Selective Coordination Compliance – Methods for Evaluation and Mitigation Dave Bradley, PE, LEED AP August 8, 2008 New requirements for Selective Coordination became a part of the National Electrical Code® in 2005. Since then the topic has been often misunderstood, avoided, discussed and debated. Selective Coordination is an enforceable code requirement in many areas, and as such is also a design requirement. This document will attempt to give the engineer and designer basic background, methodology and mitigation methods to assist in designing to these new requirements. BACKGROUND What is selective coordination? Selective coordination is a design requirement where only the overcurrent device immediately upstream from the fault will operate, minimizing the outage caused by the fault. 2005 NEC® Article 100 defines “Coordination (Selective)” as “Localization of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished by the choice of overcurrent protective devices and their ratings or settings.” In the diagram below, only device C would open under the fault. For selective coordination, the system would be designed so that for a fault of any magnitude (up to the available fault current at device C) device C is guaranteed to clear the fault with neither B nor A opening. What do the new code sections say? In addition to the definition above, new requirements were added in the 2005 and 2008 National Electrical Code to Article 700 - Emergency Systems (see 700.27), Article 701 - Legally Required Standby Systems (see 701.18), and by the 2008 NEC to Article 708 - Critical Operations Power Systems (COPS) (see 708.54). These Articles also apply to Health Care Facilities as noted in 517.26. The new requirements state that the overcurrent devices of those systems “shall be selectively coordinated with all supply side overcurrent protective devices”. There is also a clarification on the scope of the required coordination for 700.27 in the 2008 National Electrical Code® Handbook – “This coordination must be carried through each level of distribution that supplies power to the emergency system.” What’s different from the way we’ve designed these systems for years? Prior to 2005, selective coordination was only required for some elevator applications by Article 620. Until the 2005 NEC, a properly coordinated system was generally regarded as ensuring the timely operation of Page 1 Toggle Full Screen Close REV FWD overcurrent devices to assure safety and protection of equipment (using damage curves) while minimizing nuisance trips. We’ve tried to minimize nuisance trips as much as possible by ensuring that there was no overlap in coverage in the thermal region of the time-current curves, and by adjusting the instantaneous range for as little overlap as possible. However, some overlap almost always existed and was accepted. Most of us have heard of a nuisance trip or two in our careers, but probably not too many. To get two breakers to open simultaneously (or have only the upstream breaker open), a very low impedance fault would have to occur to supply a very high fault current. Low impedance faults almost always occur due to bus or cable wiring mistakes at the time of construction or during a repair – these faults are quickly identified and remedied. The vast majority of real world faults are higher impedance and generally do not cause multiple breakers to operate. It is a safe bet that the building you are in right now has breakers with overlap in the instantaneous range of their time-current curves, and that virtually all the buildings you have designed in your career do as well. However, now in order to comply with the NEC for Sections 700, 701 and 708, the engineer needs to be able to prove, using curves or other manufacturer’s data, that there is NO overlap in curves at the available fault current at that point in the system. Fuse vs. circuit breakers? Systems can, and are, being designed using either (or both) circuit breakers or fuses that selectively coordinate. In some cases fuses may more easily selectively coordinate than circuit breakers, however fuses still have inherent drawbacks that continue to make designing with circuit breakers the preferred method. These drawbacks include increased training of owners to safely replace fuses, requirement for spares and storage, single phasing, increased arc flash hazard and increased PPE requirements. Because circuit breaker design is by far more common, this paper will address system design using circuit breakers. Is it being enforced? There are several areas of the country that are currently enforcing selective coordination, and many more areas that are not – these areas can begin active enforcement at any time, and it could start with your project tomorrow. If you are in an area that has not yet begun enforcement but has adopted the requirement, remember that the Engineer and his firm may still be liable if someone is injured due to a selective coordination accident for the life of the building, even if the code inspector did not enforce the requirement. Applicable codes vary by location – be aware of the local requirements. Only areas that have adopted the 2005 or 2008 versions of the NEC will be affected by the changes discussed in this paper. There are also several municipalities, counties and states that have amended, or are in the process of amending, code requirements to modify or eliminate the NEC selective coordination requirements. Examples of proposed modifications include: • • • requiring selective coordination only where determined “practicable” by the Engineer not requiring selective coordination of time current curves below 0.1 seconds eliminating the ability of the inspector to deny a Certificate of Occupancy based on noncompliance