SPECIFICATION of MATERIALS AND WORKMANSHIP required in the GROUND FLOOR EXTENSION, INTERNAL ALTERATIONS & LOFT CONVERSION at for Project Number May 2010 SPF BS 1.00 PRELIMINARIES 1.01 This specification is to be read with the Architect's drawings numbered 487.04A, 05A, 06B, 07B, 08A and the Structural Engineer's drawings numbered 10155 and these drawings will form part of the contract. 1.02 The Employer is 1.03 The Architect is 1.04 The Work consists of: 1) a Ground Floor Extension, 2) Internal alterations to both Ground and First Floors and 3) a Loft Conversion. 1.05 The contractor shall have access to that part of the garden necessary to carry out the work. Care must be taken to cause as little damage to the rest of the garden and as little inconvenience to the occupants as is possible. Connections to the existing accommodation shall be left as late as possible and shall be made at a time mutually convenient to the Contractor and to the occupants. Use of the garage space will be required by the occupants. 1.06 Vehicular access to the site will be only via 1.07 The Contractor will be responsible for making all necessary arrangements for access with the Local Authority and or adjoining owners. 1.08 The works embraced in this Contract shall be carried out in accordance with the printed Agreement for Minor Building Works 2005, issued under the sanction of the Joint Contracts Tribunal all of which conditions are held to be incorporated in and to form part of the Contract, subject however to the undernoted alterations, modifications and supplementary clauses. 1.09 Clauses in the Conditions of Contract shall be completed or modified as follows: Clause 2.2 Dates for commencement and completion to be agreed. Clause 2.8 Liquidated Damages for non-completion to be £250.00per week. Clause 2.10 Defects Liability Period shall be six months. Clause 3.6 Work is to be carried out by sub-contractors nominated by the Architect where and if indicated in the Specification. These items will be subject to the normal discounts and the Contractor should allow for any further profit required. Clause 4.2 For the purposes of the Statutory Tax Deduction scheme the Employer is not a “Contractor.” Clause 4.3 Percentage of Certified Value retained to be 5%. Clause 4.5 Half of Retention Fund to be released on Practical Completion. Clause 4.8.1 Documentation to be supplied within six months. Clause 4.11 Clause 4.11 shall be deleted. Clause 5.3.2 Contractor‟s Insurance cover for injury or damage to property Page - 1 SPF BS etc to be not less than £5,000,000:00. Clause 5.4A Clause 5.4A shall apply. Clause 5.4B Clause 5.4B shall be deleted. Clause 6.6 Clause 6.6 shall be deleted. 1.10 The Contractor shall be deemed to have visited and inspected the site and existing buildings and to have examined the drawings and contract documents before pricing and to have adequately acquainted himself with the local conditions, accessibility of the works, the nature of the ground and sub-soil, the availability and supply of materials, water, electricity and telephones and no claim of want of knowledge in such respects will be entertained. 1.11 The materials and workmanship shall be to the reasonable satisfaction of the Architect and shall be the best of their respective kinds. Materials and workmanship shall comply where applicable with the current British Standard or British Standard Code of Practice and the latest edition of the Technical Requirements for the Design and Construction of Dwellings published by the N.H.B.C. BS 8000-1 BS 8000-2 BS 8000-2.1 BS 8000-2.2 BS 8000-3 BS 8000-4 BS 8000-5 :1989 BS 8000-6 BS 8000-7 BS 8000-8 BS 8000-9 :1997 :1990 :1994 :1999 :1990 :1990 :2001 :1989 :1990 BS 8000-10 :1995 BS 8000-11 BS 8000-11.1:1995 BS 8000-11.2:1990 BS 8000-12 :1989 BS 8000-13 :1989 BS 8000-14 :1989 BS 8000-15 :1990 BS 8000-16 :1997 Code of practice for excavation and filling. Code of practice for concrete work, comprising; mixing and transporting concrete. Site works with in-situ and pre-cast concrete. Code of practice for masonry. Code of practice for waterproofing. Code of practice for carpentry, joinery, and general fittings. Code of practice for slating, tiling roofs, and claddings. Code of practice for glazing. Code of practice for plasterboard partitions and dry linings. Code of practice for cementitious levelling screeds and wearing screeds. Code of practice for plastering and rendering. Code of practice for wall and floor tiling, comprising; Ceramic tiles, terrazzo tiles, and mosaics. Natural stone tiles. Code of practice for decorative wall coverings and painting. Code of practice for above ground drainage and sanitary applications. Code of practice for below ground drainage. Code of practice for hot and cold water services. Code of practice for sealing joints in buildings using sealants. Page - 2 SPF BS 1.12 Water for the works must be clean and uncontaminated. If other than mains supply is proposed evidence of suitability must be provided including testing to BS 3148:1980 if so instructed. The existing mains supply to the house may be used provided this does not cause inconvenience to the occupiers. 1.13 The existing electric mains supply may be used, free of charge, provided this does not cause inconvenience to the occupiers and such use is not excessive. 1.14 Existing Hedgerows, planters and trees to be preserved must be fenced before building operations begin for protection. 1.15 Building materials intended for the works must be stored securely within the site and in accordance with the manufacturer's recommendations. The location of storage areas must be agreed with the occupants. 1.16 The Contractor must adequately safeguard the existing buildings affected by the works from damage by the weather and theft. He must take all reasonable precautions to prevent unauthorised access to the site, the works and adjoining property. 1.17 The Contractor must take all reasonable precautions to prevent excessive noise or other nuisance causing undue inconvenience to the occupants of the existing buildings and adjoining property or the general public. 1.18 The Contractor shall protect all existing public and private roads, footpaths, kerbs and other works from damage arising from the works. From time to time and when so requested, all roads and paved areas used must be thoroughly cleaned of mud and other debris and on completion must be left in a condition and state of repair equal to that prevailing at the commencement of the work. 1.19 The Contractor's sign board and any other advertisement shall only be displayed with the approval of the Employer and Architect. 1.20 A competent foreman is to be placed in charge of the site and he is to be in attendance during all working hours. 1.21 The Contractor must ensure that operatives employed are appropriately skilled and experienced for the type and quality of work undertaken. 1.22 The Contractor will need to provide Architect with Method and Risk Statements for the works to be undertaken, prior to commencement of any on-site operations. 1.23 If the Contractor for any reason deems it necessary to execute works outside normal working hours he shall obtain the consent of the Employer and the Architect before doing so. 1.24 The Contractor shall carry out everything necessary for the proper execution and completion of the works, whether or not shown or described, provided the same may be reasonably inferred from the drawings or this specification. Page - 3 SPF BS 1.25 The Contractor is responsible for setting out the works, taking site dimensions and checking the dimensions on drawings etc. Any discrepancies and inconsistencies are to be immediately notified to the Architect. 1.26 For the duration of the contract the Contractor is responsible for the health and safety of those working on the building site and those with authorised entry to it. He must comply with all relevant regulations in this respect. 1.27 The Contractor must give any notices required by the Local Authority and water, electricity, gas or telephone companies. 1.28 The Contractor is responsible for providing any temporary buildings for the accommodation of materials and site operatives. The Contractor must provide temporary sanitary accommodation for site operatives. Sanitary accommodation within the existing building may be used provided the minimum inconvenience is caused to the occupants and only following employer‟s confirmation of acceptance over the pre-contract meeting. 1.29 The Contractor shall provide a mobile telephone service to the site for the duration of the contract and pay all charges in connection with it. 1.30 The Contractor must protect the works from adverse weather conditions including rain and frost and from damage by subsequent operations. 1.31 The Contractor shall allow for the general attendance of trades on each other. 1.32 The Contractor must report any defects in the existing construction to the Architect without delay. He must obtain instructions before proceeding with work which may cover up or otherwise hinder access to the defective construction or be rendered abortive by the carrying out of remedial work. 1.33 The Contractor must provide all plant tools, scaffolding and the like necessary for the purpose of proper execution of the works and their inspection by the Architect or Engineer. 