Smart Integration of Distributed Renewable Generation and Battery Energy Storage Duong Quoc Hung Bachelor of Electrical and Electronics Engineering Master Engineering in Electric Power System Management A thesis submitted for the degree of Doctor of Philosophy at The University of Queensland in 2014 The School of Information Technology and Electrical Engineering ABSTRACT Renewable energy (i.e., biomass, wind and solar) and Battery Energy Storage (BES) are emerging as sustainable solutions for electricity generation. In the last decade, the smart grid has been introduced to accommodate high penetration of such renewable resources and make the power grid more efficient, reliable and resilient. The smart grid is formulated as a combination of power systems, telecommunication communication and information technology. As an integral part of the smart grid, a smart integration approach is presented in this thesis. The main idea behind the smart integration is locating, sizing and operating renewable-based Distributed Generation (DG) resources and associated BES units in distribution networks strategically by considering various technical, economical and environmental issues. Hence, the aim of the thesis is to develop methodologies for strategic planning and operations of high renewable DG penetration along with an efficient usage of BES units. The first contribution of the thesis is to present three alternative analytical expressions to identify the location, size and power factor of a single DG unit with a goal of minimising power losses. These expressions are easily adapted to accommodate different types of renewable DG units for minimizing energy losses by considering the time-varying demand and different operating conditions of DG units. Both dispatchable and nondispatchable renewable DG units are investigated in the study. Secondly, a methodology is also introduced in the thesis for the integration of multiple dispatchable biomass and nondispatchable wind units. The concept behind this methodology is that each nondispatchable wind unit is converted into a dispatchable source by adding a biomass unit with sufficient capacity to retain the energy loss at a minimum level. Thirdly, the thesis studies the determination of nondispatchable photovoltaic (PV) penetration into distribution systems while considering time-varying voltage-dependent load models and probabilistic generation. The system loads are classified as an industrial, commercial or residential type or a mix of them with different normalised daily patterns. The Beta probability density function model is used to describe the probabilistic nature of solar irradiance. An analytical expression is proposed to size a PV unit. This expression is based on the derivation of a multiobjective index (IMO) that is formulated as a combination of ii three indices, namely active power loss, reactive power loss and voltage deviation. The IMO is minimised in determining the optimal size and power factor of a PV unit. Fourthly, the thesis discusses the integration of PV and BES units considering optimal power dispatch. In this work, each nondispatchable PV unit is converted into a dispatchable source by adding a BES unit with sufficient capacity. An analytical expression is proposed to determine the optimal size and power factor of PV and BES units for reducing energy losses and enhancing voltage stability. A self-correction algorithm is then developed for sizing multiple PV and BES units. Finally, the thesis presents a comprehensive framework for DG planning. In this framework, analytical expressions are proposed to efficiently capture the optimal power factor of each DG unit with a standard size for minimising energy losses and enhancing voltage stability. The decision for the optimal location, size and number of DG units is obtained through a benefit-cost analysis over a given planning horizon. Here, the total benefit includes energy sales, loss reduction, network investment deferral and emission reduction, while the total cost is a sum of capital, operation and maintenance expenses. The study reveals that the time-varying demand and generation models play a significant role in renewable DG planning. Depending on the characteristics of demand and generation, a distribution system would accommodate up to an estimated 48% of the nondispatchable renewable DG penetration. A higher penetration level could be obtained for dispatchable DG technologies such as biomass and a hybrid of PV and BES units. More importantly, the study also indicates that optimal power factor operation could be one of the aspects to be considered in the strategy of smart renewable DG integration. A significant energy loss reduction and voltage stability enhancement can be achieved for all the proposed scenarios with DG operation at optimal power factor when compared to DG generation at unity power factor which follows the current standard IEEE 1547. Consequently, the thesis recommends an appropriate modification to the grid code to reflect the optimal or near optimal power factor operation of DG as well as BES units. In addition, it is shown that inclusion of energy loss reduction together with other benefits such as network investment deferral and emission reduction in the analysis would recover DG investments faster. iii DECLARATION BY AUTHOR This thesis is composed of my original work, and contains no material previously published or written by another person except where due reference has been made in the text. I have clearly stated the contribution by others to jointly-authored works that I have included in my thesis. I have clearly stated the contribution of others to my thesis as a whole, including statistical assistance, survey design, data analysis, significant technical procedures, professional editorial advice, and any other original research work used or reported in my thesis. The content of my thesis is the result of work I have carried out since the commencement of my research higher degree candidature and does not include a substantial part of work that has been submitted to qualify for the award of any other degree or diploma in any university or other tertiary institution. I have clearly stated which parts of my thesis, if any, have been submitted to qualify for another award. I acknowledge that an electronic copy of my thesis must be lodged with the University Library and, subject to the General Award Rules of The University of Queensland, immediately made available for research and study in accordance with the Copyright Act 1968. I acknowledge that copyright of all material contained in my thesis resides with the copyright holder(s) of that material. Where appropriate I have obtained copyright permission from the copyright holder to reproduce material in this thesis. iv PUBLICATIONS DURING CANDIDATURE Book (1): 1. N. Mithulananthan and D.Q. Hung, “Smart integration of distributed generation”, under preparation. Published International Journal Articles (7): 2. D.Q. Hung, N. Mithulananthan, and Kwang Y. Lee, “Determining PV penetration for distribution systems with time-varying load models, IEEE Transactions on Power Systems, early access, DOI: 10.1109/TPWRS.2014.2314133 (ERA 2010: ranked A*, impact factor: 3.530). 3. D.Q. Hung, N. Mithulananthan, and R.C. Bansal, “An optimal investment planning framework for multiple DG units in industrial distribution systems”, Applied Energy, volume 124, pages 67-72, July 2014 (ERA 2010: ranked A, impact factor: 5.261). 4. D.Q. Hung, and N. Mithulananthan, “Loss reduction and loadability enhancement with DG: A dual-index analytical approach”, Applied Energy, volume 115, pages 233-241, February 2014 (ERA 2010: ranked A, impact factor: 5.261). 5. D.Q. Hung, N. Mithulananthan, and R.C. Bansal, “Integration of PV and BES units in commercial distribution systems considering energy losses and voltage stability”, Applied Energy, volume 113, pages 1162-1170, January 2014 (ERA 2010: ranked A, impact factor: 5.261). 6. D.Q. Hung, N. Mithulananthan and R. C. Bansal, “Analytical strategies for renewable distributed generation integration considering energy loss minimization,” Applied Energy, volume 105, pages 75-85, May 2013 (ERA 2010: ranked A, impact factor: 5.261). 7. D.Q. Hung, N. Mithulananthan, and Kwang Y. Lee, “Optimal placement of dispatchable and nondispatchable renewable DG units in distribution networks for minimising energy loss,” International Journal of Electrical Power and Energy Systems, volume 55, pages 179-186, February 2014 (ERA 2010: ranked C, impact factor: 3.432). 8. D.Q. Hung, N. Mithulananthan, and R.C. Bansal, “A combined practical approach for distribution system loss reduction”, International Journal of Ambient Energy, in Press, DOI: 10.1080/01430750.2013.829784. v Submitted International Journal Articles (1): 9. D.Q. Hung, N. Mithulananthan, and Kwang Y. Lee, “Probabilistic voltage profile optimization with electric vehicles and PV units in commercial systems,” under preparation, to be submitted to IEEE Transactions on Power Systems. International Conference Papers (7) 10. D.Q. Hung, and N. Mithulananthan, “Assessing the impact of loss reduction on distributed generation investment decisions,” in Proceedings of 23nd Australasian Universities Power Engineering Conference, Tasmania, Australia, 29 September - 3 Oct. 2013. 11. D.Q. Hung, N. Mithulananthan, and Kwang Y. Lee, “Placement of photovoltaic and battery energy storage units in distribution systems considering energy loss,” in Proceedings of International Smart Grid Conference & Exhibition, Seoul, Korean, 811 July 2013. 12. D.Q. Hung and N. Mithulananthan, "A Simple approach for distributed generation integration considering benefits for DNO," in Proceedings of IEEE International Conference on Power Systems Technology, Auckland, New Zealand, 30 October - 2 November 2012. 13. D.Q. Hung and N. Mithulananthan, “A dual-index based analytical approach for DG planning considering power losses,” in Proceedings of 22nd Australasian Universities Power Engineering Conference, Bali, Indonesia, 26-29 September 2012. 14. D.Q. Hung and N. Mithulananthan, "An optimal operating strategy of DG unit for power loss reduction in distribution systems," in Proceedings of 7th IEEE International Conference on Industrial and Information Systems, Chennai, India, 0609 August 2012. 15. D.Q. Hung and N. Mithulananthan, “Alternative analytical approaches for renewable DG allocation for energy loss minimization,” in Proceedings of IEEE Power and Energy Society General Meeting, USA, 22-26 July 2012. 16. D.Q. Hung and N. Mithulananthan, “Community energy storage and capacitor allocation in distribution systems,” in Proceedings of 21st Australasian Universities Power Engineering Conference, Brisbane, Australia, 25-28 September 2011. vi PUBLICATIONS INCLUDED IN THIS THESIS 1. D.Q. Hung, N. Mithulananthan and R. C. Bansal, “Analytical strategies for renewable distributed generation integration considering energy loss minimization,” Applied Energy, volume 105, pages 75-85, May 2013 – Partially incorporated as Chapters 2 and 4. Contributor Statement of contribution Duong Quoc Hung Programming, simulation and modelling (100%) Result interpretation and discussion (80%) Wrote the paper (80%) N. Mithulananthan Discussion on results (15%) Reviewed the paper (15%) R. C. Bansal Discussion on results (5%) Reviewed the paper (5%) 2. D.Q. Hung, and N. Mithulananthan “Loss reduction and loadability enhancement with DG: A dual-index analytical approach”, Applied Energy, volume 115, pages 233-241, February 2014 – Partially incorporated as Chapter 4. Contributor Statement of contribution Duong Quoc Hung Programming, simulation and modelling (100%) Result interpretation and discussion (80%) Wrote the paper (80%) N. Mithulananthan Discussion on results (20%) Reviewed the paper (20%) vii 3. D.Q. Hung, N. Mithulananthan, and Kwang Y. Lee, “Optimal placement of dispatchable and nondispatchable renewable DG units in distribution networks for minimising energy loss,” International Journal of Electrical Power and Energy Systems, volume 55, pages 179-186, February 2014 – Partially incorporated as Chapters 2 and 5. Contributor Statement of contribution Duong Quoc Hung Programming, simulation and modelling (100%) Result interpretation and discussion (80%) Wrote the paper (80%) N. Mithulananthan Discussion on results (15%) Reviewed the paper (15%) Kwang Y. Lee Discussion on results (5%) Reviewed the paper (5%) 4. D.Q. Hung, N. Mithulananthan, and Kwang Y. Lee, “Determining PV penetration for distribution systems with time-varying load models, IEEE Transactions on Power Systems, early access, DOI: 10.1109/TPWRS.2014.2314133 – Incorporated as Chapters 2, 3 and 6. Contributor Statement of contribution Duong Quoc Hung Programming, simulation and modelling (100%) Result interpretation and discussion (80%) Wrote the paper (80%) N. Mithulananthan Discussion on results (15%) Reviewed the paper (15%) Kwang Y. Lee Discussion on results (5%) Reviewed the paper (5%) viii 5. D.Q. Hung, N. Mithulananthan, and R.C. Bansal, “Integration of PV and BES units in commercial distribution systems considering energy losses and voltage stability”, Applied Energy, volume 113, pages 1162-1170, January 2014 – Incorporated as Chapters 2, 3 and 7. Contributor Statement of contribution Duong Quoc Hung Programming, simulation and modelling (100%) Result interpretation and discussion (80%) Wrote the paper (80%) N. Mithulananthan Discussion on results (15%) Reviewed the paper (15%) R. C. Bansal Discussion on results (5%) Reviewed the paper (5%) 6. D.Q. Hung, N. Mithulananthan, and R.C. Bansal, “An optimal investment planning framework for multiple DG units in industrial distribution systems”, accepted for publication in Applied Energy, volume 124, pages 67-72, July 2014 – Partially incorporated as Chapters 2, 3 and 8. Contributor Statement of contribution Duong Quoc Hung Programming, simulation and modelling (100%) Result interpretation and discussion (80%) Wrote the paper (80%) N. Mithulananthan Discussion on results (15%) Reviewed the paper (15%) R. C. Bansal Discussion on results (5%) Reviewed the paper (5%) ix Contributions by Others to the Thesis No contributions by others. Statement of Parts of the Thesis Submitted to Qualify for the Award of another Degree None. x ACKNOWLEDGEMENTS One of the most rewarding achievements in my life to date is the completion of my doctoral dissertation at The University of Queensland, which is one of the world’s top universities. I would like to take this opportunity to convey my immense gratitude to all those persons who have given their valuable support and assistance. First and foremost, I would like to express my sincere gratitude and profound respect to my supervisor Dr. N. Mithulananthan for his understanding, continuous intellectual support, invaluable advice and constant encouragement of my endeavours throughout my study. He was very generous with his time and knowledge, and assisted me enthusiastically in each step to complete the thesis. I am also grateful to him for his important advice on my future career. I am profoundly indebted to my associate supervisor Prof. R.C. Bansal from University of Pretoria for his help, suggestions and enlightening discussions towards my research. Thanks also go to Prof. Kwang Y. Lee from Baylor University for his constructive comments and guidance. I would like to acknowledge the financial support of the Government of Australia through the International Postgraduate Research Scholarship and The University of Queensland through the UQ Centennial Scholarship. I would also like to extend thanks to all my colleagues and staffs from the Power and Energy Group of The University of Queensland for their help during my study. Last but not least, special thanks go to my whole family, especially my beloved parents, wife and son, who have been an important and indispensable source of motivation and inspiration. I love my family. This thesis is dedicated to them. “Live a good, honourable life. Then when you get older and think back, you’ll be able to enjoy it a second time.” xi KEYWORDS Battery energy storage, biomass, distributed generation planning, distribution system, energy loss, optimal power factor, photovoltaic, voltage deviation, voltage stability, wind. Australian and New Zealand Standard Research Classifications (ANZSRC) ANZSRC code: 090607, Power and Energy Systems Engineering (excl. Renewable Power), 70% ANZSRC code: 090608, Renewable Power and Energy Systems Engineering (excl. Solar Cells), 30% Fields of Research (FoR) Classification FoR code: 0906, Electrical and Electronic Engineering, 100% xii TABLE OF CONTENTS 1 2 Introduction 1.1 Background ......................................................................................................... 1 1.2 Research Objectives ............................................................................................ 2 1.3 Thesis Outline ..................................................................................................... 3 Literature Review 4 2.1 Introduction......................................................................................................... 4 2.2 Technologies of DG and BES............................................................................. 4 2.3 3 1 2.2.1 Solar Photovoltaic................................................................................... 4 2.2.2 Wind Turbines ........................................................................................ 5 2.2.3 Biomass Gas Turbines ............................................................................ 5 2.2.4 Battery Energy Storage........................................................................... 6 Renewable DG Integration.................................................................................. 6 2.3.1 Technical Benefits .................................................................................. 7 2.3.2 Environmental Benefits ........................................................................ 12 2.3.3 Economical Benefits ............................................................................. 13 2.4 Renewable DG Integration with BES ............................................................... 15 2.5 Grid Codes for DG Integration ......................................................................... 16 2.6 Summary ........................................................................................................... 16 Load and Generation Modelling and Test Systems 18 3.1 Introduction....................................................................................................... 18 3.2 Load Modelling................................................................................................. 18 3.3 Generation Modelling ....................................................................................... 19 3.3.1 Dispatchable Generation....................................................................... 19 xiii 3.4 3.5 4 3.3.2 Nondispatchable Generation................................................................. 20 3.3.3 DG Penetration Level ........................................................................... 22 3.3.4 Generation Criteria ............................................................................... 22 Software Tools and Test Systems ..................................................................... 22 3.4.1 33-Bus Test System .............................................................................. 22 3.4.2 69-Bus One Feeder Test System........................................................... 23 3.4.3 69-Bus Four Feeder Test System.......................................................... 24 Summary ........................................................................................................... 24 Analytical Expressions for Renewable DG Integration 25 4.1 Introduction....................................................................................................... 25 4.2 Load and Renewable DG Modelling ................................................................ 26 4.3 4.4 4.2.1 Load Modelling .................................................................................... 26 4.2.2 Renewable DG Modelling .................................................................... 27 Problem Formulation ........................................................................................ 28 4.3.1 Power Loss............................................................................................ 28 4.3.2 Impact of the Size and Power Factor of DG on Power Losses............. 32 4.3.3 Energy Loss .......................................................................................... 33 Proposed Methodology ..................................................................................... 33 4.4.1 Approach 1 (A1) ................................................................................... 33 4.4.2 Approach 2 (A2) ................................................................................... 35 4.4.3 Approach 3 (A3) ................................................................................... 37 4.4.4 Computational Procedure ..................................................................... 39 4.5 Exhaustive Load Flow Solution........................................................................ 42 4.6 Case Study......................................................................................................... 42 4.6.1 Test System........................................................................................... 42 xiv 4.6.2 4.7 5 Summary ........................................................................................................... 54 Wind and Biomass Integration for Energy Loss Reduction 56 5.1 Introduction....................................................................................................... 56 5.2 Load and Renewable DG Modelling ................................................................ 57 5.2.1 Load Modelling .................................................................................... 57 5.2.2 Renewable DG Modelling .................................................................... 57 5.3 Problem Formulation ........................................................................................ 58 5.4 Proposed Methodology ..................................................................................... 59 5.5 5.6 6 Numerical Results................................................................................. 42 5.4.1 Expression for Sizing DG at Predefined Power Factor ........................ 59 5.4.2 Proposed Expressions for Sizing DG at Optimal Power Factor ........... 60 5.4.3 Computational Procedure ..................................................................... 61 Case Study......................................................................................................... 65 5.5.1 Test System........................................................................................... 65 5.5.2 DG Placement without Considering Power Factor Limit..................... 66 5.5.3 Biomass versus Wind ........................................................................... 70 5.5.4 Voltage Profiles .................................................................................... 70 5.5.5 Power Factor Impact on Energy Loss................................................... 71 Summary ........................................................................................................... 73 Multi-Objective PV Integration 74 6.1 Introduction....................................................................................................... 74 6.2 Load and Solar PV Modelling .......................................................................... 75 6.2.1 Load Modelling .................................................................................... 75 6.2.2 Solar PV Modelling .............................................................................. 75 6.2.3 Combined Generation-Load Model ...................................................... 78 xv 6.3 6.4 6.5 6.6 7 Problem Formulation ........................................................................................ 78 6.3.1 Impact Indices....................................................................................... 78 6.3.2 Multiobjective Index............................................................................. 81 Proposed Analytical Approach ......................................................................... 83 6.4.1 Sizing PV .............................................................................................. 83 6.4.2 Computational Procedure ..................................................................... 85 Case Study......................................................................................................... 86 6.5.1 Test Systems ......................................................................................... 86 6.5.2 Location Selection ................................................................................ 88 6.5.3 Sizing with Respect to Indices.............................................................. 91 6.5.4 PV Penetration and Energy Losses....................................................... 93 Summary ........................................................................................................... 95 PV and BES Integration for Energy Loss and Voltage Stability 96 7.1 Introduction....................................................................................................... 96 7.2 Load and Generation Modelling ....................................................................... 97 7.3 7.4 7.2.1 Load Modelling .................................................................................... 97 7.2.2 Nondispatchable PV Modelling............................................................ 97 7.2.3 Dispatchable BES Modelling ............................................................... 98 Problem Formulation ........................................................................................ 98 7.3.1 Conceptual Design................................................................................ 98 7.3.2 Impact Indices..................................................................................... 100 7.3.3 Multiobjective Index........................................................................... 101 7.3.4 Energy Loss and Voltage Stability ..................................................... 102 Proposed Methodology ................................................................................... 104 7.4.1 Proposed Analytical Expressions ....................................................... 104 xvi 7.4.2 7.5 7.6 8 Case Study....................................................................................................... 108 7.5.1 Test System......................................................................................... 108 7.5.2 Numerical Results............................................................................... 109 Summary ......................................................................................................... 116 Benefit and Cost Analyses for Biomass Integration 117 8.1 Introduction..................................................................................................... 117 8.2 Load and DG Modelling ................................................................................. 118 8.3 8.4 8.5 8.6 9 Self-Correction Algorithm.................................................................. 106 8.2.1 Load Modelling .................................................................................. 118 8.2.2 DG Modelling..................................................................................... 119 Problem Formulation ...................................................................................... 119 8.3.1 Impact Indices..................................................................................... 119 8.3.2 Multiobjective Index........................................................................... 120 8.3.3 Technical Constraints ......................................................................... 121 8.3.4 Energy Loss and Voltage Stability ..................................................... 121 8.3.5 Benefit and Cost Analysis .................................................................. 122 Proposed Methodology ................................................................................... 124 8.4.1 Optimal Power Factor......................................................................... 124 8.4.2 Computational Procedure ................................................................... 127 Case Study....................................................................................................... 127 8.5.1 Test System......................................................................................... 127 8.5.2 Assumptions and Constraints ............................................................. 128 8.5.3 Numerical Results............................................................................... 129 Summary ......................................................................................................... 137 Conclusions 138 xvii 9.1 Summary ......................................................................................................... 138 9.2 Contributions................................................................................................... 141 9.3 Future Research............................................................................................... 142 Bibliography 143 Appendix A 155 Appendix B 160 xviii LIST OF FIGURES 2.1 Overall DG benefits...................................................................................................... 7 3.1 The 33-bus test distribution system............................................................................ 23 3.2 The 69-bus test distribution system (one feeder). ...................................................... 23 3.3 The 69-bus test distribution system (four feeders). .................................................... 24 4.1 Normalized daily load demand curve......................................................................... 27 4.2 Normalized daily wind and PV output curves............................................................ 28 4.3 Impact of the size and power factor of a DG unit on system active power loss. ....... 32 4.4 Daily curves for (a) demand and (b) system power losses without a DG unit........... 43 4.5 Daily curves at bus 61: (a) dispatchable biomass DG output and (b) system power losses with a dispatchable biomass DG unit.................................................... 45 4.6 Daily curves at bus 61: (a) nondispatchable biomass DG output and (b) system power losses with a nondispatchable biomass DG unit.............................................. 47 4.7 Daily curves at bus 61: (a) wind DG output and (b) system power losses with a wind DG unit. ............................................................................................................. 48 4.8 Daily curves at bus 61: (a) PV DG output and (b) system power losses with a PV DG unit. ................................................................................................................ 49 4.9 Maximum and actual penetration for scenarios 2-5. .................................................. 51 4.10 Annual energy loss reduction for scenarios 2-5. ........................................................ 51 4.11 Voltage profiles at extreme periods for scenarios 1-5................................................ 51 4.12 DG placement with different power factors for scenarios 2-3. .................................. 53 4.13 DG placement with different power factors for scenarios 4-5. .................................. 54 5.1 Normalized hourly load demand curve. ..................................................................... 57 5.2 Normalized hourly wind output curve........................................................................ 58 5.3 Hourly optimal generation curve of biomass DG unit. .............................................. 62 5.4 Hourly optimal generation curve of nondispatchable wind DG unit. ........................ 64 5.5 Hourly optimal generation curve of wind-biomass DG mix. ..................................... 65 5.6 Hourly load demand and power loss curves (scenario 1)........................................... 67 xix 5.7 Hourly optimal generation curve of biomass DG units (scenario 2).......................... 67 5.8 Hourly optimal generation curve of wind DG units (scenario 3). .............................. 68 5.9 Hourly optimal generation curve of wind-biomass DG mix (scenario 4). ................. 68 5.10 Hourly power loss curve in scenarios 1-4. ................................................................. 68 5.11 Hourly percentage power loss reduction in scenarios 2-4.......................................... 70 5.12 Voltage profile at extreme periods (period 59) for scenarios 1-4. ............................. 71 5.13 Impact of the power factor of DG units on energy loss reduction. ............................ 73 6.1 Normalized daily demand curve for various customers. ............................................ 75 6.2 PDF for solar irradiance at hours 8, 12 and 16........................................................... 77 6.3 Expected output of a PV module at hours 8, 12 and 16. ............................................ 77 6.4 A radial distribution system: (a) without PV and (b) with PV. .................................. 79 6.5 The 69-bus test distribution system............................................................................ 87 6.6 The 33-bus test distribution system............................................................................ 87 6.7 Expected PV output for hours: (a) 6-10, (b) 11-15 and (c) 16-19. ............................. 89 6.8 Normalized daily expected PV output........................................................................ 90 6.9 PV size with respect to IMO at various locations at average load level for the industrial load model: (a) 69-bus system and (b) 33-bus system. .............................. 90 6.10 Hourly expected PV outputs at bus 61 for the 69-bus system for different timevarying load models. .................................................................................................. 91 6.11 Hourly expected IMO curves for the 69-bus system with a PV at bus 61 for different time-varying load models. ........................................................................... 92 6.12 PV size and indices for the 69-bus system with PV at bus 61 for different timevarying load models. .................................................................................................. 92 6.13 PV penetration levels in the 69- and 33-bus systems. ................................................ 94 7.1 Conceptual model of grid-connected PV-BES system: (a) Connection diagram and (b) Charging and discharging characteristics of BES and PV output.................. 99 7.2 Hybrid PV-BES system impact on maximum loadability and voltage stability margin....................................................................................................................... 103 7.3 Daily PV-BES outputs, power factor and index curves for scenario 1: (a) PVBES outputs, (b) Power factor of PV-BES units, (c) Indices with three PV-BES units. ......................................................................................................................... 110 xx 7.4 Daily charging and discharging curves of BES unit at bus 12 for scenario 1. ......... 112 7.5 PV-BES impact on energy loss. ............................................................................... 115 7.6 PV-BES impact on maximum loadability and voltage stability margin. ................. 115 7.7 Voltage profiles at extreme periods for all scenarios. .............................................. 115 8.1 Nominalised Load duration curve. ........................................................................... 118 8.2 Single line diagram of the 69-bus test distribution system with DG units............... 130 8.3 Indices (ILP, ILQ and IMO) for the system with various numbers of DG units over planning horizon............................................................................................... 131 8.4 Losses of the system with and without DG units over planning horizon................. 132 8.5 Voltage stability margin curves for all scenarios over planning horizon................. 133 8.6 NPV at various average DG utilization factors for different scenerios over planning horizon....................................................................................................... 136 8.7 Percentage ratio of the total demand plus loss to the thermal transformer limit over planning horizon............................................................................................... 136 xxi LIST OF TABLES 3.1 Load types and exponents for voltage-dependent loads............................................. 19 4.1 Dispatchable biomass DG placement ......................................................................... 45 4.2 Nondispatchable biomass DG placement................................................................... 47 4.3 Nondispatchable wind DG placement ........................................................................ 48 4.4 Nondispatchable PV DG placement ........................................................................... 49 5.1 Optimal DG placement without considering power factor limit ................................ 69 5.2 Optimal DG placement without considering power factor limit ................................ 69 5.3 Optimal DG placement considering power factor limit ............................................. 