Article title: ‘Protection coordination for distribution system in the presence of distributed generation’ Author names: 1. Muhammad YOUSAF (Corresponding Author): Full Time M.Sc. Research Scholar, Electrical Engineering Department, University of Engineering and Technology Taxila, Pakistan. Email: engryousaf47@yahoo.com , Phone # +923144412003. 2. Tahir MAHMOOD: Associate Professor, Electrical Engineering Department, University of Engineering and Technology Taxila, Pakistan. Protection coordination for distribution system in the presence of distributed generation Muhammad YOUSAF and Tahir MAHMOOD Abstract: This paper proposes an effective strategy to overcome the impacts on coordination among the protection devices due to distributed generators (DGs) integration. Increased fault current magnitude and changes in power flow directions are the major impacts imposed by DGs on a typical distribution system. The recloser-fuse coordination is much influenced upon the integration of DGs. The proposed approach presents the rehabilitation of recloser-fuse coordination for post DG integration effects using the directional properties of a recloser. The simulation results show that coordination among protection devices can be regained using fast operation of the recloser to design a fuse saving scheme in the scenario of temporary faults occurrence. The designed scheme also works satisfactorily for the isolation of permanent faulted section of the feeder. This technique is verified by simulation results performed on a real 11 KV radial distribution feeder for different faults location and DG sizes. 1 Keywords: Protection Coordination, Distribution Generation (DG), Directional Recloser, Relays, Fuses, Distribution Systems. 1. Introduction Typical distribution systems were designed to operate radial configuration in which power flows from the source towards the customers connected. So the protection coordination of the radial system is very simple in nature. The distribution system contains the protection devices e.g. fuse, recloser, relays and circuit breaker. These protective devices are coordinated in such a way to interrupt the unidirectional flow of the fault current from the source end towards the fault point [1, 2]. However keeping in view the global concerns of the environment and to meet the load growth, the distribution power planners has paid a great attention toward the distributed generation [3, 4]. Upon integration the distributed generation with distribution system, the configuration for power flow for a conventional network has been changed from unidirectional to multidirectional system. However, However, it is very important to know the margin required for the preservation of the protection coordination when a DG is being integrated to a power system. The distributed system protection is to be reviewed after the integration of DGs [2], [5], [6, 7]. In [8], researchers tried to solve miscoordination problem caused by DGs integration by formulating it a mixed integer programming problem for a directional overcurrent relays. A mathematical problem was first developed and differential evolution algorithm was used to solve the mis-coordination problem. But differential evolution method contains much complication to be used for a large distribution feeder. It was also suggested by researcher that after integrating each distribution unit, the existing protection coordination must be checked in order to identify the impacts of adding DGs to the power system. In [9],the authors used the new relay setting technique for the changed power generation and distribution in the power system to solve mis-coordination problem. In [10], mis-coordination problem was resolved 2 by dividing the whole power system into different zones and installing a circuit breaker for each zone. But this approach faced the problems of limitation for the case when very large distribution feeder was used as a test system. In [11], researchers performed research on reducing the contribution of DGs to the short circuit current level by using the concept of fault current limiter (FCL) but it resulted in some disadvantages such as the power dissipation across the fault current limiter as it is continuously being connected to the power system. This power loss was much reduced by using superconducting fault current limiter (SFCL) in by the authors since SFCL has zero resistance during normal operation of the power system and its resistance goes on increasing due to the increased fault current. The major disadvantage of using SFCL