1.34 The Contractor shall remove all debris from the site as it accumulates and on completion remove all temporary buildings, plant and surplus materials, clean all glass outside and in and generally leave all clean and tidy. 1.35 At the completion of the Contract the Contractor must provide the Employer with a certificate indicating that the building carries the 10 year warranty of the National House Building Council. The Contractor must arrange for all inspections and pay all charges required by the N.H.B.C. 1.36 Include the sum of £4,000.00 for contingencies to be used as directed by the Architect and deducted in whole or in part if not required. Page - 4 SPF BS 2.00 DEMOLITION 2.01 All demolition work shall be carried out by an approved specialist demolition contractor who must be a member of the National Federation of Demolition Contractors and provide evidence of insurance cover equivalent to the requirements of the Conditions of Contract. 2.02 Pulling down is to be carried out in such a manner as to cause as little inconvenience as possible to the occupants of the existing building, to adjoining owners, or to the public and the Contractor will be held responsible for any claims which may arise from disregard of this clause. Debris is to be kept well watered during the work to prevent dust arising. 2.03 The Contractor must design and supply all shoring, needling and strutting, or other supports to walls, floors, roofs etc., necessary for the protection and safety of existing buildings and all fans, screens and other protection necessary to protect adjoining owners and the general public. 2.04 The Contractor shall alter, adapt and maintain all such temporary works as may be necessary from time to time and finally clear away and make good all disturbance. He will be held solely responsible for the safety of existing buildings on or adjacent to the site and temporary works, and the making good of all damage done. 2.05 Sound old bricks arising from the pulling down, if cleaned and approved by the Architect, may be reused in making up. Brick rubbish or other approved hard materials arising from the pulling down, may be used in making up levels under floors etc. All other materials not described to be re-fixed or stored and all rubbish and debris are to be removed from the site. 2.06 No rubbish or material to be discarded shall be burned on site. 2.07 Materials arising from the demolitions must not be stacked or allowed to accumulate on existing structures in such a way as to endanger their stability. The Contractor will be held entirely responsible for damage arising from this cause. 2.08 The Contractor shall be responsible for locating all existing services affected by the demolitions and arranging for their disconnection or diversion so that they may be entirely self-contained within the parts of the premises which are to remain. The Contractor shall give notices to water, gas, telephone and electricity companies and allow facilities for removing any fixtures, fittings or services which may belong to them and pay any charges arising. Page - 5 SPF BS 3.00 EXCAVATION AND GROUNDWORK 3.01 The contractor is advised to visit the site and satisfy himself as to the nature of the ground to be excavated, his prices will be deemed to include for excavating in any type of ground including "made ground" or granular material filling but excepting running sand, old foundations and rock (rock shall be defined as naturally occurring stone which, in the opinion of both parties to the Contract, can only be removed by the use of explosives, compressor tools or hammers and wedges; materials which can be excavated by means of mechanical excavators will be deemed not to be rock); and must include for breaking out or grubbing up and carting away any old tree roots etc., and breaking out and sealing off old drains, which may be encountered. No allowances will be made due to the failure of the Contractor to satisfy himself on these matters. 3.02 If loose or soft ground is met with, the Contractor shall excavate the same to a solid foundation and shall fill up the excavation with concrete, granular material or earth as the Architect directs. Such extra excavation and filling will be paid for at Schedule Rates. 3.03 In the event of the Contractor excavating below the proper level in good ground and as shown on the Drawings or excavating "battered" sides to trenches or if excavation side slips occur for whatever the reason he shall remove any debris and fill up the part so excavated or fallen with concrete, granular material or earth, as the Architect directs, at his own expense. 3.04 The responsibility for draining away, pumping and otherwise removing water will rest with the Contractor throughout the duration of the Contract. The methods employed shall, in all cases, be to the satisfaction of the Architect, and if water is removed by pumping, it shall be done so that the material in or around the excavation will not be disturbed by the pumping, and adequate sumps shall be provided. If water is pumped into a sewer the Contractor shall be responsible for any damage caused or any expense in removing from such sewer deposits caused by his work. The Contractor is not to employ continuous pumping methods which could withdraw water from foundations of adjoining buildings. 3.05 The Contractor is to give notice to the Local Authority and the Architect when the excavations are ready to receive concrete, and obtain approval that a secure foundation has been reached. 3.06 The Contractor is to take all necessary precautions to prevent damage to existing trees and hedgerows during excavations either by physical damage to roots or by altering ground levels around them. 3.07 The Contractor is responsible for locating all existing services and avoiding damage to and supporting them during excavation. Should any such damage occur the appropriate companies must be notified and the damage made good at the Contractors expense. Page - 6 SPF BS 3.08 The area of the site to be covered by new building is to be stripped of all top soil and vegetable matter to a depth of not less than 150 mm or any greater depth found necessary on site. 3.09 All excavated material not required, or not suitable for backfilling is to be removed from the site. 3.10 Any coins, antiquities or other objects of interest found whilst excavating are the property of the Employer and must be handed over to the Architect. 3.11 All re-filling of excavated material next to the foundations and in the trenches is to be done in layers not exceeding 225 mm thick. Each layer is to be compacted before the next is placed. Back filling in drain and service trenches must be carried out in accordance with the drain manufacturer's recommendations and the requirements of the appropriate Authorities. 3.12 Hardcore is to consist of clean, hard, dry, broken stone or other suitable approved material, free from dust and foreign matter, broken to pass a 75 mm sieve, thoroughly rammed and consolidated in layers not exceeding 150 mm. The specified thickness is to be the finished thickness after compaction with a roller. The top surface of hardcore is to be blinded with a minimum thickness of 25 mm sand or other approved material, and finished to exact levels to form a clean and solid formation. 3.13 All existing plants and paving affected by the excavations for New Extension are to be carefully removed prior to work commencing, stored while the work is carried out and reinstated on completion. Page - 7 SPF BS 4.00 CONCRETE WORK 4.01 The cement shall be Ordinary Portland Cement to BS 12:1996 stored in a dry place not in contact with the ground. 4.02 Course and fine aggregates for concrete work shall be in accordance with BS 882:1992. 4.03 Constituent materials for concrete shall be in accordance with BS 5328-1:1997, BS 5328-2:1997, BS 5328-3:1990 Admixtures must not be used unless specified or approved. 4.04 Water for concrete is to be clean and uncontaminated. Approval must be obtained if other than mains supply is proposed and in this case testing to BS 3148:1980 may be required. 4.05 It is the Contractor's responsibility to select a suitable concrete mix for each part of the work strictly in accordance with the requirements of BS 5328:1990 Parts 1 and 2 and NHBC regulations. 4.06 Unless otherwise specified the concrete mix shall be selected from the following table and in accordance with BS 5328:1990. USE GENERAL PURPOSE CONCRETE MIX Substructure Dry Ground Rough Binding Strip Foundations Trench Fill Other mass concrete C7.5P C7.5P House and garage ground floor slabs fully or nominally reinforced C20P Fill to wall cavities Solid filling under steps C10P C10P C10P C7.5P C7.5P C10P C10P C10P Superstructure Mild General Reinforced Concrete C20P 4.07 Wet and Poor Ground Exposure Moderate Severe C25P C30P Unless otherwise specified concrete mix portions shall be as follows: Fully or nominally reinforced concrete not exposed to the weather,per50 kg bag of cement; 115 kg Fine Aggregate 195 kg Course Aggregate 4.08 Ready mixed concrete may be used provided it complies with this specification and BS 5328:1997, and it is supplied by a British Ready Mixed Concrete Association Approved Depot and delivery notes are retained for inspection. The 3 minimum cement content of designed mixes shall be 220 kg/m . Designed mixes for reinforced concrete shall comply with the requirements of BS 8110-1:1997. Page - 8 SPF BS 4.09 Extra water must not be added to ready mixed concrete. 