To move a building from within City limits, to outside City limits, the following STEPS
must be taken before the move can take place:
1. Either a removal permit or both removal and demolition permits must be obtained. Only a
removal permit is required if no demolition will be required after the building is moved off
the site – check off the “Removal” box on the RESIDENTIAL BUILDING PERMIT
APPLICATION. Both a permit for the removal and a demolition permit are required if the
building’s foundation is to be demolished after the building is moved off the site. In the
case where a demolition permit is also required, the following must be filled out:
a. REQUEST FOR DEMOLITION PERMIT form. Follow the steps to obtain a
demolition permit that are included on the form.
b. DECLARATION OF INTENT. This form is usually filled out by the demolition
contractor, and provides information about where material that is removed from
the demolition site will be hauled. The completed form must be attached to the
Request for Demolition Permit Application. See the Declaration of Intent
Information Sheet for detailed instructions on how to fill out this application.
2. Approval to move the building must be obtained in order for the building to be moved
within the City limits. To obtain this approval, an APPLICATION TO MOVE A BUILDING
form (legal-sized) must be filled out and returned to Building Standards. A licensed
building mover is required to perform building moves within the City limits. The building
mover usually fills out this form as there are many City divisions/utility company approvals
that must be obtained and the licensed building mover’s expertise will facilitate completion
of this form and obtaining the approval. The building mover is also required to post a
Performance Bond with Transportation and Utilities, Traffic Engineering Section before a
building move approval can be obtained. See items 10, 12, 13 & 14 on the BUILDING
MOVE PROCESS INSIDE CITY LIMITS handout’s NOTES section.
Updated 16/07/2014
BUILDING STANDARDS
rd
222-3 AVE NORTH, SASKATOON, SK S7K 0J5
BUILDING MOVE PROCESS TO OUTSIDE CITY LIMITS
APPLICATION TO MOVE A BUILDING
Date of Application
Building Owner
Telephone
Type of Building to be moved:
From
To
Lot
Lot
Loaded Building Height
Width
Building Mover
Blk
Blk
Plan
Plan
Length
Telephone
Route to be Taken
Special Remarks
*NOTE: This box must be completed by the Building Standards Division before scheduling a building move
Building Standards
Building Permit #(s)
Date
Approval Signature and Remarks
rd
Issued
3 Floor South, City Hall
306-975-3236
Statement of Taxes:
Sewer and Water Cut-Off Number:
To Be Completed By Divisions Listed (if required)
DEPARTMENT
APPROVAL
Traffic Planning and Operations
In all cases
3rd Floor North City Hall
975-2640
Saskatoon Police Services
76 25th Street East
975-2360
Parks Division
1101 Avenue P North
975-2537
Saskatoon Light and Power
322 Brand Road
REMARKS
In all cases
In all cases
975-2414
Only if loaded building height exceeds
5.25 meters
Electronics Shop, Municipal Eng. Traffic
Lights
14 – 450 Ontario Avenue
221-6463
SaskPower
1370 Fletcher Avenue
934-7750
In all cases
SaskEnergy
408 36th Street East
975-8515
SaskTel
210 103rd Street East
931-5411
Only if natural gas connections/lines
are involved or if necessary to locate
gas lines
Only if loaded building height exceeds 4
meters
Shaw Cable
2326 Hanselman Ave
665-3721
Only if loaded building height exceeds
5.25 meters
In all cases
Statement of Taxes
Sewer and Water Cut-off Number
I agree to abide by and observe all City by-laws and undertake to indemnify the City against any and all
manner of action or actions, cause or causes of actions, sums of money, claims and demands whatsoever at
the law or in equity which may arise by reason of the within removal.
Signature of Owner or Authorized Agent