is that they are very costly and are being used by some developed countries[12, 13]. Since in power distribution system, about 75-80 % faults are temporary in nature. These faults can be categorized as self-clearing faults [14]. Directional recloser can be used for the clearance of upstream and downstream momentary faults in coordination with other protective devices of a distribution system. The proposed approach will considerably reduce the duration of sustained interruptions. The proposed scheme is used to establish the proper coordination among fuses and recloser to eradicate the impacts of DGs integration on protection coordination. The designed scheme considers all the parameters of real 11 KV distribution feeders. 2. Algorithm for the proposed approach The proposed approach has been implemented on a particular radial distribution feeder having DGs and different protection components. The procedural steps followed for the proposed algorithm are shown in Figure 1. When a DG is being installed at a distribution feeder, then after its integration the conventional protection scheme of the hosting feeder is checked to assure that whether DG has changed the protection 3 coordination of the feeder. If there were no change in protection coordination there is no need of reconstruction of the feeder protection coordination. But it may be a very rare case when the traditional coordination is retained. Mostly, it is lost due to fault current contribution by DGs [15]. I. Calculate the Ifmin and Ifmax for the hosted feeder. In order to calculate Ifmin, the impact of DGs is neglected and calculations are performed without DG integration whereas Ifmax is calculated after integration of DGs. II. The Ifmin and Ifmax will give an idea about the current variation for the penetration of DGs into distribution system. III. The characteristics curves of all the coordinated protection devices are plotted. IV. When a DG is integrated downstream the recloser and there is fault downstream the recloser, the Irecloser will be less as compared to the Ifuse on faulted section. V. The next step is to reexamine the fast operation of the recloser in order to ensure the operation of the recloser before the melting of fuse for fuse saving scheme. VI. The recloser fast operation curve will be shifted downward by a factor of ratio of Irecloser and Ifuse. It will ensure the proper coordination is being established between fuse and recloser. The new setting obtained from the newly constructed characteristics curve is implemented on the recloser. Figure 1: The flow diagram of the proposed approach. VII. VIII. Size of the fuses can also be updated to establish proper coordination among protection devices. Revise recloser and fuses Time-Current Curves (TCC) curves according to changed parameters for coordination for different protection devices. IX. Then fuse-Relay coordination is checked for hosting and neighboring feeder and confirmation of its preservation is to be ensured. 4 X. The algorithm can be repeated to regain the proper coordination among the different protection devices. 3. Case study In order to perform a comprehensive case study on the effectiveness of designed scheme on the real distribution system, data of a practical 11 KV distribution feeder was used. This distribution feeder named as Panian radial distribution feeder has about 168 numbers of nodes starting from 132 KV Haripur grid station. It has a total length of about 98.9 km and a total load of 8425 KVA whereas 4625 KVA load is connected upstream the recloser while the 3800 is downstream the recloser. All protection devices setting for the pickup currents are usually taken as 1.25 the full load current. In order to establish a proper coordination among the protection devices, the difference among the primary and backup protection devices must always be greater than 200-300 ms. The one line diagram constructed in MS VISIO is shown in Figure 2 while Figure 3 represents the one line diagram in Electrical Transient Analysis Program (ETAP). Figure 2: One line diagram of 11 KV distribution feeder (case study) The recloser is located at the mid feeder because of the integration of two DGs will not cause the momentary interruption for a temporary fault occurrence for the case when recloser is at the start of the feeder. Keeping in view the complexity of this lengthy distribution feeder, the feeder under case study has been reduced from 168 nodes to only 38 nodes by summing the loads on respective laterals and associated sub laterals to the corresponding node. Practically, it was found that reduction of case study feeder from complex shape to a simple one did not affected the overall results of load flow and protection and protection coordination [3, 16]. 