4.10 Where sulphates are present in the ground water, the ground or any adjacent material, the level of sulphates shall be determined and concrete mixes designed appropriately to resist sulphate attack. 4.11 Site mixed concrete shall be placed within 30 minutes. Ready mixed concrete shall be placed within 2 hours of water being added to the cement. 4.12 All concrete must be thoroughly compacted for its full depth by mechanical vibration unless otherwise approved. 4.13 Concrete must not be placed against frozen or frost covered surfaces or when the o air temperature is less than 5 C 4.14 Concrete shall be covered and protected from excessive heat or cold, rain, physical damage and movement for a period of seven days after placing. During dry weather the surface of the concrete shall be kept damp by watering through a rose for a period of seven days after laying. 4.15 Lay under all new solid floor slabs a membrane of 1200 gauge polythene sheet to BS 3012. Laps are not to be less than 150 mm formed into a welt (lapped and turned over). At the edges of the floor the membrane is to be turned up to and lapped with the D.P.C. in all walls.. 4.16 The insulation for concrete floors in contact with the ground is to be 100mm „CELOTEX‟ GA3000 or similar Insulation laid over Concrete Slab. A suitable Vapour Control Layer to manufacturer‟s recommendation to be laid over Insulation (under screed). Edge insulation of 20 mm thick „CELOTEX‟ TB3000 up-stand to be provided at all perimeters to the combined full depth of the screed and insulation and lapped into wall dpc. No chasing of the insulation layer for services will be permitted without the prior consent of the Architect. 4.17 The mild steel reinforcement shall conform in all respects with BS 4449:1997, and shall be clean and free from dirt, oil, paint, loose rust or scale or other harmful matter immediately before placing concrete. Bends hooks and cranks shall conform to BS 8666:2000, and BS EN ISO 4066:2000. Laps and splices shall be in accordance with BS 8110:1997 and all fabric reinforcement shall be side lapped one complete mesh. The steel shall be accurately fixed in position with bars securely wired together with No 16 gauge soft iron wire wherever necessary to prevent displacement during concreting. Specified cover of concrete shall be maintained by the use of approved spacing devices which shall remain in the concrete after use. Page - 9 SPF BS 4.18 All formwork shall be erected true to line, level and profile and shall be of sufficient strength to withstand displacement or distortion by the weight, placing and vibration of the concrete or loss of water. Wrought formwork shall comprise either wrought timber or rough finished timber lined with 10 mm thick plywood treated with 'Phenolic' resin or other approved material to produce clean, true and smooth surfaces free from shutter marks with true and well defined arises. 4.19 If a necessity arises for use of concrete lintels, Contractor to contact Architect for exact specification to be provided. Page - 10 SPF BS 5.00 STRUCTURAL STEELWORK 5.01 Hot rolled steel sections except angles to be to BS 4, Part 1, 1980, made from steel to BS 4360. 5.02 Hot rolled steel equal and unequal angles shall be to BS 4848, Part 4, 1972, made from steel to BS 4360. 5.03 Bolts, screws and nuts shall be to BS 4190 or BS 3692. 5.04 Washers shall be to BS 4320 5.05 Steel shall be blast cleaned in accordance with BS 4232. 5.06 Fabrication and erection shall be in accordance with BS 449, Part 2. All connections are designed by Structural Engineer to safely support the loads, reactions and bending moments imposed on the structure. Engineer‟s drawings, details and calculations to be strictly followed by Contractor. Holes shall be drilled, not punched and have all burrs removed. Bolt clearances shall have the tolerances indicated on the drawings. 5.07 All steelwork shall be prepared by removing all scale and rust, cleaned free from grease and dirt. Steelwork to be delivered on site painted with one coat red oxide primer. 5.08 Steelwork must not be stacked or handled before or during erection in such a way as would cause undue stress to the members or joints or damage to priming. 5.09 The Contractor must ensure that all steelwork installed is accurately lined, levelled and plumbed in accordance with the Engineer's drawings. 5.10 Lintels to openings in all walls shall be obtained from Catnic Lintels Limited, of types indicated on Architect‟s drawings, correctly sized for the span of the opening, with 150 mm minimum bearing at each end and d.p.c. over all in accordance with the manufacturer's recommendations. All Lintels to have a three course blue brick pad-stone under bearing. Page - 11 SPF BS 6.00 BRICKWORK AND BLOCKWORK 6.01 Facing bricks shall be 215 x 102,5 x 65 mm FL quality to match the existing in colour, surface texture and size - to comply with BS 3921:1995, and the manufacturer's specification, hard, square, sound, free from cracks and defects and even in size. 6.02 Semi-Engineering bricks for use below d.p.c. shall be 65 mm red, pressed engineering bricks to BS 3921-2:1995, Table 6, Class B and obtained from an approved manufacturer. 6.03 Building blocks for the inner leaf of cavity walls shall be 100 mm thick heavyweight concrete blocks (density 1800Kg/cub.m.) to comply with BS 6073:1981. 6.04 Building blocks for internal partitions shall be 100 mm thick heavy-weight concrete blocks (density 1800Kg/cub.m.) to comply with BS 6073:1981. 6.05 Components for mortar shall be in accordance with BS 5628:2001 Part 3. 6.06 Wall ties for cavity walls are to be of galvanised stainless steel, 200 mm long, to BS 1143:1978, built in at 750 mm centres horizontally and 450 mm centres vertically and staggered. Around openings ties shall be built in at 300 mm centres. 6.07 The damp proof course shall be of a high performance pitch polymer system BS 2782: 1996 and BS 5628: 2001, on two courses of blue bricks and to extend through the full thickness of all walls including pointing, with 100 mm overlap at joints sealed with Hyload mastic. The d.p.c. is to be at least 150 mm above adjacent finished ground level and continuous with existing d.p.c.s and new and existing d.p.m.s. 6.08 Cavity wall insulation shall be 70 mm CELOTEX CW-3000 cavity wall panel insulation built in as the work proceeds strictly in accordance with the manufacturer's instructions. Insulation Panels must be tightly butted with no mortar in the joints. 6.09 Cement mortar for use below d.p.c. shall be composed of one part by volume of cement to three parts sand. 6.10 Cement lime mortar shall be composed of cement, lime and sand in the proportions of one to one to six by volume. 6.11 Mortar mixes shall be selected in accordance with the brick or block manufacturer's recommendations and BS 5628:2001. 6.12 Mortars containing cement should be used within two hours of mixing the cement and mortar which has commenced to set must be discarded. 6.13 Workmanship shall generally be in accordance with BS 5628-32001 and Page - 12 SPF BS BS 8000-3:2001. All new brickwork and blockwork is to be set out and built to the respective dimensions, thickness and heights shown on the drawings. No broken or cut bricks or blocks are to be used except where required to maintain the bond. Making out existing facework shall be in matching bond. 6.14 All bricklaying shall be suspended when the temperature is less than 2 degrees Centigrade and completed brickwork shall be suitably protected from frost and other harmful weather conditions. 6.15 No portion of brickwork is to rise more than 900 mm above adjacent work and if temporarily stopped, it is to be stepped back at the angle appropriate to the bond. 6.16 All perpends are to be kept true, square and in facework plumb with the perpends above and below, and the joints are to be of uniform thickness. The whole is to be properly bonded and levelled around at floor level. 6.17 All brickwork is to rise four courses to 300 mm 6.18 All bricks are to be lightly wetted before use. Blocks are to be kept dry before laying. 6.19 Bricks for faced brickwork shall be selected from the stack and distributed evenly throughout the work so that no patches appear. Mix different deliveries which vary in colour to avoid horizontal stripes. Faced brickwork shall be pointed with a neat flush joint – to match existing as the work proceeds. The face of the brickwork shall be kept free of mortar splashes etc. and protected from staining by scaffolding, or any other cause. 6.20 The cavities of hollow walls are to be kept clear of rubbish and mortar droppings by movable boards or other approved method. 