Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application SECTION 5 CONDITIONS OF CONTRACT PART II: CONDITIONS OF PARTICULAR APPLICATION TABLE OF CLAUSES CLAUSE & SUB-CLAUSE NAMES PAGE NO. Definitions.................................................................................................. 6 Sub-Clause 1.1 Definitions .......................................................................................................... 6 Sub-Clause 1.6 GENDER Specific Words................................................................................. 7 Engineer & Engineer Representative ..................................................... 7 Sub-Clause 2.1 Engineer’s Duties and Authority ..................................................................... 7 Sub-Clause 2.4 Appointment of Assistants................................................................................ 8 Sub-Clause 2.7 Site Meetings...................................................................................................... 9 Sub-Clause 2.8 Minutes of Site Meetings .................................................................................. 9 Assignment and Subcontracting.............................................................. 9 Sub-Clause 4.1 Subcontracting .................................................................................................. 9 Sub-Clause 4.3 Domestic Preference.......................................................................................... 9 Contract Documents ............................................................................... 10 Sub-Clause 5.1 Language and Law.......................................................................................... 10 Sub-Clause 5.2 Priority of Contract Documents..................................................................... 10 Sub-Clause 6.3 Disruption of Progress - Contractor to Examine Designs in Advance of the Works ............................................................................................................... 10 Sub-Clause 6.4 No Extension of Time - Contractor to Proceed with Works ...................... 11 Sub-Clause 6.5 Failure by Contractor to Submit Drawings.................................................. 11 Sub-Clause 6.6 Submission of Drawings for Approval.......................................................... 12 Sub-Clause 6.7 Metric Units ..................................................................................................... 12 Sub-Clause 7.6 Approved Drawing to be modified ................................................................ 12 Sub-Clause 7.7 Size of Drawings ............................................................................................. 12 Ethiopian Roads Authority Page 5.1 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 General Obligations................................................................................ 13 Sub-Clause 10.1 Performance Security ....................................................................................13 Sub-Clause 10.2 Validity of the Performance Security...........................................................14 Sub-Clause 10.3 Claims under Performance Security............................................................14 Sub-Clause 10.4 Cost of Performance Security ......................................................................14 Sub-Clause 11.1 Inspection of Site............................................................................................14 Sub-Clause 11.2 Access to Data.................................................................................................14 Sub-Clause 14.1 Programme to Be Submitted.........................................................................14 Sub-Clause 14.2 Revised Programme......................................................................................15 Sub-Clause 14.3 Cash Flow Estimate to be Submitted ...........................................................16 Sub-Clause 14.5 Supplementary Program...............................................................................16 Sub-Clause 14.6 Contractor to Expose Drainage Structures .................................................17 Sub-Clause 15.1 Contractor’s Superintendent........................................................................17 Sub-Clause 15.2 Language Ability of Contractor’s Representative......................................17 Sub-Clause 16.1 Contractor’s Employees ...............................................................................17 Sub-Clause 16.3 Language Ability of Superintending Staff .................................................17 Sub-Clause 16.4 Employment of Local Personnel...................................................................18 Sub – Clause 17.2 Unauthorized Work ....................................................................................18 Sub-Clause 17.3 Notice of Setting Out .....................................................................................18 Sub-Clause 19.1 Safety, Security, and Protection of the Environment .................................18 Sub-Clause 20.4 Employer’s Risks ...........................................................................................19 Sub-Clause 21.1 Insurance of Works and Contractor’s Equipment.....................................20 Sub-Clause 21.2 Scope of Cover................................................................................................21 Sub-Clause 21.4 Exclusions .......................................................................................................21 Sub-Clause 23.1 Third Party Insurance (Including Employer’s Property)..........................21 Sub-Clause 23.2 Minimum Amount of Insurance...................................................................21 Sub-Clause 24.2 Insurance Against Accident to Workmen ...................................................22 Sub-Clause 24.3 Liaison with Police, Labour Officers, etc. ...................................................22 Sub-Clause 25.1 Evidence and Terms of Insurance................................................................22 Sub-Clause 25.5 Source of Insurance .......................................................................................22 Sub-Clause 25.6 Insurance Notices...........................................................................................22 Sub-Clause 25.7 Notification to Insurers .................................................................................23 Sub-Clause 26.2 Inspection and Audit by the Funding Agency............................................23 Sub-Clause 28.2 Royalties..........................................................................................................23 Sub-clause 28.3 Copyright........................................................................................................24 Sub-Clause 29.1 Interference with trafic and adjoining properties ......................................24 sub-clause 29.3 Reinstatement and Compensation for Damage to Persons or Property.......................................................................................................................................25 Sub Clause 29.4 Protection of Existing Works and Services..................................................25 Sub-Clause 29.5 Protection of Survey Beacons .......................................................................26 Sub-Clause 30.5 Extraordinary Traffic .................................................................................26 Sub-Clause 30.6 Facilities for other Contractor’s .................................................................26 Page 5.2 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application Labour...................................................................................................... 27 Sub-Clause 34.3 Compensation for injury .............................................................................. 27 Sub-Clause 34.4 Costs covered ................................................................................................. 27 Sub-Clause 35.1 Returns of Labour and Contractor’s Equipment ...................................... 27 Commencement and Delays................................................................... 28 Sub-Clause 41.1 Commencement of Works ............................................................................ 28 Sub-Clause 44.1 Extension of time for Completion............................................................... 28 Sub-Clause 45.1 Restriction on Working Hours.................................................................... 31 Sub-Clause 45.2 Overtime Working ........................................................................................ 32 Sub-Clause 46.2 Monthly Progress Reports............................................................................ 32 Sub-Clause 47.3 Bonus for Early Completion ........................................................................ 32 Sub-Clause 47.4 Currency of Liquidated Damages ............................................................... 32 Sub-Clause 48.2 Taking over of Sections or Parts.................................................................. 32 Sub-Clause 48.3 Substantial Completion of Parts .................................................................. 33 Sub-Clause 49.5 Defects Liability Period of Replacements etc. ............................................ 33 Alterations, Additions and Omissions .................................................. 33 Sub-Clause 51.3 Design of Variations..................................................................................... 33 Sub-Clause 52.1 Valuation of Variations ................................................................................ 34 Sub-Clause 52.2 Power of Engineer to Fix Rates.................................................................... 35 Sub-Clause 52.3 Variations Exceeding 15 Percent ................................................................. 35 Sub-Clause 52.4 Dayworks ....................................................................................................... 35 Sub-Clause 53.1 Notice of Claims............................................................................................. 36 Sub-Clause 53.2 Contemporary Records ................................................................................ 36 Contractor’s Equipment ,Temporary Works and Materials............. 37 Sub-Clause 54.1 Contractor’s Equipment, Temporary Works, and Materials: Exclusive Use for the Works..................................................................................................... 37 Sub-Clause 54.9 Contractor’s Responsibilities for Licenses ................................................. 37 Sub-Clause 54.10 Equipment and Plant .................................................................................. 37 Measurement ........................................................................................... 38 Sub-Clause 55.2 Omissions of Quantities ................................................................................ 38 Sub-Clause 57.1 Method of Measurement............................................................................... 38 Sub-Clause 58.5 Provisional Items........................................................................................... 38 Sub-Clause 59.3 Design Requirements to be Expressly Stated ............................................. 38 Sub-Clause 59.5 Certification of Payments to Nominated Sub-Contractors ....................... 38 Certificates and Payment ....................................................................... 39 Clause 60 Certificates and Payment......................................................................................... 39 Sub-Clause 60.1 Monthly Statements ...................................................................................... 39 Sub-Clause 60.2 Monthly Payments ........................................................................................ 40 Ethiopian Roads Authority Page 5.3 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 Sub-Clause 60.3 Materials and Plant for the Permanent Works...........................................41 Sub-Clause 60.4 Place of Payment............................................................................................42 Sub-Clause 60.5 Retention Money ............................................................................................42 Sub-Clause 60.6 Payment of Retention Money........................................................................42 Sub-Clause 60.7 Advance Payment ..........................................................................................43 Sub-Clause 60.8 Time For Payment and Interest....................................................................44 Sub-Clause 60.9 Correction of Certificates..............................................................................45 Sub-Clause 60.10 Statement at Completion.............................................................................45 Sub-Clause 60.11 Final Statement ............................................................................................45 Sub-Clause 60.12 Discharge ......................................................................................................46 Sub-Clause 60.13 Final Payment Certificate ...........................................................................46 Sub-Clause 60.14 Cessation of Employer’s Liability ..............................................................47 REMEDIES............................................................................................. 47 Sub-Clause 63.1 Default of Contractor ....................................................................................47 Sub-Clause 63.2 Valuation at Date of Expulsion....................................................................47 Sub-Clause 63.3 Payment after Expulsion ...............................................................................48 Sub-Clause 63.4 Assignment of Benefit of Agreement............................................................48 Sub-Clause 63.5 Corrupt or Fraudulent Practices..................................................................48 Special Risks............................................................................................ 48 Sub-Clause 65.2 Special Risks...................................................................................................48 Sub-Clause 65.4 Projectile, Missile ...........................................................................................49 Settlement of Disputes ........................................................................... 49 Sub-Clause 67.1 Settlement of Disputes ...................................................................................49 Notices...................................................................................................... 