SECTION 230998 A. PREFUNCTIONAL CHECKLISTS MECHANICAL and ELECTRICAL GENERAL This section contains Prefunctional Checklists in a form format (PFC). The PFC procedures displayed here are intended to provide the CA with an example of a format and an indication of the rigor of the required prefunctional checklists and documentation for various equipment types. Though they were not developed specifically for this project, they are generally applicable. The checklists contain items for both Division 23 and 26 contractors to perform. On each checklist, a column is provided that should be filled out by the Contractor assigning responsibility for that line item to a trade. Those executing the checklists are only responsible to perform items that apply to the specific application at hand. These checklists do not take the place of the manufacturer’s recommended checkout and startup procedures or report. Some checklist procedures may be redundant of some checkout procedures that will be documented on typical factory field checkout sheets. Double documenting is required in those cases. Refer to Section 170100 for additional requirements regarding prefunctional checklists, startup and initial checkout. Items that do not apply should be noted along with the reasons on the form. If this form is not used for documenting, one of similar rigor and clarity shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor. B. PREFUNCTIONAL CHECKLISTS The prefunctional checklists referred to in this section are found in the Specifications immediately after this section and will be available to the successful contractors in electronic format after the contract is awarded. The checklists are provided in electronic file format (MS Word and MS Excel for Windows 2003). The file name is at the bottom of each page. The file name “pc__” stands for Prefunctional Checklist. COMPONENT ELECTRONIC FILE NAME Mechanical Equipment & Systems (checklists have both mechanical and electrical trade responsibilities) Air handler Units Building Automation System (DDC) Calibration procedures (sensors; actuators) Compressed Air Piping Computer room AC unit Ductwork Energy Recovery Units (ERU) Exhaust, Transfer, Relief fans Refrigerant Piping Startup documentation plan template Variable frequency drive ST. LOUIS COUNTY ANIMAL/VECTOR CONTROL SHELTER – OLIVETTE, MISSOURI PC-ahu.doc PC-tempcontrols.doc PC-calibdir.doc PC-compairpipe.doc PC-computac.doc PC-Ductwork.doc PC-eru.doc PC-exh_fan.doc PC-Refrigpipe.doc PC-startpln.doc PC-vfd.doc PREFUNCTIONAL CHECKLISTS SECTION 230998 − 1 Electrical Equipment & Systems (checklists have both mechanical and electrical trade responsibilities) Generator and ATS Lighting Controls C. PC Generator&ATS.xls PC LightingControls.xls SUGGESTED NUMBERING KEY FOR COMMISSIONING PROCEDURES The checklists, functional tests, documentation and training use the equipment tag numbers from the Division 23 drawings. Where tag numbers are repeated on the plans, individual numbers shall be assigned by the TAB firm (i.e. where VAV-1 represents a 6” size and is used multiple times, the TAB shall assign mark numbers for each VAV on a plan and all references to these items shall use the TAB number by all members of the commissioning team. At the beginning of the identification number is a text abbreviation for the following: Document or Event Abbreviations DOC= Documentation PC = Prefunctional Checklist SP = Startup Plan SR = Startup Report FT = Functional Test R = Review TR = Training Record END OF SECTION 230998 ST. LOUIS COUNTY ANIMAL/VECTOR CONTROL SHELTER – OLIVETTE, MISSOURI PREFUNCTIONAL CHECKLISTS SECTION 230998 − 2 AHU PREFUNCTIONAL CHECKLIST PC-_____ Prefunctional Checklist Project ____________________________________ PC-___ AIR HANDLER UNIT, AHU #’s_______________________________ Components included: ___supply fans, ___return and exhaust fans, ___coils, ___valves, ___VFD, ___dampers Associated Checklists: CHW, HW Piping, ______________________________ 1. Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _________________________ _____________ Mechanical Contractor Controls Contractor Date Date ____________________________ ______________ _________________________ _____________ Electrical Contractor Sheet Metal Contractor Date Date ____________________________ ______________ _________________________ _____________ TAB Contractor General Contractor Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • • This checklist does not take the place of the manufacturer’s recommended checkout and startup procedures or report. Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. ____________________________ ______________ _________________________ _____________ Commissioning Agent Owner’s Representative 2. Date Date Requested documentation submitted Notes: File: PC Ahu.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 1 AHU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Check Manufacturer’s cut sheets Performance data (fan curves, coil data, etc.) Installation and startup manual and plan Sequences and control strategies O&M manuals • Documentation complete as per contract documents for given trade ........___ YES ___ NO 3. Model verification [Contr = ________] 1 = as specified, 2 = as submitted, 3 = as installed. Check if Okay. Enter note number if deficient. Equip Tag---> 1 2 3 1 Model 2 3 Serial # 3 1 Capacity 2 3 1 Volts/phase 2 3 Manuf. • The equipment installed matches the specifications for given trade ..........___ YES ___ NO 4. Installation Checks Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Cabinet and General Installation Permanent labels affixed, including for fans Casing condition good: no dents, leaks, door gaskets installed Access doors close tightly - no leaks Boot between duct and unit tight and in good condition Vibration isolation equipment installed & released from shipping locks Maintenance access acceptable for unit and components Sound attenuation installed Thermal insulation properly installed and according to specification Instrumentation installed according to specification (thermometers, pressure gages, flow meters, etc.) Clean up of equipment completed per contract documents Notes: File: PC Ahu.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 2 AHU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Filters installed and replacement type and efficiency permanently affixed to housing--construction filters removed Valves, Piping and Coils (see full piping checklists) Pipe fittings complete and pipes properly supported Pipes properly labeled Pipes properly insulated Strainers in place and clean Piping system properly flushed No leaking apparent around fittings All coils are clean and fins are in good condition All condensate drain pans clean and slope to drain, per spec Valves properly labeled Valves installed in proper direction OSAT, MAT, SAT, RAT, chilled water supply sensors properly located and secure (related OSAT sensor shielded) Sensors calibrated (See calibration section below) Motors: Premium efficiency verified, if spec’d? P/T plugs and isolation valves installed per drawings Fans and Dampers Supply fan and motor alignment correct Supply fan belt tension & condition good Supply fan protective shrouds for belts in place and secure Supply fan area clean Supply fan and motor properly lubricated Return/exhaust fan and motor aligned Return/exhaust fan belt tension & condition good Return/exhaust fan protective shrouds for belts in place and secure Return/exhaust fan area clean Return/exhaust fan and motor lube lines installed and lubed Filters clean and tight fitting Filter pressure differential measuring device installed and functional (magnahelic, inclined manometer, etc.) Smoke and fire dampers installed properly per contract docs (proper location, access doors, appropriate ratings verified) All dampers close tightly All damper linkages have minimum play Low limit freeze stat sensor located to deal with stratification & bypass Ducts (preliminary check) Notes: File: PC Ahu.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 3 AHU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Sound attenuators installed Duct joint sealant properly installed No apparent severe duct restrictions Turning vanes in square elbows as per drawings OSA intakes located away from pollutant sources & exhaust outlets Pressure leakage tests completed Branch duct control dampers operable Ducts cleaned as per specifications Balancing dampers installed as per drawings and TAB’s site visit Electrical and Controls Pilot lights are functioning Power disconnects in place and labeled All electric connections tight Proper grounding installed for components and unit Safeties in place and operable Starter overload breakers installed and correct size Sensors calibrated (see below) Control system interlocks hooked up and functional Smoke detectors in place All control devices, pneumatic tubing and wiring complete VFD VFD powered (wired to controlled equipment) VFD interlocked to control system Static pressure or other controlling sensor properly located and per drawings and calibrated Static pressure or other controlling sensor calibrated Drive location not subject to excessive temperatures Drive location not subject to excessive moisture or dirt Drive size matches motor size Internal setting designating the model is correct Input of motor FLA represents 100% to 105% of motor FLA rating Appropriate Volts vs Hz curve is being used Accel and decel times are around 10-50 seconds, except for special applications. Actual decel = ______ Actual accel = _____ Lower frequency limit at 0 for VAV fans and around 10-30% for chilled water pumps. Actual = _______________ Upper frequency limit set at 100%, unless explained otherwise Unit is programmed with full written programming record on site TAB Notes: File: PC Ahu.