5 3.1. All possible zones of protection A zone of power system protection is the part of the circuit that is disconnected only when an electrical fault occurs in that part of the power system preserving the continuity of supply to the healthy sections. The radial distribution feeder has been divided into 40 zone of protection as shown in table 1. Each zone has a primary protection as well as backup protection device. Each protection zone is named after the name of the protection device being installed. To make easy to understand, each protection devices was named to its corresponding node number and each bus bar name is also named after the node number. In view of the fact that protection of 11 KV distribution feeder was designed to operate in conventional protection coordination order during the faulty conditions. In the absence of DGs, the protection devices have to control the flow of fault current from grid source point towards the fault point. So a very limited number of protection devices have to operate for the fault isolation that may be fuse, reclosers and feeder relay. Since recloser is installed to clear the temporary fault. So it must be properly coordinated with fuses. However in case of multiple numbers of DGs integration, each reclose and fuse will experience different level of fault as compared to DGs less environment for which they are being installed and coordinated. The cause for mis-coordination problem among protective devices is explained for mid feeder recloser in which a DG1 is connected downstream and another DG2 is connected upstream the recloser. In this distribution feeder, each zone contains a lateral fuse which is coordinated with recloser and can be operate according to fuse saving scheme for temporary fault occurrence. All the parameters data about the size of conductor (DOG conductor denoted by ‘D’ in Figure 2), Transmission line parameters and DGs sizes and their location is given in [2]. Figure 3: One line diagram of the radial 11 KV feeder constructed in ETAP 6 Table 1: All possible protection zones with primary and backup protection devices 4. DGs and protection coordination In order to reduce the real power loss and to make the nodes voltage within acceptable limit, two DGs have been inserted at two different nodes. DG1 having the size of about 3.722 MVA was connected to node number 30 while DG2 with size of 2.28 MVA was connected to node number 14 [3]. After the integration of DGs with distribution feeder, the power loss was much reduced from 605.5KW to 39.7 KW. And at the same time, voltage profile was much improved with 16% reduction in total voltage drop[3]. But DGs integration caused a very serious problem to protection coordination for the distribution feeder. When DGs are placed to the circuit, the objective is to isolate the faulted point fed by a number of sources The simulation results conducted shows a miscoordination between the protection devices. The sequence of operation of protection devices is listed below in table 2 in the presence of DGs for a few zones of protection. Table 2: Sequence of operation of the devices in the presence of DGs Simulation results show that in some cases the fuse was blown out before the operation of recloser which is false tripping sequence as recloser setting was designed to operate earlier than fuse (fuse saving scheme) in order to remove the temporary faults with de-energizing the faulted section and again energizing. In case of a line to ground (L-G) fault in fuse 1 zone, fuse 1 was tripped before the recloser. The reason behind this false tripping can be explained with characteristics equations and TCC of the protection devices. Now, the fault current for a fault in distribution system is contributed by three fault current sources that are from main distribution feeder, DG1 and DG2. In order to interrupt the fault current from main 7 distribution feeder, the correct tripping device is the main feeder relay which initiates the operation of the associated M.V circuit breaker. If the fault occurs in relay zone, the DG1 contribution toward the fault current (If) can be terminated by DG1 protection system while DG2 contribution can be ended up by recloser operation. If the fault is in the recloser zone, the main distribution station and DG1 contribution can be controlled by recloser tripping while that of DG2 with DG2 protection system. 