6.21 The bottom of the cavity is to be filled with fine concrete to 150 mm below d.p.c. level or ground level whichever is lower. Every fourth perpend at this level is to be left open. 6.22 Where reveal are formed in cavity walls the wall is to be built solid across the cavity and the outer skin is to be separated from the cavity filling by a d.p.c. fixed so as to ensure the weather-proof qualities of the wall. 6.23 Cavities over openings are to be bridged by a flexible d.p.c. falling towards the outer leaf, folded and cut so as to ensure the weather-proof qualities of the wall. Open perpends shall be formed in the outer leaf above the d.p.c. 6.24 All door and window templates are to be built in as the work proceeds and to be securely fixed to pallets of sound timber soaked in creosote, with long grain exposed, bedded in mortar and pointed up. Build in pallets for internal linings for doors etc., not less than 4 pallets at each side of opening. Page - 13 SPF BS 6.25 Where new openings are formed or existing openings adapted, reveals and the like are to be quoined up with new matching bricks or blocks as appropriate properly bonded to match existing and cut ,toothed and bonded at the junction with old work. Where making out face work is required following the filling of old door and window openings or the like this shall also include the removal and making out of the associated arches, lintels, cills, jambs and the like, unless specified otherwise. 6.26 Repointing old facework shall include raking out joints of all loose mortar and repointing in matching mortar in the same style of pointing. Any broken bricks, old pipe fixings, cemented up holes etc. shall be cut out and new bricks inserted. Any efflorescence, paint splashes, moss or other blemishes shall be removed by wire brushing. 6.27 Where new brickwork or blockwork is built up to, or against, existing it shall be properly toothed and bonded or connected by an approved stainless steel connection plate used strictly in accordance with the manufacturer's recommendations. In cavity walls old and new cavities shall be made continuous. 6.28 Generally allow for raking out for and repointing after all flashings, execute all cutting and bonding around openings, build in pallets, sills and lintels and chimney capping and padstones. Allow for filling between all joists and rafters. Cut holes and chases for pipes, conduits etc and make good. Page - 14 SPF BS 7.00 CARPENTRY AND JOINERY 7.01 All timber is to be well seasoned, free from large, loose and dead knots, decayed or waney edges, splits and any other defects which would render it unsuitable for its purpose. 7.02 Softwood for carpentry generally is to be in accordance with BS 4978:1996 and to the grades specified on the drawing. The timber is to be seasoned to a moisture content of or below the maximum values specified in BSCP 112: 1971 for its position in the structure before fabrication. 7.03 Softwood for joinery unless otherwise specified is to be European Redwood, European Whitewood, Douglas Fir or Western Hemlock and to conform to the requirements of BS EN 942-1:1996 (replaces BS 1186 Part 1). 7.04 Hardwood of the species specified shall be of prime quality, kiln dried, free from seasoning defects and of uniform colour and grain. 7.05 The moisture content of the timber for joinery when it is manufactured and delivered to the site shall come within the limits given in BS EN 942-1:1996, for each use, and shall be maintained until the building is completed 7.06 Plywood shall conform to BS EN 636-1:1997, -2:1997 and -3:1997 and DD ENV 1099:1998, bonding to be WBP, MR, or INT as specified on the drawing. Plywood shall be faced both sides with birch veneer and shall be grade 2 quality. 7.07 All new and replacement timbers used for structural work are to be supplied pretreated against insect and rot attack by pressure impregnation in accordance with BS 5268:1997 Part 5 and all cut surfaces and notches made on site shall be treated with a suitable brush applied preservative. 7.08 Joist hangers, timber connectors, framing anchors etc shall be of stainless steel and obtained from an approved manufacturer. 7.09 The plates, joists, rafters, purlins and other pieces used for the construction of the roof are to be of the sizes and grades specified on the Architect's and Engineer's drawings. All timbers shall be properly framed and secured with a suitable number and size of nails or as specified on the drawings. As far as possible, wall plates shall be in one piece between points of change of direction and joints where necessary and at corners shall be halved. Wallplates shall be secured to the inner leaf of cavity walls by 30 x 5 mm galvanised steel straps at 1.2 m max. centres. 7.10 Provide and fix across partition walls 100 x 50 mm bearers for cold water tanks in roof space. Page - 15 SPF BS 7.11 Floor and ceiling joists of the sizes and grades indicated on the drawing shall be built in to the inner leaf of external walls and lapped and spiked together at cross walls. Joists must not be notched at bearings. Joist hangers shall not be used except with the Architect's approval. Provide one line of herring bone strutting in the centres of floor joists where the span exceeds 2.5 m, with 150 x 38 mm struts well nailed and tightly wedged. Alternatively approved galvanised steel struts may be used. 7.12 Where holes are to be cut for the passage of pipes etc they must be confined to the middle third of the depth of the joist 7.13 The provisions of the Building Regulations shall be observed in the positioning of any timber adjoining a fireplace, flue or hearth. 7.14 Trimmer and trimming joists shall be the same depth as the common joists and of the thickness specified on the drawing. All mortise and tenon and half depth housing joints shall be accurately constructed so that the alignment of the members is maintained while the stresses of the connections are fully engaged. 7.15 Studding to partitions, casings, walls to dormers etc, shall be of the sizes specified on Architect‟s drawings. There shall be a sole and head plate and vertical studs at not more than 600 mm centres. Noggins shall be provided at not more than 1200 mm centres vertically 7.16 Allow for providing and fixing noggins where required in walls and ceilings for electrical, plumbing and other fixings. 7.17 Provide all necessary centring and templates for concrete and brickwork together with any temporary strutting, bracing, and support for the same. 7.18 Shavings, chippings, sawdust etc., shall be cleared away and must not be left in roof spaces, under suspended floors or in other hidden positions. 7.19 Where joinery is specified to be painted it shall be delivered to the site coated with an appropriate primer and all built in surfaces shall be primed. Where joinery is specified to be stained it shall be delivered to the site coated with one coat of an appropriate clear sealer in accordance with the recommendations of the stain manufacturer. Page - 16 SPF BS 7.20 All joinery work shall be carried out in accordance with BS 1176, Part 2:1971. including all necessary mortising, tenoning, grooving, matching, tonguing, housing, rebating, and other works necessary for correct jointing and fixing in the building whether or not specifically indicated on the drawing. All moulded work shall be accurately worked to the full size details supplied by the Architect. Where skirtings, architraves etc. are to match existing it is the contractor's responsibility to take accurate profiles on site. All skirtings, architraves, plates and other joinery works shall be accurately scribed to fit the contour of any irregular surface against which they may be required to form a close butt connection. It is the Contractor's responsibility to ensure that no joinery assembly is too large to be brought to its location in the building. 7.21 At eaves provide and fix ex 100 x 50 mm triangular tilting fillet and 6 mm external quality ply soffit as detailed on the drawing. 7.22 Supply and fix all eaves boards, barge boards eaves soffits and eaves ventilation strips (as described under Roofing) as shown on the drawings. 7.23 Floor boards to be ex 25 mm tongued and grooved softwood boards in about 90 mm face widths with ends butt jointed. Transverse joints are to occur over joist centres and no two adjacent boards shall have transverse joints over the same joist. Boards must be well cramped up before nailing and the nails punched below finished floor level. Access traps for electrical and plumbing installation to be screwed into place. 7.24 Supply and fix standard staircase with 250 mm treads and 180 mm risers with type of step, newels and balusters to match existing as far as practical. If not possible, Contractor to contact Architect for advice. Handrail and string capping to be match these of existing stair – if not possible, Contractor to contact the Architect for further advice. Allow for assembly and fixing on site. Newels, balusters, handrail and capping are supplied loose. Supply and fix matching newel, handrail, ballusters etc for landing ballustrade 1100 mm high. Exposed timber to be kept clean for clear lacquer finish. Provide 50 x 50 mm s.w. noggins at 600 mm centres to support plasterboard soffit to stair and ex 25 x 25 mm cover moulds to junction of plaster and string and around landing. Provide and fix ex 25 x 200 mm softwood lining to stair opening and trim to newels and string. 