150212_NTTG_Update

advertisement
-TEPPC Update NTTG Implementation of
FERC Order 1000 Regional Planning
WECC Offices
Salt Lake City, Utah
February 11-12, 2015
Regional Planning Orders
Date
FERC Issues
July, 2011 Order No. 1000
First 1st Order on NTTG's Oct.
May, 2013
2012 Commpliance Filing
FERC's 2nd Order on NTTG's
April, 2014
Sept. 2013 Compliance Filing
Dec. 8,
FERC's 3rd Order on NTTG's
2014
June 2014 Compliance Filing
NTTG Responds
October, 2012
Compliance
Filing
1
September, 2013
2
June, 2014
3
December, 2014
4
The trigger for NTTG to start implementing
FERC Order 1000 Regional Transmission
Planning.
2
Biennial Planning Cycle
Order 1000 Action
Q8 Prior Cycle Pre-Qualification Project Sponsors for Cost Allocation
Q1
Data Gathering and Project Submittal
Q2
Development of the Biennial Study Plan
Q3-4
Q7
Preparation of the Draft Regional Transmission Plan
Stakeholder Review and Comment on Draft Regional
Transmisison Plan and Update to Q1 Data and
Submission of New Unsponsored Projects
Update Biennial Study Plan; Cost Allocation Scenario
Anslysis; and Draft Final Regional Transmission Plan
Draft Final Regional Transmisson Plan Review
Q8
Regional Transmission Plan Approved
Today
Q5
Q6
3
Data Collection
4
Sponsored Project Requesting
Regional Cost Allocation
One Project Received
• Sponsor: Great Basin
Transmission (LS Power)
• Project: SWIP-North
• Sponsor was Pre-Qualified for
Regional Cost Allocation
• Regional Cost Allocation
applies if project is selected in
NTTG’s Final Regional
Transmission Plan
SWIP
North
5
Transmission Projects
Sponsor
Type
Non-Committed
Projects
LTP
Gateway West Project
LTP
B2H Project
Voltage
Circuits
500 kV
2
500 kV – 230 kV
2
500 kV
1
500 kV
1
230 kV
1
Idaho Power
Great Basin
Transmission
Sponsored (1)
LTP
NorthWestern Energy
LTP
Southwest Intertie
Project North
Broadview – Garrison
Upgrade
Millcreek – Amps
Upgrade
LTP
Gateway South Project
500 kV
1
LTP
Gateway West Project
500 kV – 230 kV
5
LTP
Blue Lake - Gresham
230 kV
1
+600 kV DC
1
PacifiCorp East
Portland General
TransWest Express
(1)
(2)
Merchant Transmission
TransWest Express
Developer (2)
Sponsored Projects and Unsponsored Projects identified by the Planning Committee will be evaluated through the use of
Change Cases.
Per customer request, the TransWest Express (Merchant) project will not be evaluated this planning cycle as an Alternative
Project for selection in the Regional Transmission Plan.
6
Public Policy Request
One Request Received
• Sponsor: Renewable Northwest Project
• Request: Public Policy Consideration
–
–
–
–
–
Retire 610 MW Colstrip Units 1&2 Units in MT
Replace with 610 MW wind as two 305 MW wind farms
New wind to be modeled at Broadview Sub, MT
Change occurs in 2020
No new transmission lines
• Study to be completed in Q6
• Study results informational
7
Technical Analysis
8
Draft Regional Transmission
Plan Evaluation
• Goal is to identify the most efficient or cost effective
Regional Transmission Plan
• Analysis
– Stressed hours selection (production cost model)
– Reliability analysis (power flow model)
– Metric analysis for benefit determination
• Analysis performed on
– Initial Regional Transmission Plan
• “Roll up” of the Transmission Providers transmission plans
– Change Cases without non-Committed projects
– Change Cases with addition of Alternative Projects and
without non-Committed project
9
Draft Regional Plan Analysis
• No significant reliability problems were identified
– N-0 (steady-state), N-1 (single-contingency), N-2 (credible
double-contingency)
• Voltage/thermal issues evaluated and resolved
• Change Cases evaluated non-Committed projects
– Boardman to Hemmingway (B2H), Energy Gateway (EG), SWIP
North
• One unsponsored non-Committed project was defined
as a result of the quarter 3-4 analysis
10
Metric Analysis
11
Metric: Change in Energy
Losses
•
•
This metric captures a transmission plans’ change in
energy losses
NTTG incremental energy loss computed for the 5
cases studied
–
–
Computed: loss without the non-Committed project less the
loss with the non-Committed transmission project
Benefit = reduction in losses
•
Average the 5 case results, annualize the data and
