending upon the complexity and investigations required.) The activities are to be completed in accordance with the Production Approval Flowchart at 1.4.1. 5. Plans and conducts Pre- and Post-PCB meetings 6. If the application does not require the establishment of a PCB, proceed as for the preliminary assessment only 7. Raises Form 883 Production Approval Assessment Control Document and place it on the appropriate Document Management System. The Form 883 is to be signed by the PO and an approval authority, to be two different persons. 1-10 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.5 Processing Inquiries and Applications for Production Approvals Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Technical Support Officer (TSO) 1. Upon notification of a new task from PAC, the TSO will review the application and the data package for completeness using the Manufacturing checklist. 2. Where additional data is required, the TSO will liaise with PAC to contact the applicant for the provision of such data. 3. When all data is available the TSO is to advise TLM and assist TLM or the PO with the development of the cost estimate. 4. Upon task completion, the TSO assists TLM or the PO with the final cost assessment and provide such to PAC. 5. The TSO acts as the PCB secretariat for document management and distribution. 6. Once TLM or the POs have issued the finalised permissions, the TSO enters the permissions and their relevant data in the regulatory database. 7. The TSO closes the task in Workflow Management System (WMS) and the document management system in conjunction with the PO’s. ■ 1-11 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.6 Production Control Board (PCB) Approved by Executive Manager, Aviation Safety Standards 1.6 1.6.1 Version 3.0: July 2011 Production Control Board (PCB) Production Control Board Description A PCB is a CASA panel established for the purpose of facilitating the assessment of a production approval. PCBs should be convened for initial production approvals covered by production under TC only or PC, or when entire facilities have been relocated or are to be added to the production approval. PCBs should not be convened for the addition of new models to the production approval or for relocation of a portion of a facility, unless significant changes in production technology or processes apply. In these instances, follow the procedures in Section 2. Assessment and Issue of Approvals. 1.6.2 PCB Membership The PCB will be chaired by TLM and will include the PO, at least one member from Certification and any other nominated specialists. These members will assist in evaluating the applicant's production, engineering, flight test procedures, and other related functions. The PO may be, or act as, the Chairperson of the PCB and will coordinate activity through the TLM. 1.6.3 PCB Member Responsibilities PCB Chairperson The PCB chairperson is responsible for: ● ● ● ● ● ● Assigning board members, as deemed appropriate for the particular product, and notifying members of the pending PCB schedule in sufficient time to permit adequate planning and preparation Notifying the applicant of the PCB schedule Selecting a representative number of the applicant's supplier facilities for evaluation to determine whether or not the applicant's quality system provides for satisfactory supplier control Conducting pre/post-PCB meetings with CASA officers and/or the applicant Reviewing and analysing the PCB findings and ensuring that appropriate corrective actions have been or will be taken by the applicant Completing, signing, and distributing the PCB minutes. 1-12 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.6 Production Control Board (PCB) Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Project Officer The PO is responsible, using administrative assistance as appropriate, for: ● Establishing schedules ● Making arrangements for meeting rooms ● Obtaining sufficient copies of quality system data ● Making all other arrangements necessary for convening and conducting the PCB in the most expeditious manner ● Ensuring that all agreed-upon corrective actions have been taken by the applicant ● Preparing the minutes of the PCB. Specialists Members Specialist members will be assigned responsibilities to: ● CASR 21.127, 21.128, 21.129, 21.143 (1)(c) ● ● ● 1.6.4 Assess the design data supplied against CASR Part 21 requirements and to provide a recommendation to the TLM for design data approval Evaluate and approve as relevant the applicant's production engine/propeller test procedures, as required by CASR 21.143(1)(c), 21.127, 21.128 or 21.129 Evaluate and approve the applicant's flight test procedures and check-off lists as required by CASR 21.143(1)(c) Report and recommend to the PO (rather than making direct communication with the applicant). Conduct of the PCB A PCB is generally conducted as follows: ● Initial CASA planning meeting ● Pre-PCB meeting ● PCB assessment of applications ● PCB meetings ● Final Phase of PCB ● PCB Conclusion. 1-13 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.6 Production Control Board (PCB) Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Initial CASA Planning Meeting A meeting of CASA personnel is held to plan the preliminary assessment, Manufacturing Section recommendations, and related correspondence between CASA and the applicant. This meeting is also used to plan the PCB schedule for subsequent meetings; and establish agenda items for the pre-PCB meetings. Pre PCB Meeting A Pre-PCB meeting may be held with the applicant's representatives upon receipt of the production approval application. This meeting should include the Chairperson and any other specialist as necessary. The purpose of this meeting is to advise the applicant of the purpose of the CASA PCB and of CASA's evaluation plans. CASR 21.125, 21.135, 21.137 Inform the applicant that the PCB is a fact-finding body convened to determine whether or not the applicant is in compliance with CASR 21.125 or 21.135 and, that in making this determination, the PCB will thoroughly evaluate the applicant’s quality system, data, organisation and production facilities. It is at this point that the Chairperson determines whether or not the location of the applicant’s facilities poses an undue burden on CASA, as specified in CASR 21.137. PCB Assessment of Applications Following the pre-PCB meeting with the applicant, the PCB evaluates the applicant's quality system data and performs an on-site evaluation of the applicant's quality system, organisation, production facility and suppliers, as appropriate. PCB Meetings PCB meetings are conducted as needed to discuss and evaluate each unsatisfactory condition and related recommendation submitted by each member. All unsatisfactory conditions are recorded as findings on Form 883 Production Approval Assessment Control Document. A final meeting, attended by all PCB members and representatives of the applicant, is held to advise the applicant of the PCB findings. Each unsatisfactory condition and recommendation should be presented and briefly discussed. Corrective Action In those instances where a product is being produced under a TC, the PCB must request that the applicant commence immediate corrective action on those items that directly involve the product and related quality practices. A reasonable time may be allowed for correcting deficiencies in the quality system data. However, the applicant must be advised that the PCB cannot recommend that an approval be issued until all applicable regulations are complied with and all corrective actions addressed to the satisfaction of the TLM. 1-14 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.6 Production Control Board (PCB) Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Formal Confirmation The applicant must also be advised that they will receive an official letter confirming the verbal presentation of the list of unsatisfactory conditions and recommendations. This formal notification should be prepared and signed by the PCB Chairperson, within ten working days of the final meeting with the manufacturer. Violations CASR Part 21 Subpart F If the applicant is manufacturing a product under a TC only, and any of the unsatisfactory conditions are determined to be violations of CASR Part 21, Subpart F, appropriate enforcement actions should be initiated by the Manufacturing Section. Final Phase of the PCB The final phase of a PCB is the evaluation by the Manufacturing Section of the corrective action taken by the applicant. The results of any re-inspection should be reported to the Chairperson of the PCB and, if satisfied, the Chairperson will document their approval on Form 883 Production Approval Assessment Control Document and then submit the Form 883 to the TLM for their sign off on Form 883 Production Approval Assessment Control Document. PCB Conclusion CASR 21.123, 21.135 1.6.5 Upon guidance from the TLM, the Permissions Application Centre will formally advise the applicant in writing, as soon as practicable, that based on a demonstrated compliance with CASR 21.123 or 21.135, an approval will be issued. Conversely, if compliance has not been demonstrated, the applicant will be formally advised that an approval will not be issued, and a statement of reasons must be advised to the applicant. PCB Records The PO shall prepare the PCB minutes for the signature of the Chairperson. The minutes should contain a concise record of the entire PCB proceedings, including the names and titles of all participants. All correspondence and forms relating to the PCB, including letters to the applicant, the applicant’s replies, etc, are considered to be part of the minutes and should be attached as appendices. Once accepted by the Chairman, the PCB minutes should be distributed as follows: ● Original to the applicant’s document management system file ● One copy to the applicant The TSO will advise all members of the PCB as correspondence is generated and stored in the document management system. ■ 1-15 Production Approval Procedures Manual 1. Introduction to Production Approval Procedures 1.6 Production Control Board (PCB) Approved by Executive Manager, Aviation Safety Standards 1.6.6 Version 3.0: July 2011 Administration of Production Approvals Granted Approval Numbers All PA numbers incorporate the Aviation Reference Number (ARN) of the organisation. PC Numbers A PC’s number consists of the letters PC- followed by the ARN of the applicant—for example, PC-123456. It is unlikely that there would be more than one PC issued to an organisation because the Production Limitation Record (PLR) can list multiple activities. An approval under CASR 21.133(2B) uses the letters PC- followed by the ARN of the applicant followed by -1, for example PC-123456-1. APMA Numbers Only one APMA is likely to be issued to an organisation. An APMA number consists of the letters APMA- followed by the ARN of the applicant—for example, APMA-123456. The specific aeronautical products and parts are listed on the supplement; an additional APMA supplement is issued to add new products. The first and any additional supplements are numbered consecutively from 001. ATSOA Identification An ATSOA is expected to be a discrete issue, and an organisation is likely to have multiple ATSOA approvals. The Letter of Approval identifies the specific item(s). The applicant’s ARN will be quoted in the letter Regulatory System Database The TSO is responsible to update the Regulatory System Database as new permissions or variations are issued as a project closure activity. ■ 1-16 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.1 Approved Production Inspection System—Production under a TC Only Approved by Executive Manager, Aviation Safety Standards 2. Version 3.0: July 2011 Assessment and Issue of Approvals 2.1 Approved Production Inspection System—Production under a TC Only 2.1.1 CASR Part 21, Subpart F Applicability – Production under Certificate Only This section provides guidance on the production of an aircraft, aircraft engine or propeller under a TC only, prior to obtaining a PC For production under a TC only, the manufacturer must comply with CASR Part 21, Subpart F, including establishing and maintaining an approved PIS. CASR 21.125 AC 21.20, 21.27 Additional guidance is contained in AC 21.20 and AC 21.27. Applicants should be aware that CASA considers that a PIS supports only an interim production stage, and they should be encouraged to achieve a PC for their activities. Additionally, as CASA provides the resources on a cost recovery basis to determine whether the product and parts manufactured by the applicant conform to the type design, and are in a condition for safe operation until a PIS is established, the cost of production under a TC only could be significant. The regulations require the PIS holder to have process specifications, materials review records, test procedures and flight check forms that are acceptable to CASA and the applicant should have started developing these data concurrently with other data relevant to type certification requirements. ■ 2.1.2 Responsibility Subsequent to the date of issue of the TC and prior to the approval of the of the production inspection system CASA has full responsibility for determining whether the product and parts thereof conform to the type design and are in a condition for safe operation. The TLM is responsible for managing all aspects of progression to a PIS and for the relevant surveillance activities before and after the PIS is established. ■ 2.1.3 Procedure for PIS Issue Preliminary Assessment Procedures CASR 21.123 An applicant for a PIS must show compliance with CASR 21.123. This preliminary assessment consists of an evaluation of the applicant’s: 2-1 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.1 Approved Production Inspection System—Production under a TC Only Approved by Executive Manager, Aviation Safety Standards ● ● Version 3.0: July 2011 Production Inspection System Facilities, equipment, processes, personnel, control of suppliers, stores, etc, to ensure that they are adequate for the purpose. The assessment of the PIS will require a number of visits to the applicant’s facilities and suppliers, as necessary; to evaluate and confirm that the procedures provide control for the conformity of detail parts, sub-assemblies and completed products. In other words, the PO must evaluate the adequacy of the quality system by personally observing the control of each stage of production, and all supporting functions such as document control. In the preliminary assessment, the appropriate sections of this manual are used to assess: ● Suppliers ● Supplier control ● All quality systems. Project Officer (PO) The PO: 1. Makes arrangements to conduct the preliminary assessment only after the applicant has accepted the CASA estimate of costs and has the capability to comply with the regulatory requirements 2. Assesses the applicant's quality system assisted by specialists, as required 3. Carries out the assessment concurrently with conformity inspections of first articles prior to approving the PIS. That is, assess the applicant’s PIS for adequacy on a progressive basis 4. As parts of the system are found to meet the regulatory requirements: ❍ Maintains a record of those portions of the system considered satisfactory on Form 883 Production Approval Assessment Control Document ❍ Reduces conformity inspections to spot-checks for articles covered by those parts of the system found satisfactory 2-2 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.1 Approved Production Inspection System—Production under a TC Only Approved by Executive Manager, Aviation Safety Standards ❍ Version 3.0: July 2011 Places increasing emphasis on securing corrective actions on the parts of the system where procedural discrepancies or nonconformities are found, or where the system is found to be inadequate, as recorded on Form 883 Production Approval Assessment Control Document. Assessing the Applicant's Progress The PO: 1. Periodically assesses the applicant's progress in obtaining approval of the PIS. CASR 21.123(1)(c) 2. If it appears that the applicant may not be eligible for approval of the PIS by the deadline date (six-month period specified in CASR 21.123(1)(c)), advises the applicant in writing of all known deficiencies. Also, cautions the applicant that after the deadline date, CASA will not issue any airworthiness certificates or any other approvals unless an extension of the time period is authorised by the delegate. Keeps the delegate informed if such a situation becomes inevitable. Extension of six-month period: An application for extension of the six-month period, must take into consideration the impact the extension would have on CASA staff, resources and safety. CASR 21.123(3) CASR 21.123(3) allows CASA to grant an extension when there are unusual or extenuating circumstances which would preclude the approval of the PIS within the six-month limitation. When an extension is to be granted, forwards requests for extension, together with a detailed summary of the inspections and assessment results during the six-month period, to the delegate. Failure to Establish a PIS: When an applicant fails to establish a PIS by the end of the six-month period (except as otherwise extended as above), CASA will no longer make conformity determinations and will discontinue all inspections. CASA will not issue airworthiness certifications and approvals. Provided that manpower resources allow, CASA may continue to counsel and advise the applicant to the extent necessary to obtain a PIS as soon as practicable. Notifying the Applicant On completion of the preliminary audit, the PO is to formally notify the applicant of any corrective actions needed. In so doing, the PO is to advise the applicant that these items only represent CASA’s preliminary findings and that additional requests for corrective actions can be anticipated as a result of subsequent findings by the PIS Board, future routine audits and surveillance activities. ■ 2-3 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.1 Approved Production Inspection System—Production under a TC Only Approved by Executive Manager, Aviation Safety Standards 2.1.4 Version 3.0: July 2011 Production Inspection System (PIS) Board A PIS Board is established under the same conditions as those detailed for the PCB. See Section 1.6.1 Production Control Board (PCB). Conduct of the PIS Board and Records of Its Findings The PIS Board is conducted in a manner similar to a PCB, including the use of a Chairperson. The PCB procedures in Section1.6.1 Production Control Board (PCB) should be followed as appropriate, by the PO. Also, the PIS Board findings should be documented in the same manner as the findings of a PCB, as applicable to the particular situation. Preparation and Delivery of the letter approving the PIS CASR Part 21 When the PIS Board has determined and documented that the manufacturer's complete PIS complies with CASR Part 21, the PO is to prepare a letter of approval for the signature of the delegate. (A sample letter is provided in section 5.9.). The letter is to be forwarded to Airworthiness And Engineering Branch (Certification Section) to accompany their TC approval. Note: When production under TC only is based on a licensing agreement for a specific period of time, the same period of time must be indicated on the PIS approval letter as a limitation to the approval. Revision of a PIS Approval Letter Subsequent to the issue of the original letter, the manufacturer may apply to add another type-certificated product or a new model to the manufacturer's PIS. The TLM must appoint a PO to evaluate any required changes to the PIS resulting from new technology change to the facilities and staff. Project Officer 1. If the change is considered to be significant, TLM may re-convene the PIS Board to make the determination, and process the application in accordance with this section. 2. If a PIS Board is not required, a PO may carry out an assessment, and draft the revised letter for the delegate. The draft letter is to refer to the original approval letter. 