1 CHAPTER I 1. INTRODUCTION: The increase in demand for electricity and the growing energy demand in metropolitan cities have made it necessary to extend the existing high voltage network right up to the consumer. For reliable power supply and economic advantages, Gas Insulated Substations (GIS) have been installed in increasing number over the last 20years and several units are under erection. GIS of up to 800kV have been developed and are being widely used. Initially, GIS were installed only where land costs are and requirements of environmental compatibility were the main considerations over a period of time as a result of rapid progress of GIS technology, GIS have become economical and popular. GIS is “compact, multi component assembly enclosed inside a grounded metallic encapsulation, which shields all energized parts from the environment the primary insulating medium is SF6 gas. It generally consists of a. Bus bars b. Circuit breakers c. Disconnecting switches d. Earthing switches e. Current transformers f. Voltage transformers 2 g. Cables and boxes h. Gas supplying and Gas monitor equipment i. Density meters j. Local control Gas Insulated Substations (GIS) have found a broad range of applications in power systems over the last two decades because of their high reliability, easy maintenance, small ground space requirement etc. In our country also, a good number of GIS units have been in operation and a large number of units are under various stages of installation. GIS is based on the principle of operation of complete enclosure of all energized or live parts in a metallic encapsulation, which shields them from the external environment. Compressed SF6 gas, which has excellent electrical insulating properties, is employed as the insulating medium between the encapsulation and the energized parts. Gas Insulated Substations have a grounded outer sheath enclosing the high voltage inner conductor unlike conventional equipment whose closest ground is the earth surface. The Basic Insulation Level (BIL) required for a Gas Insulated Substation (GIS) is different from that of the conventional substation because of certain unique properties of the former. Gas insulated bus has a surge impedance (70 Ohm) more than that of the conventional oil filled cables, but much less than that of a over head line (300 – 400 Ohms). 3 In addition, the GIS is totally enclosed and therefore is free from any atmospheric contamination. Hence, in general the GIS permit lower BIL rating than the conventional one. A GIS requires less number of lightning arresters than a conventional one. This is mainly because of its compactness. The basic consideration for insulation co-ordination is Volt-time characteristic. The Volt-time characteristic of SF6 is considerably flat compared to that of air. The air can withstand to very high voltages for very short time. On the other hand SF6 exhibits a flat characteristic. Thus the ratio of basic switching impulse level to basic lightening impulse level is close to unity for GIS, where as for the conventional substations this ratio varies between 0.6 and 0.86[1]. 1.1 ADVANTAGES OF GIS OVER THE CONVENTIONAL, OPEN AIR SUBSTATIONS: 1) GIS station occupies only about 10% of the space required by a conventional air insulated substation 2) GIS can be installed either under ground or indoors and in heavily populated areas 3) GIS are also conveniently used in coastal areas (salt pollution) and industrial and urban locations where space and pollution are the main considerations 4) These substations are generally located closer to the load centers there by reducing the losses in transmission and distribution networks 4 5) GIS Systems are immune to atmospheric conditions and pollution, the outages get reduced and coupled with their increased reliability, the overall maintenance costs are minimized 6) Estimation of radio interference with use of earthed metallic enclosures 1.2 DISADVANTAGES OF GIS: Although GIS has been in operation for several years, a lot of problems encountered in practice need fuller understanding. Some of the problems being studied are: 1. Switching operations generate Very Fast Transient Over voltages (VFTO). 2. VFTO may cause secondary breakdown inside a GIS and Transient Enclosure Voltages (TEV) outside the GIS. 3. Prolonged arcing may produce corrective / toxic by-products 4. Partial discharges with in the enclosures can cause break downs 5. Metallic particle contamination 6. Transient electric field and transient magnetic fields 7. Field non-uniformities reduce withstanding levels of a GIS. 8. Support spacers can be weak points when arc by-products and metallic particles are present. 5 For these reasons, VFTO generated in a GIS should be considered as an important factor in the insulation design. For designing a substation it is essential to know the maximum value of VFTO. Moreover, this VFTO in turn generates Transient Enclosure Voltages (TEV) outside the GIS. For designing a GIS systems it is essential to know the maximum value of VFTO moreover, this VFTO in turn generates TEV outside the GIS, hence studies are carried out on estimation of the VFTO. In GIS, Very Fast Transient Over voltages (VFTOs) are caused by two ways, due to switching operations, line to enclosure faults and internal insulation flashover. The internal FTO’s generated have traveling wave behavior of a surge. Since FTO’s have the characteristics of traveling wave, they can change significantly at different points within GIS. These FTO’s travel to the external system through enclosures, gas-air bushings, cable joints, current transformers etc. and may cause damage to the outside equipments like high voltage transformers connected to the GIS. FTO’s can also lead to secondary breakdown in GIS. Further they may give rise to electro-magnetic interference. Since the contact speed of the dis-connector switches is low, restriking occurs many times before the interruption is completed. Each re-strike generates VFTO’s with different levels of magnitude [2]. 6 Dis-connector Switches (DS) are used primarily to isolate the operating sections of an HV installation from each other as a safety measure. Beyond this, they must also be able to perform certain switching duties, such as load transfer from one bus bar to another or disconnection of bus bar, circuit breaker etc. Step shaped traveling wave generated between the dis-connector switch contacts propagates in both directions, reflecting at the components of GIS, thus resulting in a complex waveform. 1.3 THE MAIN PROBLEMS ASSOCIATED WITH THE VFTO ARE AS FOLLOWS: 1. Flashover to Ground at the dis-connector switches contacts. 2. Failure of electronic control circuits connected to GIS, because of electromagnetic interference of VFTO. 3. Dielectric strength is reduced under VFTO, if non-uniform electric field is formed by the particles (mainly metallic). 4. Effect on components such as bushing and transformer. 5. Transient Enclosure Voltage (TEV) on external surface of the sheath. This may cause flashover to near by grounded objects. 6. Transient electromagnetic field causes malfunctioning of secondary equipment. 1.4 SUPPRESSION OF VERY FAST TRANSIENT OVER VOLTAGES Switching an unloaded bus bar in GIS with a disconnectror can cause multiple restriking of the disconnector gap and produce steep 7 travelling waves propagating on the bus bar. Reflection and superimposition of the travelling waves forms very fast transients in GIS systems. These VFTOs can reach to high amplitude and steepness. The suppression of VFT in GIS has been a long standing problem. One way is to avoid dangerous layout of GIS and dangerous operation procedures of the disconnectors. However, this brings a big limitation to design and control operation of GIS, another way is design and control operation of GIS and other way is to use high speed disconnector. This can reduce the occurrence probability of VFT, but cannot avoid VFT completely. The new VFT suppression method is that putting high frequency magnetic rings on GIS bus bar can increase the local inductance of the bus bar, resist the travelling waves passing through, consume the energy of the waves and therefore make suppression effect of VFT. Modeling of ferrite rings has been proposed and simulations have been performed to investigate how the ferrite rings influence the travelling waves. 1.5 TRANSIENT ELECTROMAGNETIC PHENOMENA IN GIS SYSTEMS: In gas insulated substations (GIS) very fast transient overvoltages are generated during switching operation of disconnector switch (DS) and circuit breakers (CB). These transient currents (VFTC) have rise times of about 3-20ns The magnitude of transient currents could be a few kA depending on the location of the switch operated in the GIS these transient voltages and currents radiate electromagnetic fields during its 8 propagation along the gas insulated HV bus as the associated frequencies are in the range of few MHz to about 300MHz[3].The transient electromagnetic fields thus generated in turn may leak out into external environment through discontinuities like non-metallic flanges, SF6 to air bushing ,SF6 to cable termination, non-metallic viewing points etc. These transient fields may couple with the control wiring and data cables and produce transient current and voltage on them leading to malfunctioning of control equipment during switching operations is a severe problem in some cases. The estimation of transient EM fields is gaining importance in recent times for characterizing the transient EM fields or transient electromagnetic interference EMI in a GIS, it is essential to predict the transient EM field emission from a gas to air bushing due to the very fast transient currents generated during switching events. The characterization of transient EMI in terms of time domain and their frequency spectra for the highest expected levels is very important for temporary upset or permanent damage of the control equipment In practice, in GIS stations the wiring between the instrumentation is poorly shielded due to lack of light weight and flexible cables and simple low cost shielding terminations [4]. The control circuit shielding is very important, because VFTO produces voltages and currents in the control circuits, which get added up at the terminals of the equipment resulting in complex transient waveforms that are further complicated by 9 the presence of resonance in the cable itself. Experimental measurements have shown that open circuit voltages on control wiring within the GIS building can reach up to 1000V during disconnector switch operations. Similar