BUILDING STANDARDS rd 222-3 AVE NORTH, SASKATOON, SK S7K 0J5 BUILDING MOVE PROCESS OUTSIDE CITY LIMITS To move a building from within City limits, to outside City limits, the following STEPS must be taken before the move can take place: 1. Either a removal permit or both removal and demolition permits must be obtained. Only a removal permit is required if no demolition will be required after the building is moved off the site – check off the “Removal” box on the RESIDENTIAL BUILDING PERMIT APPLICATION. Both a permit for the removal and a demolition permit are required if the building’s foundation is to be demolished after the building is moved off the site. In the case where a demolition permit is also required, the following must be filled out: a. REQUEST FOR DEMOLITION PERMIT form. Follow the steps to obtain a demolition permit that are included on the form. b. DECLARATION OF INTENT. This form is usually filled out by the demolition contractor, and provides information about where material that is removed from the demolition site will be hauled. The completed form must be attached to the Request for Demolition Permit Application. See the Declaration of Intent Information Sheet for detailed instructions on how to fill out this application. 2. Approval to move the building must be obtained in order for the building to be moved within the City limits. To obtain this approval, an APPLICATION TO MOVE A BUILDING form (legal-sized) must be filled out and returned to Building Standards. A licensed building mover is required to perform building moves within the City limits. The building mover usually fills out this form as there are many City divisions/utility company approvals that must be obtained and the licensed building mover’s expertise will facilitate completion of this form and obtaining the approval. The building mover is also required to post a Performance Bond with Transportation and Utilities, Traffic Engineering Section before a building move approval can be obtained. See items 10, 12, 13 & 14 on the BUILDING MOVE PROCESS INSIDE CITY LIMITS handout’s NOTES section. Updated 16/07/2014 BUILDING STANDARDS rd 222-3 AVE NORTH, SASKATOON, SK S7K 0J5 BUILDING MOVE PROCESS TO OUTSIDE CITY LIMITS APPLICATION TO MOVE A BUILDING Date of Application Building Owner Telephone Type of Building to be moved: From To Lot Lot Loaded Building Height Width Building Mover Blk Blk Plan Plan Length Telephone Route to be Taken Special Remarks *NOTE: This box must be completed by the Building Standards Division before scheduling a building move Building Standards Building Permit #(s) Date Approval Signature and Remarks rd Issued 3 Floor South, City Hall 306-975-3236 Statement of Taxes: Sewer and Water Cut-Off Number: To Be Completed By Divisions Listed (if required) DEPARTMENT APPROVAL Traffic Planning and Operations In all cases 3rd Floor North City Hall 975-2640 Saskatoon Police Services 76 25th Street East 975-2360 Parks Division 1101 Avenue P North 975-2537 Saskatoon Light and Power 322 Brand Road REMARKS In all cases In all cases 975-2414 Only if loaded building height exceeds 5.25 meters Electronics Shop, Municipal Eng. Traffic Lights 14 – 450 Ontario Avenue 221-6463 SaskPower 1370 Fletcher Avenue 934-7750 In all cases SaskEnergy 408 36th Street East 975-8515 SaskTel 210 103rd Street East 931-5411 Only if natural gas connections/lines are involved or if necessary to locate gas lines Only if loaded building height exceeds 4 meters Shaw Cable 2326 Hanselman Ave 665-3721 Only if loaded building height exceeds 5.25 meters In all cases Statement of Taxes Sewer and Water Cut-off Number I agree to abide by and observe all City by-laws and undertake to indemnify the City against any and all manner of action or actions, cause or causes of actions, sums of money, claims and demands whatsoever at the law or in equity which may arise by reason of the within removal. Signature of Owner or Authorized Agent