72 5.4 Optimal DG placement considering power factor limit ............................................. 72 6.1 PV allocation in the 69- and 33-Bus Systems ............................................................ 93 6.2 Energy loss reduction over a day for 69 and 33-Bus Systems ................................... 94 7.1 PV-BES placement with optimal lagging and unity power factors.......................... 111 7.2 Sizing PV and BES units at optimal lagging power factor (Scenario 1).................. 113 7.3 Sizing PV and BES units at unity power factor (Scenario 2)................................... 113 7.4 Energy loss and voltage stability.............................................................................. 116 8.1 Economic input data. ................................................................................................ 128 8.2 Location, size and power factor of DG units............................................................ 130 8.3 Energy loss and voltage stability over planning horizon.......................................... 133 8.4 Analysis of the present value benefit and cost for different scenarios over planning horizon....................................................................................................... 135 8.5 Comparison of different scenarios over planning horizon. ...................................... 135 A.1 System data of 33-bus test distribution system ........................................................ 155 A.2 System data of 69-bus test distribution system (one feeder).................................... 156 A.3 System data of 69-bus test distribution system (four feeder) ................................... 158 xxii B.1 Mean and Standard Deviation of Solar Irradiance ................................................... 160 B.2 Characteristics of the PV module ............................................................................. 160 xxiii ABBREVIATIONS ABC Artificial Bee Colony algorithm A1, A2, A3 Analytical approach 1, 2 and 3, respectively BES Battery Energy Storage CP Critical Point CPF Continuous Power Flow CO2 Carbon dioxide DFIG Doubly-Fed Induction Generator DG Distributed Generation ELF Exhaustive Load Flow GA Genetic Algorithm GSA Gravitational Search Algorithm HSA Harmony Search Algorithm IGA Immune-Genetic Algorithm MTLBO Modified Teaching-Learning Based Optimization NOx Nitrogen oxide OPF Optimal Power Flow PDF Probability Density Function PSO Particle Swarm Optimization PV Photovoltaic PV-BES PV and BES system SA Simulated Annealing SCA Self-Correction Algorithm SO2 Sulphur dioxide VSM Voltage Stability Margin xxiv NOMENCLATURE AEy Actual annual emission of the system with DG units (TonCO2) ALossy Actual annual energy loss of the system with DG units (MWh) AIMO Average multi-objective index AVSM Average voltage stability margin of the system B Present value benefit over a planning horizon ($) BCR Benefit and cost ratio C Present value cost over a planning horizon ($) CDG Capital cost of DG ($/kW) CEy Cost of each ton of generated CO2 ($/TonCO2) CF Capacity factor CLossy Loss value ($/MWh) d Discount rate E BESk Total energy stored in the BES unit at bus k unit E PV Amount of PV module generated energy EIy Emission incentive ($/year) Eloss Total annual system energy loss, MWh GRID E PVk Amount of PV energy delivering to the grid at bus k E( PV + BES ) Energy amount of a combination of PV and BES units ILP , ILQ Active and reactive power loss indices, respectively IMO Multi-objective index I ai Active current of branch i I ak Active current of DG unit at bus k Ii Current magnitude of branch i, I i = I ai + I ri I ri Reactive current of branch i I rk Reactive current of DG unit at bus k IRR Internal rate of return IVD Voltage deviation index LF Load factor 2 xxv 2 LIy Loss incentive ($/year) n Number of branches N Number of buses ND Network deferral benefit ($/kW) NPV Net present value Ny Planning horizon (years) OMy Annual operation, maintenance and fuel costs ($/year) opf DGi Optimal power factor of DG unit at bus i pf DGi Power factor of DG unit at bus i CH DISCH PBESk and PBESk Charge and discharge power of the BES unit at bus k, respectively Pbi , Qbi Active and reactive power flow through branch i respectively PDGi , QDGi , S DGi Active, reactive and apparent power sizes of DG unit, respectively at bus i PDi , QDi Active and reactive power of load, respectively at bus i Pi , Qi Net active and reactive power injections, respectively at bus i Pk , Qk Active and reactive power of the combination of PV and BES units at bus k PL , QL Total system active and reactive power losses without DG unit (MW), respectively PLDG , QLDG Total system active and reactive power losses with DG unit (MW), respectively unit PPV Maximum output of a PV module unit p.u. demand(t) Demand in p.u. at period t p.u. DG ouput(t) DG output in p.u. at period t Ri , X i Resistance and reactance of branch i Ry Annual energy sales ($/year) TEy Annual emission target level of the system without DG (TonCO2) TLossy Annual energy loss target level of the system without DG (MWh) VD Voltage deviation Vi , δ i Voltage and angle, respectively at bus i xxvi Z ij ijth element of impedance matrix ( Z ij = rij + jxij ) α ij , βij Loss coefficients δ Growth rate of demand a year ∆AVSM An increase in the average voltage stability margin ∆E Energy loss reduction ∆Ploss System loss reduction due to DG injection, kW ∆t Time duration, hour λmax Maximum loading ρ Probability of the solar irradiance η BES Round trip efficiency ( η BES = η c × η d ) ηc , η d Charge and discharge efficiencies of the BES unit xxvii CHAPTER 1 INTRODUCTION 1.1 Background Distributed Generation (DG) based on renewable resources such as solar, wind, ocean, hydro, biomass and geothermal heat are considered as green power because of the negligible impact on greenhouse gas emissions. Such sources have emerged as an alternative energy solution to mitigate the dependence on fossil fuels since the mid-1970s after the first oil crisis [1]. However, during this period, due to its high energy production costs along with utility and government disincentives, renewable DG remained relatively dormant until the mid-2000s [2]. There has been a renewed interest in the deployment of renewable DG since the mid2000s when the issue of global warming came to the forefront of concerns by many parts of the world [2]. In addition, the technical and economical benefits, government incentives, and advancement in the technologies have lead to a significantly increased interest in the usage of renewable DG worldwide. For example, as of 2010, renewable energy supplied an approximately 16.7% of the global energy consumption [3]. Among all renewable technologies, solar photovoltaic (PV) grew the fastest with a yearly increase of 58% worldwide during the period of late 2006 to 2011 and achieved just over 102 GW of the global installed capacity in 2012 [4]. It is expected that this figure could increase to more than 423 GW by 2017. This resource is popularly used in Germany and Italy. Wind energy is growing globally at a yearly rate of 30%, and was just more than 282 GW of the global capacity at the end of 2012 [3]. Such a resource is popularly used in Europe, Asia, and the United States. 1 CHAPTER 1. INTRODUCTION 2 From the utilities’ perspective, intermittent renewable DG units (e.g., wind and solar) located close to loads in distribution systems can create several economical, technical and environmental benefits. However, the high penetration of such resources, together with demand variations has introduced many challenges to distribution networks such as power fluctuations, high losses, voltage rise and low voltage stability [5]. Consequently, in the last decade, the grid codes in many countries such as the United State, Germany, the United Kingdom, Denmark, Australia and Spain have been modified to accommodate such resources [6]. This modification has also aimed at modernizing the electric power grid to satisfy the demand for higher energy efficiency, reliability and security of the system. Meanwhile, the concept of the smart grid has been introduced as an important part of this modification to facilitate high penetration of renewable DG [7]. The smart grid is a complicated infrastructure as a combination of power systems, telecommunication communication and information technology. As an integral part of the smart grid, a smart integration approach is presented in this thesis. The main idea behind the smart integration is to accommodate and operate renewable DG and associated Battery Energy Storage (BES) units in distribution networks strategically by considering various technical, economical and environmental issues. 1.2 Research Objectives The goal of the thesis is to develop methodologies for strategically planning and operating renewable DG units along with an efficient usage of BES sources in distribution networks. This thesis also aims to show how to operate renewable DG units behind the idea of the optimal power factor to maximize technical and economical benefits. The main objectives of the research can be highlighted as follows: 1. Develop analytical approaches to locate and size different types of single renewable DG units with optimal power factor operation for minimising energy losses while considering the time-varying characteristics of demand and generation. 2. Develop a methodology to locate and size multiple dispatchable biomass and nondispatchable wind units for minimising energy losses. 3. Develop a methodology to determine intermittent PV penetration for distribution systems with time-varying load models and probabilistic generation with objectives of reducing active and reactive power losses and voltage deviation. CHAPTER 1. INTRODUCTION 3 4. Propose a methodology for sizing hybrid PV and BES units with optimal power dispatch for reducing energy losses and enhancing voltage stability. 5. Propose a comprehensive framework for biomass DG investment planning with optimal power factor operation which considers all economical, technical and environmental aspects over a given planning horizon. 1.3 Thesis Outline This thesis is organised as follows: Chapter 2 provides background knowledge about DG and BES technologies, which are needed to better comprehend this thesis. This chapter also includes an overall literature review on current approaches for DG and BES integration in distribution systems. Chapter 3 describes the modelling of loads and renewable generation used in the next chapters. The software tools and test systems used throughout this research is also introduced in this chapter. Chapter 4 introduces the idea of optimal DG power factor operation. This introduction provides a foundation for developing the methodologies with different applications presented in the next chapters. Three alternative analytical approaches are then presented in this chapter to accommodate a single renewable DG unit for minimising energy losses while considering the time-varying characteristics of demand and generation. Chapter 5 presents a methodology to integrate multiple nondispatchable and dispatchable renewable DG units for minimising energy losses. Chapter 6 presents a methodology to determine the penetration of PV in distribution systems with time-varying load models while considering the probabilistic characteristic of generation. Chapter 7 discusses the integration of hybrid PV and BES units with optimal power dispatch for reducing energy losses and enhancing static voltage stability. Chapter 8 reports a comprehensive framework for biomass DG planning that considers economical, technical and environmental aspects. Finally, Chapter 9 concludes with a summary of the research in this thesis. The contributions and directions for further research are also presented in this chapter. CHAPTER 2 LITERATURE REVIEW 2.1 Introduction This chapter provides an overview of DG and BES technologies. Secondly, it systematically reports a comprehensive literature review on different issues of DG integration in distribution systems from the perspective of utilities, covering energy losses, voltage stability, voltage profiles, network investment deferral, environment, and energy sales. Thirdly, the issues of renewable DG integration with BES units in distribution systems are thoroughly reviewed in this chapter. Finally, major limitations and gaps drawn from the survey are highlighted in this chapter. 2.2 Technologies of DG and BES DG can be defined as “small-scale generating units located close to the loads that are being served” [8]. It is possible to classify DG technologies into two broad categories: nonrenewable and renewable energy resources [9]. The former comprises reciprocating engines, combustion gas turbines, micro-turbines, fuel cells, and micro Combined Heat and Power (CHP) plants. The latter includes biomass, wind, solar PV, geothermal and tide power plants. The next subsections provide a brief overview of the technologies of solar PV, wind and biomass to be considered in this research. 2.2.1 Solar Photovoltaic Solar PV technologies use some of the properties of semiconductors to directly convert 4 CHAPTER 2. LITERATURE REVIEW 5 sunlight into electricity [1]. The advantages are that these technologies are characterized by zero emissions, silent operation, and a long life service. They also require low maintenance and no fuel costs. In addition, solar energy is redundant and inexhaustible. However, it is weather-dependent, intermittent and unavailable during the night. Given a high PV penetration level together with demand variations, power distribution systems would experience power fluctuations along with unexpected voltage rise, high losses and low voltage stability. Another drawback is that PV technologies require a high-capital investment cost. 2.2.2 Wind Turbines Wind turbines are devices that convert kinetic energy from the wind into electricity. They can be classified into two types: vertical axis wind turbines and horizontal axis wind turbines [1]. Like solar PV, wind turbines are emissions free and require no fuel costs. Wind energy is also redundant and inexhaustible. However, the main challenges are that wind turbines have an unpredictable and intermittent output, and a high-capital investment cost. In addition, the simultaneous occurrence of excessive wind generation and low demand could lead to the possibility of encountering voltage rise, high losses and low voltage stability in power distribution systems. 2.2.3 Biomass Gas Turbines Biomass power plants can generate electricity using a steam cycle where biomass raw materials such as waste are converted into steam in a boiler [1]. The resulting steam is then used to spin a turbine which is connected to a generator. Alternatively, biomass materials can be converted to biogas. This biogas can be cleaned and upgraded to natural gas standards when it becomes bio methane. The biogas can be used in a gas turbine, pistondriven engine or fuel cells to generate electricity. The advantage is that as a renewable energy source, biomass-based power plants produce low emission. As reported in [10], gas turbines have smaller sizes than any other source of rotating power and provide higher reliability than reciprocating engines. They also have superior response to load variations and excellent steady state frequency regulation when compared to steam turbines or reciprocating engines. In addition, gas turbines require lower maintenance and produce lower emissions than reciprocating engines. CHAPTER 2. LITERATURE REVIEW 6 2.2.4 Battery Energy Storage In addition to the wind, solar PV and biomass presented above, energy storage is also considered in this thesis. This source is becoming a crucial component in the distribution system, especially in the smart grid, to enhance the reliability, efficiency and sustainability. More importantly, energy storage can support to accommodate a high penetration level of intermittent renewable DG. Energy storage is being developed in a variety of solutions such as batteries, flywheels, ultracapacitors and superconducting energy storage systems. Among them, Battery Energy Storage (BES) has recently emerged as one of the most promising near-term storage technologies for power applications [11]. There are a number of leading battery technologies such as lead-acid, nickel cadmium, nickel-metal hydride and lithium iron. Among them, the lead-acid battery is the oldest, most mature technology, and low investment costs [12]. Another advantage is that it can be designed for bulk energy storage or for rapid charge and discharge; however, it is limited in terms of low energy efficiency and short cycle life [11]. The rest of the battery technologies also present promise for energy storage applications. These technologies have higher energy density capabilities than lead-acid batteries, but they are currently not cost-effective for higher power applications [11]. 2.3 Renewable DG Integration From the perspective of utilities, DG units can bring multiple technical benefits to distribution networks such as loss reduction, voltage profile improvement, voltage stability, network upgrade deferral and reliability while supplying energy sales as a primary task. These can be classified into three major categories: economic, technical and environmental benefits, as illustrated in Figure 2.1. In addition, DG units can participate into the competitive market to provide ancillary services such as spinning reserve, voltage regulation, reactive power support and frequency control [13-15]. However, the inappropriate planning and operations of these resources may lead to high losses, voltage rise and low system stability as a result of reverse power flow [5, 16]. Consequently, it is necessary to develop proper methodologies to accommodate renewable DG resources. DG planning considering various technical, economical and environmental issues has CHAPTER 2. LITERATURE REVIEW 7 been discussed considerably over the last fifty-years [17]. The aim of researches is to bring a wide variety of benefits shown in Figure 2.1 to distribution systems while satisfying technical constraints such as penetration levels, bus voltages and feeder thermal capacity. Some of the relevant methodologies found in the literature are reported below. DG integration Loss reduction Voltage stability Technical benefit Environmental benefit Economical benefit Voltage profile Reliability Network upgrade deferral Figure 2.1. Overall DG benefits. 2.3.1 Technical Benefits Energy Losses The distribution system is well-known for its high R/X ratio and significant voltage drops that could cause substantial power losses along the feeders. It is added that the distribution loss is normally higher than the transmission loss. For instance, a study in [18] has showed that an American Electric Power’s distribution system incurred a loss in the range of 6-8% when compared to the transmission loss of 2.5-7.5%. This figure would be higher in radial distribution systems with a high R/X ratio. Consequently, distribution loss reduction has been one of the greatest challenges to power distribution utilities worldwide. It is necessary to study the loss reduction at the distribution system level. The system loss reduction at the distribution system level could be one of the major benefits due to its impact on the utilities’ revenue. In addition, as a key consideration for CHAPTER 2. LITERATURE REVIEW 8 DG planning, the loss reduction can lead to positive impacts on system capacity release, voltage profiles and voltage stability [19]. DG planning methods for minimising losses can be classified into two groups, namely power and energy losses. The optimal DG placement and sizing issues for minimising power losses in distribution networks have attracted great attention in recent years. Most traditional methods have assumed that DG units are dispatchable and placed at the peak load [20]. Typical examples for such researches are analytical methods [21-25], numerical approaches [19, 26, 27] and a wide range of heuristic algorithms such as Simulated Annealing (SA) [28], Genetic Algorithm (GA) [29], Particle Swarm Optimization (PSO) [30, 31], Artificial Bee Colony (ABC) algorithm [32], Modified Teaching-Learning Based Optimization (MTLBO) [33], and Harmony Search Algorithm (HSA) [34]. However, such traditional methods may not address a practical case of the time-varying characteristics of demand and renewable generation (e.g., nondispatchable wind output) as the optimum DG size at the peak demand may not remain at other loading levels. Hence, the energy loss minimization may not be optimal. Recently, there are two major approaches based on time-series and probabilistic models found in the literature to estimate energy losses in the presence of DG, especially intermittent renewable resources. For the first model, few studies have presented renewable DG integration for minimising energy losses that considers the time-varying characteristics of demand and generation. For example, wind DG units were sized using a GA-based approach [35] and an Optimal Power Flow (OPF)-based method [26], but the locations were not considered in these works. For the second model, a probabilistic planning method was introduced to accommodate renewable resources mix (i.e. biomass, wind and solar) while considering the time-varying demand and probabilistic generation [27]. The loads were assumed to follow the hourly load profile of IEEE-RTS system [36]. The probabilistic nature of wind speed and solar irradiance was respectively described using the Weibull and Beta Probability Density Function (PDF) models [37, 38]. Biomass DG units were assumed to have constant rated outputs without associated uncertainties. A combined generation-load model was proposed to incorporate the DG output powers as multistate variables in the problem planning. In addition, a planning method that considers the probability of both demand and generation for locating and sizing wind and PV-based DG units were also reported in [19, 39]. In general, the time-series or probabilistic CHAPTER 2. LITERATURE REVIEW 9 planning method can provide a more accurate result than the traditional planning approach presented earlier. In addition, the relevant literature review shows that most of the existing studies have assumed that DG units operate at pre-specified power factor, normally unity power factor under the current standard IEEE 1547. In such researches, only the location and size have been considered, while the optimal power factor for each DG unit that would be a crucial part for minimising energy losses has been neglected. Depending on the characteristics of loads served, each DG unit that can deliver both active and reactive power at optimal power factor may have positive impacts on energy loss reduction. Voltage Stability The voltage stability at the transmission system level has been studied considerably over the last thirty-years [40]. Voltage instability normally occurs under heavily loaded system conditions together with deficient reactive power support and this may lead to voltage collapse. At the distribution system level, the voltage instability has been identified for the last decade. For instance, a voltage instability problem in a power distribution network that was widespread to a corresponding power transmission network caused a major blackout in the S/SE Brazilian system in 1997 [41]. Another study has reported that under critical loading conditions in a certain industrial area, the distribution network experienced voltage collapse [42]. In recent years, due to high intermittent renewable penetration, sharply increased loads and the demand for higher system security, it is necessary to study the voltage stability at the distribution system level. The DG placement and sizing of DG units for enhancing voltage stability in the distribution system are a new concept, but this topic has attracted the interest of some recent research efforts. Like the DG allocation for minimising power losses, most traditional methods for enhancing voltage stability have assumed that DG units are dispatchable and placed at the peak load. Typical examples of such studies are iterative techniques based on Continuous Power Flow (CPF) [43, 44], a hybrid of model analysis and CPF [45], a power stability index-based method [46], a numerical approach [47] and heuristic algorithms such as SA [28] and PSO [48-50]. Although well-suited to accommodate dispatchable DG units such as gas turbines, the approaches presented above may not solve a practical scenario that considers the time-characteristics of the varying demand and nondispatchable renewable DG output. CHAPTER 2. LITERATURE REVIEW 10 Recently, a probabilistic planning approach was successfully developed for renewable DG allocation (i.e., biomass, wind and solar) that considers the varying-time demand and probabilistic generation [51]. This model was presented in the previous study in [27] to accommodate renewable DG units for minimising energy losses. In [51], a sensitivity technique was used for searching the candidate buses to effectively reduce the search space. However, studies [22, 47, 52] indicated that sensitivity techniques may not be effective to capture the candidate buses for DG installation on radial distribution feeders with goals of minimising losses and enhancing voltage stability. Using these techniques would also potentially limit DG penetration levels in the feeders since the most sensitive buses are normally found at the end of feeders as reported in [25, 34, 43-45, 51, 52]. Another limitation of the study in [51] as well as [28, 43-50] is that the optimal power factor for each DG unit was not considered. Depending on the nature of loads served, DG operation at optimal power factor may have positive impacts on the voltage stability. Voltage Profiles The voltage profile issue of distribution systems, which is relevant to power quality, is normally less important than the energy loss from the viewpoint of utilities. However, in recent years, it appears that due to high intermittent renewable DG penetration, there has been an increasing interest in the voltage profile issue at the distribution system level [53]. The voltage profile is normally considered together with technical respects and system constraints, which can be formulated as a multiobjective, for determining the location and size of DG units. For example, exhaustive load flow analyses were adopted to address multiobjective index [54, 55]. This index is defined as a combination of impact indices by assigning a weight for each one. These impact indices are related to active and reactive power losses, voltage drops, conductor capacity and short-circuit currents. Similarly, a study in [56] proposed a hybrid of PSO and Gravitational Search Algorithm (PSO-GSA). The aim is to minimize the multiobjective index, which is a combination of different indices related to power losses, voltage profiles, MVA capacity, emissions, and the number of DG units. Overall, a constant load model was assumed in the works presented above. However, the importance of the voltage-dependent load models also needs to be examined. Recently, few studies [29, 57, 58] indicated that the voltage-dependent load models (i.e., industrial, residential and commercial) considerably affect the DG penetration planning CHAPTER 2. LITERATURE REVIEW 11 when compared to the constant load model. The research in [29] presented a multiobjective optimization planning using GA to allocate a DG unit in distribution networks with different load models. The multiobjective index is a combination of various impact indices related to active and reactive power losses, system MVA capacity and voltage profiles. It was shown that DG allocation with different types load models can produce dissimilar outcomes in terms of locations and sizes. Similarly, a multiobjective planning approach was developed using PSO for multiple DG allocation in distribution networks with different load models [58]. The multiobjective index is a combination of different indices related to active and reactive power losses, voltage profiles, MVA capacity and short circuit levels. However, the above works assumed that DG units are dispatchable and allocated at the peak load demand. Although a research in [59] indicated the effect of timevarying load models on energy loss assessment in a distribution system with wind DG units, the optimal location and size were not addressed. Another study in [60] reported that time-varying voltage-dependent load models have a critical impact on the location and size of DG. The benefit is the energy sales from DG, while the costs are related to DG investment, operation and imported energy. However, nondispatchable renewable DG that considers time-varying load models and probabilistic generation was not reported in this work. Network Upgrade Deferral The network upgrade deferral is the ability to defer the required investment on reinforcing feeders and transformers due to DG connection. In the last decade, it has been reported that the network upgrade deferral is an attractive option for DG planning to meet load growth [61-63]. The study in [61] showed that depending on technologies adopted, DG units have diverse impacts on the network deferral. For example, due to their intermittency, wind units have the ability to release the overloads of power networks less than CHP units. In addition, the report in [62] indicated that DG operation at lagging power factor, which delivers both active and reactive power, obtains a higher benefit than DG generation at unity and leading power factor. However, the importance of the location and size of DG units needs to be considered. The issues of locating and sizing DG units for deferring the distribution network investment are normally evaluated with other associated aspects such as technical and CHAPTER 2. LITERATURE REVIEW 12 economical benefits and system constraints. For example, DG placement for maximizing the benefits of network upgrade deferral and loss reduction were reported using different approaches: hybrid GA-OPF [64], ordinal optimization [65] and Immune-Genetic Algorithm (IGA) [66]. Moreover, an OPF-based method was proposed for distribution system planning in the presence of DG over a given planning horizon [67]. The objective is to minimize the costs related to feeder reinforcement, operation and energy losses. Similarly, a multiyear multiperiod OPF-based method was successfully developed for DG planning considering the network investment deferral [68, 69]. Another study in [70] developed a GA-based multiobjective framework to locate and size DG units to find the best compromise between the network upgrade deferral and the costs related to energy losses, unserved energy, and imported energy. In addition, a recent study in [71] proposed a GA-based approach to place and size renewable DG units (i.e., biomass, wind and solar) for maximizing the benefits from deferring network investments and reducing energy losses and interruption costs. The probability of renewable energy and the variability of demand were also incorporated in this approach. In addition to the benefits presented above, reliability is another technical benefit that DG can bring to distribution systems. However, it was not considered in this thesis. 2.3.2 Environmental Benefits The global climate change agreements such as Kyoto Protocol aim at reducing greenhouse gas emissions. Three main components to emissions from electricity production are namely carbon dioxide (CO2), nitrogen oxide (NOX) and sulphur dioxide (SO2). These components are emitted from the centralized power plants due to burning fossil fuels. Emissions can be lowered by increasing the amount of clean and renewable energy DG resources in power systems, thereby reducing the usage of electricity generated from centralized power plants [72]. For example, a British study estimated that CHP-based power plants reduced an estimated 41% of CO2 emission in 1999 [17]. Similarly, a report on the Danish power system showed that the usage of DG contributed an emission reduction of 30% during the period of 1998-2001. However, DG technologies adopted may have a significant impact on the amount of emission reduction. For example, renewable DG technologies such as biomass, wind and solar PV produce low or zero emissions when compared to nonrenewable DG technologies, which consume fossil fuels, such as fuel cells, natural gas CHAPTER 2. LITERATURE REVIEW 13 turbine engines and micro-turbines. It is clear that increasing DG penetration in distribution systems can reduce emissions. However, this could be limited by technical and economical aspects and system constraints. The literature shows that different approaches have been developed for locating and sizing DG units for maximizing emission reduction associated with technical and economical benefits while satisfying system constraints. For example, a honey bee mating optimization approach was proposed to reduce the emission while minimising the DG installation and operation costs, voltage deviation and energy loss [73]. Similarly, a multiobjective planning model based on an IGA approach was presented to reduce the emission while minimising the costs related to DG installation and operation, network reinforcement and imported electricity [74]. In a similar study [75], a multiobjective planning model was developed to make a trade-off between emission and cost reductions. The cost is related to DG investment and operation, energy loss and imported energy. However, the limitation of studies [73-75] is that DG units were assumed to operate as a dispatchable source without associated uncertainties. In contrast to these works, a GAbased multiobjective model was developed for wind DG planning that considers the uncertainty of generation [76]. The objective is to improve the reliability while minimising the costs related to DG investment and operation, and emission penalty. 2.3.3 Economical Benefits In addition to the technical and environmental benefits from DG units thoroughly discussed above, it is necessary to consider a comprehensive work through their cost and benefit analysis including the energy sales. The monetary values converted from the technical and environmental benefits from DG units are also included in the analysis. The literature review presented in the previous subsections shows that considerable works have presented DG planning. However, most of them have considered the cost analysis only. In addition, a study in [77] presented an approach to determine the location and number of DG units. The objective is to minimize the fuel cost and power losses. A planning framework was also developed for PV integration by reducing the investment, operation and imported energy costs [78]. Moreover, heuristic approaches were proposed to locate and size DG units with an objective of minimising the costs of investment, CHAPTER 2. LITERATURE REVIEW 14 operation, imported energy and energy losses [79, 80]. With the same objective, a research in [81] presented a DG planning approach using PSO. However, the importance of the benefit of DG units also needs to be considered in the analysis. A study in [82] presented a dynamic programming algorithm to place and size DG units through the cost and benefit analysis. The total cost is a sum of DG investment, operation and maintenance costs, while the total benefit is a sum of the benefits arising from reducing the power loss, imported energy and unserved energy. However, it seems that inclusion of the DG energy sales in the analysis may provide a more precise result. Few studies have reported comprehensive frameworks for DG investemnt planning on the basis of the cost and benefit analysis including the energy sales from DG. For instance, a study in [8] presented a heuristic approach to locate and size DG units by maximizing the utility’s profit as a function of the benefit and cost. The benefit is the energy sales, whereas the costs are related to DG investment, operation, imported energy, unserved energy, and energy losses. A research in [83] developed a GA-based cost and benefit method to accommodate DG units. The benefit is the energy sales, while the cost includes DG investment and energy loss costs. In addition, a heuristic approach was introduced to locate and size DG units through the cost and benefit analysis [84]. The benefit is the energy sales, while the costs are related to DG investment and operation, substation and feeder investments, imported energy and unserved energy. In conclusion, the above review shows that numerous methodologies have developed for DG integration in distribution systems, considering different respects: technical, economical and environmental benefits. However, most of them have assumed that DG units operate at a pre-defined power factor. Depending on the nature of loads served, DG operation at optimum power factor may have positive impacts on system losses, voltage stability, and system capacity release. Moreover, a comprehensive benefit-cost study on multiple DG allocation with optimal power factor that considers the issues of energy loss and voltage stability has not been reported in the literature. In addition, the importance of time-varying voltage-dependent load models also needs to be considered in the analysis to obtain a more realistic result. CHAPTER 2. LITERATURE REVIEW 2.4 15 Renewable DG Integration with BES Unlike conventional technologies-based DG units such as reciprocating engines and gas turbines, PV sources are time and weather-dependent, intermittent and nondispatchable. Advances in dispatchable BES technologies provide an opportunity to make these nondispatchable PV sources dispatchable like conventional generators [85, 86]. Over the last fifteen-years, a hybrid PV and BES system has been designed for stand-alone applications [87-89]. In recent years, the hybrid of BES and PV system has been utilized as one of the most viable solutions in grid-connected applications to mitigate the impacts of PV intermittency, increase PV penetration and provide multiple benefits for utilities, customers and PV owners. This topic has attracted the interest of numbers of recent research efforts [85, 90-98]. A hybrid PV-BES system was developed for demand-side applications to enhance the system electrical efficiency [92, 93]. An optimal charging and discharging schedule of BES units utilized in a grid-connected PV system was presented for peak load shaving [94]. A study in [95] proposed a methodology to determine the size of BES units for power arbitrage and peak shaving used in a grid-connected PV system. Authors in [96] presented a methodology to size BES units for increasing PV penetration in a residential system with the objectives of voltage regulation and reductions in peak power and annual cost. A strategy for charging and discharging BES units was proposed for mitigating sudden changes in PV outputs and supporting evening peak load in residential systems [97]. A concept to regulate voltages in distribution systems with high PV penetration by controlling the output of customer-side BES units was reported in [90]. In this concept, a distribution utility is permitted to control the output of BES units during a specific time period in exchange for subsidizing a part of BES investment costs. BES units are sized and controlled to eliminate the power fluctuation of PV outputs [85, 98]. Finally, an optimal charging and discharging schedule of BES units on a hourly basis was developed to mitigate the intermittency of PV-based DG outputs by minimising energy losses [91]. Overall, the above review shows that considerable works have discussed the charging and discharging schedules and size of BES units utilized in grid-connected PV systems. However, most of the studies presented have assumed that the size of PV units utilized in hybrid PV-BES systems is pre-defined and the optimal power factor dispatch for each hybrid PV-BES unit over all periods is neglected as well. Depending on the characteristics of loads served, each PV-BES hybrid unit that can deliver active and CHAPTER 2. LITERATURE REVIEW 16 reactive power at optimal power factor may have positive impacts on minimising energy loss and stabilizing the bus voltages of distribution systems. 