5. Renovation of protection coordination When the DGs are integrated, it starts to contribute toward fault current. So for the same fault at the same location, fault current magnitude increases causing a mis-coordination among the traditional protection coordination. The table 2 shows that in most of the cases, a miscoordination occurs among the protection devices. The results indicate that the original system loses selectivity after the DGs insertion. The reason behind this is explained in next sections. 5.1.Mathematical Modeling The recloser fault current (Irecloser) is always less than the corresponding laterals fuse current (Ifuse) because it follows the two cases: a) If the fault is downstream the recloser , then Ifuse = Irecloser+ IDG1 (1) Where Irecloser= Igrid+IDG2 b) If the fault is upstream the recloser, then Ifuse = Irecloser+ IDG2+Igrid (2) These equations show that fault current is always higher for a fuse in the presence of DGs so fuse is operated before the recloser tripping causing a false tripping. Since recloser follows the following equation [17, 18]: π‘ππ πΌ = ππ·π π΄ π πΌ −1 πΌππππ −π’π +π΅ (3) 8 When the πΌππππππ ππ πΌππ’π π factor is multiplied with Time Dial Setting (TDS) in equation (3), the characteristic curve of the recloser will shift down resulting in new coordination among fuse and recloser. 5.2. Protection Coordination Constraints For typical over-current protection coordination, the following constraints to be meet for proper coordination [18-20]. i. The first constraint to be met is the equipment overload constraint. Ipickup ≤ Ispec (4) This constraint satisfies the condition for each protection device of not being overloaded under any circumstances. So pickup value of each protection devices must be less than the maximum value for which it is designed. In this way, it will be able to perform its function properly. ii. There should be difference between operating time of upstream and downstream protection devices in order to satisfy specified time margin. Tup (If) - Tdown (If) ≥ tmargin (5) Where Tup (If) shows the operating time of upstream devices under faulty condition and Tdown (If) indicates the operating time of downstream devices under faulty condition and difference of these time constrains should some tome margin which is usually greater than 100 ms. iii. The recloser operating time in the fast mode must always be less than the minimum melting time (MMT) for the respective fuse in order to design fuse saving scheme. TRf (IR)-MMTf (IFuse) ≤ 0 (6) Whereas difference between recloser fast operating time TRf (IR) and minimum melting time of the fuse must be negative. It will cause the de-energizing the fault by fast operation of recloser and try to selfclear it. This will save interruption caused by fuse melting in case of temporary fault occurrence. 9 5.3. Plotting of TCC curves The Time Current Curve (TCC) represents the sequence and time of operation of the protection devices. The fuse TCC curve consists of two curves. The lower curve is Minimum Melting Time (MMT) while the upper is called Total Clearing Time (TCT). The TCC curve for the cases mentioned in table 2 is shown below in Figure 4. Figure 4: TCC curve of protection devices in the presence of DGs For the perfect coordination among the fuse and recloser, the recloser fast operation TCC curve should be lower than the respective fuse MMT curve while recloser delayed operation curve must be laid above the fuse TCT curve. This will result in recloser tripping in the fast mode of operation before the fuse start to melt giving momentary fault a possibility of self-clearing[15, 21]. However, in case of permanent fault occurrence, fuse melts to operate before the recloser trips in slow mode of operation. The relays TCC curves of main feeder relay and DGs protection relays lies above the all the fuses and reclosers curves giving a back-up protection if primary protection devices fail in successful operation. 