Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 Table of Contents 1. INTRODUCTION .............................................................................................................. 3 2. ATC METHODOLOGY………...………………………………………………………..3 3. RESPONSIBILITY……………………………………………………………………….3 4. REFERENCES……………………………………………………………………………3 5. INTERVALS AND UPDATE FREQUENCY……………………………………………3 6. DETERMINATION OF TTC……………………………………………………………..4 7. FIRM ATC CALCUATION METHODOLOGY………………………………………...7 8. NON-FIRM ATC CALCUATION METHDOLOGY…………………………………….8 9. IMPLEMENTATION……………………………………………………………………..8 10. ETC CALCULATION…………………………………………………………………...10 11. COUNTERFLOW……………………………………………………………………….12 12. GENERATION AND TRANSMISSION OUTAGE……………………………………12 13. DETERMINATION OF CBM AND TRM……………………………………………...13 14. POSTBACKS……………………………………………………………………………13 15. DATA RETENTION…………………………………………………………………….14 16. REQUESTS FOR DATA………………………………………………………………..14 17. VERSION HISTORY……………………………………………………………………15 APPENDIX A - RATED PATH NUMBERS APPENDIX B - RATED PATH METHODOLOGY (AVAILABLE UPON REQUEST) APPENDIX C - MARCH 4, 2011 LETTER FROM NERC APPENDIX D – ATC DATA TO BE PROVIDED UPON REQUEST 2 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Version 3 1. INTRODUCTION Southwest Transmission Cooperative, Inc. (SWTC), a Transmission Operator and Transmission Service Provider, has prepared this Available Transfer Capability Implementation Document (ATCID) as required by the North American Reliability Corporation (NERC) Standard MOD-001-1a. This ATCID for SWTC contains information relative to SWTC’s methodology for determining Total Transfer Capability (TTC), Available Transfer Capability (ATC) and additional requirements from MOD-029001-1a (Rated System Path Methodology). 2. ATC METHODOLOGY SWTC has selected the NERC Rated System Path Methodology as the appropriate methodology to use to determine the TTC and the ATC for the SWTC transmission system. (MOD-001-1a, R1) This document contains the documentation of SWTC’s methodology and assumptions for determining TTC and ATC. SWTC shall use the ATC and TTC as determined within this document for all determinations of ATC and TTC. (MOD-001-1a R6 and R7) 3. RESPONSIBILITY The following SWTC positions are responsible for implementing the methodology set forth in this document: Transmission Planning Manager Director of System Operations These positions are responsible for implementing the methodology described within this document. 4. REFERENCES NERC Reliability Standard MOD-001a-1 NERC Reliability Standard MOD-029a-1 5. INTERVALS AND UPDATE FREQUENCY SWTC posts the ATC for each ATC Path through OATI OASIS based on the calculations performed in WebTrans from the components of the ATC algorithms as discussed within this ATCID. SWTC’s calculation of ATC is performed and values are updated automatically for the intervals listed below and whenever the WebTrans tool detects a change in the value of any component within the ATC algorithm. 3 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 SWTC’s calculated ATC values are updated by WebTrans for the intervals and frequency as outlined below: (MOD-001-1a R2.1, 2.2, 2.3) Hourly values for the next seven days. (Recalculated each hour or as changes are made to affect the ATC calculation) (MOD-001-1a R8.1) Daily values for the next 31 calendar days. (Recalculated each day or as changes are made that affect the daily ATC calculation) (MOD-001-1a R8.2) Weekly values for five weeks. (Recalculated each day or as changes are made that affect the weekly ATC calculation) Monthly values for the next 12 months (months 2-13). (Recalculated each day or as changes are made that affect the monthly ATC calculation) (MOD-001-1a R8.3) 6. DETERMINATION OF TTC At least annually SWTC shall use the following process to determine TTC: Except where otherwise specified within NERC Reliability Standard MOD-029-1a, adjust base case generation and load levels within the updated power flow model to determine the TTC (maximum flow or reliability limit) that can be simulated on the ATC Path while at the same time satisfying all planning criteria contingencies as follows: (MOD-029-1a R2.1) During TTC studies, SWTC recognized NERC’s consideration of MOD-029-1a R2.1 by the letter from NERC to Transmission Operators and Transmission Service Providers subject to MOD-029-1a, dated March 4, 2011 (Appendix D). R2.1 – Except where otherwise specified within MOD-029-1, adjust base case generation and Load Levels within the updated powerflow model to determine the TTC that can be simulated on the ATC path while at the same time satisfying all planning criteria contingencies as listed below. If a reliability limit can be found in simulation, the TTC is set to the simulated