Squires Elementary -- Renovation Architect: JRA Architects General Contractor: GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (8): Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: D.W. Wilburn, Inc. $52,818 July 2016 73.0% No Change January 2016 Squires Elementary -- Renovation Rendering of Final Façade January 2016 Squires Elementary -- Renovation Work Completed to Date: Renovated classroom wing in Area “B” has been turned over and is in use. Exterior spray insulation is complete on the classroom wing addition in Area “B” (Phase 2A). Brick continued on the classroom wing addition in Area “B” (Phase 2A). Window installation has begun in the classroom addition in Area “B” (Phase 2A). Selective demolition is 80% complete in Area “C” and Area “D” (Phase 3). Current Work Effort (January): Brick to complete on the classroom wing addition in Area “B” (Phase 2A). Window installation to complete on the classroom wing addition in Area “B” (Phase 2A). Site demolition will complete where the kitchen will be built (Phase 3). Masonry walls will continue in Area “C” and Area “D” (Phase 3). MEP rough-in will continue in Area “C” and Area “D” (Phase 3). January 2016 Squires Elementary -- Renovation Early Start Playground New Classroom Wing New Windows Insulating Pipes January 2016 Squires Elementary -- Renovation Pulling Data Cable Temporary Partitions Selective Demolition Site Demo – New Kitchen January 2016