3. The PO will then issue the new letter, withdraw the obsolete letter and file all correspondence. ■ 2-4 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.1 Approved Production Inspection System—Production under a TC Only Approved by Executive Manager, Aviation Safety Standards 2.1.5 Version 3.0: July 2011 TC Holder's/TC Licensee's Responsibility under CASR Part 21, Subpart F CASR Part 21, Subpart F, 21.130. Manufacturers producing aircraft, aircraft engines or propellers under a TC Only (CASR Part 21, Subpart F) are required to submit to CASA a Statement of Conformity (Form 724) for each completed aircraft, aircraft engine or propeller. The Statement of Conformity is required before aircraft produced only under a TC can be issued with a Certificate of Airworthiness or, in the case of engines and propellers, before an Authorised Release Certificate (ARC) can be issued. The Statement of Conformity submitted by the manufacturer is a certification that the product conforms to its type design and is in a condition for safe operation. See Statement of Conformity (Form 724) required by CASR 21.130. CASR 21.125 Subsequent to the issue of a PIS, the TC holder/licensee is additionally responsible for maintaining the PIS in accordance with CASR 21.125 to ensure that each product conforms to the type design and is in a condition for safe operation. The manufacturer must also comply with any terms or conditions as prescribed in the PIS approval letter. CASR 21.003 A TC holder/licensee is responsible for reporting any failures, malfunctions, and defects as required by CASR 21.003. CASR 21.003 Note: The manufacturer must report to CASA serious occurrences as listed in CASR 21.003 (4) that have occurred. The manufacturer does not need to report to CASA things as listed in CASR 21.003 (4) that might occur unless the product is outside the manufacturer’s control. Normal manufacturing problems can be fixed and not reported to CASA if the product has not left the manufacturer’s control or can be readily retrieved. The manufacturer does not have to report to CASA on an occurrence that is of a kind listed in CASR 21.003 (5) (21.10 refers) i.e., improper maintenance or usage, or has already been reported. CASR Part 21, Subparts F and Q. Products manufactured under the provisions of CASR Part 21, Subpart F, must be marked in accordance with the requirements of CASR Part 21 Subpart Q. 2-5 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.1 Approved Production Inspection System—Production under a TC Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Testing (aircraft, engines, propellers) CASR Part 21, Subpart F, 21.127, 21.128, 21.129 Each person who produces a completed product (except rocket engines) under CASR Part 21, Subpart F, must flight test and/or functional test that product. ● ● Aircraft: Each aircraft produced under CASR Part 21, Subpart F, both prior to and subsequent to the issue of a PIS, must be flight-tested in accordance with CASR 21.127. Engines and Propellers: Each engine or propeller produced under CASR Part 21, Subpart F, both prior to and subsequent to the issue of a PIS, must be subjected to an acceptable test run or functional test in accordance with the requirements of regulations 21.128 or 21.129, as appropriate. ■ 2-6 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.1 Approved Production Inspection System—Production under a TC Only Approved by Executive Manager, Aviation Safety Standards 2.1.6 Version 3.0: July 2011 PIS Holder’s Facility Location A PIS holder's manufacturing complex may consist of a principal facility and associate facilities using the same quality system approved by CASA for the particular type certificated product(s). The PIS is only applicable to the principal manufacturing facility that controls the quality of the product(s) for which the approval was granted. The principal facility and associate facility addresses are listed on the PIS. A post office box address is not acceptable for a facility because the actual location must be identified. However, post office boxes may be used as postal addresses for correspondence. When a PIS holder moves the principal manufacturing facility to a new location the PIS is no longer effective. When the PIS holder moves an associate facility or adds a new plant, CASA Manufacturing must be notified of the changes. Before the new plant or moved facility is approved for production it must be subjected to a satisfactory audit or be assessed by a PIS Board if the change is significant. The PIS must be amended to reflect this change. ■ 2.1.7 Assessment of an Applicant’s Suppliers See 3.2 Assessment of an Applicant’s Suppliers for supplier evaluation procedures. ■ 2-7 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards 2.2 2.2.1 Version 3.0: July 2011 Production Certificate (PC) Only Applicability – Production Certificate CASR Part 21, Subpart G This section provides guidance on the assessment and issue of a PC when an applicant complies with CASR Part 21 Subpart G. AC 21.14 Additional guidance is contained in AC 21.14. CASR 21.135, The following persons may be issued with a PC when CASA finds, after examination of supporting data, inspection of the organisation and production facilities, that the applicant has complied with CASR 21.135: 21.021 21.029 ● The holder/licensee of a CASR 21.021/21.029 TC ● The holder/licensee of a STC Note: STC holders who only intend to produce modification parts/kits should apply for an APMA. CASR 21.025, 21.031 ● The holder/licensee of a CASR 21.025 TC, when the TC issue was based on submission by the TC applicant and CASA approval of the type design data required by CASR 21.031 A PC may not be issued to: CASR 21.027, Part 21, Subpart C ● ● The holder of a TC issued under CASR 21.027, or CASR Part 21, Subpart C (provisional TC) An organisation whose manufacturing facilities are located outside Australian territory, unless it has been determined that such location(s) would place no undue burden on CASA. ■ 2-8 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards 2.2.2 Version 3.0: July 2011 One-off PC CASR 21.133 This procedure has been introduced to assist industry in obtaining aeronautical products, required as part of the maintenance of an aircraft, from other organisations qualified to fabricate those products. A PC for this purpose may be issued under CASR 21.133(2B). The approval is limited to the manufacture of Class II or Class III product on a “One Off” basis for supply to a maintenance organisation, engaged in the maintenance of an aircraft for installation in or on the aircraft or the owner of an aircraft or the operator of an aircraft for the installation in or on the aircraft, engine or propeller in the course of maintenance activities. CASR 21.133 A PC issued under CASR 21.133 (2B) can be issued in accordance with the procedures in this manual, with the following limitation entered on the PLR section: “Limited to the manufacture and supply of parts to be consumed in the course of maintenance for the supply to: ❍ A maintenance organisation ❍ An owner/operator of the aircraft or component. The requirements on the manufacturer are the same as those requirements for any PC, other than an MRB process is not mandatory. All parts manufactured must conform to the approved data and be in a condition for safe operation. CASR 21.151 The PLR may include generic instructions e.g. for cables and hoses, by material specification, length and fittings. The PAH is expected to receive an application to manufacture each part, identifying the aircraft in which the part will be installed. Note that CASR 21.151 (c) requires the PLR to have a description of each product to be manufactured. However, note that specific replacement parts for general sale (including cables & hoses) are required to be manufactured under an APMA or ATSOA. Note: The use of CASA Form 1/Form 917 Authorised Release Certificate for a oneoff PC is described in Section 3.2.12. ■ 2.2.3 Responsibility for PCs ● The PO is responsible for managing all aspects of an application for a PC ● The TLM is responsible for ongoing certificate management. ■ 2-9 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards 2.2.4 Version 3.0: July 2011 Advising the Applicant As part of the assessment, CASA must ensure that the PC applicant understands that the holder of a PC is responsible for: ● CASR Part 21 ● ● ● CASR 21.147 ● Maintaining the quality system in accordance with the regulations, data and procedures approved for the PC The systems and elements identified in SAE AS9100, Aerospace Standard – Quality Management System, meet CASA’s expectations for a manufacturing quality assurance system, as this standard has been specifically written for aerospace organisations. CASA does not accept the registration and certification of quality systems by third parties as compliance with CASR Part 21 requirements, and will make an independent assessment of such systems as part of the entry control process for the issue of a production approval. However, a quality system based on SAE AS9100 forms a sound foundation for a quality management system that, if properly implemented, should address CASR Part 21 quality system requirements CASA-approved manufacturing organisations and applicants for Part 21 production approvals are to be encouraged to implement quality systems based on SAE AS9100 insofar as the requirements of that standard are applicable to their activities. Large or complex organisations should adopt most, if not all, requirements of the Standard, whereas smaller organisations need only adopt those that are necessary for the management and control of their activities in order to maintain compliance with regulatory requirements relating to their approval. Ensuring conformity with the Type Design or Product Design, as applicable, and condition for safe operation of each completed product or part Notifying CASA in writing of any changes to the quality system that may affect the inspection, conformity, or airworthiness of the product or part in accordance with CASR 21.147. These changes include: ❍ Relocation of a part of a facility or addition to existing facilities ❍ Discontinuing production for an extended period of time for other than normal reasons such as scheduled holidays ❍ Resumption of production after discontinuance ❍ Significant curtailment/resumption of production operations ❍ Significant reduction/reassignment of quality system personnel ❍ Changes or revisions to quality system data and related procedures. 2-10 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards ● CASR 21 Subpart Q CASR 21.003 Version 3.0: July 2011 Marking products in accordance with the requirements of the regulations (CASR 21 Subpart Q) and approved design data ● Reporting all failures, malfunctions, and defects as required by CASR 21.003 ● The PO is to advise the applicant on the data required to be submitted. ■ 2.2.5 AC 21.14 Preliminary Assessment Procedures The application Form 849 Production Approval - Application is recorded at the PAC in accordance with local procedures. Permissions Application Centre 1. On receipt of the application, issue a letter of acknowledgment. 2. Provide a draft estimate for review and approval by TLM. PAC is also to advise the applicant that CASA cannot proceed with the assessment until payment/acceptance, in writing, of the estimate of costs. Preliminary Assessment TLM Upon receipt of a notification of a new application or a variation to an application from PAC, TLM will: 1. Prepare cost estimate using PAC calculator 2. Assign a PO to the task to: ❍ Provide input to the cost estimates ❍ Provide input on completion dates of the various phases of the application, namely Documentation Evaluation, Inspection and Tests, and Certification Processes. PO 1. Complete cost estimates as required by TLM. 2. Complete completion dates in the work flow system when the task is assigned. 3. Plan for the establishment of the PCB and a pre-PCB meeting with the applicant so that the meetings can proceed on payment/acceptance of the estimate of costs. 2-11 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 4. Convene a pre-PCB meeting, before the preliminary assessment, if necessary. 5. After acceptance of the estimate of costs make arrangements to commence the preliminary assessment. This assessment consists of an evaluation of the applicant's: • Quality system data • Facilities, equipment, processes, personnel, control of suppliers, stores, etc, to ensure that they are adequate for the purpose. 6. Advise the applicant that a title must be provided for the quality system manual for positive identification. In addition, a revision page or similar control is required to ensure that the original approval date and the date of each revision are recorded. A number or letter, and date of the revision must identify each revision. 7. Where an applicant has existing quality control procedures for other purposes, the applicant must identify those parts that comprise the quality system that show compliance with CASR 21.143. For a new applicant, the assessment of the quality system data may require several visits to the applicant’s facilities and suppliers as necessary, to evaluate and confirm that the procedures are in fact adequate to control the conformity of detail parts, subassemblies and completed products. The adequacy of the quality system must be physically evaluated by observing the control of each stage of production and all supporting functions. Establishing the PCB and Holding Meetings of the PCB The PO is to establish the PCB and call PCB meetings, as appropriate, in accordance with the procedures in 1.6.1 Production Control Board Description. Design Data Approval The PCB is to determine the adequacy of the design data submitted by the applicant and provide confirmation, via the Minutes of Meeting, that the Design Data is approved for the purposes of processing a production approval and issuing a PC. Where a PCB is not required, the PO is to record the adequacy of the Design Data following the guidance provided at Section XX. TLM will be the final approver of the Design Data Approval sheet; when TLM is the PO, the Design Data Approval sheet must be signed by an independent authority having design data approval authority. Notifying the Applicant On completion of the preliminary assessment, the applicant is to be notified of any corrective actions needed. The applicant is also to be advised that these action items only represent CASA’s preliminary findings and that additional requests for corrective actions can be anticipated as a result of subsequent findings of the PCB, future routine audits and surveillance activities. 2-12 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Issuing the PC and Production Limitation Record (PLR) The PC and PLR certificates are prepared using the CASA templates for the PC (Form 737) and the PLR (Form 002). (The templates are available on CASA's Intranet). Release of PC and PLR CASR Part 21 1. When the PCB has determined and documented that the manufacturer's application has satisfied all the requirements of CASR Part 21, the PC and PLR and a draft letter of approval are prepared by the PO for the signature of the appropriate delegate. 2. The original PC and PLR are given to the applicant. Copies of the PC and PLR are kept on the project Manufacturing and PAC files and on the master folders of PCs and PLRs issued or amended When preparing the PLR, list: ❍ The TC number or Design Data Reference of each product authorised for production ❍ The model numbers and the date on which production was authorised ❍ Any limitations (e.g. limitation to parts only). 3. When the PC, PLR and cover letter are signed by the delegate, the PO is to prepare the final costing and submit to the TLM for approval before loading the relevant certificates and information in the work flow management system. Note: When a PC is issued and based on a licensing agreement for a specific period of time, the PC must terminate on the same date. The approval letter to the applicant must refer to this date. 2-13 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Additions to the PLR If a PC holder wants to add a new product to the PC, (a new model or new parts), the holder must apply in the same manner as for the original issue. When a PCB is not required, Manufacturing will conduct an audit to the extent necessary to determine whether the PIS is adequate or has been appropriately changed to ensure positive control of the product/parts to be added to the PLR. However, if changes to the PIS are substantial, TLM will convene a PCB to make the determination. Changes to the PLR are to be formalised by the re-issue of the PC, PLR and the cover letter. After the PLR has been approved and signed by the delegate, PAC will send the PLR to the applicant with a request to return the superseded PLR. Deletions to the PLR Deletions to the products or approved design data listed on the PLR are to be processed using the same process as for additions. 2-14 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Sample Production Approval Templates Sample Production Certificate CIVIL AVIATION SAFETY REGULATIONS 1998 Production Certificate Number PC-123456 In accordance with regulation 21.134 of the Civil Aviation Safety Regulations 1998, this certificate including the associated production limitation record(s) authorises: Planemaker Aircraft Pty Ltd ABN 91 123 456 789 to manufacture Class 1 Products at the following manufacturing facilities: 2A Industrial Place Werribee, Victoria 3030 This certificate terminates on: 15/06/2004 This certificate is subject to the condition that the holder must notify CASA in writing of any change to the business address of the holder. (signed) A. G. Citizen Date Issued: 15/06/2003 Original Issue: 22/05/2002 Delegate of CASA 2-15 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Sample Production Limitation Record Production Limitation Record The holder of Production Certificate No. PC-123456 may produce: Aircraft and Parts manufactured in accordance with the following design data. Design Data Model or Parts VA999 ASR028SY Airhawk 132B ACME R12 Date Production Authorised 1 December 2003 12 December 2003 Conditions and Limitations: None. (Signed) 12/12/2003 A. G. Citizen Date Issued: (dd/mm/yyyy) Delegate of CASA 2-16 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Sample Production Certificate for “One-Off PC” CIVIL AVIATION SAFETY REGULATIONS 1998 Production Certificate Number PC-123456-1 In accordance with regulation 21.134 of theCivil Aviation Safety Regulations 1998, this certificate including the associated production limitation record(s) authorises: Planemaker Aircraft Pty Ltd ABN 91 123 456 789 to manufacture Class III Products at the following manufacturing facilities: 2A Industrial Place Werribee, Victoria 3030 This certificate terminates on:15/06/2004 This certificate is subject to the condition that the holder must notify CASA in writing of any change to the business address of the holder. (Signed) A. G. Citizen Date Issued: 15/06/2003 Original Issue: 22/05/2002 Delegate of CASA 2-17 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Sample Production Certificate for One-Off PC Production Limitation Record The holder of Production Certificate No.PC-123456-1 may produce: Class III Products manufactured in accordance with the following design data. Module or Parts Design Data Design data approved by CASA or a CASR 201.001 Authorised Person, specific to an individual aircraft Sheet metal parts as defined bythe design data Date Production Authorised 1 December 2003 12 December 2003 Conditions and Limitations: Limited to the manufacture and supply of parts to be consumed in the course of maintenance for supply to: • A maintenance organisation • An owner/operator of the aircraft.. (Signed) 12/12/2003 A. G. Citizen Date Issued: (dd/mm/yyyy) Delegate of CASA ■ 2-18 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards 2.2.6 Version 3.0: July 2011 Testing Aircraft, Engines and Propellers Aircraft CASR 21.197(1)(c) All aircraft produced under a PC must pass an approved production flight test as part of the inspection procedure required for issue of an airworthiness certificate. A Special Flight Permit is issued to authorise production flight-testing under CASR 21.197 (1)(c). CASR 21.325 Small aeroplanes and gliders manufactured under a PC and being exported without assembly or flight test under the provisions of CASR 21.325 are exceptions. However, in these instances the manufacturer, as a condition of the PC, must provide CASAapproved assembly and flight test procedures. Engines and Propellers CASR 21.143(1)(c) Engines and propellers produced under a PC must pass a production test approved as part of the quality system data required by CASR 21.143(1)(c). ■ 2.2.7 PC Holder's Location(s) A PC holder's manufacturing complex may consist of a principal facility and associate facilities using the same quality control system approved by CASA, for the particular type certificated product(s). The PC is issued to the organisation that controls the final assembly, testing and airworthiness release. The principal facility, and all associate facility addresses are listed on the PC. A post office box address is not acceptable for a facility because the actual location must be identified. However, post office boxes may be used as postal addresses for correspondence. CASR 21.155, 21.159 A PC is not transferable—CASR 21.155. If the PC holder relocates any part of the manufacturing complex, the PC holder is required to apply for a new PC, as per CASR 21.159. A new PC under the same number will be issued to reflect the change. ■ 2.2.8 Assessment of an Applicant’s Suppliers See 3.2 Assessment of an Applicant’s Suppliers for supplier evaluation procedures. ■ 2-19 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.2 Production Certificate (PC) Only Approved by Executive Manager, Aviation Safety Standards 2.2.9 Version 3.0: July 2011 Summary of Distribution of Production Certification Documents The PO is to distribute the PC documents as indicated below. Application for PC, CASA Form 849 ● Original retained on PAC data management system, together with: ❍ Copies of the applicant’s legal identity ❍ Licensing agreement(s) ❍ Documented quality control system when approved. PC, PLR and Signed Letter of Approval ● ● The Manufacturing TSO saves the final signed copies of the PC, PLT and Letter of Approval on the relevant Manufacturing file. The approved copy of the Quality Manual, including the PIS, is also saved on the Manufacturing file by the TSO. 2.2.10 Final Costing The PO is to prepare the final estimate for review and approval by the TLM before despatch to PAC for re-imbursement or claim of additional costs. Request for Amendment to the Production Certificate CASR 21.153 The applicant is to submit Form 849 Production Approval - Application. A Manufacturing PO will assess the application for amendment in accordance with these procedures for revised PC and for its compliance with CASR 21.153. The PC and PLR will be re-issued to reflect the amendment. ■ 2-20 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards 2.3 Version 3.0: July 2011 Australian Parts Manufacturer Approval Only 2.3.1 Applicability of Australian Parts Manufacturer Approval This section covers the assessment and issue of an APMA for replacement and modification parts for installation on a type certificated product, in accordance with CASR Part 21, Subpart K, regulation 21.303. CASR Part 21, Subpart K, 21.303 The section provides guidance for CASA to be satisfied that the applicant has shown compliance with airworthiness requirements on the basis of tests and computations, or in certain cases, on the basis of identicality. CASR 21.303 CASR 21.303(2)(e) CASR 21.303 requires that any person producing replacement or modification parts for sale for installation on a type-certificated product must obtain an APMA. An APMA must be obtained for replacement or modification parts for an STC if they are not being produced under a PC. Note: Standard parts conforming to an established industry or Australian specification (e.g., AN bolts and nuts) are not eligible for an APMA (CASR 21.303(2)(e)). Imported Products CASR 21.502, 21.502A If, in producing a part under an APMA, imported parts are to be used, they must be imported parts in accordance with CASR 21.502 and 21.502A. ■ 2.3.2 Responsibility for Australian Parts Manufacturer Approval Applicant The applicant must show that the design meets the applicable airworthiness standards. The applicant shows compliance in two ways: 1. The applicant demonstrates that the design of the part is identical to the design of a part covered under a TC or STC; or 2. The applicant demonstrates through tests and/or computations that the design of the part meets the airworthiness requirements applicable to the product on which the part is installed. The applicant must assure that no interference with mating or adjacent hardware occurs and that the part performs its intended function. CASR 21.303(11), The applicant must establish and maintain a FIS that meets the requirements of CASR 21.303(11). ■ 2-21 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards 2.3.3 Version 3.0: July 2011 Lodgement of an Application for an APMA Applicants should be advised to submit an application for an APMA in a letter with a completed Form 849 Production Approval - Application to CASA PAC. The applicant must comply with CASR 21.303. Initial Assessment If the application or Form 849 Production Approval - Application does not contain all the relevant information the TLM will provide details to PAC and PAC will advise the applicant. ■ 2.3.4 CASA Engineering Assessment Design Assessment 1. Ensure that the applicant’s engineering design data package meets the applicable airworthiness design standards and complies with the relevant certification regulations. This may require the assessing PO to refer aspects of the design package to other engineering specialists. CASR 21.303(c) 21.303 4) 2. Design data as defined in CASR 21.303(c) that has been approved by an AP for CASR 21.303(4) is to be reviewed at the discretion of the PO, commensurate with the knowledge and experience that CASA has of the AP. 3. Determine whether the application for the APMA establishes that the part meets the relevant airworthiness requirements applicable to the type certificated product on which the part is to be installed. Also verify the eligibility for installation of the part on the type-certificated product. 