Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa AfDB Market Study Series Statistics Department (ESTA) May 2014 www.afdb.org Table of Contents SUMMARY Summary1 1.Introduction 3 2. 2.1 2.2 2.3 2.4 4 4 4 5 6 Building a Database for the Analysis of Road Costs Establishing the Baseline for a New Database on Road Costs Consolidation of Databases from Previous Studies Addition of Cost Data from Recent AfDB Projects Master Database for Analysis of Unit Rates and Cost Overruns 3. Analytical Approach for Road Infrastructure Costs 3.1 Standardizing the Unit Rate 3.2 Analytical Approach 8 8 8 4.Results 4.1 Establishing the Unit Cost Curve on the Basis of Project Size 4.1.1 Construction/Upgrading of Paved Roads 4.1.2 Rehabilitation of Paved Roads 4.1.3 Periodic Maintenance of Paved Roads 4.1.4 Regraveling of Unpaved Roads 4.1.5 Summary Results 4.2 Other Major Potential Drivers of Unit Rates 4.2.1 Location of Road Projects 4.2.2 Origin of Contractors 4.2.3 Landlocked vs. Seaboard Countries 4.3 Determining Unit Cost Trends 4.3.1 Unit Rates over Time 4.3.2 Cost Overruns/Underruns 4.3.3 Median Rates 10 10 10 10 11 12 12 12 12 14 16 18 18 20 22 5.Conclusions 5.1 Typical Road Unit Costs 5.2 Unit Cost Overruns/Underruns 5.3 Trend in Unit Costs 5.4 General Conclusions 25 25 25 26 26 Appendix A: Detailed Description of Database Parts for AICD Initiative27 Appendix B: Statistical Terms 29 Appendix C: Consolidated Data 30 Mthuli Ncube Chief Economist and Vice President Office of the Chief Economist Charles Leyeka Lufumpa Director Statistics Department Steve Kayizzi Mugerwa Director Development Research Department Victor Murinde Director Africa Development Institute The African Development Bank (AfDB) commissioned a study during 2010/11 to analyze road unit costs and the extent of cost overruns in road infrastructure projects in Africa. The study focused on three main objectives, namely: (i) to determine unit costs for road infrastructure projects in Africa; (ii) to determine the prevalence and extent of cost overruns; and (iii) to determine the evolution of unit costs and cost overruns since the completion of previous studies – specifically the Africa Infrastructure Country Diagnostics (AICD) study and a related study for the AfDB on Road Maintenance and Construction Costs in Africa. This represents the Final Report for the study and presents the findings of the analysis on unit costs and cost overruns of road infrastructure projects in Africa. Research was undertaken during 2007 and 2008, under the auspices of the joint World Bank–AfDB Africa Infrastructure Country Diagnostic (AICD), into baseline unit cost data and the causes of cost overruns, specifically on road Acknowledgements: This report was prepared by a team comprising Maurice Mubila, Chief Statistician, (Statistics Department), Altus Moolman, Consultant, (Statistics Department) and Willem Van Zyl, Consultant (Statistics Department) under the supervision of Beejaye Kokil, Manager, Economic and Social Statistics Division, and the direction of Charles Leyeke Lufumpa, Director Statistics Department. A f r i c a n projects. The research resulted in the compilation of databases on road projects in Africa, which were used as the point of departure for the current study. The databases were consolidated into a new structure, and a total of 26 new AfDB projects (with Project Completion Reports (PCRs) dated 2004 or later) were added to the database. The final database consisted of a total of 172 projects. The consolidated structure divided projects into four categories, based on the type of work that was undertaken, as follows: 1. Regraveling or periodic maintenance of unpaved roads: This involves reinstating the surface layer of gravel roads; 2. Periodic maintenance of paved roads: This involves the repair of minor surface defects and a seal or thin overlay, but without structural improvements or geometric upgrades; 3. Rehabilitation of paved roads: This typically entails the reinstatement of roads to This report was prepared by the Statistics Department in the Chief Economist Vice Presidency of the African Development Bank. Its findings reflect the opinions of the authors and not necessarily those of the African Development Bank, its Board of Directors, or the countries that they represent. Designations employed in this article do not imply the expression of any opinion on the part of the D e v e l o p m e n t B a n k African Development Bank Group concerning the legal status of any country or territory, or the delimitation of its frontiers. While every effort has been made to present reliable information, the African Development Bank accepts no responsibility whatsoever for any consequences of its use. Layout and production by ­ Phoenix Design Aid A/S, Denmark Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 the original design standard, including structural repairs; and 4. Construction and upgrading of paved roads: This typically entails the upgrading of gravel roads to paved standard, or the addition of lanes to existing paved roads. Analysis was performed on the projects in the database. The sequence of enquiry followed three steps, namely (i) establishing the position of the unit cost curve, (ii) verifying whether rates that lie off the curve can be explained, and (iii) determining whether the position of the curve is as expected (overruns) and whether it is shifting over time (unit cost trends). What this review has brought to the fore is that there is no such thing as a “typical” unit cost. This is because (i) unit costs are calculated by standardizing projects that are broadly similar but which differ in their design details and specific circumstances; and (ii) the size of the project invariably has an overriding effect on the unit rate (economy of scale). The first issue is largely overcome by excluding major project and location-specific factors (e.g. bridges, taxes). The second issue is something that anyone estimating or evaluating roads costs should be vigilant about. The table below provides a summary of the unit cost findings. It should be noted that the unit rates are all expressed per lane kilometer, i.e. a 50 km two-lane (single carriageway) road would have 100 lane km. The analysis of unit cost overruns shows that (i) there appears to be a correlation between the over/underrun and the size of the project and (ii) the estimation error (i.e. PCR value minus Project Appraisal Report (or PAR) value) is likely to be an underestimate (48 percent) rather than an overestimate (-15 percent). A typical observation is that the smaller the project, the larger the difference between the expected unit rate (PAR value) and the PCR value. The implication is that unit rates for small projects should be treated with some caution, although care should be taken not to spend more resources on refining designs, feasibility studies, and other work underlying PARs than the benefit that could be expected. In the case of the rehabilitation of paved roads, the difference occurs both above (overrun) and below (underrun) the PAR value. In the case of construction or upgrading of paved roads, it appears that the pattern is for small projects to overrun, AfDB rather than underrun. This may point to PARs being overly optimistic. The finding with respect to an increase in unit cost over time is inconclusive. This may be purely because of data constraints, i.e. a limited sample size for a specific year and standardization issues across projects in the same class. The effect is that statistically extrapolated unit cost curves (rather than rates) are compared. Given these shortcomings, comparing the cost curves of those years for which such curves can indeed be constructed, shows that unit costs for large projects (>100 lane km) have not increased during the last decade. It might even be inferred that they have reduced, although this is counterintuitive, given the field experience of AfDB task managers, which points to increasing unit rates. The main conclusion from this study is that while lenders and national road agencies will clearly benefit from having a better understanding of unit costs and related issues, a more permanent road unit cost database should be established (possibly under the AICD initiative), which can then be analyzed on a systematic basis. Summary of Unit Rate Statistics for Different Types of Road Infrastructure Investment (USD/lane km, rounded to ’00) Type of Road Infrastructure Investment Regraveling/ Periodic Maintenance of Unpaved Roads Periodic Maintenance of Paved Roads Rehabilitation of Paved Roads Construction and Upgrading of Paved Roads < 100 lane km Quartile 3 10,500 N/A 290,000 425,400 Median 9,600 N/A 180,300 227,800 Quartile 1 8,100 N/A 109,800 166,300 Quartile 3 12,800 72,200 130,500 162,000 Median 11,300 64,600 84,400 147,100 9,600 56,900 47,400 115,900 ≥ 100 lane km Quartile 1 Note: All values are given in 2006 USD. 2 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex 1.Introduction The African Development Bank (AfDB) and other development agencies are concerned about significant cost escalations of road projects under implementation. This is particularly important, given the AfDB’s firm commitment to scale up its support to infrastructure development, as an operational priority of its Ten Year Strategy 20132022. Investing in infrastructure is a prime way to boost economic growth, improve the social wellbeing of populations, and promote regional integration. However, excessive cost overrruns result in increased funding needs and act as a constraint to development; therefore a mechanism is needed to address this issue. The imperative to scale up infrastructure and improve the competitiveness of African economies is being constrained by limited data availability. Indeed, there is a scarcity of information regarding the costs of implementing road infrastructure projects in Africa, although significant data on the unit cost of projects exist, both in government records and those of development agencies in the region. There is therefore a need to systematically review and analyze these sources, to improve the generation of statistical data on the unit costs of various types of road infrastructure investments. Studies conducted about four years ago observed that cost overruns in road infrastructure projects had become increasingly common. The average cost overrun was 35 percent, but in a third of the cases it could be as high as 50 to 100 percent. The assumption has been that the increases are due to a variety of factors, including lack of competition in the bidding process, increases in fuel and bituminous product prices locally and internationally, technology used in road works, contract management practices, and the availability and quality of road construction materials. The African Development Bank commissioned a study during 2010/11 to analyze road unit costs and the extent of cost overruns in road infrastructure projects in Africa. The study focused on three main objectives, namely: (i) to determine road unit costs for road infrastructure projects in Africa; (ii) to determine the occurrence and extent of cost overruns; and (iii) to determine the evolution of unit costs and cost overruns since the time of completion of previous studies (specifically the Africa Infrastructure Country Diagnostics (AICD) study and a related study for the AfDB on Roads Maintenance and Construction Costs in Africa). The current study represents the Final Report and presents the findings of the analysis on unit costs and cost overruns of road infrastructure projects in Africa. A four-step methodology was followed for the study: (i) first, the project databases from the previous studies were consolidated; (ii) new projects were then selected from the AfDB database, for comparison with the previous studies; (iii) data were extracted for each of the selected projects and added to the consolidated database; and (iv) analysis was performed to determine unit rates and cost overruns. This report contains four sections, including this introduction. Section 2 describes the development of a consolidated database of old (i.e. from previous studies) and newly selected projects, which were used for the analysis of unit rates. Section 3 provides an analysis of unit rates and cost overruns for all projects captured in the consolidated database. Section 4 summarizes the main findings of the report. 