49 Sub-Clause 68.2 Notice to Employer and Engineer ................................................................49 Default of Employer ............................................................................... 49 Sub-Clause 69 Default of Employer .........................................................................................49 Sub-Clause 69.1 Default of Employer .....................................................................................49 Sub-Clause 69.3 Payment on Termination...............................................................................50 Sub-Clause 69.4 Contractor’s Entitlement to Suspend Work ...............................................50 Sub-Clause 69.5 Resumption of Work .....................................................................................50 Sub-Clause 69.6 Suspension of Funding Agency’s Loan or Credit .......................................50 Changes in Cost and Legislation........................................................... 51 Sub-Clause 70 Changes in Cost and Legislation .....................................................................51 Sub-Clause 70.1 Price Adjustment ...........................................................................................51 Sub-Clause 70.2 Other Changes in Cost ..................................................................................51 Sub-Clause 70.3 Adjustment Formulae....................................................................................51 Page 5.4 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application Sub-Clause 70.4 Sources of Indices and Weightings .............................................................. 52 Sub-Clause 70.5 Base, Current and Provisional Indices........................................................ 52 Sub-Clause 70.6 Adjustment after Completion ...................................................................... 53 Sub-Clause 70.7 Weightings ..................................................................................................... 53 Sub-Clause 70.8 Subsequent Legislation ................................................................................. 53 Currency and Rates of Exchange.......................................................... 54 Sub-Clause 72.2 Currency Proportions................................................................................... 54 ADDITIONAL CLAUSES..................................................................... 54 Sub-Clause 73.1 Foreign Taxation ........................................................................................... 54 Sub-Clause 73.2 Local Taxation............................................................................................... 54 Sub-Clause 73.3 Income Taxes on Staff................................................................................... 55 Sub-Clause 74.1 Illegal Payments ............................................................................................ 55 Sub-Clause 75.1 Termination of Contract for Employer’s Convenience............................. 55 Sub-Clause76.1 Restrictions On Eligibility ............................................................................ 55 Sub-Clause 77.1 Joint and Several Liability ........................................................................... 56 Sub-Clause 78.1 Importation and Use of Dangerous Materials ............................................ 56 Sub-Clause 79.1 Details to be Confidential ............................................................................ 57 Sub-Clause 80.1 Official Visitors ............................................................................................. 57 Sub-Clause 81.1 Legal Provisions ............................................................................................ 57 Ethiopian Roads Authority Page 5.5 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 CONDITIONS OF CONTRACT PART II: CONDITIONS OF PARTICULAR APPLICATION DEFINITIONS SUB-CLAUSE 1.1 DEFINITIONS (a) The “Funding Agency ” includes any International Financial Agency, which lends or makes a grant to the Employer for the execution of the mentioned project. (i) The Employer is the party stipulated in the Appendix to Bid. (iv) The Engineer is the party stipulated in the Appendix to Bid. Amend sub-paragraph (a) (iv) also by adding the following words after the word “Conditions”: “Or any other competent person appointed by the Employer, and notified to the Contractor, to act in replacement of the Engineer.” Amend sub-paragraph (b) (v) of Sub-Clause 1.1 by adding the following words at the end: “The word ‘bid’ is synonymous with ‘tender,’ and the words ‘Appendix to Bid’ with ‘Appendix to Tender,’ and the words ‘Bid documents’ with ‘tender documents’.” Add Sub-Clause 1.1 (f) (vii) (Add the following after ...Site.) The aforesaid includes lands, waters, riverbeds and other places on, under, in or through which the Works are to be carried out including all offices, workshops or places where materials are to be stored or used for the purposes of the Contract. Add Sub-Clause 1.1 (g) (v): Page 5.6 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application “(g) (v) Dates shall be construed in accordance with the Gregorian Calendar.” SUB-CLAUSE 1.6 GENDER SPECIFIC WORDS Add the following Sub-Clause 1.6 “Whenever in the Contract Documents the word ‘men’ is used directly or as a suffix it means ‘woman’ or ‘women’ also. The word ‘he’ includes ‘she’ also.” ENGINEER & ENGINEER REPRESENTATIVE SUB-CLAUSE 2.1 ENGINEER’S DUTIES AND AUTHORITY With reference to Sub-Clause 2.1 (b), the following provision shall also apply: The Engineer shall obtain the specific approval of the Employer before taking any of the following actions specified in Part I, such approval to be copied to the Contractor: (a) Consenting to the subletting of any part of the Works under Clause 4; (b) Certifying additional cost determined under Clause 12 or Clause 53; (c) Determining an extension of time under Clause 44; (d) Issuing a variation under Clause 51, except: (i) In an emergency situation, as reasonably determined by the Engineer; or (ii) If such variation would increase the Contract Price by less than the amount stated in the Appendix to Bid; (e) Issuing any variation, if the sum of all variations issued has exceeded 5% of the Contract Price; (f) Certifying payment if the Contract Price will be exceeded; (g) Issuing any Taking-Over Certificate; Ethiopian Roads Authority Page 5.7 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 (h) Authorizing the use of Provisional Sums in excess of the monetary limit for variations; (i) Certifying additional payment under Clause 65; and (j) Major changes to the Design and/or Specifications. Minor changes to be notified to the Employer within 7 days. If, in the opinion of the Engineer, an emergency occurs affecting the safety of life or of the Works or of an adjoining property, he may, without relieving the Contractor of any of his duties and responsibilities under the Contract, instruct the Contractor to execute all such work or to do all such things as may, in the opinion of the Engineer, be necessary to abate or reduce the risk. The Contractor shall forthwith comply, despite the absence of approval of the Employer, with any such instruction of the Engineer. The Engineer shall determine an addition to the Contract Price, in respect of such instruction, in accordance with Clause 52 and shall notify the Contractor accordingly, with a copy to the Employer. SUB-CLAUSE 2.4 APPOINTMENT OF ASSISTANTS (Add as a paragraph to the existing clause) Assistants and inspectors are not authorized to accept work, to accept materials, to issue instructions, or to give advice that is contrary to the contract. Work done or material furnished, which does not meet the contract requirements, shall be at the Contractor’s risk and shall not be a basis for a claim even if the inspectors or assistants purport to change the contract. Assistants and inspectors may advise the Contractor of any faulty work or materials or infringements of the terms of the contract; however, failure of the Engineer or the assistants or inspectors to advise the Contractor does not constitute acceptance or approval. Page 5.8 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 2.7 SITE MEETINGS Section 5 Part II – Conditions of Particular Application Add the following Sub-Clause 2.7: “It is the duty of the Contractor or his Representative to participate in the Site Meetings. The Employer and the Funding Agency are also entitled to attend the Site Meeting through their representatives when ever they require. The purpose of the Site Meetings is to co-ordinate the Works with the Contractor, to register the time in relation to the Program and to record agreements made. The Engineer shall arrange for the first Site Meeting where future meetings shall be scheduled on a regular basis.” SUB-CLAUSE 2.8 MINUTES OF SITE MEETINGS Add the following Sub-Clause 2.8 “Minutes of the Site Meetings should be recorded. The Minutes of the Site Meetings shall be issued within 14 calendar days and shall be numbered consecutively. Minutes shall be deemed to have been received by the Contractor unless the Contractor gives notice at the following meeting that the Minutes were not received. Any objections to the Minutes of a Site Meeting shall be raised in writing prior to the succeeding Site Meeting. If the Contractor at this time has not received the Minutes of the Site Meeting, the objection must be given in writing to the Engineer not later than seven (7) working days after the subsequent receipt of the said Minutes.” ASSIGNMENT AND SUBCONTRACTING SUB-CLAUSE 4.1 SUBCONTRACTING Replace the first sentence of sub-clause 4.1 with the following: “The Contractor shall not subcontract more than forty percent (40%) of the Works”. SUB-CLAUSE 4.3 DOMESTIC PREFERENCE Add the following Sub-Clause 4.3 Ethiopian Roads Authority If the Contractor consists of a joint venture of domestic and foreign firms which is awarded the contract through the application of the 7½-percent domestic preference, the Contractor shall not, without express approval of the Employer, Page 5.9 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 modify the profit and loss distribution and work-sharing characteristics of the joint venture with which it satisfied the criteria of eligibility for being awarded the Contract with the application of the domestic preference. CONTRACT DOCUMENTS SUB-CLAUSE 5.1 LANGUAGE AND LAW a) The language is stipulated in the Appendix to Bid. b) The law is that in force in the country stipulated in the Appendix to Bid. SUB-CLAUSE 5.2 PRIORITY OF CONTRACT DOCUMENTS Delete the documents listed 1-6 and substitute: (1) The Contract Agreement (if completed); (2) The Letter of Acceptance (3) The Bid, the Appendix to the Form of Bid, and the Bid Addendum including the Minutes of Negotiation (4) The Conditions of Contract, Part II; (5) The Conditions of Contract, Part I; (6) Method of Measurement (7) The Special Specifications (8) The Standard Specifications (9) The Drawings; (10) The Priced Bill of Quantities (11) Other documents, as listed in the Appendix to Bid SUB-CLAUSE 6.3 DISRUPTION OF PROGRESS CONTRACTOR TO EXAMINE DESIGNS IN ADVANCE OF THE WORKS Page 5.10 Amend Clause 6.3 to read as follows: "The designs for this project have been prepared by the Employer in accordance with current engineering practice. Never-the-less, clarification or revision of the designs may become necessary in order to rectify inconsistencies or discrepancies between the original design assumptions including materials investigations, topographical surveys and setting-out marks, and their interpretation that were used in the design of the Works, and the actual conditions encountered on the Site during the course of the Works. (a) Therefore, immediately on being granted possession of the Site, the Contractor shall examine the adequacy of the Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application designs for the project in terms of materials information, setting out marks, topographical surveys, Drawings and Bills of Quantities and shall give notice to the Engineer at least 120 days in advance of actual constructional requirements, with a copy to the Employer, of any inconsistencies or discrepancies in the designs which are likely to delay or disrupt the planning or execution of the Works unless further drawings or instructions are issued by the Engineer. As the Works progress, the Contractor shall review the adequacy of the designs at six (6) monthly intervals. (b) Within 90 days of the said notice, the Engineer, in consultation with the Employer, shall issue any clarification or revision of the designs for the project that is required in order to rectify inconsistencies or discrepancies between the original design assumptions including materials investigations, topographical surveys and setting-out marks, and their interpretation that were used in the design of the Works, and the actual conditions encountered during the said examination of the original designs or during the course of the Works.” (c) The Contractor shall provide the necessary personnel, facilities, equipment, vehicles and support staff to undertake all necessary investigations and calculations for such examinations of the designs. SUB-CLAUSE 6.4 NO EXTENSION OF TIME CONTRACTOR TO PROCEED WITH WORKS Amend Sub-Clause 6.4 to read as follows: “If, within the time stated above, the Engineer fails to issue, any clarification, drawing or instruction for which notice has been given by the Contractor in accordance with Sub-Clause 6.3, the Contractor shall, after giving fourteen (14) days’ notice to the Engineer, proceed in accordance with the existing designs and shall not be entitled to any extension of time for such failure by the Engineer.” SUB-CLAUSE 6.5 FAILURE BY CONTRACTOR TO SUBMIT DRAWINGS Amend Clause 6.5 to read as follows: “If the failure or inability of the Engineer to issue any drawings or instructions is caused in whole or in part by the failure of the Contractor to submit drawings, specifications or other documents which he is required to submit under the Contract, the Engineer shall take such failure by the Contractor into account when making his statement of amounts due and payable to the Contractor in accordance with Sub-Clause 60.2.” Ethiopian Roads Authority Page 5.11 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 6.6 SUBMISSION OF DRAWINGS FOR APPROVAL Add the following as Sub-Clause 6.6: SUB-CLAUSE 6.7 METRIC UNITS All units used in the Contract shall be metric and for measurement of angles the 400 grades systems shall be used. SUB-CLAUSE 7.6 APPROVED DRAWING TO BE MODIFIED SUB-CLAUSE 7.7 SIZE OF DRAWINGS Page 5.12 "All detailed working drawings, design calculations and fabrication drawings for