5.4. Designing of protection coordination scheme Since after the addition of DGs, power flow is changed from unidirectional to multidirectional; the requirement is to trip the flow of multidirectional fault current. In this scenario, directional protection scheme become the suitable choice to resolve the selectivity problem of the distribution system. Since the fuses are located at the beginning of each lateral in which the flow of fault current is unidirectional, so fuse do not need any directional property. Since fuses do not posses directional nature, if fuse are to be designed for directional protection, they are to be replaced by recloser. The fault current through the feeder relay is still unidirectional, so there is no need of directional property of this relay. Since recloser is subjected to multidirectional fault current, so it must possess the 10 directional nature. In order to possess the directional nature, recloser must have two setting. One setting is to be designed for the downstream fault location and other is designed for upstream fault location. In the above designed scenario, the total load connected downstream the recloser is 3800 KVA so the pickup current for this downstream setting is 249 A while for upstream setting of recloser, the pickup current setting is 303 A. Since DG2 is located upstream the recloser at node 14, so its protection relay should have a setting slower than the downstream setting of recloser. This will result in tripping of recloser for a fault at its zone before DG2 protection operates. This will resolve the selectivity problem recloser and DG2 protection system. For DG1 which is located at node 30, its protection setting should be slower than the upstream setting of the recloser so that it results in recloser tripping for a fault in the feeder relay zone. In order to coordinate fuses on upstream side of the recloser, they should operate faster than recloser delayed operation in order to isolate the fault zone for in case of a permanent fault. The fuse on the lateral downstream the recloser must operate before the operation of DG1 protection system. If the generator is to be connected to the sub lateral of distribution feeder, then lateral fuse can be replaced with a directional recloser that allows interruption of fault current in both cases when the fault is located upstream and downstream of the lateral recloser. After isolation of the faulted section, recloser initiates the reclosing process for restoration of supply to healthy section. Using the above mentioned scheme, protection coordination was restored among the protection devices. 5.5. Implementation of the proposed scheme If there is a fault at relay zone, the fault current contribution from the distribution system was interrupted by the feeder relay. The fault current from DG1 will be interrupted by the recloser and DG1 protection 11 will be its backup protection. The fault current contribution from DG2 will be interrupted from by DG2 protection system. In these circumstances, all the tripping decisions are correct. Now if the fault location is downstream the recloser (recloser zone), then fault current coming from distribution system and DG2 is interrupted by recloser and feeder relay and DG2 protection system will works on its backup. The contribution of DG1 towards fault current will be terminated by DG1 protection system. The Figure 5 shows the fault current level through recloser and fuse for a L-G fault on each node. Figure 5: Fault Current Calculation for Recloser and Fuse for an L-G Fault on each node After the penetration of DGs in distribution feeder, the fault current level and direction of fault current flow changes for both recloser and fuses. So the TCC curves of recloser and relays should be revised and fuses size should be updated. The multiplication of lowest value of IR/IF with recloser curve will lower down the whole curve and protection coordination will be checked again. If the fault location is in fuse zone for example Fuse 20, then fault current contribution from all sources will be interrupted by recloser opening and DG1 protection relay. If the fault was temporary, then de-energizing and the energizing the fault will result in fault removal. However if the fault still persist after the recloser opening in fast mode of operation, then this permanent fault can also be removed by the associated fusing protection device i.e. fuse 20. If this operation becomes unsuccessful in removal of fault, then recloser tripping in slow mode of operation will works as its backup protection. And protection system of DG1 will also works as the backup protection device. 