voltages on the control wiring that is directly exposed to the fields from the gas/air bushing can reach values up to 10kV [5].Due to improper shielding of the equipment housings, cable termination boxes and similar devices, certain portions will be exposed to transient electromagnetic fields. Estimation of magnitudes of these fields are essential to decide the quality of shielding to be provided to the control equipment mounted directly on the switchgear or on the bus bar enclosure [6]. Complete and effective shielding design against VFTOs is extremely difficult in the frequency range of 1MHz to 30MHz [7]. The substation configuration switchgear design and control equipment wiring process as well as the life of the electronic equipment influence the design of the shielding. Improvements in these areas will help to improve the effectiveness of shielding thus reducing the effect of electromagnetic transients on the equipment and personel.GIS stations have to meet high standards of reliability in operation and therefore the risk of failure due to over voltages must be kept to a minimum. The main parameters that gives rise to over voltages are the substation layout, the connections to the external transmission lines, arrangements of earth wires, the tower grounding and location of lightning arresters. When connecting a GIS to 10 an over head lines, the lightning performance investigations have to be carried out at very high voltage levels, more than 245kV class, it must be ensured the specified insulation levels. The insulation levels for GIS chosen from IEC 71 given in IEC 60517. The switching over voltages are higher than voltages between the lines for three phase encapsulation. The dielectric strength between phases and phase to earth is to be designed carefully. To minimize the risk of failures by over voltages and the maximum over voltages has to be safety factor. If the over voltages are obtained on experience, then it is called conventional safety factor in the case of lightning over voltages and it depends on the system voltage. The insulation coordination of GIS is mainly depends on very fast transient over voltages, the greater attention has to be paid on these to adopt standard insulation strategy. From the above it can be seen that the estimation of magnitude of very fast transient voltages and very fast transient currents and its suppression methods, estimation of transient magnetic fields and transient electric fields are also very important for design of a GIS. 11 1.6 VARIOUS COMPONENTS OF GIS The general lay out of the 245kV GIS comprising of the following components. 1.6.1 Circuit breakers for GIS systems: The synchronized axial blast method is used which significantly boosts circuit breaking performance and also hand holes are provided to access to the interrupter contacts for inspection and replacement. The overall size of the circuit breaker in a GIS is considerably reduced due to the absence of porcelain insulators and the use of short terminal connections. Since the breaker chamber is at earth potential the clearances between adjacent bays or bus bar systems is reduced. Also the energy requirement of the operating mechanism is considerably low. The breaker is normally provided with a hydraulic spring opetrating mechanism for each phase to facilitate single-phase auto-reclosing. 1.6.2 Disconnector switches: In GIS, the disconnecting switches are used for electrical isolation of circuit parts. Components of the disconnector switches are mounted in a enclosure with the active parts supported by insulating spacers these are two types 1) Axial Disconnectors 2) T-type Disconnectors 1.6.3 Earthing switch: In GIS, earthing switches are used to facilitate grounding of conducting parts during maintenance. They are generally slow acting devices that are operated during the off state of the GIS equipment 12 opening of these switches can be done either by an electric motor or normally. Fast acting switches suitable for GIS equipment and these are driven by motor operated drives. 1.6.4 Current transformers: Current transformers are required for measurement of the current flowing through the equipment and for providing protection. The current conducting bar forms the single turn primary while the secondary coils are located on a toroidal iron core which is placed concentrically around the primary. The output of secondary winding is brought out through high gas trough. 1.6.5 Voltage transformers: Voltage transformers are required for measurement of the voltages in the network for operating the protection system. The transformers are of resin cast type for lower voltages and SF6 gas insulated type for higher voltages. In case of a gas insulated voltage transformer, the primary and secondary windings are concentrically on the core. The spacer insulator is used for high voltage connections and for isolating the gas space from the GIS equipment. The low voltage leads are connected to the terminal box mounted on the enclosure through gas tight bushing insulators. The voltage transformer is fitted with gas valves for evacuation and filling up of the SF6 gas. The ratings are up to 200VA. They shall be foil-gas insulated. 13 In brief a typical 245kV Gas Insulated Substation comprises the following components: Circuit Breaker Isolator Dis-connector Switch Earthing Switch Current Transformer Voltage Transformer Bus bar & Connectors Power Transformer Bushing & Cable When designing the GIS, space-associated costs are reduced, resulting in a substantial reduction in overall station costs, as GIS occupies only roughly 10% of the space required by a conventional substation. Typical cases for which GIS is undoubtedly the more economic solution (along with areas of major cost savings) are given below: 1. Urban and Industrial areas (space, pollution) 2. Mountain areas (site preparation, altitude, snow and ice) 3. Coastal areas (salt-associated problems) 4. Underground substations (site preparation) 5. Areas where aesthetics are a major concern (Landscaping etc.) 14 1.7 GENERATION OF VERY FAST TRANSIENT OVER VOLTAGES (VFTOs) IN A GIS: During the switching operation of dis-connector switch in a GIS, restrikes (pre-strikes) occur because of the low speed of the dis-connector switch moving contact, due to the very fast voltage collapse within a few nano seconds(ns) and the subsequent traveling waves, Very Fast Transient Over-voltages are developed. The main oscillation frequency of the fast transients depends on the configuration of GIS [8]. Moreover, the effect of complexity of the configuration of a GIS on the peak value of the transients has been studied in this thesis. For the development of equivalent circuits, low voltage step response measurements of the main GIS components have been made. Using the EMTP-RV the equivalent electrical models are developed. The peak value of the fast transients often occurs when circuit structure is relatively simple, but more frequently if the structure is rather complicated. The propagation velocity of traveling wave generated during dis-connector switch operation is about 30cm/ns. The representation of bushing is important for simulating the fast transients. Generally, the transit time through a bushing is comparable to or greater than the rise time of GIS generated transients. For this reason, bushings cannot be considered as a lumped element in estimating the VFTO level. The generation of fast transients can be classified into two types. They are due to the following: 15 a) Dis-connector switch operation b) Faults between Bus bar and Enclosure In case of line-to-earth fault, the voltage collapse at the fault location occurs in a similar way as in dis-connector gap during restriking. By this event, step shape traveling surges are injected. For such a surge source inside GIS, two surges traveling in opposite directions are generated. However, if voltage collapse occurs at the open end of GIS, only single surge propagates on the bus. Spark collapse time is defined as the time to bridge the gap with the spark after the initiation of breakdown. A longer spark length causes longer spark collapse time. It was also observed that with a constant SF6 gas pressure, a higher inter electrode breakdown voltage causes longer spark collapse time. With the same voltage, a lower gas pressure also causes longer spark collapse time. When SF6 breakdown occurs it re-combines very quickly, since it has a high electro-negative property. Due to this property, re-striking voltages of the order of nanoseconds rise time are produced. Hence FTO’s are mainly due to properties of SF6. As a consequence of characteristics of breakdown in electro-negative gases and short traveling wave times in GIS resulting from short overall length, transient over-voltages with steeper voltage rise and higher frequencies are produced. Breakdown in SF6 starts initially by avalanche, starting with initiatory electron due to cosmic radiation, field emission or several other 16 phenomena producing electrons. These electrons are accelerated by electric field thereby increasing its kinetic energy. As a result, number of electrons increases because of collisions. According to streamer criteria, first avalanche occurs followed by chain of avalanches bridging the gap between the electrodes and thus forming a streamer. Thus, to have breakdown there should be sufficient electric field to produce sequence of avalanches and there should be at least one primary electron to initiate first avalanche. In the above sequence of events there exists a time lag for initiating electron to be available in the gap after the voltage is applied. This time lag is termed as the Statistical Time Lag. Similarly the formation of spark channel takes definite time known as Formative Time Lag (Tf) and is defined below [17]. KT Tf = 4.4 ∗ l ∗ U Where l = Spark Length KT = Toepler’s Constant U = Ignition Voltage This time lag is of the order of nanoseconds. Therefore the rise time of FTO’s will be of the order of nanoseconds. The above phenomenon suggests that the FTO’s are generated due to voltage collapse, which occurs when spark is produced. This spark is produced after a time lag of Tf. 17 Dis-connector Switches (DS) are designed to interrupt small charging current that flows through the short lines as fast as the circuit breaker. In this case, since the contact speed of DS is generally slow, restriking occurs a number of times before interruption is completed, resulting in generation of high frequency surge voltage each time re-strike takes place. DS operation in GIS generates the largest line-to-ground voltage transients imposed on the switchgear during normal operation. 