Temporary Works (such as form work, staging, centering, scaffolding, specialized construction, handling and launching equipment and the like) as well as bar bending and cutting schedules for reinforcement, material lists for structural fabrication as well as detailed drawings for templates and anchorage and temporary support details for prestressing cables etc. shall be prepared by the Contractor at his own cost and forwarded in triplicate to the Engineer at least six weeks in advance of actual constructional requirements. The Engineer will check and return one copy of the same for the Contractor’s use with amendments, if any, after discussion and agreement with Contractor. Such approval shall not relieve the Contractor of any of his responsibilities in connection with Temporary Works. The Contractor will supply three copies of the approved drawings for the Engineer’s use. The cost of preparing all such items of work shall be deemed to have been included in the respective rates/prices quoted by the Contractor in the Bill of Quantities." Should it be found at any time after approval has been given by the Engineer to any drawings submitted by the Contractor that the said drawings do not comply with the terms and conditions of the Contract, or that the details do not agree with any drawings submitted previously, such alterations and additions as may be deemed necessary by the Engineer shall be made therein by the Contractor and the work carried out accordingly without extra payment to the Contractor therefore. All drawings submitted by the Contractor shall for convenience in filing be as far as possible of a uniform size being not more than 101cm x 68cm overall (A1 size). The drawings shall be numbered and dated, and shall include the title of the Contract at the bottom of the drawing followed by the title of the drawing concerned. All drawings shall have the appropriate scales drawn on them and notes shall be in Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application English. All amendments to such drawings shall be noted and dated on the drawing. GENERAL OBLIGATIONS SUB-CLAUSE 10.1 PERFORMANCE SECURITY Replace the text of Sub-Clause 10.1 with the following: "The Contractor shall provide security for his proper performance of the Contract to the Employer within 28 days after the receipt of the Letter of Acceptance. The performance security shall be in the form of a bank guarantee or performance bond, as stipulated by the Employer in the Appendix to Bid. The performance security shall be denominated in the types and proportions of currencies in which the Contract Price is payable. The Contractor shall notify the Engineer when providing the performance security to the Employer. "If the performance security is a bank guarantee, it shall be issued either (a) by a bank located in the country of the Employer or a foreign bank through a correspondent bank located in the country of the Employer, or (b) directly by a foreign bank which has been determined in advance to be acceptable to the Employer. "If the performance security is a performance bond, it shall be issued by a bonding or insurance company acceptable to the Employer. "Without limitation to the provisions of the preceding paragraph, whenever the Engineer determines an addition to the Contract Price as a result of a change in cost and/or legislation or as a result of a variation amounting to more than 25 percent of the portion of the Contract Price payable in a specific currency, the Contractor, at the Engineer’s written request, shall promptly increase the value of the performance security in that currency by an equal percentage. The performance security of a joint venture shall be in the name of the joint venture." Ethiopian Roads Authority Page 5.13 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 10.2 VALIDITY OF THE PERFORMANCE SECURITY The performance security shall be valid until a date 28 days from the date of issue of the Taking-Over Certificate. The security shall be returned to the Contractor within 14 days of expiration. SUB-CLAUSE 10.3 CLAIMS UNDER PERFORMANCE SECURITY Delete Sub-Clause 10.3. SUB-CLAUSE 10.4 COST OF PERFORMANCE SECURITY The cost of complying with the requirements of this clause shall be borne by the Contractor. SUB-CLAUSE 11.1 INSPECTION OF SITE Add the following new paragraph at the end of Sub-clause 11.1: SUB-CLAUSE 11.2 ACCESS TO DATA Add new Sub-clause 11.2: “Whenever an opinion or interpretation of data is made available to the Contractor in respect of any data provided to the Contractor by the Employer, the Contractor shall be solely responsible for ascertaining the correctness of such opinion or interpretation and the Employer shall in no manner be liable in this behalf. In particular and without limiting the generality of the aforesaid, the Contractor shall not rely upon such opinion or interpretation for any claim with respect to additional time or cost under the Contract.” “Data made available by the Employer in accordance with SubClause 11.1 shall be deemed to include data listed elsewhere in the Contract as open for inspection at the address stipulated in the Appendix to Bid.” SUB-CLAUSE 14.1 PROGRAMME TO BE SUBMITTED Page 5.14 Add the following at the end of Sub-Clause 14.1 “The time within which the programme shall be submitted shall be the number of days stipulated in the Appendix to Bid." Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application Unless otherwise agreed, the program shall be generally based on the program submitted with the Bid and shall include (i) (ii) Critical Path Method (CPM) analysis of various activities from commencement of work to completion. Bar chart showing proposed execution of quantities of principal items of work, which shall not be unbalanced The program shall be related to the capability of equipment proposed to be deployed and site conditions. (iii) Proposed deployment of principal items of equipment, materials, and labour, every month. (iv) Proposal for purchase/hire of equipment, every month, along with program for their procurement. (v) A general description of the arrangements and methods which the contractor proposes to adopt for the execution of works, giving program of tests to be carried out before, during and after execution of each item of work. If the Engineer deems the work program submitted by the Contractor incomplete/improper, the Contractor will have 14 days to resubmit it to the Engineer’s satisfaction. Until then, the requirement to commence the work at site (Clause 41.1) shall be deemed unfulfilled.” The Contractor’s attention is particularly drawn to the need to familiarize himself with customs procedures in connection with importation, and to allow sufficient time in its programme for these to be completed. SUB-CLAUSE 14.2 REVISED PROGRAMME Add to Sub-Clause 14.2 the following: The Contractor shall, when instructed by the Engineer, amend, correct or modify the Program of Work so as to take into account any delays and/or advances and modifications designs or for other reasons considered necessary by the Engineer. If, during the progress of the work, the quantities of work performed per month fall below those shown in the program, or if the sequence of operations is altered, or if the program is deviated from in any other way, the Contractor shall, within two weeks after being notified by the Engineer, submit a revised programme so as to take into account any delays or advances or for other reasons considered necessary by the Ethiopian Roads Authority Page 5.15 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 Engineer without prejudice to the Employer’s right under Clause 63 of the General Conditions of Contract. If the program is to be revised by reason of the Contractor falling behind his program, he shall produce a revised program showing the modifications to the original program, necessary to ensure completion of the works or any part thereof within the time for completion as defined in Clause 43 of the General Conditions of Contract or any extended time granted pursuant to Clause 44 of the General Conditions of Contract. Any proposal to increase the tempo of work must be accompanied by positive steps to increase production by providing more labour and plant on Site, or by using the available labour and plant in a more efficient manner. Should the Employer request and the Contractor undertake to finish the whole or part of the Works ahead of the time originally required by the Contract, payment for accelerating the work shall only be made if agreed to beforehand in writing and according to the terms of such agreement. The Employer shall have the right to withhold payment for late submission of any programme, as stated in the Appendix to Bid. This amount will be payable within 60 days after submittal of the program SUB-CLAUSE 14.3 CASH FLOW ESTIMATE TO BE SUBMITTED SUB-CLAUSE 14.5 SUPPLEMENTARY PROGRAM Page 5.16 Delete “if required to do so by the Engineer” and replace with: “and each time the construction programme is revised and submitted under sub-clause 14.1.” The Contractor shall submit supplementary programs to the Engineer. The supplementary program shall be consistent in all respects with the time and order-of-work requirements of the Contract and based upon the portions of the Works already completed at the submission thereof. Supplementary programs shall not be requested at less than monthly intervals. Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application SUB-CLAUSE 14.6 CONTRACTOR TO EXPOSE DRAINAGE STRUCTURES Add the following as Sub-Clause 14.6: SUB-CLAUSE 15.1 CONTRACTOR’S SUPERINTENDENT Add the following at the end of the first paragraph of SubClause 15.1 “The detailed designs for repair and rehabilitation works at drainage structures will be prepared by the Engineer following the de-silting, cleaning or exposure of the component parts of the structures by the Contractor. Therefore, the Contractor should make due allowance in his programme and sequence of operations for the time required by the Engineer to issue appropriate instructions regarding the nature of any repairs required, and the time to import any specialised repair materials or equipment. The Contractor shall not decline to carry out such de-silting, cleaning or exposure work, or claim additional costs for such work, on the grounds that it is remote from, or in advance of, his other construction activities.” The contractor shall, within seven (7) days of receipt of the Engineer’s Order to commence the Works, confirm to the Engineer in writing, the name of the contractor’s Representative and the anticipated date of his arrival on site. SUB-CLAUSE 15.2 LANGUAGE ABILITY OF CONTRACTOR’S REPRESENTATIVE Add the following Sub-Clause 15.2: SUB-CLAUSE 16.1 CONTRACTOR’S EMPLOYEES Add the following Sub-Clause 16.1 (c): SUB-CLAUSE 16.3 LANGUAGE ABILITY OF SUPERINTENDING STAFF Add the following Sub-Clause 16.3: Ethiopian Roads Authority “The Contractor’s authorized representative shall be fluent in both the written and spoken language specified in the Appendix to Bid.” “ The Contractor shall not replace or remove its key personnel engaged in the performance of the Works without approval from the Employer which shall not be unreasonably withheld. Replacement shall be by a competent substitute approved by the Engineer and at the Contractor’s own expense.” “A reasonable proportion of the Contractor’s superintending staff shall have a working knowledge of the language specified in the Appendix to Bid, or the Contractor shall have available on Page 5.17 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 site at all times a sufficient number of competent interpreters to ensure the proper transmission of instructions and information.” SUB-CLAUSE 16.4 EMPLOYMENT OF LOCAL PERSONNEL Add the following Sub-Clause 16.4 SUB – CLAUSE 17.2 UNAUTHORIZED WORK Add the following sub-clause: SUB-CLAUSE 17.3 NOTICE OF SETTING OUT Without prejudice to the other requirements of Clause 17, the Contractor shall give to the Engineer, if required, not less than 48 hour's notice of his intention to set out or give levels for any part of the Works, so that arrangement may be made for checking or issuing instructions. SUB-CLAUSE 19.1 SAFETY, SECURITY, AND PROTECTION OF Add the following paragraph: THE ENVIRONMENT “The Contractor is required, to the extent practicable and reasonable, to employ staff and labour with appropriate qualifications and experience from sources within the country of the Employer stipulated in the Appendix to Bid.” “Any work done in addition to that required by the Contract or instructed by the Engineer shall not be paid.” (d)Be responsible for dealing with water, whether from existing drainage systems, water courses, underground springs or any other source or cause. In discharging and diverting water, he shall avoid flooding or damaging other works or services, causing erosion and/or pollution of watercourses. In addition, the Contractor shall take appropriate steps to prevent soil erosion and keep the Site and borrow areas free from flooding. (e) Notwithstanding the Contractor’s obligations under subparagraphs (a), (b) and (c) of the Sub-Clause 19.1 of the Conditions of Contract, the Contractor shall observe, without limitation to, the following measures with a view to reducing or eliminating adverse environmental effects by the Works: (i) Page 5.18 All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material. Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application (ii) Soil erosion due to the surface runoff or water from culverts or other drainage structures should be avoided by putting in place proper erosion control measures that shall include, but not limited to, grassing and planting of trees. (iii) Long traffic diversion roads shall be avoided so as to minimize the effect of dust on the surrounding environment. In any case, all diversions shall be kept damp and dust-free. (iv) Haulage routes shall be kept as short as possible, and watered as necessary. (v) Spillage of oil, fuel and lubricants shall be avoided. And if spilt, it shall be collected and disposed of in such a way as not to adversely affect the natural environment. (vi) Rock-blasting near settlement areas shall be properly coordinated with the relevant Authority in an attempt to minimize levels of noise pollution and community interference. The Contractor shall make every reasonable endeavor both by means of temporary works and by the use of appropriate plant or silencing devices to ensure that the level of noise resulting from the execution of the Works does not constitute a nuisance. (vii) SUB-CLAUSE 20.4 EMPLOYER’S RISKS Amend Sub-Clause 20.4 to read as follows: “The Employer’s risks are limited to the following; a) Insofar as they directly affect the execution of the Permanent Works in Ethiopia: Ethiopian Roads Authority (i) War and hostilities (whether war be declared or not), invasion, act of foreign enemies; (ii) Rebellion, acts of terrorism, revolution, insurrection, or military or usurped power, or civil war, international embargo. Page 5.19 Section 5 Part II – Conditions of Particular Application SUB-CLAUSE 21.1 INSURANCE OF WORKS AND CONTRACTOR’S EQUIPMENT Page 5.20 Standard Bidding Documents For Roadwork Contracts ICB – 2002 (iii) Ionizing, radiation, or contamination by radioactivity from any nuclear fuel, or from any nuclear waste from the combustion of nuclear fuel, radioactive toxic explosive or other hazardous properties of any explosive nuclear assembly or nuclear component thereof; (iv) Pressure waves caused by aircraft or other aerial devices traveling at sonic or supersonic speeds; (v) Riot, commotion or disorder, unless solely restricted to the employees of the Contractor or of his Subcontractors and arising from the conduct of the Works; b) Loss or damage due to the use or occupation by the Employer of any Section or part of the Permanent Works, except as may be provided for in the Contract; c) Loss or damage to the extent that it is due to the design of the Works, other than any part of the design provided by the Contractor or for which the Contractor is responsible; and d) Any operation of the forces of nature (insofar as it occurs on the Site) which an experienced contractor: i. Could not have reasonably foreseen, or ii. Could reasonably have foreseen, but against which he could not reasonably have taken at least one of the following measures: (A) Prevent loss or damage to physical property from occurring by taking appropriate measures, or (B) Insure against such loss or damage.” Add the following words at the end of sub-paragraph (a) and immediately before the last word of sub-paragraph (b) of SubClause 21.1: “it being understood that such insurance shall provide for compensation to be payable in the types and proportions of Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application currencies required to rectify the loss or damage incurred,” SUB-CLAUSE 21.2 SCOPE OF COVER Amend sub-paragraph (a) of Sub-Clause 21.2 by deleting the words “from the start of work at the Site” and by substituting therefore the words “from the first working day after the Commencement Date.” Add the following as sub-paragraph (c) under Sub-Clause 21.2: c) It shall be the responsibility of the Contractor to notify the insurance company of any change in the nature and extent of the Works and to ensure the adequacy of the insurance coverage at all times during the period of the Contract. SUB-CLAUSE 21.4 EXCLUSIONS Amend Sub-Clause 21.4 to read as follows: “There shall be no obligation for the insurance in Sub-Clause 21.1 to include loss or damage caused by the risks listed under Sub-Clause 20.4 sub-paragraphs (a) (i) to (iv) of the Conditions of Particular Application.” SUB-CLAUSE 23.1 THIRD PARTY INSURANCE (INCLUDING EMPLOYER’S PROPERTY) Add the following at the beginning of this Clause: SUB-CLAUSE 23.2 MINIMUM AMOUNT OF INSURANCE Sub-Clause 23.2 is amended to read as follows: “Prior to Commencement of the Works…” (i) (ii) (iii) Ethiopian Roads Authority The Contractor shall whenever required produce to the Engineer or the Engineer's Representative the policy or policies of insurance and the receipts for payment of the current premiums. The provision of such insurance and the cost thereof shall be in all respects at the expense of the Contractor. Such insurance shall be for at least the amount stated in the Appendix to Bid with no limits to the number of occurrences. Page 5.21 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 24.2 INSURANCE AGAINST ACCIDENT TO WORKMEN Add the following at the end of this Clause: SUB-CLAUSE 24.3 LIAISON WITH POLICE, LABOUR OFFICERS, ETC. Add to Clause 24 the following Sub-Clause 24.3: SUB-CLAUSE 25.1 EVIDENCE AND TERMS OF INSURANCE “The provision of such insurance and the costs thereof shall be in all respects at the expense of the Contractor.” The Contractor shall keep in close contact with the Police, Labour Officers and all other officials as appropriate regarding their requirements for the control of workmen, restricted area permits, passage through townships, or other matters and shall provide all assistance and facilities which may be required by such officials in the execution of their duties. Amend Sub-Clause 25.1 by inserting the words “as soon as practicable after the respective insurance has been taken out but in any case” before the words “prior to the start of work at the Site.” and Add at the end of the paragraph: “Insurance Policies shall include a clause forbidding both the Contractor and the Insurer to modify the terms and conditions of the insurance policies without the prior approval of the Employer.” SUB-CLAUSE 25.5 SOURCE OF INSURANCE Add the following Sub-Clause 25.5: SUB-CLAUSE 25.6 INSURANCE NOTICES Add the following Sub-Clause 25.6 Page 5.22 “The Contractor shall place all insurance relating to the Contract (including, but not limited to, the insurance referred to in Clauses 21, 23, and 24) with insurers from any eligible source country acceptable by the Funding Agency and the Employer.” Each policy of insurance effected by the Contractor for purpose of the Contract shall be renewable and shall include a provision to the effect that the insurer shall have a duty to give notice in writing to the Contractor and Employer of the date when a Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application premium becomes payable not more than thirty (30) days before that date and the policy shall remain in force until thirty (30) days after the giving of such notice. SUB-CLAUSE 25.7 NOTIFICATION TO INSURERS Add the following Sub-Clause 25.7 SUB-CLAUSE 26.2 INSPECTION AND AUDIT BY THE FUNDING AGENCY Add this new Sub-Clause: “The Contractor shall permit the Funding Agency to inspect the Contractor’s accounts and records relating to the performance of the Contract and to have them audited by auditors appointed by the Funding Agency, if so required by the Funding Agency.” Replace Sub-Clause 28.2 by the following: SUB-CLAUSE 28.2 ROYALTIES It shall be the responsibility of the Contractor to notify the insurers under any of the insurance referred to in the preceding Clauses 21, 23 and 24 on any matter or event which by the terms of such insurance are required to be so notified and the Contractor shall indemnify and keep indemnified the Employer against all losses, claims, demands, proceedings, costs, charges and expenses whatsoever arising out of or in consequence of any default by the contractor in complying with the requirements of this sub-clause whether as a result of avoidance of such insurance or otherwise. "The Employer shall be responsible for the assessment and reimbursement of payment of compensation in respect of land to be appropriated and incorporated in the works within the site together with all buildings, crops, trees and any other properties so defined from the land. The Employer shall be responsible for agreement and payment of compensation and any royalties in respect of land temporarily occupied, soil areas, working areas, the extraction of material from borrow pits and quarries, road diversions and sites for Contractor’s and Engineer’s accommodation, where such land or area is not within the site. The Employer shall be responsible for agreement and payment of compensation and any royalties in connection with the dumping of part or all of any such material." Ethiopian Roads Authority Page 5.23 Section 5 Part II – Conditions of Particular Application SUB-CLAUSE 28.3 COPYRIGHT Standard Bidding Documents For Roadwork Contracts ICB – 2002 Add the following Sub-Clause 28.3: “The Copyright of all documents and drawings prepared by or on behalf of the Contractor in connection with the Works shall be the property of the Employer”. SUB-CLAUSE 29.1 INTERFERENCE WITH TRAFIC AND ADJOINING PROPERTIES In sub-clause 29.1 (b) add the words “railway and any other right of way” add after the word “private roads.” Add the following Sub-clause: 29.1 (c) “The Contractor shall maintain two-way traffic during construction, unless otherwise approved. The Contractor shall build, maintain in a safe condition, keep open to traffic, and remove when no longer needed: (i) Detours and detour bridges, culverts including pipe culverts, that will accommodate traffic diverted from the roadway or bridges, culverts, pipe culverts during construction. (ii) Detour crossings of intersecting highways, and (iii) Temporary approaches. The Engineer shall approve all detour(s), and structure, surfacing and paving shall be sufficient to meet traffic requirements and shall be approved by the Engineer. Within 28 days prior to the commencement of any Permanent Works, the Contractor shall submit to the Engineer and have been approved by the Engineer the Traffic Management plan provided with its Bid. The Traffic Management plan shall indicate what measures will be implemented to manage the traffic while works are underway. Such a system shall describe, in the form of sketch accompanied by narrative details, the sequence of signs, diversions, lighting, fence, etc., to be applied to each section of road. The Traffic Management plan shall be approved by the Engineer before the start of works on any section of road. In case of default on the part of the Contractor in implementing such Traffic Management plan, as approved by the Engineer, an amount as stated in the Appendix to Bid shall be withheld from the Interim Monthly Certificate. In the event of deterioration due to climatic conditions or theft of the provisional system of signaling installed by the Page 5.24 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application Contractor, the Contractor will make good the diversion and/or the signaling system within 24 hours after the event has been reported by the Engineer to the Contractor. SUB-CLAUSE 29.3 REINSTATEMENT AND COMPENSATION FOR DAMAGE TO PERSONS OR PROPERTY The Contractor shall reinstate all properties whether public or private which are damaged in consequence of the construction and maintenance of the works to a condition as specified and at least equal to that prevailing before his first entry on them. If in the opinion of the Engineer the Contractor shall have failed to take reasonable and prompt action to discharge his obligations in the matter of reinstatement the Engineer will inform the Contractor in writing of his opinion, in which circumstances the Employer reserves the right to employ others to do the necessary work of reinstatement and to deduct the cost thereof from any money due or which shall become due to the Contractor. The Contractor shall refer to the Employer without delay all claims, which may be considered to fall within the provisions of Sub-clause 22.1. SUB CLAUSE 29.4 PROTECTION OF EXISTING WORKS AND SERVICES The Contractor shall acquaint himself with the position of all existing services, such as sewers, surface water drains, cables for electricity and telephone, telephone and lighting poles, water main and alike before commencing any excavation or other work likely to affect the existing service. The Contractor will be held liable for all damage to roads, Irrigation ditches, mains pipes, electric cables, lines or services of any kind caused by him or his sub-contractors in the execution of the Works. The Contractor must make good any damage without delay and, if necessary, carry out any further work ordered by the Engineer’s Representative Where work is to be carried out in the vicinity of overhead power lines, the Contractor shall ensure that all persons working in such areas are aware of the relatively large distance that high voltage electricity can “short” to earth when crane, or other large masses of steel, are in the vicinity of power lines. The Contractor’s attention is drawn to BS. 162 which gives safe clearance for the various voltages. Ethiopian Roads Authority Page 5.25 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 The Contractor shall be held responsible for injury to existing works or services, and shall indemnify the Employer against any claims in this respect (including consequential damages) The Contractor shall be responsible for the reinstatement of the services so affected, to the satisfaction of the Engineer. In all cases where such works or services are exposed, they shall be properly shared, hung up or otherwise protected. Special care must be exercised in filling and compacting the grounds under mains, cable, etc., and to leave uncovered exposed water meters, stopcock boxes and similar items. As soon as any such existing works or services or structures are encountered on, over, under, in or through the Site during the performance of the Contract, the Contractor shall make a record of the location and description of such service or structure and shall send the same forthwith to the Engineer. Installations adjacent to the Works shall be kept securely in place until the work is completed and shall then be made as safe and permanent as before Not withstanding the foregoing requirements, and without reducing the Contractor’s responsibility, the Contractor shall inform the Engineer immediately if any existing works or services are located, exposed or damaged. SUB-CLAUSE 29.5 PROTECTION OF SURVEY BEACONS The Contractor shall not remove, damage, alter or destroy in any way plot beacons. Should the Contractor consider that any beacon will be interfered with by the Work he shall notify the Engineer who, if he considers it necessary, will make arrangements for the removal and replacement of the beacons. SUB-CLAUSE 30.5 EXTRAORDINARY TRAFFIC Add Sub-Clause 30.5: SUB-CLAUSE 30.6 FACILITIES FOR Add Sub-Clause 30.6: OTHER CONTRACTOR’S Page 5.26 “Nothing contained above shall excuse the Contractor or any of his Sub-Contractor(s) from complying with state laws regulating traffic on highways and bridges.” “The Contractor shall be deemed to have fully familiarized himself with the planned construction operations on any other concurrent construction project in Ethiopia which may have any adverse effect on the Contractor’s own operations. The Contractor shall be deemed to have allowed for the effects of Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application other concurrent construction projects on any necessary transportation operations in connection with the contract, outside the confines of the Contract Site.” LABOUR SUB-CLAUSE 34.3 COMPENSATION FOR INJURY SUB-CLAUSE 34.4 COSTS COVERED Add the following Sub-Clause 34.3: “The Contractor shall, in accordance with the Workman’s Compensation Act of the law of Ethiopia and any other regulations in force from time to time in Ethiopia, pay compensation for loss or damage suffered in consequence of any accident or injury or disease resulting from his work to any workman or other person in the employment of the Contractor or any sub-Contractor.” Add the following Sub-Clause 34.4: “The forgoing provisions of this Clause 34 shall apply to all