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 4 AHU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents Final Smoke and fire dampers and unpowered TU’s are open Startup report completed with this checklist attached Safeties installed and safe operating ranges for this equipment provided to the commissioning agent If unit isstarted and will be running during construction: have quality filters on RA grills, etc. to minimize dirt in the ductwork and coils and in any finished areas. Verify moisture migration is not a problem, due to improper pressures between spaces. • The checklist items of Part 4 are all successfully completed for given trade.___ YES ___ NO • 5. Operational Checks (These augment mfr’s list. This is not the functional performance testing.) Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Supply fan rotation correct Return/exhaust fan rotation correct Fans > 5 Hp Phase Checks: (%Imbalance = 100 x (avg. - lowest) / avg.) Record all 3 voltages in cell. Imbalance less than 2%? Record full load running amps for each fan. _____rated FL amps x ______srvc factor = _______ (Max amps). Running less than max? Return /exhaust fan acceptable noise & vibration Supply fan has no unusual noise or vibration Inlet vanes aligned in housing, actuator spanned, modulate smoothly and proportional to input signal and EMS readout All dampers (OSA, RA, EA, etc.) stroke fully without binding and spans calibrated and BAS reading site verified (follow procedure in Calibration and Leak-by Test Procedures). List dampers checked: _____________________________________________________ Valves stroke fully and easily and spanning is calibrated (follow procedure in Calibration and Leak-by Test Procedures). List each actuated valve here when spanned: _____________________________________________________ Valves verified to not be leaking through coils when closed at normal operating pressure (follow procedure in Calibration and Leak-by Test Procedures). The HOA switch properly activates and deactivates the unit Notes: File: PC Ahu.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 5 AHU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Specified sequences of operation and operating schedules have been implemented with all variations documented Specified point-to-point checks have been completed and documentation record submitted for this system • The checklist items of Part 5 are all successfully completed for given trade.___ YES ___ NO 6. Sensor and Actuator Calibration [ ] All field-installed temperature, relative humidity, CO, CO2 and pressure sensors and gages, and all actuators (dampers and valves) on this piece of equipment shall be calibrated using the methods and tolerances given in the Calibration and Leak-by Test Procedures document. All test instruments shall have had a certified calibration within the last 12 months: Y/N______. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated. Sensor or Actuator & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Sensor & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Gage reading = reading of the permanent gage on the equipment. BAS = building automation system. Instr. = testing instrument. Visual = actual observation. The Contractor’s own sensor check-out sheets may be used in lieu of the above, if the same recording fields are included and the referenced procedures are followed. • All sensors are calibrated within required tolerances...................................___ YES ___ NO -- END OF CHECKLIST-- Notes: File: PC Ahu.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 6 BUILDING AUTOMATION SYSTEM PREFUNCTIONAL CHECKLIST PC-___ Prefunctional Checklist Project ____________________________________ PC-___ BUILDING AUTOMATION SYSTEM __ Entire Building __ Only Floor or Zone _______________________________ Associated checklists: ____________________________________________ 1. Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _____________ _________________________ Mechanical Contractor Controls Contractor Date ____________________________ ______________ _____________ _________________________ Electrical Contractor Sheet Metal Contractor Date ____________________________ ______________ _____________ _________________________ TAB Contractor General Contractor Date Date Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • • This checklist does not take the place of the manufacturer’s recommended checkout and startup procedures or report. Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Notes: File: PC CONTROLS-ddc.doc 6/2/2010 Commissioning Specification --PECI Page 1 of 4 BUILDING AUTOMATION SYSTEM PREFUNCTIONAL CHECKLIST PC-___ Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. ____________________________ ______________ _____________ _________________________ Commissioning Agent Owner’s Representative 2. Date Date Documentation submitted and approved: __ manufacturer’s cut sheets __ installation and checkout manual and plan __ full written sequences and list of all control strategies __ written copy of all control parameters, settings and setpoints __ O&M manual [ All ] __ performance data __ operating manual __ completed control drawings __ design criteria __ full descriptive points list • Documentation complete as per contract documents ..................................................___ YES ___ NO 3. Model verification [ Contr = ________] As Specified As Submitted n/a n/a Manufacturer Model No. Serial No. CPU Monitor Other primary features: As Installed • The equipment installed matches the specifications for given trade..........................___ YES ___ NO 4. Initial Setup and Checkout 4.1. User Terminal Interface and Sub-Panel Checks Check if Okay. Enter comment or note number if deficient. Y/N Check Contr. General appearance good, no apparent damage Equipment labels affixed Layout and location of control panels matches drawings Areas or equipment panels serve clear in control drawings Wiring labeled inside panels (to controlled components) Controlled components labeled/tagged BAS connection made to labeled terminal(s) as shown on drawings Shielded wiring used on electronic sensors 110 volt AC power available to panel Notes: File: PC CONTROLS-ddc.doc 6/2/2010 Commissioning Specification --PECI Page 2 of 4 BUILDING AUTOMATION SYSTEM PREFUNCTIONAL CHECKLIST PC-___ Y/N Check Contr. Psig compressed air available to panel (if applicable) Battery backup in place and operable Panels properly grounded Environmental conditions according to manufacturer’s requirements Date and time correct • The above setup and checkout was successfully completed for given trade............___ YES ___ NO 4.2. Device and Point Checkout [CC] The following procedures are required to be performed and documented for each and every point in the control system. The following procedures are minimum requirements. The control contractor is encouraged to identify better and more comprehensive checkout procedures in their submitted plan. These procedures are not a substitute for the manufacturer’s recommended start-up and checkout procedures, but are to be combined with them, as applicable. The documentation may be provided on the vendor’s stock form, as long as all the information in the sample table below can be clearly documented on the form. Similar checkout and calibration requirements are found on the equipment prefunctional checklists. Redundant documentation is not required. Cross reference, by name and form number, to other forms that contain documentation left blank on the current form. Procedures 1. [Wire] Verify that the wiring is correct to each point. 2. [Actu] If the device is or has an actuator, verify full free movement through its full range. 3. [Addr] Verify that the software address is correct. 4. [Load] For devices with a controller, verify that current software program with proper setpoints has been downloaded. 5. [DevCal] Device stroke/range calibration. This applies to all controlled valves, dampers, fans, pumps, actuators, etc. Simulate maximum and minimum transmitter signal values and verify minimum and maximum controller output values and positively verify each and every control device minimum and maximum stroke and capacity range. Follow procedure 6.2 below. 6. [SensLoc] Verify that all sensor locations are appropriate and away from causes of erratic operation. 7. [SensCal] Sensor calibration. Calibrate or verify calibration of all sensors and thermostats, including temperature, pressure, flow, current, kW, rpm, Hertz, etc. Verify that the sensor readings in the control system are within the sensor accuracies specified in this section, using hand-held or other external measuring instruments. Follow procedure 6.1 below. 