3 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 AfDB 2. Building a Database for the Analysis of Road Costs Significant data on the unit cost of projects exist in the records of governments and donor agencies in the region. Under the auspices of the joint World Bank–AfDB initiative of the Africa Infrastructure Country Diagnostic (AICD), research was undertaken during 2007 and 2008 into unit cost data. This then served as a baseline against which future improvements in infrastructure services could be measured. The research also analyzed the causes of cost overruns, specifically on road projects. The research resulted in the compilation of databases on road projects in Africa, containing cost data and allowing categorization of the type of work conducted. These databases were used as the point of departure for the current study. 2.1 Establishing the Baseline for a New Database on Road Costs Africon Limited completed a study on unit costs during 2008 as part of the joint World Bank–African Development Bank AICD Initiative. The main aim of the study, which focused on 24 countries in Sub-Saharan Africa, was to provide a set of baseline unit cost data against which future infrastructure improvements could be measured. This was expected to provide a more solid and empirical foundation for prioritizing investments and designing policy reforms in the infrastructure sectors in Africa. As part of this study, a database of infrastructure projects in Africa was compiled, covering roads, water, sanitation, and electricity. The database was populated from Project Completion Reports (PCRs), contractual documents from donor agencies participating in the study, and publicly available data from governments. For roads, the database covered 115 projects. variables; summary impacts on tender price; and classification. The database consisted of two parts, namely: (i) a general section common to all projects, which captured the major exogenous variables; and (ii) an infrastructure-specific section, adapted for each sector (e.g. roads, water, and electricity) and for different infrastructures and technologies within each sector. A detailed description of these parts is presented in Appendix A. Since the purpose of the 2007 AfDB study was to investigate cost overruns and not unit costs, it was not a requirement to enter these project details into a general database. Rather, the focus was on analyzing these projects on an individual basis. In 2007, Africon Limited was appointed to carry out an addendum to the AICD assignment which was then underway. The topic of the addendum generally related to the main unit cost study, i.e. an investigation into the causes of recent cost overruns, specifically on road projects. Whereas the main AICD study sought to determine the final cost of projects that had already been completed, the Addendum examined the reasons for cost changes in ongoing projects, relative to the original engineer’s estimates. The purpose of the Addendum was not to analyze and improve the project appraisal and procurement cycle per se, but rather to identify and mitigate the causes of the recent wave of cost overruns (i.e. during the time of the AICD study). 2.2 Consolidation of Databases from Previous Studies The databases developed for the AICD study (2008) and the Addendum to AICD (2007), differed slightly in terms of their structure and the data captured. This was owing to the divergent objectives of each study. There was a need to consolidate these databases into one structure, taking due account of the specific objectives of this report. The consolidated structure consisted of nine major data fields, as listed below: A total of 24 AfDB projects were selected for the purposes of the study. Project details were obtained on the following: brief project description; timeframe (listing milestones such as Specific Procurement Notices (SPNs) issued, pre-qualification, tender issued, tender received, tender evaluation approved, contract signed); key project events; procurement; project component increases; changes in explanatory 4 A f r i c a n D e v e l o p m e n t B a n k 1. Project information (general information describing the project and its location); 2. Procurement information (e.g. International Competitive Bidding (ICB) or National Competitive Bidding (NCB)); 3. Number of bidders, plus the name and nationality of the winning bidder 4. Project dates (dates for approval and signing of loan, signing of contract, expected and actual contract completion dates); 5. Type of project (road type and surface type); AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa 6. Activity (category describing the type of work performed, as discussed below); 7. Inputs & Costs: a) as per Project Appraisal Report (PAR) and b) as per Project Completion Report (PCR); 8. Size descriptors (number of lanes and road length); and 9. Currency (currency of costs, conversion factor to USD and USD CPI factor, for conversion to 2006 USD). All projects from the 2008 AICD study, as well as from the 2007 AfDB study, were captured in the new database structure for the purposes of this report. It should however be noted that some projects did not have data for all the fields in the database. Projects listed in the database were further grouped into four categories, based on the type of work that was performed. These four categories, as well as a definition of each, are as follows: 1. Regraveling or periodic maintenance of unpaved roads. This is the activity of reinstating the surface layer of gravel roads. This term was also applied when there were substantial gravel road rehabilitation activities; 2. Periodic maintenance of paved roads. This involves the repair of African Development Bank Group / Chief Economist Complex minor surface defects and a seal or thin overlay, but without structural improvements or geometric upgrades. These contracts come in a range of light to heavy upgrades. Since the term “periodic maintenance” is used by road agencies for several different types of activity, some contracts with this activity in their title were reclassified (mostly to “rehabilitation/reconstruction”); 3. Rehabilitation of paved roads. This typically entails the reinstatement of roads to the original design standard, including structural repairs; and 4. Construction and upgrading of paved roads. This covers the upgrading of gravel roads to paved standard, or the addition of lanes to existing paved roads. It should be noted that the above four categories are fairly broad, and may contain a wide variance with regard to technical standards. For example, new road construction (category 4) can include standards such as gravel base and asphalt layer, gravel base and seal layer, bitumen-treated base and asphalt layer, and concrete base. However, in order to conduct a statistical analysis, a sufficiently large sample is required (i.e. data points), and a compromise was therefore reached between the number of categories and level of detail per category. Furthermore, the data available in PCRs often did not provide a detailed technical description of the type of design and work conducted. For these reasons, the four categories indicated above were used for the purpose of this study. 2.3 Addition of Cost Data from Recent AfDB Projects The previous studies (discussed above) contained projects up to about 2007. Therefore, in the identification of new projects for addition to the database, the focus was generally on post-2007 projects. During 2010, the AfDB availed a list of 44 projects (approved since 2007) for consideration in the study. The list was then evaluated based on the availability of their project documents. For most of the projects, PARs were available but not PCRs. As the PARs did not contain all the data required for the database – information that was also needed for the analysis of unit rates and cost overruns – it was decided to investigate a wider range of projects. Subsequently, it was decided to list all projects for which PCRs dated 2004 or later (although the actual projects could have been completed much earlier) were available from DARMS (Documents and Records Management System). A further criterion was that such projects should not have been included in the previous studies. The list contained 26 projects and was approved by AfDB for addition to the database, and for use in analysis of road infrastructure costs and cost overruns. The list of 26 new projects is indicated in Table 2-1. 5 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 AfDB Table 2-1: List of New Projects Selected for Addition to the Database Number Country Project Name 1 Benin Cotonou–Porto Novo Road Rehabilitation Project 2 Botswana Trans-Kgalagadi Road Project 3 Burkina Faso Second Road Program 4 Cameroon Road Improvement in the West, Littoral and South Provinces 5 Chad Djermaya–Massaguet Road Construction Project 6 Chad Road Rehabilitation and Maintenance Project 7 Ethiopia Alemgena–Butajira Road 8 Ethiopia Road Maintenance and Rehabilitation Project 9 Ghana Achimota–Anyinam Road Rehabilitation Project 10 Morocco Road Project III 11 Lesotho Likalaneng–Thaba Tseka Road Upgrading - Lot1 (Likalaneng–Cheche’s Pass) 12 Lesotho Mpharane–Bela Bela Road Upgrading Project 13 Madagascar Road Rehabilitation and Maintenance Project 14 Malawi Msulira–Nkhotakota Road Project 15 Malawi Road Maintenance and Construction (ROMAC II) Project 16 Mauritius South-Eastern Highway Project 17 Mozambique Pemba–Montepuez Road Rehabilitation Project 18 São Tomé and Principe Second Road Maintenance Project 19 Swaziland Transportation Sector Project 20 Swaziland Two International Roads Project 21 Tanzania Himo–Arusha Road Rehabilitation Project 22 Tunisia Classified Road Network Development Project II 23 Tunisia Classified State Road Network Development Project - Phase I 24 Tunisia Classified State Road Network Rehabilitation Project 25 Uganda Kyotera–Mutukula Road Upgrading Project 26 Uganda Rural Feeder Roads Maintenance Program PCRs and PARs for the 26 projects indicated above were extracted from DARMS. All relevant data were obtained from these documents and recorded in the database. Some of the projects comprised two or more types of road infrastructure investments (e.g. rehabilitation of paved roads, as well as the upgrading of paved roads). In such cases, each road infrastructure investment was captured separately in the database, resulting in more than one entry for the specific project. 2.4 Master Database for Analysis of Unit Rates and Cost Overruns from the 2008 AICD study, the 2007 AfDB study, as well as the new AfDB projects identified during 2010. A total of 172 projects were included in the final database, as indicated in Table 2-2. The final database of projects used for the analysis of unit rates consisted of projects 6 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Table 2-2: Projects Included in Final Database Number of Projects Regraveling/ Periodic Maintenance of Unpaved Roads Periodic Maintenance of Paved Roads Rehabilitation of Paved Roads Construction and Upgrading of Paved Roads Total 2008 AICD Study 37 4 51 23 115 2007 AfDB Study 2 0 7 13 22 New projects from AfDB identified during 2010 3 2 14 16 35 Total 42 6 72 52 172 Data Source Note: As described above, some of the new projects entailed more than one type of road infrastructure investment. In such cases, each investment was captured separately, resulting in more than one entry for the specific project. Therefore a total of 35 new ‘projects’ are reflected in Table 2-2, and not 26 as indicated in Table 2-1. 