labour and personnel employed by the Contractor and his subContractors and costs, charges and expenses whatsoever that may be incurred by the Contractor and all risks involved in giving effect to the provisions of this clause including all insurance, custom duties, medical or other fees, substance, home or local leave, all other matters are deemed to be included in and covered by the rates or sums inserted by the Contractor in the Bill(s) of Quantities.” [To check if there is such a pay item in the BOQ] SUB-CLAUSE 35.1 RETURNS OF LABOUR AND CONTRACTOR’S EQUIPMENT Ethiopian Roads Authority Add the following paragraph at the end of Sub-Clause 35.1: “Returns of Personnel and Equipment shall be submitted to the Engineer’s Representative with each Monthly Statement.” Page 5.27 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 COMMENCEMENT AND DELAYS SUB-CLAUSE 41.1 COMMENCEMENT OF WORKS Add the following at the end of the Sub-Clause. “The requirements to commence the works at site’ shall be fulfilled if:a) Program has been submitted in accordance with Clause 14.1 b) The Contractor’s Technical Staff such as Site Manager(s), Site Engineer(s), with other supporting staff are in position at site; c) Equipment, materials and labor for the work programmed for execution in the first 2 months, have been mobilized at site. SUB-CLAUSE 44.1 EXTENSION OF TIME FOR COMPLETION Add, at the end of (c) : Extension of time in terms of clause 44.1(c) of the General Conditions of Contract in respect of exceptional rainfall shall be determined in terms of method (i) below, unless the Technical Specifications (Supplemental) determine that method (ii) shall be used. The extension of time that will be considered for a given calendar month shall not exceed the number of calendar days in that month less the average number of days in that month on which a rainfall of Y mm or more per day has been recorded, as derived from existing rainfall records. Method (i) (Rainfall formula) The formula below shall be used to calculate separately the delay for each calendar month or part thereof. It shall be calculated each month during the period referred to in the General Conditions of Contract as the time for completion of the Works (including any extension thereof that may have been granted), or until the issue date of the Taking-Over Certificate, whichever is the shorter period. The delay calculated for a given month shall be used to determine the interim extension of time granted for that month. At the end of the applicable period Page 5.28 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application referred to above, the aggregate of the monthly delays will be taken into account for the final determination of the total extension of time for the contract: V = (Nw - Nn) + (Rw - Rn) X If any value of V is negative and its absolute value exceeds Nn, then V shall be taken as equal to minus Nn. The delay for a part of a month shall be calculated by substituting pro rata values for the variables in the equation. The symbols shall have the following meanings: V= Delay due to rain in calendar days in respect of the calendar month under consideration. Nw = Actual number of days during the calendar month on which a rainfall of Y mm or more per day has been recorded, Rw = Actual rainfall in mm for the calendar month under consideration. Nn = Average number of days in the. relevant calendar month (as derived from existing rainfall records provided in the project specifications) on which a rainfall of Y mm or more per day has been recorded. Rn = Average rainfall in mm for the calendar month, as derived from the rainfall records supplied in the Technical Specifications (Supplemental). X = 20, unless otherwise provided in the Technical Specifications. Y= 10, unless otherwise provided in the Technical Specifications. The total delay that will be taken into account for the determination of the total extension of time for the Contract shall be the algebraic sum of the monthly totals for the period Ethiopian Roads Authority Page 5.29 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 under consideration. But if the grand total is negative, the time for completion shall not be reduced on account of abnormal rainfall. The total extension of time for any calendar month shall not exceed (Nc - Nn) calendar days, where Ne = number of calendar days in the month under consideration. The factor (Nw - Nn) shall be considered to represent a fair allowance for variations from the average number of days during which rainfall equals or exceeds Y mm per day. The factor (Rw - Rn) + X shall be considered to represent a fair allowance for variations from the average for the number of days during which rainfall does not equal or exceed Y mm per day, but when wet conditions prevent or disrupt work. This formula does not take into account any flood damage, which could cause further or concurrent delays and which shall be treated separately in so far as extension of time is concerned Accurate rain gauging shall be taken at a suitable point on the site daily at 08:00 unless otherwise agreed to by the Engineer, and the Contractor shall, at his own expense, take all necessary precautions to ensure that the rain gauges cannot be interfered with by unauthorized persons. Information regarding existing rainfall records, if available from a suitable rainfall station near the site, will be supplied in the Technical Specifications (Supplemental), together with calculations of rain delays for previous years in accordance with the above formula. The average of these delays will be regarded as normal rain delays, which the Contractor shall accommodate in his programme, and for which no extension of time will be considered. If no suitable rainfall records are available, the above formula will not apply, Method (ii) (Critical-path method) Where the critical-path method is specified in the Technical Specifications (Supplemental) for determining extension of time resulting from exceptional rainfall, it shall be applied as follows: Page 5.30 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application A delay caused by inclement weather conditions will be regarded as a delay only if, in the opinion of the Engineer, all progress on an item or items of work on the critical path of the working programme of the Contractor has been brought to a halt. Delays on working days only (based on a five-day working week) will be taken into account for the extension of time, but the Contractor shall make provision in his programme of work for an expected delay of "n" working days caused by normal rainy weather, for which he will not receive any extension of time. The value of "n" shall be given in the Technical Specifications (Supplemental). Extension of time during working days will be granted to the degree to which actual delays, as defined above, exceed the number of "n" workings days as mentioned in the Technical Specifications (Supplemental).” At the end of Sub-Clause 44.1 add the following: Neither rains falling within the rainy seasons as occurs in the Employer's country, nor floods caused by such rains shall be deemed exceptional weather conditions such as may fairly entitle the Contractor to an extension of time for the completion of the work. Similarly in respect of the provision of Clause 12 of these Conditions, neither such rains nor such floods shall be deemed to be adverse physical conditions. SUB-CLAUSE 45.1 RESTRICTION ON WORKING HOURS Ethiopian Roads Authority Add the following to Sub-Clause 45.1 : If the Contractor requests for permission to work by day and night and if the Engineer shall grant such permission, the Contractor shall not be entitled to any additional payment for so doing. All such work at night shall be carried out without unreasonable noise or other disturbance and the Contractor shall indemnify the Employer from and against any liability for damages on account of noise or other disturbance created while carrying out night work and from against all claims, demands, proceeding, costs, charges and expenses whatsoever in regard or in relation to such liability. In addition, the Contractor shall be required to provide, for any work carried out by night or recognised days of rest, adequate lighting and other facilities, so that the work is carried out safely and properly. Page 5.31 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 45.2 OVERTIME WORKING Add the following Sub-Clause 45.2: “Normal working hours shall be in accordance with the Ethiopian Labour Laws. No work shall be allowed on Sunday or Public Holidays, except with the permission of the Engineer. For any hours in excess of the normal working hours the Contractor shall be responsible for payments, for excess hours worked by the staff of the Engineer, by means of deduction made by the employer from payments due to the Contractor. The Current recognized Public Holidays are as follows: Christmas Day (January) Epiphany (January) Victory Day (March) Patriots Victory Day (May) Id-ul-Fitr Good Friday Labour Day (1st May) Downfall of the Derg (May) Id-ul-Dhar Ethiopian New Year (11th September) Birthday of the Prophet Mohammed. Finding of the True Cross (Meskel) (September)” SUB-CLAUSE 46.2 MONTHLY PROGRESS REPORTS Add the following Sub-Clause 46.2 SUB-CLAUSE 47.3 BONUS FOR EARLY COMPLETION No Bonus for early completion of the works shall be paid to the Contractor by the Employer SUB-CLAUSE 47.4 CURRENCY OF LIQUIDATED DAMAGES Liquidated damages shall be paid by the Contractor of the Employer in the types and proportions of currencies as shall be payable to the Contractor under contract. SUB-CLAUSE 48.2 TAKING OVER OF SECTIONS OR PARTS Substitute Sub-Clause 48.2 (b) by the following: Page 5.32 “The Contractor shall submit four copies of a monthly progress report to the Engineer during the first week of the month following the report period. The format of the report shall be agreed with the Engineer.” (b) Any substantial part of the Permanent Works, provided the continuous length is not less than that stated in the Appendix to Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application Bid, which has been both completed to the satisfaction of the Engineer and, otherwise than as provided for in the Contract, occupied or used by the Employer, or SUB-CLAUSE 48.3 SUBSTANTIAL COMPLETION OF PARTS Add at the end of sub-clause 48.3 the following: SUB-CLAUSE 49.5 DEFECTS LIABILITY PERIOD Add Sub-Clause 49.5 OF REPLACEMENTS ETC. “Parts or Sections of the Works shall be deemed to be Substantially Completed when the Engineer determined that the Employer has full and unrestricted use and benefit of the facilities, and only minor ancillary roadwork, and removal of temporary facilities, shall remain for the physical completion of the Works.” “The provisions of this Clause shall apply to all replacements or renewals of Plant, equipment etc. to be provided with respect to the utilities under the Contract, carried out by the Contractor to remedy defects and damages as if the replacements and renewals had been taken over on the date they were completed. The Defects Liability Period for the Works shall be extended by a period equal to the period during which the Works cannot be used by reason of the defect or damage. If only part of the Works is affected the Defects Liability Period shall be extended only for that part.” ALTERATIONS, ADDITIONS AND OMISSIONS SUB-CLAUSE 51.3 DESIGN OF VARIATIONS Add the following as Sub-Clause 51.3: "The Contractor shall be entirely responsible for any investigations and the preparation of all necessary preliminary designs, design calculations, detailed designs, detailed working drawings, fabrication drawings, bar bending and cutting schedules for reinforcement, material lists for structural fabrication etc. for any variation ordered by the Engineer and shall forward the same in triplicate to the Engineer at least six weeks in advance of actual constructional requirements. The Engineer will check and return one copy of the same for the Ethiopian Roads Authority Page 5.33 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 Contractor’s use with amendments, if any, after discussion and agreement with Contractor. Such approval shall not relieve the Contractor of any of his responsibilities in connection with design, construction or maintenance of the variation. The Contractor will supply three copies of the approved drawings for the Engineer’s use. The cost of preparing all such items of work, including any amendments required by the Engineer, shall be deemed to have been included in the respective rates/prices agreed upon between the Engineer and the Contractor in accordance with Clause 52.1. Unless, and to the extent agreed by the Engineer in writing prior to the execution of any variation, no extension of time will be granted in respect of the variation and the cost of any acceleration measures required to undertake the variation in accordance with the current programme for the works shall be deemed to have been included in the respective rates/prices agreed upon between the Engineer and the Contractor in accordance with Clause 52.1. The Contractor shall accept all risks in respect of non-foreseeable physical obstructions or conditions which may be encountered in the planning, design and execution of any variation and shall not be entitled to any extension of time or costs under Clause 12.2" SUB-CLAUSE 52.1 VALUATION OF VARIATIONS Page 5.34 Add final sentences as follows: “Where the Contract provides for the payment of the Contract Price in more than one currency, and varied work is valued at, or on the basis of, the rates and prices set out in the Contract, payment for such varied work shall be made in the proportions of various currencies specified in the Appendix to Bid for payment of the Contract Price. Where the Contract provides for payment of the Contract Price in more than one currency, and new rates or prices are agreed, fixed, or determined as stated above, the amount or proportion payable in each of the applicable currencies shall be specified when the rates or prices are agreed, fixed, or determined, it being understood that in specifying these amounts or proportions the Contractor and the Engineer (or, failing agreement, the Engineer) shall take into account the actual or expected currencies of cost (and the proportions thereof) of the inputs of the varied work without Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application regard to the proportions of various currencies specified in the Appendix to Bid for payment of the Contract Price.” SUB-CLAUSE 52.2 POWER OF ENGINEER TO FIX RATES Add a final sentence to the first paragraph, as follows: “Where the Contract provides for the payment of the Contract Price in more than one currency, the amount or proportion payable in each of the applicable currencies shall be specified when the rates or prices are agreed, fixed, or determined as stated above, it being understood that