PLANNING BRIEF PROJECT NAME: Ngan Kwong Wan Road West Date of Preparation: NOV 29, 2013 1. Site Particulars Current Proposal 1.1 District Location Remarks Islands 1.2 Site Location Mui Wo Fringe 1.3 Site Area 1.3.1 Gross Site Area (approx) (ha) 0.74 Subject to detailed survey. 1.3.2 Net Site Area (approx) (ha) 0.74 Subject to detailed survey. 1.4 Existing Land Use Vacant 1.5 Existing Zoning 1.6 Existing Land Status R(A) The site has been rezoned from "G/IC" to "R(A)" on the draft Mui Wo Fringe Outline Zoning Plan No. S/IMWF/9 gazetted on 18.10.2013. Government Land 2. Development Parameters Current Proposal 2.1 Proposed Housing Type HOS 2.2 No. of Flats Proposed 500 A +/- 10% variation is allowed for flexibility at the design stage. 1,540 Based on average household size of 3.08. 3.6 In accordance with the OZP. 26,460 Subject to detailed survey of the site area. 55mPD (maximum) Based on the design requirements of the development as stated in Item 4.3 below. 2.3 Design Population (approx) Remarks 2.4 Maximum Plot Ratio 2.4.1 Domestic and Nondomestic Plot Ratio 2.5 Maximum Gross Floor Area (GFA) 2.5.1 Domestic and Nondomestic GFA (sqm) 2.6 Maximum No. of Storeys or Building Height in mPD 1 3. Planning Requirements Provision in accordance with HKPSG HKPSG Standards Current Proposal Remarks 3.1 Open Space (sqm) 3.1.1 Local Open Space (sqm) 1 sqm person per 1,540 not less than 1540 sqm 3.2 Recreation Facilities (no.) 3.2.1 Badminton Court 1 per persons 8,000 0.19 0 3.2.2 Basketball Court 1 per 10,000 persons 0.15 0 3.2.3 Table Tennis Table 1 per persons 7,500 0.2 0 3.2.4 Children's Play Area (sqm) 400 sqm per 5,000 persons 123 not less than 125 sqm No set standard - 3.3 Greening 3.3.1 Green coverage (% of Gross Site Area) 3.4 Parking Facilities (no.) not less than 20% To promote estate greening, it is targeted to achieve a greening coverage of 30% (20% minimum), half of which will be provided atgrade and a minimum of 3 trees per 100sqm to the total green coverage. Based on the Departmental Circular No. 2/2012 on Interim Parking Standards for the New Home Ownership (HOS) 2 3. Planning Requirements Provision in accordance with HKPSG HKPSG Standards Current Proposal Remarks Projects issued by the Transport Department on 14 February 2012. 3.4.1 Car Parking (Domestic) 1 private car parking space per 13 to 19 flats for New HOS outside 500m radius of rail station 26 to 38 33 Based on 1 space per 15 flats; including one car parking space for the disabled. 3.4.2 Car Parking (Visitor) 2 to 3 visitor parking spaces per residential block 4 to 6 4 Based on 2 spaces per residential block. 3.4.3 Motorcycle Parking 1 space 110 flats per 5 5 3.4.4 Loading/Unloading (domestic) 1 bay residential block per 2 2 3.4.5 Bicycle Parking 1 per 7.5 flats for projects within 2km of existing or planned cycle tracks, subject to adjustment to take account of local circumstances, in particular safety consideration in the area 67 67 4. Technical Considerations/Constraints Current Proposal 4.1 Environmental 4.1.1 Noise EAS is not required for the proposed HOS 3 Remarks 4. Technical Considerations/Constraints Current Proposal Remarks development as agreed with EPD. 4.1.2 Air EAS is not required for the proposed HOS development as agreed with EPD. 4.1.3 Pedestrian Wind Environment Building separation is provided as far as practicable for better air ventilation. No insurmountable problem is envisaged. Based on the microclimate study results, the wind environmental performance of the proposed development is acceptable. 4.2.1 Drainage and Sewerage No insurmountable problem regarding stormwater drainage is anticipated. Timely implementation of the mitigation measures can ensure the residue impacts would be acceptable for discharging sewage into the public sewerage system. HD has commissioned DSD, under Head 711 funding, to carry out SIA for submission to EPD for vetting and endorsement. 4.2.2 Water Supply No insurmountable problem is envisaged. 