7 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 AfDB 3. Analytical Approach to Road Infrastructure Costs 3.1 Standardizing the Unit Rate The Terms of Reference for the study identified three topics that should be investigated, namely (i) what typical road unit costs are; (ii) whether the actual unit rates overran what was initially anticipated and if so, to what extent; and (iii) whether there is a trend in unit cost rates. The “unit rate” applied in this study is the cost per lane-kilometer. The lane-kilometer is the product of the number of lanes and the road length. cost, either obtained from the PCR or the project contract. The 2008 AICD data and 2010 AfDB data (i.e. the current study) are typically based on PCR values. The 2007 AfDB data mostly entailed projects that were on-going and that had experienced unexpected increases from the point of project appraisal or loan approval, prior to the contract being completed. For the purposes of this report, contract values were standardized in the same manner as for the 2007 AfDB and 2008 AICD studies. Road design standards differ between jurisdictions, and road works do not necessarily fall neatly into the four types of project classifications identified above. Projects were classified based on the description of the works in the PCR and the project contract. The main adjustment made to compensate for physical differences was to exclude all major bridges and structures. Physical characteristics that were not standardized included the use of specific materials and differing geometric standards. Unit rates are expressed as United States Dollar (USD) per lane kilometer. All contracts were standardized to 2006 USD value. This was the convention used in the previous two studies (which supply the bulk of the material considered in this study). The most common currency in the combined database is the UA (AfDB Unit of Account), followed by the FCFA and the USD, but the USD is favored as the currency to which most readers can readily relate. Data on lane widths were not always available. The 3.50 m appears to dominate the data, but there are lane width outliers from 3.25 m to 3.80 m. The unit rate does not compensate for width variations. For regraveling and periodic maintenance of paved roads, all roads were single carriageway (two lanes). For the construction of paved roads, about 4 percent of projects were dual carriageway (four lanes), while for the rehabilitation of paved roads, dual carriageways comprised about 1 percent. Financial adjustments made to standardize projects entailed excluding all (i) feasibility, environmental, design and other studies; (ii) social mitigation costs (e.g. relocation costs); (iii) supervision and audit services; and (iv) taxes. The value considered is the latest available contract 3.2 Analytical Approach In analyzing the four types of road project, a similar sequence of enquiry is followed. It entails three steps: (i) establishing the position of the unit cost curve; (ii) verifying whether rates that lie off the curve can be explained; and (iii) determining whether the position of the curve is as expected (overruns) and whether it is shifting over time (unit cost trends). These steps are further elaborated below. Step 1: The projects in the particular category are reviewed, highlighting the contribution of each of the three studies to the universum and indicating any major differences between the three data subsets. The convention applied is to plot unit rates by showing the relationship between the rate and the project size (lane length). This is a crucial understanding: in most cases, the main explanatory variable for the unit rate is economies of scale. The smaller the project, the more disproportionate is the relative contribution of project overheads such as Preliminaries & General (site establishment). Step 2: After project size, the other major potential drivers of the unit rate are considered. It is expected that these variables could help to explain any deviation from the economies-of-scale curve already established. (a) Regional characteristics such as geography, climate, business practice and state of the contracting industry are captured by grouping projects into Northern (Maghreb), Western (largely ECOWAS), Central (largely ECCAS), Eastern (EAC and surrounds), and Southern Africa (mostly SADC). (b) The origin (home country) of the main contractor is considered, to determine whether outlier unit rates can be traced back to the prevalence of home country vs regional or contractors from further away. (c) It is often argued that a country’s accessibility to the sea affects its cost of construction. This proposition is tested by comparing unit costs between landlocked countries and those with seaboards. Step 3: Movement of the unit cost curve could be short-term, i.e. the unit rate achieved exceeding the rate expected by the roads agency; or longer-term, i.e. that rates are drifting upward over time. In the short-term, “overrun” refers to a project completion amount exceeding the sum originally foreseen. Completion amounts can be the actual completion, as recorded in the PCR, or the contracted amount. The original amounts can be either as stated in the PAR or the loan agreement. This 8 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa study applied the PCR values for completion and the PAR values for the expected amount. In other words, “overrun” defines the extent to which the contracted amount was exceeded. The short-term overrun issue relies heavily on relevant project documentation being available. Of the three studies, only the 2007 AfDB investigation attempted to unpack the reasons for overruns and the current report therefore largely reflects overrun findings of that study. Here, cost overruns were assessed against the reference project amount as per the loan approval, or where this was unavailable, the PAR. African Development Bank Group / Chief Economist Complex Road projects considered were contracted through 2000–2010. For the unit rate trend investigation, for most of the project types, there are insufficient data points to explain possible long-term upward trends in unit rates. In no cases are there directly comparable projects (in terms of size, country/ location, etc.) which would enable a firm conclusion to be drawn on changes in unit rates. Unit rate trends are therefore calculated by comparing best-fit statistical simulations of different time periods. The unit rate data are subject to large variances. This may be the result of projects being incongruously categorized together, even though they may have some unique characteristics. Or it may be due to variances in contracting conditions; or a number of other considerations. This report therefore presents the unit rates not as a firm value, but as ranges of values that indicate the confidence interval around the calculated rate. The unit rates are presented as median (not average) rates, bounded by first and third quartile intervals. One set of statistics is provided for projects smaller than 100 lane km (typically subject to a large variance) and those larger than 100 lane km (typically demonstrating fairly small variance). 9 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 AfDB 4.Results 4.1 Establishing the Unit Cost Curve on the Basis of the Project Size 4.1.1 Construction/Upgrading of Paved Roads Table 4-1: Construction/Upgrade of Paved Road Projects – Sample Study/Region The database includes 52 construction or upgrading of paved roads projects, about a quarter each from the 2007 AfDB and AfDB 2010 studies, and about half from the 2008 AICD study. Of these, 47 have usable data (i.e. contracted values). As shown in Figure 4-1, for large projects (≥ 100 lane km), the unit cost rates of the three studies distribute similarly. For smaller projects (< 100 lane km), there are some outlier projects, especially in the 2010 AfDB and 2007 AfDB studies that result in very spiky curves compared with the AICD 2008 study curve, which shows a less prominent diseconomy of scale. 4.1.2 Rehabilitation of Paved Roads A total of 72 projects were classified under the “rehabilitation of paved roads” intervention. The majority (two-thirds) were from the 2008 AICD study, with 14 added in this study. Unit rates could not be calculated for one project, leaving a universum of 71 projects, as indicated in Table 4-2. North West Central East South Total 2007 AfDB - 3 - 7 2 12 2008 AICD - 4 2 14 2 22 2010 AfDB 1 1 2 3 6 13 Total 1 8 4 24 10 47 Figure 4-1: Construction/Upgrading of Paved Road Projects per Study 2,000,000 USD/lane km Swaziland MR3 Bypass 1,800,000 1,600,000 Mauritius South-Eastern Highway 1,400,000 1,200,000 AfDB 2007 1,000,000 AICD 2008 800,000 AfDB 2010 600,000 400,000 200,000 0 0 100 200 300 400 500 lane km Table 4-2: Rehabilitation of Paved Road Projects – Sample Study/Region North West Central South Total 2007 AfDB 1 5 - 1 - 7 2008 AICD - 8 2 8 33 51 2010 AfDB 3 3 3 2 2 13 Total 4 16 5 11 35 71 10 A f r i c a n East D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa AfDB African Development Bank Group / Chief Economist Complex Figure 4-2: Distribution of Paved Rehabilitation Projects per Study USD/lane km 1,400,000 1,200,000 1,000,000 AfDB 2007 800,000 AICD 2008 600,000 AfDB 2010 400,000 0 500 1,000 lane km 1,500 2,000 Table 4-3: Periodic Maintenance of Paved Road Projects – Sample Study/Region North West Central East 4.1.3 Periodic Maintenance of Paved Roads The combined data set includes six projects for the periodic maintenance of paved roads (Table 4-3). Four of these are from the 2008 AICD study and two were introduced in the 2010 AfDB review. 200,000 0 The projects that were added to the overall database by the 2010 AfDB study distribute very similarly to those of the 2008 AICD study (Figure 4-2). The projects from the 2007 AfDB study tended to be more expensive if smaller than 500 lane km. It should be recalled that the 2007 projects were specifically selected because they had resulted in overruns. Southern Total 2007 AfDB - - - - - - 2008 AICD - 3 1 - - 4 2010 AfDB 1 - - - 1 2 Total 1 3 1 - 1 6 From Figure 4-3, it can be seen that the unit rates of the two 2010 AfDB projects are substantially lower than the rates from the 2008 AICD study. The lower of the two 2010 unit rates is a resurfacing project in Morocco and the other a resealing project in Malawi. Figure 4-3: Periodic Maintenance of Paved Road Projects per Study USD/lane km 80,000 70,000 60,000 50,000 AfDB 2007 40,000 AICD 2008 30,000 AfDB 2010 20,000 10,000 0 0 100 200 300 400 lane km 11 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 4.1.4 Regraveling of Unpaved Roads For unpaved roads, the major intervention identified in the three studies is regraveling. There are 42 projects in the database, of which 37 yield useful unit rates (Table 4-4). The bulk of projects are from the 2008 AICD study, while two were added in the AfDB 2010 review. Reliable unit rates could not be calculated for the two regraveling projects from the 2007 AfDB study. The addition of the two AfDB 2010 projects enhances an understanding of the cluster of unit rates below 100 lane km (Figure 4-4). Even with the addition of these projects, the same economy-of-scale curve that appears for other project types still does not appear here. Even if the outlier projects are ignored, the curve remains flat. 4.1.5 Summary Result Location of Road Projects Study/Region North West Central East South Total 2007 AfDB - - - - - - 2008 AICD - 31 3 1 - 35 2010 AfDB - 2 - - - 2 Total - 33 3 1 - 37 Figure 4-4: Regraveling Projects per Study USD/lane km 45,000 40,000 DRC projects 35,000 30,000 AfDB 2007 AICD 2008 20,000 AfDB 2010 15,000 10,000 5,000 0 0 200 400 600 800 lane km 4.2 Other Major Potential Drivers of Unit Rates 4.2.1 Table 4-4: Regraveling of Unpaved Roads Projects – Sample 25,000 The unit cost curve confirms the economies of scale proposition, that the smaller the project, the more disproportionate is the relative contribution of project. In other words, smaller contracts with road size < 100 lane Km have higher unit costs compared to larger projects. AfDB Figure 4-5: Regional Distribution of Construction/Upgrading of Paved Road Projects 4.2.1.1 Construction/Upgrading of Paved Roads For construction/upgrading of paved roads, half of the projects are in East Africa and a fourth in Southern Africa (Figure 4-5). The unit rate variance is large (i.e. there is a high degree of scatter in the data) for small projects in both these regions. The most outlying small project is the Mbabane bypass (Swaziland) – a project that overspent notoriously. The outlier small project from the 2007 AfDB study is an 11 km project in East Africa (Mauritius). That country has a sizable contracting industry, which means that the unit rate cannot be explained simply by it being an island state. 