Permit To Work System Contents 1. 2. 3. 4. 5. 6. 7. Introduction When are Permits to Work Systems Required? Definitions Responsibilities Essentials of Permit to Work System Work Planning and Risk Assessment for Permit to work system Further information and advice Appendix 1- Permit to Work Form Appendix 2- Register of Permits to Work Systems Appendix 3- Permit to Work Monitoring Checklist Appendix 4- Flowchart for work planning and Risk Assessment Procedure Appendix 5- Flowchart for Permit to Work Safe Systems of Work 1.0 Introduction 1.1 Permit to Work system is a formal safety control document designed to prevent injury to employees, contractors and third parties as well as to property, particularly when work with foreseeable high hazard content is undertaken. The Permit sets out the work to be done, precautions to be taken and the responsibilities of individuals. This guidance is intended to assist Line Managers, Headteachers, and people in charge of divisional units to ensure that a safe system of work is in place for maintenance work, small or short term projects where previously hazardous conditions have been identified. A permit to work system will be required to ensure no worker is subjected to any significant risk, and also in fulfilling legal obligations under the Health and Safety At Work Act 1974, and The Management of Health and Safety Regulations 1999. 1.2 A permit to work system forms an essential part of a safe system of work. It also forms an integral part of a risk assessment process, where specific hazards are identified, and suitable control measures are implemented prior to commencement of the work task. However, it is important to ensure that people carrying out work task where a permit to work system is required have the necessary competence to undertake the job safely. C 2.0 When Are Permit to work Systems Required? 2.1 A permit to work system is required or should be considered whenever works intended to be carried out may adversely affect the safety of people, plant or the environment. Permit to work systems are not required for routine maintenance activities in a non-hazardous environment. Permit to work systems should be considered where: 2.2 • Non -production work (e.g. maintenance, repairs, inspections, testing, etc); • Works where two or more individuals need to co-ordinate activities to complete the job safely; • Jobs where there is a transfer of work and responsibilities from one contractor to the other; • Non -routine operations or activities. As a general guide a permit to work system may be required for work activities that involve: • Confined space working; • Hot works such as welding, flame cutting and grinding; • Working at height; • Certain excavation works; • Working on fragile roofs; • Maintenance work on lifts, conveyors, hoists etc; • Work on high voltage electrical equipment or other work on electrical equipment which may give rise to potential dangers; • Any activity which require additional precautions or personal protective equipment (PPE) to be in place; • Work involving the use of hazardous/dangerous substances. Children’s Services Health and Safety August 2008 Page 2 of 13 GN027 C 3.0 Definitions 3.1 Safe System of Work: It is a controlled and considered way of carrying out a work task, which eliminates the risk to health and safety so far as it is reasonably practicable. It sets out the work to be done and precautions to be taken. Hence, in its simplest form; Safe System of Work = Risk Assessment + Method Statement 3.2 Permit to Work System: This is a formal written system document used to closely control certain types of activities, tasks, processes or work that have specific hazards or are potentially hazardous. A permit to work system will include details of the work to be done, what is involved including all the required precautions and emergency procedures, people involved, limits on the work task or equipment to effectively carry out the job safely. Examples include hot works, excavations, and entry into a confined space. 3.3 Method Statement: This is a document detailing how a particular task will be carried out. It should detail all the possible dangers/risk associated with the job, and the methods of controls to be established to show how the job would be managed safely. 3.4 Line Manager: This means all staff who have authority and responsibility for directing and supervising people working for them, be they permanent, temporary or contractually employed. Within schools, the Headteacher is responsible for ensuring that the policies are implemented, and that appropriate responsibilities are delegated down to competent individuals. 3.5 Competent Person: Anyone but not necessarily the Line Manager would be deemed competent by virtue of training, qualification, knowledge, experience and qualities appropriate to their duties. Therefore, a competent person must have a practical knowledge of the work activity/task to be undertaken, and also be familiar with the requirements of any relevant regulations. 3.6 Person in Charge (Supervisor): This is a competent person who has accepted a permit to work system from the authorised person, and is named on the permit to work, and also has direct responsibilities for the specific work to be undertaken. 