2.5 Grid Codes for DG Integration Under the recommendation of the current standard IEEE 1547, most of the DG units are normally designed to operate at unity power factor [99]. Consequently, the inadequacy of reactive power support for voltage regulation may exist in distribution networks, given a high DG penetration level. Conventional devices such as switchable capacitors, voltage regulators and tap changers are actually employed for automatic voltage regulation, but they are not fast enough to compensate for transient events [100, 101]. It is likely that the shortage of reactive power support may be an immediate concern at the distribution system level in the future. On the other hand, depending on time and weather variability, the simultaneous occurrence of excess intermittent renewable generation (i.e., wind and solar PV) and low demand would lead to loss of voltage regulation along with unexpected voltage-rise on the feeders due to reverse power flows [102]. As a fast response device, the inverter-based PV unit is allowed to inject or absorb reactive power to stabilize load voltages as per the new German grid code [103] while supplying energy as a primary task [101, 104]. Other technologies such as synchronous machines used in biomass power plants, and Doubly-Fed Induction Generators (DFIGs) or full converter synchronous machines employed in wind farms are also capable of controlling reactive power while supplying active power [105]. 2.6 Summary This chapter provided a brief overview of technologies of DG and associated BES in distribution networks. It also reported a comprehensive literature review on renewable DG integration in distribution systems. The concept and application of a hybrid PV and BES system were also reviewed in this chapter. The literature review presented in this chapter showed that traditional DG planning approaches have assumed that DG units are dispatchable and placed at the peak demand. However, such approaches may not solve a practical case of intermittent renewable DG units (e.g., wind and solar PV). Moreover, in most existing studies, DG units have been assumed to operate at pre-specified power factor under the current standard IEEE 1547, normally unity power factor. Furthermore, this CHAPTER 2. LITERATURE REVIEW 17 chapter also showed that renewable DG planning that considers time-varying load models and probabilistic generation has not been reported in the literature. In addition, a comprehensive benefit-cost study on DG allocation with optimal power factor has not been discussed in the literature. CHAPTER 3 LOAD AND GENERATION MODELLING AND TEST SYSTEMS 3.1 Introduction As discussed in Chapter 2, an accurate modelling of the time-varying load models can help in determining the penetration of renewable DG in a distribution system precisely. In addition, the generation characteristics of intermittent renewable resources: wind and solar depend on meteorological conditions (e.g., weather and temperature). In this chapter, different time-varying voltage dependent load models are first defined. The generation characteristics of renewable DG (i.e., solar PV, wind and biomass) and BES are next presented. Finally, three different distribution test systems used throughout in this study are also described. 3.2 Load Modelling The time-varying voltage-dependent load model or the time-varying load model is defined as a load model which is dependent on the time and voltage. Accordingly, the voltage dependent load model in [106] which incorporates time-varying loads at period t can be expressed as follows: np nq Pk (t ) = Pok (t ) × Vk (t ) ; Qk (t ) = Qok (t ) × Vk (t ) 18 (3.1) CHAPTER 3. LOAD AND GENERATION MODELLING AND TEST SYSTEMS 19 where Pk and Qk are respectively the active and reactive power injections at bus k, Pok and Qok are respectively the active and reactive load at bus k at nominal voltage; Vk is the voltage at bus k; np and nq are, respectively, the active and reactive load voltage exponents as given in Table 3.1 [106]. Table 3.1. Load types and exponents for voltage-dependent loads Load types 3.3 np nq Constant 0 0 Industrial 0.18 6.00 Residential 0.92 4.04 Commercial 1.51 3.40 Generation Modelling Renewable resources (i.e., solar, wind and biomass) and BES are considered in this thesis. They can be classified into two categories: dispatchable and nondispatchable generation as far as their capability of energy delivery is concerned. DG units are considered as a dispatchable source, if its output power can be controlled at a fixed output automatically, typically by varying the rate of fuel consumption. This includes generation technologies such as biomass-based gas turbines and small hydro power plants. In contrast, DG units are considered as a nondispatchable source, if its output power cannot be automatically controlled and totally depends on weather conditions (e.g., wind speed and solar irradiance). Solar PV and wind turbines are examples of such generation technologies. 3.3.1 Dispatchable Generation Biomass As discussed in Chapter 2, biogas produced from biomass raw materials is used to run gas turbines. These gas turbines are synchronous machines and can be dispatched according to the load demand curve. Battery Energy Storage CHAPTER 3. LOAD AND GENERATION MODELLING AND TEST SYSTEMS 20 The BES unit is assumed to be connected to an AC system via bidirectional DC/AC converters that can be dispatched in all four quadrants over all given periods [107]. It can operate at any desired power factor (lagging/leading) to charge or discharge active power. In other words, the BES unit can operate as a load during charging periods and a generator during discharging periods. It can inject or absorb reactive power as well. 3.3.2 Nondispatchable Generation Solar Irradiance The probabilistic nature of solar irradiance can be described using the Beta Probability Density Function (PDF) as reported in [37]. This model has been employed in many PV studies such as [27, 39, 91, 108]. Over each period (1 hour in this study), the PDF for solar irradiance s can be expressed as follows: Γ(α + β ) (α −1) (1 − s )( β −1) 0 ≤ s ≤ 1,α , β ≥ 0 s f b ( s ) = Γ(α )Γ( β ) 0 otherwise (3.2) where f b (s ) is the Beta distribution function of s, s is the random variable of solar irradiance (kW/m2); α and β are parameters of f b (s ) , which are calculated using the mean ( µ ) and standard deviation ( σ ) of s as follows: µ (1 + µ ) β = (1 − µ ) σ 2 µ×β − 1 ; α = . 1− µ The output power from the PV module at solar irradiance s, PPVo (s ) can be expressed as follows [27, 39, 91]: PPVo ( s ) = N × FF × V y × I y where FF = VMPP × I MPP ; Vy = Voc − K v × Tcy Voc × I sc N − 20 I y = s[I sc + K i × (Tcy − 25)] ; Tcy = TA + s OT . 0 .8 (3.3) CHAPTER 3. LOAD AND GENERATION MODELLING AND TEST SYSTEMS 21 Here, N are the number of modules; Tcy and TA are respectively cell and ambient temperatures (oC); K i and K v are respectively current and voltage temperature coefficients (A/oC and V/oC); N OT is the nominal operating temperature of cell in oC; FF is fill factor; Voc and I sc are respectively the open circuit voltage (V) and short circuit current (A); VMPP and I MPP are respectively the voltage and current at maximum power point. Wind Speed The probabilistic nature of the wind speed can be described using the Weibull PDF [27], [44]. Over each period (1 hour in this study), the PDF for wind speed v can be expressed as follows: f w (v ) = k v cc k −1 v k exp − c (3.4) where f w (v) is the Weibull distribution function of v, v is the random variable of wind speed (m/s); k = 2 is the shape index, c ≈ 1.128vm is the Rayleigh scale index; vm is the mean value of wind speed that is calculated using the historical data for each time period. The output power at wind speed v ( Pwo ) can be expressed as follows [109]: 0 2 3 a + a v + a2v + a3v Pwo (v ) = 0 1 Prated 0 0 ≤ v ≤ vci vci ≤ v ≤ vr vr ≤ v ≤ vco (3.5) vco ≤ v where vci , vr , and vco are cut in, rated and cut out speed of the wind turbine, respectively; Prated is the rating of wind turbine; a0 , a1 , a2 and a3 are the coefficients calculated using any standard curve fitting technique such as ‘polyfit’ routine in Matlab [109]. Biomass The biomass-based gas turbines can be assumed to generate a constant output power at its rated value without associated uncertainties. CHAPTER 3. LOAD AND GENERATION MODELLING AND TEST SYSTEMS 22 3.3.3 DG Penetration Level The DG penetration level is the ratio of the total amount of DG energy exported to a network and its total energy consumption [110]. 3.3.4 Generation Criteria As reported in Section 2.5, most of the DG units are normally designed to operate at unity power factor under the recommendation of the standard IEEE 1547, [99]. This study assumes that inverter-based PV units are allowed to inject or absorb reactive power in compliance with the new German grid code [103]. Biomass gas turbines are modelled as synchronous machines. Wind farms are modelled as Doubly-Fed Induction Generators (DFIGs) or full converter synchronous machines. Such machines are also capable of controlling reactive power while delivering active power [105]. The relationship between the active and reactive power of a DG unit ( PDG and QDG ) can be expressed as [24]: QDG = aPDG ( where, a = ± tan cos −1 ( pf DG )) ; (3.6) a is positive for the DG unit supplying reactive power and negative for the DG unit consuming reactive power; and pf DG is the operating power factor of the DG unit. 3.4 Software Tools and Test Systems In this thesis, the study tools, which will be presented in the next chapters, including methodologies and algorithms have been developed for renewable DG integration. These tools have been coded in MATLAB environment. A variety of test distribution systems, ranging from 33 buses to 69 buses have been employed throughout in this thesis. Such systems have been commonly used by several previous studies found in the literature. A brief description of each system is provided below. 3.4.1 33-Bus Test System Figure 3.1 shows a single line diagram of the 12.66 kV, 33-bus test radial distribution system. It has one feeder with four different laterals, 32 branches and a total peak load of CHAPTER 3. LOAD AND GENERATION MODELLING AND TEST SYSTEMS 23 3715 kW and 2300 kVAr. The total loss of the base case system is 211.20 kW. The complete load data are given in Table A.1 (Appendix A) [111]. This system has been used in Chapters 6 and 7. Figure 3.1. The 33-bus test distribution system. 3.4.2 69-Bus One Feeder Test System A single line diagram of the 12.66 kV, 69-bus test radial distribution system is shown in Figure 3.2. It has one feeder with eight laterals, 68 branches, a total peak load of 3800 kW and 2690 kVAr and its corresponding loss of 224.93 kW. Its complete load data are provided in Table A.2 (Appendix A) [112]. This system has been used in Chapters 4 and 6. Figure 3.2. The 69-bus one feeder test distribution system. CHAPTER 3. LOAD AND GENERATION MODELLING AND TEST SYSTEMS 24 3.4.3 69-Bus Four Feeder Test System Figure 3.3 shows a single line diagram of the 11 kV, 69-bus test radial distribution system, which is fed by a 6 MVA 33/11 kV transformer [113]. This system consists of four feeders with 68 branches, a total peak load of 4.47 MW and 3.06 MVAr and its corresponding loss of 227.53 kW. The complete load data of this system are provided in Table A.3 (Appendix A) [113]. This system has been used in Chapters 5 and 8. S/S - 1 2 Legend 3 Substation 4 Bus Feeder 2 Feeder 1 1 16 17 10 Line 11 5 24 23 18 25 19 26 Tie-line 68 12 20 27 7 13 21 28 8 14 22 29 9 15 50 66 37 48 47 64 67 38 49 63 65 62 36 61 43 35 34 56 46 55 42 45 41 33 54 Feeder 3 44 32 31 30 39 53 60 40 52 59 58 57 51 Feeder 4 69 6 S/S - 2 Figure 3.3. The 69-bus four feeders test distribution system [113]. 3.5 Summary This chapter provided a definition of time-varying voltage-dependent load models and modelling of dispatchable and nondispatchable resources. Three test distribution systems used in the research were also explained in this chapter. CHAPTER 4 ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 4.1 Introduction As discussed in Chapter 2, the energy loss is one of the major concerns at the distribution system level due to its impact on the utilities’ revenue. The loss reduction can reduce power flows on distribution feeders, thereby resulting in positive impacts on system capacity release, voltage profiles and voltage stability [19]. From the utilities’ perspective, DG units located close to loads can significantly reduce energy losses in distribution systems. However, the high penetration level of intermittent renewable DG units (i.e., wind and solar) together with demand variations has introduced many challenges to distribution systems such as power fluctuations, voltage rise, high losses and low voltage stability as a result of reverse power flow [5]. Under the current standard IEEE 1547, renewable DG units are not allowed to supply reactive power [99]. Consequently, it is likely that the shortage of reactive power support may be an immediate concern at the distribution system level in the future with a high penetration level of renewable DG units. Given the fact that not only does the active power, but also the reactive power injection from renewable DG units play a significant role in enhancing system performances such as energy savings, voltage profiles, system capacity release and loadability. Depending on the nature of distribution systems, the former or the latter may be dominant. In addition, it could be highlighted that the lack of 25 CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 26 attention to reactive power support at the DG planning stage would potentially result in an increase in investment costs used to add reactive power resources and other devices at the operation stage. However, the redundancy of reactive power can lead to reverse power flow, thereby leading to high losses, voltage rise, low system stability, etc. To address this issue, it becomes necessary to study the optimal power factor of DG units, to which the active and reactive power injections are optimized simultaneously. As reported in Chapter 2, most of the existing studies have assumed that DG units operate at a pre-specified power factor, normally unity power factor. In these researches, only the location and size have been considered, while the optimal power factor for each DG unit that would be a crucial part for minimising energy losses has been neglected. Recently, a rule of thumb for DG operation has been developed for minimising power losses [24, 25]. For this rule, it is recommended that the power factor of DG units should be equal to the system load factor; however, the power factor is assumed to be the same for all buses in these studies. Overall, the review of relevant literature has showed that determining the power factor of renewable DG for each location that considers the timevarying characteristics of demand and generation for minimising energy losses has not been reported. Depending on the characteristics of loads served, each DG unit which can deliver both active and reactive power at optimal power factor may have positive impacts on energy loss reduction. This chapter presents three alternative analytical approaches to determine the optimum size and operating strategy of a single DG unit to reduce power losses and a methodology to identify the best location. These approaches are easily adapted to accommodate different types of renewable DG units (i.e., biomass, wind and solar PV) for minimising energy losses while considering the time-varying demand and possible operating conditions of DG units. The proposed approaches are tested in the 69-bus one feeder test distribution system (Figure 3.2) with different renewable DG scenarios. 4.2 Load and Renewable DG Modelling 4.2.1 Load Modelling The distribution system under the study is assumed to follow the nominalised 24-hour load profile of the IEEE-RTS system as shown in Figure 4.1 [36]. The time-varying constant P CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 27 and Q load model defined in Equation (3.1) is incorporated in the load characteristics. The load factor (LF) or the average load level of the system can be estimated as the area under the load curve in p.u. divided by the total duration. This can be expressed as follows: 24 LF = ∑ t =1 p.u. demand (t ) 24 (4.1) Load demand (p.u.) 1.0 0.9 0.8 0.7 0.6 0.5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Figure 4.1. Normalized daily load demand curve. 4.2.2 Renewable DG Modelling In this study, three types of renewable DG units described in Chapter 3, namely biomass, wind and solar PV are considered. The biomass DG output can be dispatched according to the nominalised load curve illustrated in Figure 4.1. The outputs of wind and PV-based DG are assumed to follow the nominalised average output curve depicted in Figure 4.2 [21, 114]. Each curve provides an hourly generation output as a percentage of the daily peak output itself. The capacity factor ( CF ) of each type of DG is estimated as the ratio of the area under the output curve in p.u. to the total duration as follows: 24 CF = ∑ t =1 p.u. DG output (t ) 24 (4.2) CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 1.0 Wind PV 0.8 Output (p.u.) 28 0.6 0.4 0.2 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Figure 4.2. Normalized daily wind and PV output curves. 4.3 Problem Formulation 4.3.1 Power Loss Elgerd’s Loss Formula The total active and reactive power losses (i.e., PL and QL) in a distribution system with N buses can be calculated by “exact loss formula” as follows [115]: N N PL = ∑∑ [α ij (Pi Pj + Qi Q j ) + β ij (Qi Pj − Pi Q j )] (4.3) i =1 j =1 N N QL = ∑∑ [γ ij (Pi Pj + Qi Q j ) + ξ ij (Qi Pj − Pi Q j )] (4.4) i =1 j =1 where α ij = rij rij cos(δ i − δ j ) ; β ij = sin (δ i − δ j ) ; ViV j ViV j γ ij = xij xij cos(δ i − δ j ) ; ξij = sin (δ i − δ j ) ; ViV j ViV j Vi ∠δ i is the complex voltage at the bus ith; rij + jxij = Z ij is the ijth element of impedance matrix [Z bus ] ; Pi and Pj are respectively the active power injections at buses i and j; Qi and Q j are respectively the reactive power injections at buses i and j. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 29 The total active and reactive power injections at bus i where a DG unit is installed are respectively given as follows [24]: Pi = PDGi − PDi (4.5) Qi = QDGi − QDi = ai PDGi − QDi (4.6) where QDGi = ai PDGi , PDGi and QDGi are respectively the active and reactive power −1 injections from the DG unit at bus i, ai = ( sign ) tan(cos ( pf DGi )) with sign = +1 : the DG unit injecting reactive power, sign = −1 : the DG unit consuming reactive power; PDi and QDi are respectively the active and reactive power of a load at bus i; pf DGi is the operating power factor of the DG unit at bus i. Substituting Equations (4.5) and (4.6) into Equations (4.3) and (4.4), we obtain the total active and reactive power losses with a DG unit (i.e., PLDG and QLDG, respectively) described as follows: N N α (( P ij DGi − PDi )Pj + (ai PDGi − QDi )Q j ) PLDG = ∑∑ i =1 j =1 + β ij ((ai PDGi − QDi )Pj − ( PDGi − PDi )Q j ) (4.7) N N γ (( P ij DGi − PDi )Pj + (ai PDGi − QDi )Q j ) QLDG = ∑∑ i =1 j =1 + ξij ((ai PDGi − QDi )Pj − (PDGi − PDi )Q j ) (4.8) Branch Current Loss Formula Alternatively, the total active and reactive power losses in a distribution system with n braches can be calculated as follows [116]: n PL = ∑ I i Ri 2 (4.9) i =1 n QL = ∑ I i X i 2 (4.10) i =1 where Ri and X i is respectively the resistance and reactance of branch i. I i is the current magnitude; this current has two components: active ( I a ) and reactive ( I r ) which can be CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 30 obtained from a load flow solution. Hence, Equations (4.9) and (4.10) is respectively rewritten as [116]: n PL = ∑ 2 I ai Ri i =1 n n + ∑ I ri Ri 2 (4.11) i =1 n QL = ∑ I ai X i + ∑ I ri X i 2 i =1 2 (4.12) i =1 When the active and reactive currents of a DG unit (i.e., I ak and I rk ) are injected at bus k, Equations (4.11) and (4.12) can be rewritten as: k PLDG = ∑ (I ai + I ak ) Ri + 2 i =1 k QLDG = ∑ (I ai + I ak ) X i + 2 i =1 n k n i =1 i =k +1 ∑ I ai Ri + ∑ (I ri + ak I ak )2 Ri + ∑ I ri Ri 2 i = k +1 n k ∑ I ai X i + ∑ (I ri + ak I ak ) X i + 2 i = k +1 i =1 2 2 (4.13) ∑ I ri X i (4.14) n 2 i =k +1 Let a k = −( sign ) tan(cos −1 ( PFDGk )) , where sign = +1 for the DG unit injecting reactive power; sign = −1 for the DG unit consuming reactive power. The relationship between I rk and I ak at bus k can be expressed as follows: I rk = ak I ak (4.15) Substituting Equation (4.15) into Equations (4.13) and (4.14), we obtain: k PLDG = ∑ (I ai + I ak ) Ri + 2 i =1 k QLDG = ∑ (I ai + I ak ) X i + 2 i =1 n k n i =1 i = k +1 ∑ I ai Ri + ∑ (I ri + ak I ak )2 Ri + ∑ I ri Ri 2 i = k +1 n k n i =1 i = k +1 2 ∑ I ai X i + ∑ (I ri + ak I ak )2 X i + ∑ I ri X i i = k +1 2 2 (4.16) (4.17) Branch Power Loss Formula The total active and reactive power losses in a distribution system with n braches can be obtained from Equations (4.9) and (4.10) as [117]: CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION n PL = ∑ i =1 n QL = ∑ i =1 Pbi + Qbi 2 31 2 2 Vi Pbi + Qbi 2 Ri (4.18) Xi (4.19) 2 2 Vi where Pbi and Qbi are respectively the active and reactive power flow through branch i. When the active and reactive power of a DG unit (i.e., PDGk and QDGk ) is injected at bus k, Equations (4.18) and (4.19) can be respectively rewritten as follows: k PLDG = ∑ ( Pbi + PDGk )2 R k QLDG = ∑ i =1 2 Vi i =1 i + ∑ i = k +1 ( Pbi + PDGk )2 X 2 Vi Pbi2 n i + 2 Vi Pbi2 n ∑ k i = k +1 Vi i =1 k 2 Vi Ri + ∑ ( Qbi + QDGk )2 R Xi + ∑ 2 ( Qbi + QDGk )2 i =1 Vi 2 Qbi2 n i + ∑ i = k +1 Vi n Xi + ∑ i = k +1 Qbi2 Vi (4.20) Ri 2 Xi 2 (4.21) The relationship between PDGk and QDGk can be expressed as: QDGk = ak PDGk (4.22) where ak is defined in (4.15). Substituting Equation (4.22) into Equations (4.20) and (4.21), we obtain: k PLDG = ∑ i =1 k QLDG = ∑ i =1 (Pbi + PDGk )2 R Vi 2 (Pbi + PDGk )2 X Vi 2 i + n 2 ∑ Pbi n Pbi 2 i =k +1 Vi i + ∑ i =k +1 Vi 2 2 k Ri + ∑ i =1 k Xi + ∑ i =1 (Qbi + ak PDGk )2 R Vi 2 (Qbi + ak PDGk )2 Vi 2 i n + ∑ 2 Qbi i = k +1 Vi Xi + n ∑ 2 (4.23) 2 Qbi i = k +1 Vi Ri 2 X i (4.24) CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 32 4.3.2 Impact of the Size and Power Factor of DG on Power Losses* It is revealed from either Equations (4.7) and (4.8) or Equations (4.16) and (4.17) or Equations (4.23) and (4.24) that the active and reactive power losses are functions of variables PDG and a (or pf DG ). Both variables have a significant impact on the power losses. Based on either Equation (4.7) or Equation (4.16) or Equation (4.23), Figure 4.3 plots a valley-shaped curve of the active power loss with respect to the size and power factor of a DG unit in a distribution system. Active power loss (MW) 0.18 0.14 0.1 0.06 0.02 1 0.95 0.8 0.9 1.3 0.85 1.8 0.8 2.3 0.75 DG power factor 2.8 0.7 3.3 DG size (MW) Figure 4.3. Impact of the size and power factor of a DG unit on system active power loss. It is observed from Figure 4.3 that for a particular power factor, the loss commences to reduce when the size of the DG unit is increased until the loss reaches the lowest level at which the optimal size is specified. If the size is further increased, the loss starts to increase and it is likely that it may overshoot the loss of the base case as a result of reverse power flow. Similarly, given a DG size, the optimal power factor at which the loss is minimum is identified. A similar trend can be observed for the variation of reactive power loss with * The work presented in this subsection has been published in D.Q. Hung, and N. Mithulananthan “Loss reduction and loadability enhancement with DG: A dual-index analytical approach”, Applied Energy, vol. 115, pp. 233-241, Feb. 2014. The rest of this chapter has been published in D.Q. Hung, N. Mithulananthan and R. C. Bansal, “Analytical strategies for renewable distributed generation integration considering energy loss minimization,” Applied Energy, vol. 105, pp. 75-85, May 2013. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 33 respect to variables PDG and a (or pf DG ), as defined by either Equation (4.8) or Equation (4.17) or Equation (4.24). In general, it is useful to operate a DG unit at its optimal size and power factor to minimize the active and reactive power losses. 4.3.3 Energy Loss The above alternative expressions for calculating the total active power loss can be utilized depending on the availability of required data. The total annual energy loss in a distribution system with a time duration ( ∆t ) of 1 hour can be expressed as follows: 24 24 0 t =1 Eloss = 365 ∫ Ploss (t )dt = 365∑ Ploss (t )∆t 4.4 (4.25) Proposed Methodology 4.4.1 Approach 1 (A1) This analytical approach 1 (A1) is developed based on “Elgerd’s loss formula” as expressed by Equation (4.3) to determine the optimal size and power factor of a single DG unit for minimising power losses. This is obtained by improving the previous work [24], where the analytical expression was developed to calculate different types of a single DG unit when the power factor is pre-specified. Approach A1 is then adapted to accommodate different types of renewable DG units for minimising energy losses while considering the time-varying characteristics of demand and generation. The study in [24] was also limited to DG allocation for reducing power losses. Sizing DG at Various Locations The optimal size at each bus i for minimising the power loss can be expressed as [24]: PDGi = α ii (PDi + ai QDi ) − Ai − ai Bi ; QDGi = ai PDGi 2 α ii (ai + 1) N N j =1 j ≠i j =1 j ≠i (4.26) where Ai = ∑ (α ij Pj − β ij Q j ) , Bi = ∑ (α ij Q j + β ij Pj ) and ai is defined in Equation (4.6). CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 34 Equation (4.26) which is used to calculate the optimal size of different types of a single DG unit at bus i for minimising power losses when pf DGi or value ai is known. The power factor of the DG unit depends on the operating conditions and DG types adopted. The optimal size of each DG type at each bus i for minimising the power loss can be determined from Equation (4.26) by setting the value of pf DG in the following different manners. DG technologies such as synchronous machine-based biomass DG, DFIG-based wind DG, and inverters-based PV DG can fall under the following types depending on their control strategy and active and reactive power capability. • Type 1 DG unit ( pf DG = 1) is capable of injecting active power only; • Type 2 DG unit ( pf DG = 0) is capable of injecting reactive power only; • Type 3 DG unit (0 < pf DG < 1 and sign = +1) is capable of injecting both active and reactive power; • Type 4 DG unit (0 < pf DG < 1 and sign = −1) is capable of injecting active power and absorbing reactive power. The optimal active and reactive power sizes of a DG unit at bus i can be obtained from Equation (4.26) by setting pf DGi = 1 or ai = 0 and pf DGi = 0 or ai = ∞ , respectively [24]. PDGi = PDi − Ai α ii ; QDGi = QDi − Bi α ii (4.27) Optimal Power Factor at Various Locations Depending on the characteristic of loads, the load power factor of a distribution system without reactive power compensation is normally in the range from 0.7 to 0.95 lagging (inductive load). Hence, the optimal power factor of the DG unit could be lagging [24]. It is assumed that the load power factor of the system considered in this work is lagging. Equation (4.27) represents the optimum active power of Type 1 DG unit ( PDGi ) and the optimal reactive power of Type 2 DG unit ( QDGi ). A combination of both PDGi and QDGi injected simultaneously at bus i can produce the optimal size of Type 3 DG, S DGi = PDGi + QDGi with lagging power factor. That means the DG unit is capable of 2 2 delivering both active and reactive power at bus i where the total system loss is minimum. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 35 Hence, in this concept, the optimal power factor of Type 3 DG at bus i ( opf DGi ) can be lagging and calculated as follows: PDGi opf DGi = (4.28) PDGi + QDGi 2 2 4.4.2 Approach 2 (A2) This analytical approach 2 (A2) is developed based on the “branch current loss formula” as given by Equation (4.9) to specify the optimal size and power factor of a single DG unit for reducing power losses. Similar to approach A1, approach A2 is then adapted to accommodate different types of renewable DG units for minimising energy losses while considering the time-varying characteristics of demand and generation. The application of Equation (4.9) was presented for capacitor allocation and DG placement with unity power factor at the peak load to reduce power losses [116, 118]. Sizing DG at Various Locations The system loss reduction, which is obtained by subtracting Equations (4.16) from Equation (4.11) (i.e. with and without a DG unit, respectively), can be expressed as follows: k k k k ∆Ploss = −2 I ak ∑ I ai Ri − I ak ∑ Ri − 2ak I ak ∑ I ri Ri − ak I ak ∑ Ri i =1 2 i =1 i =1 2 2 (4.29) i =1 The system loss reduction is maximum if the partial derivative of Equation (4.29) with respect to the active current injection from a DG unit at bus k is zero. This can be described as follows: k k k k ∂∆Ploss 2 = −2∑ I ai Ri − 2ak ∑ I ri Ri − 2I ak ∑ Ri − 2ak I ak ∑ Ri = 0 ∂I ak i =1 i =1 i =1 i =1 (4.30) The active current of the DG unit at bus k for maximizing loss reduction can be obtained from Equation (4.30) as follows: CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION k 36 k ∑ I ai Ri + ak ∑ I ri Ri I ak = − i =1 i =1 ( 2 1 + ak (4.31) )∑ R k i i =1 It is assumed that there is no significant change in the bus voltage after DG insertion. From Equation (4.31) with PDGk = Vk I ak and QDGk = ak PDGk , where Vk is the voltage magnitude of the DG unit at bus k, the optimal size of the DG unit at bus k and its corresponding maximum loss reduction can be calculated as follows: k k ∑ I ai Ri + ak ∑ I ri Ri PDGk = − Vk i =1 ( 2 1 + ak ∆Ploss i =1 )∑ R k ; QDGk = ak PDGk (4.32) i i =1 k k ∑ I ai Ri + ak ∑ I ri Ri i =1 = i =1 2 (4.33) (1 + )∑ R 2 ak k i i =1 Equation (4.32) can be used to calculate the optimal active and reactive power sizes of the DG unit at various power factors in the range of 0 to 1 (leading/lagging). When the values of pf DG are set at unity and zero, the optimal active and reactive power sizes of the DG unit, respectively can be obtained from Equation (4.32) as follows: k k ∑ I ai Ri PDGk = − Vk i =1k ∑ Ri ∑ I ri Ri ; QDGk = − Vk i =1 i =1 k (4.34) ∑ Ri i =1 Optimal Power Factor at Various Locations The optimal power factor of the DG unit at each bus ( opf DG ) for minimising power losses can be calculated by substituting Equation (4.34) into Equation (4.28). CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 37 Minimum Power Loss When the value of pf DG is set at unity in Equation (4.33), the maximum loss reduction due to the active power of the DG unit injected at bus k can be obtained. Similarly, when the value of pf DG is set at zero in Equation (4.33), the maximum loss reduction due to the reactive power of the DG unit injected at bus k can also be achieved. Hence, the total maximum loss reduction due to both active and reactive power sizes of the DG unit injected at bus k can be calculated as follows: 2 ∆Ploss k k ∑ I ai Ri ∑ I ri Ri + i =1 = i =1 k k ∑ Ri ∑ Ri i =1 2 (4.35) i =1 Hence, the total active power loss with the DG unit injected at bus k can be calculated by subtracting Equation (4.35) from Equation (4.11) as follows: PLDG = PL − ∆Ploss (4.36) 4.4.3 Approach 3 (A3) This novel analytical approach 3 (A3) is developed based on the “branch power flow loss formula” as given in Equation (4.18) to identify the optimal size and power factor of a single DG unit for minimising power losses. Similar to approaches A1 and A2, approach A3 is then adapted to accommodate different types of renewable DG units for minimising energy losses while considering the time-varying characteristics of demand and generation. Sizing DG at Various Locations The system loss reduction, which is obtained from subtracting Equation (4.23) from Equation (4.18), can be expressed as follows: k ∆Ploss = −2 PDGk ∑ i =1 Ri Pbi Vi 2 k − PDGk ∑ 2 i =1 k Ri Vi 2 − 2ak PDGk ∑ i =1 Ri Qbi Vi 2 k − ak PDGk ∑ 2 2 i =1 Ri Vi 2 (4.37) CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 38 The system loss reduction is maximum if the partial derivative of Equation (4.37) with respect to the active power injection from a DG unit at bus k becomes zero. This can be expressed as follows: k k k k ∂∆Ploss RP R RQ R 2 = −2∑ i 2bi − 2 PDGk ∑ i 2 − 2ak ∑ i 2bi − 2ak PDGk ∑ i2 = 0 ∂PDGk i =1 Vi i =1 Vi i =1 Vi i =1 Vi (4.38) It is assumed that there is no significant change in the bus voltage after DG insertion. From Equation (4.38), the active and reactive power sizes of the DG unit at bus k for maximizing loss reduction can be given by Equation (4.39) and its corresponding maximum loss reduction can be found by Equation (4.40) as follows: k ∑ PDGk = − i =1 Ri Pbi Vi 2 k + ak ∑ Vi i =1 (1 + )∑ V 2 ak ∆Ploss RiQbi k Ri i =1 i 2 ; QDGk = ak PDGk 2 k k Ri Pbi RiQbi a + k ∑ ∑ 2 i =1 Vi 2 i =1 Vi =− k R 2 1 + ak ∑ i2 i =1 Vi ( (4.39) 2 (4.40) ) Equation (4.39) can be used to calculate the optimal active and reactive power sizes of the DG unit at various power factors in the range of 0 to 1 (leading/lagging). Similar to approach A2, when the values of pf DG are set at 1 and 0, the optimal active and reactive power sizes of the DG unit, respectively can be obtained from Equation (4.39) as follows: k ∑ PDGk = − i =1 k Ri Pbi 2 ∑ RiQbi 2 Vi i =1 Vi ; QDGk = − k Ri Ri ∑V 2 i =1 k i (4.41) ∑V 2 i =1 i Optimal Power Factor at Various Locations The optimal power factor of the DG unit at each bus ( opf DG ) for minimising power losses can be calculated by substituting Equation (4.41) into Equation (4.28). CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 39 Minimum Power Loss Similar to approach A2, the total maximum loss reduction due to both active and reactive power sizes of the DG unit injected at bus k can be rewritten as: 2 ∆Ploss k Ri Pbi k RiQbi ∑ 2 2 ∑ i =1 Vi + i =1 Vi = k k Ri Ri ∑V 2 i =1 i 2 (4.42) ∑V 2 i =1 i Hence, the total active power loss with the DG unit injected at bus k can be calculated by subtracting Equation (4.42) from Equation (4.18) as defined by (4.36). 4.4.4 Computational Procedure This section presents a computational procedure for approaches A1, A2 and A3 using the expressions developed earlier. These approaches are to accommodate different types of renewable DG units to reduce energy losses while considering the time-varying demand and the possible operating conditions of DG units. In this procedure, the power loss is minimised first at the peak and average loads for dispatchable and nondispatchable DG units, respectively to determine the size, location and power factor. The output of dispatchable DG units is then adjusted based on the demand curve so that the energy loss is minimum. For nondispatchable DG units, after finding the size at the average load, the maximum size or the optimal size is identified using the DG output curve. The energy loss is subsequently calculated based on the DG output curve. In order to demonstrate the effectiveness of the proposed methodologies and algorithms developed, the following scenarios are considered. • Scenario 1: No DG unit (Base case); • Scenario 2: Dispatchable biomass DG unit; • Scenario 3: Nondispatchable biomass DG unit; • Scenario 4: Nondispatchable wind DG unit; • Scenario 5: Nondispatchable PV DG unit. Scenario 1: Run load flow for each period of the day and calculate the total annual CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 40 energy loss using Equation (4.25). In order to find the power loss, either Equation (4.3), (4.9) or (4.18) could be used depending on availability of required data. Scenario 2: The computational procedure is explained as follows: Step 1: Run base case load flow at the peak load level and calculate the total power loss using Equations (4.3), (4.9) or (4.18) for approaches A1, A2 and A3, respectively. Step 2: Identify the optimal location, size and power factor of a DG unit at the peak load level only. peak a) Find the optimal size for each bus ( S DGi ) using Equations (4.27), (4.34) and (4.41) for approaches A1, A2 and A3, respectively and calculate the optimal power factor for each bus using Equation (4.28). b) Place the DG unit obtained earlier at each bus, one at a time and calculate the approximate power loss for each case using Equation (4.3) for approach A1. For approaches A2 and A3, calculate the approximate power loss using Equations (4.36). c) Locate the optimal bus at which the power loss is minimum with the max corresponding optimal size of the DG unit or its maximum output ( S DG ) at that bus. Step 3: Find the optimal output of the DG unit at the optimal location only for period t as follows, where p.u. demand(t) is the load demand in p.u. at period t. S DG = p.u. demand (t ) S DG t max (4.43) Step 4: Run load flow with each DG output obtained in Step 3 for each period and calculate the total annual energy loss using Equation (4.25). Scenarios 3-5: The computational procedure is explained as follows: Step 1: Run load flow for the system without a DG unit at the average load level or at the system load factor (LF) using Equation (4.1) and calculate the total power loss using Equations (4.3), (4.9) or (4.18) for approaches A1, A2 and A3, respectively. Step 2: Specify the optimal location, size and power factor of a DG unit at the average load level only. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION a) 41 avg Find the optimal size for each bus ( S DGi ) using Equations (4.27), (4.34) and (4.41) for approaches A1, A2 and A3, respectively and calculate the optimal power factor for bus i using Equation (4.28). b) Place the DG unit obtained earlier at each bus, one at a time and calculate the approximate power loss for each case using Equation (4.3) for approach A1. For approaches A2 and A3, calculate the approximate power loss using Equations (4.36). c) Locate the optimal bus at which the power loss is minimum with the avg corresponding optimal size of the DG unit at the average load level ( S DG ) at that bus. Step 3: Find the CF based on its daily output curve using Equation (4.2). max Step 4: Find the optimal size of the DG unit or its maximum output ( S DG ) at the optimal location only as follows: avg max S DG = S DG (4.44) CF Step 5: Find the optimal DG output at the optimal location for period t as follows: S DG = p.u. DG output (t ) S DG t max (4.45) Step 6: Run load flow with each DG output obtained in Step 5 for each period and calculate the total annual energy loss using Equation (4.25). The above procedures are developed to accommodate different types of renewable DG units with optimal power factor. These procedures can be modified to allocate a DG unit with a pre-specified power factor. When the power factor is pre-specified, the procedures are similar to the above with exception that in Step 2.a in scenarios 2-5, the size is calculated using Equation (4.26) rather than (4.27) for approach A1, Equation (4.32) rather than (4.34) for A2, and Equation (4.39) rather than (4.41) for A3. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 4.5 42 Exhaustive Load Flow Solution To validate the effectiveness of the proposed approaches A1, A2 and A3, the Exhaustive Load Flow (ELF) solution [119] is employed. For each load level, a DG unit is placed at each bus. Its size is changed from 0% to 100% of the sum of the total demand and the total loss of the system in a step of 0.25%. The power factor of the DG unit is also varied for each case from 0 (lagging) to unity in a step of 0.001. The total system power loss is calculated for each case by load flow analyses. The total energy loss is estimated as a sum of the power losses of all load levels over 24 hours a day times 365 days a year using Equation (4.25). The best location, size and power factor are obtained in the case to which the total energy loss is minimum without any violations of the voltages. 4.6 Case Study 4.6.1 Test System The case study considered is the 69-bus one feeder radial distribution system as illustrated in Figure 3.2. The lower and upper voltage thresholds are set at 0.95 p.u. and 1.05 p.u., respectively. The system load power factor is assumed to remain unchanged for each load level (period). The distribution system considered in this work has the 24-hour load profile as depicted in Figure 4.1 [36]. It is assumed that biomass DG units can be allocated at all buses in the system. The location of PV and wind sources may be identified by resource and geographic factors. As their sites are unspecified in the test system, these sources are assumed to be available at all buses. However, when the location is pre-specified, the optimal size and power factor corresponding to the lowest power loss can be quickly determined based on the proposed approaches. 4.6.2 Numerical Results Scenario 1: Figure 4.4a shows the 24-hour load curve in MVA for the system without DG unit. This curve was developed based on the 24-hour load curve in p.u. as given in Figure 4.1. Figure 4.4b presents its corresponding 24-hour power loss curve. In this case, the total CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 43 annual energy loss is 1381.53 MWh which can be calculated as tracing the area under Figure 4.4b times 365 days as defined in Equation (4.25). Load demand (MVA) 5.0 4.5 4.0 3.5 3.0 2.5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (a) Power loss (KW) 250 200 150 100 50 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (b) Figure 4.4. Daily curves for (a) demand and (b) system power losses without a DG unit. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 44 Scenario 2: Figures 4.5a-b show the optimal output of a dispatchable biomass DG unit and its corresponding minimum power loss, respectively for each hour of the day at optimal bus 61. It is interesting to note that the DG output patterns which are determined by approaches A1 and ELF are almost the same and follow the load pattern as illustrated in Figure 4.4a. The daily power loss pattern with the DG unit also follows that of the base case as shown in Figure 4.4b. Hence, approach A1 based on the peak load solution combined with the load demand curve could be sufficient to specify the 24-hour optimal DG output curve in MVA. In contrast, as a multiple-load level solution, the ELF repeats the same computation for each load level. Similar results have been obtained using proposed approaches A2 and A3 as shown in Figures 4.5a-b. Table 4.1 summaries the results obtained by all the approaches. The outcomes achieved using the proposed approaches (A1, A2 and A3) are in close agreement with the ELF. The optimal location is found at bus 61. The difference in the optimal size and power factor due to numerical errors is negligible. More importantly, the computational time by the proposed approaches is significantly shorter than the ELF. Hence, the proposed approaches could be feasible for use in large-scale systems. In addition, it is observed from Table 4.1 that the computational time of A2 and A3 is the same since both approaches are originally derived from the same power loss formula. However, the error in the simulation results of the size and location of the DG unit exists between A2 and A3. This error happens due to the linearization of the original nonlinear equations (4.9) and (4.18). Another observation is that Approach A3 is more complex than Approach A2. Approach A2 is derived from the branch current loss formula (4.9), where the data inputs are the resistance and current of branches. Approach A3 is derived from the branch power loss formula (4.18), where the data inputs are the resistance of branches, the active and reactive power flowing through these branches, and bus voltages. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 2.4 45 A1 DG size (MVA) A2 2.1 A3 ELF 1.8 1.5 1.2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (a) 25 A1 Power loss (kW) A2 20 A3 ELF 15 10 5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (b) Figure 4.5. Daily curves at bus 61: (a) dispatchable biomass DG output and (b) system power losses with a dispatchable biomass DG unit. Table 4.1. Dispatchable biomass DG placement Approach A1 A2 A3 ELF 0.82 0.83 0.83 0.82 61 61 61 61 Optimal size (MVA) 2.222 2.222 2.298 2.241 Annual loss (MWh) 144.35 144.68 144.56 144.27 0.77 0.10 0.10 > 1625.67 Optimal power factor (lagging) Optimal bus CPU time (s) CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 46 Scenario 3: Figures 4.6a-b present the optimal output of a nondispatchable biomass DG unit and its corresponding minimum power loss, respectively for each hour of the day at optimal bus 61. The DG output pattern by the A1 is just under that by the ELF. Accordingly, the hourly power losses of both approaches are almost similar. The difference is that the size of the DG unit obtained by approach A1 is 1.844 MVA which is 0.024 MVA slightly smaller than the ELF, as shown in Table 4.2. Consequently, the total annual energy loss with the DG unit by the A1 and ELF are respectively almost the same at 184.68 MWh and 184.45 MWh, with a negligible difference of 0.12%. It is noted that only one single solution at the average load level combined with the biomass output curve was considered by the A1. Similar results have been found using the A2 and A3, as shown in Figure 4.6a-b and Table 4.2. Scenario 4: Figures 4.7a-b show the nondispatchable wind output curve following the wind output curve in Figure 4.3 for every hour of the day and its corresponding power loss at optimal bus 61. Similar to scenario 3, the wind DG output patterns specified by both A1 and ELF are nearly the same. The optimal sizes are found to be 3.684 MVA by the A1 and 3.316 MVA by the ELF. Hence, the annual total energy loss with the DG unit by the A1 is 307.52 MWh, whereas this value by the ELF is 294.24 MWh, as shown in Table 4.3. It is noted that a single solution at the average load level associated with the wind output curve in Figure 4.3 was considered by the A1. Similar results have been identified using the A2 and A3 as shown in Figure 4.7a-b and Table 4.3. Scenario 5: Figures 4.8a-b show the result of a PV DG unit at optimal bus 61 by the A1 and ELF on the assumption that its output follows the nondispatchable PV output curve (Figure 4.3). The output patterns achieved by both approaches are the same. However, the optimal size is 3.618 MVA by the A1 and is 2.985 MVA by the ELF, with a difference of 0.63 MVA, as shown in Table 4.4. Hence, the total annual energy loss by the A1 is 648.06 MWh, which is 6.06% higher than the ELF. Similar to scenario 4, one single solution at the average load level combined with the PV output curve (Figure 4.3) was considered by the A1. Similar results have been specified using approaches A2 and A3 as shown in Figure 4.8 and Table 4.4. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 4.0 A1 A2 A3 ELF 3.0 DG size (MVA) 47 2.0 1.0 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (a) Power loss (kW) 30 A1 A2 A3 ELF 25 20 15 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (b) Figure 4.6. Daily curves at bus 61: (a) nondispatchable biomass DG output and (b) system power losses with a nondispatchable biomass DG unit. Table 4.2. Nondispatchable biomass DG placement Approach A1 A2 A3 ELF 0.82 0.83 0.83 0.82 61 61 61 61 Optimal size (MVA) 1.844 1.844 1.891 1.868 Annual loss (MWh) 184.68 184.99 185.26 184.45 0.77 0.10 0.10 > 1625.67 Optimal power factor (lagging) Optimal bus CPU time (s) CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 4.0 48 A1 DG size (MVA) A2 A3 3.0 ELF 2.0 1.0 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (a) Power loss (kW) 100 A1 A2 A3 ELF 75 50 25 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (b) Figure 4.7. Daily curves at bus 61: (a) wind DG output and (b) system power losses with a wind DG unit. Table 4.3. Nondispatchable wind DG placement Approach A1 A2 A3 ELF 0.82 0.83 0.83 0.82 61 61 61 61 Optimal size (MVA) 3.684 3.684 3.777 3.316 Annual loss (MWh) 307.52 305.00 309.24 294.24 0.77 0.10 0.10 > 1625.67 Optimal power factor (lagging) Optimal bus CPU time (s) CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION DG size (MVA) 4.0 49 A1 A2 A3 ELF 3.0 2.0 1.0 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (a) Power loss (kW) 210 A1 A2 A3 ELF 160 110 60 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (b) Figure 4.8. Daily curves at bus 61: (a) PV DG output and (b) system power losses with a PV DG unit. Table 4.4. Nondispatchable PV DG placement Approach A1 A2 A3 ELF 0.82 0.83 0.83 0.82 61 61 61 61 Optimal size (MVA) 3.618 3.618 3.719 2.985 Annual loss (MWh) 648.06 657.72 668.14 608.81 0.77 0.10 0.10 > 1625.67 Optimal power factor (lagging) Optimal bus CPU time (s) Figure 4.9 shows a comparison of the maximum and actual penetration levels of DG units for scenarios 2-5. The actual penetration is calculated as the maximum DG CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 50 penetration times its CF. It is observed from Figure 4.9 that the maximum penetration levels of nondispatchable DG units (i.e., the wind and PV units in scenarios 4 and 5, respectively) are considerably higher than dispatchable DG units (i.e., the biomass unit in scenarios 2). However, the actual penetration levels of the nondispatchable DG units are significantly lower than the dispatchable DG units. This is because the dispatchable DG generation pattern (Figure 4.5a) matches better with the load demand (Figure 4.4a) than the nondispatchable DG output curves (Figures 4.7a and 4.8a for the wind and PV units, respectively). However, this is not the case for the nondispatchable biomass unit in scenario 3, which has the ability to operate at its continuous rated output for every hour of the day (Figure 4.6a). As shown in Figure 4.9, the actual and maximum penetration levels of the nondispatchable biomass unit are the same and are closer to the actual penetration of the dispatchable biomass unit in scenario 2. Figure 4.10 shows the energy loss reductions for scenarios 2-5. It is observed from the figure that the energy loss reduction for the dispatchable DG unit (scenario 2) is higher than the nondispatchable DG units (scenarios 3-5). This is due the fact that the dispatchable DG generation pattern matches better with the load demand than the nondispatchable DG output curves, as previously mentioned. Figure 4.11 shows the voltage profiles for scenarios 1-5 at the extreme periods where the voltage profiles are worst. In the absence of the DG units, the extreme period is specified at peak period 12 at which the voltages at buses 57-66 are under the lower limit of 0.94 p.u. In the presence of the DG units, by considering the combination of the demand and DG output curves, the extreme periods are determined as follows: period 12 for scenarios 2-3, period 16 for scenario 4 and period 13 for scenario 5. It is observed from the figure that after DG insertion, the voltage profiles at the extreme periods are improved significantly within the acceptable limit as expected. It is interesting to note that the voltage profiles in dispatchable DG scenario 2 are better than those in nondispatchable DG scenarios 3-5. CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 100 Max penetration 93.65 95.36 30.93 45.69 47.74 47.69 25 47.74 50 57.51 Penetration (%) Actual penetration 75 0 2 3 4 5 Scenario No. Figure 4.9. Maximum and actual penetration for scenarios 2-5. 3 25 53.09 2 77.74 50 86.63 75 89.55 Energy loss reduction (%) 100 0 4 5 Scenario No. Figure 4.10. Annual energy loss reduction for scenarios 2-5. Voltage (p.u.) 1.06 1.02 Scenario 1 Scenario 2 Scenario 3 Scenario 4 Scenario 5 0.98 0.94 0.90 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 Bus Figure 4.11. Voltage profiles at extreme periods for scenarios 1-5. 51 CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 52 It is noted that optimal sizes and locations obtained for power loss minimization using the above analytical expressions are in close agreement with the results reported in [120] and [32] using heuristic and ABC algorithms, respectively. It is worth mentioning that the power factor of DG units as well as DG types adopted can play a significant role in minimising energy losses. Based on the A1, Figures 4.12 and 4.13 depict the trends of energy loss reduction, at various DG power factors that represent different DG types at bus 61 for scenarios 2-5. The energy loss reduction commences to increase when the power factor is varied in order of leading, unity and lagging values and until it reaches the maximum value when the DG unit operates at 0.82 optimal lagging power factor. It is observed that Type 3 DG unit has the most positive impact on energy loss reduction, while the lowest impact is determined in Type 4 DG unit. However, as reported in [118], the grid codes of many countries require that grid-connected wind DG units should provide the capabilities of reactive power control or power factor control in a specific range. For instance, in the Ireland, the power factor of wind turbines is required to be from 0.835 leading to 0.835 lagging. It should be from 0.95 leading to 0.95 lagging in Italy and the United Kingdom. Hence, to assess the impact of the DG power factor on energy losses, in this study, the power factor is limited in the range of 0.9 leading to 0.9 lagging. In this case, as shown in Figures 4.12 and 4.13, the best power factor for all scenarios to achieve the highest energy loss reduction is determined at 0.9 lagging. The optimal location for all scenarios is at bus 61. The optimal size of each DG unit and its corresponding annual energy loss reduction for each scenario are presented in Figures 4.12 and 4.13. Optimal DG size (MVA) 5 4 87.38 DG size Loss 100 89.55 80 62.45 3 2 1 60 23.78 2.19 40 2.22 1.81 20 1.06 0 Energy loss reduction (%) 0.9 lag Unity 0.9 lead DG power factor 53 0.814 lag (optimal) CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 0 4 1 3 3 Type of DG Optimal DG size (MVA) 5 4 84.54 DG size Loss 86.63 100 80 60.34 3 60 2 40 22.91 1.82 1.50 1 1.84 20 0.88 0 0 4 1 3 3 Type of DG Scenario 3 Figure 4.12. DG placement with different power factors for scenarios 2-3. Energy loss reduction (%) 0.9 lag Unity 0.9 lead DG power factor 0.814 lag (optimal) Scenario 2 CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION Optimal DG size (MVA) 6 100 DG size Loss 5 75.93 77.74 3.63 3.68 80 54.33 4 60 3 20.77 40 3.00 2 20 Energy loss reduction (%) 0.814 lag (optimal) 0.9 lag Unity 0.9 lead DG power factor 54 1.76 1 0 4 1 3 3 Type of DG 0.9 lag Unity 0.9 lead DG power factor 0.814 lag (optimal) Scenario 4 5 75 DG size Loss 4 48.54 53.09 45 35.50 3.57 3 13.54 60 3.62 30 2.94 2 15 1.73 1 Energy loss reduction (%) Optimal DG size (MVA) 6 0 4 1 3 3 Type of DG Scenario 5 Figure 4.13. DG placement with different power factors for scenarios 4-5. 4.7 Summary This chapter presented three analytical approaches using three different power loss formulas to identify the optimal size and power factor of a single DG unit at various locations for minimising power losses and a methodology to identify the best location in distribution systems. These approaches were easily adapted to accommodate different CHAPTER 4. ANALYTICAL EXPRESSIONS FOR RENEWABLE DG INTEGRATION 55 types of renewable DG units (i.e., biomass, wind and solar PV) for minimising energy losses while considering a combination of time-varying demand and different DG output curves. The results demonstrated that the proposed approaches can be adequate to identify the location, size and power factor of a single DG unit for minimising energy losses. The three approaches can be utilized depending on availability of required data and produce similar outcomes. They can lead to an optimal or near-optimal result as verified by the ELF solution and other methods found in the literature. It is worth mentioning that dispatchable DG units have a more positive impact on energy loss reduction and voltage profile enhancement than nondispatchable DG units. The strategically optimized power factor of a single DG unit based on the proposed expression can make a significant contribution to energy loss reduction. CHAPTER 5 WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 5.1 Introduction The proposed approaches in Chapter 4 are well-suited to accommodate different types of single renewable DG units in distribution systems while considering the time-varying characteristics of demand and generation. However, these approaches are unable to address either multiple renewable DG units or a mix of different types of renewable DG units. As reported in Chapter 2, a combination of dispatchable and nondispatchable DG placement that considers the time-varying demand and generation for minimising energy losses has not been reported in the literature so far. This chapter presents a new methodology for the integration of dispatchable and nondispatchable renewable DG units for minimising annual energy losses. In this methodology, each nondispatchable wind unit is converted into a dispatchable source by adding a biomass unit. Here, analytical expressions are first proposed to identify the optimal size and power factor of a single DG unit simultaneously for each location for minimising power losses. These expressions are then adapted to place multiple renewable DG units for minimising annual energy losses while considering the time-varying characteristics of demand and generation. A combination of dispatchable and nondispatchable DG units is also proposed in this chapter. The proposed methodology is tested in the 69-bus four feeder test distribution system (Figure 3.3) with different scenarios of renewable DG. 56 CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 5.2 57 Load and Renewable DG Modelling 5.2.1 Load Modelling The system considered in this work is assumed to follow the normalized load curve of the IEEE-RTS system plotted in Figure 5.1 [36]. As shown in this figure, each year is divided into four seasons (winter, spring, summer and fall). For reasons of simplicity, an hourly load curve of a day is representing each season. However, two hourly load curves of two days (one for weekdays and one for weekends) which are representing each season could be incorporated in the proposed methodology. The load curve of four 24-hour days (24x4=96 hours) is subsequently representing the four seasons in a year (8760 hours). The seasonal maximum and minimum in load demand occurred during summer and fall, respectively. With a peak demand of 1 p.u., the LF or average load level of the system can be estimated as the ratio of the area under the load curve in p.u. to the total duration. 96 LF = ∑ t =1 p.u. load (t ) 96 (5.1) 1.2 Load demand in p.u. Summer 1.0 Fall Spring 0.8 Winter 0.6 0.4 0.2 0 12 24 36 48 60 72 84 96 Hour Figure 5.1. Normalized hourly load demand curve. 5.2.2 Renewable DG Modelling Two renewable resources, namely biomass and wind found in Section 3.3 are considered in this chapter. The biomass DG unit is modeled as a synchronous machine and the wind DG CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 58 unit uses DFIGs or full converter synchronous machines. The biomass DG unit is assumed to be a dispatchable source which can be dispatched according to the load curve as shown in Figure 5.1. In this case, the CF of the biomass DG unit is equal to the LF as given in Equation (5.1). The wind DG unit is assumed to be a nondispatchable source following the output curve for each season per year [121], as depicted in Figure 5.2. It is noted that different wind patterns could be easily incorporated in the proposed methodology below. As shown in Figure 5.2, a year is divided into four seasons. An hourly generation output pattern for a day is representing each season. The generation output curve of four 24-hour days (24x4=96 hours) is then representing the four seasons in a year (8760 hours). The seasonal maximum and minimum in wind power availability occurred during winter and summer, respectively. With a peak of 1 p.u., the CF of the wind DG unit is defined as the ratio of the area under the output curve in p.u. to the total duration. 96 CF = ∑ t =1 p.u. DG output (t ) 96 (5.2) 1.2 Winter Spring Fall Wind output in p.u. 1.0 Summer 0.8 0.6 0.4 0.2 0 12 24 36 48 60 72 84 96 Hour Figure 5.2. Normalized hourly wind output curve. 5.3 Problem Formulation As shown in Figure 5.1, each year has four seasons. A load curve for a 24-hour day is representing each season. The load curve of four 24-hour days (24x4=96 hours) is subsequently representing the four seasons in a year. The total number of hours per year is CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 59 365x24 (8760) hours. Therefore, the 96-hour load curve is repeated 91.25 times to represent one year (91.25x96=8760). Here, 96 hours in four seasons a year are t corresponding to 96 periods (load levels). The active power loss, Ploss , at each period t is obtained from Equation (4.3) without a DG unit or Equation (4.7) with a DG unit. Hence, the total annual energy loss in a distribution system with a time duration ( ∆t = 1 hour) can be expressed as follows: 96 Eloss = 91.25∑ Ploss ∆t t (5.3) t =1 5.4 Proposed Methodology 5.4.1 Expression for Sizing DG at Predefined Power Factor This section briefly describes an analytical expression developed in [24] to calculate different types of DG units for minimising power losses when the DG power factor is prespecified. The total active power loss can reach a minimum value if the partial derivative of Equation (4.7) with respect to the active power injection from a DG unit at bus i ( PDGi ) becomes zero. This can be expressed as follows: N ∂PLDG = 2∑ [α ij (Pj + ai Q j ) + β ij (ai Pj − Q j )] = 0 ∂PDGi j =1 (5.4) where ai is defined in Equation (4.6). Equation (5.4) can be rearranged as follows: α ii ( Pi + ai Qi ) + Ai + ai Bi = 0 where N N j =1 j ≠i j =1 j ≠i (5.5) Ai = ∑ (α ij Pj − β ij Q j ) , Bi = ∑ (α ij Q j + β ij Pj ) Substituting Equations (4.5) and (4.6) into Equation (5.5), we obtain [24]: PDGi = α ii (PDi + ai QDi ) − Ai − ai Bi 2 α ii (ai + 1) (5.6) CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 60 Equation (5.6) is used to calculate the optimal size of different types of a single DG unit at bus i for minimising power losses when ai (or pf DGi ) is known. 5.4.2 Proposed Expressions for Sizing DG at Optimal Power Factor In this section, an analytical expressions is proposed by improving the previous work [24] to determine the optimal size and power factor of each DG unit simultaneously for each location. Here, the total active power loss is minimum if the partial derivative of Equation (4.7) with respect to variable ai (or pf DGi ) becomes zero. This can be described as follows: N ∂PLDG = 2∑ [α ij Q j + β ij Pj ] = 0 ∂ai j =1 (5.7) Equation (5.7) can be rearranged as follows: α ii Qi + Bi = 0 (5.8) Substituting Equation (4.6) into Equation (5.8), we get: ai = 1 Bi QDi − PDGi α ii (5.9) The relationship between the pf DGi and variable ai can be expressed as follows: ( ) pf DGi = cos tan −1 (ai ) . (5.10) Finally, the optimal PDGi and its pf DGi for the total system loss to be minimum can be obtained from Equations (4.26), (5.9) and (5.10) as follows: PDGi = PDi − Ai α ii −1 α Q − Bi pf DGi = cos tan ii Di α P A − ii Di i (5.11) (5.12) CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 61 5.4.3 Computational Procedure In order to demonstrate the effectiveness of the proposed approach, the following four scenarios are considered: • Scenario 1: No DG unit (Base case). • Scenario 2: Dispatchable biomass DG units. • Scenario 3: Nondispatchable wind DG units. • Scenario 4: A combination of dispatchable biomass and nondispatchable wind DG units as a dispatchable source. Here, the assumption is that the wind DG unit is nondispatchable, and owned by DG developers and controlled by utilities. The biomass DG unit is dispatchable, and owned and operated by utilities. For a long-term planning purpose, this study considers that the load of all buses changes uniformly according to a load demand curve. In this method, the power loss is minimised first at the peak and average loads for dispatchable and nondispatchable DG units, respectively to determine the location, size and power factor. This method requires less computation. However, in a real system, the load of all buses does not change uniformly. In this case, the determination the location and power factor should be evaluated at all load levels to achieve a more accurate outcome. The proposed methodology can address this issue, but it requires a computational burden due to a large number of load flow analyses. Scenario 1: Run load flow for each period (or load level) of the day and estimated the total annual energy loss using Equation (5.3). Scenario 2: Figure 5.3 shows an example of the output curve of a single dispatchable biomass DG unit for the 69-bus four-feeder test system (Figure 3.3), in four seasons. This curve follows the load demand pattern in Figure 5.1 and was obtained using a computational procedure as follows: Step 1: Run base case load flow at the peak load level for the year and find the total power loss using Equation (4.3). Step 2: Find the optimal location, size and power factor of a DG unit at the peak load level for the year. CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 62 peak a) Find the optimal size ( PDGi ) and the optimal power factor using Equations (5.11) and (5.12), respectively. b) Place the DG unit obtained earlier at each bus, one at a time. Calculate the power loss for each case using Equation (4.7). c) Locate the optimal bus at which the power loss is minimum with the max corresponding optimal size or maximum output ( PDG ) at that bus. Step 3: Find the optimal DG output at the optimal location for period t as follows, where p.u. load(t) is the load demand in p.u. at period t. PDG = p.u. load (t ) PDG t max (5.13) Step 4: Run load flow with each DG output obtained in Step 3 for each period, find the total energy loss using Equation (5.3), and repeat Steps 2-4. Stop if any of the following occurs and the previous iteration solution is obtained. a) the bus voltage at any bus is over the upper limit; b) the branch current is over the upper limit; c) the total DG size is larger than the system demand plus loss†; d) the maximum number of DG units are unavailable. 1.0 Summer Generation (MW) 0.8 Spring Fall Winter 0.6 0.4 0.2 Dispatchable biomass DG 0.0 0 12 24 36 48 60 72 84 96 Hour Figure 5.3. Hourly optimal generation curve of a biomass DG unit. † In the absence of DG units, a distribution network is known as a passive network, which has a unidirectional power flow from the source to loads. In the presence of DG units, the passive network becomes an active one that has a bidirectional power flow, which exchanges between the source and loads. The problems associated with the active network is that as discussed in Section 4.3.2, an appropriately sized DG unit can help reduce system losses significantly. However, an excessively oversized DG unit in the active network may lead to feeder overloads, high losses, voltage rises and low system stability as a result of reverse power flow [5, 16, 102]. To avoid the reverse power flow, the constraint 4(c) is used. CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 63 Scenario 3: Figure 5.4 shows an example of the output curve of a single nondispatchable wind DG unit for the 69-bus four-feeder test system (Figure 3.3), in four seasons. This curve follows the wind output pattern in Figure 5.2 and was obtained using a computational procedure as follows: Step 1: Run load flow for the system without DG unit at the average load level for the year or at the load factor as given in Equation (5.1) and find the total power loss using Equation (4.3). Step 2: Find the optimal location, size and power factor of a DG unit at the average load level for the year. avg a) Find the optimal size ( PDGi ) and the optimal power factor using Equations (5.11) and (5.12), respectively. b) Place the DG unit obtained earlier at each bus, one at a time. Calculate the power loss for each case using Equation (4.7). c) Locate the optimal bus at which the power loss is minimum with the corresponding optimal size at the average load level or the average output avg ( PDG ) at that bus. Step 3: Find the CF of the wind DG unit based on its daily output curve using Equation (5.2). Step 4: Find the optimal DG size or maximum DG output at the optimal location as follows: avg max PDG = PDG (5.14) CF Step 5: Find the optimal DG output at the optimal location for period t as follows, where p.u. DGoutput(t) is the DG output in p.u. at period t. PDG = p.u. DG output (t ) PDG t max (5.15) Step 6: Run load flow with each DG output obtained in Step 5 for each period, find the total energy loss using Equation (5.3), and repeat Steps 2-6. Stop if any of the following occurs and the previous iteration solution is obtained. CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION a) the bus voltage at any bus is over the upper limit; b) the branch current is over the upper limit; c) the total DG size is larger than the system demand plus loss; d) the maximum number of DG units are unavailable. 64 The above computational procedures are developed to accommodate DG units with optimal power factor. These procedures can be modified to allocate DG units with a prespecified power factor. When the power factor of DG units is pre-specified, the computational procedure is similar to the above with exception that the optimal DG size for each bus is determined using Equation (5.6) rather than Equation (5.11). 1.0 Spring Winter Fall Summer Generation (MW) 0.8 0.6 0.4 0.2 Nondispatchable wind DG 0.0 0 12 24 36 48 60 72 84 96 Hour Figure 5.4. Hourly optimal generation curve of a nondispatchable wind DG unit. Scenario 4: Figure 5.5 shows an example of the output curve of a dispatchable and nondispatchable DG mix for the 69-bus four-feeder test system (Figure 3.3), in four seasons. This curve follows the demand profile in Figure 5.1 and was obtained using the computational procedure as explained below. Here, the wind output pattern in Figure 5.5 follows the wind output curve in Figure 5.2 on the condition that wind penetration is in its maximum. The biomass DG units are utilized as an additional dispatchable source to fill up the supply energy portion that the wind DG units cannot. Notice that the total DG output in MW for each period in scenario 4 (a mix of one dispatchable DG unit and one nondispatchable DG unit) is the same as that in scenario 2 (one dispatchable DG unit) on the condition that nondispatchable DG penetration is in its maximum. CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 65 Step 1: Find the optimal location, size and power factor of a DG unit and the corresponding total energy loss using the computational procedure in scenario 2. Step 2: Select the optimal location and power factor of dispatchable and nondispatchable DG units as calculated in Step 1. max Step 3: Find the optimal size or maximum output of the nondispatchable DG unit ( PDG ) over all periods on the condition that its output is no more than that of DG unit as specified in Step 1, at each period. Step 4: Find the optimal output of the nondispatchable DG unit for period t as given in Equation (5.15). Step 5: Calculate the output of the dispatchable DG unit that is equal to the output of the DG unit in Step 1 minus the output of the nondispatchable DG unit in Step 4, for each period; then find the optimal size or maximum output of the dispatchable DG unit over all periods. 1.0 Summer Generation (MW) 0.8 Fall Spring Winter 0.6 0.4 Dispatchable biomass DG 0.2 Nondispatchable wind DG 0.0 0 12 24 36 48 60 72 84 96 Hour Figure 5.5. Hourly optimal generation curve of a wind-biomass DG mix. 5.5 Case Study 5.5.1 Test System The proposed methodology was applied to the 69-bus four-feeder radial distribution system as shown in Figure 3.3. The lower and upper voltage thresholds should be 0.95 p.u. and 1.05 p.u., respectively. The feeder thermal limits are 5.1 MVA (270 A) [68]. CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 66 The demand of the system is assumed to follow the normalized load curve in Figure 5.1 [36]. Wind DG units are assumed to be nondispatchable and follow the normalized wind output curve in Figure 5.2. Biomass DG units are assumed to be allocated at any bus in the system. The locations of wind DG units may be identified by resources and geographic factors. As their sites are unspecified in the test system, they are assumed to be installed at any bus. However, when the locations are pre-specified, the optimal sizes and power factors with the lowest corresponding power loss can be quickly determined based on the proposed methodology. The power factor of DG units remains unchanged over all periods. The number of DG units is predefined at two for scenarios 2 and 3, and at four for scenario 4. However, the proposed methodology can consider the different number of DG units. 