6. Impact of DGs size on protection coordination To illustrate the effect of DG size on protection coordination, the above proposed approach has been examined for different sizes of the DG connected to the distribution system. As the fault current 12 contribution increases with the increase in DG size, so the time of operation of different protection devices decreases with increase in DG size [22, 23]. The simulation for fault current contribution of different sources and their effect on protection coordination can be depicted from the table 3. The simulations are carried out for a line to ground fault on the node 20 downstream the recloser. The fault current contribution of each source and operating time of each protection device is listed in table 3. Table 3: Fault current contribution and time of operation for a fault downstream the reclose It is concluded from the results that as the rating of DGs increases, their contribution towards fault current increases while that of distribution substation (DS) decreases at the same time. The simulation results also depict that operating time of main feeder relay is always greater than recloser and DG2 relay. This will result in recloser lockout operation for a recloser downstream fault before tripping of feeder relay’s circuit breaker CB1. DG1 relay is required to operate before recloser delayed operation so that before locking out the recloser; fault is completely de-energized in order to give it a chance of selfclearing. These results prove that protection coordination among these devices is survived at the increased DGs size and multiple DGs integration for a fault downstream the recloser. The Figure 6 is the graphical representation of the fault current contribution by each source while Figure 7 presents the graphical picture of the time of operation of different protection devices with variation in DGs size. Figure 6: Fault current contribution for a L-G fault downstream the reclose at node 20 Figure 7: Time of operation for different Protection Devices with different DGs Sizes with an L-G fault at node 20 The same analysis can be performed for a fault upstream the main recloser. Now an L-G fault is located in feeder relay zone upstream the recloser at node 17. The results of fault current contribution from each 13 source and operating time of each device is shown in under given table 4 and results are graphically represented in Figure 8 and Figure 9. Table 4: Fault current contribution and time of operation for a fault upstream the reclose Figure 8: Fault current contribution for a fault upstream the reclose at node 17 Figure 9: Time of operation for different Protection Devices with different DGs Sizes with an L-G fault at node 17 These results depict that temporary fault eradication needs tripping of all the fault current sources so that contribution towards the fault current is terminated. This will result in temporary fault removal. But a permanent fault needs the lockout operation of recloser along with isolation of other fault current sources. Simulation results for faults other than L-G shows that this approach works properly for any type of fault occurrence. However, the protection coordination is needed to be checked after each insertion of new DG or changing in the size of any existing DG. The selectivity problem can be resolved using the above proposed curve fitting approach. 7. Conclusion The paper illustrates the impacts of distributed generation integration on the protection coordination for radial distribution networks. The proposed approach for restoration of protection coordination mainly focuses on temporary fault removal without melting the fuse. It has been observed from simulation results that the selectivity problem of the protection devices can be addressed using the curve fitting technique. The multiple DGs integration with distribution feeder needs the utilization of directional property of the recloser along with updating the fuse sizes and relays setting. The methodology is validated for a real radial distribution feeder. The simulation results verify the proper functioning of this technique for different fault location and DGs sizes. Thus proper coordination among different 14 protection devices can be restored to eradicate the impacts of post DG integration on distribution network protection. 8. Reference Zamani A, Sidhu T, Yazdani A, editors. A strategy for protection coordination in radial distribution networks with distributed generators. Power and Energy Society General Meeting, 2010 IEEE; 2010: IEEE. pp. 1-8. [2] Conti S. Analysis of distribution network protection issues in presence of dispersed generation. Electric Power Systems Research. 2009; 79: 49-56. [3] Khan H, Choudhry MA. Implementation of Distributed Generation (IDG) algorithm for performance enhancement of distribution feeder under extreme load growth. International Journal of Electrical Power & Energy Systems. 2010; 32: 985-997. [4] Bayod-Rújula AA. Future development of the electricity systems with distributed generation. Energy. 