4. If the applicant's design does not meet all the above design considerations, the PO will advise the applicant accordingly and the application will not be processed any further. A revised application may be required to resolve outstanding issues. 2-22 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Compliance Considerations Applicant The applicant must submit: AC 21.16 ● A Compliance Statement listing the applicable regulatory requirement (refer AC 21.16) ● The means or documents showing compliance ● A compliance statement. PO 1. Regardless of the method by which an applicant chooses to show compliance as listed on the Compliance Statement, prior to issuing APMA approval, carefully review the application as appropriate, to determine whether the applicant can ensure: a. Compliance with the applicable airworthiness requirements b. That the materials conform to the specifications in the design c. That the part conforms to the drawings in the design d. That the applicant has demonstrated that the fabrication processes, construction and assembly conform to those specified in the applicant's design (CASR 21.303 (8)(d) refers) CASR 21.303 (8)(d) CASR 21.865 e. That part marking requirements are satisfactory and in accordance with CASR 21.865 CASR 21.003 f. Continued airworthiness under the applicable airworthiness requirements, including reporting requirements under CASR 21.003, for the manufactured part and the product upon which the part is installed. Note: Where required, the PO is to seek further specialist assistance to make the above determination Verification of Installation Eligibility The applicant’s claim of installation eligibility must be verified by the PO. This may be one or more of the following: ● Licensing agreement with TC or STC holder ● TC Data Sheet ● Training notes 2-23 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards ● Maintenance manuals ● Service Bulletins ● Technical Publications ● Flight Manuals ● Airworthiness Directives ● Illustrated Parts Catalogues (IPCs). Version 3.0: July 2011 While some of these sources may not be NAA approved, they may be used carefully in conjunction with other data to provide verification. Service History Considerations The PO is to: 1. Consider the service history of the part in question and verify that it is not the subject of an Airworthiness Directive (AD), other continued airworthiness problems, or subject to an incident/accident investigation. 2. If the part is subject to one of the above, and the design is identical to the original part and produced under a licensing agreement, use the following guidelines: a. If there is an AD that removes the original part from service, immediately or in the future, the APMA application should be rejected unless the application includes design changes that satisfactorily address the AD problem. b. Consult with the TLM and specialist staff as necessary to ascertain whether CASA is currently developing or considering development of an AD to remove the original part from service. CASR 21.303(4)(a) c. If CASA and/or ATSB are investigating an incident/accident where the original part may be causal, CASA may delay or suspend the processing of the APMA application until the part is cleared. (Refer CASR 21.303(4)(a).) d. If an AD calls for repetitive inspections but prescribes no terminating corrective action—eg no modification or replacement of the part provided—and if the repetitive inspections are intended to catch failures that may occur before the part reaches the published service life, CASA should reject the application for an identical part APMA. CASA should always strive for terminating corrective action; an APMA to produce and distribute identical parts only complicates and prolongs the problem. If the part is subject to Service Difficulty Reports and CASA is pursuing corrective action with the TC holder, the application for APMA should be rejected. In these cases an improved replacement part should be sought. 2-24 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 e. The fact that the TC holder issues an Alert Service Bulletin (ASB) to remove a part from service does not, in itself, exclude issue of an APMA. Life-limited Parts Irrespective of the method under which an applicant seeks an APMA, the applicant must establish the life limit of that part. The required substantiating data must include tests on components produced by the applicant. Special Considerations – Identicality Design data can be accepted for approval when the applicant shows, and CASA finds, that the design of the part for which the APMA is requested is identical in dimension, tolerances, materials, processes, and specifications to the design of the part covered under a TC or STC. Some part designs may contain features that may have nothing to do with form, fit, or function or being airworthy. Some of these features may include tooling holes, colour, tighter tolerances, location/type of part marking, etc. It may not be necessary that these features be identical, however these will require engineering assessment and acceptance. Certification Specialists In some cases, the design data may have to be reviewed by specialist Certification staff. Where such cases arise, specialist Certification will raise a report as to the acceptability of the design data which will be addressed to the TLM via the PO. This review may be particularly important for critical parts. Reverse Engineering The process of reverse engineering is one way to develop the design of a part. However, reverse engineering may not produce a design that is identical to a type certificated part. While an applicant could establish the use of identical materials and dimensions, it is more difficult to demonstrate that the tolerances, processes, and manufacturing specifications are identical. The Test and Computation method is the preferred means of demonstrating compliance with the applicable regulations. 2-25 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Rejecting an Application CASR 21.002B CASR 21.002B refers. PO CASA in general does not have access to the commercial in confidence original certified data in order to make a determination of identicality. Therefore, in practice, identicality can only be established for parts manufactured to design data supplied under licensing agreement with a TC or STC holder. 1. See 5.4.1 Sample CASA APMA Design Rejection Letter for letter rejecting the applicant’s claim of identicality. 2. That the applicant may submit inspection and test reports to substantiate that the design and manufacturing data will produce a part that meets the airworthiness requirements and is safe for installation on applicable type-certificated products. The PO will seek further information from the applicant when the airworthiness of a part cannot be assured solely by the showing of equivalence to the design covered under a TC or the design cannot be shown to comply with the original TC design standard. Considerations for the Project Officer 1. Review and evaluate the test schedule submitted prior to any CASA test to determine if it is appropriate for the part. 2. Ensure the part conforms to the design data and/or the test proposal before testing. 3. For critical parts, coordination with technical specialists may be required. Evaluate the Data Package 1. Evaluate each applicant's capabilities to reproduce a part on a case-by-case basis. 2. Coordinate with the relevant specialist to ensure that the manufacturing process produces replacement and modification parts according to the approved design. All applications should include: ❍ Detailed design criteria, including drawings, technical data necessary to establish structural strength, part marking information, and process specifications necessary to define the configuration. CAR 35, 36 ❍ For engineering design modifications approved under CAR 35, the depth of assessment may be varied at the discretion of the engineer. 2-26 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards ❍ ❍ ❍ ❍ Version 3.0: July 2011 Other data necessary to establish the pertinent characteristics of the part. The applicants must identify detail drawings as their own unless evidence of a licensing agreement is submitted. In evaluating any data package, consider the following: Manufacturing and Process Specifications: Manufacturing procedures and process specifications may affect the airworthiness of the part. If the applicant's detail drawings reference the TC holder's process specifications, those specifications must be submitted. As the data package is reviewed, coordination with the CASA type certification specialist personnel may be necessary to determine what effect these specifications may have on the airworthiness of the design or to a finding of identicality (see Special Considerations –Identicality). For critical parts, coordination with the relevant specialist is required. Master Control Drawings: Master control drawings or their equivalent must be carefully evaluated to determine whether the applicant has appropriate control over the configuration and manufacture of the part. The applicant must submit all applicable detail drawings and specifications for acceptable evaluation of the sources listed on master control drawings. The applicant must have satisfactory and verifiable control procedures included in the FIS for vendor supplied items prior to the issue of the APMA. Drawing Notes: The PO, with particular reference to any drawing notes or process specifications identified on the drawing, should check the applicant’s ability to produce conforming parts before issuing APMA approval. ■ 2-27 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards 2.3.5 CASR 21.303(11) AC 21..27 Version 3.0: July 2011 FIS Assessment The PO is to make sure that the FIS required by CASR 21.303(11) has been established and is ready for assessment. The data from the design/production holder should be nominated and confirmed as controlled data. Once notified by the applicant that the FIS is established, the PO or delegated person is to carry out an assessment of the FIS in accordance with 3.2 Assessment of an Applicant's Suppliers and 3.3 Assessment of Quality Systems for Manufacture. CASR 21 Subpart Q Ensure the FIS includes procedures for the marking of parts in accordance with CASR 21 Subpart Q requirements. Facilities Inspection CASR 21.303(5) The PO is to conduct an evaluation of the applicant's facility in accordance with CASR 21.303(5), including any supplier's facilities as appropriate, to determine whether the facilities are suitable for manufacturing the nominated parts and that the applicant's FIS is operating effectively. Validation of the Applicant’s Conformity Inspection CASR 21.303(8) 1. The PO is to conduct validation conformity checks, as necessary, to ensure conformity of the parts to the approved design drawings and data as undertaken in accordance with the applicant's FIS in compliance with CASR 21.303(8). Validation conformity checks include incoming materials and processes used in producing the conformed part. Parts inspected for conformity are to be recorded on the Conformity Inspection Record (Form 882), together with comments regarding identified non-conformities. 2. An agreement must be reached with the applicant as to how the identified nonconformities will be addressed and, if necessary, the FIS re-presented to CASA. Manufacturing Procedures CASR 21.303(8) 21.303(11) When satisfied that the manufacturing facilities, procedures and processes and inspection system comply with CASR 21.303(8) and (11), complete the relevant section of Form 883 Production Approval Assessment Control Document. ■ 2-28 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards 2.3.6 Version 3.0: July 2011 APMA Approval Design Acceptance/Approval PO 1. Confirm design compliance. 2. Confirm that satisfactory manufacturing processes, material control and FIS have been assessed and are acceptable. 3. Ensure that a master drawing list or similar has been prepared and dated at the revision level. 4. Ensure that all drawings and data required are listed. Make sure that a copy of the submitted data package is retained on the project files. Final APMA Approval PO CASR 21.303 1. Draft an APMA approval letter (pursuant to CASR 21.303) together with an APMA Supplement for approval for the appropriate delegate’s signature. Ensure that both the letter of approval and Supplement document are identified with the same APMA approval number. See: ❍ 5.2 Sample CASA APMA Approval Letter ❍ 5.3 Sample CASA APMA Supplement without Licensing Agreement ❍ 5.4 Sample CASA APMA Supplement with Licensing Agreement. Note: Form 1142 is used for portrait APMA Supplement and Form 1143 is used for landscape APMA Supplement. (Forms available to CASA staff only.) 2. Finalise costing charges by CASA in accordance with CASA’s cost-recovery procedures. 3. Forward all relevant documents to the delegate. 2-29 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 TSO 1. TSO is to forward the original documents to PAC for on forwarding to applicant and to close the job in the workflow management system. 2. TSO will also update regulatory system database with the permissions/certificate issued. 3. TSO is to update audit program as required. Design Changes CASR 21.303 (4) For an APMA based on test and computation, all the design changes must be submitted to CASA or an AP for CASR 21.303 (4) for assessment. Changes to an Existing APMA The PO should conduct or arrange for an evaluation, as appropriate, when additional parts are approved to an original APMA approval or when the manufacturer makes changes to the FIS or relocates a facility. Advice to CASA of Changes to a FIS or Location CASR 21.303 (4) A PAH is required to notify CASA within 10 days of any change to the manufacturing facility (CASR 21.303 (13)), and within 2 days of any change to the FIS (CASR 21.303(13A)). CASR 21.303(12) On advice that a facility has been expanded or relocated, the TLM is to appoint a PO to determine the likely airworthiness impact. If the same procedures are still applied, and a satisfactory first article conformity inspection is conducted and documented, then it may be sufficient to file the notification and use the advice to focus the next audit to the changed areas. If the PAH does not conduct a satisfactory first article conformity inspection after the facility is expanded or relocated, CASA may advise the PAH that the APMA is no longer in force (CASR 21.303(12)) until this is achieved or the facility is reevaluated by the PO with the intent of re-issuing the APMA or authorising continued production. If the PAH has changed the FIS without prior advice to CASA, the inspection process may not ensure conformity, and the PO needs to evaluate the APMA. When issuing an APMA the applicant should be encouraged to include suitable procedures in the procedures manual for having changes to the FIS approved by CASA before implementation so the approved system can be maintained. If conformity is affected, the APMA holder is required to quarantine production until the change is approved. 2-30 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.3 Australian Parts Manufacturer Approval Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 APMA Data Package AC 21.16 The recommended content of an applicant’s data package is given in AC 21.16. Provision of this information will assist assessment of the application. Statement of Conformity The use of CASA Form 724 Statement of Conformity by the applicant is recommended for first article Statement of Conformity. Use of the form prompts for the information required to process the application. APMA Letter of Approval ❍ For a template for the APMA Letter of Approval see 5.2 Sample CASA APMA Approval Letter ■ 2-31 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.4 Australian Technical Standard Order Authorisation (ATSOA) Only Approved by Executive Manager, Aviation Safety Standards 2.4 Version 3.0: July 2011 Australian Technical Standard Order Authorisation (ATSOA) Only 2.4.1 Applicability – ATSOA An ATSOA is a CASA design and production authorisation, issued to a specific manufacturer of an article which has been found to meet or exceed a specific TSO performance standard, or other performance standard accepted by CASA. CASR Part 21 Subpart O An ATSOA must be obtained by persons who want to manufacture ATSO articles under CASR Part 21, Subpart O, Australian Technical Standard Order System. An ATSOA holder is a manufacturer who controls the design and quality of an article produced under the ATSO system, including all related parts, processes or services obtained from an outside source. The ATSOA system does not apply to parts produced under an APMA, TC only, or a PC. A letter of ATSO design approval for an appliance may be issued to foreign manufacturers located in countries with which Australia has an agreement which provides for the acceptance of appliances, provided that: ● ● The NAA of the country in which the appliance will be manufactured certifies to CASA that the design of the particular appliance meets the pertinent design requirements of the specific ATSO/TSO The NAA is advised that each appliance that is produced under the provisions of the ATSO design approval and exported to Australia must be accompanied by an airworthiness approval issued by the NAA of the foreign country certifying that the article conforms with the appropriate ATSO/TSO and is in a condition for safe operation. ■ 2.4.2 Advising the Applicant Project Officer 1. Advise the applicant that: AC 21.27 a. An ATSOA consists of the design and production approval. b. An ATSOA can only be obtained for the current ATSO/TSO for the particular article. c. AC 21.27 contains guidance on what is an acceptable quality system. ■ 2-32 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.4 Australian Technical Standard Order Authorisation (ATSOA) Only Approved by Executive Manager, Aviation Safety Standards 2.4.3 Version 3.0: July 2011 Lodgement of an Application The applicant (or the applicant’s authorised agent) must submit an application for an ATSOA to PACS using. See 5.7 Sample ATSO Authorisation. CASR 21.605 The application must be accompanied by those documents required by CASR 21.605, and any documents required by the performance standard. CASR 21.617 Foreign manufacturers who want to obtain a letter of ATSO design approval, (as provided for in CASR 21.617) must submit their application through their NAA to Permission Application Centre, Civil Aviation Safety Authority, GPO Box 2005, Canberra, ACT 2601, Australia. ■ 2.4.4 ATSOA Issue Procedure Design Approval Permissions Application Centre 1. On receipt of the application, forward it to the TLM. TLM Upon receipt of a notification of a new application or a variation to an application from PAC, TLM will: 1. Prepare cost estimate using PAC calculator. 