8. [OperCk] For controlled devices (dampers, valves, actuators, VAV boxes, etc.), after mechanical equipment control becomes operational, perform an operational test of each control loop. Follow procedure 6.2 below. Operational checks are preparatory to the later functional testing. Other Abbreviations: [BAS] ......Building automation system or gage-read value. [Instru].....Instrument (calibrated) read value. [Ofset] .....Offset programmed into the point to correct the calibration. Notes: File: PC CONTROLS-ddc.doc 6/2/2010 Commissioning Specification --PECI Page 3 of 4 BUILDING AUTOMATION SYSTEM PREFUNCTIONAL CHECKLIST PC-___ --SAMPLE FORM-Point ID Object AI-1 ZN-T (zone T) RA-DPR (damper) Controls Checkout Documentation Table Field Device Type Hardware Checks Wire Actu Addr PhJack √ 2 na √ 4 na Dev Cal 5 na PNEU √ √ √ na √ 1 3-2a 3 Load BAS SensCal Instru Offset Sens Loc 6 √ 7 70.2F 7 71.4F 7 +1.2F na na na na Final Check Oper Ck 8 9 na √ • The initial setup and checkout has been successfully completed as described in Section 4.2 and Section 6 and documented on attached forms ..............................................................___ YES ___ NO 5. Pneumatic System Pressure Test [ • Not Applicable. 6. Sensor and Actuator Calibration [ ] All field-installed temperature, relative humidity, CO, CO2 and pressure sensors and gages, and all actuators (dampers and valves) shall be calibrated using the methods and tolerances given in the “Calibration and Leak-by Test Procedures” document. All test instruments shall have had a certified calibration within the last 12 months. Sensors installed in a packaged unit at the factory with calibration certification provided need not be field calibrated. All calibrations shall be fully documented, including initial and final readings, offsets etc., on prefunctional checklist or other suitable forms. -- END OF CHECKLIST -- Notes: File: PC CONTROLS-ddc.doc 6/2/2010 Commissioning Specification --PECI Page 4 of 4 ] CALIBRATION AND LEAK-BY TEST PROCEDURES Calibration and Leak-by Test Procedures All field-installed temperature, relative humidity, CO, CO2 and pressure sensors and gages, and all actuators (dampers and valves) on all equipment shall be calibrated using the methods described below. Alternate methods may be used, if approved by the Engineer before-hand. All test instruments shall have had a certified calibration within the last 12 months. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated. All procedures used shall be fully documented on the prefunctional checklists or other suitable forms, clearly referencing the procedures followed and written documentation of initial, intermediate and final results. 1. Sensor Calibration Methods All Sensors. Verify that all sensor locations are appropriate and away from causes of erratic operation. Verify that sensors with shielded cable, are grounded only at one end. For sensor pairs that are used to determine a temperature or pressure difference, make sure they are reading within 0.2°F of each other for temperature and within a tolerance equal to 2% of the reading, of each other, for pressure. Tolerances for critical applications may be tighter. A. Sensors Without Transmitters--Standard Application. Make a reading with a calibrated test instrument within 6 inches of the site sensor. Verify that the sensor reading (via the permanent thermostat, gage or building automation system (DDC)) is within the tolerances in the table below of the instrument-measured value. If not, install offset in DDC, calibrate or replace sensor. B. Sensors With Transmitters--Standard Application. Disconnect sensor. Connect a signal generator in place of sensor. Connect ammeter in series between transmitter and DDC control panel. Using manufacturer’s resistance-temperature data, simulate minimum desired temperature. Adjust transmitter potentiometer zero until 4 mA is read by the ammeter. Repeat for the maximum temperature matching 20 mA to the potentiometer span or maximum and verify at the DDC. Record all values and recalibrate controller as necessary to conform with specified control ramps, reset schedules, proportional relationship, reset relationship and P/I reaction. Reconnect sensor. Make a reading with a calibrated test instrument within 6 inches of the site sensor. Verify that the sensor reading (via the permanent thermostat, gage or building automation system (DDC)) is within the tolerances in the table below of the instrument-measured value. If not, replace sensor and repeat. For pressure sensors, perform a similar process with a suitable signal generator. C. Critical Applications. For critical applications (process, manufacturing, etc.) more rigorous calibration techniques may be required for selected sensors. Describe any such methods used on an attached sheet. Tolerances, Standard Applications Sensor Cooling coil, chilled and condenser water temps AHU wet bulb or dew point Hot water coil and boiler water temp Outside air, space air, duct air temps Watthour, voltage & amperage Pressures, air, water and gas Flow rates, air File: PC CALIBDIR.doc Required Tolerance (+/-) 0.4F 2.0F 1.5F Flow rates, water Relative humidity Combustion flue temps Oxygen or CO2 monitor Required Tolerance (+/) 4% of design 4% of design 5.0F 0.1 % pts 0.4F CO monitor 0.01 % pts 1% of design Natural gas and oil flow rate Steam flow rate Barometric pressure 1% of design 3% of design 10% of design Sensor Commissioning Guide Specification --PECI 6/2/2010 --Large Buildings 3% of design 0.1 in. of Hg 1 CALIBRATION AND LEAK-BY TEST PROCEDURES 2. Valve and Damper Stroke Setup and Check A. DDC Readout. For all valve and damper actuator positions checked, verify the actual position against the DDC readout. Set pumps or fans to normal operating mode. Command valve or damper closed, visually verify that valve or damper is closed and adjust output zero signal as required. Command valve or damper open, verify position is full open and adjust output signal as required. Command valve or damper to a few intermediate positions. If actual valve or damper position doesn’t reasonably correspond, replace actuator or add pilot positioner (for pneumatics). B. Closure for heating coil valves (NO): Set heating setpoint 20°F above room temperature. Observe valve open. Remove control air or power from the valve and verify that the valve stem and actuator position do not change. Restore to normal. Set heating setpoint to 20°F below room temperature. Observe the valve close. For pneumatics, by override in the DDC, increase pressure to valve by 3 psi (do not exceed actuator pressure rating) and verify valve stem and actuator position does not change. Restore to normal. C. Closure for cooling coil valves (NC): Set cooling setpoint 20°F above room temperature. Observe the valve close. Remove control air or power from the valve and verify that the valve stem and actuator position do not change. Restore to normal. Set cooling setpoint to 20°F below room temperature. Observe valve open. For pneumatics, by override in the DDC, increase pressure to valve by 3 psi (do not exceed actuator pressure rating) and verify valve stem and actuator position does not change. Restore to normal. 3. Coil Valve Leak Check A. Method 1--Water Temperature With 2-Way Valve. Calibrate water temperature sensors on each side of coil to be within 0.2°F of each other. Turn off air handler fans, close OSA dampers; keep pump running. Make sure appropriate coil dampers are open. Normally closed valves will close. Override normally open valves to the closed position. After 10 minutes observe water delta T across coil. If it is greater than 2°F, leakage is probably occurring. Reset valve stroke to close tighter. Repeat test until compliance. B. Method 2--Air Temperature With 2 or 3-Way Valve. Calibrate air temperature sensors on each side of coil to be within 0.2°F of each other. Change mixed or discharge air setpoint, override values or bleed or squeeze bulb pneumatic controller to cause the valve to close. Air handler fans should be on. After 5 minutes observe air delta T across coil. If it is greater than 1°F, leakage is probably occuring. Reset valve stroke to close tighter. Repeat test until compliance. Water leak-by less than 10% will likely not be detected with this method. C. Method 3 Coil Drain Down (not for 3-way valves). Put systDDC in normal mode. If cooling coil valve, remove all call for cooling or if heating coil valve put system in full cooling. Close isolation valve on supply side of coil, open air bleed cap, open drain-down cock and drain water from coil. Water should stop draining, else there may be a leak through the control valve. Return all to normal when done. 4. Isolation Valve or System Valve Leak Check (for valves not by coils) A. Method 1--Ultra-sonic flow meter. With full pressure in the system, command valve closed. Use an ultra-sonic flow meter to detect flow or leakage. -- END OF PROCEDURES-- File: PC CALIBDIR.doc Commissioning Guide Specification --PECI 6/2/2010 --Large Buildings 2 COMPRESSED AIR PIPING PREFUNCTIONAL CHECKLIST PC-_____ Prefunctional Checklist Project ____________________________________ PC-____ COMPRESSED AIR PIPING________ Components Included: All valves 1. Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _________________________ _____________ Mechanical Contractor Controls Contractor Date Date ____________________________ ______________ _________________________ _____________ Electrical Contractor Sheet Metal Contractor Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • • This checklist does not take the place of the manufacturer’s recommended checkout and startup procedures or report. Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. ____________________________ ______________ _________________________ _____________ Commissioning Agent Owner’s Representative 2. Date Date Requested documentation submitted Check if Okay. Enter comment or note number if deficient. Check Y/N Contr. Manufacturer’s cut sheets Performance data Flushing and cleaning plan, including staging of multiple floors Notes: PC Compressed Air Piping Page 1 of 3 COMPRESSED AIR PIPING PREFUNCTIONAL CHECKLIST PC-_____ O&M manuals • Documentation complete as per contract documents for given trade ........___ YES ___ NO 3. Physical Installation Checks Check if Okay. Enter comment or note number if deficient. Check Y/N Contr. Note Piping Pipe fittings complete and pipes properly supported Required seismic anchoring installed Pipes properly labeled Pipes properly insulated Strainers in place and clean Isolation valves valves installed Flushing and cleaning plan submitted and approved (Minimum flushing velocity in all pipe sections is the greater of 4 ft. per second, or 1.5 times the velocity at design flow) Piping system properly flushed and cleaned and temporary piping removed (report attached) 10% of strainers and Owner-selected low-point drains opened and witnessed by Owner to be clean. (List points checked below). Piping pressure tested according to contract documents (report attached) No leaking apparent around fittings ASME pressue vessel data sheet or certification tag posted and inspection complete for each expansion tank Valves Valve labels permanently affixed Valves installed in proper direction No leaks Valves stroke fully and easily and spanning is calibrated (see calibration section below) Valves that require a positive shut-off are verified to not be leaking when closed at normal operating pressure per “Calibration and Leak-by Test Procedures” document. List: __________________________________________________ Sensors and Gages Temperature, pressure and flow gages and sensors installed Piping gages, BAS and chiller panel temperature and pressure readouts match (see calibration section below) Notes: PC Compressed Air Piping Page 2 of 3 COMPRESSED AIR PIPING PREFUNCTIONAL CHECKLIST PC-_____ • The checklist items of Part 3 are all successfully completed for given trade.___ YES ___ NO 4. Sensor and Actuator Calibration [ ] All field-installed temperature and pressure sensors and gages, and all actuators (valves) on this piece of equipment shall be calibrated using the methods and tolerances given in the Calibration and Leak-by Test Procedures document. All test instruments shall have had a certified calibration within the last 12 months: Y/N______. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated. Sensor or Actuator & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Sensor & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Gage reading = reading of the permanent gage on the equipment. BAS = building automation system. Instr. = testing instrument. Visual = actual observation. The Contractor’s own sensor check-out sheets may be used in lieu of the above, if the same recording fields are included and the referenced procedures are followed. • All sensors are calibrated within required tolerances...................................___ YES ___ NO -- END OF CHECKLIST -- Notes: PC Compressed Air Piping Page 3 of 3 COMPUTER ROOM AIR CONDITIONING UNIT PREFUNCTIONAL CHECKLIST PC-_____ Prefunctional Checklist Project ____________________________________ PC-___ COMPUTER ROOM AC UNIT (Inside Section) ID#’s___________________ Components included: ___Coils ___Valves (CHW) Associated Checklists: 1. ___ Outdoor condenser/compressor Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _________________________ _____________ Mechanical Contractor Controls Contractor Date Date ____________________________ ______________ _________________________ _____________ Electrical Contractor Sheet Metal Contractor Date Date ____________________________ ______________ _________________________ _____________ TAB Contractor General Contractor Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • • This checklist does not take the place of the manufacturer’s recommended checkout and startup procedures or report. Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. ____________________________ ______________ _________________________ _____________ Commissioning Agent Owner’s Representative Date Date Notes: File: PC COMPUTAC.docCommissioning Guide Specification --Large Buildings --PECI: 6/2/2010 1 COMPUTER ROOM AIR CONDITIONING UNIT PREFUNCTIONAL CHECKLIST PC-_____ 2. Requested documentation submitted Check Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Manufacturer’s cut sheets Performance data (fan curves, coil data, etc.) Installation and startup manual and plan Sequences and control strategies O&M manuals • Documentation complete as per contract documents for given trade ........___ YES ___ NO 3. Model verification [Contr = ________] 1 = as specified, 2 = as submitted, 3 = as installed. Check if Okay. Enter note number if deficient. Equip Tag---> 1 2 3 1 Model 2 3 Serial # 3 1 Capacity 2 3 1 Volts/Ph/A 2 3 1 Humidifier 2 3 1 Reheat 2 3 Manuf. • The equipment installed matches the specifications for given trade ..........___ YES ___ NO 4. Physical Installation Checks Check Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Cabinet and General Installation Permanent labels affixed, including for fans Casing condition good: no dents, leaks, door gaskets installed Boot between duct and unit tight and in good condition Vibration isolation equipment installed & released from shipping locks Maintenance access acceptable for unit and components Notes: File: PC COMPUTAC.docCommissioning Guide Specification --Large Buildings --PECI: 6/2/2010 2 COMPUTER ROOM AIR CONDITIONING UNIT PREFUNCTIONAL CHECKLIST PC-_____ Check Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Thermal insulation properly installed and according to specification Instrumentation installed according to specification (thermometers, pressure gages, flow meters, etc.) Clean up of equipment completed per contract documents Filters installed and replacement type and efficiency permanently affixed to housing Reheat coil installed, if specified Humidifier coil installed, if specified Valves, Piping and Coils Pipe fittings complete and pipes properly supported Pipes properly labeled Pipes properly insulated Piping system properly flushed No leaking apparent around fittings All coils are clean and fins are in good condition All condensate drain pans clean and slope to drain, per spec Specified valves installed and properly labeled Valves installed in proper direction Valves stroke fully and easily and spanning is calibrated (see calibration section below) OSAT, MAT, SAT, RAT, chilled water supply sensors properly located and secure (related OSAT sensor shielded) Sensors calibrated (See calibration section below) P/T plugs and isolation valves installed per drawings Fans and Dampers Supply fan belt tension & condition good Supply fan protective shrouds for belts in place and secure Supply fan area clean Supply fan and motor properly lubricated Filters clean and tight fitting No unusual noise or vibration Smoke and fire dampers installed properly per contract docs (proper location, access doors, appropriate ratings verified) All dampers (OSA, RA, EA, etc.) stroke fully without binding and spans calibrated (follow procedure similar to valves Section 7.3 below) All dampers close tightly All damper linkages have minimum play Outside air capability to space installed Notes: File: PC COMPUTAC.docCommissioning Guide Specification --Large Buildings --PECI: 6/2/2010 3 COMPUTER ROOM AIR CONDITIONING UNIT PREFUNCTIONAL CHECKLIST PC-_____ Check Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Ducts (preliminary check) Sound attenuators installed Duct joint sealant properly installed No apparent severe duct restrictions Turning vanes in square elbows as per drawings OSA intakes located away from pollutant sources & exhaust outlets Pressure leakage tests completed Branch duct control dampers operable Electrical and Controls Pilot lights are functioning Power disconnects in place and labeled All electric connections tight Proper grounding installed for components and unit Safeties in place and operable Current overload heaters installed and correct size Sensors calibrated (see section below) Control system interlocks hooked up and functional Smoke detectors in place Enthalpy control and sensor properly installed (if applicable) Related thermostats are installed Related building automation system points are installed, including high temperature alarm and emergency power All control devices, pneumatic tubing and wiring complete TAB Installation of system and balancing devices allowed balancing to be completed per specified NEBB or AABC procedures & contract docs Final Startup report completed with this checklist attached Safeties installed and safe operating ranges for this equipment provided to the commissioning agent Functional test procedures for this equipment reviewed and approved by installing contractor • The checklist items of Part 4 are all successfully completed for given trade.