2,000,000 USD/lane km 1,800,000 1,600,000 North 1,400,000 1,200,000 West 1,000,000 Central 800,000 East 600,000 South 400,000 200,000 0 0 100 200 300 lane km 12 A f r i c a n D e v e l o p m e n t B a n k 400 500 Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa AfDB African Development Bank Group / Chief Economist Complex Figure 4-6: Regional Distribution of Paved Rehabilitation Projects USD/lane km 1,400,000 1,200,000 North 1,000,000 West 800,000 Central 600,000 East 400,000 South 200,000 0 0 500 1,000 1,500 2,000 lane km Figure 4-7: Regional Distribution of Periodic Maintenance of Paved Road Projects USD/lane km 80,000 70,000 60,000 North 50,000 West 40,000 Central 30,000 East 20,000 South 4.2.1.2 Rehabilitation of Paved Roads For rehabilitation of paved roads, half of the projects are in Southern Africa, 22 percent in West Africa, and 15 percent in East Africa (Figure 4-6). The distribution of unit rates reflects the typical economies-of-scale curve, with higher unit rates for small projects and lower rates for larger ones. As was previously noted in the 2007 AfDB and 2008 AICD reports, the variance is particularly high for projects of fewer than 100 lane-km. For paved rehabilitation projects, the initial peakiness (unit rates from about USD 500,000/lane km) is ascribed to projects in the West Africa subregion, specifically four in Benin and two in Ghana. 4.2.1.3 Periodic Maintenance of Paved Roads For periodic maintenance, as shown in Figure 4-7, the difference between the rates of the 2010 and 2008 studies may be attributable to the fact that the projects are widely distributed over the continent. A further explanatory factor could be that the two AfDB 2010 projects predate 2000 (i.e. it is expected that unit rates have increased, even in real terms). Nevertheless, the data sample (six projects) is so small that it cannot be concluded with certainty that these projects’ unit rates are in fact outlying. 10,000 0 0 100 200 lane km 300 400 13 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 4.2.1.4 Regraveling of Unpaved Roads For regraveling roads, the three apparent outlier projects are all in Central Africa, specifically the Democratic Republic of the Congo (DRC). These were all emergency projects in Katanga Province. The cluster of small (less than 25 km road length) West African projects relates to the rural access program in Burkina Faso. For purposes of calculating the summary statistics below, this program is excluded because it has a dominating effect in the overall calculation. Figure 4-8: Regional Distribution of Periodic Maintenance of Paved Road Projects USD/lane km 45,000 40,000 35,000 30,000 AfDB 2007 25,000 AICD 2008 20,000 AfDB 2010 15,000 10,000 4.2.1.5Summary Result In all four test scenarios, the location of the project does not seem to significantly influence the distribution of unit rates. 4.2.2 AfDB 5,000 0 0 200 400 lane km 600 800 Origin of Contractors 4.2.2.1 Construction/Upgrading of Paved Roads For construction/upgrading of paved roads (Figure 4-9), Chinese contractors account for a significant share of projects. However, except for one possible project (the 11.1 lane km Mauritius South-Eastern Highway Project), they are not obviously responsible for outlier contracting values. The widest variance in contract values may rather be ascribed to local contractors. Figure 4-9: Paved Road Construction/Upgrading Projects by Origin of Contractor 2,000,000 USD/lane km 1,800,000 Home Country 1,600,000 Regional Country 1,400,000 1,200,000 Europe 1,000,000 China 800,000 Other East 600,000 400,000 Other 200,000 N/A - 0 100 200 300 lane km 14 A f r i c a n D e v e l o p m e n t B a n k 400 500 Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa AfDB African Development Bank Group / Chief Economist Complex Figure 4‑10: Paved Rehabilitation Projects by Origin of Contractor USD/lane km 1,400,000 1,200,000 Home Country 1,000,000 Regional Country 800,000 Europe 600,000 China Other East 400,000 Other 200,000 N/A - 0 500 1,000 lane km 1,500 4.2.2.2 Rehabilitation of Paved Roads Although there is no discernible pattern in contractor origin versus unit rate (Figure 4‑10), three of the outlier contracts identified above were carried out by European contractors and one by a Chinese contractor. 4.2.2.3 Periodic Maintenance of Paved Roads Similarly for periodic maintenance of paved roads (Figure 4-11), it is unlikely that the origin of the contractor played a significant role in the unit rate variance. 2,000 Figure 4-11: Paved Road Periodic Maintenance Projects by Origin of Contractor 80,000 USD/lane km 70,000 Home Country 60,000 Regional Country 50,000 Europe 40,000 China 30,000 Other East 20,000 Other 10,000 N/A - 0 100 200 lane km 300 400 15 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 4.2.2.4 Regraveling of Unpaved Roads As might be expected for a type of intervention that does not require a high degree of sophistication or major capital investment, regraveling contracts are dominated by domestic contractors (Figure 4-12). When the three outlier projects (DRC) are excluded, projects in landlocked countries have very similar unit rates to those in seaboard countries (Figure 4-13). There is however still no clear pattern to make a conclusion. Figure 4-12: Regraveling Projects by Origin of Contractor USD/lane km 45,000 40,000 Home Country 35,000 Regional Country 30,000 Europe 25,000 China 20,000 Other East 15,000 Other 10,000 N/A 5,000 4.2.2.5Summary Result In all four test scenarios, the origin of the contractor does not seem to significantly influence the distribution of unit rates. 4.2.3 Landlocked vs. Seaboard Countries - 0 200 400 lane km 600 800 Figure 4-13: Construction/Upgrading of Paved Road Projects – Landlocked vs. Seaboard Countries 4.2.3.1 Construction/Upgrading of Paved Roads For construction/upgrading of paved roads, there is no apparent difference in the distribution of unit costs for landlocked countries versus those with sea coasts. AfDB 2,000,000 USD/lane km Landlocked 1,800,000 Seaboard 1,600,000 Power (Landlocked) 1,400,000 Power (Seaboard) 1,200,000 1,000,000 800,000 600,000 400,000 200,000 0 0 100 200 300 lane km 16 A f r i c a n D e v e l o p m e n t B a n k 400 500 Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa AfDB African Development Bank Group / Chief Economist Complex Figure 4-14: Paved Rehabilitation Projects – Landlocked vs. Seaboard Countries USD/lane km 1,400,000 Landlocked 1,200,000 Seaboard 4.2.3.2 Rehabilitation of Paved Roads For rehabilitation of paved road projects, the unit rate patterns are very closely correlated between landlocked and seaboard countries (Figure 4-14), with no difference in the distribution of unit costs. 4.2.3.3 Periodic Maintenance of Paved Roads The project sample is too small to draw a conclusion about the unit cost comparison between landlocked and seaboard countries (Figure 4-15). 1,000,000 Power (Landlocked) 800,000 Power (Seaboard) 600,000 400,000 200,000 0 0 500 1,000 1,500 2,000 lane km Figure 4-15: Paved Rehabilitation Projects by Landlocked vs. Seaboard 80,000 USD/lane km 70,000 60,000 50,000 Landlocked 40,000 Seaboard 30,000 20,000 10,000 0 0 100 200 lane km 300 400 17 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 4.2.3.4 Regraveling of Unpaved Roads For regraveling roads, there is no clear pattern (Figure 4-16). 4.2.3.5Summary Result For at least two test cases, it appears unit rates between landlocked and seaboard countries strongly correlate without any major influence on unit cost distribution. AfDB Figure 4-16: Regraveling Projects – Landlocked vs. Seaboard Countries USD/lane km 30,000 25,000 20,000 15,000 10,000 4.3 Determining Unit Cost Trends 4.3.1 5,000 Unit Rates over Time 4.3.1.1 Construction/Upgrading of Paved Roads Figure 4-17 shows the trend in unit rates over time (i.e. the movement of the unit cost curves). Good-fit curves can be plotted for the period prior to 2000 (grey), and for 2003 (green), 2004 (yellow), and 2006 (orange). For projects larger than 400 lane km, the 2006 curve exceeds the others, but the occurrence of projects of this length is limited, and firm statistical conclusions cannot be drawn. For projects of 200 lane km and less, the variance of unit rates is high, resulting in an apparent decrease in unit costs over time. 0 0 200 Landlocked 400 lane km Seaboard 600 Power (Landlocked) 800 Power (Seaboard) Figure 4-17: Construction/Upgrading of Paved Road Projects – Unit Rates over Time USD/lane km 2,000,000 pre-2000 1,800,000 2000 1,600,000 1,400,000 2001 1,200,000 2002 1,000,000 2003 800,000 600,000 2004 400,000 2005 200,000 0 0 100 200 300 lane km 18 A f r i c a n D e v e l o p m e n t B a n k 400 500 2006 2007 Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa AfDB African Development Bank Group / Chief Economist Complex Figure 4-18: Paved Rehabilitation Projects – Unit Rates over Time USD/lane km pre-2000 1,400,000 2000 1,200,000 2001 1,000,000 2002 800,000 2003 600,000 4.3.1.2 Rehabilitation of Paved Roads Figure 4-18 demonstrates the evolution of unit rates over time for rehabilitation of roads. Three trend lines are shown for years that had a relatively large number of projects: pre-2000 (grey), 2004 (dark yellow), and 2006 (orange). The 2004 and 2006 curves virtually overlie. Unexpectedly, they are both slightly lower than the pre2000 curve. 2004 400,000 2005 200,000 2006 0 2007 0 500 1,000 1,500 2,000 2008 lane km 4.3.1.3 Periodic Maintenance of Paved Roads The project sample is too small to make a conclusion about the unit cost comparison over time (Figure 4-19). Figure 4-19: Paved Road Periodic Maintenance Projects – Unit Rates over Time 80,000 USD/lane km pre-2000 2000 70,000 2001 60,000 2002 50,000 2003 40,000 2004 30,000 2005 20,000 2006 10,000 2007 2008 - 0 100 200 lane km 300 400 2009 19 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 4.3.1.4 Regraveling of Unpaved Roads The projects universum is dominated by projects from 2005 and 2006, with no subsequent projects recorded. There is no clear pattern of unit rate changes over time (Figure 4-20). 4.3.1.5Summary Result In cases with wide distribution of sample data, it appears that for smaller projects the unit cost rate reduces over time while for larger projects it increases. 4.3.2 Figure 4-20: Regraveling Projects – Unit Rates over Time USD/lane km 45,000 pre-2000 40,000 2000 35,000 2001 30,000 2002 25,000 2003 20,000 2004 15,000 2005 10,000 2006 5,000 2007 Cost Overruns/Underruns - The summary result above is borne out by comparing the expected unit rate (as per the PAR) with the actual contracted rate. 2008 0 200 400 lane km 600 800 2009 Figure 4-21: Construction/Upgrading of Paved Road Projects – Unit Rate Overruns/Underruns (PCR vs. PAR) % Over/Under (Contract vs PAR) 100% 80% 60% 40% 20% 0% -120% lane km It would therefore appear that small projects are more susceptible to cost overruns than are larger projects. 