2009; 34: 377-383. [5] Zayandehroodi H, Mohamed A, Shareef H, Mohammadjafari M. Impact of distributed generations on power system protection performance. International Journal of the Physical Sciences. 2011; 6: 3873-3881. [6] Kamel A, Alaam M, Azmy AM, Abdelaziz A. PROTECTION COORDINATION OF DISTRIBUTION SYSTEMS EQUIPPED WITH DISTRIBUTED GENERATIONS. [7] Nojavan M, Seyedi H, Mahari A, Zare K. Optimization of Fuse-Recloser Coordination and Dispersed Generation Capacity in Distribution Systems. Majlesi Journal of Electrical Engineering. 2014; 8: 15-24. [8] Yang H, Wen F, Ledwich G. Optimal coordination of overcurrent relays in distribution systems with distributed generators based on differential evolution algorithm. International Transactions on Electrical Energy Systems. 2013; 23: 1-12. [9] Abdelaziz AY, Talaat H, Nosseir A, Hajjar AA. An adaptive protection scheme for optimal coordination of overcurrent relays. Electric Power Systems Research. 2002; 61: 1-9. [10] Brahma SM, Girgis AA. Development of adaptive protection scheme for distribution systems with high penetration of distributed generation. Power Delivery, IEEE Transactions on. 2004; 19: 56-63. [11] Aslinezhad M, Sadeghzadeh S, Olamaei J, editors. Over Current Relays Protective Coordination in Distribution Systems in Presence of Distributed Generation. Int; 2011. pp. 40-46. [12] Lim S-H, Kim J-S, Kim J-C. Analysis on protection coordination of hybrid SFCL with protective devices in a power distribution system. Applied Superconductivity, IEEE Transactions on. 2011; 21: 2170-2173. [13] Kim M-H, Lim S-H, Kim J-C. Improvement of recloser-fuse operations and coordination in a power distribution system with SFCL. Applied Superconductivity, IEEE Transactions on. 2011; 21: 2209-2212. [14] Jamil M, Sharma SK, Singh R. Fault detection and classification in electrical power transmission system using artificial neural network. SpringerPlus. 2015; 4: 1-13. [15] Naiem A, Hegazy Y, Abdelaziz A, Elsharkawy M. A classification technique for recloser-fuse coordination in distribution systems with distributed generation. Power Delivery, IEEE Transactions on. 2012; 27: 176-185. [16] Choudhry MA, Khan H. Power loss reduction in radial distribution system with multiple distributed energy resources through efficient islanding detection. Energy. 2010; 35: 4843-4861. [1] 15 Chaitusaney S, Yokoyama A, editors. Impact of protection coordination on sizes of several distributed generation sources. Power Engineering Conference, 2005 IPEC 2005 The 7th International; 2005: IEEE. pp. 669-674. [18] Martínez-Velasco JA, Martín-Arnedo J, Castro-Aranda F. MODELING PROTECTIVE DEVICES FOR DISTRIBUTION SYSTEMS WITH DISTRIBUTED GENERATION USING AN EMTP-TYPE TOOL REPRESENTACIÓN EN EMTP DE DISPOSITIVOS DE PROTECCIÓN DE REDES DE DISTRIBUCIÓN CON GENERACIÓN DISTRIBUIDA. Ingeniare Revista chilena de ingeniería. 2010; 18: 258-273. [19] Saksornchai T, Eua-arporn B. Protection System Adjustment for High Penetration of Distributed Generation. [20] Chaitusaney S, Yokoyama A. Prevention of reliability degradation from recloser–fuse miscoordination due to distributed generation. Power Delivery, IEEE Transactions on. 2008; 23: 25452554. [21] Hussain B, Sharkh S, Hussain S, Abusara M. An adaptive relaying scheme for fuse saving in distribution networks with distributed generation. Power Delivery, IEEE Transactions on. 2013; 28: 669-677. [22] Sadeh J, Bashir M, Kamyab E, editors. Effect of distributed generation capacity on the coordination of protection system of distribution network. Transmission and Distribution Conference and Exposition: Latin America (T&D-LA), 2010 IEEE/PES; 2010: IEEE. pp. 110-115. [23] Brahma SM, Girgis A. Development of adaptive protection scheme for distribution systems with high penetration of distributed generation. Power Delivery, IEEE Transactions on. 2004; 19: 56-63. [17] 16 Tables: Protection Zone Primary Protection Devices Feeder Relay Zone Feeder Relay Recloser Zone Recloser Fuse 1 Zone Backup Protection Device Incoming Feeder Protection Protection Zone Primary Protection Device Backup Protection Device Fuse 19 Zone Fuse 19 Feeder Relay Feeder Relay Fuse 20 Zone Fuse 20 Recloser, Relay Fuse 1 Feeder Relay Fuse 21 Zone Fuse 21 Recloser, Relay Fuse 2 Zone Fuse 2 Feeder Relay Fuse 22 Zone Fuse 22 Recloser, Relay Fuse 3 Zone Fuse 3 Feeder Relay Fuse 23 Zone Fuse 23 Recloser, Relay Fuse 4 Zone Fuse 4 Feeder Relay Fuse 24 Zone Fuse 24 Recloser, Relay Fuse 5 Zone Fuse 5 Feeder Relay Fuse 25 Zone Fuse 25 Recloser, Relay Fuse 6 Zone Fuse 