5.5.2 DG Placement without Considering Power Factor Limit Figure 5.6 shows the hourly load demand and power loss curves of the system in four seasons a year in scenario 1. The load demand curve shown in Figure 5.6 follows the hourly load demand curve in Figure 5.1. The peak demand occurred at period 59 in summer, whereas the lowest demand was at period 77 in fall. The significant power losses were observed at periods in summer. The total annual energy import from the grid without DG units is estimated as tracing the area under Figure 5.6 times 91.25 days. In this case, the total annual energy import is found at 24.556 GWh, which is a sum of the total system load demand (23.787 GWh) and the total system energy loss (0.769 GWh). Without considering the power factor limit (i.e., the optimal power factor for each DG unit is considered), Figures 5.7, 5.8 and 5.9 show the optimal output curves of DG units in four seasons in scenarios 2, 3 and 4, respectively, and the power import from the grid. For scenario 2, the total output of biomass DG units at each period (Figure 5.7) is dispatched following the demand curve (Figure 5.6). Similarly, for scenario 4, the total output of biomass-wind DG units at each period in Figure 5.9 is also dispatched according to the demand curve in Figure 5.6. Here, the wind output pattern in Figure 5.9 follows the wind output curve in Figure 5.2 on the condition that the wind penetration is in its maximum. The biomass DG units are utilized as an additional dispatchable source to fill up the supply energy portion that the wind DG units cannot. As the total DG output patterns of scenarios 2 and 4 are the same and are dispatched following the load demand in Figure 5.6, the power loss at each period in scenario 2 is identical to that in scenario 4 as depicted in CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 67 Figure 5.10. On the other hand, as the wind DG units in scenario 3 (Figure 5.8) cannot dispatch following the demand pattern in Figure 5.6, the power loss at each period in scenario 3 is higher than that in scenarios 2 and 4 as shown in Figure 5.10. In addition, it can be revealed from Figures 5.8-5.10 that the integration of DG units amounts to the reduction in the total energy import from the grid in all scenarios, resulting from the DG energy production and system energy loss reduction. 6 Summer Load demand (MW) 5 Spring 4 Fall Loss Winter 3 2 1 Demand 0 0 12 24 36 48 60 72 84 96 Hour Figure 5.6. Hourly load demand and power loss curves (scenario 1). 6 Summer Generation (MW) 5 Fall Spring 4 Winter 3 Grid import 2 Biomass 2 1 Biomass 1 0 0 12 24 36 48 60 72 84 96 Hour Figure 5.7. Hourly optimal generation curve of biomass DG units (scenario 2). CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 6 Summer 5 Generation (MW) 68 Fall Spring 4 Winter 3 Grid import 2 1 Wind 2 Wind 1 0 0 12 24 36 48 60 72 84 96 Hour Figure 5.8. Hourly optimal generation curve of wind DG units (scenario 3). 6 Summer Generation (MW) 5 Fall Spring 4 Winter 3 Grid import 2 Biomass 2 1 Wind 2 Biomass 1 Wind 1 0 0 12 24 36 48 60 72 84 96 Hour Figure 5.9. Hourly optimal generation curve of a wind-biomass DG mix (scenario 4). 300 Scenario 1 Scenario 2 Scenario 3 Scenario 4 Power loss (kW) 250 Summer Spring 200 Fall Winter 150 100 50 0 0 12 24 36 48 Hour Figure 5.10. Hourly power loss curve in scenarios 1-4. 60 72 84 96 CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 69 Tables 5.1 and 5.2 show a summary and comparison of the simulation results obtained for four scenarios with and without DG units in the 69-bus system. For scenarios 2-4 with DG units, the results include the type of DG units and the location, size and power factor for each type. The annual energy loss and its loss reduction for each scenario are also presented in these tables. The optimal locations of DG units for each scenario are identified at buses 62 and 35 with the corresponding sizes and power factors as shown in the tables. A significant energy loss reduction is observed in scenarios 2-4 (with DG units) when compared to scenario 1 (without DG units). In scenarios with DG units, the highest loss reduction is found in scenarios 2 and 4, while the lowest loss reduction is obtained in scenario 3. The combination of dispatchable and nondispatchable DG units in scenario 4 can yield the same loss reduction as dispatchable biomass DG units in scenario 2. It is noted that the optimal DG power factors at buses 62 and 35 are different at 0.79 and 0.83 (lagging), respectively. Table 5.1 Optimal DG placement without considering power factor limit Scenarios 1 (Base case) DG type 2 (Biomass) No DG Biomass 1 Biomass 2 62 35 Size (MVA) 0.94 0.99 Power factor (lag.) 0.79 0.83 Bus Annual loss (MWh) 768.50 365.38 Loss reduction (%) 52.46 Table 5.2 Optimal DG placement without considering power factor limit Scenarios DG type 3 (Wind) 4 (Wind-Biomass mix) Wind 1 Wind 2 Wind 1 Bio 1 Wind 2 Bio 2 62 35 62 62 35 35 Size (MVA) 0.86 0.99 0.49 0.71 0.56 0.82 Power factor (lag.) 0.79 0.83 0.79 0.79 0.83 0.83 Bus Annual loss (MWh) 426.92 365.38 Loss reduction (%) 44.45 52.46 CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 70 5.5.3 Biomass versus Wind Figure 5.11 shows the power loss reduction over 96 periods in four seasons in scenarios 24. It is obvious that scenario 2 can produce a maximum loss reduction over each period because the biomass output was dispatched according to the varying demand curve. On the other hand, the maximum loss reduction is found at a few periods in scenario 3 because the wind DG output cannot be dispatched according to the varying demand curve. Scenario 4 can yield the same loss reduction as scenario 2. The advantage is that the biomass DG units have capability to dispatch according to the load demand. Consequently, scenarios 2 and 4 that include the dispatchable biomass DG units are superior to scenario 3 from the perspective of total annual energy loss reduction as shown in Figure 5.11. Loss reduction (%) 100 Scenario 2 Scenario 3 Scenario 4 80 Fall Summer Spring Winter 60 40 20 0 0 12 24 36 48 Hour 60 72 84 96 Figure 5.11. Hourly percentage power loss reduction in scenarios 2-4. 5.5.4 Voltage Profiles Figure 5.12 shows the voltage profiles for scenarios 1-4 at the extreme periods (load levels) where the voltage profiles are worst. In the absence of DG units, the extreme period is at the peak period 59 as depicted in Figure 5.6, at which the voltages at some buses are under 0.94 p.u. In the presence of DG units, by considering the combination of the demand and DG output curves, the extreme periods are also at the peak period 59 for scenarios 2-4, as shown in Figures 5.8-5.10. It is observed from the figure that after DG units are integrated at the extreme periods, CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 71 the voltage profiles are improved significantly. It is interesting to note that the voltage profiles in scenario 2 (dispatchable DG units) or scenario 4 (a mix of dispatchable and nondispatchable DG units) are better than those in scenario 3 (nondispatchable DG units). It is worth noting that the optimal size and location of DG units obtained for power loss minimization using the proposed method are in close agreement with the results of recently published methods such as heuristic [120], PSO [30, 122], SA [28], ABC [32], MTLBO [33], HSA [34]. Voltage (p.u.) 1.06 Scenario 1 Scenario 2 Scenario 3 Scenario 4 1.02 0.98 0.94 0.90 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 Bus Figure 5.12. Voltage profile at extreme periods (period 59) for scenarios 1-4. 5.5.5 Power Factor Impact on Energy Loss As reported in [123], the grid codes of many countries require that grid-connected wind turbines should provide the capability of reactive power control or power factor control in a specific range. For instance, in the Ireland, the power factor of wind turbines is required to be from 0.835 leading to 0.835 lagging. It should be from 0.95 leading to 0.95 lagging in Italy and the United Kingdom. Hence, in this study, the power factor is limited in the range of 0.95 leading and 0.95 lagging to assess the impact of the power factor of DG units on energy losses. Tables 5.3 and 5.4 summarize and compare the results of DG placement for four different scenarios with and without DG units in the 69-bus system considering the power factor limit from 0.95 leading to 0.95 lagging. For each scenario with DG units, the results include the type, location, size, power factor and corresponding energy loss. The CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION 72 optimal locations of DG units for each scenario are identified at buses 62 and 35 with the corresponding sizes as shown in Tables 5.3 and 5.4. In this case, the best power factor of all DG units is found to be at 0.95 lagging. However, the optimal power factor of DG units are 0.79 and 0.83 (lagging), at buses 62 and 35, respectively, when the power factor limit was not considered as shown in Tables 5.1 and 5.2. It is revealed that imposing the power factor limit has a negative impact on the energy loss reduction at a maximum difference of nearly 5% when compared to the case without considering the power factor limit, as presented in Figure 5.13. However, this value may depend on the characteristics of the system and DG output. Table 5.3 Optimal DG placement considering power factor limit Scenarios 1 (Base case) DG type No DG 2 (Biomass) Biomass 1 Biomass 2 62 35 Size (MVA) 0.89 1.05 Power factor (lag.) 0.95 0.95 Bus Annual loss (MWh) 768.50 401.41 Table 5.4 Optimal DG placement considering power factor limit Scenarios DG type 3 (Wind) 4 (Wind-Biomass mix) Wind 1 Wind 2 Wind 1 Bio 1 Wind 2 Bio 2 62 35 62 62 35 35 Size (MVA) 0.81 0.96 0.44 0.67 0.52 0.79 Power factor (lag.) 0.95 0.95 0.95 0.95 0.95 0.95 Bus Annual loss (MWh) 458.04 401.41 CHAPTER 5. WIND AND BIOMASS INTEGRATION FOR ENERGY LOSS REDUCTION Energy loss reduction (%) 100 73 Without power factor limit With power factor limit 75 52.46 50 47.77 52.46 44.45 47.77 40.40 25 0 Scenario 2 Scenario 3 Scenario 4 Figure 5.13. Impact of the power factor of DG units on energy loss reduction. 5.6 Summary This chapter presented a methodology to determine the optimal location, size and power factor of dispatchable and nondispatchable renewable DG units for minimising annual energy losses in distribution systems. In this methodology, analytical expressions were first proposed to determine the optimal size and power factor of a single DG unit simultaneously for each location to minimize power losses. These expressions were then adapted to locate and size different types of renewable DG units and calculate the optimal power factor for each unit to minimize energy losses while considering the time-varying characteristics of demand and generation. Moreover, a combination of dispatchable and nondispatchable renewable DG units was proposed in this chapter. The proposed methodology was applied to the 69-bus four-feeder test distribution system with different renewable DG scenarios. The results showed that dispatchable DG units or a combination of dispatchable and nondispatchable DG units can minimize annual energy losses significantly when compared to nondispatchable DG units alone. The results also indicated that a maximum annual energy loss reduction is obtained for all the scenarios proposed with DG operation at optimal power factor. CHAPTER 6 MULTI-OBJECTIVE PV INTEGRATION 6.1 Introduction Depending on the location and technology of PV adopted, a power system would accommodate up to an estimated 50% of the PV penetration [16], [124]. However, the time-varying load model (i.e., time-varying voltage-dependent load model) may diversely affect the estimated PV penetration. Moreover, Chapter 2 showed that multiobjective planning for renewable DG in distribution systems that considers probabilistic generation and time-varying load models has not been reported in the literature. In addition, Chapters 4-5 reported DG allocation for minimising energy loss as a single-objective function. This chapter studies the penetration of PV units in a distribution system with several different types of time-varying load models. Here, a new multiobjective index (IMO)based analytical expression is proposed to identify the size of a single PV-based DG unit with objectives of simultaneously reducing active and reactive power losses and voltage deviation. This expression is then adapted to place PV units while considering the characteristics of varying-time load models and probabilistic generation. Three different types of customers with dissimilar load patterns (i.e., industrial, residential and commercial) and a mix of all these customers are defined by time-varying voltagedependent load models. The 33- and 69-bus test distribution systems shown in Figures 3.1 and 3.2, respectively are employed to validate the proposed methodology. 74 CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 6.2 75 Load and Solar PV Modelling 6.2.1 Load Modelling The demand of the system under the study is assumed to follow different normalized daily load patterns (i.e., industrial, residential and commercial) with a peak of 1 p.u., as shown in Figure 6.1 [125]. The time-varying voltage-dependent load model or the time-varying load model defined in Section 3.2 is also considered in this work. For each load model, the load factor (LF) or the average load level of the system can be defined as the area under the load curve in p.u. divided by the total duration: 24 LF = ∑ t =1 Demand (p.u.) 1.0 0.8 p.u. demand (t ) 24 (6.1) Industrial Residential Commercial 0.6 0.4 0.2 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Figure 6.1. Normalized daily demand curve for various customers. 6.2.2 Solar PV Modelling The solar irradiance for each hour of the day is modeled by the Beta Probability Density Function (PDF) based on historical data which have been collected for three years from the site (lat: 39.45, long: -104.65, California, USA) [126]. To obtain this PDF, a day is split into 24-h periods (time segments), each of which is one hour and has its own solar irradiance PDF. From the collected historical data, the mean and standard deviation of the hourly solar irradiance of the day is calculated. It is assumed that each hour has 20 states CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 76 for solar irradiance with a step of 0.05 kW/m2‡. From the calculated mean and standard deviation, the PDF with 20 states for solar irradiance is generated for each hour of the day and the probability of each solar irradiance state is determined. Accordingly, the PV output power is obtained for that hour. The model is explained below. The probability of the solar irradiance state s during any specific hour can be calculated as follows [27]: ρ ( s) = s2 ∫ f b (s)ds (6.2) s1 where s1 and s2 is solar irradiance limits of state s; f b (s ) is the Beta distribution function of s, which is calculated using Equation (3.2). The total expected output power (average output power) of a PV module across any specific period t, PPV (t ) (t = 1 hour), can be obtained as a combination of Equation (6.2) and Equation (3.3) [27]. This can be expressed as follows: 1 PPV (t ) = ∫ PPVo ( s ) ρ ( s )ds (6.3) 0 For example, given the mean ( µ ) and standard deviation ( σ ) of the hourly solar irradiance found in Table B.1 (Appendix B), the PDF for 20 solar irradiance states with an interval of 0.05 kW/m2 for periods 8, 12 and 16 are generated using Equations (3.2) and (6.2), and plotted in Figure 6.2. Obviously, as the solar irradiance is time and weatherdependent, different periods have different PDFs. The area under the curve of each hour is unity. Another example is that given the parameters of a PV module found in Table B.2 (Appendix B), the expected output of the PV module with respect to 20 solar irradiance states (Figure 6.2) is calculated using Equation (6.3) and plotted in Figure 6.3. For period 8, the total expected output power, which is calculated as the area under the curve of that period (Figure 6.3), is 53.08 W. As the period is assumed at one hour, the PV module is expected to output at 53.08 Wh. Similarly, the expected PV outputs for periods 12 and 16 are found to be 129.96 and 73.42 Wh, respectively. It is observed from Figure 6.3 that a ‡ This study considers the solar irradiance in the range of 0-1 kW/m2. However, a larger range (e.g., 0-1.5 kW/m2) can be used, providing that the maximum solar irradiance is included in this range. In such a case, the number of steps or the size of each step is changed to suit the range. CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 77 difference in the expected PV output patterns exists among hours 8, 12 and 16. 0.25 0.20 Hour 8 Hour 12 Probability Hour 16 0.15 0.10 0.05 0.00 0.05 0.15 0.25 0.35 0.45 0.55 0.65 0.75 0.85 0.95 0.75 0.85 0.95 Solar irradiance (kW/m2) Figure 6.2. PDF for solar irradiance at hours 8, 12 and 16. Expected PV output (W) 25 Hour 8 Hour 12 20 Hour 16 15 10 5 0 0.05 0.15 0.25 0.35 0.45 0.55 0.65 Solar irradiance (kW/m2) Figure 6.3. Expected output of a PV module at hours 8, 12 and 16. The capacity factor of a PV module ( CFPV ) can be defined as the average output power avg max ( PPV ) divided by the rated power or maximum output ( PPV ) [27]: avg CFPV = PPV max (6.4) PPV Once the average output power is calculated using (6.3) for each hour based on three years of the collected historical data as previously mentioned, the average and maximum output powers are obtained for the day. The CFPV is then obtained using (6.4). CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 78 As described in Section 3.3.4, the inverter-based PV technology [101, 104], which is capable of delivering active power and exporting or consuming reactive power, is adopted in this study. The relationship between the active and reactive power of a PV unit at bus k ( PPVk and QPVk ) can be expressed as follows [24]: Q PVk = a k PPVk ( where, a k = ± tan cos −1 ( pf PVk )); (6.5) a k is positive for the PV unit supplying reactive power and negative for the PV unit consuming reactive power; and pf PVk is the operating power factor of the PV unit at bus k. 6.2.3 Combined Generation-Load Model To incorporate the PV output powers as multistate variables in the problem formulation, the combined generation-load model reported in [27] is adopted in this study. The continuous PDF has been split into different states. As previously mentioned, each day has 24-h periods (time segments), each of which has 20 states for solar irradiance with a step of 0.05 kW/m2 for calculating the PV output powers. As the load demand is constant during each hour, its probability is unity. Therefore, the probability of any combination of the generation and load is the probability of the generation itself. 6.3 Problem Formulation 6.3.1 Impact Indices In this study, three indices: active power loss, reactive power loss and voltage deviation are employed to describe the PV impacts on the distribution system. These indices play a critical role in PV planning and operations due to their significant impacts on utilities’ revenue, power quality, and system stability and security. They are explained below. Active Power Loss Index Figure 6.4a shows a n-branch radial distribution system without a PV unit, where Pi and Qi are respectively the active and reactive power flow through branch i; PDi and QDi are respectively the active and reactive load powers at bus i. The total power loss in n-branch CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 79 system without a PV unit (PL) can be calculated using Equation (4.18). Figure 6.4b presents this system with a PV unit located at any bus, say bus k, where PPVk and QPVk are respectively the active and reactive powers of the PV unit at bus k. In this case, bus k is identical to bus i+1 (k = 2, 3, … n+1). As illustrated in Figure 6.4b, due to the active and reactive powers of the PV unit injected at bus k, the active and reactive powers flowing from the source to bus k is reduced, whereas the power flows in the remaining branches are unchanged. Accordingly, the power loss defined by Equation (4.18) can be rewritten as: k PLPV = ∑ i =1 k +∑ i =1 (Pi − PPVk )2 R Vi 2 i (Qi − QPVk )2 R Vi i 2 + + n Pi i = k +1 Vi ∑ 2 2 (6.6) 2 n Qi i = k +1 Vi ∑ Ri 2 Ri (a) (b) Figure 6.4. A radial distribution system: (a) without a PV unit and (b) with a PV unit. Substituting Equations (6.5) and (4.18) into Equation (6.6), we obtain: CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION k PLPV = ∑ 80 PPVk − 2 Pbi PPVk 2 Vi i =1 k +∑ 2 Ri ak PPVk − 2Qbi ak PPVk 2 (6.7) 2 Vi i =1 2 Ri + PL The active power loss index (ILP) can be defined as the ratio of Equations (6.7) and (4.18) as follows: ILP = PLPV (6.8) PL Reactive Power Loss Index The total reactive power loss (QL) in a radial distribution system with n branches can be using Equation (4.19). Similar to Equation (6.7), when both PPVk and Q PVk = a k PPVk are injected at bus k, Equation (4.19) can be rewritten as: k QLPV = ∑ PPVk − 2 Pbi PPVk 2 Vi i =1 k +∑ 2 Xi ak PPVk − 2Qbi ak PPVk 2 (6.9) 2 Vi i =1 2 X i + QL The reactive power loss index (ILQ) can be defined as the ratio of Equations (6.9) and (4.19) as follows: ILQ = QLPV QL (6.10) Voltage Deviation Index As shown in Figure 6.4a, the voltage deviation (VD) along the branch from bus i to bus i+1, ( Ri + jX i ), can be expressed as [127]: VDi = Ri Pbi + X i Qbi Vi +1 (6.11) CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 81 2 From Equation (6.11), the total voltage deviation squared ( VD ) in the whole system with n branches can be written as: n VD = ∑ 2 (Ri Pbi + X i Qbi )2 (6.12) 2 Vi +1 i =1 When both PPVk and QPVk are injected at bus k (Figure 6.4b), Equation (6.12) can be rewritten as: k Ri (Pbi − PPVk ) i =1 Vi +1 VDPV = ∑ 2 2 2 2 X i (Qbi − QPVk ) i =1 Vi +1 2 k + 2∑ ∑ 2 Vi +1 2 2 n 2 X i Qbi ∑ + 2 2 Ri Pbi i = k +1 k +∑ 2 n + i = k +1 Vi +1 Ri X i (Pbi − PPVk )(Qbi − QPVk ) Vi +1 i =1 2 (6.13) 2 +2 n ∑ Ri X i Pbi Qbi i = k +1 Vi +1 2 Substituting Equations (6.5) and (6.12) into Equation (6.13), we obtain: 2 VDPV k =∑ ( Ri PPVk − 2 Pbi PPVk 2 i =1 k +∑ 2 ( Vi +1 2 ) X i ak PPVk − 2Qbi ak PPVk 2 i =1 k − 2∑ 2 ( 2 Vi +1 2 ) (6.14) Ri X i Pbi ak PPVk + Qbi PPVk − ak PPVk 2 Vi +1 i =1 2 ) +VD 2 Finally, the voltage deviation index (IVD) of a distribution system can be defined as the ratio of Equations (6.14) and (6.12) as follows: 2 IVD = VDPV VD 2 (6.15) 6.3.2 Multiobjective Index On the one hand, when the PV unit is allocated for minimising either the active or reactive power loss (i.e., ILP or ILQ, respectively), this would potentially limit the PV penetration CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 82 with a high voltage deviation. On the other hand, a high penetration level could be achieved when the PV unit is considered for reducing the voltage deviation (IVD) alone, but the system losses could be high. To include all the indices in the analysis, a multiobjective index (IMO) can be defined as a combination of the ILP, ILQ and IVD indices with proper weights: IMO = σ 1 ILP + σ 2 ILQ + σ 3 IVD where ∑i=1σ i = 1.0 ∧ σ i ∈ [0, 1.0] . 3 (6.16) This can be performed as all impact indices are normalized with values between zero and one [29]. When a PV unit is not connected to the system (i.e., base case system), the IMO is the highest at one. The weights are intended to give the relative importance to each impact index for PV allocation and depend on the analysis purpose (e.g., planning or operation) [29, 54, 55, 58]. The determination of the proper weighting factors will also depend on the experience and concerns of the system planner. The PV installation has a significant impact on the active and reactive power losses and voltage profiles. The active power loss is currently one of the major concerns due to its impact on the distribution utilities’ profit, while the reactive power loss and voltage profile are less important than the active power loss. Considering these concerns and referring to previous reports in [29, 54, 55, 58], this study assumes that the active power loss receives a significant weight of 0.5, leaving the reactive power loss and the voltage deviation of 0.25 each. However, the above weights can be adjusted based on the distribution utility priority. As the solar irradiance is a random variable, the PV output power and its corresponding IMO are stochastic during each hour. The IMO can be formulated in the expected value. To calculate the IMO, the power load flow is analyzed for each combined generation-load state. It is assumed that IMO (s ) is the expected IMO at solar irradiance s, the total expected IMO over any specific period t, IMO (t ) (t = 1 hour) can be formulated as a combination of Equations (6.2) and (6.16) as follows: 1 IMO(t ) = ∫ IMO( s ) ρ ( s )ds 0 (6.17) CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 83 The average IMO (AIMO) over the total period (T = 24) in a system with a PV unit can be obtained from Equation (6.17). This can be expressed as follows: T AIMO = 1 1 T IMO ( t ) dt = ∑ IMO(t ) × ∆t T ∫0 T t =1 (6.18) where ∆t is the time duration or time segment of period t (1 hour in this study). The lowest AIMO implies the best PV allocation for reducing active and reactive power losses and enhancing voltage profiles. 6.4 Proposed Analytical Approach 6.4.1 Sizing PV Most of the existing analytical methods have addressed DG allocation in distribution systems for reducing the active power loss as a single-objective index [21-24]. This work proposes a new analytical expression based on the multiobjective index (IMO) as given by Equation (6.16) for sizing a PV-based DG unit at a pre-defined power factor. Substituting Equations (6.8), (6.10) and (6.15) into Equation (6.16), we get: IMO = σ1 PL PLPV + σ2 QL Q LPV + σ3 VD 2 2 VD PV (6.19) To find the minimum IMO value, the partial derivative of Equation (6.19) with respect to PPVk becomes zero: ∂IMO σ 1 ∂PLPV σ 2 ∂QLPV σ ∂VD PV = + + 32 =0 PL ∂PPVk Q L ∂PPVk VD ∂PPVk ∂P PVk 2 (6.20) The partial derivatives of Equations (6.7), (6.9) and (6.14) with respect to PPVk can be written as: ∂PLPV 2 = −2 Ak + 2C k PPVk − 2 Bk a k + 2C k a k PPVk ∂PPVk (6.21) CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 84 ∂Q LPV 2 = −2 Dk + 2 Fk PPVk − 2 E k a k + 2 Fk a k PPVk ∂PPVk (6.22) ∂VD PV 2 = 2Gk PPVk − 2 H k + 2 I k a k PPVk − 2 J k a k ∂PPVk 2 (6.23) − 2 K k a k − 2 Lk + 4M k a k PPVk k Ak = ∑ where i =1 k Dk = ∑ i =1 2 k Ri i =1 Vi +1 Gk = ∑ k Ri Pbi Vi 2 X i Pbi Vi ; Bk = ∑ 2 i =1 k ; Ek = ∑ k Kk = ∑ i =1 ; Hk = ∑ i =1 Ri X i Pbi Vi +1 2 Vi 2 Ri Pbi Vi +1 2 2 Vi k i =1 Vi 2 k ; Fk = ∑ i =1 2 k i =1 Ri X i Qbi Vi +1 Ri i =1 ; Ik = ∑ ; Lk = ∑ k ; Ck = ∑ X i Qbi i =1 k 2 Ri Qbi 2 Xi Vi 2 k Xi Vi +1 2 2 ; Jk = ∑ i =1 k ; Mk = ∑ i =1 2 X i Qbi Vi +1 2 Ri X i Vi +1 2 Substituting Equations (6.21), (6.22), (6.23) into Equation (6.20), we get: PPVk σ2 σ 1 P ( Ak + a k Bk ) + Q (Dk + a k E k ) L L σ3 (H k + a k J k + a k K k + Lk ) + 2 VD = σ2 σ 1 2 2 P C k + a k C k + Q Fk + a k Fk L L σ3 2 Gk + a k I k + 2a k M k + 2 VD ( ) ( ( ) (6.24) ) The power factor of a PV unit depends on the operating conditions and technology adopted. Given a pf PVk or ak value, the active power size of a PV unit for the minimum IMO can be obtained from Equation (6.24). The reactive power size is then obtained using Equation (6.5). CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 85 6.4.2 Computational Procedure In this section, a computational procedure is developed to allocate PV units for reducing the AIMO while considering the time-varying load models and probabilistic generation. To reduce the computational burden, the IMO is first minimised at the average load level as defined by Equation (6.1) to specify the location of a PV unit. This average load level has a significantly larger duration than other loading levels (e.g., peak or low load levels). The size is then calculated at that location based on the probabilistic PV output curve by minimising the AIMO over all periods. The computational procedure is summarized in the following steps: Step 1: Run load flow for the system without a PV unit at the average load level or at the system load factor (LF) using (6.1) and calculate the IMO using (6.16). Step 2: Specify the location and size at a pre-defined power factor of a PV unit at the average load level only. avg a) Find the PV size at each bus ( PPV ) using (6.24). k b) Place the PV unit obtained earlier at each bus and calculate the IMO for each case using (6.16). c) Locate the optimal bus at which the IMO is minimum with the corresponding avg size of the PV unit at the average load level ( PPV ) at that bus. k Step 3: Find the capacity factor of the PV unit ( CFPVk ) using (6.4). max Step 4: Find the optimal size of the PV unit or its maximum output ( PPVk ) at the optimal location obtained in Step 2 as follows, where depending on the patterns of demand and generation, an adjusted factor, k PV (e.g., 0.8, 0.9 or 1.1) could be used to achieve a better outcome: avg max PPVk = k PV × PPV k CFPVk (6.25) Step 5: Find the PV output at the optimal location for period t as follows, where p.u. PV output (t ) is the PV output in p.u. at period t, which is calculated using equations (3.2), (3.3), (6.2) and (6.3), and normalized: CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 86 PPVk (t ) = p.u. PV output (t ) × PPVk max (6.26) Step 6: Run load flow with each PV output obtained in Step 5 for each state over all the periods of the day and calculate the AIMO using (6.18). Step 7: Repeat Steps 4-6 by adjusting k PV in (6.25) until the minimum AIMO is obtained. 6.5 Case Study 6.5.1 Test Systems The proposed approach was applied to two radial test distribution systems. The first system illustrated in Figure 3.2 has one feeder, 69 buses and a peak demand of 3800 kW and 2690 kVAr [112]. The second system shown in Figure 3.1 has one feeder, 33 buses and a peak demand of 3715 kW and 2300 kVAr [111]. Figures 6.5 and 6.6 present the 69- and 33-bus systems, respectively, which are incorporated with different load types (i.e., industrial, residential and commercial). The constraint of operating voltages is assumed from 0.95 to 1.05 p.u. [99]. Load Modelling Five types of time-varying load models are considered in this study: 1. Time-varying industrial load model 2. Time-varying residential load model 3. Time-varying commercial load model 4. Time-varying mixed load model 5. Time-varying constant load model For both 69- and 33-bus systems, the loads are modeled by Equation (3.1) by combining the time-varying demand patterns for industrial, residential and commercial loads. These loads are shown in Figure 6.1 with the voltage-dependent load type with appropriate voltage exponents defined in Table 3.1. CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 87 Figure 6.5. The 69-bus test distribution system. Figure 6.6. The 33-bus test distribution system. Solar PV Modelling The presented method can be applied to either solar farm or roof-top PV. However, the roof-top PV has been considered as an example to validate the proposed methodology in this work. It is assumed that a PV unit provides active and reactive power at a lagging power factor of 0.9 which is compliant with the new German grid code [103]. The mean CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 88 and standard deviation (i.e., µ and σ, respectively) for each hour of a day are calculated using the hourly historical solar irradiance data collected for three years, as provided in Table B.1 (Appendix B) [126]. The characteristics of a PV module [91] employed for the PV model (3.3) can be found in Table B.2 (Appendix B). The solar irradiance s is considered at an interval of 0.05 kW/m2. Using Equations (3.2), (3.3), (6.2) and (6.3), the hourly expected output of the PV module is calculated and plotted in Figures 6.7a-c. It is observed from these figures that a difference in the PV output patterns exists among hours 6-19. Actually, this is due to dependence of the PV output on the solar irradiance, ambient temperature and the characteristics of the PV module itself. The total expected output power for each hour can be calculated as a summation of all the expected output powers at that hour. Accordingly, the normalized expected PV output for the 24-h period day is plotted in Figure 6.8. 6.5.2 Location Selection As previously mentioned, to select the best location, after one load flow analysis for the base case system at average load level, a PV unit is sized at various buses using Equation (6.24) and the corresponding multiobjective (IMO) for each bus is calculated. The best location at which the IMO is lowest is subsequently determined. Figure 6.9a shows the optimal sizes of a PV unit at various buses with the corresponding IMO values in the 69bus system with the industrial load model. The sizes are significantly different in the range of 0.39 to 2.34 MW. It is observed from the figure that the best location is bus 61 where the IMO is lowest. Similarly, the best location is specified at bus 6 in the 33-bus system with the industrial load model, as depicted in Figure 6.9b. It is noticed that given a fixed location due to resource availability and geographic limitations, the optimal size to which the IMO is lowest can be identified from the respective figures. For the other load models (i.e., constant, residential, commercial and mixed), the best locations are at buses 61 and 6 in the 69- and 33-bus systems, respectively. However, depending on the daily demand patterns and characteristic of systems, the locations may be different among load models. CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION Expected PV output (W) 25 89 Hour 6 Hour 7 Hour 8 Hour 9 Hour 10 20 15 10 5 0 0.05 0.15 0.25 0.35 0.45 0.55 0.65 0.75 0.85 0.95 0.75 0.85 0.95 0.75 0.85 0.95 Solar irradiance (kW/m2) (a) Expected PV output (W) 25 Hour 11 Hour 12 Hour 13 Hour 14 Hour 15 20 15 10 5 0 0.05 0.15 0.25 0.35 0.45 0.55 0.65 Solar irradiance (kW/m2) (b) Expected PV output (W) 25 Hour 16 Hour 17 Hour 18 Hour 19 20 15 10 5 0 0.05 0.15 0.25 0.35 0.45 0.55 0.65 Solar irradiance (kW/m2) (c) Figure 6.7. Expected PV output for hours: (a) 6-10, (b) 11-15 and (c) 16-19. CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 90 PV output (p.u.) 1.0 0.8 0.6 0.4 0.2 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Figure 6.8. Normalized daily expected PV output. PV size IMO 1.0 8 0.8 6 0.6 4 0.4 2 0.2 0 IMO Optimal PV size (MW) 10 0.0 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 Bus (a) PV size IMO 1.0 8 0.8 6 0.6 4 0.4 2 0.2 0 IMO Optimal PV size (MW) 10 0.0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 Bus (b) Figure 6.9 PV size with respect to IMO at various locations at average load level for the industrial load model: (a) 69-bus system and (b) 33-bus system. CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 91 6.5.3 Sizing with Respect to Indices For the 69-bus system, Figure 6.10 shows the hourly expected outputs of a PV unit at bus 61 over one day (06:00 to 19:00) with different time-varying load models. These PV output patterns exactly follow the expected PV output curve depicted in Figure 6.8. The maximum output of the PV unit for each load models, which is indentified at hour 11, shows its optimum size. Figure 6.11 presents the expected IMO values which are respectively obtained for the 69-bus system with the PV unit. At each period of the day, the IMO values in the system with the PV unit are substantially declined when compared to the system without the PV unit (IMO = 1 p.u.). This indicates that the PV installation positively affects the IMO. Figure 6.12 shows a comparison of the optimal PV size, and the averages of IMO and its components (ILP, ILQ and IVD) in the 69-bus system for different time-varying load models. As shown in Figure 6.12, a significant difference in the optimal size of the PV unit is observed when different time-varying load models are considered. The PV size for the commercial load is remarkably larger than the industrial and residential loads. This is due to the fact that the commercial consumption and PV output availability (Figures 6.1 and 6.11) almost occurred simultaneously during the day, while the industrial and residential customers had most of the consumption during the night. It is revealed from Figure 6.12 that the maximum PV size is determined for the commercial load, whereas the minimum PV size is indentified for the residential load. In addition, the size of the PV unit for the time-varying constant load model is roughly 9.09% bigger than the time-varying mixed load model. A similar trend has been observed for the 33-bus system. 