at the time of construction This is a period of change and adjustment in the industry, so you should always consult the code enforcement officer or authority having jurisdiction in the project location to make sure you are following the correct standards. What if I already call for coordination studies? Coordination studies are performed after construction so that the actual equipment, fault current levels, conductor lengths and trip settings can be used to evaluate the system coordination. In the past these Page 2 Toggle Full Screen Close REV FWD studies have allowed for proper adjustment of the breakers to minimize nuisance trips and establish the base system settings. However if the study indicates that there are areas that do not selectively coordinate (which is almost assured if not designed properly), it is too late to fix easily. All the study can do is to confirm that the system was designed in a non-compliant fashion. In many, if not most, cases redesign and replacement of many system components (switchboards, panelboards, ATS, etc.) will be required to meet NEC requirements and allow you to get a Certificate of Occupancy. Can I require the manufacturer to provide selectively coordinated breakers in the project specifications? No, and for several important reasons. There’s no such thing as a selectively coordinated breaker, only two breakers that selectively coordinate at a given available fault current. In order to even evaluate if two breakers selectively coordinate, one must know the available fault current at each applicable point in the system. If the Engineer has provided the calculated available fault currents (not to be confused with AIC ratings) at each of the panels, it is possible to evaluate the sizes he has scheduled. Without these values, no evaluation can be made. If a breaker must increase in size to selectively coordinate (a very common and likely condition), a series of additional changes must occur that are outside the scope and ability of the contractor or manufacturer during the bidding period. • • • • • The new breaker may not fit in the specified panel type and the new panel may not fit in the space anticipated by the engineer. In some cases rooms may need to be enlarged. The wiring and conduit size must change due to the increased breaker size – the increased breaker size and the upsized conductor are design changes that must be approved by the Engineer. Other components that are not supplied by the manufacturer may also be required to change in size (automatic transfer switches, generators, etc.) – these changes and their possible impact on space requirements can not be accounted for during the bidding period. The increased conductor size requires recalculation of the available fault current, which in turn may require another increase in breaker size – only the Engineer can do these design calculations. In the majority of projects the bidding package drawings and specifications are never seen by the manufacturer. In most cases the contractor does the take-off and asks a distributor or manufacturer for a price on the bill of materials the contractor created. The Engineer can not delegate design responsibility to a contractor, distributor or manufacturer, especially during the bid period. In most states, sealed drawings require that the Licensed Engineer be in direct supervision of project designers and engineers that produced the contract documents. Page 3 Toggle Full Screen Close REV FWD NUTS & BOLTS How do I evaluate a system for compliance with NEC? Let’s take a look at a very simple system and evaluate it for compliance with 700.27. The riser above shows a 480V system with an automatic transfer switch (ATS) and a 35kW natural gas fueled generator. The main switchboard has a 2000A insulated case main circuit breaker, and has a 60A molded case circuit breaker feeding the 60A ATS. The ATS feeds a 100A main lug only panelboard with 20A branch circuit breakers that feed egress lights, exit signs and the fire alarm panel. The building has an occupancy that requires these emergency loads to meet the building code requirements, and the community has adopted the 2005 National Electrical Code. The Engineer has calculated the available fault current at the main switchboard to be 9,000A and the available fault current on the normal source at the emergency branch panelboard to be 900A. This is a typical design that many of us have done in the past (and may have out to bid right now). As shown, does this meet code? No. Let’s evaluate it and see what has to change. We have the essential first piece of information – the available fault currents computed by the Engineer (remember, the Engineer of record is the only person who can issue these values for design purposes). The first step is to evaluate the largest branch breaker in the emergency branch panel and the next supply side breaker (the 60A feeder in the main switchboard). You need to evaluate the largest breaker in the branch panel because that’s the worst case – it would be harder for the supply side breaker to coordinate with a 90A breaker than a 20A. Since a 20A branch is the largest in our example, we’ll compare the curves for that and the 60A feeder. Page 4 Toggle Full Screen Close REV FWD We always evaluate breakers in pairs for selective coordination, and only look at the curve to the left of the available fault current. Imagine taking scissors and cutting the right side of the paper off at the current available at the downstream breaker – if the curves on the left side of the available fault current do not overlap, the breakers selectively coordinate. The 20A (red) and 60A (orange) breaker curves shown above clear each other in the entire thermal range (curved part), however the instantaneous