20 A f r i c a n D e v e l o p m e n t B a n k 500 -80% -100% 450 -60% 400 -40% 350 300 250 200 150 100 50 -20% 0 4.3.2.1 Construction/Upgrading of Paved Roads Cost over/underrun data are available for 24 of the projects (Figure 4-21). Significant overruns (>20%) occurred in seven projects and significant under-expenditure (< -20%) in five projects. The major overrunning projects were: the Cameroon Road Improvement Project; Swaziland Two International Roads Projects; the Lesotho Mpharane–Bela Bela Road Upgrading Project; Swaziland M3 Bypass Project; and the Ghana Akatsi-Dzodze (Akatsi-Akanu Section) Project. The Tanzania Kigoma– Lusahunga Project (308 lane km) is the only large project that overran significantly. AfDB AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Figure 4-22: Paved Rehabilitation Projects – Unit Rate Overruns/ Underruns (PCR vs. PAR) % Over/Under (Contract vs PAR) 120% 100% 80% 60% 40% 4.3.2.2 Rehabilitation of Paved Roads Over/underruns were generally not significant except for very small contracts, which in any case are subject to much wider price variances. In the case of rehabilitation of paved roads (Figure 4-22), there appears to be a clear correlation between the degree of over/underrun and the size of the project: the smaller the project, the larger the difference between the expected unit rate (PAR value) and the contracted value. 20% 4.3.2.3 Periodic Maintenance of Paved Roads From Figure 4-23, it can be seen that contracts for the two 2010 AfDB projects were concluded substantially below the rates originally estimated. 0% 2,000 1,800 1,600 1,400 1,200 1,000 800 600 400 200 0 -20% -40% lane km Figure 4-23: Paved Road Periodic Maintenance Projects – Unit Rate Overruns/Underruns (PCR vs. PAR) % Over/Under (Contract vs PAR) 20% 10% 4.3.2.4 Regraveling of Unpaved Roads It was only possible to calculate cost overruns for the two 2010 AfDB projects. In both cases, the projects had underruns of less than 1 percent compared with the PAR estimate. It was therefore not possible to draw any conclusions from the limited sample size. 0% 400 350 300 250 200 150 100 50 0 4.3.2.5Summary Results »» Small projects are more susceptible to cost overruns than larger projects. -10% -20% -30% »» Construction/Upgrading of roads is more susceptible to cost overruns than underruns. -40% -50% lane km »» Rehabilitation of roads exhibits both characteristics (overrun/underrun). 21 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 4.3.3 Median Rates 4.3.3.1 Construction/Upgrading of Paved Roads Small construction/upgrade of paved road projects have a median unit rate (i.e. the unit rate in the middle of the dataset) of about USD 228,000/lane km, but ranging from USD 61,000 below to USD 198,000 above. For large projects, the expected rate is USD 147,000 but ranging from USD 31,000 lower to USD 15,000 higher, as indicated in Figure 4-24. For both small and large projects, the inclusion of the 2010 AfDB dataset exerts an augmenting effect on unit rates. For small projects, the 2008 AICD median unit rate was USD 201,000/lane km. The 2008 AICD median unit rate for large projects was USD 145,000/lane km. 4.3.3.2 Rehabilitation of Paved Roads Figure 4-25 shows the dataset for paved rehabilitation projects after correcting for the major outliers. “Outliers” includes two 2007 projects that exceeded the PAR significantly, as well as the other very peaky West African projects. AfDB Figure 4-24: Representative Dataset for Construction/Upgrading of Paved Road Projects USD/lane km 3,500,000 3,000,000 Data 2,500,000 Median<100km Q1<100km 2,000,000 Q3<100km 1,500,000 Median>100km 1,000,000 Q1>100km 500,000 Q3>100km 0 0 100 200 300 400 500 lane km Table 4-5: Unit Rate Statistics for Construction/Upgrading of Paved Road Projects (USD/lane km, rounded to ‘000) Metric < 100 lane km ≥ 100 lane km Quartile 3 425,400 162,000 Median 227,800 147,100 Quartile 1 166,300 115,900 Figure 4-25: Representative Dataset for Paved Road Rehabilitation Projects USD/lane km 600,000 Data 500,000 Median<100km 400,000 Q1<100km Q3<100km 300,000 Median>100km 200,000 Q1>100km Q3>100km 100,000 0 0 500 1,000 lane km 22 A f r i c a n D e v e l o p m e n t B a n k 1,500 2,000 AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Table 4-6: Unit Rate Statistics for Paved Road Rehabilitation Projects (USD/lane km, rounded to ‘000) Metric < 100 lane km ≥ 100 lane km Quartile 3 290,000 130,500 Median 180,300 84,400 Quartile 1 109,800 47,400 Figure 4-26: Representative Dataset for Periodic Maintenance of Paved Road Projects 80,000 USD/lane km 70,000 Data 60,000 Median<100km 50,000 Q1<100km 40,000 Q3<100km 30,000 Median>100km Accommodating the wide variance in unit rates for projects below 100 lane km, the summary statistics for paved road rehabilitation projects are shown in Table 4-6. For small rehabilitation of paved road projects, the unit rate is expected to be about USD 180,000/lane km, but it can range from USD 70,000 lower to USD 110,000 higher. For large projects, the expected rate is USD 84,000, but ranging from USD 37,000 lower to USD 46,000 higher. The median unit rates in the 2008 AICD study were USD 150,000/lane km for small projects and USD 79,000/lane km for large projects. (The unit rate was not calculated in the 2007 AfDB study.) 4.3.3.3 Periodic Maintenance of Paved Roads Two 2010 AfDB outlier projects (Figure 4-26) are excluded, leaving three fairly tightly spaced unit rate data points for periodic maintenance of paved roads. Q1>100km 20,000 Q3>100km 10,000 0 0 100 200 lane km 300 400 Table 4-7: Unit Rate Statistics for Periodic Maintenance of Paved Road Projects (USD/lane km, rounded to ‘00) Metric < 100 lane km ≥ 100 lane km Quartile 3 N/A 72,200 Median N/A 64,600 Quartile 1 N/A 56,900 The median unit rate for projects larger than 100 lane km is USD 65,000. The first quartile is about USD 8,000/lane km lower, while the upper quartile is about USD 8,000/lane km higher than the median. Since only the 2008 AICD projects are used to calculate the summary statistics, the median rate is the same as calculated in that in the study. 23 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 4.3.3.4 Regraveling of Unpaved Roads With the exclusion of two outlier projects, the DRC and Burkinabé program, the regraveling dataset is graphically presented in Figure 4-27. This is the only type of road project reviewed that does not demonstrate a clear pattern of economy of scale. The median unit rate for small projects (less than 100 lane km) is about USD 10,000, ranging downward by USD 2,000 and upward by USD 1,000/lane km. The median rate for large regraveling projects (≥ 100 lane km) is USD 11,000, minus or plus USD 2,000/ lane km. In the 2008 AICD study, the median rate was calculated for all (i.e. small and large projects) at USD 7,800/lane km. 4.3.3.5Summary Result The median unit rates clearly demonstrate a pattern of economy of scale, i.e. smaller contracts have higher unit costs compared to larger projects. AfDB Figure 4-27: Representative Dataset for Regraveling Projects 3,500,000 USD/lane km 3,000,000 Data 2,500,000 Median<100km Q1<100km 2,000,000 Q3<100km 1,500,000 Median>100km 1,000,000 Q1>100km 500,000 Q3>100km 0 0 100 200 300 400 500 lane km Table 4-8: Unit Rate Statistics for Regraveling Projects (USD/lane km, rounded to ‘00) Metric < 100 lane km ≥ 100 lane km Quartile 3 10,500 12,800 Median 9,600 11, 300 Quartile 1 8,100 9,600 24 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Conclusions The analysis for this report was performed on a total of 172 projects (sourced from the 2008 AICD study, the 2007 AfDB study, and newly selected projects obtained from AfDB during 2010), to determine unit rates for different types of road infrastructure investments. Of these 172 projects, unit rates could be calculated for 161 projects in this study. In response to the study’s Terms of Reference, the following conclusions are drawn: 5.1 Typical Road Unit Costs One very important conclusion from this review is that there is no such thing as a “typical” unit cost. This is because (i) unit costs are calculated through a process of standardizing projects that are broadly similar but which differ in their design details and specific circumstances, and (ii) the size of the project invariably has an overriding effect on the unit rate (economy of scale). The first issue is largely overcome by excluding major project and location-specific factors (e.g. bridges, taxes). The second issue is something that anyone estimating or evaluating roads costs should be vigilant about. Although it may be advantageous, from a statistical analysis perspective, to recommend that road project costs should be cast into a standard format (e.g. standard bills of quantities) that will facilitate ex post comparison, this could add to the administrative burden of national road agencies. Rather, it is recommended that lenders – through programs such as AICD – classify relevant data into standardized databases, as extracted by task team leaders at PAR and subsequent stages. Table 5-1 provides a summary of the unit cost findings. 5.2 Unit Cost Overruns/Underruns Nearly a third of the projects are from the 2008 AICD Study, where cost overrun was not an area investigated. This implies that the conclusions on overruns are based on a smaller dataset than the rest of the analysis. Analysis of cost overruns indicates that for all the projects where data on over/underruns are available, the overruns amount to 48 percent and the underruns to -15 percent of the PAR values. The main conclusions are that: (i) there appears to be a correlation between the over/underrun and the size of the project and (ii) the estimation error (i.e. PCR value minus PAR value) is likely to be an underestimate (48 percent) rather than an overestimate (-15 percent). These two conclusions are further elaborated upon in the next paragraphs. Table 5-1: Summary of Unit Rate Statistics for Different Types of Road Infrastructure Investment (USD/lane km, rounded to ’00) Type of Road Infrastructure Investment Regraveling/ Periodic Maintenance of Unpaved Roads Periodic Maintenance of Paved Roads Rehabilitation of Paved Roads Construction and Upgrading of Paved Roads 10,500 N/A 290,000 425,400 Median 9,600 N/A 180,300 227,800 Quartile 1 8,100 N/A 109,800 166,300 Quartile 3 12,800 72,200 130,500 162,000 Median 11,300 64,600 84,400 147,100 9,600 56,900 47,400 115,900 < 100 lane km Quartile 3 ≥ 100 lane km Quartile 1 Note: All values are given in 2006 USD. 25 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 In terms of conclusion (i), the analysis shows that the smaller the project, the larger the difference between the expected unit rate (PAR value) and the contracted value. This may be because larger contractors are more sophisticated in their costing, and/or that funding agencies expend more effort on the price estimates of larger projects. The implication is that unit rates for small projects should be treated with some caution. However, care should be taken not to spend more resources on refining designs, feasibility studies, and other work underlying PARs than might be expected to accrue in terms of the project benefits. In terms of (ii), the estimation error varies according to the type of project undertaken. For the rehabilitation of paved roads, the difference occurs both above (overrun) and below (underrun) the PAR value. In the case of the construction or upgrading of paved roads, it appears that the pattern is for small projects to overrun, rather than underrun. This suggests that PARs may have a tendency to be overly optimistic. 5.3 Trend in Unit Costs The finding on an increase in unit cost over time is inconclusive. This may be purely because of data constraints, i.e. the limited sample size for a specific year and standardization issues across projects in the same class. The effect is that statistically extrapolated unit cost curves (rather than “rates”) are compared. AfDB Two general conclusions can be drawn, the first related to the implications of the study findings and the second regarding the analysis process: 1. The study findings point out that many of the traditional causes of high road costs (e.g. geographic location, origin of contractor) are not very useful to explain unit cost rates. The principal explanatory factor appears to be project size and related issues, e.g. that small contracts get less attention from lenders. Teasing out deeper statistical relationships will require a more thorough and larger database. Given these shortcomings, where comparisons can be made, these indicate that unit costs for large projects (>100 lane km) have not increased during the last decade. It could even be inferred that they have reduced, although this is counterintuitive, given the field experience of AfDB task managers, which points to an upward trend in unit rates. 