2. Assign a PO to the task to: a. Provide input to the cost estimates b. Provide input on completion dates of the various phases of the application, namely, Documentation Evaluation, Inspection and Tests, and Certification Processes. 2-33 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.4 Australian Technical Standard Order Authorisation (ATSOA) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 PO CASR 21.605 1. On receipt of the application, check all incoming material to determine that documents and all data conform to the requirements of CASR 21.605. 2. If the data are incomplete, provide guidance to PAC to advise the applicant by letter via the PAC that no further work will be done until the missing data are supplied. CAR 35 The design and production approval must be carried out by CASA. Data submitted with a CAR 35 AP’s approval still needs to be assessed by the CASA PO. 3. Examine the technical data to ascertain that the technical requirements of the ATSO are met. The examination should include: ❍ A check of the adequacy and validity of technical data and test results CASR Part 21.605 ❍ Drawings and prescribed equipment installation information, and specified limitations should be checked for completeness and adequacy since such data are important to evaluation of aircraft type designs as well as for determination of the ability of the applicant to produce duplicate articles per CASR 21.605(4). 4. Notify the applicant in writing of any omissions. 5. Visit the applicant’s facility for the purpose of appraising the applicant’s competence to certify conformance with the ATSO. This visit should be in company with the assigned MI responsible for production approval compliance who should determine that compliance tests, as prescribed, are being realistically conducted. 6. Prepare letter of ATSO Approval for release by the TLM or appropriate delegate. 7. Advise TLM and PAC of task completion and update the work flow management system. TSO 1. Once advised by the PO that the ATSOA activities are completed, update the regulatory system database with copies of the relevant letters issued. 2. Update audit schedule to verify holders continue to comply with the performance standards of the ATSO. 2-34 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.4 Australian Technical Standard Order Authorisation (ATSOA) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Quality System Data Compliance CASR 21.143, 21.144 The applicant for an ATSOA must submit, along with the application, a written description of the quality system in the detail specified in CASR 21.143 and 21.144. The quality system data compliance is determined in the following manner: PO; 1. Conduct a thorough evaluation of the quality system data submitted by the applicant. 2. If evidences of quality system deficiencies are noted, ensure all unsatisfactory conditions are addressed. 3. Carry out the procedures detailed in Section 3. Assessment of an Applicant’s Quality Systems for Manufacture, to determine compliance with CASR 21.143 and 21.144. The quality system data must include an acceptable test procedure meeting the ATSO requirement to which each production article will be tested. 4. Guidance on an acceptable quality system is in AC 21.27 Manufacturing Approval Overview. 5. Determine whether or not these data comply with CASR 21.605. 6. In those instances when the quality system is found to be unsatisfactory, note the deficiencies on the Form 883 Production Approval Assessment Control Document and advise the applicant. 7. When satisfied that the data is in compliance with CASR 21.605, prepare the latter of approval. Issue of the ATSOA 1. When satisfied that both the design approval aspects and quality control data aspects are compliant, forward a recommendation for the issue of an ATSOA to the TLM. 2. Advise the PAC of the approval details for entry onto the Regulatory system database. 3. Provide advice to the TSO of the ATSO Approval for the update of the Manufacturing Section’s Surveillance audit schedule. 2-35 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.4 Australian Technical Standard Order Authorisation (ATSOA) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Post-issue Compliance CASR 21.143 CASR 21.144 Subsequent revisions to the quality system must be submitted by the ATSOA holder to PAC to determine compliance with CASR 21.143 and 21.144. CASR 21.143 CASR 21.144 The assigned Manufacturing PO is to advise the ATSOA holder as to whether or not the revisions comply with CASR 21.143 and 21.144. ■ 2.4.5 ATSOA Holder's Facility Location An ATSOA holder's manufacturing complex may consist of a principal facility and associate facilities using the same quality control system approved by CASA. The ATSOA is issued to the applicant at the address of the principal manufacturing facility which controls the design and quality of the product(s). The principal facility, and all associate facility addresses are listed on the ATSOA. A post office box address is not acceptable for a facility because the actual location must be identified. However, post office boxes may be used as postal addresses for correspondence. If an ATSOA holder moves a manufacturing facility to a new location, CASA must conduct an assessment at the new location to ensure that the ATSOA holder continues to comply with CASR 21.605 and 21.607. CASR 21.605, 21.607 ■ 2.4.6 Approval of Materials and Processes Introduction CASR Subpart K CASR 1998, Subpart K also provides for approval of the use of materials and processes. CASR 21.305 Under the provisions of CASR 21.305, the use of a particular material or process may be approved: CASR 21.502 CASR 21.305 ● If it is included as part of an APMA or ATSOA ● In conjunction with type certification for an aircraft engine or propeller ● If it meets the requirements of CASR 21.502 (1) (a) and (b) for imported materials ● In any other manner approved by CASA. 2-36 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.4 Australian Technical Standard Order Authorisation (ATSOA) Only Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Application CASR 21.305 Applicants seeking CASA specific approval of the use of a material or process under CASR 21.305 (e) should be advised to lodge their application to PAC. This letter of application should include details regarding: ● ● ● ● The identity of the type certificated product or part on which the material or process will be utilised The name and address of the material manufacturing or process application facility Material or process specification details, including test reports showing the material’s physical and chemical properties Reports and computations necessary to show that the use of the material or process is compatible with, and does not in any way compromise, the design of the type certificated product or part on which it is utilised The applicant may be required: ● ● To carry out any other tests considered necessary to verify material or process specifications To carry out appropriate tests to show the effect of the material or process in service. ■ 2-37 Production Approval Procedures Manual 2. Assessment and Issue of Approvals 2.4 Australian Technical Standard Order Authorisation (ATSOA) Only Approved by Executive Manager, Aviation Safety Standards Blank Page 2-38 Version 3.0: July 2011 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.1 General Principles Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3. Assessment of an Applicant's Quality Systems for Manufacture 3.1 General Principles 3.1.1 General Principles CASR Part 21, Subparts F, G, K or O The purpose of this part is to assist in assessing quality systems of applicants seeking production approvals under CASR Part 21, Subparts F, G, K or O (Production under TC certificate only, PC, APMA, ATSOA). Not all the functions/elements specified in this part are necessarily applicable to every applicant's system, and the assessing officer before undertaking this assessment should ensure a good understanding of the applicant's organisation and the extent of the manufacturing work to be undertaken. All aspects of the intended manufacturing activity must be clearly and adequately specified in the applicant's quality system. Assessment Stages Assessment of any quality system is normally a three-stage process. Stage 1 Quality System Assessment—Desk-top Review Conduct a "desk top" review of the applicant's system to ensure that all the required procedures are included and adequately address the regulatory requirements. Stage 2 Quality System Assessment—Quality System Evaluation Evaluate the system at the manufacturing facility or facilities to ensure that the procedures have been documented, implemented and effectively control the work. Stage 3 Quality System Assessment—Manufacturer's Corrective Action The manufacturer rectifies any noted deficiencies and discrepancies by amending documented procedures or correcting discrepancies at the manufacturing facility or facilities. Quality Systems Documentation All production approval applicants are required to establish and maintain a quality system. It follows that the documented system must contain adequate procedures for the maintenance of the approved system. The documented system should identify the person who is responsible for CASA liaison, and will approve and implement quality system changes within the entity. 3-1 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.1 General Principles Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Quality systems for PC and ATSOA applicants are required to comply with CASR 21.143 and 21.144. The quality system must be documented in a manual, and must include procedures for the following functions. CASR 21.143, 21.144 1. Organisation Structure, Authority and Responsibility of APs 2. Technical Data Control 3. Manufacturing Processes 4. Special Processes 5. Non-destructive Inspection 6. Tool and Gauge Control 7. Receiving Inspection/Supplier Control 8. Inspection and Testing 9. Material Review Procedure (Except for a CASR Part 21.133(2B) PC) 10. Stores Control 11. Certification and Release 12. Service Difficulty Reporting and Control. CASR 1998 21.123(1), 21.303(11) The Quality System (QS) requirements for Production under Type Certificate Only (PIS) and APMA (FIS) must also address items (1) to (12) above. The regulations covering PIS and FIS do not contain a specific requirement for the applicant's organisational structure to be included. However, CASR 1998 21.123 (1)(c) and 21.303 (11) require the applicant to establish and maintain a system which ensures that each completed product or part conforms to its design and is safe for operation or installation. Establishment of Evaluation Teams The PO shall coordinate with relevant Manufacturing and specialist staff to conduct an evaluation of an applicant's quality system. When the application is for manufacture of aircraft, the flight test personnel from Airworthiness and Engineering Branch are required to evaluate the relevant sections of the data and approve the production flight test schedule. ■ 3-2 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.2 Assessment of an Applicant’s Suppliers Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3.2 Assessment of an Applicant’s Suppliers 3.2.1 Assessment of an Applicant’s Suppliers Preliminary and Ongoing Audits of the Supplier’s Facilities CASR Part 21 This section provides guidelines for CASA’s assessment of an applicant’s supplier production facility to ensure that the supplier control system implemented by the Production Approval Holder (PAH) meets the intent of CASR Part 21. The PAH has initial and on-going responsibility for control of suppliers. CASA may undertake audit of the facilities. CASR Part 21, Subparts F, G, K, and O CASR Part 21, Subparts F, G, K, and O, require the establishment of a quality system as a prerequisite to the issue of a CASA production approval. A critical part of such a system is to establish and maintain procedures for ensuring that components and materials produced by suppliers conform to the approved design data and are in a condition for safe operation. It is the PAH's responsibility to ensure that each completed product, part or appliance, including supplied components and materials, conforms to the approved design data and is in condition for safe operation. When suppliers are located outside of Australian territory CASA may request assistance from the NAA of the foreign country to act on its behalf, to perform assessment (and audit) activities. Such assistance may come under the terms of formal state agreements, memorandums of agreement between the authorities, or requests for assistance on a case-by-case basis. A PAH may utilise any supplier as long as the PAH’s quality control system provides assurance that all parts or services, including engineering services, furnished by a supplier are in compliance with its production approval. The PAH should place special emphasis on controlling those suppliers that it authorises to deliver parts/materials directly to a user/operator of the PAH’s completed product. Each PAH must make available to CASA a list of its direct ship suppliers. The PAH should have objective evidence that the suppliers have been notified that their facilities are subject to CASA audit. Emphasis is placed on the PAH's control of its suppliers, since the PAH is totally responsible for all of its supplier-furnished parts and services. CASA may evaluate the PAH's quality system implementation at selected suppliers. 3-3 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.2 Assessment of an Applicant’s Suppliers Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Assessment The same procedures and criteria used to accomplish and record assessment of the PAH quality system and facilities are to be used for evaluating suppliers, even though not all elements may be applicable to individual suppliers. Staff are to exercise their judgment and experience in performing supplier assessments. These procedures and criteria are detailed in 3.3 Quality System Assessment. Note: When a supplier to multiple PAHs is evaluated, it is of the utmost importance to ensure that the quality control requirements for the applicant being currently evaluated are met by the supplier. ■ 3-4 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3.3 Quality System Assessment 3.3.1 Stage 1 Quality System Assessment—Desk-top Review System Evaluation This stage is a thorough evaluation of a manufacturer's system (including any referenced procedures, policies, standards, instructions, processes), which describes the quality system required for a particular production approval. Note: All applications to CASA for production approval, conformity inspection, certificates of airworthiness or special flight permits must be signed by a legally empowered company principal or a letter of agency must accompany each application. Evaluation Method 1. It is of the utmost importance that the PO critically evaluates the submission to ensure that: a. The described quality system will adequately provide for the consistent acceptance of only those products/parts that conform with the approved design data. b. The manufactured products/parts are in a condition for safe operation. 2. The prime objective of all quality system data is to ensure that it describes the procedures that meet the intent of the pertinent regulations, and can be realistically implemented. Applicants must understand that penalties can apply to non-compliance with the approved system; therefore the system described must reflect ‘local’ operations rather than ‘generic’ procedures. 3. All documents must be positively identified by title, revision, and date; and must be approved for use by an authorised management representative (often the Quality Manager). 4. The initial evaluation of a manufacturer's quality system documents must be thorough and comprehensive. However, any subsequent evaluation of a particular manufacturer's quality system may consist of: a. A cursory review of previously submitted data to determine whether or not it has remained adequate. b. A thorough review of any data that has been revised since the last evaluation. c. A thorough review of any new data that has been developed and implemented since the last analysis—for example, review of the quality assurance provisions of a new bonding process introduced subsequent to the last analysis. 3-5 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 5. When evaluating the system, inspectors should flag: a. Any ambiguous data that may be subject to misinterpretation. b. Any overly complex or cumbersome inspection procedures that may be difficult to implement, be disregarded or even circumvented. Consistency of Compliance Standards CASR Part 21 Although the CASR Part 21 production approvals require different types of production control systems, this does not mean that less stringent standards are acceptable for manufacturers of like products or parts. Notwithstanding the type of production approval held, the product or part must, when completed, conform to its approved design and be in a condition for safe operation. Quality System Elements The system elements detailed below are common to all production approvals, although the level of detail required to ensure control of any particular element may vary between the different types of approvals. Evaluating inspectors must be satisfied that the applicant has adequately addressed each necessary requirement and the procedures are satisfactory to ensure the product or part conforms to the approved design. The following tables include the essential elements and evaluation criteria. Note 1: In describing the quality system, references to other documents or data maintained by the applicant may be used, provided that a brief description is included in the quality system. All referenced documents must be submitted for evaluation. Note 2: In the tables the ‘Essential Elements’ define the breadth of requirements under each sub-title. The ‘Evaluation Criteria’ column briefly outlines criterion that satisfy the requirements. The Essential Elements and Evaluation Criteria in the following tables are not meant to directly correlate across the table. 3-6 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 1. Organisation Structure, Authority and Responsibility of Appointed Persons Essential Elements Evaluation Criteria 1. Management has responsibility for the quality system. 1. A concise statement that describes the assigned responsibilities and delegated authority of senior management for the quality system including maintenance of the system. 2. Clearly described responsibilities for control of production and quality functions, including internal audit responsibilities. 2. (i) An organisation chart that shows the functional relationship of the QC organisation to management and to the other organisational components. (ii) A concise statement that describes the authority and responsibilities of each AP, including CASA APs, within the production and quality functions. 3. Management responsibility for training of personnel. 3. A description of the chain of authority and responsibilities within the organisation for task-specific training and maintenance of operator approvals. 4. Personnel performing critical operations, inspections, special processes etc, or certifying for inspections and/or stages of work are adequately trained and approved. 4. Procedures for incorporating changes to the quality system and outlining the authority of those authorised to make such changes. 5. Ensure that each tag, form or other document used under the approved system is described by sample in the approved manual and has instructions for correct use. 5. (i) Procedures to ensure that any change to the quality system that may affect inspection, conformity, or airworthiness of the product are forwarded immediately to CASA in writing. (ii) Procedures to ensure that any change to the production location results in a first article inspection following start-up production at the new location, and advice to CASA within 10 days of the re-location. 3-7 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Essential Elements Evaluation Criteria 6. Ensure procedures exist for keeping 6. Procedures for establishing and a technical master file and record of maintaining all controlled documents all current and superseded identified in the quality system. approved design and production system documentation to ensure the complete production history of product and parts is available. 7. Management has and applies procedures for inspection record retention compliant with the applicable regulatory provision. Record retention includes back-up and security provisions. 7. Procedures that provide for an adequate method of self-audit by the manufacturer of the entire QC system, including supplier facilities. (The prime objective of the self-audit is for the manufacturer to determine compliance with their own procedures and to ensure that management is aware of any existing system deficiencies.) 2. Technical Data Control Essential Elements Evaluation Criteria 1. Technical data (drawings, specifications, software and changes thereto) must be approved only by authorised personnel. 1. Procedures for drawing, engineering and software change control including drawing and specification lists necessary to define the configuration of the CASA approved design. 