___ YES ___ NO Notes: File: PC COMPUTAC.docCommissioning Guide Specification --Large Buildings --PECI: 6/2/2010 4 COMPUTER ROOM AIR CONDITIONING UNIT PREFUNCTIONAL CHECKLIST PC-_____ 5. Operational Checks (These augment mfr’s list. This is not the functional performance testing.) Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Supply fan rotation correct Fans > 5 Hp Phase Checks: (%Imbalance = 100 x (avg. - lowest) / avg.) Record all 3 voltages in cell. Imbalance less than 2%? Record full load running amps for each fan. _____rated FL amps x ______srvc factor = _______ (Max amps). Running less than max? Supply fan has no unusual noise or vibration All dampers (OSA, RA, EA, etc.) stroke fully without binding and spans calibrated (follow procedure similar to valves Section 7 below). List each actuated damper here when spanned: Valves stroke fully and easily and spanning is calibrated (see calibration section). List each actuated valve here when spanned: Valves that require a positive shut-off are verified to not be leaking when closed at normal operating pressure per “Calibration and Leak-by Test Procedures” document. Valves tested: ____________ _____________________________________________________ The HOA switch properly activates and deactivates the unit Specified sequences of operation and operating schedules have been implemented with all variations documented Specified point-to-point checks have been completed and documentation record submitted for this system • The checklist items of Part 5 are all successfully completed for given trade.___ YES ___ NO 6. Sensor and Actuator Calibration [ ] All field-installed temperature, relative humidity, CO, CO2 and pressure sensors and gages, and all actuators (dampers and valves) on this piece of equipment shall be calibrated using the methods and tolerances given in the Calibration and Leak-by Test Procedures document. All test instruments shall have had a certified calibration within the last 12 months: Y/N______. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated. Sensor or Actuator & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Sensor & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Notes: File: PC COMPUTAC.docCommissioning Guide Specification --Large Buildings --PECI: 6/2/2010 5 COMPUTER ROOM AIR CONDITIONING UNIT PREFUNCTIONAL CHECKLIST PC-_____ Gage reading = reading of the permanent gage on the equipment. BAS = building automation system. Instr. = testing instrument. Visual = actual observation. The Contractor’s own sensor check-out sheets may be used in lieu of the above, if the same recording fields are included and the referenced procedures are followed. • All sensors are calibrated within required tolerances...................................___ YES ___ NO -- END OF CHECKLIST-- Notes: File: PC COMPUTAC.docCommissioning Guide Specification --Large Buildings --PECI: 6/2/2010 6 DUCTWORK PREFUNCTIONAL CHECKLIST PC-_____ Prefunctional Checklist Project ____________________________________ PC-___ DUCTWORK Supply, Return, Exhaust for Equipment #’s #’s_______________________________ Components included: ___ducts, ___liner, ___insulation, ___sound attenuators, ___manual dampers, ___motorized dampers, ___ 1. Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _________________________ _____________ Mechanical (Sheet Metal) Contractor TAB Contractor Date ____________________________ ______________ General Contractor Date _________________________ _____________ Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. ____________________________ ______________ _________________________ _____________ Commissioning Agent Owner’s Representative Date Date Notes: 1 of 5 PC DUCTWORK - DUCTWORK PREFUNCTIONAL CHECKLIST PC-_____ 2. Requested documentation submitted Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Check Manufacturer’s cut sheets for purchased items. Ductwork shop drawings and installation details. • Documentation complete as per contract documents for given trade ........___ YES ___ NO 3. Model verification for purchased items. [Contr = ________] 1 = as specified, 2 = as submitted, 3 = as installed. Check if Okay. Enter note number if deficient. Equip Tag---> 1 2 3 1 Model 2 3 Serial # 3 1 Capacity 2 3 1 Volts/phase 2 3 Manuf. • The equipment installed matches the specifications for given trade ..........___ YES ___ NO 4. Installation Checks Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. General Installation Maintenance access acceptable for components Sound attenuation installed Thermal insulation properly installed and according to specification Instrumentation installed according to specification (thermometers, pressure gages, flow meters, etc.) Ducts cleaned as per specifications Ducts (preliminary check) Duct joints are the proper type for each size Duct joint sealant properly installed No apparent severe duct restrictions Hangers installed per SMACNA standards Notes: 2 of 5 PC DUCTWORK - DUCTWORK PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Hangers at elbows installed within 2 feet of elbows and details on plans Trapeze hangers installed diagonally under all elbows greater than 54 inches wide. Hanger rods shall have double nuts and lockwashers Branch take-offs installed tight to duct wall with projections into main duct kept to a minimum. No ragged edges projecting into the main duct. All open ends of ductwork during construction are covered with plastic sheeting to prevent dirt and debris from entering ducts. Longitudinal seams are made with a Pittsburgh lock or a grooved seam. Reinforcements between transverse joints for ducts >36” wide extend past the edge of the duct and are secured with a tie rod or tie angle as shown in SMACNA 1995 Figure 1-11. Turning vanes in square elbows installed per drawings Radius elbows installed with correct radius per drawings Radius elbows with turning vanes installed with correct number of vanes and correct radius per drawings OSA intakes located away from pollutant sources & exhaust outlets Sound attenuators installed Leakage tests completed per specifications Dampers Branch duct balancing dampers installed per plans Branch duct balancing dampers operable Balancing dampers installed as per drawings and TAB’s site visit Manual dampers have locking quadrants per specs Locking quadrants have stand-offs for insulated ducts Motorized dampers installed per plans Motorized damper actuators are accessible for maintenance Linkages for motorized damper actuators operate freely, have minimum play, and dampers operate from 0 to 100% of range All dampers close tightly Fire dampers install where shown on the plans Smoke dampers install where shown on the plans Notes: 3 of 5 PC DUCTWORK - DUCTWORK PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Fire Dampers Fire dampers installed where shown on the plans Fire damper frames secured to wall Fire dampers are all open Smoke Dampers Smoke dampers installed where shown on the plans Smoke detectors in place Pilot lights are functioning if specified Smoke damper actuators have power and operate Smoke damper frames secured to wall Smoke dampers are all open Control system interlocks hooked up and functional Combination Smoke & Fire Dampers Smoke/Fire dampers installed where shown on the plans Smoke detectors in place Pilot lights are functioning if specified Smoke/Fire damper frames secured to wall Smoke/Fire dampers are all open Control system interlocks hooked up and functional TAB Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents • The checklist items of Part 4 are all successfully completed for given trade.___ YES ___ NO • 5. Operational Checks (These augment mfr’s list. This is not the functional performance testing.) Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Smoke and Smoke/Fire damper actuators have power and operate Motorized damper actuators have power and operate Notes: 4 of 5 PC DUCTWORK - DUCTWORK PREFUNCTIONAL CHECKLIST PC-_____ • The checklist items of Part 5 are all successfully completed for given trade.___ YES ___ NO 6. Sensor and Actuator Calibration [ ] All field-installed damper, smoke damper, and smoke/fire damper actuators shall be calibrated using the methods and tolerances given in the Calibration and Leak-by Test Procedures document. All test instruments shall have had a certified calibration within the last 12 months: Y/N______. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated. Actuator & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Actuator & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Gage reading = reading of the permanent gage on the equipment. BAS = building automation system. Instr. = testing instrument. Visual = actual observation. The Contractor’s own sensor check-out sheets may be used in lieu of the above, if the same recording fields are included and the referenced procedures are followed. • All sensors are calibrated within required tolerances...................................