2.0 PV output (MW) 1.6 1.2 Constant Industrial Residential Commercial Mixed 0.8 0.4 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Figure 6.10. Hourly expected PV outputs at bus 61 for the 69-bus system for different time-varying load models. CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 92 1.0 IMO (p.u.) 0.8 0.6 Constant Industrial Residential Commercial Mixed 0.4 0.2 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Figure 6.11. Hourly expected IMO curves for the 69-bus system with a PV unit at bus 61 for different time-varying load models. PV size and indices 2.0 1.6 1.2 0.8 0.4 0.0 Const Ind Res Com Mixed Load model Size (MW) AILP AILQ AIVD AIMO Figure 6.12. PV size and indices for the 69-bus system with a PV unit at bus 61 for different time-varying load models. Table 6.1 shows a summary and comparison of the results of PV allocation obtained in the 69- and 33-bus systems with different time-varying load models. The results include the optimum bus, size and penetration of the PV unit and corresponding AIMO for each load model. Differences in the location, size and penetration exist among the load models. For the 69-bus system, the minimum and maximum AIMO values are respectively 0.573 (p.u.) for the commercial load model and 0.660 (p.u.) for the residential load model. A similar trend is observed for the 33-bus system. The lowest AIMO is 0.716 (p.u.) for the CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 93 commercial load model, whereas the highest AIMO is 0.770 (p.u.) for the residential load model. Table 6.1. PV allocation in the 69- and 33-Bus Systems 69-bus System 33-bus system Load models Bus Size (MW) AIMO Bus Size (MW) AIMO Constant 61 1.20 0.609 6 1.80 0.737 Industrial 61 1.05 0.590 6 1.55 0.722 Residential 61 0.90 0.660 6 1.15 0.770 Commercial 61 1.85 0.573 6 2.50 0.716 Mixed 61 1.10 0.622 6 1.65 0.754 6.5.4 PV Penetration and Energy Losses Figure 6.13 shows the PV penetration levels in the 69- and 33-bus systems with different time-varying load models. First, it is observed that the time-varying load models adopted have a diverse impact on the penetration level. In the 69-bus system, the penetration levels are 32.59% for the commercial load model and 19.55% and 17.38% for the industrial and residential load models, respectively. This is because the PV generation pattern (Figure 6.7) matches better with the commercial demand than the industrial and residential demand curves (Figure 6.1). Similarly, in the 33-bus system, the penetration levels are 45.23% for the commercial load model and 29.64% and 22.80% for the industrial and residential load models, respectively. Secondly, it is shown from Figure 6.13 that there is a difference in the PV penetration between the time-varying constant and mixed load models in both test systems. In the 69-bus system, the PV penetration is 22.18% for the time-varying constant load model, whereas this value is 20.34% for the time-varying mixed load model. Similarly, in the 33-bus system, the PV penetration levels are 34.18% and 31.33% for the time-varying constant and mixed load models, respectively. Finally, it is also revealed that the system load characteristics play a crucial role in determining the PV penetration. For each load model, the PV penetration in the 69-bus system is lower than the 33-bus system, as shown in Figure 6.13. CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 40 69-bus system 33-bus system 31.33 20.34 45.23 32.59 22.80 17.38 29.64 10 19.55 20 34.18 30 22.18 PV penetration (%) 50 94 0 Const Ind Res Com Mixed Load models Figure 6.13. PV penetration levels in the 69- and 33-bus systems. Table 6.2 shows a summary and comparison of the energy loss of the system without and with the PV unit over a day (EL and ELPV, respectively) for different time-varying load models. The daily energy loss is calculated as a sum of all hourly power losses over the day. For each load model, it is observed that the energy loss of the system with the PV unit is significantly reduced when compared to that of the system without the PV unit. In addition, due to inclusion of the active and reactive load voltage exponents in the mixed load model, the energy losses with and without the PV unit for this model are respectively lower than the constant load model. Table 6.2 also shows the results of the energy loss reduction of the two systems (∆E) for all load models. In both systems, the maximum loss reduction is observed in the commercial load, whereas the minimum value is obtained in the industrial customer. This is due to the fact that the PV generation matches better with the commercial load than the industrial customer, as previously mentioned. Table 6.2. Energy loss reduction over a day for 69 and 33-Bus Systems 69-bus System Load models 33-bus system EL (MWh) ELPV (MWh) ∆E (%) EL (MWh) ELPV (MWh) ∆E (%) Constant 1.87 1.32 29.54 1.73 1.25 28.13 Industrial 1.56 1.11 28.50 1.51 1.18 21.32 Residential 1.49 1.01 32.28 1.45 1.11 23.33 Commercial 1.68 0.52 68.90 1.63 0.81 50.20 Mixed 1.54 1.08 29.79 1.43 1.04 27.58 CHAPTER 6. MULTI-OBJECTIVE PV INTEGRATION 6.6 95 Summary This chapter proposed an analytical approach to determine the penetration of PV units in a distribution system with different types of time-varying load models. In this approach, an IMO-based analytical expression was proposed to identify the size of PV units, which is capable of supplying active and reactive power, with objectives of simultaneously reducing active and reactive power losses and voltage deviation. The analytical expression was then adapted to accommodate PV units while considering the characteristics of time-varying voltage-dependent load models and probabilistic generation. The Beta PDF model was used to describe the probabilistic nature of solar irradiance. The results indicated that the time-varying load models play a critical role in determining the PV penetration in any distribution system. For the residential load model, a poor match between the generation and demand leads to relatively low PV penetration levels, roughly 17% and 23% in the 69and 33-bus systems, respectively. Similarly, for the industrial load, due to a mismatch between the generation and demand, the 69- and 33-bus systems can accommodate PV penetration levels of approximately 20% and 30%, respectively. In contrast, for the commercial load model, a good match between the demand and generation results in higher penetration levels at around 33% and 45% in the respective 69- and 33-bus systems. In addition, a practical load model which is defined as a time-varying mixed load model of residential, industrial and commercial types was examined. It was observed that the PV penetration in the time-varying mixed load model is lower than the time-varying constant load model. This study recommends that the time-varying mixed load model should be used for determining PV penetration for a distribution network. CHAPTER 7 PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 7.1 Introduction As discussed in Chapters 4-6, PV units can be allocated to minimize energy losses and enhance voltage profiles in distribution systems. However, the high penetration of this intermittent renewable source together with demand variations has introduced many challenges to distribution systems such as power fluctuations, voltage rise, high losses and low voltage stability [5]. Consequently, generated power curtailment, dump loads and dispatchable BES systems have been utilized together with intermittent renewable DG units (i.e., wind and solar) to eliminate the intermittency, reduce power fluctuations and avoid any violation of the system constraints [128]. As discussed in Chapter 2, renewable DG integration in distribution systems that considers energy loss and voltage stability has attracted attention in recent years, but both issues have been addressed separately. Few studies on renewable DG allocation (e.g., biomass, wind and solar) have been presented for minimising energy losses considering demand and generation variations. Similarly, few works on renewable DG placement have been reported for voltage stability enhancement. Furthermore, depending on the characteristics of loads served, optimal DG power factor dispatch for each load level would be a crucial part for minimising energy losses. However, most of the current studies have assumed that DG units operate at pre-specified power factors. 96 CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 97 This chapter studies the integration of PV and BES units in a commercial distribution system for reducing energy loss and enhancing voltage stability. Here, each nondispatchable PV unit is converted into a dispatchable source with a combination of PV and BES units. New multiobjective index (IMO)-based analytical expressions are proposed to capture the size and power factor of the combination of PV and BES units. A SelfCorrection Algorithm (SCA) is also developed for sizing multiple PV and BES units while considering the time-varying demand and probabilistic generation. The proposed methodology is tested in the 33-bus test distribution system (Figure 3.1). 7.2 Load and Generation Modelling 7.2.1 Load Modelling The demand of the system under the study is assumed to follow a 24-h daily commercial load curve [125] as shown in Figure 6.1. The time-varying commercial load model as defined in Section 3.2 is also considered in this work. 7.2.2 Nondispatchable PV Modelling The PV unit considered is a nondispatchable and probabilistic source and its modelling is described in Section 6.2.2. Given the fact that capacitors have been traditionally utilized to deliver reactive power or correct power factors for loss reduction and voltage stability enhancement. However, they are not smooth in controlling voltages and not flexible to compensate for transient events due to the impact of intermittent renewable energy resources [100, 101]. As a fast response device, the inverter-based PV unit has the capability to control reactive power or power factors for loss minimization and voltage regulation while supplying energy as a primary purpose [100, 101]. This study considers that a PV unit is associated with two types of converters (type 1 and type 2) for comparison. • Type 1 is capable of operating at any desired power factor (lagging/leading) to deliver active power and inject or absorb reactive power over all periods [100, 101, 104]. • Type 2 can deliver active power only (i.e., unity power factor) as per the standard IEEE 1547 [99]. CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 98 7.2.3 Dispatchable BES Modelling The Battery Energy Storage (BES) unit is modelled as a dispatchable source described in Section 3.3.1.2. The BES energy variation at bus k in period t can be expressed as [129]: DISCH E BESk (t ) = E BESk (t − 1) − PBESk (t ) ηd ∆t , for PBESk (t ) > 0 (7.1) E BESk (t ) = E BESk (t − 1) − η c PBESk (t )∆t , for PBESk (t ) ≤ 0 CH CH DISCH where E BESk is the total energy stored in the BES unit; PBESk and PBESk are respectively the charge and discharge power of the BES unit; η c and η d are respectively the charge and discharge efficiencies of the BES unit; ∆t is the time duration of period t. The lower and upper bounds of the BES unit should be satisfied as follows [107]: E BESk ≤ E BESk (t ) ≤ E BESk min min max (7.2) max where E BESk and E BESk are respectively the lower and upper bounds of the energy in the BES unit. In this research, the lower and upper bounds are assumed to be 20% and 90% of the installed capacity of the BES unit, respectively [107, 130]. 7.3 Problem Formulation 7.3.1 Conceptual Design Figure 7.1a-b shows the proposed conceptual model of a grid-connected PV and BES system (PV-BES). This system is intended to be installed on the rooftop areas of commercial buildings. The idea is to convert each nondispatchable to dispatchable PV unit with a combination of PV and BES units to retain the system active and reactive power losses for each load level at the lowest levels. This combination can produce a daily amount of dispatchable energy, E( PV + BES ) . Here, in a 24-h day cycle, the PV unit is generating an amount of energy, E PV . A portion of this energy is delivered to the grid, GRID E PV CH . The redundant energy of the PV unit is used to charge the BES unit, E BES rather than curtailing it when the PV output is high during the day. This stored energy is then CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY DISCH discharged to the grid, E BES 99 when the PV output is small or zero during the night. The PV and BES units are placed in the same bus to avoid network energy losses during the charge of the BES unit. The daily energy amount of a combination of PV and BES units over the total period (T = 24 hours) at bus k can be written as: (a) 2 Output (MW) E PV BES charging from PV ( E CH ) BES 2 1 E ( PV + BES ) 1 DG generating to grid ( GRID ) EPV BES discharging DISCH ) to grid (E BES 0 1 2 3 4 5 6 7 8 BES discharging to grid ( E DISCH ) BES 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (b) Figure 7.1. Conceptual model of grid-connected PV-BES system: (a) Connection diagram and (b) Charging and discharging characteristics of BES and PV outputs. T 24 0 t =1 E ( PV + BES )k = ∫ Pk (t )dt = ∑ Pk (t )∆t (7.3) where Pk (t ) is the active power output of the combination of PV and BES units at bus k at period t across a given day. The power factor of PV and BES units are optimally CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 100 dispatched for each 1-h period. From the utility perspective, this model can reduce energy loss and enhance voltage stability, which are respectively related to active and reactive power loss indices as explained below. 7.3.2 Impact Indices Active Power Loss Index When a mix of PV and BES units, ( PV + BES ) is injected both active power ( Pk ) and reactive power ( Qk ) at bus k, Equation (4.18) can be rewritten as: k PL ( PV + BES ) = ∑ (Pbi − Pk )2 R i =1 ( Let ak = ± tan cos Vi −1 i 2 + 2 n Pbi ∑ i = k +1 Vi ( pf k )) ; 2 k Ri + ∑ (Qbi − Qk )2 R Vi i =1 i 2 + n ∑ 2 Qbi i =k +1 Vi 2 Ri (7.4) ak is positive for the PV-BES mix injecting reactive power and ak is negative for the PV-BES mix consuming reactive power; pf k is the operating power factor of the PV-BES mix at bus k, the relationship between Pk and Qk at bus k can be expressed as: Qk = ak Pk (7.5) From Equations (4.18), (7.4) and (7.5), we obtain: k PL ( PV + BES ) = ∑ i =1 Pk − 2 Pbi Pk 2 Vi 2 k Ri + ∑ ak Pk − 2Qbi ak Pk 2 i =1 2 Vi 2 Ri + PL (7.6) Finally, the active power loss index (ILP) is defined as the ratio of Equations (7.6) and (4.18) as follows: ILP = PL ( PV + BES ) PL (7.7) where the total active power loss (PL) in a radial distribution system with n branches can be calculated as Equation (4.18). CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 101 Reactive Power Loss Index Similar to Equation (7.6), when a mix of PV and BES units, ( PV + BES ) is injected both Pk and Qk = ak Pk at bus k, Equation (4.19) can be rewritten as follows: k QL ( PV + BES ) = ∑ Pk − 2 Pi Pk 2 Vi i =1 2 k Xi + ∑ ak Pk − 2Qi ak Pk 2 2 i =1 Vi 2 X i + QL (7.8) Finally, the reactive power loss index (ILQ) is defined as the ratio of Equations (7.8) and (4.19) as follows: ILQ = QL ( PV + BES ) QL (7.9) where the total reactive power loss (QL) in a radial distribution system with n branches can be calculated as Equation (4.19). 7.3.3 Multiobjective Index The multiobjective index (IMO) is a combination of the ILP and ILQ indices, respectively related to energy loss and voltage stability by assigning a weight to each index. The IMO index that can be utilized to assess the performance of a distribution system with PV and BES inclusion can be expressed as follows: IMO = σ 1ILP + σ 2 ILQ where ∑i=1σ i = 1.0 ∧ σ i ∈ [0, 1.0] . 2 (7.10) This can be performed since all impact indices are normalized (values between zero and one) [29]. When hybrid PV and BES systems are not connected to the system (i.e., base case system), the IMO is the highest at one. These weights are intended to give the corresponding importance to each impact index for the connection of hybrid PV-BES systems and depend on the required analysis (e.g., planning and operation) [29, 54, 55, 58]. The determination of suitable values for the weights will also rely on the experience and concerns of engineers. The integration of hybrid PV-BES systems has a significant impact on the energy loss and voltage stability of distribution networks. Currently, the energy loss is one of the major concerns at the CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 102 distribution system scale due to its impact on the utilities’ profit, while the voltage stability is less important than the energy loss. Therefore, the weight for the energy loss should be higher than that for the voltage stability. In future, if the importance of voltage stability is increased due to high intermittent renewable penetration and an increase in loads and system security, the weights can be adjusted based on the priority. Considering the above current concerns and referring to previous research papers [29, 54, 55, 58], this study assumes that the active power loss related to energy loss receives a significant weight of 0.7, leaving the reactive power loss related to voltage stability at a weight of 0.3. The IMO at period t, IMO (t ) is obtained from Equation (7.10). Hence, the average multiobjective index (AIMO) over the total period (T = 24 hours) in a distribution system with an interval ( ∆t ) of 1 hour can be expressed as follows: T AIMO = 1 1 24 IMO ( t ) dt = ∑ IMO(t )∆t T ∫0 24 t =1 (7.11) The lowest AIMO implies the best PV and BES allocation for energy loss reduction and voltage stability enhancement. The objective function defined by the AIMO in Equation (7.11) is subject to technical constraints as follows. The bus voltages ( Vk ) must remain within acceptable limits in all periods Vmin ≤ Vk (t ) ≤ Vmax (7.12) 7.3.4 Energy Loss and Voltage Stability Energy Loss The active power loss at each period t, Ploss (t ) can be obtained from Equation (4.18) without a PV-BES unit or Equation (7.6) with a PV-BES unit. Hence, the total annual energy loss ( Eloss ) over the total period (T = 24 hours) in a distribution system with a time duration ( ∆t ) of 1-h can be expressed as: T 24 0 t =1 Eloss = 365∫ Ploss (t )dt = 365∑ Ploss (t )∆t (7.13) CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 103 Voltage Stability The static voltage stability can be analyzed using the relationship between the receiving Power (P) and the Voltage (V) at a certain bus in a distribution power system, as illustrated in Figure 7.2. This curve is known as a P-V curve and obtained using the CPF technique [131]. The Critical Point (CP) or the voltage collapse point in the curve represents the maximum loading (λmax) of the system. The Voltage Stability Margin (VSM) is defined as the distance from an operating point to the critical point. As shown in Figure 7.2, the scaling factor of the load demand at a certain operating point (λ) varies from zero to λmax. When a hybrid PV-BES system is properly injected in the system, the loss reduces. Accordingly, the V1 and CP1 enhance to V2 and CP 2 , respectively. Hence, the maximum loadability increases from λmax1 to λmax2 as defined as follows [45, 51]. The voltage stability margin subsequently improves from VSM1 to VSM2. PD = λPDo ; QD = λQDo (7.14) where PDo and QDo correspond to the initial active and reactive power demands, respectively. 1.1 Without DG unit 1.0 With DG unit V2 V1 0.9 Voltage (p.u.) 0.8 0.7 VSM2 0.6 VSM1 0.5 CP1 0.4 0.3 00 1 2 (λ) Loading parameter 3 CP2 λmax1 4λmax2 Figure 7.2. Hybrid PV-BES system impact on maximum loadability and voltage stability margin [45, 51]. CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 7.4 104 Proposed Methodology 7.4.1 Proposed Analytical Expressions Most of the current analytical approaches have addressed PV placement in distribution systems for active power loss minimization as a single-objective index [21-25]. Chapter 4 also presented the analytical approaches to accommodate renewable DG units for energy loss reduction only. In addition, a multiobjective index (IMO)-based analytical approach was reported in Chapter 6, but it can be used for the PV allocation only. This section presents new analytical expressions based on the multiobjective index (IMO) defined by Equation (7.10) to calculate the size and power factor of a mix of PV and BES units. Substituting Equations (7.7) and (7.9) into Equation (7.10), we obtain: IMO( Pk , ak ) = σ1 PL PL ( PV + BES ) + σ2 QL QL ( PV + BES ) (7.15) As given in Equation (7.15), the IMO variation is a function of the PV-BES penetration level related to variables Pk and ak (or pf k : the power factor of the PV-BES mix at bus k). At the minimum IMO, the partial derivative of Equation (7.15) with respect to both variables at bus k becomes zero. ∂IMO σ 1 ∂PL ( PV + BES ) σ 2 ∂QL ( PV + BES ) = + =0 ∂P k PL ∂Pk QL ∂Pk (7.16) ∂IMO σ 1 ∂PL ( PV + BES ) σ 2 ∂QL ( PV + BES ) = + =0 ∂a k ∂ak ∂ak PL QL (7.17) The derivative of Equations (7.6) and (7.8) with respect to Pk can be expressed as follows: ∂PL ( PV + BES ) 2 = −2 Ak + 2 Bk Pk − 2Ck ak + 2 Bk ak Pk ∂Pk (7.18) ∂QL ( PV + BES ) 2 = −2 Dk + 2 Ek Pk − 2ak Fk + 2ak Ek Pk ∂Pk (7.19) CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY k where Ak = ∑ i =1 k Dk = ∑ i =1 k Ri Pbi Vi 2 i =1 X i Pbi Vi ; Bk = ∑ 2 k ; Ek = ∑ i =1 k Ri Vi 2 Vi 2 Ri Qbi ; Ck = ∑ Vi i =1 k Xi ; Fk = ∑ 105 2 X i Qbi i =1 Vi 2 Substituting Equations (7.18) and (7.19) into Equation (7.16), we get: Pk = σ 1 ( Ak + Ck ak )QL + σ 2 ( Dk + ak Fk ) PL 2 2 σ 1 ( Bk + Bk ak )QL + σ 2 ( Ek + Ek ak ) PL (7.20) The derivative of Equations (7.6) and (7.8) with respect to ak can be expressed as follows: ∂PL ( PV + BES ) 2 = −2Ck Pk + 2 Bk ak Pk ∂ak (7.21) ∂QL ( PV + BES ) 2 = −2 Fk Pk + 2ak Ek Pk ∂ak (7.22) Substituting Equations (7.21) and (7.22) into Equation (7.17), we obtain: ak = σ 1Ck QL + σ 2 Fk PL Pk (σ 1Bk QL + σ 2 Ek PL ) (7.23) The relationship between the power factor of a PV-BES unit ( pf k ) and variable ak at bus k can be expressed as follows: ( pf k = cos tan −1 (ak )) (7.24) At the minimum IMO, the optimal size and power factor at bus k, period t (i.e., Pk (t ) and pf k (t ) , respectively) can be obtained from Equations (7.20), (7.23) and (7.24) as: Pk (t ) = σ 1 Ak (t )QL (t ) + σ 2 Dk (t ) PL (t ) σ 1Bk (t )QL (t ) + σ 2 Ek (t ) PL (t ) (7.25) CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY −1 σ C (t )QL (t ) + σ 2 Fk (t ) PL (t ) pf k (t ) = cos tan 1 k σ A ( t ) Q ( t ) σ D ( t ) P ( t ) + 1 k L 2 k L 106 (7.26) The optimal size and power factor of a single PV-BES unit for each period can be calculated using Equations (7.25) and (7.26), respectively. When multiple PV-BES units are considered, the SCA developed below is employed. 7.4.2 Self-Correction Algorithm Sizing PV-BES This section presents a new algorithm to size multiple PV-BES units, which are known as a combination of PV and BES units, at a number of pre-specified buses to minimize the active and reactive power losses at each load level. As proposed in Section 7.2.1, each PVBES unit is placed at the same bus. Here, the PV-BES unit is modelled as a dispatchable source. The algorithm includes two tasks. The first task is to calculate the approximate size and power factor of the PV-BES unit using Equations (7.25) and (7.26) at pre-specified buses, respectively. The second task is to re-calculate the size and power factor of each PV-BES unit obtained previously using Equations (7.25) and (7.26), respectively. The second task is repeated until the difference between the last and previous IMO values is reached to a pre-defined tolerance (zero in this study). The algorithm involves the following steps: Step 1: Set buses to install PV-BES units. Step 2: Run load flow for the first period and calculate the size and power factor of each PV-BES unit for each bus using Equations (7.25) and (7.26), respectively. Find the IMO for each case using Equation (7.10). Locate the bus where the IMO is the lowest with the corresponding size and power factor. Update the load data with the PV-BES unit obtained at this bus. Repeat Step 2 for the rest of the selected buses. Step 3: Re-calculate the size and power factor by repeating Step 2 until the difference between the last and previous IMO values is reached to zero. Step 4: Repeat Steps 2 to 3 for the rest periods. Calculate the AIMO using Equation (7.11). The above algorithm is developed to place PV-BES units considering the optimal power factor. This algorithm can be modified to allocate PV-BES units with a pre-specified CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 107 power factor. When the power factor is pre-specified, the algorithm is similar to the above with exception that in Step 2, the size of the PV-BES unit for each bus is determined using Equation (7.20) rather than Equation (7.25). After the size of the combination of the PVBES unit is found for each bus, two additional analyses explained below are implemented to capture the individual size of the PV and BES units for each selected bus. Sizing PV As shown in Figure 7.1a-b, the daily charging and discharging energies at bus k is obtained from the hourly input and output power of the BES unit. T CH EBES k =∫ CH PBES k 24 (t )dt = ∑ PBES k (t )∆t CH T 24 E BES k = ∫ PBES k (t )dt = ∑ PBES k (t )∆t DISCH (7.27) t =1 0 DISCH DISCH (7.28) t =1 0 The total output energies of the PV-BES mix and PV unit at bus k is respectively calculated as follows: E( PV + BES ) k = EPVk + EBES k (7.29) E PVk = E PVk + E BES k (7.30) GRID GRID GRID where E PVk DISCH CH is the amount of PV energy delivering to the grid at bus k. The charging and discharging energy of the BES unit at bus k with a round trip efficiency ( η BES = ηc ×ηd ) is expressed as: DISCH E BES k = η BES E BES k CH (7.31) The total output energy of the PV unit at bus k can be obtained from Equations (7.29), (7.30) and (7.31) as follows: E( PV + BES ) k − (1 − η BES )E PVk GRID E PVk = η BES (7.32) CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 108 The maximum power generation of the PV unit during a specific period over a 24-h day cycle is utilized to specify the power rating or optimal size of the PV unit at bus k. PPVk = k PV EPVk unit (7.33) unit where k PV = unit amount of PPV unit EPV unit unit , PPV is the maximum output of a PV module unit, and E PV is the PV generated energy over a 24-h day. Assuming η BES =1, i.e., E PVk = E( PV + BES ) k , the initial PV size is calculated from Equation (7.33) as PPVk = k PV E( PV + BES ) k , and E PVk ' unit GRID ' is then obtained from Figure 7.1a-b, for example. When ηBES is less than unity, PPVk increases. However, as demonstrated in the simulation GRID GRID ' results, E PVk rises insignificantly compared to E PVk . Hence, the optimal PV size is obtained from Equations (7.32) and (7.33) as follows: PPVk = E unit k PV ( PV + BES ) k GRID ' − (1 − η BES )EPVk η BES (7.34) Sizing BES The optimal size of the BES unit at bus k is calculated with respect to the power rating ( PBES k ) and energy capacity ( E BES k ) such that it can accommodate all redundant energy of the PV unit that needs to be curtailed to maintain the system loss for each period at the lowest level. The maximum charging and discharging power during a specific period across a 24-h day cycle is utilized to specify the power rating of the BES unit. The maximum charging energy during this cycle is used to determine the energy capacity of the BES unit. 7.5 Case Study 7.5.1 Test System The proposed methodology was applied to the 33-bus distribution system depicted in CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 109 Figure 3.1. The system demand follows a commercial load curve illustrated in Figure 6.1. It is assumed that operating voltages are from 0.95 to 1.05 p.u. The hourly expected output of the PV module is plotted in Figure 6.8. Three PV units are assumed to be allocated at buses 12, 20 and 24. Sodium-sulfur BES unit considered has a roundtrip efficiency of 77%. To demonstrate the effectiveness of the methodology, the following scenarios are considered. • Scenario 1: Three PV-BES units that can generate both active and reactive power at optimal power factor for each period, as proposed in this chapter. • Scenario 2: Three PV-BES units that can deliver active power only (i.e., unity power factor) for all periods as per the standard IEEE 1547 [99]. 7.5.2 Numerical Results Sizing PV and BES Units Figure 7.3a-c shows the results of PV-BES placement with optimal power factor dispatch at buses 12, 20 and 24 for scenario 1. The number of PV-BES units can be limited due to the availability of PV resources and geographic limitations. The output and power factor of PV-BES units are optimally dispatched for each 1-h period across a 24-h day cycle such that the system can achieve the lowest IMO for each period. As shown in Figure 7.3a, PVBES units 1, 2 and 3 correspond to the PV-BES units located at buses 12, 20 and 24 respectively. The output curves of these PV-BES units follow the load demand pattern in Figure 3.1 as the PV-BES units are dispatchable sources. It can be seen from Figure 7.3b that the power factor of PV-BES unit 1 at bus 12 is dispatched for each period across a 24h day in the range of 0.860 and 0.867 (lagging). For PV-BES unit 2 at bus 20, the power factor varies from 0.899 to 0.901 (lagging). Similarly, the power factor of PV-BES unit 3 at bus 24 varies between 0.872 and 0.876 (lagging). Figure 7.3c shows the ILP, ILQ and IMO values for each period related to the active power loss, reactive power loss and multiobjective indices respectively after the three PV-BES units are installed in the system. Significant reductions in the indices ILP, ILQ and IMO show the positive effect of three PV-BES units placement on the system. At each period, the ILP is lower than the ILQ, indicating that the system can benefit more from reducing the active power loss than the reactive power loss. Similar results have been obtained for scenario 2 (i.e., the PV-BES unit is capable of delivering active power only). CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 1.5 110 PV-BES 1 Ouput (MW) PV-BES 2 1.0 PV-BES 3 0.5 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (a) 0.910 PV-BES 1 PV-BES 2 PV-BES 3 Power factor 0.900 0.890 0.880 0.870 0.860 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (b) ILP/ILQ/IMO 0.38 ILQ ILP IMO 0.37 0.36 0.35 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour (c) Figure 7.3. Daily PV-BES outputs, power factor and index curves for scenario 1: (a) PVBES outputs, (b) Power factor of PV-BES units, (c) Indices with three PV-BES units. CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 111 Table 7.1 summaries the results of PV-BES placement for scenarios 1 and 2, including the optimal size and power factor for each location. The optimal size of each PV-BES unit which corresponds to its maximum output at hour 11 is obtained from Figure 7.3a. Table 7.1 also shows the AILP, AILQ and AIMO values which correspond to the average active power loss, average reactive power loss and average multiobjective indices over 24 hours across the day, respectively. It can be seen from Table 7.1 that in scenario 1, the power factors of the PV-BES units at buses 12, 20 and 24 are different at 0.867, 0.901 and 0.876 (lagging), respectively. It is also observed from the table that operation of the PV-BES units with power factor dispatch for each period in scenario 1 can make a significant contribution to minimising the AIMO when compared to that with unity power factor in scenario 2. Table 7.1. PV-BES placement with optimal lagging and unity power factors Scenario Bus Size (MW) Power factor AILP AILQ AIMO 1 12 1.160 0.867 0.3484 0.3691 0.3546 20 0.326 0.901 24 1.164 0.876 12 1.155 1.000 0.5150 0.5255 0.5181 20 0.327 1.000 24 1.167 1.000 2 Figure 7.4 presents the hourly expected PV output at bus 12 for scenario 1 with optimal power factor dispatch. This curve exactly follows the expected PV output curve in Figure 3.2. The maximum output of each PV unit that is indentified at hour 12 indicates its optimum size. The figure also shows the amount of energy that the PV unit can generate versus the amount of PV-BES energy accommodated by the network to retain the loss for each period at the lowest level. The sum of the hourly differences between these two patterns identifies the amounts of energy charged and discharged by the BES unit. The amount of PV energy that needs to be curtailed to remain the minimum energy loss is stored into the BES unit. This stored energy portion is then discharged to the grid CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 112 following the PV-BES output curve to keep the lowest energy loss as well. The maximum difference found at hour 13 gives the maximum power of the charging energy or the power rating of the BES unit ( PBES ). The maximum charging energy over a 24-h day cycle is used to calculate the capacity of the BES unit ( E BES ). The charging and discharging time of the BES unit can be identified from Figure 7.4. Similar results have been found for the PV-BES units at buses 20 and 24 in scenario 1 (optimal power factor) and buses 12, 20 and 24 in scenario 2 (unity power factor) as well. PV-BES output 1.0 PPV Output (MW) 1.5 PBES PV output BES charging from PV 2.0 0.5 0.0 BES discharging to grid PV generating to grid BES discharging to grid 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Figure 7.4. Daily charging and discharging curves of BES unit at bus 12 for scenario 1. Tables 7.2 and 7.3 summarize the results of the size of PV units and the power rating and energy capacity of BES units for each location in scenarios 1 and 2, respectively. It is observed from the tables that the similarity in the size of the PV units in MW, the power rating of the BES units in MW and the energy capacity of the BES units in MWh exist between scenarios 1 and 2. However, as previously mentioned, the PV-BES units in scenario 1 deliver both active and reactive power at optimal lagging power factor for each period across a 24-h day (see Figure 7.3b), as proposed in this chapter, whereas the PVBES units in scenario 2 only supply active power over all periods as per the standard IEEE 1547 [99]. Particularly, as shown in Table 7.2, the total size of the PV units is 4.336 MW of the active power and 2.396 MVAr of the reactive power. The total active and reactive power ratings of the BES units are 1.804 MW and 0.997 MVAr, respectively and the total energy capacity of the BES units over the day is 13.544 MWh. In this scenario, the BES CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 113 units also either absorb or inject the amount of reactive power for each hour of the day. For scenario 2, as shown in Table 7.3, the total active power size of the PV units is 4.336 MW. The total active power rating of the BES units is 1.803 MW and the total energy capacity of the BES units over the day is 13.549 MWh. Unlike scenario 1, in this scenario, as the BES units operate at unity power factor, there is no reactive power delivered or absorbed by these units. Table 7.2. Sizing PV and BES units at optimal lagging power factor (Scenario 1) Bus 12 20 24 Total PV size (MW) 1.858 0.526 1.952 4.336 PV size (MVAr) 1.068 0.253 1.075 2.396 BES power rating (MW) 0.770 0.221 0.813 1.804 BES power rating (MVAr) 0.443 0.106 0.448 0.997 BES energy capacity (MWh) 5.750 1.655 6.139 13.544 Table 7.3. Sizing PV and BES units at unity power factor (Scenario 2) Bus 12 20 24 Total PV size (MW) 1.858 0.526 1.952 4.336 BES power rating (MW) 0.773 0.220 0.810 1.803 BES energy capacity (MWh) 5.786 1.648 6.115 13.549 Energy Loss and Voltage Stability Figures 7.5 and 7.6 show the results of energy loss and PV curve-based voltage stability margin of the system with and without the PV-BES units, respectively. The power factors of the PV-BES units is set at unity in compliance with the current standard IEEE 1547 [99] and optimally dispatched for each period as proposed in this chapter. It is observed from the figures that operation of the PV-BES units with optimal power factor dispatch (scenario 1) can significantly reduce energy loss and better enhance voltage stability when compared to that with unity power factor (scenario 2). CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 114 As illustrated in Figure 7.5, the system power loss for scenario 1 with optimal power factor dispatch for each period is rather lower than that for scenario 2 with unity power factor. Table 7.4 summarizes the results of the annual energy losses of the system for all scenarios. Before PV-BES insertion (i.e., for the base case scenario), the annual energy loss is 701.33 MWh. After PV-BES installation, scenario 1 obtains a maximum energy loss reduction of 70.44%, whereas scenario 2 achieves an energy loss reduction of 56.55% only. As shown in Figure 7.6, V is the normal operating point voltages (λ = 1), λmax is the maximum loading, VSM is the voltage stability margin that is defined as the distance from the operating point to a voltage collapse point or a critical point (CP), ∆VSM is an increase in the voltage stability margin. In scenario 1, when three PV-BES units generate an amount of 2.65 MW at their optimal power factors found in Table 7.1, the normal operating point voltage at the weakest point (bus 18) improves from V0 (without PV-BES units) to V1 (with PV-BES units). The maximum loading increases from λmax0 (without PV-BES units) to λmax1 (with PV-BES units). Hence, the voltage stability margin in scenario 1 (∆VSM1) is enhanced by roughly 0.29. Similarly, the ∆VSM2 in scenario 2 is increased by approximately 0.25. These results are summarized in Table 7.4. It is obvious that the combination of the PV and BES units with optimal power factor dispatch for each period (scenario 1) achieves a larger VSM value than that with unity power factor (scenario 2). Figure 7.7 presents the voltage profiles for scenarios: without the PV-BES units (base case scenario) and with the PV-BES units at the optimal and unity power factors (i.e., scenarios 1 and 2, respectively) at the extreme periods where the voltage profiles are worst. Without the PV-BES units, the extreme period is specified at the peak period 11 as depicted in Figure 7.7, at which the voltages at several buses are under the lower limit of 0.95 p.u. With the PV-BES units, by considering the combination of the demand and PVBES output curves, the extreme period is identified at the peak period 11. It is observed from Figure 7.7 that after the PV-BES units are integrated at the extreme periods, the voltage profiles improve significantly. The voltage profile in scenario 1 is better than that in scenario 2. CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 160 No PV-BES Power loss (kW) PV-BES, unity PF 120 PV-BES, optimal PF 80 40 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Figure 7.5. PV-BES impact on energy loss. 1.2 No PV-BES PV-BES, optimal PF V2 V1 V0 1.0 Voltage (p.u.) PV-BES, unity PF 0.8 VSM 2 0.6 VSM 1 CP 1 CP 2 0.4 CP 0 VSM 0 ∆ VSM 2 ∆VSM 1 λ max0 λ max1λ max2 0.2 0 1 2 3 Loading parameter (λ ) 4 5 Figure 7.6. PV-BES impact on maximum loadability and voltage stability margin. Voltage (p.u.) 1.02 No PV-BES PV-BES, unity PF PV-BES, optimal PF 0.98 0.94 0.90 1 3 5 7 9 11 13 15 17 19 21 23 25 27 Bus Figure 7.7. Voltage profiles at extreme periods for all scenarios. 