7.25 Door frames to all external doors to be securely fixed to pallets and built in as the work proceeds and pointed externally with mastic. 7.26 Linings to internal door openings to be 30 mm thick crosstongued painted softwood to extend the full thickness of the finished wall, securely fixed to pallets built into the blockwork. 7.27 External doors to be White U-PVC. 7.28 Existing Garage Door prepared to be treated and stained in White colour to match (in colour) New windows and doors. Page - 17 SPF BS 7.29 Internal doors including airing cupboard to be supplied with clear lacquer finish, to be delivered to site wrapped and the covering not removed until completion. 7.30 Window frames to be White U-PVC as indicated on the drawing, complete with standard hinges, casement stays, fasteners and adjustable ventilators. 7.31 Airing Cupboard to be provided with two dividing shelves of separate 50 x 25 mm wrought slats on 78 x 25 mm wrought battens plugged to side walls. 7.32 125 x 19 mm, or 175 x 19mm, or to match existing painted softwood skirtings with rounded top edge (or to match existing) to be fixed in all rooms internally. Skirtings to be nailed to rough grounds or to plugs fixed before plastering is carried out. 7.33 Architraves to be fitted to all openings internally, whether frames or lined, to be out of 78 x 25 mm, rounded on arises next to opening and with properly mitred corners and no joints elsewhere. 7.34 Provide and fix 25 mm U-PVC window boards, nailed to plugs, with rounded oversailing noses, extending 50 mm beyond the sides of the opening, grooved on underside for plaster to all rooms internally. 7.35 Provide and fix over all new window openings internally, ex 50 x 25 mm curtain track batten fixed in accordance with the directions of the lintel manufacturer. Tracks in all cases except in Bathroom and W.C. to extend 100 mm beyond each side of opening and are to fixed to face of wall 75 mm above soffit of window head. 7.36 Supply assemble and fix appropriate number of kitchen units to follow Architect‟s drawings and Client‟s recommendation. Client to suggest on desirable type and design of units. Allow for assembly, fixing and cutting worktops to size, forming close fitting mitred join at corners and cutting opening for inset sink. 7.37 Provide and fix in accordance with the manufacturer's directions Duraflex domestic type threshold strips at all external doors. Allow for raking cutting to bottom edge of doors to fit closely over strips. 7.38 Allow for supply only door furniture to be selected by the Client/Employer. Allow for fixing furniture as follows: Internal Doors: 1 pair fire-closing hinges, mortice lock or latch plus bolt on bathroom and w.c. doors Page - 18 SPF BS Airing Cupboard: 1 pair [stainless] steel butt hinges , dee handles and roller catches 7.39 Except where a painted, stained or polished finish is specified, all floors, stairs, landings and other joinery works shall be cleaned down, scrubbed and left in good order to the complete satisfaction of the Architect on completion. 7.40 All internal doors to be 30min FDs with self-closing hinges. Contractor to visit site and satisfy himself as to suitability of existing doors to provide 30min Fire Resistance and if proved insufficient, allowance for New 30FDs doors to be made. Page - 19 SPF BS 8.00 DRAINAGE BELOW GROUND 8.01 Pipes, bends,junctions, gullies and access fittings to be 100 mm SuperSleve flexible jointed vitrified clay to BS 65:1997 or U-PVC to BS 4660, Kitemark certified, manufactured by the Hepworth Iron Company Ltd and installed strictly in accordance with their recommendations. 8.02 Before starting work the Contractor must check invert levels and positions of existing drains, sewers, inspection chambers and manholes against information shown on drawings and report any discrepancies to the Architect. Adequately protect existing live drains and maintain normal flows during construction. 8.03 Transport, store, bed and joint pipes fittings and components in accordance with the manufacturer's site-work instructions. Store rubber jointing rings so that they are not exposed to sunlight. Lay pipes straight to line and true to gradient on an even bed for the full length of the barrel and joint using the recommended lubricants, leaving recommended gaps at ends of spigots to allow for movement. Adequately protect pipelines from the ingress of debris and seal all exposed ends of pipelines during construction. Carefully backfill in accordance with the manufacturer's instructions immediately after successful testing. 8.04 Excavate trenches to approximately 150 mm below invert level of pipes and with vertical sides up to 300 mm above crown of pipe and width at this point as narrow as practical but not less than the external diameter of the pipe plus 300 mm. Ensure that the trench bottom is free of hard or soft spots and lay bed of 10 mm single size granular aggregate to BS 882 across the full width of the trench. After testing lay and compact further granular material uniformly in 100 mm layers to 150 mm above the crown of the pipe. Above this level backfill with material excavated from the trench in well compacted layers not exceeding 300 mm thick. Mechanical compaction must not be used until there is a minimum of 600 mm of compacted material above the crown of the pipe. Trenches under roads to be backfilled with Granular Sub-base material type 1 Department of Transport clause 803. 8.05 Where the crown of the pipe is less than 300 mm below the underside of any concrete slab or less than 450 mm below the surface of any road or driveway the pipe must be provided with a concrete surround as specified below. Where the bottom of the drainage trench is lower than and less than 1 m from building foundations the pipe must be surrounded in 150 mm concrete and the trench filled with concrete up to the level of the foundation bottom. Where the trench is further than 1 m from the foundation but the depth of the trench below the bottom of the foundation is greater than the distance from the foundation (the critical level) the pipe must be surrounded by 150 mm concrete and the trench filled with concrete to a level equal to the critical level. 8.06 Where a concrete surround is specified above, form vertical construction joints in surround at face of pipe joints using 18 mm thick compressible fibreboard or polystyrene pre-cut to finished profile of concrete and pipes. Fill any gap between Page - 20 SPF BS spigot and socket with resilient material to prevent entry of concrete. Lay and compact bed of concrete grade C20 to BS 5328 (20 mm nom. max. size of aggregate) over full width of the trench to a level just clear of pipe couplings and allow to, set. Lay pipes on concrete bed and after testing place and compact further concrete to encase pipe up to a level 150 mm above crown or to other levels as specified above or shown on drawings. 8.07 Pipes passing through walls, foundations or other structural elements must be surrounded by 50 mm of compressible material and a lintel incorporated into the brickwork. Page - 21 SPF BS 9.00 PLUMBING INSTALLATION 9.01 The design and pipe sizing of the heating, sanitary, hot and cold water and gas installations shall be the responsibility of the Contractor subject to the routing of pipework being approved by the Architect. 9.02 The entire plumbing installation shall be designed and installed in accordance with good practice and any relevant British Standard Code of Practice and shall comply with the Building Regulations and the Water and Gas Companies regulations. The Contractor shall carry out any such tests as may be required to satisfy these regulations. 9.03 Rainwater gutters, downpipes and fittings shall be the „Roundline‟ system, or similar in black U-PVC to match existing manufactured by Osma and installed in accordance with their instructions. 9.04 Soil, waste and ventilating pipes, traps and other fittings shall be the jointed and fixed in accordance with the manufacturer's instructions. Pipe sizes shall be as indicated on the drawing. 9.05 Hot and Cold Water and Gas pipework shall be in copper to BS EN 1057:1996, BS EN 12449:1999, and BS EN 12451:1999, and shall be fixed with single copper saddle clips except where lagging is required when two piece copper spacing clips shall be used. Fittings shall be of the capillary type to BS 864 using lead free solder. 9.06 Cold water storage cisterns (if applicable) shall be complete with purpose made lid and protected vent, to BS 4213:2001. Ball valves shall comply with BS 1212:1990 Part 1. 9.07 Hot water storage cylinder(s) shall be of copper and comply with BS 699 with integral insulation. Provision for immersion heater(s) supply and installation shall be made. 9.08 Supply, connect and fix only 3no low level w.c. suites including directly connected cistern, flush, seat and flap. Connect pedestal to soil pipe outlet using purpose made uPVC gasket. Fix pedestal and cistern using non-corrosive screws strictly in accordance with the manufacturer's instructions. 