2. In terms of the analysis of road unit costs, much greater effort is required in two areas, namely: (i) the management of documentation (enabling ex post analysis) and (ii) proactively extracting relevant data, while issues are still recent and well-understood. Although the data may only be analyzed periodically, the database itself should be kept up to date. The AICD initiative, based on collaboration among the World Bank, AfDB, and other lenders, is a useful platform to establish a permanent database. 5.4 General Conclusions It is important for lending agencies and national road agencies to track road unit cost trends and issues so that these can be reflected in their planning. Their ability to influence the rates is probably fairly limited, other than in the case of contractor market distortions (e.g. collusion). However, a greater understanding of issues and trends will allow planners and lending agencies to make more accurate projections. REFERENCES Africon Limited. 2008. Africa Infrastructure Country Diagnostic Study: Consulting Services for the Evidence on Unit Costs of Infrastructure Projects in Sub-Saharan Africa. Washington, DC: World Bank Group. Africon Limited. 2007. Africa Infrastructure Country Diagnostic Study: Study on Unit Costs of Infrastructure Projects in SubSaharan Africa, Addendum 2: African Development Bank Study on Roads Maintenance and Construction Costs in Africa. Washington, DC: World Bank Group. 26 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex APPENDIX A: Detailed Description of Database Parts for AICD Initiative Africa Infrastructure Country Diagnostic Database (2008) Africon Limited carried out a study on unit costs during 2008 under the auspices of the joint World Bank–African Development Bank initiative on Africa Infrastructure Country Diagnostic (AICD). As part of this study, a database of infrastructure projects in Africa was compiled, including roads, water, sanitation, and electricity. The database was designed to consist of two parts, namely: a) a general section common to all projects, capturing the major exogenous variables; and b) an infrastructure-specific section, adapted for each sector (e.g. roads, water, and electricity) and for different infrastructures and technologies within each sector. A short description of these parts is given in the next sections. a) General Contract Information »» The following general information was obtained for all contracts: »» Project and contract information, including project/program title, project/program unique number, contract title, and contract unique number. »» Task Team Leader information, including name and contact details (email, telephone number). »» Geographic information (country/ies, district/s and location/s) and whether urban, rural, or deep rural. An attempt was made to standardize the use of “urban” for cities, towns, and large settlements, “rural” for small settlements, and “deep rural” for locations totally isolated from towns and villages. In the case of roads, the term “inter-urban” was used for roads through rural areas but connecting towns, and “rural access” for rural feeder roads. »» Implementing agency/ies, including the main funding Development Finance Institution (DFI), other DFIs and local funders and role players. »» Procurement, which may be National Competitive Bidding (NCB), International Competitive Bidding (ICB) or direct appointment. »» Bidders information, including the number of bidders (at Request for Proposal/tender stage), the name of the winning bidder, and nationality of the winning bidder. »» Key dates, including the date the contract was signed, the contracted completion date, and the actual completion date (in as far as these are available). b) Specific Contract Information »» The following information for each infrastructure (e.g. roads) was obtained: »» Infrastructure type, i.e. what technology. Road projects were differentiated according to whether they were urban, inter-urban and rural access, whether with or without a shoulder, and whether paved or unpaved. »» Activity, including preservation, rehabilitation, improvement, and/or new construction. 27 A f r i c a n D e v e l o p m e n t B a n k »» Basis of costing, i.e. whether a pre-contract estimate, contracted value, or the contract value as modified in the course of the contract. »» Input costs. This subsection divided the infrastructures into their major components. This allowed some comparison to be made between technologies, but importantly, it provided the basis on which to isolate components of costs, which appeared to be out-ofthe-norm in the course of standardizing contract information. The major components considered were: ·· Studies, design, land acquisition and environmental costs prior to construction (note that for roads, “environment” is isolated as a standalone item to facilitate the use of the study data in ROCKS); ·· Contractor’s establishment and mobilization (for roads, “demolition, dismantling, site clearance and other site preparation” are again isolated for use in ROCKS); ·· Mass earthworks; ·· Civils and structures. These were further subdivided into the following: ·· Major bridges and structures; ·· Minor bridges, culverts and drainage; ·· Accesses and junctions; ·· Pavement courses; ·· Shoulder works; and ·· Ancillary road works; Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 ·· In the calculation of unit costs, the cost of major structures and bridges was not included, as these were very contract-specific and did not cast light on average road costs. ·· Other (non-categorized costs); AfDB amount, on the basis of which output unit costs are calculated. For road projects, the key descriptors were the number of lanes and road length (km). ·· Taxes; ·· Contingencies; and ·· Mechanical, electrical, and control equipment; ·· Supervision (owner’s engineering costs). ·· Installation and commissioning (including dayworks); »» Output descriptors, i.e. the number of units “purchased” with the contract 28 A f r i c a n D e v e l o p m e n t B a n k »» Currency-related information, including the contract currency/ies, the conversion date, the conversion factor/s (to USD) and USD CPI factor (for conversion to 2006 USD). AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex APPENDIX B: Statistical Terms Note on Statistical Terms This report employs a number of statistical terms to describe the methodology and findings. These all have to do with the distribution of unit costs, i.e. how unit rates distribute around a value that indicates the norm for the particular type of project (construction, rehabilitation, etc.). In the analysis, there are two major steps to interpret the data statistically: »» “Best-fit” curve. The first step is to determine a formula that eliminates the “noise” of the scattered unit cost data, so that the data can be shown as a curve. The best-fit curve is the mathematical formula that reduces most noise. The formula used in the analysis is a negative exponential curve (y = a.x-b). The best-fit curve allows conclusions to be drawn about the typical unit rates across all project sizes. »» Statistics of distribution. The best-fit curve allows projects to be divided into “large” (> 100 lane km) and small projects. For each group, the central value is determined with reference to the median. The central value shows a point around which the data cluster. The “median” is the value in the middle 29 A f r i c a n D e v e l o p m e n t B a n k of the data range, i.e. there are as many values smaller than the median as values larger than it. The median is generally accepted to be a truer reflection of the central value than the “average,” as it gives a lower importance to outlier values (very high or very low values in the data set). The data clustering or “noise” around the median is measured by the data variance. The more scattered the data, the higher the variance and the lower therefore the confidence that can be placed in the median. Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 AfDB APPENDIX C: Consolidated Data Dates Source Class Project Title Country/ies Contractor Nationality PAR Contract Completion Contract Price PCR PAR PCR Dimensions USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm Periodic Maintenance/Regravel (Unpaved roads) AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.049 2 0.30 FCFA 1.00 1.00 - AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.035 2 1.00 FCFA 1.00 1.00 17,485.40 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.076 2 4.20 FCFA 1.00 1.00 8,988.80 AICD 2008 Regravel & related Village reinstatement Communities Support Program (Phase 1) Guinea Guinea 10/22/2002 3/1/2003 - 0.067 2 4.20 FG 1.00 1.00 8,004.86 AICD 2008 Regravel Nakivubo Channel Uganda Rehabilitation Project Uganda 2/2/2004 10/13/2004 - 0.976 2 4.25 USH 1.00 1.00 - AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.045 2 5.10 FCFA 1.00 1.00 4,422.17 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.094 2 6.50 FCFA 1.00 1.00 7,192.47 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso Burkina Faso 3/21/2005 - 0.101 2 6.66 FCFA 1.00 1.00 7,603.35 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.099 2 7.80 FCFA 1.00 1.00 6,353.96 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.130 2 8.30 FCFA 1.00 1.00 7,812.75 AICD 2008 Regravel & related Village reinstatement Communities Support Program (Phase 1) Guinea Guinea 11/5/2002 3/24/2003 - 0.161 2 8.40 FG 1.00 1.00 9,590.55 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.155 2 9.10 FCFA 1.00 1.00 8,506.85 AICD 2008 Regravel Senegal Senegal 11/23/2001 - 0.300 2 10.00 FCFA 1.00 1.00 14,985.06 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.051 2 10.60 FCFA 1.00 1.00 2,421.70 AICD 2008 Regravel & related Village reinstatement Communities Support Program (Phase 1) Guinea Guinea 11/5/2002 3/26/2003 - 0.196 2 11.50 FG 1.00 1.00 8,532.42 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.247 2 13.00 FCFA 1.00 1.00 9,504.16 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso Burkina Faso 4/11/2005 9/21/2005 - 0.150 2 15.00 FCFA 1.00 1.00 4,983.96 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.280 2 16.00 FCFA 1.00 1.00 8,750.07 AICD 2008 Regravel & related Village reinstatement Communities Support Program (Phase 1) Guinea Guinea 10/22/2002 3/24/2003 - 0.228 2 16.30 FG 1.00 1.00 6,994.72 AfDB 2007 Pobe-Ketou-Illara (regraveling) Benin Benin 4.000 4.312 2 16.50 UA 1.47 0.99 - Second Transport Sector Program 0 9/1/2004 6/7/2006 8/1/2006 30 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Dates Source Class Project Title Country/ies Contractor Nationality PAR Contract Completion AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso Burkina Faso 3/21/2005 AICD 2008 Regravel Second Transport Sector Program Senegal Senegal AICD 2008 Regravel Second Transport Sector Program Senegal AICD 2008 Regravel & related Transport Sector reinstatement Project AICD 2008 Contract Price PCR PCR USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm - 0.838 2 18.30 FCFA 1.00 1.00 22,894.44 11/23/2001 - 0.436 2 19.70 FCFA 1.00 1.00 11,053.69 Senegal 11/23/2001 - 0.407 2 20.00 FCFA 1.00 1.00 10,181.31 Burkina Faso Burkina Faso 3/21/2005 7/26/2005 - 0.179 2 20.50 FCFA 1.00 1.00 4,369.03 Regravel & related Transport Sector reinstatement Project Burkina Faso Burkina Faso 3/21/2005 7/6/2005 - 1.055 2 20.80 FCFA 1.00 1.00 25,358.84 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso Burkina Faso 4/11/2005 9/22/2005 - 0.298 2 23.00 FCFA 1.00 1.00 6,481.25 AICD 2008 Regravel & related Village reinstatement Communities Support Program (Phase 1) Guinea Guinea 10/28/2002 3/24/2003 - 0.277 2 25.10 FG 1.00 1.00 5,520.62 AICD 2008 Regravel Senegal Senegal 11/23/2001 - 0.570 2 26.40 FCFA 1.00 1.00 10,798.40 AICD 2008 