2. Technical data must be approved prior to release, and should contain the effective date and the signature and position of the person authorised to release the data. 2. Procedures for informing company inspectors of approved changes in engineering data, specifications and the quality system. 3. Distribution of technical data is controlled to ensure that current data is readily available to production and inspection personnel. 3. Procedures that require all process changes to be submitted to CASA for evaluation and incorporation into the approval. Process specification changes are deemed to be major changes. 3-8 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 4. Inapplicable, inappropriate, or obsolete technical data must be removed from use. 4. Procedures to ensure that changes to the design data are distributed to all relevant users simultaneously. 5. Current approved technical data must be used for inspection acceptance. 5. Procedures to ensure that design changes are immediately incorporated in the design data to ensure that the design change is incorporated on production products. 6. Drawings and specifications bearing unauthorised changes or unauthorised notations must not be used for inspection acceptance purposes. 6. Procedures to ensure that design changes are immediately incorporated in the design data to ensure that the design change is incorporated on production products. 7. Ensure procedures have been properly 7. Procedures to ensure that design implemented to adequately provide for changes are immediately incorporated immediate incorporation of design in the design data to ensure that the changes resulting from ADs and other design change is incorporated on directives and bulletins. production products. CASR Part 21 21.093 21.132A(2) 21.303 (3)(c) 21.611 8. Where appropriate, ensure procedures are applied to incorporate production changes back into the applicable Instructions for Continued Airworthiness and Flight Manual. 8. Procedures to ensure that design changes are reviewed for their impact on instructions for continuing airworthiness and operational manuals. Review design change management check lists. 9. Ensure a determination of major or minor change is made and recorded for each design change. 9. Procedures to ensure that design change management decisions, including judgement of significance, are properly recorded and reviewed by an “authorised panel/body” at regular intervals. CASR Part 21.093 applies to PIS and TC designs only. Part 21.132A(2) defines Class ll and III product designs, 21.303(3)(c) defines APMA designs and 21.611 applies to ATSOA designs. Ensure procedures acceptable to CASA are applied to approve minor design changes. 3-9 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3. Manufacturing Processes Essential Elements Evaluation Criteria 1. Production facilities should be arranged to preclude contamination of products and parts—for example, isolation of grinding, painting, or sanding areas from a critical assembly area. 1. Procedures for generating, validating and approving manufacturing and inspection function recording sheets. These should list the approved data to be used, together with methods of inspection by tooling, characteristics, and sampling quantities, and also identify the persons performing the manufacturing work, and those conducting the inspection and certification. 2. Products and parts must be properly handled and stored to prevent corrosion, damage or contamination. 2. Procedures for the proper segregation of serviceable and unserviceable parts and quarantining of defective parts. 3. Shop travellers, checklists, or similar media should be used to ensure the proper movement, handling, and storage of products and parts from one station to another through all phases of the manufacturing process. 3. A description of actions required, or a flow chart, for processing all products and parts through the manufacturing cycle. 4. Inspection records must be maintained and used as required. 4. Procedures that will provide for the selection of appropriate inspection methods and plans for each product and part to ensure that all parts will be inspected as required to eliminate discrepancies and to ensure that the end item will be in conformity to the design. 5. The degree of protection afforded by any sampling plan used should be known and the associated conditions for its satisfactory use enforced by the manufacturer. 5. Procedures for reviewing sample test reports and for providing feedback on the adequacy of the sample size, the frequency of sampling and the in-service failure data versus inspection model. 6. 3-10 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Essential Elements 6. Technical data must be appropriately authorised and must reflect the proper revision for the particular manufacturing process. Evaluation Criteria 6. (i) Procedures to control material lot splitting to ensure complete accountability—that is, action to be taken when a lot or batch contains more or less pieces than recorded on the shop traveller or routing sheet. (ii) Procedures to ensure that design changes are reviewed for their impact on instructions for continuing airworthiness and operational manuals. Review design change management check lists. 7. Inspection stations must be located at points in the manufacturing process where accurate quality determinations can be made. 7. Procedures to control the movement of products and parts throughout the manufacturing process showing production and inspection status at all times. 8. Inspection equipment being used must be adequately controlled for accuracy. 8. Procedures for control of measuring equipment must be available for review. 9. The facilities and equipment must be adequate for the manufacture and inspection of the products and parts. 9. Outcome of physical facilities inspection. 10. Planning methods must ensure the complete inspection of the in-process product or part up to its completion. 10. Inspection procedures. 11. Inspection sequences must be established and inspections accomplished at intervals where accurate quality determinations can be made. 11. Inspection procedures. 12. Nonconforming products or parts thereof must be segregated and identified to preclude incorporation into the end product or part. 12. MRB and supply quarantining procedures. 3-11 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Essential Elements Evaluation Criteria 14. The degree and timeliness of training that production personnel receive should be commensurate to the skill level necessary to perform the assigned duties. 13. Achievement against Training Plan. 15. The conditions in environmentally controlled areas must be established and maintained through appropriate procedures and calibrated controls. 14. PIS/FIS with particular attention to processes in environmentally controlled conditions. 3-12 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 4. Special Processes Essential Elements Evaluation Criteria 1. All special processes being performed should be covered by appropriate and approved specifications. 1. Procedures for the control of special process characteristics that affect safety. 2. Special process specifications should 2. Procedures that require all special contain inspection/quality assurance process changes to be submitted to criteria that will ensure that all products CASA for evaluation and approval. and parts that are processed and accepted, conform to the particular specification. 3. Current special process specifications should be readily available and be used by operator and inspection personnel. 3. Procedures for special processes to address necessary controls related to personnel qualifications, equipment, and testing methods. 4. Equipment such as tools, gauges, instruments, timers, ammeters, voltmeters, should be readily available and continuously maintained for accuracy. 4. Procedures for the inspection and quality assurance provisions of the special process specification should be approved as part of the quality system data, when applicable. 5. Processes, equipment, and operators should be qualified and approved by the manufacturer in accordance with the specification/manufacturer's procedures. 5. Procedure for the qualification of special processes and the re-testing should changes be implemented. 6. Products and parts should be properly 6. Warehousing and storage procedures. handled throughout the area to prevent damage, contamination, rust, etc. 7. Records should be maintained to accurately reflect compliance with the special process specification requirements. 7. Record keeping and technical data control. 8. The degree and timeliness of training production personnel received is commensurate to the skill level necessary to perform the assigned duties. 8. Training Plan. 3-13 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 5. Non-destructive Inspection Essential Elements Evaluation Criteria 1. Operators should be qualified, and approved by CASA, or by the manufacturer when authorised by CASA. 1. Procedure for training, qualification and periodic re-qualification of personnel. 2. Operators' qualifications must be kept current. 2. Procedure for periodic calibration of test equipment, and validation of processes and materials. 3. The operator must always work to the current, applicable process specifications. 3. Procedure for performance of each NDT method utilised, including use of approved data, and certification of completed NDT inspection together with a record of inspection results. 4. Equipment must be inspected and calibrated periodically to ensure accuracy. 4. Measuring equipment calibration plan. 5. Realistic acceptance criteria must be established. 5. Acceptance check list 6. Inspection acceptance/rejection criteria 6. Acceptance check list. must be established to conform with the current design data. 7. Records must be maintained to accurately reflect compliance with the specification requirements. 7. Data control and test data recording. 3-14 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 6. Tool and Gauge Control Essential Elements Evaluation Criteria 1. All equipment used for inspection purposes must have the degree of accuracy necessary to determine conformity of the characteristic being inspected. 1. (i) Procedures to ensure that calibrations are traceable to national standards recognised by NATA. 2. Tool and gauge controls should include procedures for protecting, maintaining, and updating this equipment as required, to ensure product conformity to approved design data. 2. Procedures that provide adequate instructions for the operation, inspection, and testing of all equipment and tooling used for the acceptance of dimensional characteristics. 3. The quality system should require identification, inspection acceptance and periodic reinspection of all inspection equipment. 3. Procedures that ensure adequate control of tools and gauges including initial approval and periodic inspections. The procedures should define acceptable methods of tool and gauge rework and reinspection. 4. 4. Procedures to ensure quarantine until re-calibration of tools or gauges identified as out of tolerance or of unknown calibration status. Control of inaccurate inspection tools, gauges, instruments, and jigs, must ensure their identification and removal from use until repair, rework, or recalibration has been accomplished. 5. Calibration records must be maintained of all equipment used for inspection purposes. These records should contain the nomenclature, serial number, location, details of all repair or rework accomplished and date next inspection is due. (ii) Measuring equipment calibration plan. 5. Test and inspection results records for each tool at each location. 3-15 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 7. Receiving Inspection/Supplier Control Essential Elements Evaluation Criteria 1. Any holder of a production approval 1. Procedures relative to the who has delegated inspection duties or manufacturer's periodic evaluation, relies on suppliers for controlling surveillance, and control of supplier conformity should ensure by evaluation produced raw materials, purchased and/or surveillance that those suppliers items, parts and assemblies. Purchase are continuously in compliance with his Order documents must be reviewed for approved QC system. accuracy and completeness by an appointed person. 2. Each manufacturer must make information available to CASA regarding all delegation of authority to suppliers to make major inspection of any products/parts thereof. 2. A description of any delegation of authority to suppliers to make inspections or conduct tests of products or parts on behalf of the manufacturer. 3. The manufacturer must advise CASA, in writing, of any authority granted the supplier to ship directly to the user. 3. Procedures for advising CASA of any suppliers performing inspections of products or parts that cannot or will not be completely inspected by the manufacturer. 4. The supplier control function should ensure that all material review actions and design changes taken on supplierfurnished parts and services are approved by the manufacturer, prior to use. 4. Procedures outlining inspection acceptance of raw materials, purchased items, parts and assemblies, including independent verification of material specification. 5. The manufacturer's receiving 5. Procedures to ensure that suppliers inspection function must ensure that all submit all design changes for approval supplier furnished parts/services and are provided with the latest conform to the approved design. applicable revisions to the design data. 3-16 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Essential Elements Evaluation Criteria 6. Procedures to ensure that all incoming 6. The manufacturer's receiving inspection function must ensure that all material is supplied with appropriate documentation or details of verification incoming raw material is properly testing to be carried out. identified by batch, specification and verification test results for the batch to Shelf-life limited materials and products the specification. must have life verified to specification. Parts received under cover of an ARC First article inspection is required on (Form 1/Form 917) and marked parts from a new supplier. ‘Conformity only’, a Statement of Conformity, or equivalent document from a recognised authority would be acceptable in lieu of providing verification test results. If verification test results, an ARC from a CASA approved distribution house or a ‘Statement of Conformity’ from a supplier are not provided, the manufacturer must undertake verification testing to the material specifications. 7. The manufacturer's purchase order or equivalent must reflect the current design data, and the pertinent quality system requirements. 7. Procedures for ensuring inspection acceptance, identification, proper segregation, protection and issuance of product and parts in storage areas, including controls for incorporation of applicable design changes in stored items. 8. Parts that are damaged in transit or parts that are waiting certification must be properly segregated until dis-positioned. 8. Quarantine procedures and facilities. 9. Supplier quality system data, procedures, certificates, reports required for CASA review must be translated to English. 9. Supplier audit procedures. 10. Receiving inspection records must be generated and maintained to establish final conformity of products and parts. 10. Data control procedures. 3-17 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 8. Inspection and Testing Essential Elements Evaluation Criteria 1. The manufacturer must establish and comply with test procedures applicable to products or part design data. 1. Procedures to ensure that the inspection of products or parts will be performed and properly recorded at points in production where accurate quality determinations can be made. 2. For aircraft, the manufacturer must establish and ensure compliance with the approved flight test procedures and flight test check-off form. 2. Procedures to properly perform, control, record, and identify all inspection processes. 3. Test equipment must be controlled and 3. Measuring equipment calibration plan. calibrated to ensure accuracy. 4. Products and parts subjected to adjustment or rework after inspection must be retested to approved test procedures. 4. (i) Procedures that provide adequate instructions for recording information in inspection records. (ii) MRB procedures for review of reworked parts. 5. Where sampling inspection tests are 5. (i) Procedures for the control, used, other inspections and tests issuance, and use of all inspection should be implemented, as required, to stamps, and other in-process ensure the acceptance of only those marking equipment. products or parts that conform to the (ii) Procedures to ensure that the use design data and are safe for operation. of any statistical sampling inspection plan will not result in an unsafe condition in a product or part. 6. Records of all tests conducted must be 6. Technical data control and archiving maintained in accordance with the procedures. manufacturer's approved procedures. 3-18 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 9. Material Review Procedure Note 1: The material review process is only permitted to disposition minor changes to the CASA approved design. A major change to design must be approved by CASA before formal disposition of parts through the MRB. Note 2: Parts from assemblies dis-positioned as ‘Scrap’ may be recovered only if the MRB determines those parts do not contain the identified non-conformances. Essential Elements Evaluation Criteria 7. Except for APMA, ATSOA, Process Approval and a CASR 21.133(2B) PC a MRB must be established and must include representatives from the Inspection and Engineering departments. 1. MRB Procedures including procedures that require corrective action (in-plant, at suppliers, and in-service) where processes or procedures result in a nonconforming product/part thereof. 2. The MRB procedures must outline the complete MRB system including requirements for obtaining CASA engineering approval on any nonconformities to the product/part thereof which constitute a major change to the approved design data, prior to final acceptance of the product or part. 2. A description of the MRB including the procedure for recording MRB decisions and disposing of nonconforming products or parts—that is, use as is, rework, scrap, return to supplier. 3. The MRB procedures must provide controls for identification, segregation, and disposition of nonconforming products or parts. 3. Procedures for the identification and segregation of products or parts set aside for MRB review. 4. As part of the decision recording requirements the manufacturer should list the MRB members present. 4. MRB delegation procedures to a similar standard as the manufacturer when the manufacturer relies upon or delegates MRB duties to supplier facilities. Note: ‘Use as is,’ is not an option unless the design data is changed. 5. Nonconforming products/parts thereof must not be released by MRB until they have been properly dis-positioned and suitable reinspection and retest procedures determined. 5. Procedures for the review of inspection and service records for evaluation and corrective action on repetitive discrepancies. 3-19 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Essential Elements Evaluation Criteria 6. MRB withheld products or parts must be quarantined to prevent their unauthorised removal. 6. Quarantine procedures and facilities 7. The MRB records must as a minimum include part number, quantity, date, adequate description of nonconformance including a determination of major or minor, disposition, and authorised MRB signatures. 7. MRB Minutes of Meetings. 8. The MRB procedures must provide a system for obtaining effective corrective action in-plant, at suppliers or in-service to prevent recurrence. The procedures must provide for monitoring corrective action response, implementation and effectiveness. 8. MRB Minutes of Meetings, in particular records of follow up action. 3-20 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 10. Stores Control Essential Elements Evaluation Criteria 1. The system must ensure that only conforming, accepted and identified products or parts are placed in production storage. Non-conforming items must be suitably identified and quarantined. 1. Procedures for each of the essential element items 1 to 5. 2. The system must ensure that products and parts that are subject to deterioration from prolonged storage are periodically reinspected and dispositioned and controlled. 2. Procedure for the traceability of incoming material, parts and standard parts, including their matching records and certification or specification documents. 3. The system should assure the protection from damage and deterioration of products and parts that are in process or in transit or stored. 3. Procedures to quarantine and identify non-conforming parts, parts awaiting conformity inspection or materials, including those shelf life expired, awaiting MRB disposition. 4. The system must ensure that required design changes are incorporated on products or parts in storage prior to their release. 4. Design change management process. 5. The system must ensure that only those products or parts, identified as having passed company conformity inspection are issued from stores. 5. Design change management process. 3-21 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 11. Certification and Release Essential Elements Evaluation Criteria 1. All engineering data used for the acceptance of the product or part must be CASA approved. 1. Procedures to identify completed products and parts. 2. The product or part must conform to the approved engineering data. 2. Procedures to ensure that all required inspections and tests are satisfactorily accomplished prior to final acceptance of the completed products or parts. 