in specifying these amounts or proportions the Contractor and the Engineer (or, failing agreement, the Engineer) shall take into account the actual or expected currencies of cost (and the proportions thereof) of the inputs of the varied work without regard to the proportions of various currencies specified in the Appendix to Bid for payment of the Contract Price.” Add a third paragraph: “Provided further that no change in the rate or price for any item contained in the Contract shall be considered unless such item accounts for an amount more than 2 percent of the Contract Price, and the actual quantity of work executed under the item differs from the quantity set out in the Bill of Quantities by more than 25 percent.” SUB-CLAUSE 52.3 VARIATIONS EXCEEDING 15 PERCENT SUB-CLAUSE 52.4 DAYWORKS Ethiopian Roads Authority Add a final sentence, as follows: “Where the Contract provides for the payment of the Contract Price in more than one currency, the amount or proportion payable in each of the applicable currencies shall be specified when such further sum is agreed or determined, it being understood that in specifying these amounts or proportions the Contractor and the Engineer (or, failing agreement, the Engineer) shall take into account the currencies (and the proportions thereof) in which the Contractor’s Site and general overhead cost of the Contract were incurred without being bound by the proportions of various currencies specified in the Appendix to Bid for payment of the Contract Price.” Add the following at the end of Sub-Clause 52.4. Page 5.35 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 "The work so ordered shall immediately become part of the works under the contract. The Contractor shall, as soon as practicable after receiving the Dayworks order from the Engineer, undertake the necessary steps, for due execution of such work-prior to commencement of any work to be done on a Day work basis. The Contractor shall give an advance notice to the Engineer stating the exact time of such commencement." SUB-CLAUSE 53.1 NOTICE OF CLAIMS Add at the end of Sub-Clause 53.1: SUB-CLAUSE 53.2 CONTEMPORARY RECORDS Add at the end of clause 53.2 The Contractor shall also state on which Clause or Clauses of the Conditions of Contract his claim is based. In order that the extent and validity of such claims may be properly assessed when they are submitted at a later date, all circumstances relating to claims must be investigated, recorded and agreed upon as far as possible between the Contractor and the Engineer as and when they occur. For this purpose the Contractor shall furnish the Engineer from day to day with records, in a form approved by the Engineer, of all the facts and circumstances that the Contractor considers relevant and may wish to rely upon in support of his claims. The Engineer may in turn record such other facts and circumstances as he considers relevant and the Contractor shall for this purpose, supply him with all the information that he may require in this respect. The Engineer and the Contractor shall at the time of recording, indicate in writing and by signature, their agreement or disagreement as to the correctness of the information recorded. Page 5.36 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application CONTRACTOR’S EQUIPMENT ,TEMPORARY WORKS AND MATERIALS SUB-CLAUSE 54.1 CONTRACTOR’S EQUIPMENT, TEMPORARY WORKS, AND MATERIALS: EXCLUSIVE USE FOR THE WORKS Amend Sub-Clause 54.1 as follows: Line 5, add “written” between “the” and “consent”. Add a final sentence as follows: “The Contractor shall every month give to the Engineer a statement showing the amount of plant and Contractor’s equipment, which has been brought to this Site, including the equipment condition (Operational, stand by, under repair, etc.) of the month .” SUB-CLAUSE 54.9 CONTRACTOR’S RESPONSIBILITIES FOR LICENSES The Contractor shall obtain his own information with regard to the granting of import and export licenses for materials, equipment and plant. The Contractor shall bear all expenses for Plant, Materials, Equipment and Maintenance required for the completion and maintenance of the works and shall be deemed to have satisfied himself with regard to all his liabilities under the laws and regulations governing the granting of these licenses. The Contractor shall ensure that requests for import and export licenses are submitted in sufficient time to clear all formalities before said licenses are required. SUB-CLAUSE 54.10 EQUIPMENT AND PLANT The Contractor shall identify each piece of his equipment, other than hand tools, by means of an identification number plainly stencilled or stamped on the equipment at a conspicuous location, and shall furnish to the Engineer a list giving the description of each piece of equipment and its identification number. In addition, the make, model number and empty gross weight of each unit of compaction equipment shall be plainly stamped or stencilled in a conspicuous place on the unit. The gross weight shall be either the manufacturer’s rated weight or the scale weight. The make, model, serial number and manufacturer’s rated capacity of each scale shall be clearly stamped on the load- Ethiopian Roads Authority Page 5.37 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 receiving element and its indicator or indicators. All meters shall be similarly identified, rated and marked. MEASUREMENT SUB-CLAUSE 55.2 OMISSIONS OF QUANTITIES SUB-CLAUSE 57.1 METHOD OF MEASUREMENT SUB-CLAUSE 58.5 PROVISIONAL ITEMS SUB-CLAUSE 59.3 DESIGN REQUIREMENTS TO BE EXPRESSLY STATED SUB-CLAUSE 59.5 CERTIFICATION OF PAYMENTS TO NOMINATED SUBCONTRACTORS Page 5.38 Add the following to Sub-Clause 55.2: Items of the Works described in the Bill of Quantities for which no rate or price has been entered in the Contract shall be considered as included in other rates and prices in the Contract and will not be paid for separately by the Employer. Delete the text of this Sub-Clause and substitute with the following: “The measurement of the works shall be performed on the All items set out in the Bill of Quantities which are stated to be provisional items, or for contingencies, shall be used only at the discretion of the Engineer and if not used, either wholly or in part, then the amount not used shall be deducted from the contract price. Delete this Sub-Clause 59.3 “Add the following paragraph at the end of the Sub-Clause: If the Engineer desires to secure or certify final payment to any nominated Sub-Contractor before final payment is due to the Contractor and if such Sub-Contractor has satisfactorily indemnified the Contractor against any latent defects, the Engineer may, in an interim certificate, include an amount to cover the said final payment, and thereupon the Contractor shall pay to such nominated Sub-Contractor the amount so certified. Upon such final payment the SubContractor shall be discharged from all liability for the work, Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application materials or goods executed or supplied by such SubContractor under the contract to which the payment relates.” CERTIFICATES AND PAYMENT CLAUSE 60 CERTIFICATES AND PAYMENT Clause 60 of the General Conditions is deleted and the following Sub-Clauses 60.1-60.14 are substituted therefore: SUB-CLAUSE 60.1 MONTHLY STATEMENTS The Contractor shall submit a statement in the number of copies stipulated in the Appendix to Bid to the Engineer at the end of each month, in a tabulated form approved by the Engineer, showing the amounts to which the Contractor considers himself to be entitled. The statement shall include the following items, as applicable, which shall be taken into account in the sequence listed: (a) The estimated Contract value of the Temporary and Permanent Works executed up to the end of the month in question, determined in accordance with Sub-Clause 56.1, at the unit rates and prices included in the Contract; (b) The value of any variations executed up to the end of the month in question, less the amount certified in the previous Interim Payment Certificate, pursuant to Clause 52; (c) Amounts approved in respect of Day work executed up to the end of the month in question, less the amount for Day work certified in the previous Interim Payment Certificate, as determined from the Day work schedule of the Bill of quantities. (d) Amounts reflecting changes in cost and legislation, pursuant to Clause 70; (e) Any amount to be withheld under the retention provisions of Sub-Clause 60.5, determined by applying the percentage set forth in Sub-Clause 60.5 to the amount due under paragraphs 60.1 (b), (c) and (d); (f) Ethiopian Roads Authority Any credit in respect of materials and Plant for the Permanent Works, and under the conditions set forth in Page 5.39 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 Sub-Clause 60.3; (g) Any amount to be deducted as repayment of the Advance under the provisions of Sub-Clause 60.7; and (h) Any other sum to which the Contractor may be entitled under the Contract or otherwise. (i) SUB-CLAUSE 60.2 MONTHLY PAYMENTS The amount certified for payment up to the end of the previous month The said statement shall be approved or amended by the Engineer in such a way that, in his opinion, it reflects the amounts in various currencies due to the Contractor in accordance with the Contract, after deduction, other than pursuant to Clause 47, of any sums which may have become due and payable by the Contractor to the Employer. In cases where there is a difference of opinion as to the value of any item, the Engineer’s view shall prevail. Within 28 days of receipt of the monthly statement referred to in Sub-Clause 60.1, the Engineer shall determine the amounts due to the Contractor and shall deliver to the Employer and the Contractor an Interim Payment Certificate, certifying the amounts due to the Contractor. Provided that the Engineer shall not be bound to certify any payment under this sub-clause if the net amount thereof, after all retentions and deductions, would be less than the Minimum Amount of Interim Payment Certificates stated in the Appendix to Bid. However, in such case, the unpaid certified amount will be added to the next interim payment, and the cumulative unpaid certified amount will be compared with the minimum amount of interim payment. Notwithstanding the terms of this clause or any other clause of the Contract, no amount will be certified by the Engineer for payment until the performance security has been provided by the Contractor and approved by the Employer. Page 5.40 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 60.3 MATERIALS AND PLANT FOR THE PERMANENT WORKS Section 5 Part II – Conditions of Particular Application With respect to materials and Plant brought by the Contractor to the Site for incorporation in the Permanent Works, the Contractor shall (a) receive a credit in the month in which these materials and Plant are brought to the Site and (b) be charged a debit in the month in which they are incorporated in the Permanent Works, both such credit and debit to be determined by the Engineer in accordance with the following provisions: a) No credit shall be given unless the following conditions shall have been met to the Engineer’s satisfaction: (i)The materials and Plant are in accordance with the specifications for the Works; (vi) The materials and Plant have been delivered to the Site and are properly stored and protected against loss, damage, or deterioration; (vii) The Contractor’s records of the requirements, orders, receipts, and use of materials and Plant are kept in a form approved by the Engineer, and such records are available for inspection by the Engineer; (viii) The Contractor has submitted a statement of his cost of acquiring and delivering the materials and Plant to the Site, together with such documents as may be required for the purpose of evidencing such cost; (ix) The origin of the materials and Plant and the currencies of payment therefore are those indicated in the Appendix to Bid; and (x) The materials are to be used within a reasonable time. b) The amount to be credited to the Contractor shall be the equivalent of 75 percent of the Contractor’s reasonable cost of the materials and Plant delivered to the Site, as determined by the Engineer after review of the documents listed in sub-paragraph (a) (iv) above; c) The amount to be debited to the Contractor for any materials and Plant incorporated into the Permanent Works shall be equivalent to the credit previously granted to the Contractor for such materials and Plant pursuant to Sub-Clause (b) above, as determined by the Engineer; and Ethiopian Roads Authority d) The currencies in which the respective amounts shall be credited or debited as set forth above shall be determined by Page 5.41 the Engineer Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 60.4 PLACE OF PAYMENT Payments to the Contractor by the Employer shall be made in the currencies in which the Contract Price is payable into a bank account or accounts nominated by the Contractor. SUB-CLAUSE 60.5 RETENTION MONEY A retention amounting to the percentage stipulated in the Appendix to Bid of the amounts due in each currency, determined in accordance with the procedure set out in SubClause 60.1 (i) shall be made by the Engineer in the first and following Interim Payment Certificates. SUB-CLAUSE 60.6 PAYMENT OF RETENTION MONEY Upon the issue of the Taking-Over Certificate with respect to the whole of the Works, one half of the Retention Money, or upon the issue of a Taking-Over Certificate with respect to a Section or part of the Permanent Works only such proportion thereof as the Engineer determines having regard to the relative value of such Section or part of the Permanent Works, shall be certified by the Engineer for payment to the Contractor. The Contractor may substitute the remaining retention money with an on-demand bank guarantee in a form, and from a source, acceptable to the Employer. Upon the expiration of the Defects Liability Period for the Works, the other half of the Retention Money shall be certified by the Engineer for payment to the Contractor (or return of the remaining security, which replaced the Retention Money). Provided that, in the event of different Defects Liability Periods being applicable to different Sections or parts of the Permanent Works pursuant to Clause 48, the expression “expiration of the Defects Liability Period” shall, for the purposes of this subclause, be deemed to mean the expiration of the latest of such periods. Provided also that if at such time, there shall remain to be executed by the Contractor any work instructed, pursuant to Clauses 49 and 50, in respect of the Works, the Engineer shall be entitled to withhold certification until completion of such work of so much of the balance of the Retention Money as shall, in the opinion of the Engineer, represent the cost of the work remaining to be executed. Page 5.42 