Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXX Study Performed by El Paso Electric Company System Planning Section January 2001 Short Circuit Analysis with Generation Proposed by XXXXXXXXXXXXXXXXX pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXX (XXXXX) January 2001 Short Circuit Analysis with New Generation Connected to EPE’s Newman 115 kV Bus I. Introduction El Paso Electric Company (EPE) has agreed to perform a Transmission and Facilities Study, for XXXXXXXXXXXXXXXXXXXXXXXXXXXXX (XXXXX), with regard to the construction and interconnection of 500 MW of new generation (two 250 MW generators) at EPE’s Newman 115 kV bus. The powerflow and stability analysis of this study is also being performed by EPE. When generation is added to a system, the available fault current of that system increases. Therefore, a study has been performed to determine if EPE’s existing substation circuit breakers in the substations electrically near the new generation have adequate short circuit interruption duties. II. Short Circuit Study The new generation proposed by XXXXX is sited, as per XXXXX, just south of EPE’s Newman Power Plant. The interconnection to the existing EPE transmission system is EPE’s Newman 115 kV Substation bus through a XXXXX 115 kV Switchyard and four (4) 115 kV circuits of approximately 2500 feet in length consisting of 954 kCmil 45/7 ACSR “Rail”, 2-conductor bundles per phase. The positive sequence impedance of each of these lines is: Z1= 0.00002571 + J0.00023722 per unit (100 MVA base) EPE determined an estimated zero sequence impedance, based on standard construction and spacing, of: Z0 = 0.00022195 + J0.00079049 per unit (100 MVA base) The generators will be connected to the 115 kV transmission system through two (2) 330 MVA, 21/115 kV step-up transformers, with rated short circuit impedances of 15% each at a 330 MVA base. These impedances were modeled in the short circuit analysis as: Z = 0.00090 + J0.04545 per unit (100 MVA base) The new generators is defined as 270 MVA each with the following reactance values on the generator MVA base: Xd = Direct Axis Synchronous Reactance = 1.95 per unit 2 Short Circuit Analysis with Generation Proposed by XXXXXXXXXXXXXXXXXXXX pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXXXXXX (XXXXX) January 2001 X’d = Direct Axis Transient Reactance = 0.200 per unit X’’d = Direct Axis Subtransient Reactance = 0.150 per unit These reactance values were converted to a 100 MVA base and used to model the new generators in the short circuit study. Maximum fault currents were then determined at the Newman 345 kV and the Newman 115 kV buses, and the substations immediately connected to Newman: Arroyo 345 kV Luna 345 kV Butterfield 115 kV Cromo 115 kV Shearman 115 kV Caliente 345 kV AAP 115 kV Chaparral 115 kV Milagro 115 kV Vista 115 kV The resulting fault current was then compared to the circuit breaker interruption ratings of the breakers at each of the above mentioned substations. III. Results of the Short Circuit Analysis The circuit breakers used by EPE at the 345 kV and 115 kV vary between the substations. The following is a list of the existing circuit breakers, along with the interruption rating, at each of the pertinent substations: Substation Newman Newman Breaker Voltage 345 345 345 345 Breaker Number 2448B 6018B 8378B 0538B 115 115 115 115 115 115 115 115 115 11950 11101 15601 N-115-1 11951 11401 N-115-7 11957 N-115-8 Interruption Rating (Amps) 40,000 40,000 40,000 40,000 40,000 50,000 40,000 40,000 40,000 40,000 43,000 43,000 43,000 3 Short Circuit Analysis with Generation Proposed by XXXXXXXXXXXXXXXXXXXX pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXXXXXX (XXXXX) January 2001 Substation Newman Breaker Voltage 115 115 115 115 115 115 115 115 115 115 115 115 115 115 115 Breaker Number N-115-2 11952 11601 N-115-3 11953 15501 N-115-19 11967 N-115-20 N-115-21 11968 N-115-22 N-115-23 11969 N-115-24 Interruption Rating (Amps) 40,000 40,000 50,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 Arroyo 345 345 345 345 345 345 345 2418B 2458B 4348B 3018B 5428B 7548B 2098B 40,000 40,000 40,000 40,000 40,000 40,000 40,000 Caliente 345 345 345 345 345 1828B 3928B 0428B 4178B 4688B 40,000 40,000 50,000 40,000 40,000 Luna 345 345 345 345 345 345 345 345 01982 02182 03082 09682 08582 10682 11782 15082 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 4 Short Circuit Analysis with Generation Proposed by XXXXXXXXXXXXXXXXXXXX pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXXXXXX (XXXXX) January 2001 Breaker Voltage 115 Breaker Number 