6 Feeder Relay Fuse 26 Zone Fuse 26 Recloser, Relay Fuse 7 Zone Fuse 7 Feeder Relay Fuse 27 Zone Fuse 27 Recloser, Relay Fuse 8 Zone Fuse 8 Feeder Relay Fuse 28 Zone Fuse 28 Recloser, Relay Fuse 9 Zone Fuse 9 Feeder Relay Fuse 29 Zone Fuse 29 Recloser, Relay Fuse 10 Zone Fuse 10 Feeder Relay Fuse 30 Zone Fuse 30 Recloser, Relay Fuse 11 Zone Fuse 11 Feeder Relay Fuse 31Zone Fuse 31 Recloser, Relay Fuse 12 Zone Fuse 12 Feeder Relay Fuse 32 Zone Fuse 32 Recloser, Relay Fuse 13 Zone Fuse 13 Feeder Relay Fuse 33 Zone Fuse 33 Recloser, Relay Fuse 14 Zone Fuse 14 Feeder Relay Fuse 34 Zone Fuse 34 Recloser, Relay Fuse 15 Zone Fuse 15 Feeder Relay Fuse 35 Zone Fuse 35 Recloser, Relay Fuse 16 Zone Fuse 16 Feeder Relay Fuse 36 Zone Fuse 36 Recloser, Relay Fuse 17 Zone Fuse 17 Feeder Relay Fuse 37 Zone Fuse 37 Recloser, Relay Fuse 18 Zone Fuse 18 Feeder Relay Fuse 38 Zone Fuse 38 Recloser, Relay Table 1: All possible protection zones with primary and backup protection devices 17 Faulted Zone Fault Type Fuse 1 Zone Fuse 10 Zone Fuse 20 Zone Fuse 30 Zone Fuse 38 Zone Status of Power Sources Sequence of Operation of Protection Devices Grid DG1 DG2 1st 2nd 3rd 4th 5th L-G ON ON ON Fuse 1 Recloser Feeder Relay Relay DG2 Relay DG1 L-G ON ON ON Recloser Fuse 1 Relay DG2 Feeder Relay Relay DG1 L-G ON ON ON Fuse 20 Recloser Relay DG2 Relay DG1 L-G ON ON ON Fuse 30 Recloser Relay DG1 Relay DG2 L-G ON ON ON Recloser Fuse 38 Relay DG1 Relay DG2 Feeder Relay Feeder Relay Feeder Relay Table 2: Sequence of operation of the devices in the presence of DGs DG Size (MVA) Fault Current Contribution (A) DG 1 DG 2 DS DG1 DG2 2 3 4 5 6 1 2 3 4 5 270 201 167 145 133 871 896 983 1060 1114 603 899 1120 1301 1450 Operating Time of various protection devices (Seconds) Feede r Relay 1.691 1.745 1.830 1.925 2.024 Recloser Fast Delay 0.091 0.088 0.085 0.084 0.083 1.655 1.631 1.567 1.518 1.479 DG1 Relay DG2 Relay 1.435 1.370 1.097 0.937 0.833 6.209 3.247 2.206 1.725 1.547 Table 3: Fault current contribution and time of operation for a fault downstream the recloser DG Size (MVA) Fault Current Contribution (A) DG1 DG2 DS DG1 DG2 2 3 4 5 6 1 2 3 4 5 337 261 222 197 178 710 746 791 836 880 751 1170 1490 1760 1990 Operating Time of various protection devices (Seconds) Feeder Relay 0.836 0.851 0.882 0.919 0.957 Recloser Fast Delay 0.091 0.073 0.067 0.064 0.062 3.143 2.087 1.713 1.522 1.407 DG1 Relay DG2 Relay 3.207 2.278 1.821 1.654 1.481 2.587 1.175 0.797 0.618 0.514 Table 4: Fault current contribution and time of operation for a fault upstream the recloser 18 Start Figures: Sectionalize the whole distribution Feeder Plot TCC Curves of Reclosers and Fuses and Relays Determine Initial and changed Parameters due to DGs Integration Is Recloser-Fuse Coordination is lost due to DG integration? NO Analysis of the Coordination between Protection Devices Use the Fast and delayed Characteristics Curve of Recloser Determine Fuse (IF) and Recloser (IR) Fault Current Determine the factor IR/IF Modify the Recloser Fast and Delayed Curve by factor IR/IF andrecloser Fault Current Update Fuses Size NO Is Fuse-Relay Coordination is lost in the Feeder? YES Capacity of DGs to Suitable Value to meet all Constraints Stop Figure 1: shows the flow diagram of the proposed approach. 19 Figure 2: One line diagram of an 11 KV distribution feeder (case study) Figure 3: One line diagram of the radial 11 KV feeder constructed in ETAP 20 Figure 4: TCC curve of protection devices in the presence of DGs 6 Recloser 5 Fuse Current (KA) 4 IR/IF 3 Fault Current without DGs 2 1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Node Figure 5: Fault Current Calculation for Recloser and Fuse for an L-G Fault on each node 21 1600 Current Contribution by each Source (A) 1400 1200 1000 800 DS DG1 600 DG2 400 200 0 1 2 3 4 5 DGs Size (MVA) Figure 6: Fault current contribution for a L-G fault downstream the reclose at node 20 7 6 Feeder Relay 5 Time (Sec) Recloser (Fast) 4 Recloser (Delay) 3 DG1 Relay 2 DG2 Relay 1 0 1 2 3 4 5 DG Size (MVA) Figure 7: Time of operation for different Protection Devices with different DGs Sizes with an L-G fault at node 20 22 Current Contribution by each Source (A) 2500 2000 1500 DS DG1 1000 DG2 500 0 1 2 3 4 5 DGs Size (MVA) Figure 8: Fault current contribution for a fault upstream the reclose at node 17 3.5 3 2.5 Time (Sec) Feeder Relay 2 Recloser (Fast) Recloser (Delayed) 1.5 DG1 Relay 1 DG2 Relay 0.5 0 1 2 3 4 5 DG Size (MVA) Figure 9: Time of operation for different Protection Devices with different DGs Sizes with an L-G fault at node 17 23