___ YES ___ NO -- END OF CHECKLIST-- Notes: 5 of 5 PC DUCTWORK - ERU PREFUNCTIONAL CHECKLIST PC-_____ Prefunctional Checklist Project ____________________________________ PC-___ ENERGY RECOVERY UNIT, ERU #’s_______________________________ Components included: ___supply fans, ___return and exhaust fans, ___coils, ___valves, ___VFD, ___dampers, ___energy wheels Associated Checklists: CHW, HW Piping, ______________________________ 1. Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _________________________ _____________ Mechanical Contractor Controls Contractor Date Date ____________________________ ______________ _________________________ _____________ Electrical Contractor Sheet Metal Contractor Date Date ____________________________ ______________ _________________________ _____________ TAB Contractor General Contractor Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • • This checklist does not take the place of the manufacturer’s recommended checkout and startup procedures or report. Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. ____________________________ ______________ _________________________ _____________ Commissioning Agent Owner’s Representative Date Date Notes: 1 of 7 PC ERU - ERU PREFUNCTIONAL CHECKLIST PC-_____ 2. Requested documentation submitted Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Check Manufacturer’s cut sheets Performance data (fan curves, coil data, etc.) Installation and startup manual and plan Sequences and control strategies O&M manuals • Documentation complete as per contract documents for given trade ........___ YES ___ NO 3. Model verification [Contr = ________] 1 = as specified, 2 = as submitted, 3 = as installed. Check if Okay. Enter note number if deficient. Equip Tag---> 1 2 3 1 Model 2 3 Serial # 3 1 Capacity 2 3 1 Volts/phase 2 3 Manuf. • The equipment installed matches the specifications for given trade ..........___ YES ___ NO 4. Installation Checks Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Cabinet and General Installation Permanent labels affixed, including for fans Casing condition good: no dents, leaks, door gaskets installed Access doors close tightly - no leaks Boot between duct and unit tight and in good condition Vibration isolation equipment installed & released from shipping locks Maintenance access acceptable for unit and components Sound attenuation installed Thermal insulation properly installed and according to specification Instrumentation installed according to specification (thermometers, pressure gages, flow meters, etc.) Clean up of equipment completed per contract documents Notes: 2 of 7 PC ERU - ERU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Filters installed and replacement type and efficiency permanently affixed to housing--construction filters removed Valves, Piping and Coils (see full piping checklists) Pipe fittings complete and pipes properly supported Pipes properly labeled Pipes properly insulated Strainers in place and clean Piping system properly flushed No leaking apparent around fittings All coils are clean and fins are in good condition All condensate drain pans clean and slope to drain, per spec Valves properly labeled Valves installed in proper direction OSAT, MAT, SAT, RAT, chilled water supply sensors properly located and secure (related OSAT sensor shielded) Sensors calibrated (See calibration section below) Motors: Premium efficiency verified, if spec’d? P/T plugs and isolation valves installed per drawings Fans and Dampers Supply fan and motor alignment correct Supply fan belt tension & condition good Supply fan protective shrouds for belts in place and secure Supply fan area clean Supply fan and motor properly lubricated Return/exhaust fan and motor aligned Return/exhaust fan belt tension & condition good Return/exhaust fan protective shrouds for belts in place and secure Return/exhaust fan area clean Return/exhaust fan and motor lube lines installed and lubed Filters clean and tight fitting Filter pressure differential measuring device installed and functional (magnahelic, inclined manometer, etc.) Smoke and fire dampers installed properly per contract docs (proper location, access doors, appropriate ratings verified) All dampers close tightly All damper linkages have minimum play Low limit freeze stat sensor located to deal with stratification & bypass Notes: 3 of 7 PC ERU - ERU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Ducts Equip Tag-> Contr. (preliminary check) Sound attenuators installed Duct joint sealant properly installed No apparent severe duct restrictions Turning vanes in square elbows as per drawings OSA intakes located away from pollutant sources & exhaust outlets Pressure leakage tests completed Branch duct control dampers operable Ducts cleaned as per specifications Balancing dampers installed as per drawings and TAB’s site visit Electrical and Controls Pilot lights are functioning Power disconnects in place and labeled All electric connections tight Proper grounding installed for components and unit Safeties in place and operable Starter overload breakers installed and correct size Sensors calibrated (see below) Control system interlocks hooked up and functional Smoke detectors in place All control devices and wiring complete Frost Wheel start stop Freeze Filter pressure drop smoke Damper interlocks VFDs VFD powered (wired to controlled equipment) VFD interlocked to control system Static pressure or other controlling sensor properly located and per drawings and calibrated Static pressure or other controlling sensor calibrated Drive location not subject to excessive temperatures Drive location not subject to excessive moisture or dirt Drive size matches motor size Notes: 4 of 7 PC ERU - ERU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Internal setting designating the model is correct Input of motor FLA represents 100% to 105% of motor FLA rating Appropriate Volts vs Hz curve is being used Accel and decel times are around 10-50 seconds, except for special applications. Actual decel = ______ Actual accel = _____ Lower frequency limit at 0 for VAV fans and around 10-30% for chilled water pumps. Actual = _______________ Upper frequency limit set at 100%, unless explained otherwise Unit is programmed with full written programming record on site Energy Wheel(s) Wheel rotor bearings have been greased. Shipping restraints have been removed. Wheel rotates by hand without binding. Rotor is centered in casing and does not tilt. Ensure bearing bolts, rim bolts and the Allen screws on the bearing collar are tight. TAB Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents Final Smoke and fire dampers and unpowered TU’s are open Startup report completed with this checklist attached Safeties installed and safe operating ranges for this equipment provided to the commissioning agent If unit isstarted and will be running during construction: have quality filters on RA grills, etc. to minimize dirt in the ductwork and coils and in any finished areas. Verify moisture migration is not a problem, due to improper pressures between spaces. • The checklist items of Part 4 are all successfully completed for given trade.___ YES ___ NO • 5. Operational Checks (These augment mfr’s list. This is not the functional performance testing.) Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Supply fan rotation correct Return/exhaust fan rotation correct Energy wheel rotation is correct Notes: 5 of 7 PC ERU - ERU PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Fans > 5 Hp Phase Checks: (%Imbalance = 100 x (avg. - lowest) / avg.) Record all 3 voltages in cell. Imbalance less than 2%? Record full load running amps for each fan. _____rated FL amps x ______srvc factor = _______ (Max amps). Running less than max? Return /exhaust fan acceptable noise & vibration Supply fan has no unusual noise or vibration Inlet vanes aligned in housing, actuator spanned, modulate smoothly and proportional to input signal and EMS readout All dampers (OSA, RA, EA, etc.) stroke fully without binding and spans calibrated and BAS reading site verified (follow procedure in Calibration and Leak-by Test Procedures). List dampers checked: _____________________________________________________ Valves stroke fully and easily and spanning is calibrated (follow procedure in Calibration and Leak-by Test Procedures). List each actuated valve here when spanned: _____________________________________________________ Valves verified to not be leaking through coils when closed at normal operating pressure (follow procedure in Calibration and Leak-by Test Procedures). The HOA switch properly activates and deactivates the unit Specified sequences of operation and operating schedules have been implemented with all variations documented Specified point-to-point checks have been completed and documentation record submitted for this system • The checklist items of Part 5 are all successfully completed for given trade.