1.7.1 Principle of FTO Generation: During opening operation of Dis-connector Switch (DS), transients are produced due to large number of re strikes between the contacts. The magnitude of these transients and rise times depends on the circuit parameters like Inductance, Capacitance and Connected Load. Assuming that some trapped charge is left during opening operation, transients can be calculated during closing operation of DS. Fast Transient Over voltages generated during Dis-connector Switch operation are a sequence of voltage steps created by voltage collapse across the gap at re-striking. Specific over voltage shape is formed by multiple reflections and refractions. Operation of Dis-connector Switch (DS) is shown in the Fig. 1.1. 18 Fig 1.1 Electric Circuit for explaining re-strikes Where L1 = Inductance of Source C1 = Capacitance of Source C2 = Capacitance of GIS Open Part U1 = Power Frequency Voltage U2 = Voltage of GIS Section The more frequent service situation of the isolator is its use to connect or dis-connect unloaded parts of the installation as is shown in Fig.1.1. For example, a part of the GIS is dis-connected by an isolator from a generator or from an overhead supply line, where by the selfcapacitance C2 of this part of circuit can be up to several nF, depending on its length. First re-strike across the gap occurs when voltage across the gap exceeds the breakdown voltage. The occurrence of sequence of re-strikes is described with the following Fig. 1.2. 19 Fig 1.2 Voltage of the open-ended GIS side of the Isolator The voltage across the gap is the difference between U1 and U2. If it is assumed that the breakdown voltage UB of the gap increases with increasing separation and therefore with time as shown in Fig 1.2. Then the curve U2 can be constructed as follows. At the instant of mechanical contact separation, U1 and U2 have the same value, the voltage U2 continues to retain this value, while U1 changes with power frequency. The voltage (U2 - U1) across the gap of the isolator also changes. As soon as, (U2–U1) exceeds the dielectric strength UB of the gap, a breakdown and thus a first re-strike occur. Both electrodes are there by electrically connected by a conducting spark, whereby GIS section with initial voltage U2 is very rapidly charged to instantaneous value of U1. The transient current flowing through the 20 spark then interrupts as soon as the GIS have been charged to U1 and spark extinguishes. The voltage U2 now remains constant with time, while the voltage U1, on the side of supply keeps changing. This continues until the second re-strike occurs with an increased breakdown voltage UB as a consequence of larger separation. Hence U2 follows U1, until finally at the end of the switching process the gap no longer can be broken down. Transients are also produced due to faults in the system. When there is a fault, there will be short circuit in the system. Due to this, oscillations occur due to presence of inductance and capacitance on both sides of the fault section causing transients. 1.8 SECONDARY BREAKDOWN IN A GIS: Very Fast Transient Over voltages (VFTO) caused by switching operations can lead to Secondary Breakdowns within Gas Insulated Substations. In the first type, the flashover to ground at the dis-connector switch contacts is due to the streamer generated during re-strike or pre-strike between the dis-connector switch contacts. Secondly, inside the GIS, like particles or fixed protrusions cause an inhomogeneous field distribution and insulation can fail. In these two types of earth faults, VFTO are developed. The flashover voltages under these two conditions are appreciably lower than the normal withstanding voltages to the ground. 21 1. Streamers are generated from several locations over a contact. Apparently one of these streamers develops a flashover between the contacts, while the flashover to ground is caused by the development of the other streamers. 2. The flashover voltage to ground is lower when the spark is generated between the disconnector switch contacts by an impulse voltage than when the spark is simulated with a piece of wire. This is because of the existence of streamers. Practically, it can be observed that the VFTO induced earth faults are possible at the disconnector switch contacts during its operation. This is because of the development of the enhanced field gradient to earth and later VFTO will be generated in the GIS. The breakdown from the live conductor to the outer conductor is possible under VFTO or impulse voltages. Thus it is important to develop a simulation model for the breakdown and the characteristics of the spark channel. The time varying process during voltage breakdown and the resulting VFTO can be measured. The computer simulation model for this breakdown can be developed. The results obtained with EMTP-RV are compared with measured values. The time varying process during the building of the spark will be simulated by using the Toepler’s spark law. 1.9 SURGES IN GIS: The discharge process during each individual re-strike begins with a voltage collapse across the contact gap, which because of the particular 22 breakdown mechanism in electronegative gases takes place within only approximately 10-8 sec [9]. This voltage collapse is directly related to the formation of the spark channel. With a typical voltage decrease rate of 1013 v/s (100 kV in 10 ns), it is the stimulus for a traveling wave, which propagates away from the gap into the installation. After a certain travel time the wave front reaches the open end of the GIS section, is then reflected and travels back again crossing the gap that is still short-circuited by the spark, until it reaches the next discontinuity in the surge impedance, such as for example the connection of the GIS to the overhead line. Here it is now partly reflected. On this partial reflection the wave splits itself into a Reflected and a Transmitted component. The Reflected component travels a second time towards the open end of the GIS and is there again reflected. For this reason, the discharge transient shows a periodicity of double the traveling time of the wave in the GIS. The amplitudes of the voltage and current surges depend on the restriking voltage and on the parameters of the circuit. Therefore very different amplitudes can occur depending on the complexity of the installation. 1.10 RE-STRIKES AND PRE-STRIKES IN GIS: Disconnector Switch (DS) operation typically involves slow moving contacts which results in numerous discharges during operation. For example, a floating section of switchgear between a disconnect switch and 23 an open breaker (load side) may be disconnected from an energized Gas Insulated System (supply side). For capacitive currents below 1Amp, a re-strike occurs every time the voltage between the contacts exceeds the dielectric strength of the gaseous medium between them. Each re-strike generates a spark, which equalizes the potential between the switch contacts. Following spark extinction, the supply and load side potentials will deviate according to the AC supply voltage variation and the discharge characteristics of the load side respectively. Another spark will result when the voltage across the electrode gap dependent breakdown voltage UB and the potential difference of the load and supply side, U. Each Dis-connector Switch (DS) operation generates a large number of ignitions between the moving contacts. The number of ignitions depends on the speed of the contacts. The largest and steepest surge voltages are generated only by those breakdowns at the largest contact gap. Therefore, only a few breakdowns (10–50) need be considered for dielectric purpose. The slow operation and very rapid breakdown give rise to ‘TRAPPED CHARGE’ and traveling wave surges within Gas Insulated Substation (GIS). 24 1.11 TRAPPED CHARGE IN GIS: When a Disconnect Switch is opened on a floating section of switchgear, a Trapped Charge may be left on the floating section. The potential caused by this charge will decay very slowly as a result of leakage through spacers. A trapped charge near 1.0p.u (peak) can levitate particles [10] Particle motion under D.C conditions is much more severe than that for A.C excitation and may lead to scattering of particles onto insulating surfaces. However, such particle motion leads to appreciable D.C currents of few µA, which will normally discharge the floating section in a relatively short time. A trapped charge of 1 p.u implies that the first breakdown upon closing the disconnect switch will occur at 2 p.u across the switch contacts and may lead to conductor–to–ground over voltages of up to 2.5 p.u. Thus the magnitude of trapped charge left after operation of a disconnect switch may be of some consequence to switchgear reliability. During recent field tests on a 500kV sub station, measurements were made of the trapped charge left when a DS was opened onto a floating section of switchgear. Numerous measurements led to the conclusion that for this switch, a potential of 0.1 – 0.2p.u is left on the floating section and that this result is consistent. The reason for this consistent result is that the negative breakdown occurs at approximately 25 15% greater potential difference than the positive breakdowns for this switch. The asymmetry in breakdown voltages leads to the “falling” pattern near the end of operation which continues until the potential is low enough that breakdowns can occur during the rising portion of a power frequency cycle as shown in below Fig.1.3. Fig. 1.3 Load side voltage waveform during opening of disconnect switch Two such breakdowns bring the potential back to a large positive value after which the falling pattern is re-established. The end point of this process is inevitably a transition from a large negative potential to a slightly positive potential at a gap distance for which the positive breakdown potential is ≈ 1.1 p. u (peak) and the negative breakdown potential is ≈ 1.2 p. u (peak). At this point another positive and negative breakdown cannot occur, as a result 0.1 - 0.2 p. u (peak) is left on the floating switchgear. 26 The salient features which lead to this small trapped charge are the asymmetry in breakdown potential and relatively long arcing time. This trapped charge can be controlled through careful design of contact geometry. For the purpose of calculating transient magnitudes, a trapped charge of 1.0p.u (peak) prior to closing of Dis-connector Switch (DS) is assumed. One of the methods suggested to suppress these over voltages is by insertion of a resistor with an appropriate value during switching. 