9.09 Supply, fix and connect only 3no vitreous china wash basins including (matching pedestals – if required by client), mixer taps, waste chains and plugs. 9.10 Supply, fix and connect only 1no stainless steel sink and drainer unit to be inset in kitchen worktop and to include mixer tap waste chain and plug. 9.11 Supply, fix and connect only 2nos vitreous china acrylic shower trays to include slotted waste. Contractor to allow for Shower Enclosures to be supplied and fixed. Page - 22 SPF BS 9.12 Supply, fix and connect only 2nos concealed shower mixing valves, including flexible hose, shower head and adjustable bracket. 9.13 Provide trapped standpipe and cold water supply for washing machine and dishwasher. Supply pipes must terminate with valves suitable for flexible hose connection. 9.14 Wherever possible pipework shall be out of sight under floorboards, in ducts or cupboards and in roof spaces or the like. Pipework shall be adequately fixed to walls and other surfaces. Care shall be taken to avoid vibration being transmitted from circulating pumps and noise caused by water hammer. Where exposed, pipes shall be neatly and unobtrusively arranged, running vertically or horizontally subject to any required falls. 9.15 Stop valves complying with BS 1010:1973 shall be provided on all hot and cold water services in the following positions: (1) On all cold water down services from a storage cistern at the cistern. (2) On all hot and cold water service pipes before every appliance, or range of appliances served. 9.16 Access doors shall be provided on all main soil and waste stacks with access panels in any enclosing structure as described under Carpentry and Joinery. All waste traps shall be accessible. 9.17 All water storage cisterns shall be insulated with purpose made plastic covered insulation jacket held with plastic straps. All pipe-work in roof spaces or other unheated areas shall be insulated with preformed foam pipe lagging adequately secured, without gaps. 9.18 The overflows from all cisterns are to be of a larger diameter than the supply pipes. They shall be carried through the external wall and terminate with a tee at least 100 mm from the outside face of the wall. 9.19 All water storage cisterns, cylinders and the like shall be adequately supported with joists, bearers and boarding etc and pipes shall be supported throughout their length to prevent misalignment. 9.20 The Contractor must include for extending the existing central heating system to serve the new extension/loft conversion, with sufficient radiators to maintain a temperature of 20 degrees centigrade when the outside temperature is 0 degrees centigrade. The Contractor must assess the capacity of the existing boiler to serve the new extension and advise the Architect accordingly. If capacity of existing boiler proves to be insufficient, New Boiler to be supplied and connected to the specification shown on Architect‟s drawings. Page - 23 SPF BS 9.21 Radiators shall be panel type, supplied by an approved manufacturer finished with heat resisting primer paint, and fixed in accordance with the manufacturer's instructions. All radiators shall have a wheel type C.P. radiator valve on the flow connection and a lock-sheild pattern radiator valve on the return connection. Wherever possible radiators shall be situated under windows. 9.22 The Contractor must include for extending the existing hot and cold water services to the new fittings. 9.23 Contractor to Include a suitable sum for additional builder's work in connection with services. Page - 24 SPF BS 10.00 ELECTRICAL INSTALLATION 10.01 The electrical installation is to be designed, supplied and installed by the Contractor to the requirements of this Specification and the Architect‟s drawings. 10.02 The installation must comply with the latest edition of the IEE Regulations for the Electrical Equipment of Buildings and the requirements of the local Electricity Company. The Contractor shall carry out any tests required to prove compliance, give all notices and pay all charges arising. Where installing, inspection and testing of electrical installations, either: 1. Use an Electrician / Installer registered with a Competent Person‟s scheme, or 2. Submit a Building Regulations Application, where: a) An Electrician registered with a recognised trade body such as NICEIC, ECA and NAPIT (who need not to be registered under a Competent Persons scheme) tests the works and issue a design, installation and test certificate under BS 7671 b) The work is carried out by an unregistered electrician or is a DIY installation, the applicant is required to have the work inspected and tested by a registered electrician as in part (a) above 10.03 Wiring generally shall be carried out using PVC sheathed cables complying with BS 6004:2000 and shall be concealed. As far as possible cables shall be run in the interfloor spaces or the roof void. Holes through joists shall be as near as possible to the neutral axis and in any case not less than 50 mm from the top of the joist. Cables shall be adequately supported and secured to avoid straining or kinking. In roof voids cables shall be secured by buckle clips at not more than 1 m centres. 10.04 The whole of the electrical installation and all other metal fixtures and fittings to be installed as part of the building shall be earthed in accordance with the requirements of the IEE Regulations and the Local Electricity Supply Company. 10.05 Cables concealed in plastered walls shall be protected by galvanised metal capping and as far as possible run vertically from floor or ceiling to the fitting. In no case shall the plaster cover be less than 6 mm. 10.06 All cables shall be spaced at least 230 mm from any pipes intended to carry hot water. The Contractor shall be responsible for checking the proposed runs of any such pipes before commencing wiring. 10.07 The Contractor shall check and confirm with Client/Empoyer the location of all fittings prior to the commencement of wiring, and should it be necessary to make minor adjustments to the location of any fitting this shall be done without charge. Page - 25 SPF BS 10.08 Switched socket outlets and fused connection units shall be supplied and installed in locations as directed by the Client/Employer. All socket outlets shall be 13A rating 3 pin shuttered, switched, rectangular pin pattern, complying with BS 1363:1995 Cooker control unit shall include 45A DP main switch and 13A switch socket outlet with neon indicators, faceplate marked "Cooker", complying with BS 4177:1992 and BS 1363:1995. 13A fused connection units shall comply with BS 5733:1979. Plate light switches and ceiling switches shall comply with BS 3676:-1:1989. Co-axial socket outlets shall comply with BS 3041:1985. Telephone socket outlets shall be B.T. approved. 10.09 Switch plates, socket outlets, fused connection units, co-axial socket outlets, telephone socket outlets and cooker control unit shall be flush pattern, white plastics fittings from the Capital range manufactured by Crabtree Electrical Industries Limited or similar approved, on concealed galvanised steel installation boxes complying with BS 4662:1989 fixed squarely and flush with wall surfaces. Socket outlets shall be generally positioned 450 mm above floor level or 200 mm above worktops and light switches under 1200mm above floor level. 10.10 All pendant light points shall be fitted with an approved white plastics ceiling rose complying with BS 67:1990, 450 mm white heat resisting flex and white plastics shade and lamp holder complying with BS EN 61184:1995. 10.11 If new consumer unit is required, this shall be metal clad and comply with BS 5486:1989 Miniature circuit breakers to BS EN 61008 and of adequate rating for the duty. Miniature circuit breakers to BS EN 60898:1991 shall be provided for all circuits. Sufficient ways shall be provided for lighting, ring main power circuits, electric cooker, immersion heater(s), garage, door bell and two spare. A list of circuits shall be provided clearly marked in ink. 10.12 Supply install and connect electric immersion heater(s) of the 1 kw/3kw split element type to BS 3456. 10.13 Supply install and connect 4nos extract ventilators, Expelair or similar (to specification shown on Architect‟s drawings) and controllers situated where shown on Architect‟s drawings and more specifically: 1) within re-formed Kitchen, 2) within re-formed Bathroom at First Floor, 3) new WC at First Floor and 4) new Bathroom within Loft. 10.14 From an agreed position in the roof void, run co-axial television aerial wire to the position(s) directed by Client/Employer, 450 mm above finished floor level, for T.V. aerial outlets. 10.15 From the position directed by Client/Employer for the BT telephone inlet, run suitable telephone connection cable to the telephone socket connection points, 450 mm above finished floor level. 