ranges begin to overlap at just under 600A. This makes sense, since a typical 60A molded case breaker will have an instantaneous pickup about 10 to 12 times its frame rating minus a +/- manufacturing tolerance (the width of the curve). Since we have 900A of available fault current in our example, we will need an upstream breaker that does not trip on instantaneous at that value – the first breaker with an instantaneous pickup (left edge of the vertical section) above 1000A is a 125A (see green curve below). The 125A breaker will now selectively coordinate with the 20A branch at an available fault current value of 900A. Page 5 Toggle Full Screen Close REV FWD A - Our first change is to replace the 60A feeder breaker with a 125A breaker (the red A refers to the designation on Page 4). In this case, a 125A breaker will physically fit without problem in our switchboard, but had this been a regular branch panelboard with a maximum breaker size of 100A, a larger panel would have had to be installed. The next breaker pair that must selectively coordinate is the new 125A breaker and the next supply side overcurrent device, the 2000A main breaker. Comparing the curves below (125A – green, 2000A – blue), we see that these two breakers do selectively coordinate at 9,000A of available fault current (no overlap to the left of the available fault current at the downstream device), so no additional changes are needed. Note that these two curves actually do not overlap at any current, so they would selectively coordinate in any situation where the available fault current didn’t exceed their AIC ratings. Page 6 Toggle Full Screen Close REV FWD B - There are now several things that must change due to increasing the size of that feeder breaker. The branch panel, a 100A, must now be increased in size to at least a 125A. Make sure there is space to mount this larger panelboard. C - The 60A ATS must also be increased in size so its rating is at least 125A. Remember to check for additional mounting space for the larger transfer switch. D - The conductor and conduit size between the feeder breaker and the ATS, and between the ATS and the branch panel must also change because of the increased size of the breaker. Now comes a fun part – you must recalculate the available fault current at the branch panel because the conductor got larger, then recheck the curves to make sure the 20A branch breaker still selectively coordinates with the 125A feeder at the new, larger available fault current. Sometimes they will, sometimes they won’t and you must upsize again. In our example they did coordinate so an additional increase is not needed. E - We have now modified the design to comply with code on the normal supply side. Now we must evaluate the emergency source side. On emergency source, the next supply side overcurrent device from the 20A branch is the 60A output circuit breaker at the generator. In most cases the Page 7 Toggle Full Screen Close REV FWD manufacturer of this breaker will be unknown, but for this exercise we’ll assume it is the same as the 60A curves above. Will this 60A breaker selectively coordinate with the 20A? It all depends on the available fault current, in this case the fault current delivered by the generator. Since we need to evaluate these breakers in the instantaneous range of operation, we need to know the fault current the generator can produce in the 1-6 cycle range. To find this we must know the sub-transient reactance (not transient or steady state) of the alternator on the generator. This per unit value, X’’d, is available from the generator manufacturers and varies a good bit between alternators and generators. Once you obtain the value of X’’d, you divide the rated output current of the generator by this value and you will have the sub-transient available fault current at the generator output – from this you can determine the available fault current at the branch panel. In our example (based on real values from an actual project) the generator provided 700A of fault current at the panel. The 60A output breaker curve overlaps the 20A at this value, so we must increase the size of the output breaker. The only problem is that the output breaker protects the alternator windings, so the only apparent alternative is… F - increase the size of the generator so that the output breaker can get larger. A larger generator has a larger fault current and a different X’’d, and in the real world project a 50kW generator with its larger output breaker finally did selectively coordinate with the 20A branches. Anything else that can go wrong in the process of meeting code for this example? Remember to check to see if there was enough natural gas pressure at the jobsite to increase from 35kW to 50kW! The example has now been modified to meet National Electrical Code requirements. This example was of a small project with a relatively small available fault current from the utility. If the design were of a more complex system with a distribution level on the load side of the ATS, and 50,000A of available fault current at the service entrance, and had the same emergency requirements (60A), another selective coordination issue may appear. A large normal source available fault current can cause the breakers to grow very quickly. If we had 5,000A at our example branch panel instead of 1,000A, the feeder breaker would have grown from 125A (won’t trip on 1,000A instantaneous) to a 600A (won’t trip on 5,000A). There are methods given of reducing these “growing” breakers later in this paper, but many breakers will still have to increase in size in systems with high available currents. If the output breaker of the generator is less than twice the size of the largest downstream breaker (a reasonable ratio in many