Protection System Modeling Paul McGlynn PJM System Planning 11/7/13 1 PJM©2013 Background • Table 1 of the NERC TPL Standard identifies transmission system performance requirements following various contingencies – Old TPL Standard referred to as Category A (no contingencies), Category B (events resulting from the loss of a single element) and Category C (events resulting in the loss of two or more elements) – New TPL Standard is similar but category of events are P0 through P7 2 PJM©2013 Issue • • Recently been suggested by a stakeholder that the TPL standards require the transmission planner to evaluate the failure of a blocking relay that would result in the simultaneous loss of two circuits Entity is suggesting the transmission planner should evaluate this type of an event as a Category C event based on the hi-lighted section of Table 1 on the right. 3 PJM©2013 Blocking Relay Failure Example • • • • Fault on Line A-C Line relays at substation A and substation C properly detect the Sub A fault and open the breakers shown Blocking relay failure on line C-E causes the breaker at substation E to incorrectly open for the fault Sub B on line A-C All breakers open at roughly the same time (typically on the order of 4 cycles for 230 kV and above facilities) 4 Sub C Sub D Sub E PJM©2013 Discussion • Table 1 of the old TPL standard requires the transmission planner to simulate “SLG Fault, with Delayed Clearing (stuck breaker or protection system failure)” on a transmission element • The same event in the new standard is “P5 Multiple Contingency (Fault plus relay failure to operate)” and requires the transmission planner to simulate “Delayed Fault Clearing due to the failure of a non-redundant relay protecting the Faulted element to operate as designed” on a transmission element • These are the only references to relay failures in the table of events that need to be simulated. 5 PJM©2013 Discussion • • • • PJM has historically applied the criteria by simulating faults with delayed clearing (i.e. the fault remains on the system longer) and simulating the resulting breaker operations due to the relay failure to operate. PJM evaluates all combinations of two single contingency outages as part of our N-1-1 testing however system adjustments are completed between contingencies PJM has not historically evaluated the simultaneous loss of two transmission elements due to a fault and the incorrect operation of a blocking relay as a “Category C” event Following are examples of events that PJM evaluates as part of our “category C delayed clearing” analysis 6 PJM©2013 Relay Failure - Delayed Clearing Example • • • Fault on Line A-C Line relays at substation A Sub A open the line breaker (in approximately 4 cycles) Primary line relays at substation C fail to operate. Back-up relays operate to Sub B clear the fault after some time delay (10-15 cycles) Sub C Sub D Sub E 7 PJM©2013 Breaker Failure - Delayed Clearing Example • • • • Fault on Line A-C Line relays at substation A open the line breaker (in Sub A approximately 4 cycles) Line relays at substation C operate to clear the fault but circuit breaker (shown in black) fails to clear the fault Sub B After some time delay, breaker failure relays at substation C open the breakers shown 8 Sub C Sub D Sub E PJM©2013 Discussion • • • • NERC standards require transmission planners to simulate multiple single contingency outages through our N-1-1 testing. However system adjustments are made after the first contingency and prior to simulating the second contingency. N-1-1 testing does not simulate two simultaneous single contingencies. Application of a criteria that would simulate the simultaneous outage of two unrelated BES facilities would likely require significant upgrades due to thermal issues and stability issues. Relay system considerations – Use other schemes that do not rely on a blocking signal to remain secure – Periodically test blocking signals to ensure they will work when required – Automatic reclosing considerations 9 PJM©2013 Discussion and Follow-Up? • • PJM does not believe that the NERC TPL standards require the transmission planner to simulate the simultaneous loss of two BES elements due to a fault on one facility and the incorrect operation of a blocking relay on an adjacent facility, as a category C event under the old standard or as a category P3 – P7 event under the new TPL standard. Do stakeholders believe PJM should be evaluating the simultaneous loss of two or more BES facilities due to a blocking relay failure? – PJM would need information from TOs on the location and the contingencies that could result • Other ideas? 10 PJM©2013