29 31 33 115 CHAPTER 7. PV AND BES INTEGRATION FOR ENERGY LOSS AND VOLTAGE STABILITY 116 Table 7.4. Energy loss and voltage stability Scenario 7.6 Annual energy loss Annual loss reduction (MWh) (%) Voltage stability V (p.u.) λmax 0.9175 4.1217 ∆VSM Base case 701.33 1 207.31 70.44 0.9878 4.4120 0.2903 2 304.72 56.55 0.9663 4.3673 0.2456 Summary This chapter presented a new methodology to accommodate a combination of PV and BES units for reducing energy loss and enhancing voltage stability in distribution systems. Here, each nondispatchable PV unit is converted into a dispatchable source with a combination of PV and BES units. New IMO-based analytical expressions were proposed to calculate the size and power factor of the PV-BES combination. A self-correction algorithm was developed as well to size multiple PV and BES units while considering the time-varying demand and probabilistic generation. The power factors are optimally dispatched at each load level. The Beta PDF model was employed to describe the probabilistic nature of solar irradiance. The results indicated that the model can support high PV penetration associated with an efficient usage of BES sources. Operation of PV and BES units with optimal power factor dispatch for each load level can significantly reduce energy losses and better enhance voltage stability when compared to that with unity power factor which currently follows the standard IEEE 1547. This result implies that the standards and regulatory frameworks regarding PV planning and operations need to be revised. CHAPTER 8 BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 8.1 Introduction Chapters 4-7 presented approaches to integrate renewable DG and its operating strategies for energy loss reduction and voltage stability enhancement in distribution systems. However, the size of DG units obtained from the existing studies may not match the standard sizes available in the market. Furthermore, a comprehensive benefit-cost study on multiple DG planning with optimal power factor that considers the issues of energy losses and voltage stability has not been reported in the literature. In this chapter, analytical expressions are presented based on a multi-objective index (IMO) to determine the optimal power factor for reducing energy losses and enhancing voltage stability in industrial distribution systems over a given planning horizon. Here, new analytical expressions are developed to efficiently capture the optimal power factor of each DG unit with a commercial standard size to ease the computational burden. In this study, it is assumed that DG units are owned and operated by distribution utilities. To make the work comprehensive, in addition to the analytical expressions presented to specify the optimal power factor, a benefit-cost analysis is carried out in this work to determine the optimal location, size and number of DG units. The total benefit as a sum of energy sales, energy loss reduction, network upgrade deferral and emission reduction is 117 CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 118 compared to the total cost including capital, operation and maintenance costs. The methodology is applied to a 69-bus industrial distribution system. 8.2 Load and DG Modelling 8.2.1 Load Modelling The system considered under the study is assumed to follow the industrial load duration curve as shown in Figure 8.1, including four discrete load bands (maximum, normal, medium and minimum) that change as the load grows over a planning horizon. The load factor or average load level of the system over the base year, LFbase can be defined as the ratio of the area under load curve to the total duration (four load bands: 8760 hours). That means LFbase = 8760 ∑ t =1 p.u. load (t ) , where p.u. load (t) is the demand in p.u. at period t. 8760 Assuming the growth rate of demand a year (δ), the load factor or average load level of the system over a given planning horizon (Ny), LF can be calculated as: 1 Ny 8760 p.u. load (t ) y LF = × (1 + δ ) ∑ ∑ Ny y =1 t =1 8760 (8.1) The time-varying industrial load model defined in Section 3.2 is considered in this work. Figure 8.1. Nominalised Load duration curve. CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 119 8.2.2 DG Modelling As described in Section 3.3.1, gas turbine engines fuelled by biogas produced from biomass materials are adopted in this work. The biogas can be considered as natural gas standards. As a synchronous generator, the biomass gas turbine-based DG unit is capable of delivering active power and injecting or absorbing reactive power. It is assumed that the DG units offer constant output powers at their rated capacities. Given PDGi and QDGi values which correspond to the active and reactive power of a DG unit injected at bus i, the power factor of the DG unit at bus i ( pf DGi ) can be expressed as follows: opf DGi = 8.3 PDGi 2 PDGi + QDGi 2 (8.2) Problem Formulation 8.3.1 Impact Indices Active and reactive power loss indices have been used to evaluate the impact of DG inclusion in a distribution system [29, 54, 55, 57]. These indices play a critical role in DG planning and operations due to their significant impacts on utilities’ revenue, power quality, system stability and security, and environmental efficiency. In this study, the active and reactive power loss indices are utilized for reducing power losses and enhancing voltage stability. Active Power Loss Index Substituting Equations (4.5) and (4.6) into Equation (4.3), we obtain the total active power loss with a DG unit (PLDG) as follows: N N α ij ( ( PDGi − PDi ) Pj + ( QDGi − QDi ) Q j ) PLDG = ∑∑ i =1 j =1 + βij ( ( QDGi − QDi ) Pj − ( PDGi − PDi ) Q j ) (8.3) The active power loss index (ILP) is defined as the ratio of Equations (8.3) and (4.3) as follows: CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION ILP = PLDG PL 120 (8.4) where PL is calculated using Equations (4.3). Reactive Power Loss Index Substituting Equation (4.5) and (4.6) into Equation (4.4), we obtain the total reactive power loss with DG unit (QLDG) as follows: N N γ ij ( ( PDGi − PDi ) Pj + ( QDGi − QDi ) Q j ) QLDG = ∑∑ ξ + Q − Q P − P − P Q ( ) ( ) ( ) ij DGi Di j DGi Di j i =1 j =1 (8.5) The reactive power loss index (ILQ) is defined as the ratio of Equations (8.5) and (4.4) as follows: ILQ = QLDG QL (8.6) where QL is calculated using Equations (4.4). 8.3.2 Multiobjective Index The multiobjective index (IMO) is a combination of the ILP and ILQ impact indices, which are respectively related to energy loss and voltage stability by giving a weight to each impact index. This IMO index can be expressed by Equation (8.7) which is subject to the constraint on the pre-specified apparent power of DG capacity ( S DGi ) through a relationship between PDGi and QDGi . That means: IMO = σ 1ILP + σ 2 ILQ S DGi = PDGi + QDGi 2 subject to where (8.7) ∑i=1σ i = 1.0 ∧ σ i ∈ [0, 1.0] . 2 2 2 This can be performed as all impact indices are normalized with values between zero and one [29]. When DG units are not connected to the system (i.e., base case system), the IMO is the highest at one. As described in Section CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 121 7.3.3, this study assumes that the active power loss related to energy loss receives a significant weight of 0.7, leaving the reactive power loss related to voltage stability at a weight of 0.3. The lowest IMO implies the best DG allocation for energy loss reduction and voltage stability enhancement. The objective function defined by the IMO in Equation (8.7) is subject to technical constraints described below. 8.3.3 Technical Constraints The maximum DG penetration, which is calculated as the total capacity of DG units, is limited to less than or equal to a sum of the total system demand and the total system loss. N N N N i=2 i =2 i=2 i=2 ∑ PDGi ≤ ∑ PDi + PL ; ∑ QDGi ≤ ∑ QDi + QL (8.8) where PL and QL are respectively calculated using Equations (4.3) and (4.4). The voltage at each bus is maintained close to the nominal voltage. Vi min ≤ Vi ≤ Vi max (8.9) where Vi min and Vi max are respectively the lower and upper bounds of the voltage at bus i, Vi = 1 p.u. (substation nominal voltage). max The thermal capacity of circuit n ( S n ) is less than the maximum apparent power transfer ( S n ). Sn ≤ S n max (8.10) 8.3.4 Energy Loss and Voltage Stability Energy Loss The total active power loss of a system with a DG unit at each period t, Ploss (t ) can be obtained from Equation (4.7). Here, the total period duration of a year is 8760 hours, which CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 122 are calculated as a sum of all the total period durations of all the load levels throughout a year as shown in Figure 8.1. The total annual energy loss in a distribution system can be calculated as ALoss y = 8760 ∑ Ploss (t ) . Hence, the total energy loss over a given planning t =1 horizon (Ny), E Loss can be expressed as: Ny 8760 E Loss = ∑ ∑ Ploss ( y, t ) × ∆t (8.11) y =1 t =1 where ∆t is 1 hour, which is the time duration of period t. Voltage Stability As described in Section 6.2, static voltage stability in a power system can be analyzed using a P–V curve, which is obtained using the continuous power flow method [131]. As DG units are injected appropriately in the system, the VSM increases. The power of the load demands increases by a scaling factor ( λ ) as defined by Equation (7.14). 8.3.5 Benefit and Cost Analysis Utility’s Benefit The present value benefit (B) in $ given to a utility to encourage DG connection over a planning horizon from owning and sitting its own DG units can be expressed as follows: Ny B=∑ y =1 R y + LI y + EI y (1 + d ) y N + ND ∑ PDGi (8.12) i =2 where all annual values are discounted at the rate d; Ry is the annual energy sales ($/year); LIy is the loss incentive ($/year); EI y is the emission incentive ($/year); ND is the network deferral benefit ($/kW); PDGi is the total DG capacity connected at bus i (kW); and Ny is the planning horizon (years). The LIy can be written as [68, 69]: LI y = CLoss y (TLoss y − ALoss y ) where CLossy is the loss value ($/MWh), ALossy is the actual annual energy loss of the CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 123 system with DG units (MWh), and TLossy is the target level of the annual energy loss of the system without DG units (MWh). When DG units are integrated into the grid for primary energy supply purposes, the environmental benefit as a result of reducing the usage of fossil fuel energy resources could be obtained. The EIy including the emission produced by the electricity purchased from the grid and DG units can be formulated as [74]: EI y = CE y (TE y − AE y ) where CEy is the cost of each ton of generated CO2 ($/TonCO2); AEy is the actual annual emission of a system with DG units (TonCO2); TEy is the target level of the annual emission of the system without DG unit (TonCO2). Utility’s Cost The present value cost (C) in $ incurred by a distribution utility over a planning horizon can be expressed as [68, 69]: Ny C=∑ y =1 OM y (1 + d ) y N + C DG ∑ PDGi (8.13) i=2 where OMy is the annual operation, maintenance and fuel costs ($/year) in year y; CDG is the capital cost of a DG unit ($/kW). Benefit-Cost Ratio Analysis The benefit to cost ratio (BCR) can be expressed as follows: BCR = B C (8.14) where the B and C are calculated using Equations (8.12) and (8.13), respectively. The decision for the optimal location, size and number of DG units is obtained when the BCR as given by Equation (8.14) is highest. CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 8.4 124 Proposed Methodology As discussed in Chapter 4, it becomes necessary to study the optimal power factor of DG units for minimising power losses to which the active and reactive power injections of each DG unit are optimized simultaneously. 8.4.1 Optimal Power Factor In practice, the choice of the best DG capacity may follow commercial standard sizes available in the market or be limited by energy resource availability. Given such a prespecified DG capacity, the DG power factor can be optimally calculated by adjusting the active and reactive power sizes at which the IMO as defined by Equation (8.7) can reach a minimum level. Using the Lagrange multiplier method, we can mathematically convert the constrained problem defined by Equation (8.7) into an unconstrained one as follows: ( L(PDGi , QDGi , λi ) = σ 1ILP + σ 2 ILQ + λi S DGi − PDGi − QDGi 2 2 2 ) (8.15) where λi is the Lagrangian multiplier. Substituting Equations (8.4) and (8.6) into Equation (8.15), we obtain: L= σ1 PL PLDG + σ2 QL ( QLDG + λi S DGi − PDGi − QDGi 2 2 2 ) (8.16) The necessary conditions for the optimization problem, given by Equation (8.16), state that the derivatives with respect to control variables PDGi , QDGi and λi become zero. ∂L σ ∂P σ Q = 1 LDG + 2 LDG − 2λi PDGi = 0 ∂PDGi P L ∂PDGi QL ∂PDGi (8.17) ∂L σ ∂P σ Q = 1 LDG + 2 LDG − 2λi QDGi = 0 ∂QDGi P L ∂QDGi QL ∂QDGi (8.18) ∂L 2 2 2 = PDGi + QDGi − S DGi = 0 ∂λi (8.19) The derivative of Equations (8.3) and (8.5) with respect to PDGi and QDGi are given as: CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 125 N ∂PLDG = 2∑ [α ij Pj − β ij Q j ] = 2α ii Pi + 2 Ai ∂PDGi j =1 (8.20) N ∂QLDG = 2∑ [γ ij Pj − ξ ij Q j ] = 2γ ii Pi + 2Ci ∂PDGi j =1 (8.21) N ∂PLDG = 2∑ [α ij Q j + β ij Pj ] = 2α ii Qi + 2 Bi ∂QDGi j =1 (8.22) N ∂QLDG = 2∑ [γ ij Q j + ξij Pj ] = 2γ ii Qi + 2 Di ∂QDGi j =1 (8.23) where N N j =1 j ≠i j =1 j ≠i N N j =1 j ≠i j =1 j ≠i Ai = ∑ (α ij Pj − β ij Q j ) ; Bi = ∑ (α ij Q j + β ij Pj ) ; Ci = ∑ (γ ij Pj − ξij Q j ) ; Di = ∑ (γ ij Q j + ξij Pj ) Substituting Equations (8.20) and (8.21) into Equation (8.17), we obtain: 2σ 1 [α ii Pi + Ai ] + 2σ 2 [γ ii Pi + Ci ] − 2λi PDGi = 0 PL QL (8.24) Substituting Equation (4.5) into Equation (8.24), we obtain: PDiYi − PDGi = where Yi = σ 1 Ai − σ 2Ci PL Yi − λi σ 1α ii PL + QL (8.25) σ 2γ ii QL Similarly, substituting Equations (8.22) and (8.23) into Equation (8.18), we obtain: 2σ 1 [α ii Qi + Bi ] + 2σ 2 [γ iiQi + Di ] − 2λi QDGi = 0 PL QL (8.26) CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 126 Substituting Equation (4.6) into Equation (8.26), we obtain Equation (8.27), where Yi is given in Equation (8.25). QDiYi − QDGi = σ 1Bi PL Yi − λi − σ 2 Di QL (8.27) Substituting Equations (8.25) and (8.27) into Equation (8.19), we obtain: Yi − λi = ± 2 1 S DGi σ A σ C σB σ D PDiYi − 1 i − 2 i + QDiYi − 1 i − 2 i PL QL PL QL 2 (8.28) Substituting Equation (8.28) into Equations (8.25) and (8.27), we obtain: PDGi = ± QDGi = ± σ A σ C PDiYi − 1 i − 2 i S DGi PL QL 2 σ A σ C σB σ D PDiYi − 1 i − 2 i + QDiYi − 1 i − 2 i PL QL PL QL 2 σB σ D QDiYi − 1 i − 2 i S DGi PL QL 2 σ A σ C σB σ D PDiYi − 1 i − 2 i + QDiYi − 1 i − 2 i PL QL PL QL 2 (8.29) (8.30) It is observed from Equation (8.29) that PDGi can be positive or negative, depending on the characteristic of system loads. However, the load power factor of a distribution system without reactive power compensation is normally in the range from 0.7 to 0.95 lagging (inductive load). PDGi is assumed to be positive in this study, i.e., the DG unit delivers active power. QDGi can be positive or negative, as given by Equation (8.30). QDGi can be positive with inductive loads or negative with capacitive loads (i.e., the DG unit injects or absorbs reactive power). Given a S DGi value is pre-defined, the optimal PDGi and QDGi values are respectively calculated using Equations (8.29) and (8.30) to minimize the IMO as defined by Equation (8.7), after running only one load flow for the base case system. Accordingly, the optimal CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 127 power factor ( pf DGi ) value is specified using Equation (8.2). Any power factors rather than the optimal pf DGi value will lead to a higher IMO. 8.4.2 Computational Procedure DG units are considered to be placed at an average load level (LF), defined by Equation (8.1), over a given planning horizon, which has the most positive impact on the IMO. This also reduces the computational burden and the search space. The energy loss given by Equation (8.11) is calculated by a multiyear multiperiod power flow analysis over the planning horizon. The computational procedure is explained for each step as follows: Step 1: Set the apparent power of DG units ( S DGi ) and the maximum number of buses to connect DG units. Step 2: Run load flow for the system without DG units at the average load level over the planning horizon (LF) using Equation (8.1). Step 3: Find the optimal power factor of each DG unit for each bus using Equation (8.2). Place this DG unit at each bus and find the IMO for each case using Equation (8.7). Step 4: Locate the optimal bus for DG installation at which the IMO is the lowest with the corresponding optimal size and power factor at that bus. Step 5: Run multiyear multiperiod load flow with the DG size obtained in Step 4 over the planning horizon. Calculate the energy loss and its corresponding BCR using Equations (8.11) and (8.14), respectively. Step 6: Repeat Steps 3-5 until “the maximum number of buses is reached”. These buses are defined as “a set of candidate buses”. Continue to connect DG units to “these candidate buses” by repeating Steps 3-5. Step 7: Stop if any of the violations of the constraints (Section 8.3.3) occurs or the last iteration BCR is smaller than the previous iteration one. Obtain the results of the previous iteration. 8.5 Case Study 8.5.1 Test System The proposed methodology was applied to an 11 kV 69-bus radial distribution system that CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 128 is fed by a 6 MVA 33/11 kV transformer, as depicted in Figure 3.3 [113]. The total active and reactive power of the system at the average load level defined by Equation (8.1) is 3.35 MW and 2.30 MVAr, respectively. 8.5.2 Assumptions and Constraints The operating voltages at all buses are limited in the range of 0.95 to 1.05 p.u. The feeder thermal limits are 5.1 MVA (270 A) [68]. It is assumed that the time-varying voltage dependent industrial load as defined in Equation (3.1) is considered in this simulation. The loading at each bus follows the industrial load duration curve across a year shown in Figure 8.1 over a planning horizon of 15 years with a yearly demand growth of 3%. As given by Equation (8.1), the load factor or average load level over the planning horizon (LF) is 0.75. All buses are candidate for DG investment and more than one DG unit can be installed at the same bus. The substation transformers are close to their thermal rating and would need replacing in the near future while the conductors exhibit considerable extra headroom for further demand. For reasons of simplicity, DG units are connected at the start of the planning horizon and operating for the whole time a year (8760 hours) at rated capacity throughout the planning horizon. That means the average utilization factor of DG units is 100%. Gas turbine-based DG technology is used. Its size (SDG) is pre-specified at 0.8 MVA. The input data given in Table 8.1, are employed for benefit and cost analyses. Table 8.1. Economic input data Gas turbine-based DG capacity [68] Investment cost [68] 0.8 MVA $976 / kW Operation and maintenance and fuel costs [68] $46 / MWh Electricity sales [68] $76 / MWh Loss incentive [68] $78 / MWh Network upgrade deferral benefit for deferral of transformer upgrades [68] $407 / kW of DG Emission factor of grid [74] 0.910 TonCO2 / MWh Emission factor of 1 MVA gas engine [74] 0.773 TonCO2 / MWh Emission cost [74] $10 / TonCO2 Discount rate [68] 9% CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 129 8.5.3 Numerical Results The total load of the system is 4.07 MVA. Given a pre-defined DG size of 0.8 MVA each and the constraint of DG penetration as defined by Equation (8.8), the maximum number of DG units is limited to be five with a total size of 4 MVA. To compare the benefits brought to the utility, five following scenarios have been analysed. • Scenario 1: One biomass DG unit; • Scenario 2: Two biomass DG units; • Scenario 3: Three biomass DG units; • Scenario 4: Four biomass DG units; • Scenario 5: Five biomass DG units. Location, Size and Power Factor with respect to Indices Figure 8.2 presents the 69-bus system with DG units. The optimal locations are identified at buses 62, 35, 25, 4 and 39 where five DG units (i.e., DGs 1, 2, 3, 4 and 5, respectively) are optimally placed. Table 8.2 shows a summary of the results of the location, power factor and size of DG units for the five scenarios as mentioned earlier over the planning horizon of 15 years. As each DG unit is pre-defined at 0.8 MVA, its power factor is adjusted such that the IMO index obtained for each scenario is lowest. The optimal power factor for each location is quite different, in the range of 0.82-0.89 (lagging). The total size is increased from 0.8 to 4 MVA with respect to the number of DG units increased from one to five. It has been found from the simulation that three scenarios (i.e, 3, 4 and 5 DG units) satisfy the technical constraints. When less than three DG units are considered, the violation of the voltage constraint (i.e., the operating voltages are under 0.95 p.u) occurs at several buses in the system. CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 130 Figure 8.2. Single line diagram of the 69-bus test distribution system with DG units. Table 8.2. Location, size and power factor of DG units Scenarios DG location DG size (MVA) DG power factor (lag.) Total DG size (MVA) Permissible constraints? 1 DG 62 0.8 0.87 0.8 No 2 DGs 62 35 0.8 0.8 0.87 0.89 1.6 No 3 DGs 62 35 25 0.8 0.8 0.8 0.87 0.89 0.89 2.4 Yes 4 DGs 62 35 25 4 0.8 0.8 0.8 0.8 0.87 0.89 0.89 0.85 3.2 Yes 5 DGs 62 35 25 4 39 0.8 0.8 0.8 0.8 0.8 0.87 0.89 0.89 0.85 0.82 4.0 Yes CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 131 Figure 8.3 shows a comparison of the ILP, ILQ and IMO indices with different numbers of DG units over the planning horizon, which are related to the active power loss index, reactive power loss index and a multi-objective index. As shown in Figure 8.3, the indices reduce when the number of DG units is increased from one to five. However, when the number of DG units is further increased, the total penetration of DG units is higher than the total demand as previously mentioned along with an increase in the values of indices. Substantial reductions in the indices are observed in three scenarios (i.e., 3, 4 and 5 DG units) when compared to one and two DG units. For each scenario, the ILP is lower than the ILQ. This indicates that the system with DG units can benefit more from minimising the active power loss than to the reactive power loss. 1.0 ILP ILQ IMO Indices 0.8 0.6 0.4 0.2 0.0 1 2 3 4 5 Number of DGs Figure 8.3. Indices (ILP, ILQ and IMO) for the system with various numbers of DG units over planning horizon. DG Impact on Energy Loss and Voltage Stability Figure 8.4 presents the total energy loss of the system for different scenarios without and with DG units over the planning horizon. For each scenario, the total energy loss for each year is estimated as a sum of all the energy losses at the respective load levels of that year. As shown in Figure 8.4, the system energy loss with no DG units increases over the planning horizon due to the annual demand growth of 3%. A significant reduction in the energy loss over the planning horizon is observed for the scenarios with DG units when compared to the scenario without DG units. The lowest energy loss is achieved for the scenario with five DG units. As the amount of the power generation from three DG units is CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 132 still not sufficient, the system energy loss for the scenario with three DG units reduce insignificantly when compared to that with four or five DG units. Energy loss (MWh) 1500 No DG 3 DGs 4 DGs 5 DGs 1200 900 600 300 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Year Figure 8.4. Losses of the system with and without DG units over planning horizon. Figure 8.5 shows the impact of DG allocation on the voltage stability of the system with and without DG units over the planning horizon of 15 years. For each year, the simulation has been implemented at the maximum demand, where the voltage stability margin (VSM) is worst when compared to the other loading levels. In each year, as defined in Figure 7.2, the VSM of the system with 3-5 DG units significantly enhances when compared to that of the system without DG units. For example, when three DG units generate an amount of 2.4 MVA at buses 62, 35 and 25 in the first year, as found in Table 8.2, the VSM increases to 4.5918 from the base case value of 2.8681 (without DG units). A similar trend has been found for years 2-15 as shown in Figure 8.5. Furthermore, it can be seen from Figure 8.5 that a significant increase in the voltage stability margin is found for the scenarios with four or five DG units when compared to three DG units. This is due to the fact that the ILP, which is related to the reactive power loss of the system, significantly reduces for the scenario with four or five DG units when compared to three DG units, as shown in Figure 8.3. In addition, it can be observed from Figure 8.5 that the VSM values with and without DG units reduce with respect to a yearly demand growth of 3%. Hence, the lowest VSM values are found in the year 15. CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION Voltage stability margin 6.0 No DG 4 DGs 133 3 DGs 5 DGs 4.5 3.0 1.5 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Year Figure 8.5. Voltage stability margin curves for all scenarios over planning horizon. Table 8.3 shows a summary of the results of energy losses without and with DG units for each scenario over the planning horizon of 15 years. The energy savings due to loss reduction is beneficial. A maximum energy savings is achieved for the scenario with five DG units when compared to three and four DG units. Table 8.3 also presents a summary of the results of voltage stability with and without DG units over the planning horizon. The average voltage stability margin of the system (AVSM) is calculated as a sum of the VSM values of all years divided by the total planning horizon. An increase in the average voltage stability margin (∆AVSM) is observed after 3-5 DG units are installed in the system. It is observed from Table 8.3 that the VSM for each scenario increases with respect to an increase in the number of DG units installed in the system as well as a reduction in the overall energy loss of the system. Table 8.3. Energy loss and voltage stability over planning horizon Scenarios Energy loss Energy savings (GWh / 15 years) (GWh / 15 years) Voltage stability AVSM ∆AVSM Base case 14.91 2.1667 3 DGs 5.97 8.94 3.5745 1.4078 4 DGs 4.46 10.45 3.5758 1.4091 5 DGs 4.35 10.56 3.6855 1.5188 CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 134 Benefit and Cost Analysis Table 8.4 presents the results of the total benefit and cost for three scenarios (i.e., 3, 4 and 5 DG units) without and with additional benefits over the planning horizon of 15 years. The additional benefit includes the loss incentive (LI), emission incentive (EI) and network upgrade deferral (ND). The total benefit (B) is a sum of all the additional benefits and the energy sales (R). The total cost (C) is a sum of the operation, maintenance and fuel cost (OM) and the DG capacity cost (CDG ∑PDGi). Table 8.5 shows a comparison of the results for three different scenarios without and with additional benefits over the planning horizon. The results include the benefit-cost ratio (BCR), net present value (NPV = B - C), payback period, and internal rate of return (IRR). For exclusion of the additional benefits, it is observed from Table 8.5 that the BCR is the same for all the scenarios at 1.288. The best solution is five DG units as the NPV is highest at k$4162. This solution generates an IRR of 16.48% and a payback period of 5.6 years. For inclusion of the additional benefits, it can be seen from Table 8.4 that the energy sales (R) accounts for around 89-90% of the B, leaving the total additional benefit (LI, EI and ND) at roughly 10-11%. It is obvious that the R has a significant impact on the BCR when compared to the total additional benefit. However, the additional benefits, particularly the LI play a critical role in decision-making about the total number of DG units or the amount of DG capacity installed. This factor has an impact on the BCR. As shown in Table 8.5, the BCR slightly drops from 1.450 to 1.438 when the number of DG units is increased from three to five, respectively. The best solution is three DG units with the highest BCR of 1.450. This solution generates an NPV of k$3993, an IRR of 32.65% and a payback period of 2.80 years. In general, in the absence of the additional benefits, the optimal number of DG units is five, while in the presence of the additional benefits, this figure is three. Inclusion of the additional benefits in the study can lead to faster investment recovery with a higher BCR, a higher IRR and a shorter payback period when compared to exclusion of the additional benefits. In addition, it can be observed from Table 8.5 that the NPV value will further increase with increasing DG units installed. However, the system cannot accommodate more than five DG units due to the violation of the maximum DG penetration constraint as defined by Equation (8.8). CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 135 Table 8.4. Analysis of the present value benefit and cost for different scenarios over planning horizon Without additional benefits With additional benefits Number of DGs 3 DGs 4 DGs 5 DGs 3 DGs 4 DGs 5 DGs R (k$) 11421 15090 18624 11421 15090 18624 LI (k$) -- -- -- 336 392 387 EI (k$) -- -- -- 244 316 379 ND ∑PDGi (k$) -- -- -- 860 1137 1403 11421 15090 18624 12862 16934 20793 R / B (%) 88.80 89.11 89.57 (LI+EI+ ND ∑PDGi) / B (%) 11.20 10.89 10.43 Total benefit, B (k$) OM (k$) 6804 8990 11095 6804 8990 11095 CDG ∑PDGi (k$) 2065 2728 3367 2065 2728 3367 Total cost, C (k$) 8869 11718 14462 8869 11718 14462 Table 8.5. Comparison of different scenarios over planning horizon Without additional benefits With additional benefits Number of DGs 3 DGs 4 DGs 5 DGs 3 DGs 4 DGs 5 DGs BCR = B/C 1.288 1.288 1.288 1.450 1.445 1.438 NPV = B – C (k$) 2552 3372 4162 3993 5216 6331 Payback period (years) 5.60 5.60 5.60 2.80 2.82 2.86 Internal rate of return, IRR (%) 16.48 16.48 16.48 32.65 32.38 31.93 Figure 8.6 shows an increase in the NPV with the corresponding average DG utilization factors over the planning horizon of 15 years for three scenarios (i.e., 3, 4 and 5 units) with the additional benefits. It is observed from the figure that given a certain average DG utilization factor in the range of 0-100%, the NPV is highest for the scenario with five DG units, whereas this figure is lowest for the scenario with three DG units. In addition, for each scenario, the NPV is maximum when the utilization factor is 100% as estimated in Table 8.5. However, in practice, this factor may be less than 100% due to interruption for maintenance and others. Consequently, the respective NPV will be reduced as shown in Figure 8.6. CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 136 Figure 8.7 shows the percentage ratio of the total demand plus total loss to the thermal limit (6 MVA) of the transformer over the planning horizon with a demand growth of 3%. For the scenarios with DG units, the curves are plotted at the average DG utilization factor of 100%. Obviously, without DG connection, an investment would be needed to add a new transformer before year 4. However, the selected three-DG scenario can defer in upgrading this current transformer (6 MVA) to 11 years. A higher deferral is achieved for the scenarios with four or five DG units. 7.5 3 DGs 4 DGs NPV (million $) 6.0 5 DGs 4.5 3.0 1.5 0.0 10 20 30 40 50 60 70 80 90 100 Average utilization of DG (%) Figure 8.6. NPV at various average DG utilization factors for different scenerios over planning horizon. Percentage ratio (%) 200 No DGs 3 DGs 4 DGs 5 DGs 150 Transformer upgrade required 100 Trans. rating 50 Trans. upgrade deferred 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Year Figure 8.7. Percentage ratio of the total demand plus loss to the thermal transformer limit over planning horizon. CHAPTER 8. BENEFIT AND COST ANALYSES FOR BIOMASS INTEGRATION 8.6 137 Summary This chapter developed an investment planning framework for integrating multiple DG units in industrial distribution systems where the DG units are assumed to be owned and operated by utilities. In this framework, analytical expressions were proposed to efficiently identify the optimal power factor of DG units for minimising energy losses and enhancing voltage stability. The decision for the optimal location, size and number of DG units is achieved through a benefit-cost analysis. The total benefit includes energy sales and three additional benefits including loss reduction, network upgrade deferral and emission reduction. The total cost is a sum of capital, operation and maintenance costs. The results obtained on a 69-bus test distribution system indicated that the additional benefits, particularly the loss incentive have a significant impact on decision-making about the total number of DG units or the amount of DG capacity installed. The additional benefits together accounted for 10-11% of the total benefit when compared to the energy sales of 89-90%. Inclusion of these benefits in the study can lead to faster investment recovery with a high benefit-cost ratio, a high internal rate of return and a short payback period. When DG units are owned by DG developers, the additional benefits should be shared between the distribution utility and DG developer to encourage DG connection. In this situation, the proposed methodology could be used as guidance for the utility on how to plan and operate DG units to obtain the additional benefits. CHAPTER 9 CONCLUSIONS 9.1 Summary Increasing interest in the deployment of renewable DG worldwide, especially intermittent resources (i.e., wind and solar), together with demand variations is forcing modifications to the planning and operations of renewable DG units. The smart grid has been introduced as an important part of these modifications. As an integral part of the smart grid, a smart integration approach was presented in this thesis, specifically focusing on high renewable penetration along with an efficient usage of BES units in distribution systems. The thesis also aimed to show how to accommodate and operate renewable DG and associated BES units behind the concept of the optimal power factor to maximize technical, economical and environmental benefits from the utilities’ perspective. The thesis can be summarized along with main findings drawn from the individual chapter as below. In Chapter 2, the background of DG integration and associated BES usage in distribution systems was provided. This was followed by a literature review addressing DG integration in distribution systems with different aspects such as loss reduction, voltage stability, voltage profiles and benefit-cost analyses. It was observed that traditional DG planning approaches are typically focused on locating and sizing where DG units are assumed to be dispatchable and located at the peak demand. However, few studies indicated that such approaches may not solve a practical case of intermittent renewable DG units that considers the time-varying demand and variant/probabilistic generation. Moreover, most existing approaches have assumed that DG units operate at pre-specified 138 CHAPTER 9. CONCLUSIONS 139 power factor under the recommendation of the current standard IEEE 1547, normally unity power factor. The concept and application of hybrid PV and BES systems in distribution systems was also reviewed. The hybrid system was found to be favoured in the literature to eliminate the intermittency of PV sources and support high PV penetration. In addition, it was shown that a constant or voltage-dependent load model is usually assumed in most traditional DG planning approaches. In contrast to the traditional approaches, Chapter 3 described the models of timevarying voltage-dependent load demand and the time-varying/probabilistic generation which were adopted for renewable DG planning in this thesis. These models can make the assessment of renewable integration more accurate when compared to the traditional model. In addition, this chapter introduced three test distribution systems: 33-bus (one feeder), 69-bus (one feeder) and 69-bus (four feeders), which were employed to validate the effectiveness of the proposed methods in this thesis. The contribution chapter started with Chapter 4 where three alternative analytical approaches were presented to facilitate the determination of the size and operating strategy of a single renewable DG unit to reduce power losses. A methodology to identify the best location was also developed in this chapter. The three approaches were respectively derived from three different power loss formulas. They were easily adapted to accommodate different types of renewable DG units (i.e., biomass, wind and solar PV) for minimising energy losses while considering the time-varying demand and possible operating conditions of DG units. It was indicated that the three approaches can be utilized depending on availability of required data and produce similar outcomes. It was also shown that a maximum energy loss reduction is achieved for all the proposed scenarios with optimal power factor operation when compared to pre-defined power factors, especially unity power factor. Depending on the characteristics of demand and generation, a distribution system would accommodate up to an estimated 48% of the nondispatchable renewable DG penetration. A higher penetration level could be obtained for dispatchable renewable DG units. However, the importance of hybrid dispatchable and nondispatchable DG units also needs to be examined. Chapter 5 presented a methodology to determine the optimal location, size and power factor of hybrid dispatchable and nondispatchable renewable DG units for minimising CHAPTER 9. CONCLUSIONS 140 annual energy losses. The concept behind this methodology is that each nondispatchable wind unit is converted into a dispatchable source with a mix of wind and biomass units. In this methodology, analytical expressions were first proposed to determine the optimal size and power factor of each DG unit simultaneously for each location to minimise power losses. These expressions were then adapted to locate and size different types of renewable DG units and calculate the optimal power factor for each unit to minimise energy losses while considering the time-varying characteristics of demand and generation. It was shown that dispatchable DG units or hybrid dispatchable and nondispatchable DG units can minimise annual energy losses significantly when compared to nondispatchable DG units alone. In addition to the methods using the constant load models presented in Chapters 4-5, an analytical approach was introduced in Chapter 6 to determine the penetration of PV units in a distribution system with different types of time-varying load models. In this approach, an IMO-based analytical expression was proposed to identify the size of a PV unit, which is capable of supplying active and reactive power, with a multi-objective of simultaneously reducing active and reactive power losses and voltage deviation. The analytical expression was then adapted to accommodate PV units while considering the characteristics of timevarying voltage-dependent load models and probabilistic generation. The Beta PDF model was used to describe the probabilistic nature of solar irradiance. It was indicated that an accurate modeling of the demand profile based on the time-varying voltage-dependent load models together with probabilistic generation can help in determining the penetration of PV units into a distribution system precisely. Unlike Chapters 4-6, a new methodology to accommodate hybrid PV and BES systems was proposed in Chapter 7 for reducing energy loss and enhancing voltage stability. Here, each nondispatchable PV unit is converted into a dispatchable source with a combination of PV and BES units. New IMO-based analytical expressions were proposed to calculate the size and power factor of hybrid PV and BES units. A self-correction algorithm was developed as well to size multiple PV and BES units while considering the time-varying demand and probabilistic generation. It was shown that the model can support high PV penetration associated with an efficient usage of BES sources. Optimal power factor dispatch could be one of the aspects to be considered in the strategy of PV integration. A significant energy loss reduction and voltage stability enhancement can be achieved for all CHAPTER 9. CONCLUSIONS 141 the proposed scenarios with PV dispatch at optimal power factor for each load level when compared to PV generation at unity power factor which follows the current standard IEEE 1547. Consequently, this result implies that the standards and regulatory frameworks regarding PV planning and operations need to be revised. Finally, in addition to the technical benefits thoroughly discussed in Chapters 4-7, it is necessary to evaluate the costs and benefits of DG installation. Chapter 8 developed a comprehensive multi-year framework for biomass DG investment planning in distribution systems. In this framework, given a DG unit with a commercial standard size, the dualindex based expressions proposed can identify the optimal power factor for minimising energy losses and enhance voltage stability. The decision for the optimal location, size and number of DG units is achieved through a benefit-cost analysis. It was shown that inclusion of energy loss reduction together with other benefits such as network investment deferral and emission reduction in the analysis would recover DG investments faster. 