cases to keep the curves from overlapping) it will probably not selectively coordinate. Even though the output breaker only has to coordinate in the instantaneous range based on its own available fault current producing ability (X’’d), it still has to selectively coordinate with the downstream breakers in the thermal curve area. If we have a 125A breaker downstream of the 60A output breaker and we get a 70A fault, the output breaker will trip before the downstream breaker and we lose selective coordination. As pointed out by this example, the evaluation and correction of this design to meet code is something that can only be reasonably done by the Engineer during the design phase. If this project were to bid with the uncorrected drawings, and the specifications were written to require the manufacturer (or study provider) to provide “selectively coordinated breakers”, one can see that it is just about impossible to comply. If the project were to be built as shown and the code enforcement officer asked for proof of compliance before a Certificate of Occupancy would be given, one can easily add up the extras and liquidated damages resulting from making the changes A - F above in the field vs. on the drawing board. If someone gives you assurances that their breakers selectively coordinate without having evaluated the entire design with you, for the sake of your firm’s name, insurance, and your license, make sure that you go through all the steps yourself before issuing drawings for bid. Page 8 Toggle Full Screen Close REV FWD MITIGATION What are some ways to design the system to meet code? The best way to design for selective coordination may be to change how we approach the design from the start. New ideas and methods will continue to appear as long as the requirements exist. There are many complex applications, such as hospitals, that will truly challenge the engineer, but there are also many smaller applications where mitigation is more easily achieved. Here are a few methods that may help mitigate some of the problems associated with selective coordination: Is selective coordination really needed? - Let’s look again at our example. Selective coordination was required because of the presence of components covered under Section 700. If I called for the installation of unit equipment to provide the minimum allowable egress illumination and exit signage, and my fire alarm panel had an integral emergency power supply (as required for listing), I could have bid the project as drawn with no requirement for selective coordination. Here’s why – NEC 700.12 states in part “Unit equipment in accordance with 700.12(F) shall satisfy the applicable requirements of this article.” For a simple installation such as our example, installing unit equipment satisfies the code requirements – I can then install the generator and transfer switch to feed any loads I wish, even additional egress lighting in excess of the bare minimum provided by the unit equipment. This approach will not be reasonable for large projects, but may be perfectly applicable to many smaller ones. Minimize the emergency system. - Carefully evaluate the loads on the emergency ATS. Have only the loads required by 700 and 701 (and 708 if applicable) on the emergency transfer switch. Optional loads may then be supplied by a second ATS. Smaller loads with smaller overcurrent devices are easier to selectively coordinate than larger ones. Use less levels of distribution. - Fewer levels are far simpler to coordinate. The fewest is achievable by feeding the ATS from a second main disconnect (one of the six allowable). That provides the smallest load with the smallest conductor running the longest distance which minimizes the available fault current to the emergency side and further facilitates selective coordination. Use “turned down” solid state circuit breakers. - Molded case circuit breakers are required to have instantaneous devices, and in the majority of devices this pick-up level is 10-12 times the breaker’s frame size. If you have a circumstance where you need a larger breaker for its higher instantaneous pick-up but really want a smaller breaker, consider adjustable solid state breakers. For example, 175A breaker will have an instantaneous curve where the leading edge (left side) picks up at about 900A. As an alternative you can take a 600A solid state breaker with a 0.3x long time setting (180A) and turn the instantaneous setting to maximum – the left edge is now at 5,000A. Use insulated case circuit breakers for high fault current applications. - You may find that fault currents are so high that coordinating the instantaneous band with molded case breakers is impractical. Using an insulated case breaker (available in both switchboard and switchgear versions) in many cases allows you to turn off the instantaneous range simplifying selective coordination. These are larger, higher end breakers and should be evaluated by the Engineer for practicality. Use “special” breakers. - There are some circuit breakers whose curves have shorter instantaneous “feet”, such as the Siemens NGB breaker. These make coordination easier than standard breakers, but they must be specifically called for by the Engineer. Page 9 Toggle Full Screen Close REV FWD Use transformation to reduce high available fault currents. - If you have a very high normal source available fault current it can make selective coordination very difficult. Inserting an isolation transformer or step down transformer will immediately limit the downstream available fault current to a more manageable level. There is, however, a catch to using transformers in any selective coordination application. The code required secondary overcurrent device for three phase transformers is almost