1.12 CURRENT CHOPPING: When a Circuit Breaker (C.B) is made to interrupt low inductive currents such as currents due to no load magnetizing current of a transformer, it does so even before the current actually passes through zero value, especially when the breaker exerts the same de-ionizing force for all currents within its short circuit capacity. This breaking of current before it passes through the natural zero is termed as “Current Chopping”. The energy contained in the electro-magnetic field cannot become zero instantaneously. The only possibility is the conversion from electromagnetic to electro-static of energy. i.e. ⇒ 1 2 1 LI = CV 2 2 2 V= L ∗I C 27 Generally in Vacuum or SF6 circuit breakers the currents chopped are of the order of 5 Amps. When a constant de-ionizing force is applied by a breaker for arc interruption, then force must be high enough to interrupt highest value of short circuit current. Fig 1.4 waveform of over voltage with current chopping Now, if the breaker is called upon to break a load current which is less than the highest short circuit current, then the de-ionizing force would be sufficient enough to force the arc from its high value straight to 28 zero before the same actually reaches to natural zero. This results a tremendous amount of over voltage as shown in the above Fig 1.4. This phenomenon is termed as “Current Chopping”. 1.13 FREQUENCY CHARACTERISTICS OF VFTOS/VFTCS IN GIS SYSTEMS AND ITS IMPORTANCE: Very fast transient over voltages generated due to switching operations of disconnectors in GIS system. These VFTOs and associated VFTCs radiate electromagnetic fields (EM) fields during its propagation through the coaxial GIS bus section as the associated frequencies are in the range of few MHz to about a hundreds of MHz. The transient electromagnetic fields in turn, leak out into the external environment through discontinuities such as SF6 gas to air bushing, gas to cable termination, non-metallic viewing ports, insulated flanges etc. in addition to the radiated EM field coupling, conducted mechanisms are also responsible for the coupling of very fast transient currents to the control wiring. The size of the electrical components in GIS are much smaller than AIS(Air Insulated Substation), so the frequencies of multiple reflection of travelling waves on the bus bars of GIS at least ten time higher than the AIS. The characteristic impedance of the high voltage bus bars in GIS is about five times smaller than that of AIS. i.e 60Ω in GIS instead of 300400Ω in AIS. Therefore the capacitive currents of off-loaded bus bars in GIS are larger than such capacitive currents in AIS. Because of the lower 29 characteristic impedance as well as large gradient of electric field between the prestrike and restrike arcs in SF6 gas under pressure in reference to grounded enclosure. This leads to an important difference of impedance at the junction of the GIS and high voltage over head line, bushings, open circuit breaker or disconnetor contacts as well as open air bus bars. These differences are, during switching operations, origin of high standing voltage and current waves. The amplitudes of voltage waves depends on the voltage level and it is comparable of the current waves are inversely proportional to characteristic impedance. The metal enclosure of the GIS presents a shielding discontinuity, i.e. at the junction with high voltage over head lines or cables; it becomes an important source of radiation. The consequences of the features, during switching operations are very high potentials induced in the grading system of the substation and in the secondary circuits. These problems are more dangerous in usually small distances in GIS systems. As said above, the transient response of the control circuits is a function of the frequency content of the VFTC. Hence it is essential to segregate VFTC waveform into time and frequency scales simultaneously. For this purpose a GOBOR wavelet function is used to obtain time-frequency spectrum of the VFTC waveform at important locations of the 245kV GIS. 30 1.14 TRANSIENT ELECTRIC FIELD AND MAGNETIC FIELDS GENERATION AT GIS STATIONS The estimation of transient magnetic and electric fields are very important in the GIS systems because usually the high frequency EM fields are leak out at the bus bar terminations i.e. air-gas bushing, cable termination during disconnector switch (DS) operation. The transient voltages and currents radiate electromagnetic fields during its propagation along the gas insulated high voltage bus as the associated frequencies are in the range of few MHz. to about 300MHz [11]. The transient electromagnetic fields thus generated in turn may leak out into external environment through discontinuities like non-metallic viewing ports etc. these transient fields may couple with the control wiring and data acquisition systems etc. Malfunctioning of the primary /secondary equipment have been reported by many authors during switching operations of the GIS due to induce and /conducted voltages on control circuits. It is essential to predict the transient EM field emission from a gas to air bushing due to the very fast transient currents generated during switching events. The characterization of these transient EM fields are essential, because these are very sensitive to VLSI circuits, SCADA systems etc. The estimation of emission levels from the gas insulated equipment during switching events is found to be important to the EMC design of control devices operating in such EM environment and hence to ensure 31 reliable operation of the system. So, the estimation of Transient EM fields are important in GIS systems to avoid temporary upset or permanent damage of control equipment. 1.15 LITERATURE SURVEY: 1.15.1 Literature survey on VFTOs Working group of 33/13-09, CIGRE [1] deals with the given qualitative description of origin of VFTOs associated with gas insulated substation. They also described the effect of these VFTOs on different equipments like transformers, circuit breakers and bushings etc. B.P. Singh [2] et al deal with the modeling concept of a typical GIS and various over voltages generated due to switching operations and line fault for fixed and variable arc resistances and in the presence or absence of load. J.Meppelink [3] et al described the origin of very fast transients in GIS. The different types of very fast transients are classified. Switching operations in GIS lead to VFTOs. The effects due to these VFT’S are radiate transient magnetic fields and transient electric fields at bushing terminations and cable terminations. Ivo Uglesic[4], et al described the problems associated with VFT’S in Gas insulated sub stations. He describes the electromagnetic compatibility (EMC) of secondary equipment in the 123kV GIS. The cause for malfunctioning of bus bar protection scheme due to disconnector switch operation was discussed. Continuous monitoring of 32 GIS equipment against VFT’S and influence on secondary equipment and some precautionary measures also recommended. K. Diederich[5] et al, described the Origin of Very Fast Transients in GIS. Switching operations in a GIS lead to very fast transient phenomena, which can be subdivided into internal and external very fast transients. These VFT’s stress the equipment in GIS as well as the secondary equipment. S. Yanabu [6] et al has experimentally estimated fast transient over voltages in GIS. The maximum FTO estimated from observation was 2.7p.u. This was observed infrequently and occurred only at the open end of the bus bars. S. A. Bogss [7] et al carried out field tests for measurement of disconnector switch operation induced transients and indicated that transients do not exceed 2.0p.u. Further it gives that the trapped charge left during dis-connector switch opening depends on the design of the switch. S. Ogawa [8] et al, proved that re-striking surge of dis-connector switches can be estimated by conducting calculations with considerably high accuracy than measured waveforms. Accuracy of as low as 3% to 5% has been achieved for measured and calculated values. Z. Haznadar [9] et al & R. Witzmann [8] et al, have developed models for different GIS components and conducted experiments with regard to waveform distortion on various models consisting of spacers, bushing etc. Amir Mansour Miri[10] et al, presented numerical and experimental evaluation of the transient behavior of GIS. With the help of electrical 33 equivalent circuits of GIS components, the generation and propagation of transients inside GIS have been evaluated. Nobuhiro Shimoda [11] & J. Ozawa [11], describes the method of suppression of transient over voltages caused by dis-connector switch. This is obtained by insertion of resistor with appropriate value during switching operation. T. G. Engel [12] et al, determined the resistance of high-current pulsed arc by various formulae. The results indicate that in the initial stages of discharges (t < 0.5µs), equation developed by Toepler and some other authors are identical. G. Ecklin and D & Schlicht [13], describes the operation and switching procedures with isolators occurring in GIS and the principle operation of FTO’s generated in GIS. Tohei Nitta [16] et al, describes surge propagation in GIS. Traveling velocity of surges is equal to the velocity of light. Any component, which adds extra ground capacitance to the system, should be properly included in the calculation model. Small inductance plays important in the surge propagation performance of a given system. P. Osmokrovic [17] et al, describes the formative times and Toepler’s constant approach to modeling the breakdown event and it depends on the macroscopic parameters of the insulation. V.Vinod kumar[18] et al describes the VFTO computations on 420kV GIS system. The variation of VFTO peak along the nodes for disconnector and circuit breaker operations as well as the variation of 34 VFTO with different trapped charges have been studied. The results indicate a distinct pattern of variation of VFTO Peak along the nodes of the GIS in the case of disconnector switch operation as compared to that of circuit breaker operation. D.Povh,[19] et al reported the phenomena of very fast transients in a gas insulated substations. The corresponding GIS equivalent circuits are useful to simulate VFT’s in the range of 100 KHz to 50MHz. validation of simulations is proved by comparing the results with measurement results. Jinsong tao[20] et al describes disconnect switches operation is most frequent