flow on the ATC Path corresponding to the reliability limit. If no reliability limit is found in the simulation, the TTC may be set equal to the Facility Rating of the path or the maximum simulated flow on the path. Flow Limited Definition: A path is “flow limited” if the simulated flow, at the established transfer level, on the path is less than the facility rating, and new reliability limits have been found. A reliability limit is found if contingency results in a violation of a Facility Rating or SOL on the ATC Path being rated or an outage of any element of the ATC Path being rated 4 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 results in a criteria violation on any part of the system. If a reliability limit is not found in the simulation, the TTC is set to either a) the simulated flow or b) the Facility Rating. SWTC also followed NERC’s recommendation (refer Appendix D, NERC letter dated March 4, 2011) to calculate TTC consistent with past practices. The methodology incorporating the proposed R2.1 language was used to provide evidence of “flow limited” paths. In the interim, NERC suggests (but does not require) that entities calculate the TTC of “Flow Limited” paths consistent with practices used in the past (such as using the path thermal rating). During audits, any paths for which TTC has not been calculated based on R2.1 will be expected to be demonstrably “Flow Limited”. Evidence to demonstrate this will be considered on a case by case basis, but in general, a presentation of the studies showing the results of the simulation will be adequate proof of compliance. When modeling normal conditions, all Transmission Elements will be modeled at or below 100% of their continuous rating. (MOD-029-1a R2.1.1) When modeling contingencies the system shall demonstrate transient, dynamic and voltage stability, with no Transmission Element modeled above its Emergency Rating. (MOD029-1a R2.1.2) Uncontrolled separation shall not occur. (MOD-029-1a R2.1.3) Where it is impossible to actually simulate a reliability-limited flow in a direction counter to prevailing flows (on an alternating current Transmission line), set the TTC for the nonprevailing direction equal to the TTC in the prevailing direction. If the TTC in the prevailing flow direction is dependent on a Special Protection System (SPS), set the TTC for the non-prevailing flow direction equal to the greater of the maximum flow that can be simulated in the non-prevailing flow direction or the maximum TTC that can be achieved in the prevailing flow direction without use of a SPS. (MOD-029-1a R2.2) For an ATC Path whose capacity is limited by contract, set TTC on the ATC Path at the lesser of the maximum allowable contract capacity or the reliability limit as determined by 2.2.1. (MOD-029-1a R2.3) For an ATC Path whose TTC varies due to simultaneous interaction with one or more other paths, develop a nomogram describing the interaction of the paths and the resulting TTC under specified conditions. SWTC does not currently have any paths requiring nomograms. (MOD-029-1a R2.4) 5 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 SWTC shall identify when the TTC for the ATC Path being studied has an adverse impact on the TTC value of any existing path. Done by modeling the flow on the path being studied at its proposed new TTC level simultaneous with the flow on the existing path at its TTC level while at the same time honoring the reliability criteria outlined in 2.2.1. SWTC shall include the resolution of this adverse impact in its study report for the ATC Path. (MOD-029-1a R2.5) Where multiple ownership of Transmission rights exists on an ATC Path, allocate TTC of that ATC Path in accordance with the contractual agreement made by the multiple owners of that ATC Path. (MOD-029-1a R2.6) Data Received for ATC Calculation (MOD-0001-1a R3.3) • Tucson Electric Power (TEP) • Salt River Project (SRP) Data Provided for ATC Calculation (MOD-001-1a R3.4) • None SWTC does not provide an allocation of transfer capability to any other entities. (MOD001-1a R3.5) For ATC Paths whose path rating, adjusted for seasonal variance, was established, known and used in operation since January 1, 1994, and no action has been taken to have the path rated using a different method, set the TTC at that previously established amount. (MOD029-1a R2.7) SWTC does not establish TTC for any ATC path where three phase faults damping is used to determine stability limits. In Appendix C SWTC describes the process in developing the TTC and ATC numbers on the SWTC system. A detailed documentation listing system assumptions, base cases, contingencies and results are included. Also included in the report are stability plots and a list of each path as either flow