Regravel & related Village reinstatement Communities Support Program (Phase 1) Guinea China 10/24/2002 2/12/2004 - 0.435 2 26.60 FG 1.00 1.00 8,178.04 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.341 2 30.50 FCFA 1.00 1.00 5,583.90 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso NA 12/1/2006 - 0.489 2 35.00 FCFA 1.00 1.00 6,980.63 AICD 2008 Regravel Senegal Senegal 11/23/2001 - 0.778 2 39.30 FCFA 1.00 1.00 9,899.65 AICD 2008 Regravel & related Transport Sector reinstatement Project Burkina Faso Burkina Faso 3/21/2005 7/21/2005 - 0.701 2 50.25 FCFA 1.00 1.00 6,972.42 AICD 2008 Regravel Burkina Faso Burkina Faso Burkina Faso 7/31/2001 - 1.501 2 75.00 FCFA 1.00 1.00 10,009.68 AICD 2008 Regravel Emergency Recovery and Rehabilitation Project Ethiopia Ethiopia 9/11/2003 11/29/2006 - 2.704 2 120.00 ETB 1.00 1.00 11,264.74 AICD 2008 Regravel Emergency Living Conditions Improvement Support DRC DRC 1/18/2006 2/27/2006 - 13.665 2 168.00 USD 1.00 1.00 40,668.29 AfDB 2007 Wacha-Maji 0 (upgrade to gravel) Ethiopia China 23.310 51.102 2 173.00 UA 1.53 0.97 - AICD 2008 Regravel Emergency Living Conditions Improvement Support DRC DRC 12/20/2005 2/27/2006 - 16.347 2 208.00 USD 1.00 1.00 39,296.73 AICD 2008 Regravel Emergency Living Conditions Improvement Support DRC DRC 1/18/2006 2/27/2006 - 18.072 2 224.00 USD 1.00 1.00 40,339.22 AfDB 2010 Second Road Program Periodic Burkina Faso Maintenance on Earth Roads - Lot 1 Burkina Faso 11/14/2001 4/28/2004 6/1/2008 9/1/2008 5.011 4.978 2 276.00 UA 1.48 1.07 14,347.32 AfDB 2010 Second Road Program Periodic Burkina Faso Maintenance on Earth Roads - Lot 2 Burkina Faso 11/14/2001 5/6/2004 6/1/2008 9/1/2008 3.825 3.799 2 377.80 UA 1.48 1.07 7,953.41 Second Transport Sector Program Second Transport Sector Program 7/6/2005 PAR Dimensions 8/11/2003 5/1/2007 31 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 Dates Source AfDB 2010 Class Project Title Contractor Nationality Country/ies Rural Feeder Roads Rural Feeder Roads Uganda Maintenance Maintenance Program Program PAR Contract Completion 6/1/2001 Contract Price PCR PAR PCR AfDB Dimensions USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm ? 10/30/1991 2/1/1996 11/1/2005 8.860 8.360 2 4,003.00 UA 1.45 1.30 - Periodic Maintenance (Paved roads) AfDB 2010 Road Maintenance Resealing of and Construction two paved (ROMAC II) Project roads (BengaNkhotakotaDwangwa) Malawi UK 2/15/1990 11/1/1993 10/1/1998 10/1/2005 6.362 3.747 2 109.00 UA 1.40 1.38 33,243.18 AfDB 2010 Road Project III Resurfacing of main roads (132 km) Kingdom of Morocco Morocco 12/15/1994 11/1/1995 8/31/2001 4.869 3.516 2 126.00 UA 1.52 1.31 27,863.11 AICD 2008 Paved: Interurban Periodic Maintenance Second Transport Sector Program Senegal Senegal 7/29/2004 11/16/2006 - 9.986 2 89.00 - 1.00 1.00 56,098.72 AICD 2008 Paved: Interurban Light Reconstruction Emergency DRC Multisector Rehabilitation amd Reconstruction Project (EMRRP) NA 9/27/2006 - 13.526 2 93.85 FCFA 1.00 1.00 72,064.04 AICD 2008 Paved: Interurban Periodic Maintenance Transport Corridors Mali Improvement Project France 10/4/2005 3/29/2006 - 21.725 2 150.00 USD 1.00 1.00 72,418.14 AICD 2008 Paved: Interurban Periodic Maintenance 0 Other 1/19/1999 - 19.801 2 173.00 FCFA 1.00 1.00 57,229.57 Burkina Faso 9/1/2002 Rehabilitation (Paved roads) AICD 2008 Paved: Inter-urban Roads and Bridges Mozambique Rehab/Reconstruct Management and Maintenance Program Italy 11/11/2004 10/5/2006 - 1.841 2 1.95 MT 1.00 1.00 472,098.28 AICD 2008 Paved: Urban Road Maintenance Malawi Rehab/Reconstruct and Rehabilitation Project Malawi 4/28/2004 - 1.192 2 2.60 MKW 1.00 1.00 229,284.64 AICD 2008 Paved: Urban Urban Rehab/Reconstruct Development and Decentralization Project Senegal 12/29/2000 3/7/2005 - 1.753 4 1.48 FCFA 1.00 1.00 296,722.27 AICD 2008 Paved: Urban Road Maintenance Malawi Rehab/Reconstruct and Rehabilitation Project Malawi; Zimbabwe 10/5/2005 - 1.048 2 3.50 MKW 1.00 1.00 149,762.87 AICD 2008 Paved: Urban Road Maintenance Malawi Rehab/Reconstruct and Rehabilitation Project Malawi 4/11/2004 - 1.715 2 3.64 MKW 1.00 1.00 235,535.15 AICD 2008 Paved: Improvement/ Upgrade Uganda 3/2/2004 10/13/2004 - 0.743 2 3.70 USH 1.00 1.00 100,338.29 AICD 2008 Paved: Inter-urban Roads Sector Zambia Rehab/Reconstruct Invetment Program South Africa 12/16/2003 4/12/2004 - 3.251 2 4.10 ZMK 1.00 1.00 396,479.45 AICD 2008 Paved: Urban Road Maintenance Malawi Rehab/Reconstruct and Rehabilitation Project Malawi 4/28/2004 - 1.659 2 4.50 MKW 1.00 1.00 184,318.02 AICD 2008 Paved: Urban Road Maintenance Malawi Rehab/Reconstruct and Rehabilitation Project Malawi 10/7/2005 - 2.094 2 4.60 MKW 1.00 1.00 227,575.06 Mali Nakivubo Channel Uganda Rehabilitation Project 32 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Dates Source Class Project Title Country/ies AICD 2008 Paved: Inter-urban Road Rehabiliation Zambia Rehab/Reconstruct and Maintenance AfDB 2010 Cotonou–Porto Novo Road Rehabilitation Project Contractor Nationality PAR Zambia (Consultancy: United Kingdom) Contract Completion Contract Price PCR 10/14/2005 12/27/2005 PAR PCR Dimensions USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm - 0.946 2 7.00 ZMK 1.00 1.00 67,603.23 13.635 11.248 4 3.85 UA 1.34 1.24 1,215,099.16 ‘Cotonou–Porto Novo Road Rehab - Lot A Benin France 9/4/1996 4/17/1998 3/1/2002 1/1/2006 AICD 2008 Paved: Urban Rehabilitation/ Reconstruction RSA NA 12/1/2004 - 2.696 2 9.00 ZAR 1.00 1.00 149,788.47 AICD 2008 Paved: Inter-urban Rehab/Reconstruct Burundi China 10/28/2005 4/14/2006 - 5.396 2 10.00 FCFA 1.00 1.00 269,787.94 AICD 2008 Paved: Urban Rehab/ Reconstruction RSA NA 10/1/2005 - 13.101 2 15.20 ZAR 1.00 1.00 430,958.82 AfDB 2010 Cotonou–Porto Novo Road Rehabilitation Project 13.157 10.853 2 16.16 UA 1.34 1.24 556,264.47 - 5.407 2 16.60 USD 1.00 1.00 162,858.34 4.970 4.543 2 18.48 UA 1.34 1.24 204,107.78 - 7.440 2 21.10 MT 1.00 1.00 176,306.64 22.910 18.898 4 10.75 UA 1.34 1.23 724,485.34 - 35.980 4 11.75 FCFA 1.00 1.00 765,526.41 - 5.444 2 24.60 AKW 1.00 1.00 110,643.47 4/1/2000 7.179 7.000 2 26.30 UA 1.33 1.55 274,226.20 10/1/1998 10/1/2005 6.759 3.981 2 26.30 UA 1.38 1.26 131,794.32 - 6.178 2 27.00 CVE 1.00 1.00 114,416.65 Cotonou–Porto Novo Road Rehab - Lot C Benin France 9/4/1996 7/22/1998 1/18/2007 AICD 2008 Paved: Interurban Rehab/ Reconstruction Projet de réhabil- Benin itation de la route Poke–Ketou–Illara France AfDB 2010 Second Road Maintenance Project Rehabilitation of: (I) RN2 between Ribeira Peixe and Porto Alegre; (II) Structures on the RN1 and RN2 Portugal AICD 2008 Paved: Interurban Rehab/ Reconstruction Roads and Bridges Mozambique Management and Maintenance Program AfDB 2010 Cotonou-Porto Novo Road Rehabilitation Project Cotonou–Porto Novo Road Rehab - Lot B Sao Tome and Principe Benin 8/31/1993 5/29/1998 Italy 7/1/2003 5/1/2002 9/4/1996 11/16/1998 12/31/2004 1/1/2006 AICD 2008 Paved: Urban Rehab/ Reconstruction Amenagement de Benin la route Cotonou– Porto Novo (Lot B) NA AICD 2008 Paved: Urban Rehab/ Reconstruction 0 NA AfDB 2010 Road Rehabilitation Rehabilitation Chad and Maintenance works on the Project N’djamena bypass, and rehabilitation of Walia-N’gueli bridge road France 10/26/1987 7/25/1990 10/1/1998 AfDB 2010 Road Maintenance Rehabilitation and Construction of Chikwawa– (ROMAC II) Project Bangula Road Malawi South Africa 2/15/1990 3/1/1997 AICD 2008 Paved: Interurban Rehab/ Reconstruction Cape Verde Cape Verde Road Sector Support Project 5/1/2004 11/11/2004 10/5/2006 France Angola 1/1/2006 11/9/1998 11/2/2005 1/19/2006 33 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 Dates Source Class Project Title Country/ies Contractor Nationality PAR Contract Completion Contract Price PCR PAR PCR AfDB Dimensions USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm AICD 2008 Paved: Urban Rehab/ Reconstruction 0 Angola NA - 5.230 2 27.30 AKW 1.00 1.00 95,786.50 AICD 2008 Paved: Urban Rehab/ Reconstruction 0 Angola NA - 5.380 2 27.92 AKW 1.00 1.00 96,340.20 AICD 2008 Paved: Urban Rehab/ Reconstruction South Africa RSA N014-0613-2005/1 NA 9/1/2005 - 12.164 2 28.00 ZAR 1.00 1.00 217,211.06 AICD 2008 Paved: Interurban Rehab/ Reconstruction Tetteh Quarshie Circle – Mamfe Project/ PantangMamfe Section Ghana China 3/22/2004 - 21.184 2 29.40 USD 1.00 1.00 360,267.57 AICD 2008 Paved: Interurban Rehab/ Reconstruction Road Sector Development Project Burundi Rwanda 10/26/2005 2/1/2006 - 6.573 2 30.00 BIF 1.00 1.00 109,542.75 AICD 2008 Paved: Urban 0 Rehab/Reconstruct Angola NA - 5.808 2 30.90 AKW 1.00 1.00 93,984.49 AICD 2008 Paved: Interurban Rehab/ Reconstruction Road Rehabiliation Zambia and Maintenance China Consultancy : South Africa - 23.232 2 34.70 ZMK 1.00 1.00 334,753.67 AICD 2008 Paved: Urban Rehab/ Reconstruction 0 Angola NA - 7.049 2 34.70 AKW 1.00 1.00 101,573.07 AICD 2008 Paved: Interurban Rehab/ Reconstruction Northern Corridor Transport Improvement Project Kenya NA - 30.809 2 35.00 KSH 1.00 1.00 440,135.53 AICD 2008 Paved: Improvement/ Upgrade 0 Angola NA - 16.676 2 37.80 AKW 1.00 1.00 220,583.92 AICD 2008 Paved: Interurban Rehab/ Reconstruction Road Sector Development Program Ghana Netherlands 12/15/2003 2/13/2004 - 28.083 4 19.00 Cedi 1.00 1.00 369,515.45 AICD 2008 Paved: Interurban Rehab/ Reconstruction Road Rehabiliation Zambia and Maintenance China (Consultancy : Zambia) 2/18/2005 6/10/2005 - 11.709 2 40.50 ZMK 1.00 1.00 144,558.03 AfDB 2007 Nsawam-Apedwa (rehab and new construction) 0 China 23.230 48.880 2 41.00 UA 1.53 0.98 888,850.37 AICD 2008 Paved: Inter-urban Road Ghana Rehab/Reconstruct Infrastructrure Project 2003/ Nsawam–Apedwa Road NA 11/14/2006 - 48.892 2 41.00 Cedi 1.00 1.00 596,249.97 AICD 2008 Paved: Inter-urban Roads and Bridges Mozambique Rehabilitation Management and Maintenance Program Mozambique 4/26/2004 08/22/2006 - 8.276 2 48.00 Mt 1.00 1.00 86,204.35 AICD 2008 Paved: Interurban Heavy Rehabilitation South Africa 9/30/2003 12/23/2003 - 3.001 2 50.00 ZMK 1.00 1.00 30,008.07 AICD 2008 Paved: Inter-urban Roads and Bridges Mozambique Rehabilitation/ Management Reconstruction and Maintenance Program Portugal 4/26/2004 10/5/2006 - 13.773 2 52.00 MT 1.00 1.00 132,432.88 Ghana Roads Sector Zambia Invetment Program 10/7/2005 12/28/2005 8/29/2006 4/1/2004 4/1/2007 34 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Dates Source Class AICD 2008 Paved: Urban Rehab/ Reconstruction AICD 2008 Paved: Urban Rehab/ Reconstruction AICD 2008 Paved: Interurban Rehab/ Reconstruction AfDB 2007 Project Title Contractor Nationality Country/ies RSA NA 0 Angola Tema–Aflao Project/ Akatsi– Aflao Road PAR Contract Completion Contract Price PCR PCR USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm - 9.397 2 52.40 ZAR 1.00 1.00 89,663.57 NA - 19.958 2 57.00 AKW 1.00 1.00 175,069.50 Ghana NA - 37.762 2 58.49 Cedi 1.00 1.00 322,806.71 Tema-Aflao (Akatsi- 0 Aflao Section) (rehabilitation and new construction) Ghana - 11/1/2006 19.910 36.000 2 58.50 UA 1.47 1.00 452,318.72 AfDB 2007 Techiman– Kintampo (reinforcement) 0 Ghana - 12/1/2006 26.721 31.040 2 60.00 UA 1.47 1.00 379,683.99 AICD 2008 Paved: Interurban Rehab/ Reconstruction 0 Namibia NA 7/6/2004 - 15.943 2 61.40 N$ 1.00 1.00 129,828.00 AICD 2008 Paved: Interurban Rehab/ Reconstruction Road Development Uganda Program Phase 1 Serbia 12/29/2006 - 10.251 2 66.00 USH 1.00 1.00 77,658.74 AICD 2008 Paved: Interurban Rehab/ Reconstruction Roads and Bridges Mozambique Management and Maintenance Program Mozambique 3/15/2006 2/12/2007 - 6.250 2 76.00 MT 1.00 1.00 41,115.71 AICD 2008 Paved: Urban Rehab/ Reconstruction 0 NA - 34.304 2 85.00 AKW 1.00 1.00 201,788.61 AICD 2008 Paved: Interurban Rehab/ Reconstruction Emergency DRC Multisector Rehabilitation amd Reconstruction Project (EMRRP) - 6.974 2 86.40 USD 1.00 1.00 40,359.93 AfDB 2010 Road Maintenance Semera - Dobi and Rehabilitation Junction Project Reconstruction 29.210 25.500 2 94.00 UA 1.40 1.40 264,865.14 AICD 2008 Paved: Reseal - 7.750 2 100.00 USH 1.00 1.00 38,747.92 AfDB 2010 Himo-Arusha Road Himo-Arusha Road Tanzania Rehabilitation Rehabilitation Project Project Italy 36.992 24.730 2 104.00 UA 