process in switch yard and substation and it is also a source of electromagnetic interference to control circuits in substation or environment for its radiated and conducted characterstics. V.Vinod kumar[21] et al estimated the magnitudes of very fast transient over voltages in a 420kV GIS. The variation of peak along with the GIS bus nodes for disconnector and circuit breaker switching operations. Xiang Zutao[22] et al describes suppression of very fast transient over voltages in a GIS systems. Suppressing with MOA and resistance switching are discussed. The calculated results are compared with the measured results. The results shows that VFTO’S are suppressed up to some extent. L.I.Qing–min [23] et al describes the use of ferromagnetic rings suppress the amplitude and steepness of VFTO generated with in GIS. Based on equivalent description of the complex magnetic spectrum of ferromagnetic materials as well as the application of transmission line 35 theory, a simulation model is established in frequency domain to analyze the suppressing characteristics of very fast transients in GIS. Z. Haznadar [24] et al presented modeling techniques of GIS components to estimate very fast transient electromagnetic transients. Very fast electromagnetic transients caused by switching operation in gas insulated substations are estimated using most suitable models. The results are compared with the results obtained from field tests. Mastake Kawada [25] et al describes non contact method for detecting insulation fault. To detect the wide-band electromagnetic wave emitted during switching operation of disconnector switch using wavelet transform. The wavelet transform provides a direct quantitative measure of spectral content, dynamic spectrum in the time-frequency domine. Lu lu & Lin Xin [26] et al describes the three dimensional electric field of 800kV SF6 Air chamber is analyzed by using the finite element based software. For the complex analysis the extra-high voltage disconnector chamber is considered to estimate electric filed intensity distribution. Theoretical basis for construction design of disconnector is supplied according to analyzed results of electric fields. Toshihiro Hoshino [27] et al describes detection of electromagnetic by antennas to diagnose the insulation performance of GIS to establish high sensitive diagnosis technique of GIS insulation, frequency charaterstics of electromagnetic wave are established. Based on these results how the aperture condition contributed to the radiation 36 characteristics of electromagnetic wave. Finally they concluded that the electromagnetic wave radiated from GIS aperture was based on different radiation mechanism in frequency. C.M.Wiggins[28] et al has measured transient electric field and magnetic fields and he described the characterization of the these fields .the dominant frequency components are also presented. The dominant frequencies of switching transients are observed between 0.5MHz to 120MHz. J.A.Martinez [29] et al describes the guide lines for digital simulation of very fast transients in gas insulated substations and also he discussed about the origin of VFT over voltages, their propagation and effects on GIS equipment is included. Meng Tao [30] et al described calculation of VFTO’S in GIS systems. He also discussed the suppression effect of cable and SF6 bus bar. He pointed out that VFTO peak values may be restricted by increasing the length of the cable and by varying the capacity of shunt capacitor. Zhang Bo [31] et al describes VFT effect on generator transformer insulation in 500kV GIS. He simulated Tian Huangping pumped storage power station in east china power system. The magnitudes are analyzed for various conditions. C.Y.Lui[32] et al describes the effect of VFT on GIS spacer insulation, and he discussed the critical transient fields occured along the surfaces of cone type insulators, and he estimated various fields levels at various voltage conditions. OS.Singa [33] et al describes the 37 study of the very fast transient over voltages with SF6-N2 gas mixtures as the insulating medium. With different percentages of SF6 he recorded the VFTO levels during disconnector switch operation. In mixtures no significant difference in the VFTO levels is seen between pressure 2-4 bar. Shigeto Fjita[34] et al describes the effect of VFTO on shell type transformer. In his work inorder to simulate waveforms of VFT invading a transformer a simple equivalent circuit for shell type transformer in a high frequency range is derived using this model, the over voltages are analyzed for various configurations of GIS. Akihiro Ametani [35] et al describes the effect of VFTO particularly on low voltage control circuit cable through a measuring voltage transformer. He found that the oscillating frequency of the switching surge exceeds certain limit. He investigated switching surge characterstic in the low voltage control circuits. Laboratory tests are performed accordingly to IEC 61000-4-12. K.Feser[36] et al describes very fast transients occur in a gas insulated substations stresses the equipment in GIS , adjacent equipment. The different types of very transients are classified and their characterstic parameters are summarized based on the measurements. They concluded transient over voltages are of two types internal and external, but the frequency spectrums have not clearly discussed. Jinsong Tao [37] et al describes the electromagnetic interferences is most common during disconnector switch operation. Peak values of 38 high frequency interferences are different according to the time of operation of disconnector switch. The value at zero crossing of power frequency voltage wave shape is far less than at peak point time. Joy Thomas .M [38] et al carried out EMTP simulations on 420kV Gas Insulated sub station. The variation of VFTO peak along the nodes for disconnector and circuit breaker operations as well as the VFTO with various operations as well as the VFTO with various trapped charges have been studied. They concluded that the VFTO peak levels are not proportional to the increase in the trapped charge. Xulianyuan [39] et al describes the effect of GIS apparatus parameter on a very fast transient over voltages. The suppression effect of cable and SF6 bus bar is discussed and influence of the shunted capacitor is analysed in this paper. They concluded that the VFTO peak values may be restricted by increasing the length of the cable and SF6 bus abr. Liu weidong [40] et al describes the suppressing methods of VFTO wee discussd. Simulation tests were conducted on GIS model, with time variant resistor as a arc in switch. Different magnetic materials were used to suppress the VFTOs. They concluded that the VFTOs distinctly suppressed by amorphous material (R2KB). Lu Tiecheng [41] et al describes the simulation of 500kV GIS substation to estimate VFTOs using EMTP, they also discussed about various factors influences the over voltages. The VFTO effect on transformer insulation is discussed. 39 Thomas H. Dodds[42] et al presents the development of basic insulation level. The unique properties of the ga insulated substation are analysed and insulation coordination design techniques are utilized to determine BIL ratings for the substation eequipment. Tavakoli.A [43] et al discussed regarding effective factors which effect on wave shape and level of the VFTO and VFTC. The effect of trapped charge compensation resistor, hybrid compensation filters L and T types and variation of arrangement of switchgear is discussed. And they concluded the considerable when compared to hybrid compensation filters L and T. J.A.Martinez [44] et al describes the modeling guide for digital simulation of VFT in Gas insulated substations. They discussed regarding origin of VFTs, propagation and effects. Several examples corresponding to actual cases with detailed data input and validated simulation results are presented. In the digital simulation, they considered the arc resistance is a variable resistance which varies experimentally decreasing resistance and the resultant time for break down considered as 10ns. The investigation clearly shows that detailed information of the internal design of GIS and also external equipment like bushings, transformers etc. J.C.Mendes [45] et al describes the EMTP simulations of a standard GIS disconnector when interrupting small capacitive currents. They mainly discussed high frequency transformer model to with stand VFT, the evaluation of the VFT voltage stress on the HV terminal of the 40 transformer directly connected to the GIS. They estimated voltage stress to design transformer winding insulation. Amit kumar[46] et al investigated phenomena of VFT in Gas Insulated S ubstations, the typed EHV-GIS substation is modeled and simulated using PSCAD4.2 version. They considered closed disconntor is fixed impedance and open disconnector as a capacitance of few pF. They concluded that lengths of disconnector and bushing do not affect the VFT magnitude and transient frequency M.Mhohan Rao [47] et al estimated transient electromagnetic (EM) fields generated during switching operations in a Gas Insulated Substation depend on the wave shape of very fast transient over voltages and very fast transient over currents. The peak magnitudes of VFTC and their dominant frequency content at various locations have been computed in 245kV GIS for different switching operations as well as substation configuration. S.Carsimamovic [48] et al estimated very fast transients due to disconnector operation in a 400Kv gas insulated substation. They mainly discussed breaking of small capacitive currents by disconnector. Transient over voltages are computed and discussed for different switching conditions and points of buses as well as for different points at grounding enclosure. Selim Trabulus [49] et al investigates integration of digital measuring technology in gas insulated substations. They discussed conventional technology and modern technology and intelligent GIS 41 systems. They discussed sensors and actuators used in the GIS systems. They also discussed difficulties with conventional instrument transformers used in the GIS systems. M.Mohan Rao[50] et al estimated transients included on control cables and secondary circuit of instrument transformers in a GIS during switching operations. The effect of the length of control circuit, type of grounding of the cable sheath characteristics of the transient fields, type of secondary circuits and LC loading of the control circuitry on the induced voltages have been analyzed and reported. They