Underground Electrical Duct Bank McCauley Street Pittsboro Street South Columbia Street McCauley, Pittsboro, and Columbia Street August 9, 2006 Neighborhood Meeting Construction Process Underground Electrical Duct Bank •Purpose –Increase reliability and capacity of power to campus facilities and UNC Hospitals –Provides a critical connection to the Manning Substation •Implementation –Install underground duct bank in McCauley, Pittsboro, and South Columbia Streets –Four phases: •Phase 1 RansomRansom-McCauley Intersection: Fall of 2006 with 1.5 month duration •Phase 2 McCauley Street: Winter of 2007 with 7 month duration •Phase 3 Pittsboro: Fall of 2007 with 4 month duration •Phase 4 S. Columbia: Fall of 2007 with 4 month duration •Needs to be complete by Spring 2008 McCauley, Pittsboro, and S. Columbia Street Construction Process Underground Electrical Duct Bank •Duct Bank Construction –Six foot wide trench in street and eight feet deep –6 inch conduits encased in concrete buried three feet below street •High voltage transmission and distribution circuits •Telecommunications and control circuits McCauley, Pittsboro, and S. Columbia Street Construction Process Underground Electrical Duct Bank Construction limited to Right of Way Approximately 6 new access vaults Phase 1 Construction: Intersection of McCauley and Ransom Streets Fall 2006 1.5 month duration Phase 2 Construction: McCauley Street Winter 2007 7 month duration McCauley Street Construction Process Underground Electrical Duct Bank No plantings, or retaining walls will be removed. Install in west bound lane (north side) Access vault will span from sidewalk to road 16’ 16’ x 8’ 8’ McCauley Street EXAMPLE CROSS-SECTION A Construction Process Underground Electrical Duct Bank Road Closed to Thru Traffic McCauley and Pittsboro Intersection Road Closure with DETOUR Pedestrian Traffic on north side closed to pedestrians McCauley Street Construction Process Underground Electrical Duct Bank East bound lane open for neighbor traffic Driveway access in evening TYPICAL STREET CONSTRUCTION Lane Closure with one way traffic McCauley Street Construction Process Underground Electrical Duct Bank Installed in sections to limit the number of driveways blocked to 1 to 3 driveways. Flaggers used to control one way access Section opened in evening for two way traffic TYPICAL STREET CONSTRUCTION Lane Closure with one way traffic McCauley Street Construction Process Underground Electrical Duct Bank Phase 3 construction: Pittsboro Street Fall 2007 4 month duration Left Lane (east side) closed Pittsboro Street Construction Process Underground Electrical Duct Bank Right lane open to thru traffic Pedestrian traffic closed on east side Pittsboro Street EXAMPLE CROSS-SECTION Construction Process Underground Electrical Duct Bank Lane Closure for crossing only (One lane at a time) Pedestrian traffic closed on east side Phase 4 construction: S. Columbia Street Fall 2007 4 month duration Duct bank installed off street Columbia Street Construction Process Underground Electrical Duct Bank Questions and Comments McCauley, Pittsboro, and S. Columbia Street Construction Process