___ YES ___ NO 6. Sensor and Actuator Calibration [ ] All field-installed temperature, relative humidity, CO, CO2 and pressure sensors and gages, and all actuators (dampers and valves) on this piece of equipment shall be calibrated using the methods and tolerances given in the Calibration and Leak-by Test Procedures document. All test instruments shall have had a certified calibration within the last 12 months: Y/N______. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated. Sensor or Actuator & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Sensor & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Notes: 6 of 7 PC ERU - ERU PREFUNCTIONAL CHECKLIST PC-_____ Gage reading = reading of the permanent gage on the equipment. BAS = building automation system. Instr. = testing instrument. Visual = actual observation. The Contractor’s own sensor check-out sheets may be used in lieu of the above, if the same recording fields are included and the referenced procedures are followed. • All sensors are calibrated within required tolerances...................................___ YES ___ NO -- END OF CHECKLIST-- Notes: 7 of 7 PC ERU - EXHAUST FAN PREFUNCTIONAL CHECKLIST PC-_____ Prefunctional Checklist Project ____________________________________ PC-____ 1. EXHAUST FANS ID #’s_____________________________________ Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _____________ _________________________ Mechanical Contractor Controls Contractor Date ____________________________ ______________ _____________ _________________________ Electrical Contractor Sheet Metal Contractor Date ____________________________ ______________ _____________ _________________________ TAB Contractor General Contractor Date Date Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • • This checklist does not take the place of the manufacturer’s recommended checkout and startup procedures or report. Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. ____________________________ ______________ _____________ _________________________ Commissioning Agent Owner’s Representative Date Date Notes: File: PC EXH_FAN.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 1 EXHAUST FAN PREFUNCTIONAL CHECKLIST PC-_____ Notes: File: PC EXH_FAN.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 2 EXHAUST FAN PREFUNCTIONAL CHECKLIST PC-_____ 2. Requested documentation submitted Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Check Manufacturer’s cut sheets Performance data (fan curves, coil data, etc.) Installation and startup manual and plan Sequences and control strategies O&M manuals • Documentation complete as per contract documents for given trade........................___ YES ___ NO 3. Model verification [Contr = ________] 1 = as specified, 2 = as submitted, 3 = as installed. Check if Okay. Enter note number if deficient. Equip Tag---> 1 2 3 1 Model 2 3 Serial # 3 1 CFM 2 3 Sound Pwr 1 Level @ 63, 2 250; 1K Hz 3 Manuf. • The equipment installed matches the specifications for given trade..........................___ YES ___ NO 4. Installation Checks Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Cabinet and General Installation Permanent labels affixed Casing condition good: no dents, leaks, door gaskets installed Mountings checked and shipping bolts removed Vibration isolators installed Equipment guards installed Pulleys aligned Belt tension correct Plenums clear of debri Fans rotate freely Fire and balance dampers installed Backdraft dampers installed, per drawings, and operate freely Notes: File: PC EXH_FAN.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 3 EXHAUST FAN PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Equip Tag-> Contr. Duct system complete Electrical Electrical connections complete Disconnect switch installed Overload heaters in place Control connections complete Operational Checks Fan rotation correct Electrical interlocks verified Any fan status indicators functioning No unusual vibration or and noise Record full load running amps for each fan. _____rated FL amps x ______srvc factor = _______ (Max amps). Running less than max? Check voltage: Rate = ______ Actual = _______ Within 5%? The disconnect switch properly operates After 24 hours of operation, recheck belt tension and alignment • The checklist items of Part 4 are all successfully completed for given trade. ...........___ YES ___ NO -- END OF CHECKLIST-- Notes: File: PC EXH_FAN.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 4 PREFUNCTIONAL CHECKLIST GENERATOR & TRANSFER SWITCH Page 1 of 1 Project__________________________________________________________ Tag No._________________________________________ Manufacturer_____________________________________ Model __________________________________________ Serial No._______________________________________ Checklist Item Generator Set Check engine, oil filter. Check coolant level, antifreeze and rust inhibitor. Check all coolant hoses. Check condition of engine water pump. Check condition and adjust tension on all belts as necessary. Check for normal operation of jacket water heater(s). Check battery electrolyte, specific gravity, clean connections. Check battery charger. Check unit for oil, fuel and coolant leaks. Clean crankcase breather. Check air cleaner. Inspect ignition wiring, if equipped. Check ignition timing, points and plugs, if equipped. Check duct work for defects. Check that the generator has a source of combustion air. Check that the exhaust from the radiator has a path to exit the vicinity so the generator will not overheat. Transfer Switch Check contacts. Check start relay. Check time delays. Remarks: Contractor_________________________Initials____________Date____________ Completed PREFUNCTIONAL CHECKLIST Page 1 of 1 LIGHTING RELAY PANELS Project__________________________________________________________ Tag No. ___________________________ Model No.: _________________________ Manufacturer: ________________________ Serial No.: _________________________ Checklist Item Panel Relay Number Panel 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Contractor - Circuit - Relay is functioning Relay Number 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 Initials Panel - Circuit - Date Relay is functioning CHILLED WATER PIPING PREFUNCTIONAL CHECKLIST PC-_____ Prefunctional Checklist Project ____________________________________ PC-____ CHILLED WATER PIPING________ Components Included: All valves, except coil valves Associated checklists: Chiller, Cooling Tower, CDW Piping, CHW & CDW Pumps 1. Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _________________________ _____________ Mechanical Contractor Controls Contractor Date Date ____________________________ ______________ _________________________ _____________ Electrical Contractor Sheet Metal Contractor Date Date ____________________________ ______________ _________________________ _____________ TAB Contractor General Contractor Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • • This checklist does not take the place of the manufacturer’s recommended checkout and startup procedures or report. Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, CC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. ____________________________ ______________ _________________________ _____________ Commissioning Agent Owner’s Representative 2. Date Date Requested documentation submitted Notes: File: PC Refrigpipe.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 1 CHILLED WATER PIPING PREFUNCTIONAL CHECKLIST PC-_____ Check if Okay. Enter comment or note number if deficient. Check Y/N Contr. Manufacturer’s cut sheets Performance data Flushing and cleaning plan, including staging of multiple floors O&M manuals • Documentation complete as per contract documents for given trade ........___ YES ___ NO 3. Physical Installation Checks Check if Okay. Enter comment or note number if deficient. Check Y/N Contr. Note Piping Pipe fittings complete and pipes properly supported Required seismic anchoring installed Pipes properly labeled Pipes properly insulated Strainers in place and clean Isolation valves and balancing valves installed Test ports (P/T) installed near all control sensors and as per spec Flushing and cleaning plan submitted and approved (Minimum flushing velocity in all pipe sections is the greater of 4 ft. per second, or 1.5 times the velocity at design flow) Piping system properly flushed and cleaned and temporary piping removed (report attached) 10% of strainers and Owner-selected low-point drains opened and witnessed by Owner to be clean. (List points checked below). Piping pressure tested according to contract documents (report attached) Chemical treatment system or plan installed Water treatment report submitted according to contract documents No leaking apparent around fittings ASME pressue vessel data sheet or certification tag posted and inspection complete for each expansion tank Expansion tanks verified to not be air bound and system completely full of water. System purged of all air. Air vents and bleeds at high points of systems functional Valves (except coil valve checklists are with the unit checklist) Valve labels permanently affixed Valves installed in proper direction Notes: File: PC Refrigpipe.