Widening and Reconstruction of Malavalli to Pavagada Section of SH-33 and SH-3 in Karnataka State on BOT (Annuity) Basis Request for Proposal Part-III Non Technical Schedule SCHEDULE- J TESTS TO BE CONDUCTED 1 GENERAL: 1.1 All materials to be used, all methods adopted and all works performed shall be strictly in accordance with MOSRT&H (earlier known as MORT&H) Specifications for Road and Bridges works. For this purpose as responsibility of contract as mentioned in Section 900 shall be taken up by the Concessionaire and the responsibility of Engineer shall be taken up by Independent Consultant/PIU-KSHIP. 1.2.1 The Concessionaire shall carry out quality control tests on the materials and work at the frequency stipulated in Section 900 of MOSRT&H’s (earlier known as MORT&H) Specifications for road and Bridges works. In the absence of clear indications about the method and/or frequency of tests for any item, the instructions of the Independent Consultant/PIU-KSHIP shall be followed. 1.3 The Concessionaire shall carry out all necessary tests on materials and work independently and keep their record for reference. The Concessionaire shall prepare a quality audit manual in consultation with Independent Consultant to ensure better quality of work. Following circulars of MOSRT&H’s (earlier known as MORT&H) and IRC codes may also be referred. a) IRC:SP-11” Handbook of Quality Control for construction of Roads and Runways” b) IRC:SP-47”Guidelines on Quality systems for Road Bridges (Plain, Reinforced, Pre stressed and composite concrete) c) IRC:SP-51 “Guidelines for Load Testing of Bridges” d) IRC:SP-57 “ Guidelines for Quality Systems for Road Construction” e) MoSRT&H’s (earlier known as MoRT&H) Circular No. RW/NH-34059/1/96S&R dated 30.11.2000”Revised Interim Specifications for Expansions Joints” 1.4 Above stipulated requirements for tests and quality control are minimum. The Concessionaire shall conduct all possible tests to ensure quality construction. 1.5 Independent Consultant, at his discretion and consistent with sound engineering practice, shall carryout any non-destructive tests on pavement, structure and any other component to ascertain the soundness of work. ____________________________________________________________________________________________________ Project Implementation Unit-KSHIP Page J-1 Widening and Reconstruction of Malavalli to Pavagada Section of SH-33 and SH-3 in Karnataka State on BOT (Annuity) Basis Request for Proposal Part-III Non Technical Schedule 2 Schedule for Tests 2.1 The Concessionaire shall, not later than 30 (thirty) days prior to the likely completion of work [2-Laning reconstruction], notify the Independent Consultant and PIU-KSHIP of its intent to subject the Project Highway to Tests, and not later than 10 (ten) days prior to the actual date of Tests, furnish to the Independent Consultant and PIU-KSHIP a detailed inventory and particulars of all works and equipments forming part of Project Highway. 2.2 The Concessionaire shall notify the Independent Consultant of its readiness to subject the Project Highway to Tests at anytime after 10(ten) days from the date of such notice, and upon receipt of such notice, the independent Consultant shall, in consultation with the Concessionaire, determine the date and time for each Test and notify the same to PIU-KSHIP who may designate its representative to witness the Tests. The Independent Consultant shall thereupon conduct the Tests itself or cause any of the Tests to be conducted in accordance with Article 16 and this Schedule-J. 3. Tests Visual and physical Tests: The Independent Consultant shall conduct a visual and physical check of Project Highway to determine that all works and equipment forming part thereof conform to the provisions of this Agreement. Test Drive: The Independent Consultant shall take test drive of the Project Highway by a Car and a fully loaded Truck to determine that the quality of service conforms to the provisions of this Agreement. Riding quality Test: Riding quality of each lane of the carriageway shall be checked with the help of a calibrated integrator as mentioned at annexure A of this Schedule. Pavement Composition Test: the thickness and composition of the pavement structure shall be checked on a sample basis by digging pits to determine conformity of such pavement structure with Specifications and Standards. The sample shall consists of one pit in each direction of travel to be chosen at random in each stretch of 5 (five) kilometers of the Project Highway. The first pit for the sample shall be selected by the Independent Consultant through an open draw of lots and every fifth kilometer from such first pit shall from part of the sample for this pavement quality Test. Cross-section Test: the cross-sections of the Project Highway shall be checked on a sample basis through physical measurements of their dimensions for determining the conformity thereof with Specifications and Standards. For the road portion, the sample shall consists of one spot to be selected at random in each stretch of 1 (one) kilometer of the Project Highway. The first spot shall form part of the sample which shall selected by the Independent Consultant through an open draw of lots and the spots located at every one kilometer from such first spot shall form part of the sample. For the bridge portion, one spot shall be selected at random by the Independent Consultant in each span of the bridge. Structural Test for bridges: All major and minor bridges constructed by the Concessionaire shall be subjected to the Rebound Hammer and Ultrasonic Pulse Velocity tests, to be conducted in accordance with the procedure described in Special Report No. 14; ____________________________________________________________________________________________________ Project Implementation Unit-KSHIP Page J-2 Widening and Reconstruction of Malavalli to Pavagada Section of SH-33 and SH-3 in Karnataka State on BOT (Annuity) Basis Request for Proposal Part-III Non Technical Schedule 1996 of the IRC Highway Research Board on Non-destructive Testing Techniques, at two spot in every span, to be chosen random by the Independent Consultant. Environment audit: The Independent Consultant shall carry out a check to determine conformity of the Project Highway with the environment requirements set forth in Applicable Laws and Applicable Permits. Safety Review: Safety audit of the Project Highway shall have been undertaken by the Safety Consultant as set forth in Schedule-L and on the basis of such audit, the Independent