limited or reliability limited. Where a path was deemed flow limited, NERC did not require entities to calculate the TTC rather use the path thermal rating which is consistent with practices in the past. (MOD-029-1a R2.8) SWTC shall establish the TTC at the lesser of the value calculated in MOD-029-1a R2.2 or any System Operating Limit (SOL) for that ATC Path. (MOD-029-1a R3) 6 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 Within seven calendar days of the finalization of the study report, SWTC (Transmission Operator) shall make available to SWTC (Transmission Service Provider), the most current value for TTC and the TTC study report documenting the assumptions used and steps taken in determining the current value for TTC for that ATC Path. All SWTC paths may be viewed on the SWTC OASIS (http://www.oatioasis.com/SWTC/index.html). (MOD-0291a R4) The needs for updates are normally tied to a significant system modification such as a new interconnected resource, transmission network modification and/or changes in forecast loads. 7. FIRM ATC CALCULATION METHODOLOGY When calculating firm ATC for an ATC Path for a specified period, SWTC shall use the following algorithm: (MOD-029-1a R7) ATCF = TTC – ETCF – CBM – TRM + PostbacksF + counterflowsF Where: ATCF is the firm Available Transfer Capability for the ATC Path for that period. TTC is the Total Transfer Capability of the ATC Path for that period. ETCF is the sum of existing reserved firm commitments for the ATC Path during that period. CBM is the Capacity Benefit Margin for the ATC Path during that period. TRM is the Transmission Reliability Margin for the ATC Path during that period. PostbacksF are changes to firm Available Transfer Capability due to a change in the use of Transmission Service for that period, as defined in Business Practices counterflowsF are adjustments to firm Available Transfer Capability as determined by SWTC and specified in this ATCID. 8. NON-FIRM ATC CALCULATION METHODOLOGY When calculating non-firm ATC for an ATC Path for a specified period, SWTC shall use the following algorithm: (MOD-029-1 R8) ATCNF = TTC – ETCF – ETCNF – CBMS – TRMU + PostbacksNF + counterflowsNF Where: 7 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 ATCNF is the non-firm Available Transfer Capability for the ATC Path for that period. TTC is the Total Transfer Capability of the ATC Path for that period. ETCF is the sum of existing reserved firm commitments for the ATC Path during that period. ETCNF is the sum of existing non-firm commitments for the ATC Path during that period. CBMS is the Capacity Benefit Margin for the ATC Path that has been scheduled during that period. TRMU is the Transmission Reliability Margin for the ATC Path that has not been released for sale (unreleased) as non-firm capacity by the Transmission Service Provider during that period. PostbacksNF are changes to non-firm Available Transfer Capability due to a change in the use of Transmission Service for that period, as defined in Business Practices. counterflowsNF are adjustments to non-firm Available Transfer Capability as determined by SWTC and specified in this ATCID. 9. IMPLEMENTATION Transmission Model When calculating TTCs for ATC Paths, SWTC shall use a Transmission model that satisfies the following requirements: (MOD-029-1a R1) The model utilizes data and assumptions consistent with the time period being studied and that meets the following criteria: (MOD-029-1a R1.1) Includes at least: The SWTC transmission area. Although equivalent representation of radial lines and facilities 161kV or below is allowed, SWTC chose to represent all 115 kV and above excluding radial lines. All load off radial lines was lumped on the high voltage (HV) side of the system it was located on. (MOD-029-1a R1.1.1) All Transmission Operator areas contiguous to SWTC’s area. (Equivalent representation is allowed) (MOD-029-1 R1.1.2) Any other Transmission Operator area linked to SWTC’s area by joint operating agreement. (Equivalent representation is allowed) MOD-029-1a R1.1.3 SWTC utilized a Western Electricity Coordinating Council (WECC) approved 2015 and 2016 Heavy Summer and Light Winter Operating cases. These cases are compiled by WECC entities therefore they show the most up to data information known at the time of 8 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 compilation. Therefore, SWTC modeled all system Elements as in-service for the assumed initial conditions. (MOD-029-1a R1.1.2) All WECC approved base cases include firm transfers required to meet projected load levels in each case. Therefore, SWTC modeled all generation (may be either a single generator or multiple generators) that is greater than 20 MVA at the point of interconnection in the studied