3.7 Authorised Person: This is the person responsible for authorising and issuing permit to the people to do the work. 4.0 Responsibilities 4.1 The assessment of risks and the control of works requiring a permit to work system is the responsibility of Headteacher/Line Manager. In many cases the Headteacher/Line Manager may require the assistance of competent persons, which may include staff working with the process, or a nominated person in charge, to supply details to complete the activity safely. The use of such assistance does not absolve the Headteacher/Line Manager from their responsibilities for health and safety at work. It will however, enable the Line Manager to demonstrate that their duties have been discharged adequately. Children’s Services Health and Safety August 2008 Page 3 of 13 GN027 C 4.1.1 The Management of health and Safety at Work Regulation 1999 specifies duties under the Health and Safety at Work Act 1974, which relate to the control of work activity and risk assessment establishes a clear hierarchy of measures for Managers. Line Managers, Headteachers and people in charge of divisional units are therefore responsible for ensuring that all work tasks under their control are carried out safely. Where required, a permit to work system must be introduced, developed, followed and continually monitored for its effectiveness. Managers responsibilities include: • Ensuring appropriate permit to work systems are implemented where required; introduced and • Ensuring a permit to work is completed correctly and passed to the relevant authorised person; • Ensuring a competent person is appointed to be the person in charge of the work task; • Making sure appropriate procedures are established and maintained for all work tasks completed under the permit to work system; • co-ordinating with the authorised person to monitored the progress of the activity for effective and correct use of the permit to work; • Ensuring the permit to work system is audited and reviewed; • Ensuring copies of the permits, or records of their issue are kept for a period of 4years to enable auditing or incident investigation; • Making sure contractors working within the permit system have sufficient knowledge and competence to carry out their duties; • Ensuring appropriate Personal Protective Equipment (PPE) are used and stored correctly; • Making sure there is adequate heating and lighting etc. • Ensuring upon completion of works, the supervisor return the completed permit, and signed off by the authorised person. 5.0 Essentials of Permit to Work Systems 5.1 Permit Display: Copies of the permit to work should be clearly displayed at the work site or in a location close to where the work activity is being undertaken. Line Managers are also required to ensure that a copy of the permit to work is kept and made available where the work site is located else where on the premises. Appendix 1 – shows a permit to work form. 5.2 Permit Suspension: Some work activities where a permit to work system is required may be suspended if there is a general alarm for operational reasons, and where the wrong permit to work have been issued for a different type of work, a change in scope of work or waiting for Children’s Services Health and Safety August 2008 Page 4 of 13 GN027 C spares (Example is using a hot work permit to undertake a work activity in a confined space). 5.3 Permit Interaction: Line Managers are also required to ensure that one activity under a permit to work does not create possible danger for others even if the other work activity does not require a permit to work system. Permit authorisers should be aware of potential interaction, and ensure that completed permit takes into account other currently planned activity. 5.4 Permit Authorisation: A permit to work system is fully effective only if the permits are co-ordinated and controlled, and with a signature confirming that isolations (electrical, mechanical, substances etc.) have been made and precautions (protective equipment & clothing) taken by an issuing authority to undertake an activity safely. 5.5 Permit Number: This is a unique number that may be required to be cross-referenced to any other permit or isolation certificate. 5.6 Activity/Task Location: Exact location where the work activity is to be carried out. 5.7 Plant Identification: Outlines a description of the type, identification number, etc. of plant to be used for works. 5.8 Work Activity/Task: This should outline details of the work activity to be carried out with the step by step procedure and precautions 5.9 Hazard Identification: Includes residual hazards as well as hazards introduced by the work activity. 5.10 Control Measures: This details what control measures need to be implemented and followed by person in charge to ensure a safe system of work is achieved. E.g. for electrical isolation works person who carries out isolation should sign to acknowledge that all required precautions have been taken. 5.11 Protective Equipment: All required protective equipment necessary for undertaking work activity safely. 5.12 Authorisation Signature confirming that isolations have been made and precautions taken, excepts where these can only be taken during the work activity. It should specify the date, time and duration of the permit to work system. 5.13 Acceptance: Signature of person in charge acknowledging understanding of the work task to be carried out, limitations on whom may do the work, hazards involved precautions to be taken and explanation of works by the authorised person. Children’s Services Health and Safety August 2008 Page 5 of 13 GN027 C 5.14 Permit Hand back: The hand-back procedure should confirm whether works for which the permit was issued have been completed, stopped or suspended and needs confirmation from the permit authoriser. All plant or equipment used in undertaking the task must be returned safe, and any isolation removed and verified by the person in charge. 