4.2.3 Electricity, Telephone, Gas No insurmountable problem is envisaged. Town Gas is not available. A LPG centralised gas compound will be built within the site. 4.2.4 Quantitative Risk Assessment Quantitative Risk Assessment (QRA) is required to assess the development proposal against the risk of chlorine leakage in relation to the transport, storage and handling of chlorine at the Silver Mine Bay Water Treatment Works (SMBWTW). EPD has reviewed the QRA report with no further comment. No insurmountable risk is envisaged. The QRA Report was submitted to EPD for review on 24.7.2013. EPD raised no objection to the Report. It is now under circulation by CCPHI for endorsement. 4.2.5 Roads/Traffic Improvement No insurmountable problem is envisaged. The TIA report was submitted to TD for comment on 10.9.2013. Results indicated that the existing junctions have no problem to cope with the additional traffic. 4.2.6 Geotechnical Requirement No insurmountable problem is envisaged. 4.2 Infrastructure 4.3 Urban Design, Visual and Landscape Domestic block with stepped height profile and set-back from the river front. Quality landscaped areas will be provided with a greening ratio target of 30% (20% minimum). 4 At least 50% will be provided at-grade; to provide a minimum of 3 trees per 100sqm to the 4. Technical Considerations/Constraints Current Proposal Remarks total green coverage and a green buffer around the site boundary where feasible. The Sustainable Building Design Guidelines would be taken into account by HD at the detailed design stage. 5. Development Programme Current Proposal 5.1 Foundation Commencement Date 2014/2015 5.2 Building Completion Date 2017/2018 Remarks 6. Attachments 6.1 6.2 Location Plan Development Concept Plan Notes: 1. NET SITE AREA (NSA): In accordance with the Hong Kong Planning Standards and Guidelines (HKPSG), the NSA should exclude: (a) district and public open space, public recreation facilities, free-standing schools and community facilities (including those on the podium), open-air public transport terminal / interchange; (b) internal roads; and (c) natural vegetated slopes and man-made slopes (for the latter, except slopes regraded to form developable area). 2. NUMBER OF FLATS AND DESIGN POPULATION: To allow flexibility in the design, ±10% adjustment will be allowed for the number of flats and design population together with corresponding adjustments to ancillary facilities in line with HKPSG or the requirements of client departments. If a project remains within the 10% allowance, no revision to PB and no re-submission to DipCon is necessary subject to no adverse comments from client departments on the corresponding adjustments to ancillary facilities. 3. GROSS FLOOR AREA (GFA): Covered public transport terminal/interchange should be accountable for GFA calculation. 4. PLOT RATIO (PR): PR should be calculated on the basis of net site area. 5. MAXIMUM GFA, PR AND NUMBER OF STOREYS OR BUILDING HEIGHT: OZP restrictions have to be specified under the Remarks column. The maximum GFA, PR and No. of storeys or building height for the current proposal should be based on the optimal development intensities of the site with reference to relevant planning studies or proposal by PlanD, or HD, with justifications instead of blanket adoption of the maximum development restrictions stipulated in the OZP. 5 6. MAXIMUM NUMBER OF STOREYS OR BUILDING HEIGHT in mPD: Should there be variations in height limits across the site, the different maximum heights in mPD at main roof level or number of storeys permitted should be indicated on a plan. 7. PLANNING REQUIREMENTS: The District Planning Officer will check compliance with the HKPSG where appropriate. 8. SOCIAL WELFARE AND COMMUNITY FACILITIES: District and territorial welfare/community facilities are determined by client departments (SWD, HAD, etc) and any site area involved in free standing facilities should be excluded from site area for PR calculation. 9. RETAIL AND COMMERCIAL FACILITIES: HD will determine the amount of retail floor space required in the development. 10. PEDESTRIAN WIND ENVIRONMENT: HPLB / ETWB Joint Technical Circular No.1/06 on Air Ventilation Assessments to be referred, if appropriate. 11. DEPARTMENTAL COMMENTS: Following circulation, a summary of comments with responses should be included in the appendix for submission of the draft planning brief for endorsement by DipCon. Prepared by Planning Section, Housing Department 6 *** End of Report ***