area. (MOD-029-1a R1.1.3) SWTC does not maintain phase shifters, therefore this requirement does not apply. (MOD029-1a R1.1.4) All WECC approved operating cases contain load forecast prepared by Sierra Southwest Cooperative Services’ Inc. (Sierra) Power Services department in conjunction with member cooperatives. Load forecast information is provided by SWTC’s Balancing Authority, Western Area Power Administration, Desert Southwest (WALC) and to the WECC for regional studies. (MOD-029-1a R1.1.5) SWTC uses the most recent operating cases, each case was developed utilizing the best information available at the time of the study for planned facility changes. In the event of a change in the work plans or current configuration, the case was adjusted to reflect the most relevant information. The following transmission facilities were adjusted to reflect the cases.(MOD-029-1a R1.1.6) SWTC delivers all AEPCO resources to the Class A Members in addition to its other contractual obligations. Although three Class A Members can receive capacity and energy from sources other than AEPCO, the total load for the members is modeled on the SWTC Transmission System to ensure adequate delivery of all resources necessary to reliably serve the entire forecasted Class A Member load as well as the loads associated with SWTC’s transmission service agreements. SWTC did not currently have any Generation Facility additions or retirements within the timeframe modeled. (MOD-029-1a R1.1.7) SWTC incorporates Special Protection System (SPS) models where currently existing or projected for implementation within the studied time horizon. SPS schemes that influence the TTC results will be noted in the TTC study report for a specific ATC Path. SWTC does not currently have any SPS’s in place. TEP and SWTC currently have a Local Area Protection Scheme (LAPS) that is utilized under an outage on the TEP system, whereupon SWTC will open a portion of its 115 kV system. Currently the LAPS is not defined under NERC and WECC. (MOD-029-1a R1.1.8) 9 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 Models series compensation for each line at the expected operating level, unless specified otherwise below. (MOD-029-1a R1.1.9) • SWTC does not own or operate any series compensation devices on its system. Includes any other modeling requirements or criteria specified below. (MOD-029-1a R1.1.10) • No additional modeling requirements or criteria were used in the model. SWTC is listed as a Transmission Owner therefore they are responsible in maintaining facility ratings based on the most limiting factors per the FAC 008-1 and 009-1 reliability standards. (MOD-029-1a R1.2) 10. ETC CALCULATION When calculating ETC for firm Existing Transmission Commitments (ETCF) for a specified period for an ATC Path, SWTC shall use the algorithm below: (MOD-029-1a R5) ETCF = NLF + NITSF + GFF + PTPF + RORF + OSF Where: NLF is the firm capacity set aside to serve peak Native Load forecast commitments for the time period being calculated, to include losses, and Native Load growth, not otherwise included in Transmission Reliability Margin or Capacity Benefit Margin. NITSF is the firm capacity reserved for Network Integration Transmission Service serving Load, to include losses, and Load growth, not otherwise included in Transmission Reliability Margin or Capacity Benefit Margin. SWTC utilizes this calculation in the NL calculation. GFF is the firm capacity set aside for grandfathered Transmission Service and contracts for energy and/or Transmission Service, where executed prior to the effective date of a Transmission Service Provider’s Open Access Transmission Tariff or “safe harbor tariff.” SWTC does not currently have any GF on its system. 10 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 PTPF is the firm capacity reserved for confirmed Point-to-Point Transmission Service. SWTC models these contracts using specified megawatt quantity, point of receipt, and point of delivery. RORF is the firm capacity reserved for Roll-over rights for contracts granting Transmission Customers (TC) the right of first refusal to take or continue to take Transmission Service when the TC’s Transmission Service contract expires or is eligible for renewal. SWTC assumes that a TC will rollover its existing long term TSR. To account for this, transmission in the amount of the confirmed TSR is set aside. ROR is modeled as using specified megawatt quantity, point of receipt and point of delivery. If a TC does not exercise its rollover right, that amount may be removed from the ETC, unless that capacity is reserved by another TC. OSF is the firm capacity reserved for any other service(s), contract(s), or agreement(s) not specified above using Firm Transmission Service as specified