always too small to selectively coordinate with any other breakers in that panel. For example, a 75kVA 480V transformer has a rated output of about 90A, an available fault current at 4.5% of about 2,000A, and a maximum secondary overcurrent device of 125A. Even if you use the actual primary available fault current to calculate the secondary fault current, you still can’t selectively coordinate with a typical 20A branch breaker. This is a perfect application for an adjustable solid state breaker for the secondary protection. What information and aids are available from manufacturers? There are aids available from all the manufacturers to assist the Engineer. Curves - Most manufacturers provide time-current curves for all their breakers. Siemens provides their curves in electronic form in its EasyTCC software available for free download on its website – http://www2.sea.siemens.com/support/consulting-engineers (don’t forget the www2). This software allows the user to overlay curves and adjust all settings for all Siemens circuit breakers. The example curves in this paper were created using EasyTCC. Charts - Charts are available which list, in varying styles, breakers that selectively coordinate with other breakers at specific available fault current levels. An advantage of the charts is that they are often more accurate than curve comparisons as they are based on more specific test data derived for selective coordination. If there is disagreement between overlaid curves and charts, the chart data should be used. These charts do not always list all breakers from the manufacturer. Siemens breaker coordination charts are available for download on its website and are included on the Siemens Design Assistant Disc. Tools - Siemens has developed a Selective Coordination Tool (part of the Available Fault Current Tool) to assist in designing code compliant systems. This tool provides very conservative (and more likely to be competitively biddable) sizing for design. It is available for free download on Siemens’ website and is included on the Siemens Design Assistant Disc. What else should I be aware of as the Engineer? The rules changed slightly from the 2005 to the 2008 NEC regarding overcurrent devices in series. It was observed, and changed in 2008, that devices in series of the same ampere rating and the primary and secondary overcurrent devices for transformer protection may not themselves selectively coordinate, but do not affect the selective coordination of the system (the scope of the outage is not increased by the upstream device or both devices operating). However, if your project is still governed by 2005 code make sure that the AHJ will accept the variance if you use the 2008 rules. Arc flash hazard is also a much discussed topic recently, and it should be. There are people injured each day from arc flash incidents, including contractors, building occupants, and even consulting engineers. Some important variables that determine arc flash energy are the voltage (can’t change that), the current (can’t do much about that) and the duration of the flash (this we have some control over). In reducing arc flash energy the object is to drive the overcurrent devices feeding the arc fault into their instantaneous operation as soon as possible to more quickly extinguish the arc. High available fault currents are actually better for this application because overcurrent devices can be driven into their instantaneous ranges and clear more quickly. Even though it sounds backwards, low available fault currents will actually increase the arc flash energies in many circumstances because overcurrent devices may stay in the thermal range of operation allowing the arc to stay “lit” longer. Ironically, the same attributes that make thermal magnetic breakers harder to apply in selective coordination applications can make them more suited for arc flash hazard reduction. Accepted methods of reducing arc flash energy include Page 10 Toggle Full Screen Close REV FWD lowering the instantaneous pick-up of adjustable breakers (moving the instantaneous band to the left) and having overlap in the instantaneous ranges of multiple breakers. Contrast these goals to the goals of selective coordination design – it mandates that there be no overlap in operation, and to do that the engineer will deliberately keep the instantaneous settings as high as possible and limit the available fault current in the system to facilitate coordination. Once again the Engineer must decide between the two extremes of design – better coordination (higher pickup values, longer clearing times, less nuisance trips) or greater safety (lower pickup values, shorter clearing times, more nuisance trips). In the case of selective coordination, however, there is now a code requirement to bias the design in favor of coordination. What’s the conclusion? Selective coordination is a requirement in most areas of the country for emergency systems, and barring legislation that modifies or eliminates it, will be a requirement in the future. The only person who can plan and design a system to comply with this requirement is the Engineer – responsibility for selecting components can not be passed on to the contractor or supplier. There is technical help available to the Engineer and designer. Use these early days of enforcement and compliance to change your design approach and meet the required codes – do not let your firm be the first to be exposed to liability when a code that has been in effect for the past several years begins to be enforced in your area tomorrow morning. National Electrical Code® and NEC® are registered trademarks of the National Fire Protection Association. © 2008 by Siemens Energy & Automation Page 11 Toggle Full Screen Close REV FWD