concluded the transient voltages appearing at the secondary circuit of the instrument transformers are in the order of instrument transformers are in the order of a few kilovolts, characterized by type of control circuit and are more for the potential transformers than for the C.Ts. the reduction in the induced voltage levels due to the attenuating transient fields is more for the PT secondary circuit than for the CT secondary circuit. Marcin stosur[51] et al estimated very fast transient over voltages at the transformer terminals, resulting from a disconnectro switching operations in a typical GIS substation. They proposed disconnector model as a single spark model, with including many re or pre-strikes has incorporated. N.H.Malik [52] et al carried out experiments to evaluate performance of SF6 Gas under various pressures and with various gas mixtures. The SF6+N2 and SF6+CO2 gas mixtures are subjected under positive 150/1500µs switching impulse applications in non-uniform field 42 electrode systems. The gas mixtures pressure is varies from 1-5bar during the experimentation. Tian Chi [53] et al proposed mathematical model based on 500Kv GIS and 800kv GIS to study the amplitudefrequency of VFTO and its effects on power transformers. The protective effect of shunt resistor of disconnector switch has been verified. They concluded that compared with 550kv GIS, the rated voltage of 800kv is increased by 0.5 times, but relative value of VFTO appears almost same. The insulation can be distorted by the resonant over voltages. Li-Ming Zhou [54] et al estimated fast transients and high frequency in a 15kv distribution cable. They conducted that the attenuation (or) loss in power cables is generally seen as bad attribute, they also concluded that high frequency loss of power cables protects power system components from the detrimental effects of fast surges. A.R.Memari [55] et al discussed mitigation of magnetic field near load carrying conductors of an existing power line. They proposed a new method of estimating magnetic field near high voltage conductor the computed results are compared with the experimental results. C.M.Wiggins [56] et al has experimentally estimated bus current transients, electric and magnetic field transients. The current transients coupled onto control and CT cables produced by switching operations in a115kv ring bus have been measured and characterized. The transients during opening and closing operations of disconnector switches have been observed under normal conditions. Ali F. Imece [57] et al has given 43 modeling guide lines for the digital simulations involving fast front waveforms. They mainly focused on lightning surges on the line conductors near the GIS system. The selection of surge arrester location and rating for protection of transmission lines in the Gas insulated substations were discussed. Smajic [58]et al presented a detailed analysis of very fast transient electromagnetic (VFT) initiated by disconnetcor switching operations in gas insulated substations. They also performed electromagnetic simulations performed on real life GIS geometries along with modeling details are presented. Igor Ivankovic [59] et al describes problems with electromagnetic compatibility (EMC) of the secondary equipment in the 132kv gas insulated substation through measurements and computer simulations were conducted in order to determine magnitudes and frequencies of the transient voltages and currents in the secondary circuits. Ing. M artin Mach [60] et al investigates the magnetic field emission caused by two different types of medium voltage switchgears; because of complexity of the substation geometry they suggested simplifications of the real arrangement. The 3D solution models are obtained. They also discussed some aspects associated with processing models characterized by pressure of incommensurable sub domains and mathematical aspects of solution. W.K.Dialy [61] et al estimated magnetic fields generated by typical distribution substation based on 44 currents in the grounding systems, distribution feeder neutrals, over head ground wires and ground grid loops. They concluded that mainly magnetic fields are significantly influenced by the ground wires their study revealed that circulating equipment caused noticeable distributions in the magnitudes of magnetic fields. Robert G.osen [62] et al described a technique to calculate the coefficients of spherical and finite length cylindrical multiple sources whose positions have been defined by the user. The differences between actual fields and equivalent source fields can be used to determine additional source locations. S.E.Wright [63] et al estimated electric and magnetic fields of switching transients in a 500kv gas insulated substation. Peak vertical electric fields of 16kV/m and horizontal magnetic fields of 212 A/m have been measured near SF6 to air bushing of a Gas Insulated substation. The dominant frequencies of switching transients are observed between 0.5MHz and 120MHz. Zijad Bajramovic [64] et al investigated very fast transient electromagnetic transients (VFT) in air insulted and gas insulated substations caused by switching operation of disconnectros are investigated. Digital simulations of VFT for different models of power net work are performed using EMTP-ATP. The peak values estimated. I.O.Habibalah [65] et al estimated magnetic fields on a typical 230kV substation in Saudi Arabia. The simulation of magnetic fields was done by using SBCALC magnetic field modeling program developed by 45 EPRI environment division running the resulting magnetic field environment in a variety of graphical formats including contour and three dimensional maps. The measured and modeling results were coordinated and showed almost full agreement. The results were reasonably lower than the limits presented by international guidelines. Bojan Trkulja [66] et al calculated electric field based on integral equations approach and suited to solving large problems is presented. The integral equations are solved by both the methods BEM and Galerkin. They compared the numerical results with measured fields, the comparison shows good agreement. They mainly concentrated on computation of low-frequency quasi-static electric fields. Antonio F. Otero [67] et al describes the simulation of the magnetic field generated by electrical lines through a simple model accurately predicts the measured values. FFT analysis of the magnetic frequency and amplitude of the possible induced currents. B.Vancia [68] et al describes the electric field calculations at the line end of 275kV substation. They observed that the fields can be high enough to cause damage to insulators due to corona discharge; they suggested grading devices need to be used to reduce the electric field to acceptable levels. Charles L. Wagner [69] et al investigated insulation coordination for gas insulated substations. They describe an analysis made to determine the BIL ratings and protective distances for the gas insulated equipment in a insulated substation at various system levels 46 and lightning arrester ratings. They developed analysis to select required. BIL ratings for either conventional (or) gas insulated lighting arresters located at the terminals of the gas insulated substations. Pinches D.S [70] et al describes modeling of GIS systems for computation of VFTOs. Simulations have been performed with the use of the model of a very typical GIS system, based on state of the art GIS modeling. Song fan [71] et al describes three dimensional finite element analysis of GIS disconnector. The distribution of magnetic field intensity and the values of eddy currents are calculated. The FEM models of 100kv GIS disconnector has developed. The distribution of magnetic field intensity of the disconnector and distribution of current density of the disconnector are given. LiLinling [72] et al describes the construction of 800kv gas insulated transmission line (GITL) they also discussed the filling pressure of SF6 gas is 10psi (gauge reading) at 1000meters altitude. The same amount of SF6 at 2500m will result in 12.09 PSI on the gauge reading. They suggested 12.09 PSI on the gauge reading. They suggested that the filling pressure should not exceed 0.48kpa to 0.58Mpa on gauge reading. Miroslav Krepela [73] et al describes the transient phenomena originating from switching of 400kv SF6 circuit breaker. They analyzed the unsymmetrical phase inrush currents during a circuit breaker switching and over voltages provoked by current chopping and reigniting of electrical arc are analyzed. 47 M.Gamlin [74] et al presents recent experience regarding reliability of GIS/GIL. They described the high voltage test systems with their advantages and limitations and the applicable partial discharge measuring methods. The onsite testing of a GIS terminated by a SF6 air bushing. S.Huigang [75] et al desrcribes a method and device for suppressing vacuum switch re-striking voltage. They proposed a magnetic ring string provided around the conductor and a resistor is coupled to the conductor which can limit the over voltage both in steepness and amplitude, and it is simple in structure and reliable in its own insulation. Anastasia S. Safigianni [76] et al investigates the electric and magnetic fields values in the area of indoor gas insulated substation 100MVA, 150/20kV in xanthi, Greece. They have used isotropic magnetic-field probe and the measurement ranges 5nT to 10nT and 0.1V/m to 100kV/m. the measured magnetic and electric field values are very small in the supervision room, they are slightly higher values at SF6 to air bushing termination. Marjan Popov [77] et al estimated very fast transient over voltages by both measurements and simulations in layer type distribution transformer. The modeling of the transformer and computations are verified by measurements. They suggested observing transients with a longer period of time, the influence of frequency dependent core losses, the influence of frequency dependent core losses must be taken into account. 