in this ATCID. When calculating ETC for non-firm Existing Transmission Commitments (ETCNF) for all time horizons for an ATC Path SWTC shall use the following algorithm: (MOD-029-1a R6) ETCNF = NITSNF + GFNF + PTPNF + OSNF Where: NITSNF is the non-firm capacity set aside for Network Integration Transmission Service serving Load (i.e., secondary service), to include losses, and load growth not otherwise included in Transmission Reliability Margin or Capacity Benefit Margin. GFNF is the non-firm capacity set aside for grandfathered Transmission Service and contracts for energy and/or Transmission Service, where executed prior to the effective date of a Transmission Service Provider’s Open Access Transmission Tariff or “safe harbor tariff.” PTPNF is non-firm capacity reserved for confirmed Point-to-Point Transmission Service. OSNF is the non-firm capacity reserved for any other service(s), contracts(s), or agreements(s) not specified above using non-firm transmission service as specified in this ATCID. 11 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 11. COUNTERFLOW SWTC accounts for internal counterflow by adding the appropriate Firm counter-schedules to the Non-firm ATC for real time and next day periods (scheduling and operating horizons). (MOD-001-1a R3.2.1) Rationale: Counterflow from expected Firm Interchange schedules from reservations on SWTC’s transmission system in the base case in the opposite direction is included at 100% to Non-Firm ATC. Counterflow for the impact of firm schedules has been set to utilize the “netting” of firm energy on paths to maximize the associated ATC. (MOD-0010-1a R3.2.2) 12. GENERATION AND TRANSMISSION OUTAGE Planned generation and transmission outages of the system are typically studied in advance to assess the impact an outage may have on a specific path’s TTC for the expected conditions during the outage. This provides quantification of the TTC impact and any potential curtailment requirements. The effect of outages on the ATC calculation is managed through WebTrans software. The percentage decrease in TTC on a path from an outage is entered into WebTrans software which in turn triggers updates to the ATC calculation. Outages are entered based on the known or scheduled start date and time through the estimated restoration date and time. (MOD-001-1a R3.2) Outages in Effect for Part of a Day Outages in effect for part of a day will be determined from the starting date and time and ending date and time. For an outage that is in effect part of a day, the hourly ATC will be reduced by the indicated amount for any hours after the start time and any hours prior to the end time. The daily ATC calculation will be set to the minimum hourly ATC. (MOD001-1a R3.6.1) Outages in Effect for Part of a Month Outages in effect for part of a month will be determined from the starting date and time and ending date and time. The daily ATC for any days within the month will be set to the minimum ATC for any hour for the day and the monthly ATC will be set to the minimum daily ATC during the month. (MOD-001-1a R3.6.2) Outages from other Transmission Providers not Mapped to the SWTC Transmission System All transmission studies are performed as off-line studies with sufficient detail to assess impacts of outages from other Transmission Service Providers within the model. Outages 12 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 of one Transmission Provider with known impacts on another Transmission Provider or Transmission Operator are communicated sufficiently in advance to allow time for off-line studies to assess TTC and update ATC postings.(MOD-029-1a R3.6.3) 13. DETERMINATION OF CBM AND TRM SWTC does not use CBM on any ATC paths therefore; SWTC’s CBM value is set to zero (0). SWTC does not use TRM on any ATC paths therefore; SWTC’s TRM value is set to zero (0). SWTC’s CBMID and TRMID are posted on SWTC’s OASIS http://www.oatioasis.com/SWTC/ 14. POSTBACKS Postbacks are positive adjustments to ATC due to reservation annulments, redirects, recalls, or the release of unscheduled use of confirmed reserved firm capacity. SWTC applies Postbacks based upon the following criteria: • • • • 15. Recall of transmission reservation Redirect of a transmission service on a firm basis Annulment of a transmission reservation Released capacity due to unscheduled firm transmission reservations (Scheduling and Operating Horizons only) DATA RETENTION SWTC shall keep data or evidence to show compliance for a specific audit period unless directed by WECC to retain specific evidence for a longer period of time as part of an investigation: 16. REQUESTS FOR DATA SWTC, as the Transmission Provider, shall make this ATCID available to all entities by posting it on the SWTC OASIS. (MOD-001-1a