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 60.7 ADVANCE PAYMENT Section 5 Part II – Conditions of Particular Application a) Up on the request of the Contractor, the Employer will make an interest-free advance payment to the Contractor exclusively for the costs of mobilization in respect of the Works in an amount, payable in the proportions of foreign and local currencies of the Contract Price not exceeding the amount stated in the Appendix to Bid. Payment of such advance amount will be due under separate certification by the Engineer after (a) execution of the Form of Agreement by the parties hereto; (b) provision by the Contractor of the performance security in accordance with Sub-Clause 10.1; and (c) provision by the Contractor of an unconditional bank guarantee in a form and by a bank acceptable to the Employer in amounts and currencies equal to the advance payment. Such bank guarantee shall remain effective until the advance payment has been repaid pursuant to the paragraph below, but the amount thereof shall be progressively reduced by the amount repaid by the Contractor as indicated in Interim Payment Certificates issued in accordance with this Clause. (b)In addition to the advance mentioned in Sub-para (a) above, the Employer will pay another interest free advance against key construction equipment required for the work and brought to site, if so requested by the Contractor subject to the same terms and conditions specified in paragraphs (a) above. The maximum of such advance shall be five percent of the Contract price. In case of new equipment, the advance shall be limited to ninety percent of the price of such new plant and equipment, by the Contractor for which the Contractor shall produce satisfactory evidence. In case of used equipment, the amount of such advance shall be limited to ninety percent of the depreciated value of equipment as may be determined by the Engineer. This advance shall be further subject to the condition that (i) such equipment are considered by the Engineer to be necessary for the works, (ii) such equipment are in working order, and (iii) such equipment shall be on site without any delay. c) The advance payment shall be repaid through percentage deductions from the interim payments certified by the Ethiopian Roads Authority Page 5.43 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 Engineer in accordance with this Clause. Deductions shall commence in the next Interim Payment Certificate following that in which the total of all interim payments certified to the Contractor has reached the percentage of the Contract Price stipulated in the Appendix to Bid less Provisional Sums, and shall be made at the rate stated in the Appendix to Bid of the amount of all Interim Payment Certificates in the types and proportionate amounts of currencies of the advance payment until such time as the advance payment has been repaid; always provided that the advance payment shall be completely repaid prior to the time when 80 percent of the Contract Price has been certified for payment. SUB-CLAUSE 60.8 TIME FOR PAYMENT AND INTEREST a) The amount due to the Contractor for any advance payment shall be paid within 56 days of a satisfactory application for the same. b) The amount due to the Contractor under any Interim or Final Payment Certificate issued by the Engineer pursuant to this Clause, or to any other term of the Contract, shall, subject to Clause 47, be paid by the Employer to the Contractor as follows: i. i) In the case of Interim Payment Certificates, within 56 days after the Contractor's monthly statement has been submitted to the Engineer for certification, pursuant to SubClause 60.1, provided that if the Engineer's Interim Certificate has not been issued within said 56 days, the Employer shall pay the amount shown in the Contractor's monthly statement and that any discrepancy shall be added to, or deducted from, the next payment to the Contractor; and ii. In the case of the Final Payment Certificate pursuant to SubClause 60.13, within 56 days after the Final Statement and written discharge have been submitted to the Engineer for certification; and (c) In the event of the failure of the Employer to make payment within the times stated, the Employer shall pay to the Contractor interest compounded monthly at the rate(s) stated in the Appendix to Bid upon all the sums unpaid from the date upon which the same should have been paid, in the currencies in which the payments are due. The provisions of this Sub-Clause are without prejudice to the Contractor's entitlement under Clause 69 or otherwise." Page 5.44 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application SUB-CLAUSE 60.9 CORRECTION OF CERTIFICATES The Engineer may by any Interim Payment Certificate make any correction or modification in any previous Interim Payment Certificate, which has been issued by him, and shall have authority, if any work is not being carried out to his satisfaction, to omit or reduce the value of such work in any Interim Payment Certificate. SUB-CLAUSE 60.10 STATEMENT AT COMPLETION Not later than 84 days after the issue of the Taking-Over Certificate in respect of the whole of the Works, the Contractor shall submit to the Engineer a Statement at Completion in the number of copies specified in the Appendix to Bid with supporting documents showing in detail, in the form approved by the Engineer, a) The final value of all work done in accordance with the Contract up to the date stated in such Taking-Over Certificate; b) Any further sums which the Contractor considers to be due; and c) An estimate of amounts, which the Contractor considers, will become due to him under the Contract. Estimated amounts shall be shown separately in such Statement at Completion. The Engineer shall certify payment in accordance with Sub-Clause 60.2. SUB-CLAUSE 60.11 FINAL STATEMENT Not later than 56 days after the issue of the Defects Liability Certificate pursuant to Sub-Clause 62.1, the Contractor shall submit to the Engineer for consideration a draft final statement in the number of copies stipulated in the Appendix to Bid with supporting documents showing in detail, in the form approved by the Engineer, a) The value of all work done in accordance with the Contract; and b) Any further sums which the Contractor considers to be due to him under the Contract or otherwise. Ethiopian Roads Authority Page 5.45 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 If the Engineer disagrees with or cannot verify any part of the draft final statement, the Contractor shall submit such further information as the Engineer may reasonably require and shall make such changes in the draft as may be agreed between them. The Contractor shall then prepare and submit to the Engineer the final statement as agreed (for the purposes of these Conditions referred to as the “Final Statement”). If, following discussions between the Engineer and the Contractor and any changes to the draft final statement which may be agreed between them, it becomes evident that a dispute exists, the Engineer shall deliver to the Employer an Interim Payment Certificate for those parts of the draft final statement, if any, which are not in dispute. The dispute shall then be settled in accordance with Clause 67. The Final Statement shall be agreed upon settlement of the dispute. SUB-CLAUSE 60.12 DISCHARGE Upon submission of the Final Statement, the Contractor shall give to the Employer, with a copy to the Engineer, a written discharge confirming that the total of the Final Statement represents full and final settlement of all monies due to the Contractor arising out of or in respect of the Contract. Provided that such discharge shall become effective only after payment due under the Final Payment Certificate issued pursuant to SubClause 60.13 has been made and the performance security referred to in Sub-Clause 10.1 has been returned to the Contractor. SUB-CLAUSE 60.13 FINAL PAYMENT CERTIFICATE Within 28 days after receipt of the Final Statement, and the written discharge, the Engineer shall deliver to the Employer (with a copy to the Contractor) a Final Payment Certificate stating a) The amount which, in the opinion of the Engineer, is finally due under the Contract or otherwise, and b) After giving credit to the Employer for all amounts previously paid by the Employer and for all sums to which the Employer is entitled, other than under Clause 47, the balance, if any, due from the Employer to the Contractor or from the Contractor to the Employer as the case may be. Page 5.46 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 60.14 CESSATION OF EMPLOYER’S LIABILITY Section 5 Part II – Conditions of Particular Application The Employer shall not be liable to the Contractor for any matter or thing arising out of or in connection with the Contract or execution of the Works, unless the Contractor shall have included a claim in respect thereof in his Final Statement and (except in respect of matters or things arising after the issue of the Taking-Over Certificate in respect of the whole of the Works) in the Statement at Completion referred to in SubClause 60.10. REMEDIES SUB-CLAUSE 63.1 DEFAULT OF CONTRACTOR Delete the last paragraph of this sub-clause and substitute: SUB-CLAUSE 63.2 VALUATION AT DATE OF EXPULSION Modify the heading of Sub-Clause 63.2 by substituting “Valuation at Date of Expulsion” for “Valuation at Date of Termination”. In Sub-Clause 63.2, delete the word “termination on the second and fifth lines and substitute “expulsion”. Ethiopian Roads Authority “then the Employer may, after giving 14 days’ notice to the Contractor, enter upon the Site and expel the Contractor therefrom without thereby voiding the Contract, or releasing the Contractor from any of his obligations or liabilities under the Contract, or affecting the rights and powers conferred on the Employer or the Engineer by the Contract, and may himself complete the Works or may employ any other contractor to complete the Works. The Employer or such other contractor may use for such completion so much of the Contractor’s Equipment, Plant, Temporary Works, and materials, which have been deemed to be reserved exclusively for the execution of the Works, under the provisions of the Contract, as he or they may think proper, and the Employer may, at any time, sell any of the said Contractor’s Equipment, Temporary Works, and unused Plant and materials, and apply the proceeds of sale in or towards the satisfaction of any sums due or which may become due to him from the Contractor under the Contract.” Page 5.47 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 63.3 PAYMENT AFTER EXPULSION Modify the heading of Sub-Clause 63.3 by substituting “Payment after Expulsion” for “Payment after Termination”. In Sub-Clause 63.3, delete the words “terminates the Contractor’s employment” on the first line and substitute “shall enter and expel the Contractor”. SUB-CLAUSE 63.4 ASSIGNMENT OF BENEFIT OF AGREEMENT In Sub-Clause 63.4, delete the word “termination” on the second line, and substitute “expulsion”. SUB-CLAUSE 63.5 CORRUPT OR FRAUDULENT PRACTICES If in the judgment of the Employer the Contractor has engaged in corrupt or fraudulent practices, in competing for or in executing the Contract, then the Employer may, after having given 14 days notice to the Contractor, terminate the Contractor’s employment under the Contract and expel him from the Site, and the provisions of Clause 63 shall apply as if such expulsion had been made under Sub-Clause 63.1. For the purpose of this sub-clause: “Corrupt practice” means the offering, giving, receiving or soliciting of any thing of value to influence the action of a public official in the procurement process or in contract execution. “Fraudulent practice” means a misrepresentation of facts in order to influence a procurement process or the execution of a contract to the detriment of the Borrower, and includes collusive practice among bidders (prior to or after bid submission) designed to establish bid prices at artificial non-competitive levels and to deprive the Borrower of the benefits of free and open competition.” SPECIAL RISKS SUB-CLAUSE 65.2 SPECIAL RISKS Page 5.48 Amend Sub-Clause 65.2 to read as follows: “The Special Risks are the risks defined under para. (a), sub-paragraphs (i) to (v) of Sub-Clause 20.4.” Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 65.4 PROJECTILE, MISSILE Section 5 Part II – Conditions of Particular Application Delete “whenever and wherever occurring” in line 2 and add “on or near the site” after “explosive of war” in line 3. SETTLEMENT OF DISPUTES SUB-CLAUSE 67.1 SETTLEMENT OF DISPUTES Add to Sub-Clause 67.1 "The procedure for settlement of disputes is stipulated in the Appendix to Tender. Section 12 of the Tendering Documents shall be incorporated in and be part of these Conditions of Particular Application." NOTICES SUB-CLAUSE 68.2 NOTICE TO EMPLOYER AND ENGINEER For the purposes of this Sub-Clause, the addresses are those specified in the Appendix to Bid. DEFAULT OF EMPLOYER SUB-CLAUSE 69 DEFAULT OF EMPLOYER In Sub-Clauses 69.1, 69.4 and 69.5, substitute “Sub-Clause 60.8” for “Sub-Clause 60.10”. SUB-CLAUSE 69.1 DEFAULT OF EMPLOYER Delete paragraph (b) and substitute the following: Ethiopian Roads Authority “ (b) Interfering with or obstructing or refusing any required approval to the issue of any such certificate, except that the acts of the Employer set out in Sub Page 5.49 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 Clause 2.1 hereof shall not be construed as such interference, obstruction or refusal.” Delete paragraph (d) SUB-CLAUSE 69.3 PAYMENT ON TERMINATION Delete from ", but in addition to the payments specified...” to the end of the Sub-Clause. SUB-CLAUSE 69.4 CONTRACTOR’S ENTITLEMENT TO SUSPEND WORK Add this paragraph: Without prejudice to the Contractor’s entitlement to interest under Sub-Clause 60.8 and to terminate under Sub-Clause 69.1, the Contractor may suspend work or reduce the rate of work within 56 days after notification by the Funding Agency to the Employer’s government that the Funding Agency has suspended disbursements from its loan or credit, which finances in whole or in part the execution of the Works. SUB-CLAUSE 69.5 RESUMPTION OF WORK Delete in line three “Sub-Clause 60.10” and substitute with “Sub-Clause 60.8”. SUB-CLAUSE 69.6 SUSPENSION OF FUNDING AGENCY’S LOAN OR CREDIT In the event the Funding Agency suspends the loan or credit from which part of the payments to the Contractor are being made: (a) The Employer shall notify the Contractor, with copy to the Engineer, of such suspension within 7 days of having received the suspension notice from the Funding Agency, provided (i) that the Employer shall state in such notification whether sufficient funds in appropriate currencies are expected to be available to the Employer to continue making payments to the Contractor beyond a date 60 days after the date of the Funding Agency notification