48 P.S.Nickel [78] et al described a time domain model for predicting transient bus currents, electromagnetic fields, and cables coupling effects caused by switching actions in high voltage substations. They estimated EM field data at both normal and abnormal conditions. Hu Qin [79] et al described optimized charge simulation method to calculate condition surface electric field of 800kV. Surface electric field is calculated when the charge is in the optimal position, the distribution of the surface electric field and its maximal value calculated accurately. The charge simulation method advantages are discussed. Garry H.Rodrigue [80] et al describes quantitatively how the wavelet transform can be effective mathematical tool for the analysis of transient signals. They have used various types of wavelet functions to analyze electro cardiogram signals. J.Ozawa [81] et al describes transient phenomena in power systems due to switching operation faults. The transient voltage waveforms are analyzed using fast transient voltage waveforms and critical frequencies are identified. Suppression of fast transient over voltages during DS switching is discussed. Soo-Hwan Cho [82] et al describes a time-frequency analysis of power quality disturbances using winder wavelet transform. The various PQ disturbances including voltage swells, voltage sag, harmonics, inter harmonics, transients with multiple high frequencies and voltage fluctuations will be thoroughly investigated by using this new timefrequency analysis method. 49 J.Amarnath [83] et al estimated VFTO levels using PSPICE models. Equivalent circuits were developed for 245kV GIS system, various lengths of GIS sections. The maximum level of VFTO observed is 2.72p.u. The VFTO levels are estimated using fixed arc resistance and variable arc resistance. Transient’s suppression is verified with parallel resistance across the Disconnectors. Gayan Wije weera [84] et al describes a new type of electric field sensor that has been fabricated using micro machine technology. The sensor requires minimal operating power with the shutter being driven by a 75mV drive signal while consuming only 70µW. The sensor has a linear response to the electric field amplitude. Ying Wang [85] et al describes operation of GIS disconnectors can leave a DC voltage on the switchgear which can cause charging of spacer surfaces. They explained about probability of surface flashover when disconnector is closed. They concluded that because of trapped charge left on electrode causes surface charge distribution across the spacer. The failures in some 550kv disconnector switches were discussed. RUAN quanrong [86] et al describes the opening and closing resistor method to suppress VFT generated during disconnector operation. They have data analysis to 28 different connection modes using EMTP program. Data shows that open /close resistance is larger than 200Ω, the amplitude of VFT is reduced by 15%. 50 A. Sabot [87] et al describes the insulation coordination of GIS. They conducted that the insulation coordination practice mainly dealing with fast over voltages. They presented on site test procedures related to the insulation coordination. The dielectric diagnostic techniques are also discussed. J.M.Garablenkow [88] et al conducted tests on the subject of capacitive switching currents by disconnector switches in gas insulated substations with various test objects and arrangements. They also described the influence of various test parameters such as voltage, gas pressure and distributed capacitances etc. Vinodh kumar .V [89] et al estimated very fast transient over voltages in a 520kV gas insulated substations using EMTP software. They observed variation of VFTO peaks at various nodes of the GIS bus in the case of disconnector operation rather than circuit breaker operation. It is also noticed that the variation of VFTO peak levels are not in direct proportion to the trapped charge present on the high voltage bus. Sakai.K [90] et al discussed extremely low frequency (ELF) magnetic field environment in a 500kV/275kV Gas Insulated Substation. They also investigated magnetic field distribution around the 3-phase GIS. From the results they characterize the distinct features of magnetic field distribution in 500kV/275kV Gas insulated substation by comparing with another type of substation. 51 M.MohanRao [91] et al described a numerical characterization of the transient electromagnetic field generated in a gas insulated substation during operation of a disconnector switch. The frequency spectrums of various EM field emissions are characterized. Finally, the transient EM field emission levels from gas to air bushing due to VFTC are established. V.S.Rashkes [92] et al estimated VFTO levels during disconnector operations in a open air substations .they observed that highest spark over voltage observed across the contacts of the breaker. The calculations have showed that 787 and 525kv substations with branched buses very high frequency over voltages (VHFOV) could result in flashovers on a bus open end with un favorable ratio of bus lengths. For transformer insulation protected with an arrester VHFOV are not dangerous .some protective measures are recommended. Hiroshi Koyama [93] et al discussed a correlation between the ultra-high-frequency (UHF) signal (mV) and apparent charge (9pc) for onsite calibration regarding partial discharge (PD). The sensitivity line of 3-phase gas insulated switchgear (GIS) is compared to that of single phase GIS and differences in defects are also discussed. Eduardo ZABALA [94] et al explained an over vie of wavelet transforms applications in power systems. Mainly they have analyzed transient waveforms other than transform approach. They also discussed multi 52 wavelet and second generation wavelets to improve the actual and future applications. Hongsheng li [95] et al estimated very fast transient over voltages caused by disconnecting switch operation using ATP-EMTP program. The various protection measures including metal oxide arrester, R-C absorbers, opening and closing resistors and applications of ferrite rings have been discussed Shun-Li Lu .[96] et al describes a new method of measuring power frequency magnetic fields due to distorted sinusoidal currents in power system. In the field actual test results are accomplished by a standard area-type measurement set up to identity and characterize magnetic fields in a 69kV SF6 GIS substation. M.R.Iravani [97] et al submitted a report on modeling guide lines for the investigation of fast transients, and also proposed new method of digital-computer time domain simulation methods. They proposed sample test systems and typical time-domain simulation results. Hussain H [98] et al presented measurement results of power frequency magnetic fields on 275kV GIS substation in Malaysia. The measurements cover the magnetic fields at important locations in a substation. The results are presented in various formats. Statistical representation of measured data also presented. The results from the measurements will be used for future simulations and for comparison purpose. C.M.Wiggins[99] et al estimated electromagnetic interference levels on sensitive electronic equipment are quantified experimentally. They 53 also reviewed measuring techniques for interference voltages, currents and electric and magnetic fields. The nominal maximum field and control wire interference levels expected in the switchyard are estimated using high frequency transient coupling models. Farag A.S [100] et al proposed methodology to evaluate the magnetic field in a gas insulated substation. Proposals for magnetic field measurements wee given relations between the fields and various design factors are studied in order to optimize substation parameters to reduce the magnetic fields. Qingmin Li [101] et al describe high frequency magnetic coils used in a Gas Insulated substations based on magnetic spectrum of ferromagnetic materials different magnetic materials are used to suppress the VFTO levels at gas insulated substations. A.Ardito [102] et al carried out digital simulations of the overall substation behavior during electromagnetic transients. A design and modeling of GIS bushings against the very fast transient over voltages have been made in this work. The initial partial discharges in the bushing have been discussed. LU Tiebing [103] et al estimated radiated magnetic field from the junction between GIS enclosure and high voltage cable. The estimated results are compared with the results obtained from the software TEMFGIS. They concluded that the frequency of over voltages generated by closing operation of 125kV disconnector switch is 250MHz. The generated fields are strongly depending up on the location of switches. 54 Huijuan Zhang [104] et al have analyzed the electromagnetic transients when switching the no load bus in the 500kV substation by the ATP software the results are compared with actual results. They concluded that simulation model has a better accuracy and it is proved that electromagnetic transient simulation is reliable and effective. D.E.Thomas [105] et al describes switching transients EMI response measurements on several types of substation cables and internal cable wires. The measures and predictable voltage transients in a gas insulated substation and air insulated substations are presented. Model predictions are compared to and validated against measured wire transients. Amara Graps [106] is introduced wavelets in the digital signal processing field. She describes the basics of wavelets beginning with Fourier, compares wavelet transforms with Fourier Transforms, properties and other important aspects of wavelets. Also, the applications of wavelets like image processing, musical tones, and de-noising of noisy data have been used. The basic concept behind wavelets is to analyze the signal according to scale. Wavelets are functions that satisfy certain mathematical requirements and are used in representing data or other functions. The author described wavelet overview, historical perspective, basis of functioning of wavelet, different Fourier transforms like Fast Fourier transforms, and Discrete Fourier transforms. Windowed Fourier transformers. Further, she also compared the Fourier transforms with 55 Wavelet transforms. transforms and She their also discussed applications. about Finally she different wavelet concluded with advantages of wavelet over Fourier transforms. In recent years, researchers in applied mathematics and signal processing have developed powerful wavelet techniques for the multi-scale representation and analysis of signals. The main wavelets in use are Daubechies, Graps, Morlet, Kaiser, Lee and Yamamoto, Mallet, Resinkoff and Burrus, Rioni and Vetterli, Mexican, Gabor, etc. These new methods differ from the traditional Fourier techniques. Wavelets localize the information in the time-frequency plane; in particular, they are capable of trading one type of resolution for another, which makes them especially suitable for the analysis of non stationary signals. Chien-Hsing Lee et al. [107] provides lot of literature survey of recent wavelet developments in power engineering applications. This survey includes detection, localization, identification, classification, compression, and storage and network system analysis of power disturbance signals. In each case, they proved them with some general information and brief explanation. The authors explained about wavelet properties in the context of power engineering applications like decomposition and reconstruction of a signal, timefrequency localization of signals using different wavelets. The Morlet or Daubechies wavelet has the best time-frequency localization and is confined with the Heisenberg uncertainty principle. 