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 2 CHILLED WATER PIPING PREFUNCTIONAL CHECKLIST PC-_____ Check Y/N Contr. Note No leaks Valves stroke fully and easily and spanning is calibrated (see calibration section below) Valves that require a positive shut-off are verified to not be leaking when closed at normal operating pressure per “Calibration and Leak-by Test Procedures” document. List: __________________________________________________ Sensors and Gages Temperature, pressure and flow gages and sensors installed Piping gages, BAS and chiller panel temperature and pressure readouts match (see calibration section below) TAB Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents • The checklist items of Part 3 are all successfully completed for given trade.___ YES ___ NO 4. Sensor and Actuator Calibration [ ] All field-installed temperature, relative humidity, CO, CO2 and pressure sensors and gages, and all actuators (dampers and valves) on this piece of equipment shall be calibrated using the methods and tolerances given in the Calibration and Leak-by Test Procedures document. All test instruments shall have had a certified calibration within the last 12 months: Y/N______. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated. Sensor or Actuator & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Sensor & Location Location OK 1st Gage or BAS Value Instr. Meas’d Value Final Gage or BAS Value Pass Y/N? Gage reading = reading of the permanent gage on the equipment. BAS = building automation system. Instr. = testing instrument. Visual = actual observation. The Contractor’s own sensor check-out sheets may be used in lieu of the above, if the same recording fields are included and the referenced procedures are followed. • All sensors are calibrated within required tolerances...................................___ YES ___ NO -- END OF CHECKLIST -- Notes: File: PC Refrigpipe.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 3 Start-up Plan. Form C-8 _________ Plan and Documenting Requirements for Startup and Initial Checkout Primary Equipment and Tag:_____________________________________ Component or Related Equipment Included: ________________________ ____________________________________________________________ Project: ___________________________________ Date: ______________ The purpose of documenting the startup and checkout process is to ensure to the Owner that all recommended startup and initial checkout procedures are completed and that a written record of the work is generated. PLAN and REQUIRED PROCEDURES: 1. The prefunctional checklists provided by _____________________________________________ should be filled out and signed for the above primary and related equipment. 2. The manufacturer recommended field startup and checkout sheets should be fully filled out. These startup and checkout sheets ___are attached, ___are not attached. 3. On the manufacturer field startup and checkout sheets, the recommended ranges for readings taken shall be added to each reading field and an explanation given for any variances. 4. Additional documentation: ___ Further documentation beyond the above is required as follows: The attached pages have been copied from the ____________________________________________ installation manuals submitted to __________________________________. They have had paragraphs and sections identified and marked with a signature lines in the margins. Separately for each piece of equipment, during startup and checkout, the technician should check and date each check box and initial and date each line made for that purpose, signifying completion of the task. All readings and settings shall be recorded, not just checked. Provide clear, written notes at the bottom, margin or back-side of each page, as necessary. Written notes shall be provided for why an item was not done or does not apply. A signature and date of the startup technician shall be provided at the end of the startup and checkout documents. Other pages applicable to this piece of equipment in the installation manual or any other procedures completed should be added. ___ No further documentation beyond the attached checklist and the manufacturer’s installation and startup sheets are required: This list of procedures does not constitute a recommendation of the full installation and startup procedures or release the installer from following all factory recommendations, the specifications, applicable codes and good practice. All stock startup record forms normally generated should be filled out and submitted. All documentation should be submitted to ____________________________________________ upon completion and is required prior to the execution of functional testing. File: PC STARTPLN.doc, 6/2/2010Commissioning Guide Specification --PECI / USDOE 1 VFD PREFUNCTIONAL CHECKLIST PC-_______ Prefunctional Checklist Project ____________________________________ PC-_____ VARIABLE FREQUENCY DRIVE on __________________________________ 1. Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This prefunctional checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. ___ List attached. ____________________________ ______________ _____________ _________________________ Mechanical Contractor Controls Contractor Date ____________________________ ______________ _____________ _________________________ Electrical Contractor Sheet Metal Contractor Date ____________________________ ______________ _____________ _________________________ TAB Contractor General Contractor Date Date Date Date Prefunctional checklist items are to be completed as part of startup & initial checkout, preparatory to functional testing. • • • • • This checklist does not take the place of the manufacturer’s recommended checkout and startup procedures or report. Items that do not apply shall be noted with the reasons on this form (N/A = not applicable, BO = by others). If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. “Contr.” column or abbreviations in brackets to the right of an item refer to the contractor responsible to verify completion of this item. A/E = architect/engineer, All = all contractors, CA = commissioning agent, TCC = controls contractor, EC = electrical contractor, GC = general contractor, MC = mechanical contractor, SC = sheet metal contractor, TAB = test and balance contractor, ____ = _______________________________________. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. Notes: File: PC VFD.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 1 VFD PREFUNCTIONAL CHECKLIST PC-_______ ____________________________ ______________ _____________ _________________________ Commissioning Agent Owner’s Representative Date Date Notes: File: PC VFD.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 2 VFD PREFUNCTIONAL CHECKLIST PC-_______ 2. Requested documentation submitted Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Check Manufacturer’s cut sheets Performance data (fan curves, coil data, etc.) Installation and startup manual and plan Sequences and control strategies O&M manuals • Documentation complete as per contract documents for given trade........................___ YES ___ NO 3. Model verification [Contr = ________] 1 = as specified, 2 = as submitted, 3 = as installed. Check if Okay. Enter note number if deficient. Equip Tag---> Manuf. Model Serial # Capacity 1 2 3 1 2 3 3 1 2 3 • The equipment installed matches the specifications for given trade..........................___ YES ___ NO 4. Installation Checks Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Check General Installation Permanent label affixed Securely mounted Drive location not subject to excessive temperatures Drive location not subject to excessive moisture or dirt Drive size matches motor size Pilot lights functioning VFD wired to controlled equipment Programming and Controls Internal setting designating the model is correct Input of motor FLA represents 100% to 105% of motor FLA rating Appropriate Volts vs Hz curve is being used Notes: File: PC VFD.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 3 VFD PREFUNCTIONAL CHECKLIST PC-_______ Check if Okay. Enter comment or note number if deficient. Equip Tag-> Contr. Check Accel and decel times are around 10-50 seconds, except for special applications. Record actual for each unit. Lower frequency limit at 0 for VAV fans and around 10-30% for chilled water pumps. Record actual for each unit. Upper frequency limit set at 100%, unless explained otherwise VFD interlocked to control system Static or differential pressure sensor or other controlling sensor properly located and per drawings Controlling sensor calibrated Unit is programmed with full written programming record submitted RPM readout in BAS verified with VFD readout All control devices, pneumatic tubing and wiring complete Specified sequences of operation and operating schedules have been implemented with all variations documented Specified point-to-point checks have been completed and documentation record submitted for this system Final Startup report completed with this checklist attached Safeties installed and safe operating ranges for this equipment provided to the commissioning agent • The checklist items of Part 4 are all successfully completed for given trade. ...........___ YES ___ NO -- END OF CHECKLIST -- Notes: File: PC VFD.doc Commissioning Guide Specification --PECI: 6/2/2010 --Large Buildings 4