10.16 Allow suitable sum for Builder‟s work in connection with services. Page - 26 SPF BS 11.00 ROOFING 11.01 Existing Roof Tiles removed from Rear part of Roof for Box-Dormer to be formed, to be re-used for Front Dormer. 11.02 Battens to be 50 x 25 mm softwood grade GS to CP112 part 2, preservative treated, fixed with galvanised steel cut or wire nails 65 mm long to each rafter. 11.03 Roofing felt underlay to BS 747:2000 Part 2 Type 1F to be fixed with galvanised steel extra large head felt nails 19 mm long parallel to eaves so that water will drain freely, with 150 mm horizontal laps and vertical laps not less than 100 mm wide coinciding with supports. Cut neatly and accurately around pipes. 11.04 Mortar for bedding and pointing to consist of 1:3 cement:sand. To be finished neatly and any residue removed. 11.05 Lead for flashings, saddles, pipe flanges etc. to be mild sheet lead to BS EN 12588:1999 unless specified otherwise. Flashings shall be in lengths of not more than 1.5 m and fixed with lead wedges at not more than 400 mm centres. 11.06 Each course of tiles must be laid with tails aligned using special tiles at ends of courses to maintain bond and to ensure that cut tiles are as large as possible. Tiles must be fixed in accordance with the manufacturers recommendations using aluminium nails, with minimum head lap to manufacturer‟s recommendation. 11.07 Form tiling edges and junctions using the specified and manufacturer's recommended fittings and accessories to match tile colour and finish unless specified otherwise. Fix edge tiles and fittings securely to neat true lines. Fix every tile adjacent to an edge or junction by nailing or clipping as appropriate. Ensure that all flashings are fixed with or immediately after tiling and are neatly dressed down. 11.08 At eaves (to Front Dormer) fix continuous fillet to support underlay and prevent water retaining troughs. Dress underlay into gutter and fix tiles with tails projecting to ensure that all water discharges into gutter. 11.09 Install „Glidevale‟ monovent, or similar Eaves Ventilation system (to Front Dormer and to main roof only if existing system proves to be insufficient) in accordance with the manufacturer's recommendations. Install in accordance with the manufacturer's recommendations Glydevale G3, or similar approved tile vents to match roof tiles in colour and profile at 1 m centres at high level on each roof slope (of Front Dormer and main roof only if it is proved that tile vents are either non-existent or insufficient). 11.10 Remove existing tiles, battens, underlay, etc., the minimum necessary to carry out the alterations, ensuring the minimum disturbance to adjacent tiles, re-use number of tiles necessary to „roof‟ dormer at Front and cart away the rest. Page - 27 SPF BS 11.11 Cover valley with strip of underlay 600 mm wide, under-lapping general underlay. Lay valley tiles loose and coursed in with general tiling. Cut adjacent tiles to fit neatly and fix the last tile in each unfixed course with 2 nails each. 11.12 At ridges lay a length of underlay to overlap by not less than 150 mm, securely fix ridge ventilation terminals at a rate of 1 per 2.8 m of ridge length, to manufacturers fixing instructions. Fix each roof tile in the last course of each slope and make weather-tight with ridge tiles laid to a true line with edges bedded and joints solidly bedded in mortar, neatly struck off flush as the work proceeds. 11.13 At junction of ridge with hip, valley, abutment, or higher roof slope fix code 4 lead saddle over the underlay. 11.14 Over plywood roof deck laid to falls, specified elsewhere, lay a vapour barrier of a single layer of BS type 3B glass fibre base felt bonded in hot bitumen, turned up at roof perimeters. Apply built up felt roofing system consisting of the following layers: Top Layer: High Performance Polyester base cap sheet, bonded in bitumen 2nd Layer: High performance Polyester base underlayer, bonded in bitumen 11.15 The horizontal surface of the roof shall be finished with a layer of 10 mm stone chippings in bitumen based adhesive compound. The areas not covered by chippings shall be finished with a mineral surfaced version of the specified top layer of roofing felt. 11.16 Any other flat-roof system proposed to be used, will be considered – subject to discussion and approval of the Architect. 11.17 At abutments with walls or parapets the roofing felt must be turned up the wall with an angle fillet, to finish at least 150 mm above the level of the finished roof, bonded to the turned up vapour barrier, and covered with a lead flashing specified elsewhere. 11.18 Where a gutter is indicated on the drawings a welted drip shall be formed in mineral surfaced roofing felt, over a timber batten, with 50 mm downstand, to discharge over the gutter. 11.19 The supply and installation of the roofing felt, insulation and vapour barrier is to be carried out by an approved specialist roofing contractor who must provide a minimum 10 year guarantee in respect of his materials and workmanship. On completion a copy of the guarantee must be handed to the Architect. 11.20 Fascia to Flat Roof to follow a „corbelled pattern‟ as shown on Architect‟s drawings. If further assistance / information is required, Contractor to contact the Architect. Page - 28 SPF BS 11.21 With regard to assembly, methodology, timber sizes etc adopted for each type of roof construction, refer to Architect‟s drawings and Structural Engineer‟s details, drawings and calculations. Page - 29 SPF BS 12.00 FLOOR WALL AND CEILING FINISHES 12.01 Cement for screeds shall be ordinary Portland Cement in accordance with BS 12:1989. 12.02 Sand for screeds shall be in accordance with BS 882 : Part 2 1992.. 12.03 All beds for screeds shall be well wetted, brushed clean and free from all mortar droppings etc and well brushed with clean water before laying commences 12.04 Floors indicated on the drawings to have a screed finish shall be rendered with cement and sand 1:3 trowelled to a uniform smooth finish free from trowel marks and other blemishes with the following maximum permissible deviations: From a 3 m straight edge : 6 mm. From a 1 m straight edge : 2 mm. Unless otherwise specified cast screeds continuously as far as possible, without joints. As soon as screed has set closely cover with polythene sheeting and keep in position for not less than 7 days and protect screed from physical damage. The screed shall be reinforced with galvanized wire mesh positioned at approximately mid-depth of the screed. 12.05 Floor and wall beds and backings shall be in cement and sand 1:3 and to be finished to the satisfaction of the specialist executing the floor or wall finishing. 12.06 Plasters are to be Thistle board finish plaster and Carlite pre-mixed plaster manufactured by British Gypsum Ltd. All plastering on old, previously damp, brickwork shall be carried out using Limelite renovating plaster and finishing plaster manufactured by Tilcon Ltd., Special Products Division. 12.07 All plasters are to be mixed and used strictly in accordance with the manufacturer's printed instructions. 12.08 Include a p.c. sum of £25.00/sq.m. for supply only of carpet, or laminate or vinyl floor finishes to be carried out by a specialist. Include a suitable allowance for installation. Add for profit. Allow for general attendance. 12.09 Ceiling and timber partition wall linings shall be formed using 12.7 mm Gyproc Baseboard. Gyproc Duplex Plasterboard (foil-backed) shall be used where ceilings are under roof voids. Gyproc Moisture Resistant Plasterboard shall be used on partitions in wet areas. 12.10 Plasterboards shall be stored and used strictly in accordance with the manufacturers printed instructions. All joints and angles shall be filled with Gyproc joint filler and reinforced with 85 mm wide jute scrim embedded in plaster. Page - 30 SPF BS Plasterboards shall be finished with 'Thistle' board finish plaster 5 mm thick trowelled to a smooth but not polished surface. 12.11 All external angles in plasterwork are to be formed using Expamet stainless steel plaster or plasterboard beads as appropriate supplied by The Expanded Metal Company Ltd or similar approved. 12.12 Walls and floors shall be prepared for tiling in accordance with the recommendations of BSCP 212 : 1963 Section 3. 12.13 Walls to Kitchen (over work-tops only: up to 1,5m from Finished Floor Level, or up to the underside of wall-mounted units), First Floor WC (up to 1,2m from Finished Floor Level around corner of hand wash-basin only), First Floor and Loft‟s Bathroom (full height to all walls) shall be tiled with ceramic tiles to Client‟s/Employer‟s selection. Round edge and round edge corner tiles shall be used on all external angles and corners and tiling shall be continued into the reveals of all window and door openings within the tiled areas. 12.14 Contractor to allow £25.00 / sq.m. for the supply only of tiles and allow for tiling all walls specified on 12.13. Include a suitable allowance for installation. Add for profit. Allow for general attendance. 