56 Rosa M de Castro Fernandez et al. [108] presented a descriptive overview of wavelet transform application in power systems. The main publications carried out in this field have been analyzed and classified by choosing those that are more representative of certain feature, related to their contribution or continuity of a line of investigation. J.P.Antoine [109] reviewed the general properties of the wavelet transform both in its continuous and discrete versions in one or two dimensions and some of the application in signal and image processing. It is a fact that most real life signals are non-stationary. They often contain transient components, sometimes very significant, physically, and mostly cover a wide range of frequencies. Karen L.Butler-Purry et al. [110] and. The analyzed data was obtained from simulations and experiments. Time frequency analysis was performed using Discrete Wavelet Transform (DWT). From the timedomain results, it is observed that distinct spikes are conveyed in the high frequency bands during incipient activity. El Sayed M. and Tag Eldin [111] used a new approach for classifying transient phenomena in power transformer. Discrimination between internal faults, external faults with current transformer saturation and magnetizing inrush current is achieved by wavelet transforms. The wavelet transform is applied for the analysis of the power transformer transient phenomena because of its ability to extract information from the transient signals in both time and frequency 57 domain. The authors used a new algorithm for Wavelet transforms for extracting different features of the transient voltages. Fast electromagnetic transients are typically non-periodic signals, which contain both high-frequency oscillations and localized impulses superimposed on the power frequency and its harmonics. A.P.S. Meliopoulos et al. [112] used the transient analyzers via wavelet method of dynamical systems. This method consists of the traditional frequency domain analysis to capture the steady state operation of the system and a wavelet based transient analysis, which captures the disturbances. The authors have named this method Wavelet-based Transient Analysis (WBTA). The authors implemented Daubechies wavelets. The results obtained using this method are compared and verified with a numerical time-domain analysis method. In the signal and image processing community there is chance of having noise, or more generally, an unknown error in the actual signal. Sylvain Durand and Jacques Froment [113] proposed a model to reconstruct wavelet coefficients using total variation minimization algorithm. The authors focused on two promising approaches, which are Wavelet thresholding and total variation minimization. The approach is motivated by wavelet signal de-noising methods where thresh holding small wavelet coefficients are available. Wavelet de-noising consists of decomposing the noisy data into an orthogonal wavelet, superimposing the wavelet coefficients smaller than given amplitude, using a so-called 58 soft or broad thresh holding, and transforming the data back into the original domain. Tertulien Ndjountche et al. [114] used the technique for noise reduction and is based on the Hidden Markov Tree (HMT) structure, which can efficiently model the statistical characteristics of practical signals. Wavelet transform can localize the signal information in the time-frequency plane with different resolutions. This property has been found to be useful in noise reduction. D.T.Nguyen and J.A.Hoang [115] used wavelet transform to detect the disturbances on electricity supply. The work carried out by these authors is a demonstration of diversity of types of disturbances on electricity supply and consequently the complexity of the digital signalprocessing task required in order to analyze and to identify the disturbances. The authors propose use of FFT for the separation of the power supply frequency and its harmonics before resorting to the wavelet of the analysis for the transient disturbances. Transient disturbance is carefully isolated from the rest of the signal and is detected using wavelet transform. Features such as onset time, duration and dominant frequencies of a disturbance can be accurately and efficiently extracted using this wavelet transform technique for disturbance identification. D.C. Robertson et al. [116] employed wavelet transform method for analyzing electromagnetic transients associated with power system faults and switching. This method is very effective for the non-periodic, wide- 59 band signals associated with electromagnetic transients for analyzing the source of transients. Summary: The detailed literature survey has carried out on VFTOs and its effects. Many authors described that very fast transient over voltages depends up on arc resistance, effect of trapped charge and circuit configuration and voltage ratings etc. few authors have considered it as a fixed arc resistance most of the authors considered as a variable arc resistance. Ivo uglesic et al described the problems of electromagnetic compatibility of secondary equipment in GIS systems . they also recommended precautionary methods . Yanabu S et al has experimentally estimated fast transient over voltages in GIS, but they obtained VFTO of 2.7pu at the ope end of the bus bars. Amir Mansour et al presented VFTO propagation inside the GIS. Ozawai et al describes the method of suppress of transient over voltages by inserting resistance during switching operation. Toheri nitta et al describes that ground capacitance has significant effect on propagation of trvelling waves. Vinodh kumarr et al describes the the VFTO computations on 420kV GIS system. In the earlier literature suppression of VFTO at origin is not discussed and also suppression of high frequency components in VFTO and VFTC have not discussed. The use of time frequency analysis is also not discussed in detail. 60 ORGANISATION OF THESIS CHAPTER-I Introduction to Gas Insulated Substations, advantages of GIS over the conventional open air substations, disadvantages of GIS have been presented. The principle of VFTO generation, secondary breakdown phenomena and prestrike, trapped charge effect and current chopping in GIS are discussed. The very fast transient phenomena in GIS, suppression techniques, transient electromagnetic phenomena in GIS have been discussed. The Literature survey on Very fast transient over voltages and measurements, Transient electric and magnetic fields in GIS systems and Wavelet applications for transient analysis have been discussed. CHAPTER-II The statement of the problem, main contribution of the thesis and brief organization of the thesis have been discussed. CHAPTER-III Modeling of GIS components, the EMTP modeling concepts have been presented. The calculation of parameters and equivalent circuits of GIS components, modeling of arc are presented. VFTOs are computed for fixed arc resistance and variable arc resistance conditions. The VFTO computations have been made with and without trapped charge and the results are presented. The Fast Fourier Transform (FFT) technique using MATLAB 7.1(Signal Processing Tool Box) has been used in order to 61 identify the dominant frequencies of the transient voltages/currents. The frequency spectrums have been calculated for the finite time duration of 5µsec. The various VFTO suppression techniques have been discussed. First case the suppression effect of VFTOs is verified with resistance switching. Next case, the suppression effect of VFTOs is verified by proposed technique of application of high frequency ferrite rings. Modeling concepts of ferrite rings has been discussed. The VFTOs are computed with and without ferrite rings. The frequency spectrums of all the cases were obtained. The results of both the techniques have been compared and discussed in this chapter. CHAPTER-IV A series of experiments have been conducted on 1-Phase, SF6, 3.3kV GIS system with disconnector arrangement. The VFTOs are captured by specially designed high frequency capacitive surge sensor. To know the effect of trapped charge on VFTO, a voltage of 4.7kV (D.C) is applied to floating electrode in steps of 10%. The VFTOs are captured recorded through Digital Storage Oscilloscope of 250 MHz, 1GS/s with FFT. The data is recorded through Digital storage oscilloscope (DSO) of 250MHz; 1GS/s with FFT function then it is transferred to computer system through RS-232 serial communication port provided. The VFTOs are captured during both opening and closing operations of the disconnector switch. Proposed method of suppressing VFTOs is verified experimentally. The corresponding frequency spectrums are also obtained for all the cases. The suppression effect of VFTOs by both resistance switching and ferrite application methods are compared and results are analyzed. 62 CHAPTER-V The fast transient electromagnetic fields (FTEMF) in GIS systems are computed. The FTEM fields at four important locations were computed by using ELECNET & OPERA field computational soft ware’s. The EM field measurements are carried out at 245kV GIS substation along with ABB, India as a part of GIS (SCADA) automation project, and the corresponding results are presented. The results obtained from EM field computations are compared with the measured data. The final conclusions are presented in this chapter. CHAPTER -VI The VFTCs generated during Disconnector Switching in a 245kV are analyzed using wavelet transforms. The time-frequency spectrums of VFTCs at two important locations are obtained. The variations of current magnitude with time for different frequencies associated with the VFTC are calculated. The results are discussed. CHAPTER-VII In this chapter conclusions and scope for future work have been presented. SUMMARY: In this chapter the statement of the problem and main objectives of the thesis have been discussed. The brief outline on the thesis organization has been explained.