DEPARTMENT OF ENERGY CABLE AGING MANAGEMENT RESEARCH PROJECTS REVIEW Slide 1 CURRENT ACTIVITIES • Research for U.S. Department of Energy – “A Holistic Approach for In-Situ Cable Condition Monitoring in Nuclear Power Plants.” – “Integrated System for Management of Cable Aging in Support of Long Life Operation of Nuclear Power Plants.” Slide 2 NRC AND EPRI RECOMMENDATIONS NRC DG 1240 Recommended Testing Procedures Direct Current High-Potential Test (dc High Voltage) EPRI TR 1020804 Recommended Testing Procedures Visual/Tactile Assessment Indenter Testing Step Voltage Test (dc High Voltage) Ultrasonic Velocity Assessment Illuminated Borescope Line Resonance Analysis Visual Inspection Near-Infrared Spectroscopy Compressive Modulus (Polymer Indenter) Laboratory Tests Dielectric Loss – Dissipation Factor/Power Factor Insulation Resistance/Polarization Index Partial Discharge Test Traditional Troubleshooting Techniques EPRI TR 1020805 Recommended Testing Procedures Time Domain Reflectometery Partial Discharge Line Resonance Analysis Tan Delta Infrared Imaging Thermography Power Frequency or Very Low Frequency (VLF) Withstand Slide 3 AMS CABLE AGING MANAGEMENT PROGRAM Cable Aging Management Program Visual/Tactile Electrical Mechanical Embedded Sensors Thermography FDR Indenter AgeAlert™ Walkdown TDR EAB LCR IR RTDR Tan Delta Partial Discharge Slide 4 ACCELERATED CABLE AGING Slide 5 ELONGATION AT BREAK (EAB) EAB sample prepared to the IEC 62582 Standard Slide 6 CABLE AGING RESULTS Cable Artificially Aged for 334 Hours at 150° C FDR IR Slide 7 TDR RISE TIME • How does the pulse rise time affect the reflected signal? • How does the length of the cable under test affect the reflected signal of different pulse rise times? • Four TDR Pulsers – – – – 100ps 5ns 7ns 20ns Slide 8 TDR RISE TIME 50 Ω Coaxial Cable Impedance Change in Cable Under Test CABLE085-01 50 Ω Coaxial Cable Impedance Impedance Change Change Impedance Change 50 Ω Coaxial 50 ΩCable Coaxial Cable 50 Ω Coaxial Cable Slide 9 ROCKBESTOS CABLE TESTING Slide 10 ROCKBESTOS CABLE TESTING IR Test Baseline Test 1 186.58 GOhms Test 2 160.88 GOhms Test 3 142.80 GOhms Average 163.42 GOhms TDR Trace Revealing Moisture Intrusion and Jacket Cuts Moisture Intrusion 53.77 GOhms 60.62 GOhms 57.32 GOhms 57.24 GOhms FDR Trace Revealing Moisture Intrusion and Jacket Cuts Slide 11 IN PLANT TESTING: RTDS Slide 12 IN PLANT TESTING: NUCLEAR INSTRUMENTATION Slide 13 2012 CHAR SYSTEM • TDR • RTDR • LCR • IR • I-V • FDR • Waveform Slide 14 THANK YOU! Slide 15