3. All required inspections and tests necessary to ensure that the end product or part conforms to the approved design data and is in a condition for safe operation must be accomplished before the product or part can be certificated as airworthy. 3. Procedures that ensure products or parts are in conformity with approved design data and are in a condition for safe operation. 4. The aircraft, engine, or propeller logbooks and records should have inspections and operating time properly recorded, signed and dated. 4. Procedures to ensure that certifications for completed work are only made by appointed or authorised personnel. 5. Each product or part must be properly identified. 5. Procedure to ensure that the final certification for completion of the manufacture of the product or part is made pursuant to the applicable CASR. 6. 6. Procedures to ensure that the ARC (Form 1/Form 917), or other approved document is properly completed, signed and issued by appointed personnel, and that this document provides traceability for the applicable part. A Statement of Conformity under for “Production under Type certificate Only” must be properly documented, signed, dated, and submitted to CASA. 7. Applications for conformity inspection, Certificate of Airworthiness (CoA) or Special Flight Permit (SFP) issue should be properly executed, signed, and submitted to CASA, or where appropriate, an authorised person. 7. Procedures to ensure that completed aircraft, engines and propellers are released with appropriate Log Books, Instructions for Continued Airworthiness and for aircraft, a Flight Manual. 3-22 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Essential Elements Evaluation Criteria 8. Personnel making final certifications are appointed in the quality system. 8. Procedures to ensure that all pre-CoA issue work on type certificated products is properly certified. For an aircraft, CoA issue or acceptance by CASA of a Statement of Conformity for “Production under Type Certificate Only” marks the end of the production cycle. 9. The system must ensure that before final release, all required ADs are incorporated or accounted for (for aircraft) that all post flight test adjustment has been certified, and the approved flight test completed. 9. Procedures for airworthiness certification of products or parts to be exported, includes appointment of personnel authorised to make such certifications. 10. Persons approving export of products or parts are identified in the quality system and are appropriately authorised. For export approval of aircraft a CASA instrument of authorisation must be held. 10. Relevant delegation for CASA and Industry. 12. Service Difficulty Reporting and Control CASR 21.003 Essential Elements Evaluation Criteria 1. The system should ensure that service problems are investigated and the manufacturer takes corrective actions. 1. Procedures that define the manufacturer's responsibilities and corrective actions relative to service difficulties involving products or parts inplant, or in-service, including spares in storage or shipped to a user. 2. The system should have a means for keeping users of the product or part informed of service difficulties and resultant CASA-approved changes to the type design. 2. Procedure to ensure reporting of failures, defects and malfunctions to CASA as required by CASR 21.003. 3. The system should provide for receiving feedback on service problems from users of the product or part. 3. Continuing airworthiness procedures and plans. ■ 3-23 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3.3.2 CASR 21.123(1), 21.135, 21.303(5), 21.605(4) Stage 2 Quality System Assessment – Quality System Evaluation This stage of the assessment consists of an evaluation of the quality system at the production facilities to determine that the applicant has satisfactorily implemented and is capable of maintaining the required quality system. During this stage inspect parts applicable to the application in order to assess the applicant's ability to produce conforming parts or products. CASR 21.123(1), 21.135, 21.303(5) and 21.605(4) refer. System Assessment An adequately described system is useless if not properly implemented and maintained. The PO must therefore ensure that the manufacturer practices rigid system discipline. CASA does not dictate to a manufacturer the specific manner in which a product will be produced. However, once a manufacturer commits to a specific system that is approved by CASA, the manufacturer is obligated to adhere to every facet of the system without deviation. Whenever a change to the system is necessary, the manufacturer must make the change in accordance with the provisions of his approved system prior to implementation. The following guidelines should be utilised during the course of evaluating a manufacturer's quality system functions: 1. Use the standards described under the Essential Elements columns in the preceding tables—as applicable—as the basis for conducting the evaluation. 2. Use the information detailed under the Evaluation Criteria columns in the preceding tables as an aid in conducting the evaluations of the applicable quality system elements. 3. Be alert to any inadequacies in the system, such as a lack of necessary instructions or procedures, or, more commonly, repetition of regulatory requirements instead of proper procedures. It is virtually impossible during the desk-top review of Section 3.2.2 to determine whether the submitted system complies with all regulatory requirements and provides the necessary safety assurances. Findings When a non-conformance to the design or design data is noted, the PO must continue with the evaluation to determine whether the condition is a symptom of a quality system deficiency or breakdown. When a quality system deficiency or breakdown is indicated, the inspector must evaluate the system to determine the cause. Necessary corrective action must be taken by the applicant to ensure the quality system remains compliant and effective. Stage 3 Quality System Assessment—Manufacturer's Corrective Action refers (see following section). ■ 3-24 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3.3.3 Stage 3 Quality System Assessment—Manufacturer's Corrective Action Before CASA can approve the application, the manufacturer must complete corrective action to address all deficiencies or discrepancies arising from assessment of an initial application or change to an existing system. This stage is completed when the inspector finds that the manufacturer's corrective actions and quality system amendments comply with all pertinent Part 21 requirements and conforming products or parts have been produced following the final form of the quality system submitted for approval. ■ 3.3.4 Manufacturer’s Service Documentation The PAH may need to issue Service Bulletins (SBs), Service Letters or other continuing airworthiness information. CASA only approves the relevant technical content of a Service Bulletin if a SB is required to address an Airworthiness Directive. The PAH is to submit such a proposed SB to CASA for engineering assessment and approval of the technical content in the form of a letter to the PAH authorising the issue of the SB. The PAH is permitted to issue any other SBs or Service Letters etc. without reference to CASA. However, changes to a design must be approved in accordance with the PAH’s Procedures Manual. ■ 3.3.5 Service Difficulty Reports In-service Service Difficulty Reports (SDRs) received by CASA relating to production item issues will be processed in accordance with CASA’s SDR procedures, and referred to the relevant specialists. CAR 50 The PO is to be involved in any follow-up actions (CAR 50). ■ 3-25 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3.3.6 Reporting of Failures, Malfunctions and Defects during Manufacture CASR 21.003(4) The manufacturer does not have to report to CASA all failures, defects or malfunctions that might cause an occurrence (as listed in CASR 21.003 (4)) unless the defective part has left the holder’s control by the time the defect is discovered. CASR 21.003(4) CASR 21.003(10) The manufacturer must report to CASA all failures, defects or malfunctions that have resulted in an occurrence [as listed in CASR 21.003(4)]. However, failures, malfunctions and defects caused by improper maintenance or improper usage, or which have been reported to CASA by another person, may not have to be reported to CASA by the holder. See CASR Sub regulation 21.003(10). Manufacturing errors and irregularities can be rectified. Parts found to be defective by the manufacturer’s quality system can be repaired, scrapped or quarantined. These defects do not have to be reported to CASA if the parts have not left the holder’s control, or can be reliably retrieved. ■ 3.3.7 Supplier Quality Control The last production quality system is that for suppliers. Suppliers may not have a CASA production approval, however, suppliers make up the bulk of the manufacturing effort in producing aircraft, aircraft engines, and propellers. Suppliers are controlled by the PAH that they work for, i.e., PC, Production under TC Only, APMA and ATSOA. Suppliers are not required to have a quality manual, and have no regulatory privileges or responsibilities. However, they may not sell production parts on the open market without their own production approval. ■ 3-26 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3.3.8 Engineering Drawings Drawings reviewed by CASA and used in the conduct of conformity inspections must meet the minimum standards of the CASRs. CASA regulations require that an applicant submit sufficient drawings, special process documents, specifications and test reports to identify and substantiate the product for which CASA approval is sought. CASA reviews this data for minimum compliance with the airworthiness standards. That data is then used for inspecting the product. CASA uses the data to witness a conformity inspection of the product at the applicant’s facility, or at an agreed upon location. Provided all of the drawing requirements have been met, the product is then tested. If the test is acceptable, the product is approved, and the applicant proceeds to manufacture the part/assembly. Once a CASA approval is issued, the drawings used to inspect the original product are considered to be the approved CASA baseline. That baseline never changes unless there is a modification to the drawings after the approval is issued. Any deviations from the drawings for a part or assembly must be documented, dis-positioned, and approved in the same manner as the original drawings were. CASA will accept drawings that meet some recognised drawing standard that can produce a quality part within a minimum tolerance range when the manufactured part has been inspected and tested and has shown to meet the minimum CASR requirements. ■ 3.3.9 Use of CASA Form 1/Form 917 Authorised Release Certificate CAR 42 CAAP 42W2(3) CAR (1988) 42 WA sets out the requirement for Form 1/Form 917, and CAAP 42W2(5) provides guidance as to the use of the form. Manufacturers holding a PA may sign a Form 1/Form 917 to accompany a finished part. However, suppliers to the PAH can only issue some form of conformity statement with clear delivery documents. They are not entitled to issue a Form 1/Form 917. CASR 21.133(2B) For use by the holder of a PC issued for the support activity in Block 12 ‘Remarks,’ add the words “This ARC is issued under the provisions of CASR 21.133(2B).” Additionally, a statement qualifying Block 13 is to be entered in Block 12, “This part is manufactured for certificate of Approval Holder number xxx (or owner/operator by name, as appropriate) per order number yyy. Block 12 ‘Remarks’ should also provide details (S/N or Tail No.) of the aircraft, aircraft engine or propeller. ■ 3-27 Production Approval Procedures Manual 3. Assessment of an Applicant's Quality Systems for Manufacture 3.3 Quality System Assessment Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 3.3.10 Use of CASA Form 1/Form 917 for Unapproved Parts These are parts produced (and to be conformed) to certain controlled design data that has not yet been approved to be part of the Type Design, Usually, these parts are for use in a ground or flight test development or certification program, ie usually a prototype. Neither the manufacturer nor CASA can sign a release for fitment to a certificated aircraft for such a part. However, the manufacturer or CASA (if requested by a foreign NAA) can do the administrative function of signing a Form 1/Form 917 limited to conformity only and referring to the particular controlled data against which the product is conformed. This fulfils the function of communication between NAAs in a standardised form. ■ 3.3.11 Export Airworthiness Approvals A person must be included in the class of persons of the appropriate CASA Instrument of Appointment, to issue a Form 1/Form 917 as an Export Airworthiness Approval. ■ 3-28 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards 4. Version 3.0: July 2011 Inspections 4.1 Conformity Inspections 4.1.1 Introduction to Conformity Inspections This Chapter provides procedures and methods to be followed by the inspector when conducting inspections to determine that parts, appliances and products (aircraft, aircraft engines, propellers or parts) conform to the approved design drawings and specifications. For manufacturing under a PC using the TC as authorised data, Conformity Verification Plans (CVP) are to be established during the pre PCB phase. Conformity to the plan needs to be shown by the PA applicant and verified by CASA during the certification phase, ahead of the issue of a TC, and during the initial production phase to verify that parts and products conform to design data. Once a production approval is issued, Conformity Inspections are conducted to verify that manufacture is in accordance with the approved manufacturing process approved by CASA. ■ 4.1.2 Conformity Inspections The depth of conformity inspections may vary depending on the particular manufacturer. In the case of a manufacturer with well-established policies, quality system procedures, experience, inspection personnel, equipment and facilities and who have previously demonstrated first article acceptability, the inspector may choose to reduce the depth of conformity inspection by a form of sampling inspection of the manufacturer’s product and procedures. In the case of a manufacturer whose ability is unknown—e.g., during the initial production period by a manufacturer producing under a TC only—it will be necessary to conduct in-depth conformity inspections until the inspector is confident that reducing the degree of assessment will not compromise safety. The PO is recommended to use CASA Form 1248 Request for Conformity Inspection as a positive means of documenting those particular inspections required. Inspector 1. Regardless of the manufacturer’s ability, the initial parts or products inspected for conformity for issue of a production approval need to be inspected to a level which confirms conformity to the design data. 2. When the degree of conformity inspection required has been determined, develop an appropriate CVP. The Plan should focus on: ❍ Verifying the conformity of the critical and major characteristics of materials, parts and assemblies 4-1 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards ❍ ❍ ❍ 3. Version 3.0: July 2011 Evaluating process controls to assure production of consistent and uniform products. For other than initial conformity, statistical quality control methods may be utilised for process evaluation. Complete descriptions of such statistical methods should be documented Observing tests of important functional parameters of systems, modules, components and completed products Identifying clearly the responsibilities for “recommending” conformity compliance and for “finding’ conformity compliance for each inspection throughout the initial certification stage and the First Article Inspection Phase. The responsibilities should be identified in the conformity inspection matrix attached to the CVP. Regardless of the manufacturer’s experience, CASA is responsible for verifying that the manufacturer has carried out a complete article conformity inspection and that the results of that inspection are properly recorded, before carrying out the conformity inspection (Refer to 4.1.3). In the case of a manufacturer producing under a TC only prior to the issue of a PIS, CASA holds full responsibility for the conformity inspection and for “finding” conformity compliance. 4. Using the CVP as a guide, record all conformity inspections conducted or tests witnessed on Form 882 CASA Conformity Inspection Record and include all discrepancies, non-conformities and corrective actions. Alternatively, all results can be documented in the matrix to the CVP and attached to the Form 882. 5. Retain these records on the applicable CASA TRIM file. 6. Where design non-conformities or discrepancies are found, forward a copy of the applicable documents to the Manager, Initial Airworthiness, AEB. 4-2 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 7. Address the following issues when undertaking a conformity inspection as described in sections 4.1.4 through 4.1.17 as follows: ❍ 4.1.4 Materials ❍ 4.1.5 Processes and Processing ❍ 4.1.6 Automatic Production Processes ❍ 4.1.7 Non-destructive Inspection (NDI) Method Evaluation ❍ 4.1.8 Critical and Major Characteristics ❍ 4.1.9 Workmanship ❍ 4.1.10 Adequacy of Drawings and Related Change Records ❍ 4.1.11 Adequacy of Inspection Records ❍ 4.1.12 Material Review Action ❍ 4.1.13 Software ❍ 4.1.14 Conformity Inspections of Test Articles ❍ 4.1.15 Structural Test Articles—Aircraft ❍ 4.1.16 Flight Test Articles—Aircraft ❍ 4.1.17 Endurance Test Articles—Engines and Propellers. Should discrepancies be found, you may require the manufacturer to carry out a requalification of the part/product. 8. Following any re-qualification of the manufacturer, carry out a further conformity inspection, considering the previous results as appropriate. ■ 4-3 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards 4.1.3 Version 3.0: July 2011 First Article Inspection (Reference Standard SAE AS 9102.) The purpose of First Article Inspection (FAI) is a physical and functional inspection process commonly used to provide objective evidence that all engineering design and specification requirements are properly understood, accounted for, verified and documented. The first conforming article is intended to be a ‘standard’ that verifies conformance and one that provides a yardstick for corrective actions and problem resolution. FAI shall be performed by the applicant and verified by CASA for a new part representative of the first production run including all detail parts and sub assemblies that constitute the end item ordered. The FAI record is not complete until all non-conformities are resolved. Note: Prototype parts or parts made using different methods or processes cannot be considered part of the first production run unless full .traceability can be shown for the differences between the standard manufacturing processes and the “unique” part manufacturing process.. The FAI requirement applies even after initial production compliance and CASA approval. Depending on the degree to which characteristics are affected partial or complete accomplishment of the FAI is required for the following events: 1. A change of design affecting form, fit or function of the part. 2. A change in manufacturing source(s), processes, inspection method(s), location, tooling or materials with the potential of affecting the form, fit or function of the part. 3. When required as part of a corrective action for a part with repetitive rejection history. (Typically with three repeat rejections). 4. A change in the numerical control program or translation to another media. 5. A natural or man-made occurrence that may adversely affect the process. 6. A lapse in production of two years. All documented FAI reports are considered a quality record under the CASR record keeping requirements. 