R5) SWTC will respond to requests for ATC data within thirty (30) days of receiving such request. (MOD-001-1a R9) Such request shall be made to the following: Director of System Operations Shane Sanders 13 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 ssanders@swtransco.coop 520-586-5239 Data that may be provided is listed in Appendix E. 17. VERSION HISTORY Version 0 Date 3-31-2011 Change Tracking E.King 12-13-2011 Action Creation & Implementation of documentation Administrative cleanup 1 2 12-31-2012 Language cleanup & updated Study Tumarin/Sanders 3 12-31-2013 Annual Update Tumarin/Sanders 4 06-30-2014 Annual Update Tumarin/Sanders 5 07-07-2015 Annual Update Tumarin/Sanders 14 J.Cook Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Version 3 Appendix A SWTC Rated Path Numbers SWTC – MOD-29 Results Table SWTC Path Limiting Element/Limiting Contingency TTC (MW) Apache 115 kV – Hayden 115 kV Flow Limited 114 Hayden 115 kV – Apache 115 kV Flow Limited 114 Apache 230 kV – Bicknell 230 kV Flow Limited 309 Bicknell 230 kV – Apache 230 kV Flow Limited 309 Apache 230 kV – Dos Condados 230 kV Flow Limited 402 Dos Condados 230 kV – Apache 230 kV Flow Limited 402 Apache 230 kV – Winchester 345 kV Flow Limited 402 Winchester 345 kV – Apache 230 kV Flow Limited 402 Vail 345 kV – Bicknell 230 kV Flow Limited 225 Bicknell 230 kV – Vail 345 kV Flow Limited 225 Hackberry 230 kV – Dos Condados 230 kV Dos Condados 230 kV – Hackberry 230 kV Marana 115 kV – Bicknell 230 kV Flow Limited 402 Flow Limited 402 Flow Limited 119 Bicknell 230 kV – Marana 115 kV Flow Limited 64 Greenlee 345 kV – Morenci 230 kV Flow Limited 193 Morenci 230 kV – Greenlee 345 kV Flow Limited 193 Morenci 230 kV – Hackberry 230 kV Flow Limited 402 Hackberry 230 kV – Morenci 230 kV Flow Limited 402 Apache 230 kV – Apache 115 kV Flow Limited 224 Apache 115 kV – Apache 230 kV Flow Limited 224 Palo Verde 500 kV Pinal West 345 kV (SRP Owner) Refer to SRP Path Rating Methodology (SRP Contractually limited SWTC 7.3%) 120 West Wing 345 kV - Pinal West 345 kV (TEP Owner) Refer to TEP Path Rating Methodology (TEP Contractually limited SWTC 24%) 161 Pinal West 345 kV - Vail 345 kV (TEP Owner) Refer to TEP Path Rating Methodology (TEP Contractually limited SWTC 24%) 222 The Three Points to Bicknell segment of the Marana – Bicknell 115 kV line is limited to 64 MW due to conductor rating. It is determined that due to loads dropped off prior to the limited segment of this line, the rating of the Marana – Bicknell 115 kV line will be 92 MW. 3 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 Appendix B Rated Path Methodology (Available Upon Request) 16 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 Appendix C 17 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 18 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 19 Southwest Transmission Cooperative, Inc. Available Transfer Capability Implementation Document Procedure Version 5 Appendix D ATC DATA TO BE PROVIDED UPON REQUEST • • • • • • • • • • • • • • • • • • • Expected generation and Transmission outages, additions, and retirements. Load forecasts. Unit commitments and order of dispatch, to include all designated network resources and other resources that are committed or have the legal obligation to run, as they are expected to run, in one of the following formats chosen by the data provider. Dispatch Order Participation Factors Block Dispatch Aggregated firm capacity set-aside for Network Integration Transmission Service and aggregated non-firm capacity set aside for Network Integration Transmission Service (i.e. Secondary Service). Firm and non-firm Transmission reservations. Aggregated capacity set-aside for Grandfathered obligations Firm roll-over rights. Any firm and non-firm adjustments applied by the Transmission Service Provider to reflect parallel path impacts. Power flow models and underlying assumptions. Contingencies, provided in one or more of the following formats: o A list of Elements o A list of Flowgates o A set of selection criteria that can be applied to the Transmission model used by the Transmission Operator and/or Transmission Service Provider Facility Ratings. Any other services that impact Existing Transmission Commitments (ETCs). Values of Capacity Benefit Margin (CBM) and Transmission Reliability Margin (TRM) for all ATC Paths or Flowgates. Values of Total Flowgate Capability (TFC) and AFC for any Flowgates considered by the Transmission Service Provider receiving the request when selling Transmission service. Values of TTC and ATC for all ATC Paths for those Transmission Service Providers receiving the request that do not consider Flowgates when selling Transmission Service. Source and sink identification and mapping to the model. 20