multiply by nodal energy price
•
•
Result = monetized annual benefit
Power flow analysis
12
Metric: Change in Reserve
• Identifies potential benefit of new transmission to lower
the reserve capacity costs of two or more entities
assuming:
– Incremental load and generation
additions for the 10 year planning
period
– Generation capacity based on a
simple cycle Frame F ($800/kW)
– Reserve event energy costs based
on the TEPPC 2024 case zonal
gas prices
• Four transmission
upgrades examined
–
–
–
–
Gateway (West & South)
SWIP North
Boardman to Hemmingway
Montana to NW Upgrade
Bozeman
Montana-NW
Portland
Gateway W
Wyoming
Boise
B2H
enabled by
Gateway W
Gateway S
SWIP
Salt
Lake
Desert
Southwest
13
Metric: Capital Cost
• TEPPC Transmission Capital Cost tool
– Validate project capital cost if submitted by project sponsor
– Develop capital cost estimate if not submitted
• TEPPC annual capital related cost model
– Develop the annual capital-related costs over 40 years
• Developed incremental costs as the sum of:
–
–
–
–
Levelized annual capital-related costs
Monetized annual energy losses
Monetized annual reserves
Effects on neighboring regions (mitigated internal to NTTG)
14
Incremental Cost
Comparison 2014 M$
Case Configuration
B2H=Boardman-Hemmingway
EG=Energy Gateway
Annual
Capital
Related
Costs
Positive = Benefit
Incremental
Cost*
NTTG
Losses
Reserve
$484.95
$0.00
$0.00
$484.95
$389.04
$0.36
$0.00
$388.68
IRP+SWIP North
$88.89
$581.63
-$1.94
-$0.22
$0.00
$0.83
$90.83
$581.02
IRP-B2H+SWIP North
$485.73
-$0.20
$0.83
$485.10
IRP-B2H-EG+SWIP North
$96.68
-$0.44
$0.83
$96.29
Initial Regional
Transmission Plan (IRTP)
IRTP-B2H
IRTP-B2H-EG+Alt Project**
* Incremental Cost = Levelized Annual Capital Related Cost – NTTG Loss Benefit – Reserve Benefit
** Alternate Project required an unsponsored non-Committed project from Aeolus to Populus to
eliminate reliability problems external to NTTG footprint.
15
Draft Regional Transmission Plan
• Based on the studies performed thus far the Draft
Regional Transmission Plan is:
― Initial Regional Transmission Plan without the non-Committed
projects, and
― Addition of a unsponsored non-Committed project from Aeolus
(southern Wyoming) to Populus (Idaho)
• Lesson Learned
― The Study Plan did not fully account for transmission service
obligations received during the Q1 data submittal period
• Revise the Study Plan in Q5 to address this concern
16
Possible Revision to the Biennial
Study Plan
• Include two threshold requirements
– Plan must be a reliable transmission system
– Plan must meet the transmission needs:
•
•
•
•
•
Loads
Resources
Public Policy Requirements
Transmission service obligation and
Other identified transmission requirements
• Implement the revised Study Plan in Q6 analysis
• Develop the Draft Final Regional Transmission Plan in
Q7
17
NTTG Next Steps
NTTG Q4 Stakeholder Meeting
Salt Lake City
December 18, 2014
Order No. 1000
2015 Near Term Milestones
Stakeholder Comments
Public Updates
and Public Review
• Material Updates to Q1
Data
Process
• Draft Regional
Transmission Plan
• PPC Draft Study Plan
• New Unsponsored
Projects
Q5
Economic Study Request
Window Closes
Submission of Economic Study
Requests
2015: Q5
February 26 (Portland, OR)
Western Regions Planning
Coordination Meeting
12
Late March
(Portland, OR)
Q5 public meeting to discuss
NTTG Regional Order 1000 RTP
and ESR Process
19
Order No. 1000 High Level
Milestones 2015 Q6-Q8
Q6
Updated Biennial Study Plan
Updated with Q5 Stakeholder
Comments, 2014 TWG Lessons
Learned and Updated Q1 data
Q7
• Draft Final Regional Transmission Plan
Review
• Economic Studies Performed
• Q7 Stakeholder Mtg: Bozeman, MT
Q6
Stakeholder Meeting
Late June (Boise, ID)
Q6: 2015
Q6
ESR Study Plan
Study Plan for
Economic Study
Requests to be
modeled
Q6
Cost Allocation
CAC allocates
costs of projects
selected into the
Draft RTP
Q7-Q8: 2015
Q6
Draft Final
Regional
Transmission Plan
Produced
•
•
•
•
12
Q8
NTTG Regional Transmission Plan Approval
Regional Economic Study Results
Q8 Stakeholder Mtg: SLC, UT
NTTG 2016-2017 Project Sponsor PreQualification Process
20
Questions?
21
Download