4-4 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Inaccessible characteristics shall be evaluated as early in the process as possible provided they are not affected by subsequent operations. Naturally, tooling used to verify a design characteristic must be qualified by FAI verification back to national standards. Where feasible, FAI measurement equipment and/or personnel shall be independent of the equipment or personnel utilized for the final product acceptance inspection. It should be noted that where FAI results are near limits of tolerances, additional parts should be inspected to verify hardware conformance. The FAI process for a given part initially includes identification of the original source documents and their respective revision status. Purchase orders or equivalent documents must be examined to determine the basic requirements and the validity of the data called up by the customer. Relevant drawings and specifications must be subject to source substantiation to ensure that the current complete data is available for the inspection. ■ 4.1.4 Materials The following tests are to be conducted: ● ● ● ● Were raw materials used in the fabrication process in conformity with the design data? Is evidence available to assure that chemical and/or physical properties were identified and checked as appropriate? Is there documented evidence to show traceability from the raw material to the completed part? Are there any parts or process deviations recorded against the submitted design data (including material review dispositions)? ■ 4-5 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards 4.1.5 Version 3.0: July 2011 Processes Conformity Production approval regulations require fabrication methods that consistently produce conforming parts and all methods requiring close control to attain this objective must be covered by approved process specifications. In evaluating processes, CASA is primarily concerned with performance and conformity. Process performance should be capable of consistently producing articles that meet the specified requirements. Process conformity is determined by checking the articles being processed to determine that they are being processed in accordance with the process specification and that the materials, tools, and equipment called for are being utilised. Since the end results depend on strict adherence to the process instructions, any deviation or discrepancy should be corrected on the initial runs. Product conformity is determined by inspecting the processed articles. The manufacturer should make a determination that the process operations are capable of consistently producing articles in conformity with the design requirements. The method used in determining this fact should be measurable, as required by the process specification, and recorded. ■ 4-6 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards 4.1.6 Version 3.0: July 2011 Automated Production Processes Background Modern production methods involve many automatic machines such as: ● Milling machines ● Lathes ● Work Centres ● Riveters ● Routers ● Fabric cutters ● Lay-up placers ● Electronic component placers, etc. Traditionally, conformity inspection has been against clearly defined Type Design (TD) data, in the form of drawings and specifications. With numeric- or computer numeric-controlled (NC or CNC) machines, traditional conformity inspections may be difficult due to the non-existence of traditional TD data. In such cases, TD data includes the Computer Aided Design (CAD) models or other programmed (software) instructions which can be used to achieve and demonstrate conformity. Conformity can be evidence that the automatic machine software is performing correctly. Conformity Inspection Requirements CASA must be satisfied that the applicant has the systems and ability to produce conforming parts. CASA should ensure that the applicant has a system in place that ensures that: ● The approved TD data is permanently stored and available for conformity inspections. The TD may be in the form of drawings and specifications or computer generated models or instructions ● Any software used is identifiable as to the package and the version ● Computer programs such as CAD programs used are of proven validity 4-7 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards ● ● ● ● ● ● Version 3.0: July 2011 Operators of CAD programs have demonstrated competencies in the use of the particular CAD package Computer Aided Manufacturing (CAM) programs used are of proven validity Operators of CAM programs have demonstrated competencies in the use of the particular CAM program Operators of NC or CNC machines have demonstrated competencies in the use of the machine(s) Manually-inserted CNC machine instructions are related to approved drawings Conformity is performed against the approved TD data, which may be held electronically. The conformity inspection may be in any form acceptable to CASA that achieves the result, eg; a. Comparison against drawings printed out from the relevant CAD package, or from other approved drawings or sketches. b. Use of calibrated “go” and “no go” gauges developed from the TD data, for specified dimensions. c. Use of a Computer Coordinate Measuring Machine (CCMM) for comparison with the computer-held model. ■ 4.1.7 Non-destructive Inspection (NDI) Method Evaluation The procedure for evaluating an NDI method must provide for the manufacturer to demonstrate to CASA’s satisfaction that the NDI method used has the capability to detect the allowable defect size and location specified by the engineering data, that the inspection results are repeatable, and that instruments required to perform the inspection meet the procedural acceptability requirements. ■ 4.1.8 Critical and Major Characteristics ● ● ● ● Has the manufacturer identified and inspected all the critical and major characteristics? Does the manufacturer have a record of these inspections? Does witnessing the re-inspection and surveillance indicate that the above inspections were accurate and adequate? Are there any deviations recorded against the approved design data (including material review disposition)? ■ 4-8 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards 4.1.9 Version 3.0: July 2011 Workmanship ● ● Does workmanship contribute to the safety of the product? Have criteria been established to identify acceptable production techniques and practices? ■ 4.1.10 Adequacy of Drawings and Related Change Records ● ● ● ● ● ● Can the part be produced and inspected using the information on the drawing? Are drawing tolerances practicable and attainable under production conditions? What evidence supports this? Have all of the changes been correctly made to drawings submitted for CASA approval or MRB approval in the case of minor changes? What procedure is used to ensure the incorporation of an engineering change in the production part, on the relevant drawing/s and on completed parts in store? Does the drawing include all the characteristics necessary to inspect the part, the material to be used, the treatment of the material such as hardness, finish and special process specifications? Does the drawing (or associated engineering data) include applicable test specifications? ■ 4.1.11 Adequacy of Inspection Records ● Do the inspection records show all inspections that are conducted? ● Do they show who conducted the inspection? ● ● Do they indicate the results of the inspection and disposition of unsatisfactory conditions? Are procedures adequate to ensure re-inspection of any parts that are reworked? ■ 4.1.12 Material Review Action ● ● Is the material review procedure documented and adequate to ensure disposition of non-conformities? Is there adequate corrective action for observed non-conformities to prevent recurrence? ■ 4-9 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 4.1.13 Software ● ● ● ● ● ● ● ● Are all software products (version description document, source code, object code, documentation, test procedures, loaded hardware/firmware etc) properly identified, including revision levels, when compared to the hardware and software engineering drawings? Have all software problem reports been properly actioned? Do the records indicate that all software products, including support software and procedures, have been placed under configuration control? Have the verification and acceptance tests been successfully executed to approved test procedures and results recorded? Are there records that indicate that the object code was compiled from released source code by approved procedures? Do records indicate technical acceptance of the software prior to loading into the system or product? Are there any indications of non-compliance with the software manufacturer’s procedures? How is the hardware/software integration managed and how is the hardware ID updated with an update of software? ■ 4.1.14 Conformity Inspections of Test Articles ● ● ● Prior to initiating conformity inspection activity for test articles, it is essential that the manufacturer and CASA establish and document the parameters of the test article configuration and test equipment configuration. The conformity of the test article and test set-up such as for static, endurance, operational, pressure, environmental tests, should be established as appropriate to determine conformity. In all cases, the approved engineering data should include: ❍ Appropriate instructions ❍ Reference to the manufacturer’s agreed test plan. When witnessing tests, CASA should determine that the instructions and test schedule described in the agreed test plan are followed. ■ 4-10 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 4.1.15 Structural Test Articles – Aircraft CASR 21.033 CASR 21.033 requires the manufacturer to allow CASA to perform or witness conformity inspections. This includes structural tests during fabrication and assembly. The final design submitted for CASA inspection must reflect all changes that have been found necessary as a result of previous tests. CASA must ensure that such changes are incorporated into the production drawings. Only then can CASA be certain that subsequent production articles conform to the tested articles. It is strongly recommended, due to the different effects of non-conformities on structural test articles versus flight articles, that parts and assemblies destined for structural testing should be clearly identified. This should be necessary only in those cases where structural test articles are being fabricated concurrently with prototype flight articles. Once parts and assemblies have been subjected to structural testing beyond limit load they must be clearly and permanently identified to prevent their use in production. ■ 4.1.16 Flight Test Articles—Aircraft Determining conformity of flight test articles, including system checks, should begin during fabrication. It is important that flight test articles conform to the data specified in the design data on which the manufacturer’s statement of conformity is based. ■ 4.1.17 Endurance Test Articles—Engines and Propellers In addition to conformity of production, endurance test conformity will also be required. These tests will be part of the CASA approved specifications, and the inspector should coordinate with the CASA engineers before undertaking conformity of endurance tests. CASR Part 33 Part 35 CASR 201.001 At the conclusion of the endurance test, during the teardown inspection, CASA should spot-check conformity of major and critical parts by witnessing the manufacturer’s inspections, paying particular attention to critical characteristics. Teardown inspection of test articles after endurance testing is a specific requirement of CASR Part 33 and Part 35. These activities should be witnessed by a CASA inspector/AWE or a CASR 201.001 appropriately authorised person. The manufacturer should not clean or disassemble the test article until the independent inspector is present, at which time the manufacturer’s inspection should be conducted as follows. 4-11 Production Approval Procedures Manual 4. Inspections 4.1 Conformity Inspections Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Inspector 1. Verify that the manufacturer carefully notes the appearance of subassemblies during the teardown and before complete disassembly. The manufacturer should specifically note any abnormal leakage in valves, seals, fittings, etc.; indication of excessive or lack of lubrication; excessive coking; metal or foreign particles in the oil screens or passages; sticking or breakage of parts; lack of freedom of moving parts; breakaway torques; and any other condition which may not be noticeable after complete disassembly and cleaning. 2. Verify that all parts are thoroughly cleaned and visually inspected for indications of galling, metal pickup, corrosion, distortion, interference between moving parts, and cracks. Highly finished surfaces should be checked for condition and any discolouration due to excessive heat and lack of lubrication. Special attention should be given to bearings, gears, and seals. Engine pistons, cylinder heads, and turbine assemblies should be carefully inspected for indications of cracking, burning or local collapse. 3. Verify that both ferrous and nonferrous stressed parts are inspected for incipient failures by suitable non-destructive testing methods such as magnetic particle inspection, x-ray, penetrant, ultrasonics, in accordance with the test plan. 4. Verify that all parts subject to wear of distortion are dimensionally inspected to determine the extent of change during the test. This may be done by pre-test and post-test dimensional comparisons. The manufacturer should record the results in a suitable manner. 5. On completion of the above steps for certification of an engine or propeller, the manufacturer’s inspection report, verified by the independent inspector, is submitted to the TLM. This report should contain the results of the inspection, giving a comprehensive description of all defects, failures, wear or other unsatisfactory conditions including photographs as required. Since the report is used for evaluation, its importance cannot be overemphasised. 6. Ensure that non-conforming parts are identified and retained by the manufacturer in safe storage for review by CASA. ■ 4-12 Production Approval Procedures Manual 4. Inspections 4.2 Final Inspection and Flight Test Approved by Executive Manager, Aviation Safety Standards 4.2 Final Inspection and Flight Test 4.2.1 Applicability — Final Inspection and Production Flight Test Version 3.0: July 2011 The basic purpose of the ground inspection is to physically determine that the aircraft readied for flight test and therefore ● Conforms with the technical data and ● Is safe for the flight tests intended. The results should be recorded for the project file, together with any other data requested by CASA engineering and flight test personnel. The ground inspection is normally a progressive inspection of parts and assemblies culminating in the aircraft being finally readied for its initial test flight. ■ 4.2.2 Preliminary Ground Inspection Preliminary ground inspection includes all inspections of the first production unit that can be performed satisfactorily in the course of construction. The manufacturer is to notify the CASA inspector whenever changes are made to components, systems, or installations previously cleared. Upon such notification, the inspector is to witness such re-inspections as necessary. ■ 4.2.3 Final Ground Inspection The final ground inspection is the final inspection of the complete aircraft and should be performed just prior to first production flight test. Detailed procedures for conducting inspections and test for the assembled product should be included in the approved production procedures. They should also be coordinated by the manufacturer to preclude unnecessary delays and duplication of effort and to assure that all required inspections and tests are properly accomplished before flight. The PO is to notify CASA flight test personnel when the initial flight test phase is to commence to ensure that flight test personnel have sufficient time to prepare for the flight test program. The manufacturer should provide all necessary assistance, equipment, and data essential for the flight test. 4-13 Production Approval Procedures Manual 4. Inspections 4.2 Final Inspection and Flight Test Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Flight Test and Manufacturing Inspector 1. Carry out the inspection: ❍ Witness the operation of all ground operable systems by the manufacturer’s personnel. ❍ Witness the weighing of the aircraft and verify scale accuracy. ❍ Verify equipment installed, including test equipment, during each flight test to determine flight loadings. ❍ Verify the weight and balance report, showing the actual empty weight centre of gravity together with the list of equipment installed. Retain a copy of these records and make sure flight test personnel have a copy. ❍ If necessary during this phase, verify weights and moment arms of equipment items. 2. Determine what other inspections remain, such as instrument markings, placards, unusable fuel, etc. These inspections must be completed prior to issue of the Statement of Conformity by the manufacturer. ■ 4.2.4 Flight Inspection Manufacturing Inspector (MI) 1. Establish with the Flight Test Pilot a mutually agreeable system for informing the TLM of changes to the aircraft and any problems encountered during flight test. Cooperation with the Flight Test Pilot is crucial to the safe and professional completion of the flight-testing. 2. Prior to the flight test, determine that the manufacturer carries out the various loading conditions specified by the flight test specialist. This includes a determination that the ballast used is accurately weighed, located, and safely secured. 3. Throughout the flight test program, determine that the manufacturer has a plan to ensure that the aircraft is adequately inspected to reveal any unsafe conditions that may develop and to require their correction prior to further flight tests. The frequency and extent of such checks should be coordinated with CASA. Participate in the checks whenever practicable to determine compliance. The MI and the flight test specialist should have a system of informing each other of changes made to the aircraft and problems encountered during any flight test. 4-14 Production Approval Procedures Manual 4. Inspections 4.2 Final Inspection and Flight Test Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Flight Test Pilot The Flight Test Pilot is not to fly a test aircraft without coordinating with the PO to be assured that the aircraft is released for flight. The final acceptance of the test aircraft as it relates to the operation of the aircraft and the integrity of the test is the responsibility of the CASA Flight Test Pilot. Instruments, gauges, recording devices, etc., which are used in the official flight test program for flight, should be in current calibration by a qualified agency and calibration reports furnished. The Flight Test Pilot is to be given copies of the reports prior to flight. ■ 4-15 Production Approval Procedures Manual 4. Inspections 4.2 Final Inspection and Flight Test Approved by Executive Manager, Aviation Safety Standards Blank page 4-16 Version 3.0: July 2011 Production Approval Procedures Manual 5. Sample Letters 5.1 Introduction Approved by Executive Manager, Aviation Safety Standards 5. 5.1 Version 3.0: July 2011 Sample Letters Introduction Contents of this Chapter This chapter includes the following sample letters: 5.2 Sample CASA APMA Approval Letter 5.3 Sample CASA APMA Supplement without Licensing Agreement 5.3.1 5.4 Sample CASA APMA Supplement (Design Approval) Test and Computation Sample CASA APMA Supplement with Licensing Agreement 5.4.1 Sample CASA APMA Supplement (Design Approval) Identicality 5.5 Sample APMA Supplement 5.6 Sample CASA APMA Design Rejection Letter 5.7 Sample ATSO Authorisation 5.8 Sample PIS Approval Letter. 5-1 Production Approval Procedures Manual 5. Sample Letters 5.2 Sample CASA APMA Approval Letter Approved by Executive Manager, Aviation Safety Standards 5.2 Version 3.0: July 2011 Sample CASA APMA Approval Letter File Ref:EF10/999x Trim No xxxx CIVIL AVIATION SAFETY AUTHORITY AUSTRALIAN PARTS MANUFACTURING APPROVAL APMA No: APMA-123456 Mr John Thomas Managing Director Thomas Manufacturing P/L 12 Aviation Street TULLAMARINE VIC. 3043 Dear Mr Thomas, I refer to your APMA application to CASA dated 5 August 2010. In accordance with the provisions of CASR 21.303, CASA has found the design/process data and specifications submitted as design data by Thomas Manufacturing P/L (the Manufacturer) on 5 August 2010 meet the airworthiness requirements of the Civil Aviation Safety Regulations (1998) applicable to the products on which the part(s) is to be installed. Additionally, CASA has determined that the Manufacturer has established the documented Fabrication Inspection System (FIS) required by CASR 21.303(11). The attached Supplement defines the extent of approval given under this APMA and is to be read in conjunction with this approval. Manufacture in accordance with the established Fabrication Inspection System, and the attached Supplement, is approved at the following locations: 12 Aviation Street TULLAMARINE VIC 3043. In accordance with CASR 21.303(9), this APMA is granted to the Manufacturer to produce the part(s) listed in the attached Supplement in conformity with the CASA approved design. This APMA is not transferable and unless suspended, continues in force until cancelled. Subject to due process, CASA may suspend or cancel this APMA by written notice if the holder ceases to comply with the relevant parts of CASR Part 21. This APMA is issued subject to Thomas Manufacturing Pty Ltd complies with all the requirements of CASR Part 21.K. This approval is issued subject to the following conditions: 5-2 Production Approval Procedures Manual 5. Sample Letters 5.2 Sample CASA APMA Approval Letter Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 1. The Manufacturer FIS, methods and procedures provided in Thomas Manufacturing Pty Ltd Quality System Manual Revision 2, dated 30 July 2010 (or later approved revision). 2. The Manufacturers facilities, including suppliers, are subject to CASA surveillance or investigations. Accordingly, the manufacturer must advise any parts/material supplier that their facilities are also subject to CASA surveillance 3. The design/process data listed on the supplement enclosed with this letter of approval is to be considered as approved data. This data is not to be altered by the manufacturer unless permitted or approved by CASA. 4. The manufacturer must report to CASA Manufacturing Section within 3 working days, all information concerning service difficulties on any part produced under this approval, in addition to failures, malfunctions and defects to be reported in accordance with CASR 21.003. 5. The manufacturer must perform a full First Article Inspection (FAI), or a partial FAI for the affected characterises, when there is a lapse in production of two years for any item listed in the APMA Supplements. 