6.0 Work Planning and Risk Assessment for Permit to Work Systems 6.1 Line Managers planning for maintenance work involving a permit to work system need to identify any significant hazard, competency and training where required to carry out work activity, and also to ensure that risk assessments are completed and control measures implemented. Appendix 2 & 3- A flowchart of work planning and risk assessment procedure. Monitoring 6.2 Permit to work methods should be monitored by supervisors to ensure compliance with step by step work activity instructions and control measures. Monitoring records should be kept on site, and reviewed during permit to work audits. Line Managers should be alerted immediately if any non-conformance is identified during monitoring or auditing of the permit system. A checklist for day to day monitoring of permit to work is outlined in Appendix 4. Reviews 6.3 Permit to work systems should be reviewed at least annually by Line managers/headteachers to assess their effectiveness. The review should account for both good and poor indicators together with any specific incidents that could relate to any insufficient control of the work activity. Review should also take into account any previous audit reports and recent safety alerts. Review of the permit to work system is required when: • Shortly after implementing a permit to work system in order to assess the effectiveness of control measures. The review would also look at medium and long-term measures that may have resource implications, which may have been raised upwards through the chain of command (Time scales may vary). • An accident or incident occurs, and any subsequent investigation identifies specific changes in relation to permit to work for the work task. • There has been a significant change in the work task procedure, equipment or competency, • There is reason to suspect that, there is inadequate control of the work task. Children’s Services Health and Safety August 2008 Page 6 of 13 GN027 C Retention of Permit Records 6.4 Permits to work certificates and risk assessments for work activities are subject to audits, and should be retained by authorised person for a period of 4 years to enable effective monitoring and audit process. • Permit to work certificate and risk assessment should be retained at the site for at least 30 days after completion of works. • Permit to work and risk assessments should be retained by Line Managers for a period of 4 years after they are issued, cancelled or superseded by the permit authoriser. • Training Records should also be retained for a period of 4 years Training and Competence: 6.5 Effective training and competence of workers involved in a permit to work system are essential in achieving a safe system of work. This provides the backbone for effective implementation of the permit to work system. The Line Manager is responsible for ensuring that personnel to be actively involved in the permit to work system have received training and understand the working environment, associated hazards and the control measures required to manage the risks presented by hazards from the work to be done. Competence should also be determined by assessing the personnel involved against the work activities being carried out for the purposes of health and safety. 7.0 Further advice and assistance 7.1 If at any time during an investigation further advice, assistance or information is needed, contact the Children’s Services Health and Safety Team at Tooley Street, 4th Floor on extensions 55034, 55035, 55259 & 53808 who will be able to help. Children’s Services Health and Safety August 2008 Page 7 of 13 GN027 C Appendix 1 – Permit to Work Form 1. Project 3. Job Work being done: 2. Permit Reference Number: Location: 4. Plant Identification: 5. Description of work activity to be carried out and its limitations: _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ 6. Cross-Referenced Documentation: (The following Risk assessments, Permits, Safe Systems of Work, Method Statements, and Maintenance procedures are applicable to this task). ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ 7. Hazard identification and Control Measures: (The following residual hazards, and associated work hazards exist with this work activity and the listed control measures are to be implemented including personal protective equipmentPPE). Hazard Control Measures _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ 8. Precautions necessary and actions in the event of an emergency: _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ 9. Protective equipment (including PPE): 10. Authorisation: (I have reviewed all aspects of the work activity and i certify that isolations and precautions have been taken as detailed in the method statement/ safe system of work, except where these precautions can only be taken during the work). Name:______________________________________ Date:____/____/_____ Time:____:_____ Signature:_______________________________________ Permit duration: From:___:____ hrs To: : hrs Date:_____/____/_____ Date: / / 11. Acceptance by Person in Charge: (I Certify that i have read and fully understand the documentation associated with this work activity, the hazards involved and precautions required, and that procedures to carry out works have been explained. I am also satisfied that the workforce to undertake the work activity are properly equipped and understand the safety and