of the suspension, and (ii) that, if such funds are not expected to be available, the Employer shall immediately instruct the Engineer to instruct the Contractor to suspend the progress of the Works pursuant to Clause 40.1. (b) If the Contractor has not received sums due to him upon the expiration of the 14 days referred to in Sub-Clause 60.8 (a) (i) (B) for payments under Interim Certificates, the Page 5.50 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application Contractor may without prejudice to the Contractor's entitlement to interest under Sub-Clause 60.8 immediately take one or both of the following actions, namely (i) suspend work or reduce the rate of work, and (ii) terminate his employment under the Contract by giving notice to the Employer, with a copy to the Engineer, such termination to take effect 14 days after the giving of the notice." CHANGES IN COST AND LEGISLATION SUB-CLAUSE 70 CHANGES IN COST AND LEGISLATION SUB-CLAUSE 70.1 PRICE ADJUSTMENT Delete Clause 70 in its entirety, and substitute: SUB-CLAUSE 70.2 OTHER CHANGES IN COST To the extent that full compensation for any rise or fall in costs to the Contractor is not covered by the provisions of this or other Clauses in the Contract, the unit rates and prices included in the Contract shall be deemed to include amounts to cover the contingency of such other rise or fall of costs. SUB-CLAUSE 70.3 ADJUSTMENT FORMULAE The adjustment to the Interim Payment Certificates in respect of changes in cost and legislation shall be determined from separate formulae for each of the currencies of payment and each Bill of Quantities. The formulae will be of the following type: The amounts payable to the Contractor, in various currencies pursuant to Sub-Clause 60.1, shall be adjusted in respect of the rise or fall in the cost of labor, Contractor’s Equipment, Plant, materials and other inputs to the Works by applying to such amounts the formulae prescribed in this clause. Pn= a + b Ln/Lo + c Mn/Mo + d En/Eo + etc. Where: Pn is a price adjustment factor to be applied to the amount in each specific currency for the payment of the work carried out in the subject month, determined in accordance with Sub-Clause 60.1 (d), and Sub-Clauses 60.1 (e) and (f), where such variations and Daywork are not otherwise subject to adjustment; Ethiopian Roads Authority Page 5.51 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 a is a constant, specified in the Appendix to Bid, representing the nonadjustable portion in contractual payments; b, c, d, etc., are weightings or coefficients representing the estimated proportion of each cost element (labor, materials, equipment usage, etc.) in the Works or sections thereof, net of Provisional Sums, as specified in the Appendix to Bid; Ln, Mn, En, etc., are the current cost indices or reference prices of the cost elements in the specific currency for month “n” determined pursuant to Sub-Clause 70.5, applicable to each cost element; and Lo, Mo, Eo, etc., are the base cost indices or reference prices corresponding to the above cost elements at the date specified in Sub-Clause 70.5. If a price adjustment factor is applied to payments made in a currency other than the currency of the source of the index for a particular indexed input, a correction factor Zo/Z will be applied to the respective component factor of Pn for the formula of the relevant currency. Zo is the number of units of currency of the country of the index, equivalent to one unit of the currency of payment on the date of the base index, and Z is the corresponding number of such currency units on the date of the current index. SUB-CLAUSE 70.4 SOURCES OF INDICES AND WEIGHTINGS The sources of indices shall be those listed in Appendix to Bid, as approved by the Engineer. Indices shall be appropriate for their purpose and shall relate to the Contractor's proposed source of supply of inputs on the basis of which his Contract Price and expected foreign currency requirements shall have been computed. As the proposed basis for price adjustment, the Contractor shall have submitted with his bid the tabulation of Weightings and Source of Indices in the Appendix to Bid, which shall be subject to approval by the Engineer. SUB-CLAUSE 70.5 BASE, CURRENT AND PROVISIONAL INDICES The base cost indices or prices shall be those prevailing on the day 28 days prior to the latest date for submission of bids. Current indices or prices shall be those prevailing on the day 28 days prior to the last day of the period to which a particular Page 5.52 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application Interim Payment Certificate is related. If at any time the current indices are not available, provisional indices as determined by the Engineer will be used, subject to subsequent correction of the amounts paid to the Contractor when the current indices become available. SUB-CLAUSE 70.6 ADJUSTMENT AFTER COMPLETION If the Contractor fails to complete the Works within the time for completion prescribed under Clause 43, adjustment of prices thereafter until the date of completion of the Works shall be made using either the indices or prices relating to the prescribed time for completion, or the current indices or prices, whichever is more favorable to the Employer, provided that if an extension of time is granted pursuant to Clause 44, the above provision shall apply only to adjustments made after the expiry of such extensions of time. SUB-CLAUSE 70.7 WEIGHTINGS The weightings for each of the factors of cost given in the Appendix to Bid shall be adjusted if, in the opinion of the Engineer, they have been rendered unreasonable, unbalanced or inapplicable as a result of varied or additional work already executed or instructed under Clause 51 or for any other reason. SUB-CLAUSE 70.8 SUBSEQUENT LEGISLATION If, after the date 28 days prior to the latest date for submission of bids for the Contract, there occur in the country in which the Works are being or are to be executed changes to any National or State Statute, Ordinance, Decree, or other Law or any regulation or by-law of any local or other duly constituted authority, or the introduction of any such State Statute, Ordinance, Decree, Law, regulation or by-law which causes additional or reduced cost to the Contractor, other than under the preceding sub-clauses of this clause, in the execution of the Contract, such additional or reduced cost shall, after due consultation with the Employer and the Contractor, be determined by the Engineer and shall be added to or deducted from the Contract Price and the Engineer shall notify the Contractor accordingly, with a copy to the Employer. Notwithstanding the foregoing, such additional or reduced cost shall not be separately paid or credited if the same shall already have taken into account in the indexing of any inputs to the Price Adjustment Formulae in accordance with the provisions of Sub-Clauses 70.1 to 70.7. Ethiopian Roads Authority Page 5.53 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 CURRENCY AND RATES OF EXCHANGE SUB-CLAUSE 72.2 CURRENCY PROPORTIONS Amend Sub-Clause 72.2 as follows: Delete the words from " Central Bank of the country in which the Works are to be executed" and substitute the following: "source stated in the Appendix to Bid.” After “prevailing”, insert “for similar transactions”. ADDITIONAL CLAUSES SUB-CLAUSE 73.1 FOREIGN TAXATION The prices bid by the Contractor shall include all taxes, duties, and other charges imposed outside the Employer’s country on the production, manufacture, sale, and transport of the Contractor’s Equipment, Plant, materials, and supplies to be used on or furnished under the Contract, and on the services performed under the Contract. SUB-CLAUSE 73.2 LOCAL TAXATION The prices bid by the Contractor shall include all customs duties, import duties, business taxes, and income and other taxes that may be levied in accordance with the laws and regulations in being on the date 28 days prior to the latest date for submission of bids in the Employer’s country on the Contractor’s Equipment, Plant, materials, and supplies (permanent, temporary, and consumable) acquired for the purpose of the Contract and on the services performed under the Contract. Nothing in the Contract shall relieve the Contractor from his responsibility to pay any tax that may be levied in the Employer’s country on profits made by him in respect of the Contract. Page 5.54 Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application SUB-CLAUSE 73.3 INCOME TAXES ON STAFF The Contractor’s staff and labor will be liable to pay personal income taxes in the Employer’s country in respect of such of their salaries and wages as are chargeable under the laws and regulations for the time being in force, and the Contractor shall perform such duties in regard to such deductions thereof as may be imposed on him by such laws and regulations. SUB-CLAUSE 74.1 ILLEGAL PAYMENTS If the Contractor, or any of his Subcontractors, agents or servants gives or offers to give any person any payment, gift, gratuity or commission as an inducement or reward for doing or forbearing to do any action in relation to the Contract or any other contract with the Employer, or for showing or forbearing to show favor or disfavor to any person in relation to the Contract or to any other contract with the Employer, the Employer may enter upon the Site and the Works and expel the Contractor and the provisions of Clause 63 hereof shall apply as if such entry and expulsion had been made pursuant to that clause. SUB-CLAUSE 75.1 TERMINATION OF CONTRACT FOR EMPLOYER’S CONVENIENCE The Employer shall be entitled to terminate this Contract at any time for the Employer’s convenience after giving 56 days’ prior notice to the Contractor, with a copy to the Engineer. In the event of such termination, the Contractor a) Shall proceed as provided in Sub-Clause 65.7; and b) Shall be paid by the Employer as provided in Sub-Clause 65.8. SUB-CLAUSE76.1 RESTRICTIONS ON ELIGIBILITY a) Any Plant, materials, or services which will be incorporated in or required for the Works, as well as the Contractor’s Equipment and other supplies, shall have their origin in any of the countries and territories eligible under the Guidelines of the Funding Agency if such requirement is stipulated in the Agency’s Guide line b) For the purposes of this clause, “origin” means the place where the materials and equipment were mined, grown, produced, or manufactured, or from which the services are provided. c) The origin of Goods and Services is distinct from the nationality of the Supplier. Ethiopian Roads Authority Page 5.55 Section 5 Part II – Conditions of Particular Application Standard Bidding Documents For Roadwork Contracts ICB – 2002 SUB-CLAUSE 77.1 JOINT AND SEVERAL LIABILITY If the Contractor is a joint venture of two or more persons, all such persons shall be jointly and severally bound to the Employer for the fulfillment of the terms of the Contract and shall designate one of such persons to act as a leader with authority to bind the joint venture. The composition or the constitution of the joint venture shall not be altered without the prior consent of the Employer. SUB-CLAUSE 78.1 IMPORTATION AND USE OF DANGEROUS MATERIALS The Contractor and his subcontractors shall in the conveyance, handling, storage and use of all dangerous materials such as explosives, detonators, petroleum, acetylene, oxygen, calcium carbide, radioactive materials, etc., comply with and adhere strictly to in all respects with the Laws of the Federal Democratic Republic of Ethiopia. Explosives and Blasting Page 5.56 (a) No explosives of any kinds shall be used without the prior consent, in writing by the Engineer. Once this consent is granted, the Contractor shall be solely responsible for obtaining, handling, transporting, storing, accounting for using, and disposal of surplus detonators, fuels, bulk explosives and other things associated with blasting, and for complying in all respect with the Laws of the Federal Democratic Republic of Ethiopia, and shall save the Employer and the Engineer harmless from all consequences whatsoever arising out of the consent so given by the Engineer. (b) The Contractor shall at all times take every possible precaution and shall conform with the appropriate laws and regulations relating to the importation, handling, transportation, storage and use of explosives and shall at all times when engaged in blasting operations post sufficient warning flagmen, watchmen and barricades to the full satisfaction of the Engineer and arrange the timely clearance of debris. On any work requiring the use of explosives, the Contractor shall employ men experienced in blasting and these men must be in position of a current blasting certificate. Ethiopian Roads Authority Standard Bidding Documents For Roadwork Contracts ICB – 2002 Section 5 Part II – Conditions of Particular Application (c) The Contractor shall at all times liaise with and inform well in advance and obtain such permission as is required from all government authorities, public bodies and private parties whatsoever concerned or affected or likely to be concerned or affected by blasting operations. (d) The Contractor shall be solely responsible to provide, supply, handle, store and transport all explosives ancillary materials and stores and all other things of every kind whatsoever required for blasting operations and shall not delegate or sub-contract these activities. (e) Before the beginning of the Defects Liability Period the Contractor shall remove all unused explosives from the site on completion of the Works or when ordered by the Engineer, and shall submit written confirmation of compliance with this instruction to the Engineer. SUB-CLAUSE 79.1 DETAILS TO BE CONFIDENTIAL The Contractor shall treat the details of the Contract as private and confidential, save insofar as may be necessary for the purposes thereof, and shall not publish or disclose the same or any particulars thereof in any trade or technical paper or elsewhere without the previous consent in writing of the Employer or the Engineer. If any dispute arises as to the necessity of any publication or disclosure for the purpose of the Contract the same shall be referred to the Employer whose determination shall be final. SUB-CLAUSE 80.1 OFFICIAL VISITORS The Contractor shall at all times when authorised by the Engineer give free and undisputed access and all facilities to any authorised employee of the Government or other authorised person wishing to view or inspect any part of the Site or Works or the materials therein. SUB-CLAUSE 81.1 LEGAL PROVISIONS The Contractor shall keep himself fully conversant with the latest enactments, provisions and regulations of all legislative and statutory bodies, and, in all respects and at all times, shall comply with such enactment, provisions and regulations in regard to executing the contract. Ethiopian Roads Authority Page 5.57