6. The Manufacturer must allow CASA to make any inspections and tests necessary to determine compliance with the applicable requirements of CASR Part 21 Subpart 21.K Yours sincerely, {Signed} Delegate of CASA Date of original issue: 30 September 2010 Attachment: APMA Supplement 5-3 Production Approval Procedures Manual 5. Sample Letters 5.3 Sample CASA APMA Supplement without Licensing Agreement Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 5.3 Sample CASA APMA Supplement without Licensing Agreement 5.3.1 Sample CASA APMA Supplement (Design Approval) Test and Computation Australian Parts Manufacturing Approval Supplement No. 001 Australian Parts Manufacturing Approval No. APMA-123456 Dated: 30 September 1999 To: Thomas Manufacturing P/L 12 Aviation Street, TULLAMARINE, VICTORIA 3043 APMA Replacement Part: Part Name: For Installation on: Part P/N: Replacement for Part P/N: Design Data: Approval Means: Licence Agreement: Spring General Aircraft Models THOMAS 7654321 Bendix BS 89 Drawing No 7654321 Rev 1 Test and Computation Nil APMA Supplement Revision: 0 Yours faithfully, {Signed} Delegate of the Civil Aviation Safety Authority. 5-4 Production Approval Procedures Manual 5. Sample Letters 5.4 Sample CASA APMA Supplement with Licensing Agreement Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 5.4 Sample CASA APMA Supplement with Licensing Agreement 5.4.1 Sample CASA APMA Supplement (Design Approval) Identicality APMA Production Approval Supplement No. 001 Australian Parts Manufacturing Approval No. APMA-654321 Dated: 14 December 1998 To: Thomas Aircraft Interiors, Inc., 12 Aviation Street, TULLAMARINE, VICTORIA 3043 APMA Replacement Part: Part Name: For Installation on: Eligibility: Part P/N: Replacement for original P/N: Design Data: Design Approved: Approval Means: Licensing Agreement: Galley ACE Aircraft Model 700 ACE Aircraft Model 700, S/N 123 and up S101001-101 S101001-301 101001-101 101001-301 Interior Inc STC, drawings per licensing agreement Interior Inc. FAA STC No xxxx Identicality License agreement between Thomas Aircraft Interiors and Interiors Inc. Refer Thomas File No 04/8888 FAA STC No. NN12345 Holder : Interiors Inc. 12 Main Street, Los Angeles Airport, CA 900012, USA APMA Supplement Rev 1 Yours faithfully, {Signed} Delegate of the Civil Aviation Safety Authority. 5-5 Production Approval Procedures Manual 5. Sample Letters 5.5 Sample APMA Supplement Approved by Executive Manager, Aviation Safety Standards 5.5 Version 3.0: July 2011 Sample APMA Supplement AUSTRALIAN PARTS MANUFACTURING APPROVAL SUPPLEMENT Manufacturer Thomas Manufacturing Pty Ltd 12 Aviation St Tullamarine Victoria 3045 Approved Location(s) 747 Mackay Ave. Bowenmango QLD. 4108 Part Name Part Number Battery Kit 1 A123 Battery Kit 2 A125 Spacer Block A126-1 Battery Tray A126-2 L/H Support Bracket A126-3 Approved Replacement for Part Number(s) See STC NN555 APMA No: APMA-599999 Supplement No: 001 ARN: 599999 Date: 30 September 2004 Approval Basis Approved Design/Process Data Make Eligibility Model Eligibility Identicality per STC NN555 Anstrom Unitsia 204 Series A126-4 End of Listing (Signed) Delegate of the Civil Aviation Safety Authority. 5-6 Production Approval Procedures Manual 5. Sample Letters 5.6 Sample CASA APMA Design Rejection Letter Approved by Executive Manager, Aviation Safety Standards 5.6 Version 3.0: July 2011 Sample CASA APMA Design Rejection Letter Ref File 04/12345 Trim No. XXX To: Thomas Aircraft Interiors, Inc., 12 Aviation Street, TULLAMARINE, VICTORIA 3043 14 December 1998 I refer to your APMA application dated 01 November 1998 CASA has reviewed the data you submitted. CASA does not find that compliance with the regulatory requirements for APMA has been demonstrated. Non-compliance in relation to CASR 21.303(3) was found in the following areas: The design data was not found to be compliant with the corresponding end product Type Certificate design standard or for ‘Identicality’, Or The design data was not found to be identical with the corresponding replacement part data. The data you submitted is enclosed. Yours faithfully, {Signed} Delegate of the Civil Aviation Safety Authority. 5-7 Production Approval Procedures Manual 5. Sample Letters 5.7 Sample ATSO Authorisation Approved by Executive Manager, Aviation Safety Standards 5.7 Version 3.0: July 2011 Sample ATSO Authorisation Ref: 04/12345 Trim No. XXX Avia Belts Pty. Ltd. PO Box 578910 Numpytown Qld 4896 For Attention: Mr D Samuelson Subject: Avia Belt Restraint Harness Technical Standard Order C114 Dear Sir, This Letter of Approval refers to your application, dated 01 May, 2003, requesting an Australian Technical Standards Order Authorisation (ATSOA) for your restraint harness Part Number ABPL 5-A1. Based on the data presented and your statement certifying that the article meets in full the minimum performance standards of TSO C114 as applicable, and the requirements of Civil Aviation Safety Regulations Part 21, Subpart O, authorisation is granted. Effective from the date of this authorisation you are authorised to manufacture the restraint harness P/N ABPL 5-A1 and mark the articles with the identification marks required in CASR 21.607(c) and, if applicable, any additional marking requirement. All ATSO articles must be manufactured at the authorised location in accordance with the Avia Belts Pty. Ltd. ATSOA Quality Assurance and Procedures Manual, Initial Issue dated 27 July, 2003 or later CASA-approved revision. Revisions must be passed to CASA for review before implementation. Your production authorisation methods, and procedures documented in the approved quality system manual, together with the manufacturing facilities, are subject to CASA audit or investigation. As CASA does not separately approve suppliers, you should advise any suppliers or contractors that their facilities and processes are also subject to CASA audit in assuring CASA your system is being properly maintained. The authorised design data may be changed, however the requirements of CASR 21.611 apply. Minor design changes must be forwarded to CASA at intervals not exceeding six months. Major design changes require a new ATSOA application to CASA. You are required to report to CASA information in the detail and to the timeframe required by CASR 21.003, all defects, failures and malfunctions in any parts produced, or in processes authorised under this ATSOA. Reports are to be forwarded to your CASA controlling office. 5-8 Production Approval Procedures Manual 5. Sample Letters 5.7 Sample ATSO Authorisation Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 The production location is identified as: 9 Markus Street, Numptytown QLD 4896 This authorisation is not transferable to another location or person and continues in force until it is surrendered, suspended or cancelled. Subject to due process, CASA may suspend or cancel this ATSOA by written notice if the holder ceases to comply with the relevant parts of CASR Part 21. Parts, appliances or services furnished by any suppliers located in a foreign country may not be used in the production of any ATSOA article unless: a) That part or service can and will be completely inspected for conformity at the authorised manufacturer’s Australian facility; or b) CASA has determined that the supplier’s location places no undue burden upon CASA in administering the applicable airworthiness requirements; or c) The parts/services furnished by the foreign supplier are produced under the provisions of an Australian Bilateral Airworthiness Agreement or Bilateral Aviation Safety Agreement, and approved for import to Australia in accordance with CASR 21.502. Should you cease to manufacture the subject ATSO article, you are required to send to CASA copies of the complete and current technical data file for the article including design drawings and specifications in accordance with CASR 21.613(1)(a). This ATSOA is a design and manufacturing authorisation, not an installation approval. Therefore, to address end user/installer responsibilities and in accordance with the applicable TSO requirements, the following text must be supplied with each article: “The conditions and tests required for ATSO approval of this article are minimum performance standards. It is the responsibility of each person intending to install the article on or within an aircraft to determine that the conditions in which the article will be installed are not more onerous than those specified in the ATSO. The article may only be installed in accordance with installation data approved by CASA or an appropriately authorised person.” Yours faithfully, Delegate of the Date issued: ……………….. Civil Aviation Safety Authority 5-9 Production Approval Procedures Manual 5. Sample Letters 5.8 Sample PIS Approval Letter Approved by Executive Manager, Aviation Safety Standards 5.8 Version 3.0: July 2011 Sample PIS Approval Letter Ref: 04/12345 Trim No. XXX Avia Belts Pty. Ltd. PO Box 578910 Numpytown Qld 4896 Dear , Production Inspection System Approval Your production inspection system established and maintained at {facility address} has been evaluated and found to be in compliance with CASR 21.125. You are now authorised to produce the following Aircraft/Engines/Propellers and their associated parts in compliance with the requirements contained in CASR Part 21, Subpart F, and in conformity with the type design data forming the basis for the following type certificate(s): Type Certificate Make Model Subject to due process, CASA may cancel this approval by written notice if the holder ceases to comply with the relevant parts of CASR Part 21. 1. The Manufacturer must manufacture all products and parts in accordance with the documented …(Manufacturer’s name) … Approved Production Inspection System manual, Revision …, dated ……….., or later CASA approved revision. 2. The Manufacturer’s Production Inspection System, together with the Manufacturer’s facilities, are subject to CASA audit or investigation. As CASA does not separately approve suppliers, the Manufacturer must advise any suppliers or contractors that their facilities and processes are also subject to CASA audit in assuring the Manufacturer’s system is being properly maintained. 3. Changes to the approved Production Inspection System that affect inspection or conformity to the design data are considered major changes. CASA must be advised in writing of the changes within 2 days of implementation. Product or parts produced between the time the change is implemented and CASA evaluation of the change must be quarantined until released by CASA. 4. Relocation, or expansion of the manufacturing facilities to include new facilities, must be notified to CASA in writing within 10 days of the date the relocation or expansion takes place. Product or parts produced between the dates the relocation or expansion takes place and CASA evaluation of the changes effected in the manufacturing facility, must be quarantined until released by CASA. 5. Products and parts produced under this approval must be permanently marked with identification in the detail required by CASR Part 21, Subpart Q. 5-10 Production Approval Procedures Manual 5. Sample Letters 5.8 Sample PIS Approval Letter Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 6. CASR 21.003 requires the Manufacturer to report to CASA information in the detail and to the timeframe required by CASR 21.003, all defects, failures, and malfunctions in any parts produced, or in processes approved under this approval. 7. The Manufacturer must make available to CASA, on request, information concerning suppliers who furnish parts or services including: a. b. c. d. e. f. g. h. i. 8. A description of the part/s including part name, and part number, Where and by whom the part or service will be inspected, Any delegation of inspection functions to the supplier, Any delegation of material review functions to the supplier, Name and title of the company contact at the supplier facility, Inspection procedures required to be implemented by the supplier Results of the manufacturer’s internal evaluation, audit and surveillance of suppliers, Related purchase and work orders Feedback relative to service difficulties originating from the manufacturer’s suppliers. Parts, appliances or services furnished by any suppliers located in a foreign country may not be used in the production of any product under this approval unless: a. That part or service can and will be completely inspected for conformity at the Manufacturer’s Australian facility; or b. CASA has determined that the supplier’s location places no undue burden upon CASA in administering the applicable airworthiness requirements; or c. The parts/services furnished by the foreign supplier are produced under the ‘components’ provisions of an Australian Bilateral Airworthiness Agreement or Bilateral Aviation Safety Agreement, and approved for import to Australia in accordance with CASR 21.502. 9. All technical data required for the parts to be produced under this approval, must be readily available to CASA at the facility at which the parts are being produced. CASR 21.123(1)(b) 10. CASA must be notified within 10 days if the Manufacturer’s address shown in this approval changes. Yours faithfully, {Signed} Delegate of CASA Date issued: ……………….. 5-11 Production Approval Procedures Manual 5. Sample Letters 5.8 Sample PIS Approval Letter Approved by Executive Manager, Aviation Safety Standards Blank page 5-12 Version 3.0: July 2011 Production Approval Procedures Manual 6. Definitions Approved by Executive Manager, Aviation Safety Standards 6. Version 3.0: July 2011 Definitions Term Definition AC Advisory Circular Act Civil Aviation Act 1988 as amended Aeronautical Product Any part or material that is, or is intended by its manufacturer to be, a part of or used in an aircraft, unless excluded by the regulations. APMA Australian Parts Manufacturer Approval. It is a design and production approval document issued to the applicant by CASA. This would normally be accompanied by an APMA Supplement, which specifies the limit of design and production approval. Appliance Any instrument, mechanism, equipment, part, apparatus, appurtenance, or accessary, including communication equipment that is used or intended to be used in operating or controlling an aircraft in flight, is installed in or attached to the aircraft and is not part of an airframe, engine or propeller. Applicant Person who applies to engage in an activity for which a Production Approval is required. ARN Aviation Reference Number – a unique number issued by CASA to an industry participant. Article A part or component manufactured under an ATSOA for use on type certificated products. Associate Facility A facility that has been approved as an addition to an original production approval. The address must be listed in the PLR or APMA Appendix. ATSO Australian Technical Standard Order: the minimum performance standard for specified articles. ATSOA Australian Technical Standard Order Authorisation is a CASA design and production authorisation issued to a specific manufacturer of an article which has been found to meet or exceed a specific Australian Technical Standard Order (ATSO) performance standard. The ATSOA does not confer installation authority. The installation of the article must be separately approved as part of the type design of a type certificated product. Authorised Person A person authorised under an Instrument of Authorisation to exercise a power in a specific provision of CASR or CAR where the term ‘authorised person’ appears. The authorisation is specific to the legislative provision. MI Manufacturing Inspector 6-1 Production Approval Procedures Manual 6. Definitions Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Term Definition BAA Bilateral Airworthiness Agreement BASA Bilateral Aviation Safety Agreement CAO Civil Aviation Order CAR Civil Aviation Regulations 1988 Certificate Management The ongoing audit function carried out by CASA following the issue of a production approval. CASR Civil Aviation Safety Regulations 1998 CIR Conformity Inspection Record – Form 882 Critical A term applicable to parts, appliances, characteristics, processes, maintenance procedures, or inspections which, if they fail, are omitted, or are non-conforming, may cause significantly degraded airworthiness of the product during takeoff, flight, or landing. Delegate A person authorised under an Instrument of Delegation to exercise the power of a specific CASR or CAR. Design Data Consists of all drawings and specifications, which may be summarised on a master drawing list, that are necessary to show the configuration of the part, and all information on dimensions, tolerances, materials, processes, and procedures necessary to define all characteristics of a part as well as the Airworthiness Limitations Section of the Instructions for Continued Airworthiness. It also includes analysis, technical reports and other related data. FAA Federal Aviation Administration of the USA FAR Federal Aviation Regulation of the USA FIS Fabrication Inspection System ICAO International Civil Aviation Organisation Life Limited Part Any part which has an established replacement time, inspection interval, or related procedure specified in the Airworthiness Limitations section under CASRs 21.50, 23.1529, 25.1529, 27.1529, 29.1529, 31.82, 33.4, and 35.4 or under an ATSOA or APMA. Manufacturer A person producing duplicates of a product, part, appliance or article. MRB Material Review Board NATA National Association of Testing Authorities NAA National Airworthiness Authority 6-2 Production Approval Procedures Manual 6. Definitions Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Term Definition PAH Production Approval Holder: the holder of a PC, APMA, ATSOA or other special manufacturing approval, who controls the design and quality of a product or part. PC Production Certificate PCB Production Certification Board: a panel of CASA specialists acting under the direction of a chairperson for the purpose of determining the eligibility of the holder of a TC, STC or licence for issue of a complex production approval. PIS Production Inspection System PLR Production Limitation Record – a schedule attached to, and forming part of a PC, that lists the limits of production approved under the PC. Production Manufacture of aircraft, aircraft engines, propellers and parts, including control of materials and processes used in the manufacture. Project Officer The CASA officer responsible for the coordination and management of the production approval application. QS Quality System: the total network of administrative and technical data and detailed procedures required to control the product and parts to specified airworthiness standards. It also denotes inspection systems in regard to holders of an APMA or an organisation manufacturing under a TC only. RCA Request for Corrective Action Special Process A process where the results cannot be readily verified by subsequent inspection and testing, and where processing deficiencies may become apparent only after the product is in use. Such processes shall be carried out by qualified operators, and require continuous monitoring and control of process parameters to ensure that the specified design requirements are met. Standard Part An item manufactured in complete compliance with an established government or industry-accepted specification that includes design, manufacturing, and uniform identification requirements. The specification must include all information necessary to produce and conform the part. The specification must be published so that any party may manufacture the part. Examples include, but are not limited to, National Aerospace Standards (NAS), Army-Navy Aeronautical Standard (AN), Society of Automotive Engineers (SAE), SAE Aerospace Standard (AS), Military Specification (MS), (RTCA). Supplier Any person who furnishes parts or related services (at any tier) to the production approval holder manufacturing an aeronautical product or part. Supplemental Type Certificate Type Certificate STC TC 6-3 Production Approval Procedures Manual 6. Definitions Approved by Executive Manager, Aviation Safety Standards Blank page 6-4 Version 3.0: July 2011 Production Approval Procedures Manual Revision History Approved by Executive Manager, Aviation Safety Standards Version 3.0: July 2011 Revision History Note: The Revision History shows details of the most recent version first, followed by information about previous versions. Version Date Part/Section Details 3.0 July 2011 All Complete manual revised. 2.2 November 2010 Table of Contents Added Preface. 2.1 February 2010 All Minor changes to reflect Organisational changes as of October 2009 (restructure, realignment and renaming of roles). 2.0 August 2004 All Complete manual revised. New Form 1248 Request for Conformity Inspection introduced. Form 1143 Australian Parts Manufacturing Approval Supplement (Landscape version) introduced. (Form 1142 remains as Australian Parts Manufacturing Approval Supplement (Portrait version). Form 1148 Name of Part and Technical Standard (Letter) introduced. 1.1 September 2003 2.2.4 Production Certificate (Form 737) and Production Limitation Record (Form 002) introduced. As a result section 2.2.4 amended, in particular subsection entitled Issuing the PC and Production Limitation Record (PLR): Three introductory paragraphs and a new subsection Certificate Numbers added (pages 2-14 to 2-15) Sample Production Approval Templates included (pages 2-18 to 2-19) 1.0 May 2000 4.1.5 New section Automatic Production Process inserted and remaining sections renumbered. This necessitated a change in section 4.1.2, list item 7 under ‘Inspector’ to insert the new section 4.1.5. 5.2 APMA Approval Letter revised. All New manual RH-1 Production Approval Procedures Manual Revision History Approved by Executive Manager, Aviation Safety Standards Blank page RH-2 Version 3.0: July 2011