emergency procedures to be followed and are competent). Name:_________________________________________ Children’s Services Health and Safety August 2008 Page 8 of 13 Signature:_______________________________ GN027 C Date: / / Time: : 12. Hand Back by Person in Charge: (I certify that the work activity detailed above has been :- *delete as required) *a. Completed *b. Stopped/suspended. The work activity was stopped/suspended at ___:___hrs on the ____/____/____(date) Details of the reasons for stoppage/suspension and arrangements to isolate and prevent all unauthorised access to the work activity are: a. The work activity detailed above has been stopped/suspended for the reason listed below: _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ b. The following arrangements have been put in place to prevent unauthorised access to the work site _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ _____________________________________________________________________________________________________ Name (person in charge):_______________________________ Signature:_____________________________ Date: _____/_____/______ Time: ____:____ hrs Name (permit authoriser):_______________________________ Signature:_____________________________ Date: Time: / / : hrs 13. Cancellation: (I certify that this permit to work is cancelled and that the work activity detailed above has been:- * delete as required) *a. Completed at ____:_____ hrs on the ____/_____/______(date) *b. Stopped/suspended. I confirm that the work activity was stopped/suspended for the reason detailed above, and i agree with the arrangements that have been put in place to prevent unauthorised access. This permit to work is now cancelled and all further work will be authorised on Permit to Work Serial No________________ Name (permit authoriser):_______________________________ Signature:_____________________________ Date: Time: / / Children’s Services Health and Safety August 2008 Page 9 of 13 : hrs GN027 C Appendix 2 – Register of Permits to Work Systems Date: Name of person in charge: Time: : hrs Project Work being done: Work Location: Permit Serial No. Children’s Services Health and Safety August 2008 Page 10 of 13 Start date of Permit to Work Permit Type Date Permit to work closed Line Managers Signature GN027 C Appendix 3 –Permit to Work Monitoring Checklist Date: / / Permit Type: Time: Active: Permit No: Complete: Person in charge (Name): Appended certificates: *If any unsafe conditions are found, the work activity must be stopped and the Line Manager notified immediately. Yes No N/A Is the scope of work activity clearly specified? Are completed risk assessments for the work activity available for review? Are hazards associated with the work activity listed on the permit to work? Are all the required precautions listed on the permit to work system? Is the time limit for the permit to work clear, and are any extensions properly authorised? Are certificates completed and appended to the permit to work? Are copies of certificates, permits and attachments legible? Are signatures and initials traceable and legible? Are copies of permits and certificates posted at correct locations? Are all attachments, drawings etc. held at correct locations? Have permit to work users been briefed and acknowledged understanding of all the necessary requirements to the permit? Is the work group aware of what to do in the event of an emergency? Are isolations appropriate for the task, correctly specified on the permit and implemented? Is the work activity being carried out in conformance with the permit to work system? Are control measures and protective equipment including PPE appropriate for the work activity? Are tools and work equipment suitable for the work activity? Is general housekeeping maintained in good standard? Comments: Children’s Services Health and Safety August 2008 Page 11 of 13 GN027 C Appendix 4 - Flowchart for work planning and Risk Assessment Procedure Activity/Task Request Activity/Task Parameters (Identify what the work activity will involve, competencies required and assess the risk) Categorise Specific Activity/Task (Review task and identify what task specific risk assessment is required) Previously Assessed Work activity/task Existing assessment Review Work Activity/task outside scope of permit system Newly Identified Activity/Task (Activity/task not previously assessed or performed) Activity/Task Risk Assessment (Identify all the hazards, control measures, implementation, monitoring &review) Agreement to proceed with Work Activity/Task? Stop Work No Stop Work Yes Changes to Scope of work Activity/Task Implement Control Measures Permit Issued and Accepted? Yes Carry out Work Activity Children’s Services Health and Safety August 2008 Page 12 of 13 GN027 C Appendix 5 – Flowchart for Permit to Work Safe Systems of Work No Has Activity/Task Risk Assessment been completed? Yes Undertake a Risk Assessment for Work Activity Have hazards relating to work activity been identified, and control measures implemented? Yes Do significant risks still exist after control measures have been implemented? No Yes No Has a Method Statement been prepared for work activity/task? Yes Prepare a written safe system of work or method statement for work activity Do significant risks still exist after introducing a safe system of work/method statement or the safe system of work require further control measures? No Yes Permit to work System is Required Children’s Services Health and Safety August 2008 Page 13 of 13 Permit to Work System Not Required GN027