9.2 Contributions The main contributions of this thesis can be summarized as follows: Chapter 4: A new concept behind the optimal power factor operation was introduced. Three alternative analytical approaches were presented to determine the location, size and power factor of different types of single renewable DG units for minimising energy losses while considering the time-varying demand and generation. Chapter 5: A new concept to covert each nondispatchable wind into a dispatchable source with a combination of wind and biomass units was proposed. Analytical expressions were developed to identify the optimal size and power factor of DG units simultaneously. A methodology was presented to accommodate hybrid dispatchable biomass and nondispatchable wind units for minimising energy losses. Chapter 6: An IMO-based expression was developed to locate and size a PV unit with a multiobjective of simultaneously reducing active and reactive power losses and voltage deviation. A methodology was presented to determine the penetration of PV units for distribution systems while considering the characteristics of time-varying load models and probabilistic generation. CHAPTER 9. CONCLUSIONS 142 Chapter 7: A new concept to covert each nondispatchable PV unit into a dispatchable source with a combination of PV and BES units was introduced. IMO-based analytical expressions were presented to calculate the size and power factor of hybrid PV-BES units for reducing energy losses and enhancing voltage stability. A self-correction algorithm was developed to size multiple PV and BES units. Chapter 8: Dual index-based analytical expressions were proposed to efficiently capture the optimal power factor of each DG with a standard size for minimising energy losses and enhancing voltage stability. A comprehensive multi-year multi-period framework for biomass DG investment planning was presented based on a benefit-cost analysis over a given planning horizon. 9.3 Future Research Future research should be focused on the following issues: 1. A cost-benefit analysis for integrating dispatchable and non-dispatchable sources (biomass, PV and wind) as well as BES units into distribution systems. 2. A framework for DG planning that includes reliability to provide a more accurate evaluation of DG benefits. 3. A policy or mechanism of power factor dispatch in the electricity market for renewable DG and associated BES units. 4. A framework for distribution system planning with renewable DG and associated BES units in a deregulated environment. 5. A framework for hybrid PV and Electric Vehicle (EV) planning. 6. An advanced framework for distribution system planning which simultaneously considers reconfiguration, renewable DG, BES units and capacitors. 7. A strategy of coordination control considering the interaction of renewable DG and EV units with voltage and reactive power control devices such as switchable capacitors, voltage regulators and tap changers. BIBLIOGRAPHY [1] S. Rahman, "Green power: what is it and where can we find it?," IEEE Power Energy Mag., vol. 1, no. 1, pp. 30-37, Jan./Feb. 2003. [2] C. J. Mozina, "Impact of green power distributed generation," IEEE Indust. Applicat. Mag., vol. 16, no. 4, pp. 55-62, Jul./Aug. 2010. [3] Renewables global futures report 2013 [Online]. Available: http://www.ren21.net. [4] G. Masson, M. Latour, and D. Biancardi (2012). Global market outlook for photovoltaics until 2016. European Photovoltaic Industry Association [Online]. Available: http:// http://www.epia.org/news. [5] F. Katiraei, J. R. Aguero, "Solar PV integration challenges," IEEE Power Energy Mag., vol. 9, no. 3, pp. 62-71, May/Jun. 2011. [6] Call for papers for the ieee transactions on sustainable energy special issue on large scale grid integration and regulatory issues of variable power generation [Online]. Available http://www.ieee-pes.org/." [7] M. G. Simoes, R. Roche, E. Kyriakides, S. Suryanarayanan, B. Blunier, K. D. McBee, P. H. Nguyen, P. F. Ribeiro, and A. Miraoui, "A Comparison of smart grid technologies and progresses in Europe and the U.S," IEEE Trans Indust. Applicat.,vol. 48, no. 4, pp. 1154-1162, Jul./Aug. 2012. [8] W. El-Khattam, K. Bhattacharya, Y. Hegazy, and M. M. A. Salama, "Optimal investment planning for distributed generation in a competitive electricity market," IEEE Trans. Power Syst., vol. 19, no. 3, pp. 1674-1684, Aug. 2004. [9] H. B. Puttgen, P. R. MacGregor, and F. C. Lambert, "Distributed generation: Semantic hype or the dawn of a new era?," IEEE Power Energy Mag., vol. 1, no. 1, pp. 22-29, Jan./Feb 2003. 143 BIBLIOGRAPHY [10] 144 H.L. Willis and W. G. Scott, Eds., Distributed power genertaion: Planning and evaluation. New York: Marcel Dekker, Inc, 2000. [11] P. F. Ribeiro, B. K. Johnson, M. L. Crow, A. Arsoy, and Y. Liu, "Energy storage systems for advanced power applications," Proc. IEEE, vol. 89, no. 12, pp. 17441756, Dec. 2001. [12] C. Nirmal-Kumar and G. N. Nair, "Battery energy storage systems: Assessment for small-scale renewable energy integration," Energy Build., vol. 42, no. 11, pp. 21242130, Nov. 2010. [13] E. Mashhour and S. M. Moghaddas-Tafreshi, "Bidding strategy of virtual power plant for participating in energy and spinning reserve markets - Part I: Problem formulation," IEEE Trans. Power Syst., vol. 26, no.2, pp. 949-956, May 2011. [14] A. C. Rueda-Medina and A. Padilha-Feltrin, "Distributed generators as providers of reactive power support - A market approach," IEEE Trans. Power Syst., vol. 28, no. 1, pp. 490-502, Feb. 2013. [15] C. Yuen, A. Oudalov, and A. Timbus, "The provision of frequency control reserves from multiple microgrids," IEEE Trans. Ind. Electron., vol. 58, no. 1, pp. 173-183, Jan. 2011. [16] S. Eftekharnejad, V. Vittal, G. T. Heydt, B. Keel, and J. Loehr, "Impact of increased penetration of photovoltaic generation on power systems," IEEE Trans. Power Syst., vol. 28, pp. 893-901, May 2013. [17] R. Viral and D. K. Khatod, "Optimal planning of distributed generation systems in distribution system: A review," Renew. Sustain. Energy Rev., vol. 16, no. 7, pp. 5146-5165, Sep. 2012. [18] A. Nourai, V. I. Kogan, and C. M. Schafer, "Load leveling reduces T&D line losses," IEEE Trans. Power Del., vol. 23, no. 4, pp. 2168-2173, Oct. 2008. [19] Y. M. Atwa and E. F. El-Saadany, "Probabilistic approach for optimal allocation of wind-based distributed generation in distribution systems," IET Renew. Power Gener., vol. 5, no. 1, pp. 79-88, Jan. 2011. [20] P. S. Georgilakis and N. D. Hatziargyriou, "Optimal distributed generation placement in power distribution networks: Models, methods, and future research," IEEE Trans. Power Syst., vol. 28, no. 3, pp. 3420 - 3428, Aug. 2013. [21] C. Wang and M. H. Nehrir, "Analytical approaches for optimal placement of distributed generation sources in power systems," IEEE Trans. Power Syst., vol. 19, no. 4, pp. 2068-2076, Nov. 2004. BIBLIOGRAPHY [22] 145 N. Acharya, P. Mahat, and N. Mithulananthan, "An analytical approach for DG allocation in primary distribution network," Int. J. Elect. Power Energy Syst., vol. 28, no. 10, pp. 669-678, Dec. 2006. [23] T. Gözel and M. H. Hocaoglu, "An analytical method for the sizing and siting of distributed generators in radial systems," Electr. Power Syst. Res., vol. 79, no. 6, pp. 912-918, Jun. 2009. [24] D. Q. Hung, N. Mithulananthan, and R. C. Bansal, "Analytical expressions for DG allocation in primary distribution networks," IEEE Trans. Energy Convers., vol. 25, no. 3, pp. 814-820, Sep. 2010. [25] D. Q. Hung and N. Mithulananthan, "Multiple distributed generator placement in primary distribution networks for loss reduction," IEEE Trans. Ind. Electron., vol. 60, no. 4, pp. 1700-1708, Apr. 2013. [26] L. F. Ochoa and G. P. Harrison, "Minimizing energy losses: Optimal accommodation and smart operation of renewable distributed generation," IEEE Trans. Power Syst., vol. 26, no. 1, pp. 198-205, Feb. 2011. [27] Y. M. Atwa, E. F. El-Saadany, M. M. A. Salama, and R. Seethapathy, "Optimal renewable resources mix for distribution system energy loss minimization," IEEE Trans. Power Syst., vol. 25, no. 1, pp. 360-370, Feb. 2010. [28] S. K. Injeti and N. Prema Kumar, "A novel approach to identify optimal access point and capacity of multiple DGs in a small, medium and large scale radial distribution systems," Int. J. Elect. Power Energy Syst., vol. 45, no. 1, pp. 142-151, Feb. 2013. [29] D. Singh and K. S. Verma, "Multiobjective optimization for DG planning with load models," IEEE Trans. Power Syst., vol. 24, no. 1, pp. 427-436, Jan. 2009. [30] M. R. AlRashidi and M. F. AlHajri, "Optimal planning of multiple distributed generation sources in distribution networks: A new approach," Energy Convers. Manage., vol. 52, no. 11, pp. 3301-3308, Oct. 2011. [31] S. Kansal, V. Kumar, and B. Tyagi, "Optimal placement of different type of DG sources in distribution networks," Int. J. Elect. Power Energy Syst., vol. 53, pp. 752760, Dec. 2013. [32] F. S. Abu-Mouti and M. E. El-Hawary, "Optimal distributed generation allocation and sizing in distribution systems via artificial bee colony algorithm," IEEE Trans. Power Del., vol. 26, no. 4, pp. 2090-2101, Oct. 2011. [33] J. A. Martín García and A. J. Gil Mena, "Optimal distributed generation location BIBLIOGRAPHY 146 and size using a modified teaching–learning based optimization algorithm," Int. J. Elect. Power Energy Syst., vol. 50, pp. 65-75, Sep. 2013. [34] R. S. Rao, K. Ravindra, K. Satish, and S. V. L. Narasimham, "Power loss minimization in distribution system using network reconfiguration in the presence of distributed generation," IEEE Trans. Power Syst., vol. 28, no. 1, pp. 317-325, Feb. 2013. [35] F. Ugranlı and E. Karatepe, "Optimal wind turbine sizing to minimize energy loss," Int. J. Elect. Power Energy Syst., vol. 53, pp. 656-663, Dec. 2013. [36] J. M. S. Pinheiro, C. R. R. Dornellas, M. T. Schilling, A. C. G. Melo, and J. C. O. Mello, "Probing the new IEEE reliability test system (RTS-96): HL-II assessment," IEEE Trans. Power Syst., vol. 13, no. 1, pp. 171-176, Feb. 1998. [37] Z. M. Salameh, B. S. Borowy, and A. R. A. Amin, "Photovoltaic module-site matching based on the capacity factors," IEEE Trans. Energy Convers., vol. 10, no. 2, pp. 326-332, Jun. 1995. [38] G. Boyle, Ed., Renewable energy. Oxford, UK: Oxford University Press, 2004. [39] D. K. Khatod, V. Pant, and J. Sharma, "Evolutionary programming based optimal placement of renewable distributed generators," IEEE Trans. Power Syst., vol. 28, no. 2, pp. 683-695, May 2013. [40] V. Ajjarapu and B. Lee, "Bibliography on voltage stability," IEEE Trans. Power Syst., vol. 13, no. 1, pp. 115-125, Feb. 1998. [41] R. B. Prada and L. J. Souza, "Voltage stability and thermal limit: Constraints on the maximum loading of electrical energy distribution feeders," Proc. IEE Gener. Transm. Distrib., vol. 145, no. 5, pp. 573-577, Sep. 1998. [42] M. Chakravorty and D. Das, "Voltage stability analysis of radial distribution networks," Int. J. Elect. Power Energy Syst., vol. 23, no. 2, pp. 129-135, Feb. 2001. [43] H. Hedayati, S. A. Nabaviniaki, and A. Akbarimajd, "A method for placement of DG units in distribution networks," IEEE Trans. Power Del., vol. 23, no. 3, pp. 1620-1628, Jul. 2008. [44] N. G. A. Hemdan and M. Kurrat, "Allocation of decentralized generators in distribution networks for enhancing normal operation loadability," in PowerTech, 2009 IEEE Bucharest, 2009, pp. 1-7. [45] M. Ettehadi, H. Ghasemi, and S. Vaez-Zadeh, "Voltage stability-based DG placement in distribution networks," IEEE Trans. Power Del., vol. 28, no. 1, pp. 171-178, Jan. 2013. BIBLIOGRAPHY [46] 147 M. M. Aman, G. B. Jasmon, H. Mokhlis, and A. H. A. Bakar, "Optimal placement and sizing of a DG based on a new power stability index and line losses," Int. J. Elect. Power Energy Syst., vol. 43, no. 1. pp. 1296-1304, Dec. 2012. [47] M. Esmaili, "Placement of minimum distributed generation units observing power losses and voltage stability with network constraints," IET Gener. Transm. Distrib., vol. 7, no. 8, pp. 813-821, Aug. 2013. [48] M. M. Aman, G. B. Jasmon, A. H. A. Bakar, and H. Mokhlis, "A new approach for optimum DG placement and sizing based on voltage stability maximization and minimization of power losses," Energy Convers. Manage., vol. 70, pp. 202-210, Jun. 2013. [49] P. Kayal and C. K. Chanda, "Placement of wind and solar based DGs in distribution system for power loss minimization and voltage stability improvement," Int. J. Elect. Power Energy Syst., vol. 53, pp. 795-809, Dec. 2013. [50] N. C. Hien, N. Mithulananthan, and R. C. Bansal, "Location and sizing of distribution generation units for loadability enhancement in primary feeder," IEEE Syst. Journal, vol. 7, no. 4, pp. 797-806, Dec. 2013. [51] R. S. Al Abri, E. F. El-Saadany, and Y. M. Atwa, "Optimal placement and sizing method to improve the voltage stability margin in a distribution system using distributed generation," IEEE Trans. Power Syst., vol. 28, no. 1, pp. 326-334, Feb. 2013. [52] Ravindra Kollu, Srinivasa Rao Rayapudi, and V. L. N. Sadhu, "A novel method for optimal placement of distributed generation in distribution systems using HSDO," Int. Trans. Electr. Energy Syst., DOI: 10.1002/etep.1710, to be publised. [53] W.-S. Tan, M. Y. Hassan, M. S. Majid, and H. Abdul Rahman, "Optimal distributed renewable generation planning: A review of different approaches," Renew. Sustain. Energy Rev., vol. 18, pp. 626-645, Feb. 2013. [54] L. F. Ochoa, A. Padilha-Feltrin, and G. P. Harrison, "Evaluating distributed generation impacts with a multiobjective index," IEEE Trans. Power Del., vol. 21, no. 3, pp. 1452-1458, Jul. 2006. [55] L. F. Ochoa, A. Padilha-Feltrin, and G. P. Harrison, "Evaluating distributed timevarying generation through a multiobjective index," IEEE Trans. Power Del., vol. 23, no. 2, pp. 1132-1138, Apr. 2008. [56] T. Wen Shan, M. Y. Hassan, H. A. Rahman, M. P. Abdullah, and F. Hussin, "Multidistributed generation planning using hybrid particle swarm optimisation- BIBLIOGRAPHY 148 gravitational search algorithm including voltage rise issue," IET Gener. Transm. Distrib., vol. 7, no. 9, pp. 929-942, Sep. 2013. [57] D. Singh and R. K. Misra, "Effect of load models in distributed generation planning," IEEE Trans. Power Syst., vol. 22, no. 4, pp. 2204-2212, Nov. 2007. [58] A. M. El-Zonkoly, "Optimal placement of multi-distributed generation units including different load models using particle swarm optimisation," IET Gener. Transm. Distrib., vol. 5, no. 7, pp. 760-771, Jul. 2011. [59] K. Qian, C. Zhou, M. Allan, and Y. Yuan, "Effect of load models on assessment of energy losses in distributed generation planning," Int. J. Elect. Power Energy Syst., vol. 33, no. 6, pp. 1243-1250, Jul. 2011. [60] R. Ebrahimi, M. Ehsan, and H. Nouri, "A profit-centric strategy for distributed generation planning considering time varying voltage dependent load demand," Int. J. Elect. Power Energy Syst., vol. 44, no. 1, pp. 168-178, Jan. 2013. [61] V. H. Méndez, J. Rivier, J. I. d. l. Fuente, T. Gómez, J. Arceluz, J. Marín, and A. Madurga, "Impact of distributed generation on distribution investment deferral," Int. J. Elect. Power Energy Syst., vol. 28, no. 4, pp. 244-252, May 2006. [62] H. A. Gil and G. Joos, "On the quantification of the network capacity deferral value of distributed generation," IEEE Trans. Power Syst., vol. 21, no. 4, pp. 1592-1599, Nov. 2006. [63] S. Favuzza, G. Graditi, M. G. Ippolito, and E. R. Sanseverino, "Optimal electrical distribution systems reinforcement planning using gas micro turbines by dynamic ant colony search algorithm," IEEE Trans. Power Syst., vol. 22, no. 2, pp. 580-587, May 2007. [64] G. P. Harrison, A. Piccolo, P. Siano, and A. R. Wallace, "Hybrid GA and OPF evaluation of network capacity for distributed generation connections," Electr. Power Syst. Res., vol. 78, no. 3, pp. 392-398, Mar. 2008. [65] R. A. Jabr and B. C. Pal, "Ordinal optimisation approach for locating and sizing of distributed generation," IET Gener. Transm. Distrib., vol. 3, no. 8, pp. 713-723, Aug. 2009. [66] A. Soroudi and M. Ehsan, "Efficient immune-ga method for dnos in sizing and placement of distributed generation units," Eur. Trans. Electr. Power, vol. 21, no. 3, pp. 1361-1375, Apr. 2010. [67] E. Naderi, H. Seifi, and M. S. Sepasian, "A dynamic approach for distribution system planning considering distributed generation," IEEE Trans. Power Del., vol. BIBLIOGRAPHY 149 27, no. 3, pp. 1313-1322, Jul. 2012. [68] P. Siano, L. F. Ochoa, G. P. Harrison, and A. Piccolo, "Assessing the strategic benefits of distributed generation ownership for DNOs," IET Gener. Transm. Distrib., vol. 3, no. 3, pp. 225-236, Mar. 2009. [69] A. Piccolo and P. Siano, "Evaluating the impact of network investment deferral on distributed generation expansion," IEEE Trans. Power Syst., vol. 24, no. 3, pp. 1559-1567, Aug. 2009. [70] G. Celli, E. Ghiani, S. Mocci, and F. Pilo, "A multiobjective evolutionary algorithm for the sizing and siting of distributed generation," IEEE Trans. Power Syst., vol. 20, no. 2, pp. 750-757, May 2005. [71] M. F. Shaaban, Y. M. Atwa, and E. F. El-Saadany, "DG allocation for benefit maximization in distribution networks," IEEE Trans. Power Syst., vol. 28, no. 2, pp. 639-649, May 2013. [72] A. G. Tsikalakis and N. D. Hatziargyriou, "Environmental benefits of distributed generation with and without emissions trading," Energy Policy, vol. 35, no. 6, pp. 3395-3409, Jun. 2007. [73] T. Niknam, S. I. Taheri, J. Aghaei, S. Tabatabaei, and M. Nayeripour, "A modified honey bee mating optimization algorithm for multiobjective placement of renewable energy resources," Appl. Energy, vol. 88, no. 12, pp. 4817-4830, Dec. 2011. [74] A. Soroudi, M. Ehsan, and H. Zareipour, "A practical eco-environmental distribution network planning model including fuel cells and non-renewable distributed energy resources," Renew. Energy, vol. 36, no. 1, pp. 179-188, Jan. 2011. [75] V. Vahidinasab, "Optimal distributed energy resources planning in a competitive electricity market: Multiobjective optimization and probabilistic design," Renew. Energy, vol. 66, pp. 354-363, Jun. 2014. [76] J. Tongdan, T. Yu, Z. Cai Wen, and D. W. Coit, "Multicriteria planning for distributed wind generation under strategic maintenance," IEEE Trans. Power Del., vol. 28, no. 1, pp. 357-367, Jan. 2013. [77] A. Kumar and W. Gao, "Optimal distributed generation location using mixed integer non-linear programming in hybrid electricity markets," IET Gener. Transm. Distrib., vol. 4, no. 2, pp. 281-298, Feb. 2010. [78] S. Kucuksari, A. M. Khaleghi, M. Hamidi, Y. Zhang, F. Szidarovszky, G. Bayraksan, and Y.-J. Son, "An integrated GIS, optimization and simulation BIBLIOGRAPHY 150 framework for optimal PV size and location in campus area environments," Appl. Energy, vol. 113, pp. 1601-1613, Jan. 2014. [79] W. El-Khattam, Y. G. Hegazy, and M. M. A. Salama, "An integrated distributed generation optimization model for distribution system planning," IEEE Trans. Power Syst., vol. 20, no. 2, pp. 1158-1165, May 2005. [80] S. Porkar, P. Poure, A. Abbaspour-Tehrani-fard, and S. Saadate, "A novel optimal distribution system planning framework implementing distributed generation in a deregulated electricity market," Electr. Power Syst. Res., vol. 80, no. 7, pp. 828-837, Jul. 2010. [81] K. D. Mistry and R. Roy, "Enhancement of loading capacity of distribution system through distributed generator placement considering techno-economic benefits with load growth," Int. J. Elect. Power Energy Syst., vol. 54, pp. 505-515, Jan. 2014. [82] N. Khalesi, N. Rezaei, and M. R. Haghifam, "DG allocation with application of dynamic programming for loss reduction and reliability improvement," Int. J. Elect. Power Energy Syst., vol. 33, no. 2, pp. 288-295, Feb. 2011. [83] M. F. Akorede, H. Hizam, I. Aris, and M. Z. A. Ab Kadir, "Effective method for optimal allocation of distributed generation units in meshed electric power systems," IET Gener., Transm. Distrib., vol. 5, no. 2, pp. 276-287, Feb. 2011. [84] A. S. Bin Humayd and K. Bhattacharya, "Comprehensive multi-year distribution system planning using back-propagation approach," IET Gener. Transm. Distrib., vol. 7, no. 12, pp. 1415-1425, Dec. 2013. [85] S. Teleke, M. E. Baran, S. Bhattacharya, and A. Q. Huang, "Rule-based control of battery energy storage for dispatching intermittent renewable sources," IEEE Trans. Sustain. Energy, vol. 1, no. 3, pp. 117-124, Oct. 2010. [86] C. A. Hill, M. C. Such, C. Dongmei, J. Gonzalez, and W. M. Grady, "Battery energy storage for enabling integration of distributed solar power generation," IEEE Trans. Smart Grid, vol. 3, no. 2, pp. 850-857, Jun. 2012. [87] B. S. Borowy and Z. M. Salameh, "Methodology for optimally sizing the combination of a battery bank and PV array in a wind/PV hybrid system," IEEE Trans. Energy Convers., vol. 11, no. 2, pp. 367-375, Jun. 1996. [88] O. Ekren and B. Y. Ekren, "Size optimization of a PV/wind hybrid energy conversion system with battery storage using response surface methodology," Appl. Energy, vol. 85, no. 11, pp. 1086-1101, Nov. 2008. [89] S. Avril, G. Arnaud, A. Florentin, and M. Vinard, "Multi-objective optimization of BIBLIOGRAPHY 151 batteries and hydrogen storage technologies for remote photovoltaic systems," Energy, vol. 35, no. 12, pp. 5300-5308, Dec. 2010. [90] H. Sugihara, K. Yokoyama, O. Saeki, K. Tsuji, and T. Funaki, "Economic and efficient voltage management using customer-owned energy storage systems in a distribution network with high penetration of photovoltaic systems," IEEE Trans. Power Syst., vol. 28, no. 1, pp. 102-111, Feb. 2013. [91] J. H. Teng, S. W. Luan, D. J. Lee, and Y. Q. Huang, "Optimal charging/discharging scheduling of battery storage systems for distribution systems interconnected with sizeable PV generation systems," IEEE Trans. Power Syst., vol. 28, no. 2, pp. 14251433, May 2013. [92] M. Castillo-Cagigal, A. Gutiérrez, F. Monasterio-Huelin, E. Caamaño-Martín, D. Masa, and J. Jiménez-Leube, "A semi-distributed electric demand-side management system with PV generation for self-consumption enhancement," Energy Convers. Manage., vol. 52, no. 7, pp. 2659-2666, Jul. 2011. [93] S. Wei-Fu, H. Shyh-Jier, and E. L. Chin, "Economic analysis for demand-side hybrid photovoltaic and battery energy storage system," IEEE Trans. Indust. Applicat., vol. 37, no. 1, pp. 171-177, Jan./Feb. 2001. [94] A. Nottrott, J. Kleissl, and B. Washom, "Energy dispatch schedule optimization and cost benefit analysis for grid-connected, photovoltaic-battery storage systems," Renew. Energy, vol. 55, pp. 230-240, Jul. 2013. [95] R. Yu, J. Kleissl, and S. Martinez, "Storage size determination for grid-connected photovoltaic systems," IEEE Trans. Sustain. Energy, vol. 4, no. 1, pp. 68-81, Jan. 2013. [96] J. Tant, F. Geth, D. Six, P. Tant, and J. Driesen, "Multiobjective battery storage to improve PV integration in residential distribution grids," IEEE Trans. Sustain. Energy, vol. 4, no. 1, pp. 182-191, Jan. 2013. [97] M. J. E. Alam, K. M. Muttaqi, and D. Sutanto, "Mitigation of rooftop solar PV impacts and evening peak support by managing available capacity of distributed energy storage systems," IEEE Trans. Power Syst., vol. 28, no. 4, pp. 3874 - 3884, Nov. 2013. [98] M. Z. Daud, A. Mohamed, and M. A. Hannan, "An improved control method of battery energy storage system for hourly dispatch of photovoltaic power sources," Energy Convers. Manage., vol. 73, pp. 256-270, Sep. 2013. [99] IEEE Standard for Interconnecting Distributed Resources with Electric Power BIBLIOGRAPHY 152 Systems, IEEE Std 1547, Aug. 2003. [100] H. G. Yeh, D. F. Gayme, and S. H. Low, "Adaptive VAR control for distribution circuits with photovoltaic generators," IEEE Trans. Power Syst., vol. 27, no. 3, pp. 1656-1663, Aug. 2012. [101] K. Turitsyn, P. Sulc, S. Backhaus, and M. Chertkov, "Options for control of reactive power by distributed photovoltaic generators," Proc. IEEE, vol. 99, no. 6, pp. 10631073, Jun. 2011. [102] M. Thomson and D. G. Infield, "Network power-flow analysis for a high penetration of distributed generation," IEEE Trans. Power Syst., vol. 22, no. 3, pp. 1157-1162, Aug. 2007. [103] A. Samadi, M. Ghandhari, and L. Söder, "Reactive power dynamic assessment of a PV system in a distribution grid," Energy Procedia, vol. 20, pp. 98-107, 2012. [104] F. L. Albuquerque, A. J. Moraes, G. C. Guimarães, S. M. R. Sanhueza, and A. R. Vaz, "Photovoltaic solar system connected to the electric power grid operating as active power generator and reactive power compensator," Solar Energy, vol. 84, no. 7, pp. 1310-1317, Jul. 2010. [105] F. Blaabjerg, R. Teodorescu, M. Liserre, and A. V. Timbus, "Overview of control and grid synchronization for distributed power generation systems," IEEE Trans. Ind. Electron., vol. 53, no. 5, pp. 1398-1409, Oct. 2006. [106] S.G asper, C.O. Nwankpa, R.W. Bradish, H-D. Chiang, C. Concordia, J.V. Staron, C.W. Taylor, E. Vaahedi, and G. Wu, "Bibliography on load models for power flow and dynamic performance simulation," IEEE Trans. Power Syst., vol. 10, no. 1, pp. 523-538, Feb. 1995. [107] A. Gabash and L. Pu, "Active-reactive optimal power flow in distribution networks with embedded generation and battery storage," IEEE Trans. Power Syst., vol. 27, no. 4, pp. 2026-2035, Nov. 2012. [108] A. Soroudi, M. Aien, and M. Ehsan, "A probabilistic modelling of photo voltaic modules and wind power generation impact on distribution networks," IEEE Syst. Journal, vol. 6, no. 2, pp. 254-259, Jun. 2012. [109] M. H. Haque, "Evaluation of power flow solutions with fixed speed wind turbine generating systems," Energy Convers. Manage, vol. 79, pp. 511-518, Mar. 2014. [110] V. H. M. Quezada, J. R. Abbad, and T. G. S. Roman, "Assessment of energy distribution losses for increasing penetration of distributed generation," IEEE Trans. Power Syst., vol. 21, no. 2, pp. 533-540, May 2006. BIBLIOGRAPHY 153 [111] M. E. Baran and F. F. Wu, "Network reconfiguration in distribution systems for loss reduction and load balancing," IEEE Trans. Power Del., vol. 4, no. 2, pp. 14011407, Apr. 1989. [112] M. E. Baran and F. F. Wu, "Optimal capacitor placement on radial distribution systems," IEEE Trans. Power Del., vol. 4, no. 1, pp. 725-734, Jan. 1989. [113] D. Das, "A fuzzy multiobjective approach for network reconfiguration of distribution systems," IEEE Trans. Power Del., vol. 21, no. 1, pp. 202-209, Jan. 2006. [114] "Dept. Trade and Industry, Nov. 2006, System integration of additional microgeneration." [115] I. O. Elgerd, Electric energy system theory: an introduction. New York: McGrawHill Inc., 1971. [116] S. F. Mekhamer, M. E. El-Hawary, S. A. Soliman, M. A. Moustafa, and M. M. Mansour, "New heuristic strategies for reactive power compensation of radial distribution feeders," IEEE Trans. Power Del., vol. 17, no. 4, pp. 1128-1135, Jun. 2002. [117] C. Chung-Fu, "Reconfiguration and capacitor placement for loss reduction of distribution systems by ant colony search algorithm," IEEE Trans. Power Syst., vol. 23, no. 4, pp. 1747-1755, Nov. 2008. [118] S. K. Nagarajua, S. Sivanagarajub, T. Ramanac, S. Satyanarayanac, and P. V. Prasadd, "A novel method for optimal distributed generator placement in radial distribution systems," Distrib. Gener. Alter. Energy J., vol. 26, no. 1, pp. 7-19, 2011. [119] D. Q. Hung and N. Mithulananthan. (Jan. 2011). Handbook of renewable energy technology. Chapter 23: DG allocation in primary distribution systems considering loss reduction, World Scientific Publishing Co, Singapore. [120] F. S. Abu-Mouti and M. E. El-Hawary, "Heuristic curve-fitted technique for distributed generation optimisation in radial distribution feeder systems," IET Gener. Trans. Distrib., vol. 5, no. 2, pp. 172-180, Feb. 2011. [121] G. Sinden, "Characteristics of the UK wind resource: Long-term patterns and relationship to electricity demand," Energy Policy, vol. 35, no. 1, pp. 112 -127, Jan. 2007. [122] N. Jain, S. Singh, and S. Srivastava, "A generalized approach for DG planning and viability analysis under market scenario," IEEE Trans. Ind. Electron., vol. 60, no. BIBLIOGRAPHY 154 11, pp. 5075-5085, Nov. 2013. [123] M. Tsili and S. Papathanassiou, "A review of grid code technical requirements for wind farms," IET Renew. Power Gener., vol. 3, no. 3, pp. 308-332, Sep. 2009. [124] C. Whitaker, J. Newmiller, M. Ropp, and B. Norris (2008, Feb.). Distributed Photovoltaic Systems Design and Technology Requirements. Sandia National Laboratories. Available: http://www1.eere.energy.gov/solar/sunshot/index.html. [125] E. Lopez, H. Opazo, L. Garcia, and P. Bastard, "Online reconfiguration considering variability demand: applications to real networks," IEEE Trans. Power Syst., vol. 19, no. 1, pp. 549-553, Feb. 2004. [126] SolarAnywhere [Online]. Available: https://solaranywhere.com. [127] F. A. Viawan and D. Karlsson, "Combined local and remote voltage and reactive power control in the presence of induction machine distributed generation," IEEE Trans. Power Syst., vol. 22, no. 4, pp. 2003-2012, Nov. 2007. [128] W. A. Omran, M. Kazerani, and M. M. A. Salama, "Investigation of methods for reduction of power fluctuations generated from large grid-connected photovoltaic systems," IEEE Trans. Energy Convers., vol. 26, no. 1, pp. 318-327, Mar. 2011. [129] S. X. Chen, H. B. Gooi, and M. Q. Wang, "Sizing of energy storage for microgrids," IEEE Trans. Smart Grid, vol. 3, no. 1, pp. 142-151, Mar. 2012. [130] A. Gabash and P. Li, "Flexible optimal operation of battery storage systems for energy supply networks," IEEE Trans. Power Syst., vol. 28, no. 3, pp. 2788-2797, Aug. 2013. [131] C. A. Canizares and F. L. Alvarado, "Point of collapse and continuation methods for large AC/DC systems," IEEE Trans. Power Syst., vol. 8, no. 1, pp. 1-8, Feb. 1993. APPENDIX A Table A.1. System data of 33-bus test distribution system Sending bus no. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 2 19 20 21 3 23 24 6 26 27 28 29 30 31 32 Receiving bus no. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Resistance (Ω) 0.0922 0.4930 0.3660 0.3811 0.8190 0.1872 1.7114 1.0300 1.0400 0.1966 0.3744 1.4680 0.5416 0.5910 0.7463 1.2890 0.7320 0.1640 1.5042 0.4095 0.7089 0.4512 0.8980 0.8960 0.2030 0.2842 1.0590 0.8042 0.5075 0.9744 0.3105 0.3410 Reactance (Ω) 0.0477 0.2511 0.1864 0.1941 0.7070 0.6188 1.2351 0.7400 0.7400 0.0650 0.1238 1.1550 0.7129 0.5260 0.5450 1.7210 0.5740 0.1565 1.3554 0.4784 0.9373 0.3083 0.7091 0.7011 0.1034 0.1447 0.9337 0.7006 0.2585 0.9630 0.3619 0.5302 Substation voltage = 12.66 kV, MVA base = 10 MVA 155 Load at receiving end bus P (kW) Q (kVAr) 100 60 90 40 120 80 60 30 60 20 200 100 200 100 60 20 60 20 45 30 60 35 60 35 120 80 60 10 60 20 60 20 90 40 90 40 90 40 90 40 90 40 90 50 420 200 420 200 60 25 60 25 60 20 120 70 200 600 150 70 210 100 60 40 APPENDIX A 156 Table A.2. System data of 69-bus one feeder test distribution system Sending bus no. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 3 28 29 30 31 32 33 34 3 36 37 38 39 40 41 42 43 44 45 4 47 48 Receiving bus no. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 Resistance (Ω) 0.0005 0.0005 0.0015 0.0251 0.3660 0.3811 0.0922 0.0493 0.8190 0.1872 0.7114 1.0300 1.0440 1.0580 0.1966 0.3744 0.0047 0.3276 0.2106 0.3416 0.0140 0.1591 0.3463 0.7488 0.3089 0.1732 0.0044 0.0640 0.3978 0.0702 0.3510 0.8390 1.7080 1.4740 0.0044 0.0640 0.1053 0.0304 0.0018 0.7283 0.3100 0.0410 0.0092 0.1089 0.0009 0.0034 0.0851 0.2898 Reactance (Ω) 0.0012 0.0012 0.0036 0.0294 0.1864 0.1941 0.0470 0.0251 0.2707 0.0691 0.2351 0.3400 0.3450 0.3496 0.0650 0.1238 0.0016 0.1083 0.0690 0.1129 0.0046 0.0526 0.1145 0.2745 0.1021 0.0572 0.0108 0.1565 0.1315 0.0232 0.1160 0.2816 0.5646 0.4673 0.0108 0.1565 0.1230 0.0355 0.0021 0.8509 0.3623 0.0478 0.0116 0.1373 0.0012 0.0084 0.2083 0.7091 Load at receiving end bus P (kW) Q (kVAr) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.60 2.20 40.40 30.00 75.00 54.00 30.00 22.00 28.00 19.00 145.00 104.00 145.00 104.00 8.00 5.50 8.00 5.50 0.00 0.00 45.50 30.00 60.00 35.00 60.00 35.00 0.00 0.00 1.00 0.60 114.00 81.00 5.30 3.50 0.00 0.00 28.00 20.00 0.00 0.00 14.00 10.00 14.00 10.00 26.00 18.60 26.00 18.60 0.00 0.00 0.00 0.00 0.00 0.00 14.00 10.00 19.50 14.00 6.00 4.00 26.00 18.55 26.00 18.55 0.00 0.00 24.00 17.00 24.00 17.00 1.20 1.00 0.00 0.00 6.00 4.30 0.00 0.00 39.22 26.30 39.22 26.30 0.00 0.00 79.00 56.40 384.70 274.50 APPENDIX A Sending bus no. 49 8 51 9 53 54 55 56 57 58 59 60 61 62 63 64 11 66 12 68 157 Receiving bus no. 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 Resistance (Ω) 0.0822 0.0928 0.3319 0.1740 0.2030 0.2842 0.2813 1.5900 0.7837 0.3042 0.3861 0.5075 0.0974 0.1450 0.7105 1.0410 0.2012 0.0047 0.7394 0.0047 Reactance (Ω) 0.2011 0.0473 0.1114 0.0886 0.1034 0.1447 0.1433 0.5337 0.2630 0.1006 0.1172 0.2585 0.0496 0.0738 0.3619 0.5302 0.0611 0.0014 0.2444 0.0016 Substation voltage = 12.66 kV, MVA base = 10 MVA Load at receiving end bus P (kW) Q (kVAr) 384.00 274.50 40.50 28.30 3.60 2.70 4.35 3.50 26.40 19.00 24.00 17.20 0.00 0.00 0.00 0.00 0.00 0.00 100.00 72.00 0.00 0.00 1244.00 888.00 32.00 23.00 0.00 0.00 227.00 162.00 59.00 42.00 18.00 13.00 18.00 13.00 28.00 20.00 28.00 20.00 APPENDIX A 158 Table A.3. System data of 69-bus four feeder test distribution system Sending bus no. 1 2 3 4 5 6 7 8 4 10 11 12 13 14 1 16 17 18 19 20 21 17 23 24 25 26 27 28 1 30 31 32 33 34 35 36 37 32 39 40 41 42 40 44 42 35 47 48 49 1 51 52 53 54 Receiving bus no. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 Resistance (Ω) 1.097 1.463 0.731 0.366 1.828 1.097 0.731 0.731 1.080 1.620 1.080 1.350 0.810 1.944 1.080 1.620 1.097 0.366 1.463 0.914 0.804 1.133 0.475 2.214 1.620 1.080 0.540 0.540 1.080 1.080 0.366 0.731 0.731 0.804 1.170 0.768 0.731 1.097 1.463 1.080 0.540 1.080 1.836 1.296 1.188 0.540 1.080 0.540 1.080 1.080 1.080 0.366 1.463 1.463 Reactance (Ω) 1.074 1.432 0.716 0.358 1.790 1.074 0.716 0.716 0.734 1.101 0.734 0.917 0.550 1.321 0.734 1.101 1.074 0.358 1.432 0.895 0.787 1.110 0.465 1.505 1.110 0.734 0.367 0.367 0.734 0.734 0.358 0.716 0.716 0.787 1.145 0.752 0.716 1.074 1.432 0.734 0.367 0.734 1.248 0.881 0.807 0.367 0.734 0.367 0.734 0.734 0.734 0.358 1.432 1.432 Load at receiving end bus P (kW) Q (kVAr) 100 90 60 40 150 130 75 50 15 9 18 14 13 10 16 11 20 10 16 9 50 40 105 90 25 15 40 25 60 30 40 25 15 9 13 7 30 20 90 50 50 30 60 40 100 80 80 65 100 60 100 55 120 70 105 70 80 50 60 40 13 8 16 9 50 30 40 28 60 40 40 30 30 25 150 100 60 35 120 70 90 60 18 10 16 10 100 50 60 40 90 70 85 55 100 70 140 90 60 40 20 11 40 30 36 24 30 20 APPENDIX A Sending bus no. 55 52 57 58 59 55 61 62 63 62 65 66 7 68 159 Receiving bus no. 56 57 58 59 60 61 62 63 64 65 66 67 68 69 Resistance (Ω) 0.914 1.097 1.097 0.270 0.270 0.810 1.296 1.188 1.188 0.810 1.620 1.080 0.540 1.080 Substation voltage = 11 kV, MVA base = 10 MVA Reactance (Ω) 0.895 1.074 1.074 0.183 0.183 0.550 0.881 0.807 0.807 0.550 1.101 0.734 0.367 0.734 Load at receiving end bus P (kW) Q (kVAr) 43 30 80 50 240 120 125 110 25 10 10 5 150 130 50 30 30 20 130 120 150 130 25 15 100 60 40 30 APPENDIX B Table B.1. Mean and Standard Deviation of Solar Irradiance Hour µ (kW/m2) σ (kW/m2) Hour µ (kW/m2) σ (kW/m2) 6 0.019 0.035 13 0.648 0.282 7 0.096 0.110 14 0.590 0.265 8 0.222 0.182 15 0.477 0.237 9 0.381 0.217 16 0.338 0.204 10 0.511 0.253 17 0.190 0.163 11 0.610 0.273 18 0.080 0.098 12 0.657 0.284 19 0.017 0.032 Table B.2. Characteristics of the PV module PV module characteristics Value 0 43 Current at maximum power point, IMPP (A) 7.76 Voltage at maximum power point, VMPP (V) 28.36 Nominal cell operating temperature, NOT ( C) Short circuit current, Isc (A) 8.38 Open circuit voltage, Voc (V) 36.96 o Current temperature coefficients, Ki (A / C) 0.00545 o Voltage temperature coefficients, Kv (V / C) 0.1278 160