12.15 Floors to Kitchen, First Floor Bathroom and WC and Loft‟s Bathroom shall be tiled with ceramic tiles to Client‟s / Employer‟s selection, UNLESS client instructs for another type of flooring (of the same supply cost / sq.m.) to be used on the above areas. A matching coved skirting shall be provided at the junction with all walls including purpose made internal and external angle fittings. Matching bull nosed edge and corner tiles shall be used at external angles and corners. 12.16 If vinyl tiles (or sheet vinyl) are selected to be used by client on any area (to be confirmed over pre-contract meeting), supply cost to be £25.00 / sq.m. The tiles shall be laid strictly in accordance with the manufacturer's instructions using the recommended adhesives. Before tiling commences the sub-surface must be dry and clean in accordance with the tile manufacturer's recommendations. Boarded floors must be covered by sheets of 6 mm plywood fixed with 1mm gap between sheets with annular ring shank nails at 150 mm centres in all directions. Page - 31 SPF BS The flooring material must be stored on site at a minimum temperature of 18 degrees centigrade for 24 hours before laying. All seam joins must be heat welded, using the manufacturer's welding rod in a matching colour, to afford a continuous finish (in case of vinyl sheet). In bathroom, shower room and w.c. (if required by client instead of ceramic tiles) form vinyl sheet into 100 mm high skirting with manufacturer's recommended cove former and plastic capping strip and welded mitred corners. 12.17 All wall and floor tiling shall be carried out in accordance with BSCP 212 and the recommendations of the British Ceramic Tile Council and the tile manufacturer. Tiles shall be set out from the centre line of each wall or panel with either a full tile or a joint at the centre. 12.18 Jointing of wall tiles is to be in white cement based waterproof grouting as recommended by the tile manufacturer for wet areas. All joints between sanitary fittings, Kitchen worktops and vanity units and tiling to be sealed with white Dow Corning or similar silicone sealant, neatly pointed. 12.19 Jointing of floor tiles is to be in matching cement based waterproof grouting as recommended by the tile manufacturer for wet areas. 12.20 All tiled surfaces are to be washed down and left clean on completion. 12.21 All finished floors must be protected from any following operations and any damage made good at the Contractor's expense. Page - 32 SPF BS 13.00 GLAZING 13.01 The whole of the glass shall be of British manufacture to BS 952, Part 1:1995, free from spalls, cracks, bubbles or other defects. 13.02 Clear sheet glass shall be Ordinary Quality (O.Q.). Clear float glass shall be General Glazing (G.G.) quality. 13.03 Obscured glass shall be Pilkington. 13.04 If half hour fire resisting glass is required, Contractor to contact the Architect for exact specification and further instructions. 13.05 All safety glass to be tested and marked in accordance with BS 6206:1994, thickness 6 mm unless otherwise indicated. Safety glass to external high level glazing to be toughened. All other safety glass to be toughened or laminated. 13.06 Double glazing units shall be 28 mm thick sealed units consisting of two sheets of 6 mm float glass and an 16 mm cavity sealed by aluminium edge section. Units to be installed in Loft‟s bathroom are to have inner pane of obscure glass as per 13.03, only if required by client. Units installed in locations requiring safety glass shall have both panes of safety glass. 13.07 All glazing shall be carried out in accordance with BS 6262:1994. 13.08 Safety glazing to be specified and installed in positions suggested on Architect‟s drawings. 13.09 On completion all glass shall be cleaned inside and out and left perfect. 13.10 Mirrors within Bathrooms and WC to be 6 mm Electro-copper backed clear float glass with polished edges, four times drilled for and plugged and screwed to wall with chromium plated dome head screws and nylon washers. Page - 33 SPF BS 14.00 DECORATION 14.01 All paints, stains and other materials are to be supplied in the manufacturers' sealed containers and are to be obtained from approved manufacturers. 14.02 All materials must be stored and used strictly in accordance with the manufacturer's instructions and BS 6150:1991. 14.03 All ironmongery and other removable fixtures and fittings, including radiators and electrical fittings, shall be removed prior to decoration and cleaned and re-fixed on completion. 14.04 Floors and any fittings etc which cannot be removed must be protected during decoration from damage and from marking by paint. 14.05 The Contractor is to allow for complete decoration and redecoration internally of the affected from works areas ONLY. 14.06 All surfaces to be painted shall be prepared in accordance with the paint manufacturer's recommendations. 14.07 No painting shall be carried out during wet, frosty or foggy weather or upon surfaces not thoroughly dry. Areas must be free from dust before painting is commenced. All newly painted surfaces must be protected from dust or other injury. 14.08 All finished paintwork and stain shall be uniform in colour, free from blemishes, runs, etc., and conspicuous brush marks. 14.09 Preparation of softwood joinery for painting shall include treating all knots with two thin coats Pure Shellac Knotting, priming with 1 coat pink wood primer internally and 1 coat aluminium wood primer externally, stopping with White Lead Putty and rubbing down to smooth keyed surface. 14.10 Pipework and other metalwork for painting shall be thoroughly cleaned, degreased and primed with 1 coat Zinc Chromate Primer P13. 14.11 Painted joinery shall be supplied to site finished with one coat primer. 14.12 Joinery for staining shall be supplied to site finished with the manufacturer's basecoat stain. Any cut ends shall be treated with two coats of preservative and one brush coat of penetrating stain before building-in Page - 34 SPF BS 14.13 Where and if required, carefully and completely burn off old paintwork to expose the timber. Rub down with dry glass-paper to produce a clean, firm, smooth surface and well dust down. Remove all nails and screw heads, or sink beneath the surface. Gouge out large and loose knots and replace with sound timber. Apply two thin coats Pure Shellac Knotting to all knots. Apply Wood and Metal Primer well into grain and cover all surfaces, including thoroughly primimg all end grains. Fill all cracks and holes with White Lead Putty. 14.14 Plaster surfaces shall be clean of all efflorescence, dirt, plaster splashes, etc., and all cracks, imperfections and damaged plaster shall be cut out and the edges undercut. Large cracks shall be made good with Keene's or other approved cement and small cracks filled with Polyfilla or similar filler. 14.15 If and where applicable, existing wallpaper and lining paper to areas affected by works ONLY is to be removed from walls and ceilings by thoroughly soaking with warm water and using a broad scraper, taking care not to damage plaster. Wash down new surface to remove any old size, paste, paper debris, etc., and make good any cracks. When dry, glass paper over surface and apply coat of size. Hang selected paper – to match existing as far as practicle (if applicable) with good paste of stout consistency well brushed out. 14.16 All new and existing-affected joinery, pipe work, radiators and other painted metalwork to be prepared and finished with 2 coats oil based undercoat and 1 coat oil based top coat, gloss finish, to colours selected by the Client / Employer from the range indicated in BS 4800:2000. 14.17 All hardwood surfaces internally (if applicable) to be prepared and finished with two coats Sikkens Cetol TS Interior lacquer, in a colour selected by the Client / Employer from the standard range, sanding very lightly between coats. 14.18 New external joinery to be prepared and finished with two coats Sikkens Cetol THB lacquer. 14.19 After preparation, all walls and ceilings either New or Existing affected by works, except where tiled are to be hung with woodchip paper and finished with 2 coats vinyl matt emulsion paint, the surface having been first primed with 1 dilute coat or specialist primer. Contractor to base his quote on the possibility for Client / Employer to request for wallpaper on certain areas. Page - 35 SPF BS 15.00 EXTERNAL WORKS 15.01 Carefully take up existing paving slabs before construction is commenced and store for re-use. 15.02 If required, supply and lay pressed precast concrete paving slabs to match existing. Slabs are to be laid with staggered bond with joints of 2-5 mm and stabilised with several passes of a plate vibrator. Sweep fine dry sand over the paved surface and vibrate until all joints are filled with sand and sweep away surplus. 15.03 Contractor to make sure that all tree(s) and planting beds are protected throughout duration of works. If works relating to New Planting is required as part of the works, Contractor to inform and liaise with Architect in this respect. 15.04 As works in relation to proposed development will involve alterations to Side Lobby, Contractor to make sure that there is a suitable sum allowed for modifications / adjustments to Side Lobby‟s roof and Finished Floor and these operations will form part of the Contract Works. Page - 36