4806B Butterfield 115 115 115 115 0796B 2236B 5386B 6936B Chaparral 115 Cromo 115 115 115 115 0306B 0596B 0766B 0666B 40,000 40,000 40,000 40,000 Milagro 115 11602 25,000 Shearman 115 115 115 0136B 3126B 2486B 22,000 22,000 22,000 Vista 115 115 115 115 115 115 3656B 0106B 4426B 6256B 5186B 7026B 25,000 40,000 40,000 25,000 25,000 25,000 Substation AAP Interruption Rating (Amps) 40,000 20,000 40,000 31,500 31,500 No Circuit Breakers at this Substation The short circuit analysis was first performed with no new generation. This gave the “base case” fault duties of the circuit breakers. Then the two new generators were modeled and the short circuit study was re-run. The incremental between these two studies gave the impact of the new generators on the existing circuit breakers in the EPE system. The short circuit (fault) currents for each case at all of the possibly impacted substations are: 5 Short Circuit Analysis with Generation Proposed by XXXXXXXXXXXXXXXXXXXX pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXXXXXX (XXXXX) January 2001 Three Phase Line to Ground: Substation Faulted Newman 345 kV Bus Newman 115 kV Bus Arroyo 345 kV Bus Caliente 345 kV Bus Luna 345 kV Bus AAP 115 kV Bus Butterfield 115 kV Bus Chaparral 115 kV Bus Cromo 115 kV Bus Milagro 115 kV Bus Shearman 115 kV Bus Vista 115 kV Bus No XXXXX Generators With 2 XXXXX Generators Fault Current (Amps) Fault Current (Amps) 6,568.9 7,634.5 22,202.8 31,519.1 5,227.2 5,762.6 5,259.7 5,933.7 7,193.6 7,587.1 10,099.7 11,096.1 11,203.5 11,988.8 13,072.1 15,736.5 16,247.4 17,617.9 9,629.6 11,475.9 10,553.6 12,225.6 12,361.7 13,572.9 Single Phase Line to Ground: Substation Faulted Newman 345 kV Bus Newman 115 kV Bus Arroyo 345 kV Bus Caliente 345 kV Bus Luna 345 kV Bus AAP 115 kV Bus Butterfield 115 kV Bus Chaparral 115 kV Bus Cromo 115 kV Bus Milagro 115 kV Bus Shearman 115 kV Bus Vista 115 kV Bus No XXXXX Generators With 2 XXXXX Generators Fault Current (Amps) Fault Current (Amps) 6,884.0 7815.4 26,617.6 37,746.4 4,735.2 5,052.8 5,381.2 5,870.1 6,110.2 6,301.4 7,449.5 7,852.3 8,376.9 8,671.4 10,875.2 12,295.3 15,580.8 16,411.7 7,684.7 8,713.4 7,963.1 8,810.8 11,199.0 11,855.6 Comparing these fault currents to the appropriate existing circuit breaker interruption ratings shows that the interconnection of the new generators at EPE’s Newman 115 kV Substation, in the configuration and parameters as given by XXXXX, will not cause any existing circuit breaker to operate outside its design rating. 6 Short Circuit Analysis with Generation Proposed by XXXXXXXXXXXXXXXXXXXX pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXXXXXX (XXXXX) January 2001 IV. Results and Conclusions A short circuit study was performed on the EPE system comparing the maximum fault current on the system at various substations: Newman Substation (both 345 kV and 115 kV) and each substation directly connected to Newman, both with and without the two new generators proposed by XXXXX. The results of this study show that the maximum fault current with the two new generators is less than the minimum interruption rating of any effected existing circuit breaker: Substation Newman 345 kV Newman 115 kV Arroyo 345 kV Caliente 345 kV Luna 345 kV AAP 115 kV Butterfield 115 kV Cromo 115 kV Milagro 115 kV Shearman 115 kV Vista 115 kV Minimum Circuit Breaker Interruption Rating (Amps) 40,000 40,000 40,000 40,000 40,000 40,000 20,000 40,000 25,000 22,000 25,000 Maximum Fault Current with 2 New Generators (Amps) 7,815.4 37,746.4 5,762.6 5,870.1 7,587.1 11,096.1 11,988.8 17,617.9 11,475.9 12,225.6 13,572.9 Therefore, the operation of the two new generators with the parameters as given by XXXXX connected to EPE’s Newman 115 kV bus will not cause any existing circuit breaker to operate outside its interruption rating limit. 7 Short Circuit Analysis with Generation Proposed by XXXXXXXXXXXXXXXXXXXX pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXXXXXX (XXXXX) January 2001 V. Certification This Short Circuit Analysis was performed pursuant to the Agreement for a Transmission and Facilities Study, dated December 8, 1999 requested by XXXXX. The generator, step-up transformer and new transmission line parameters were supplied by XXXXX. The Short Circuit Analysis was performed by El Paso Electric Company. Name: Dennis H. Malone Title: Supervisor, System Planning Signature: Dennis H. Malone Date: February 8, 2001 8 Short Circuit Analysis with Generation Proposed by XXXXXXXXXXXXXXXXXXXX pursuant to a Transmission and Facilities Study Requested by XXXXXXXXXXXXXXXXXXXXXXXXXX (XXXXX) January 2001