January

advertisement
Squires Elementary -- Renovation

Architect:
JRA Architects

General Contractor:

GC Contract Sum:
$12,166,000

Total Project Cost:
$15,207,000

Change Orders to Date (8):

Scheduled Contract Completion Date:

% of Contract Completed:

Revised Completion Date per GC:
D.W. Wilburn, Inc.
$52,818
July 2016
73.0%
No Change
January 2016
Squires Elementary -- Renovation
Rendering of Final Façade
January 2016
Squires Elementary -- Renovation
Work

Completed to Date:

Renovated classroom wing in Area “B” has been turned over and is in use.

Exterior spray insulation is complete on the classroom wing addition in Area “B”
(Phase 2A).

Brick continued on the classroom wing addition in Area “B” (Phase 2A).

Window installation has begun in the classroom addition in Area “B” (Phase 2A).

Selective demolition is 80% complete in Area “C” and Area “D” (Phase 3).
Current Work Effort (January):

Brick to complete on the classroom wing addition in Area “B” (Phase 2A).

Window installation to complete on the classroom wing addition in Area “B”
(Phase 2A).

Site demolition will complete where the kitchen will be built (Phase 3).

Masonry walls will continue in Area “C” and Area “D” (Phase 3).

MEP rough-in will continue in Area “C” and Area “D” (Phase 3).
January 2016
Squires Elementary -- Renovation
Early Start Playground
New Classroom Wing
New Windows
Insulating Pipes
January 2016
Squires Elementary -- Renovation
Pulling Data Cable
Temporary Partitions
Selective Demolition
Site Demo – New Kitchen
January 2016
Download