Consultant shall determine conformity of the Project Highway with the provisions of this Agreement. Completion / Provisional Certificate Upon successful completion of Tests, the Independent Consultant shall issue the completion Certificate or the Provisional Certificate, as the case may be, in accordance with the provisions of Article 16.4. ____________________________________________________________________________________________________ Project Implementation Unit-KSHIP Page J-3 Widening and Reconstruction of Malavalli to Pavagada Section of SH-33 and SH-3 in Karnataka State on BOT (Annuity) Basis Request for Proposal Part-III Non Technical Schedule Schedule J Annexure-A TEST PROCEDURE FOR MEASURING ROUGHNESS INDEX OF THE RIDING SURFACE OF A FLEXIBLE PAVEMENT EQUIPMENT- Bump Integrator Fitted in a Vehicle. Test Procedure: The following test procedure shall be adopted for the test. 1) Check that the installation and operation of the equipment is in order and meets the requirements prescribed in its operational manual. The tyre pressure of wheels should be prescribed. 2) The instrument shall be calibrated prior to its use for measurement as prescribed in its operational manual. 3) The operators shall familiarizes themselves with the Bump Integrator & other equipment associated with its operation using its Test Model before commencing a survey. 4) Generally a speed varying between 30 km/hour +/– 5 km/hour shall be maintained during measurements. The readings shall be taken for each carriageway independently. 5) The equipment shall run on two lane in both the directions once and the average to two values taken for its roughness index. 6) Pavement unevenness / roughness of two lane carriageway shall be obtained from the average of the values of the two lane recorded. 7) The roughness index value of obtained by sung the internationally accepted software associated with the equipment from the measured Bumps. 8) All date shall be properly recorded with appropriate referencing and stored in a prescribed manner as in the operational manual. 9) The roughness measurements shall be properly calibrated using the procedure recommended in the World Bank Technical Publication No. 46. Schedule –J ____________________________________________________________________________________________________ Project Implementation Unit-KSHIP Page J-4 Widening and Reconstruction of Malavalli to Pavagada Section of SH-33 and SH-3 in Karnataka State on BOT (Annuity) Basis Request for Proposal Part-III Non Technical Schedule Annexure – B LOAD TESTING OF A BRIDGE SUPERSTRUCTURE The load test shall be carried out to atleast one full superstructure check and establish the serviceability and working strength of the superstructure. 1 Test Load The “Test Load” is the equivalent static load equal to the impacted working design Live Load (applied in addition to all dead loads) placed for maximum effect (bending moment, shear, deflection, etc. as the case may be) and applied either through an appropriate test loading truck or through loading platforms resting on tyre contact area plates simulating and actual areas of wheels. 2 Load Application and Testing Procedure i. Fix deflection gauges (supported on unyielding supports) under the superstructure, just touching its soffit, at the pre-marked critical ‘Points’. ii. Apply the test load in five equal increments (including the weight of platforms of trucks in the first increment), allowing about two hours in between completion of one load increment and commencement of the next. About an hour after completing a load increment, note the deflections and any crack patterns together with maximum crack widths. iii. After measuring the deflections, etc. one hour after applying the fifth increment, i.e. the final load increment, keep the test load maintained for about 24 hours and again measure the deflections and crack widths (if any) iv. Remove the test load in five equal decrements, allowing about two hours in between completion of one load decrement and commencement of the next. Note the deflections and crack widths (if any) at the end of each load decrement. v. Note the deflection and crack widths (if any – 24 hours after removal of the test load in order to see whether the recovery is completed or there is any residual deflection, etc. 3 Acceptance Criteria i. Increase and decrease in deflections at a point shall follow a linear relations, with actual deflection not exceeding the theoretically estimated ones by more than 10%. ii. The maximum crack width in reinforced concrete shall not exceed 0.25 mm to 0.30 mm (but no cracks in case of prestressed concrete). iii. The deflection at the end of the 24 hours of maintaining the test load shall not exceed the corresponding values at the start of this 24 hours period by 5% and iv. The residual deflection at any point 24 hours after compete unloading shall not exceed 10% of the maximum observed deflection at the point (i.e. recovery: 90% or more); ____________________________________________________________________________________________________ Project Implementation Unit-KSHIP Page J-5 Widening and Reconstruction of Malavalli to Pavagada Section of SH-33 and SH-3 in Karnataka State on BOT (Annuity) Basis 4 Request for Proposal Part-III Non Technical Schedule Observation The cracks in reinforced concrete shall close upon removal of test load but may not completely disappear. ____________________________________________________________________________________________________ Project Implementation Unit-KSHIP Page J-6 Widening and Reconstruction of Malavalli to Pavagada Section of SH-33 and SH-3 in Karnataka State on BOT (Annuity) Basis Request for Proposal Part-III Non Technical Schedule Schedule – J Annexure – C Testing Procedure for Illumination Intensity by Luxmeter Instrument Luxmeter (make of renowned company) Basis Comparison with a calibrated Luxmeter standard lamp by renowned Photometric Lab. through a Test Procedure: Following steps shall be taken for the test • Calibration of the Luxmeter • Put off the lights to be tested • Take calibrated Luxmeter reading • Put on the lights in the area to be tested • Observe the Luxmeter reading • Difference (positive or negative) in addition with standard light luminance level will give the actual luminance of existing lighting system. Note:- The testing procedure shall be as per the Manual of the Luxmeter used. ____________________________________________________________________________________________________ Project Implementation Unit-KSHIP Page J-7