1.40 1.40 232,490.49 AICD 2008 Paved: Interurban Rehab/ Reconstruction Roads and Bridges Mozambique Management and Maintenance Program China 4/26/2004 8/22/2006 - 24.742 2 109.00 MT 1.00 1.00 113,495.06 AICD 2008 Paved: Interurban Rehab/ Reconstruction 0 NA 5/26/2002 - 8.675 2 113.80 KSH 1.00 1.00 38,115.75 AICD 2008 Paved: Interurban Heavy Rehabilitation Roads and Bridges Mozambique Management and Maintenance Program South Africa 4/26/2004 08/22/2006 - 19.766 2 123.00 Mt 1.00 1.00 80,350.07 AICD 2008 Paved: Interurban Rehab/ Reconstruction 0 NA 2/19/2003 - 13.003 2 131.30 N$ 1.00 1.00 49,517.66 Angola China Ethiopia Ethiopia Road Development Uganda Program Phase 1 9/30/2004 9/16/2006 11/22/1989 7/1/1993 NA Kenya Namibia 8/1/2003 PAR Dimensions 8/1/2001 8/1/2005 12/29/2006 6/11/1990 5/7/1993 4/4/1997 6/1/2004 35 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 Dates Source Class Project Title Contractor Nationality Country/ies PAR Contract Completion Contract Price PCR PAR PCR AfDB Dimensions USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm AICD 2008 Paved: Interurban Rehab/ Reconstruction Emergency DRC Multisector Rehabilitation amd Reconstruction Project (EMRRP) China 3/30/2005 - 26.658 2 141.90 USD 1.00 1.00 93,932.04 AICD 2008 Paved: Interurban Heavy Rehabilitation Roads and Bridges Mozambique Management and Maintenance Program Italy 4/26/2004 08/22/2006 - 12.648 2 159.00 Mt 1.00 1.00 39,774.23 AICD 2008 Paved: Interurban Heavy Rehabilitation Roads and Bridges Mozambique Management and Maintenance Program South Africa 4/26/2004 10/05/2006 - 23.623 2 173.00 Mt 1.00 1.00 68,276.01 AfDB 2010 Road Rehabilitation RN1 & RN1, RN6: and Maintenance Rehabilitation Project and Periodic Maintenance of Paved Roads Madagascar Madagascar 10.600 22.340 2 173.40 UA 1.32 1.16 98,667.36 AICD 2008 Paved: Interurban Rehab/ Reconstruction Namibia NA - 23.554 2 203.30 N$ 1.00 1.00 57,928.84 AfDB 2010 Pemba-Montepuez Pemba–Montepuez Mozambique Road Rehabilitation Road Rehabilitation Project Project Italy 6/25/1997 3/1/2000 27.030 23.870 2 210.00 UA 1.32 1.18 88,474.49 AfDB 2007 Toliara (rehabilitation) RN 34 only Madagascar China 7/1/2004 8/1/2006 24.530 21.973 2 221.00 UA 1.47 0.99 72,217.68 AfDB 2007 Multinational UEMOA/GhanaProgram Routier 1 – Mali Section (reinforcement) 0 Mali, Ghana - 1/1/2006 9/1/2006 11.374 14.999 2 221.00 UA 1.47 0.99 49,541.76 AfDB 2007 Multi- Waenu/ MaliSenegalDakar: Mali Section (road improvement) Lot 1 & 2 Mali - 1/1/2006 6/1/2006 51.600 59.243 2 226.40 UA 1.47 0.99 191,006.46 AfDB 2010 Classified State Road Network Rehabilitation Project Classified State Road Network Rehabilitation Project Tunisia Mostly Tunisian 31/05/1995 1/1/1997 30/06/2002 9/1/2002 40.660 30.312 2 260.00 UA 1.38 1.27 102,073.46 AfDB 2010 Classified State Road Network Development Project - Phase I Classified State Road Network Development Project - Phase I Tunisia Tunisia 26/11/1997 30/06/2002 12/1/2002 19.667 14.929 2 340.80 UA N/A N/A - AfDB 2007 Tunisia, Classified Road Network rehabilitation Phase IV Part 2 (23 lots) Tunisia Tunisian 11/1/2004 5/1/2007 62.680 59.985 2 421.10 UA 1.53 0.97 105,557.01 AfDB 2010 Road Project III Reinforcement of main roads (801km) Kingdom of Morocco Morocco 12/15/1994 11/1/1995 8/31/2001 37.685 31.743 2 938.00 UA 1.52 1.31 33,795.15 AfDB 2010 Classified Road Network Development Project II Classified Road Network Development Project II Tunisia Tunisia 09/06/1999 8/1/1999 31/12/2003 8/1/2004 157.644 2 981.90 USD 1.00 1.21 96,848.91 0 1/5/1991 Jan 99/ Dec 00 12/1/2005 5/1/2009 5/10/2002 various 7/1/2002 1/1/2005 9/1/2002 184.439 36 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Dates Source Class Project Title Contractor Nationality Country/ies PAR Contract Completion Contract Price PCR PAR Dimensions USD Original Exchange CPI Rate Lanes Length Currency Factor PCR USD/lkm Construction and upgrading of paved roads AfDB 2010 South-Eastern Highway Project Construction of a Mauritius new Road linking Plaine Magnien to Ferney Community Centre (5.526 km) China AICD 2008 Inter-urban: Construction (paved) Road Sector Support Project Cape Verde AICD 2008 Inter-urban Upgrade to Paved Road Sector Ethiopia Development Support Program II NA AfDB 2007 Tombo-Gbessia (improvement of paved road and other activities) 0 - AICD 2008 Inter-urban Upgrade to Paved Road Sector Ethiopia Development Support Program II AfDB 2007 Mayange-Nemba 0 (upgrade to paved) AICD 2008 Inter-urban Upgrade to Paved AfDB 2010 Achimota-Anyinam Construction of Road Rehabilitation Apedwa–Bunso Project Section of the Achimota– Anyinam Road Ghana AfDB 2007 MR3 Bypass (upgrade) 0 Swaziland AICD 2008 Inter-urban Upgrade to Paved ADB Ghana Ghana P-GH-D00-002 REHABILITATION OF ACHIMOTAANYINAM ROAD - APEDWA-BUNSO SECTION NA AfDB 2010 Road Improvement in the West, Littoral and South Provinces Road works, bridge Cameroon construction and related improvements between Melong and Dschang, and between Eseka and Lalodorf Brazil 3/29/2001 10/6/2003 7/1/2007 AfDB 2010 Mpharane–Bela Construction works Lesotho Bela Road for upgrading of Upgrading Project Mpharane – Bela Bela, St Theresa and Kolojane in Leribe and Berea districts of Lesotho South Africa 1/16/2002 7/27/2003 5/12/2005 AICD 2008 Inter-urban Upgrade to Paved Cape Verde Guinea Rwanda Ghana 6/30/2008 5/1/2009 #DIV/0! 9.767 2 5.53 UA 1.48 1.08 1,419,590.65 10/31/2005 11/07/2006 - 2.186 2 11.00 CVE 1.00 1.00 99,370.48 - 4.536 2 11.00 ETB 1.00 1.00 - 49.530 - 2 11.10 UA 1.48 1.03 - 7/4/2006 - 4.418 2 13.00 ETB 1.00 1.00 169,911.65 10/1/2006 12/1/2006 11.280 10.942 2 20.00 UA 1.47 1.00 401,535.04 - 16.751 2 20.70 USD 1.00 1.00 404,618.30 ? 12/15/1997 12/19/2000 12/31/2008 12/15/2009 22.130 20.840 2 21.80 USD 1.00 1.16 553,799.43 South Africa 12/1/2003 2/1/2007 35.350 56.563 4 11.00 UA 1.53 0.99 1,946,864.80 - 14.668 2 22.00 USD 1.00 1.00 333,359.21 9/1/2008 14.020 24.350 2 22.50 UA 1.40 1.09 823,349.05 4/1/2008 4.230 6.860 2 23.54 UA 1.40 1.10 223,036.12 - 30.812 2 28.47 USD 1.00 1.00 541,194.01 7/1/2005 NA Germany ADB Rwanda Rwanda P-Z1-DB0-037 Travaux routiers d’aménagement de la section Mayange - Nemba Akatsi–Noepe Project/Akatsi– Akanu road 6/13/2001 2/1/2004 NA NA 37 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 Dates Source Class Project Title Country/ies AfDB 2010 Classified State Road Network Rehabilitation Project AfDB 2007 Akatsi-Dzodze 0 (Akatsi-Akanu Section) (upgrade to paved) AfDB 2010 LikalanengThaba Tseka Road Upgrading - Lot1 (LikalanengCheche’s Pass) AfDB 2007 13. Likalaneng0 Thaba Tseka (upgrade to paved) AICD 2008 Inter-urban Upgrade to Paved ADB Lesotho Lesotho P-LS-DB0-009 Likaleneng-Thaba Teseka Road Upgrading Project AICD 2008 Inter-urban Upgrade to Paved Central Transport Corridor Project AICD 2008 Inter-urban Upgrade to Paved AfDB 2007 Classified State Road Network Rehabilitation Project Contractor Nationality PAR Tunisia Mostly Tunisian 31/05/1995 Ghana - 1/1/2007 ? 10/29/2003 South Africa Contract Price Contract Completion PCR USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm 3.978 2 29.10 UA N/A N/A - 13.271 21.250 2 29.75 UA 1.53 1.06 581,139.28 2/28/2009 5/27/2010 18.190 13.660 2 31.00 UA N/A N/A - 11/1/2006 4/1/2006 18.180 17.942 2 31.00 UA 1.47 1.00 425,407.71 NA 3/5/2006 - 20.899 2 31.00 USD 1.00 1.00 337,076.11 Tanzania China 4/29/2005 7/20/2005 - 12.902 2 33.00 TSH 1.00 1.00 195,486.26 Central Transport Corridor Project Tanzania China 4/29/2005 11/07/2005 - 11.312 2 34.00 TSH 1.00 1.00 166,346.04 Gasenyi-Kirundo (asphalting) Lot 3 Burundi France 9.150 10.345 2 37.00 UA 1.47 1.00 205,209.60 AICD 2008 Inter-urban Upgrade to Paved Construction de la RN 14 Kicukiro - Nyamata Mayange - Nemba Tronçon Kirundo - Gasenyi’ Burundi NA 14.009 2 37.00 USD 1.00 1.00 189,311.15 AfDB 2010 Two International Roads Project Two International Swaziland Roads Project Mbabane-Ngwenya Road Swaziland/ South Africa AfDB 2007 Lot 1 (upgrade to paved) 0 Zanzibar AfDB 2007 Lot 2 (upgrade to paved) 0 Zanzibar AfDB 2010 Lesotho 30/06/2002 9/1/2002 PAR Dimensions 4.580 Likalaneng -Thaba Lesotho Tseka Road Upgrading - Lot1 (Likalaneng Cheche’s Pass) various PCR AfDB 9/1/2006 12/1/2006 11/18/1994 7/1/1999 4/26/2004 12/1/2005 19.710 32.550 4 19.30 UA 1.37 1.21 697,941.62 Kenya 6/1/2005 12/1/2005 7.007 6.647 2 44.10 UA 1.48 1.02 114,494.08 Italy 6/9/2004 6/1/2006 6.904 8.386 2 44.30 UA 1.47 0.99 138,171.83 Kyotera–Mutukula Kyotera–Mutukula Uganda Road Upgrading Road Upgrading Project Project Italy- Germany 17/09/1998 8/1/2000 10/1/2002 11/1/2005 10.200 8.090 2 44.74 UA 1.32 1.17 139,443.25 AICD 2008 Inter-urban Upgrade to Paved NA 11/14/2003 - 20.500 2 45.00 USD 1.00 1.00 227,781.28 AfDB 2007 Gitarama-Ngorero 0 (rehab and paving) Rwanda China 2/1/2005 12/1/2006 11.590 9.372 2 46.60 UA 1.47 1.00 147,604.06 AfDB 2010 Djermaya– Massaguet Road Construction Project Chad France 1/23/1997 12/14/1998 8/31/2001 11/1/2001 3.420 3.098 2 47.00 UA 1.34 1.23 54,358.06 ADB Cameroun Cameroun P-CM-D00-005 Projet d’aménagement routier dans les provinces de l’ouest, du sud et du littoral Tarring of the two-lane road from Djermaya to Massaguet 38 A f r i c a n D e v e l o p m e n t B a n k AfDB Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex Dates Source Class Project Title Contractor Nationality Country/ies PAR Contract Completion Contract Price PCR PAR PCR Dimensions USD Original Exchange CPI Rate Lanes Length Currency Factor USD/lkm AfDB 2010 Two International Roads Project Two International Swaziland Roads Project Luyengo-Sicunusa Road Swaziland/ South Africa 11/18/1994 10/1/1999 7/1/2003 12/1/2005 20.870 16.600 2 47.20 UA 1.37 1.20 288,490.23 AfDB 2010 Transport Sector Project MbabaneSwaziland Ezulwini-Matsapha Upgrading Swaziland/ Denmark 8/24/1992 10/1/1994 1/1/1999 12/1/2004 49.423 55.799 4 26.40 UA 1.42 1.35 1,009,348.37 AICD 2008 Inter-urban Upgrade to Paved Uganda Road Development Program Phase 2 Uganda Netherlands 6/21/2004 07/15/2004 - 15.792 2 53.00 USH 1.00 1.00 148,977.64 AICD 2008 Inter-urban Upgrade to Paved Kenya NA 9/30/1996 - 41.316 2 53.30 KSH 1.00 1.00 387,579.83 AICD 2008 Inter-urban Upgrade to Paved Uganda Road Development Program Phase 2 Uganda China 6/21/2004 10/26/2004 - 15.784 2 55.00 USH 1.00 1.00 143,491.02 AICD 2008 Inter-urban Upgrade to Paved Uganda Road Development Program Phase 2 Uganda China 3/25/2004 06/07/2004 - 14.484 2 62.50 USH 1.00 1.00 115,874.32 AfDB 2010 Msulira-Nkhotakota Msulira-Nkhotakota Malawi Road Project Road Project 0 11/25/1991 6/16/2000 8/31/2003 11/1/2006 14.140 15.880 2 80.00 UA 1.32 1.17 153,430.59 AfDB 2007 Multinational Senegal Section Waemu/ Mali-Senegal (rehabilitation and construction) Senegal AICD 2008 Inter-urban Upgrade to Paved Road Sector Ethiopia Development Support Program II China AICD 2008 Inter-urban Upgrade to Paved ADB Uganda Uganda P-UG-DBO-017 Uganda: Upgrading of Kabale–Kisoro– Bunagana/Kyanika Road NA AICD 2008 Inter-urban Upgrade to Paved Northern Main Swaziland Road Construction Project South Africa/ Lebanon AICD 2008 Inter-urban Upgrade to Paved ADB Cameroun P-CM-DB0-007 Projet d’aémenagement route Ambam-Eking AICD 2008 Inter-urban Upgrade to Paved AICD 2008 Senegal 4/1/2007 21.760 22.822 2 82.50 UA 1.53 0.98 206,241.25 7/4/2006 - 27.126 2 86.00 ETB 1.00 1.00 157,711.83 - 98.452 2 98.70 USD 1.00 1.00 498,742.71 9/22/2004 3/24/2007 - 7.761 2 106.00 SEM 1.00 1.00 36,607.42 France 10/18/2003 - 16.240 2 114.00 USD 1.00 1.00 71,230.13 Road Sector Ethiopia Development Support Program II China 6/23/2006 10/30/2006 - 50.449 2 117.25 ETB 1.00 1.00 215,135.05 Inter-urban Upgrade to Paved Road Sector Ethiopia Development Support Program II China 6/23/2006 10/30/2006 - 27.825 2 119.00 ETB 1.00 1.00 116,912.30 AfDB 2010 Alemgena Butajira Road Alemgena-Butajira Ethiopia Road Upgrading China 6/17/1998 10/25/2000 4/5/2004 23.640 21.270 2 120.00 UA 1.32 1.16 135,745.58 AfDB 2007 Djougou-Ndali (regravel/ asphalting) 0 Benin, France 1/1/2004 12/1/2006 21.230 24.167 2 125.00 UA 1.47 1.00 141,892.92 AICD 2008 Inter-urban Upgrade to Paved Road Sector Ethiopia Development Support Program II China 1/0/1900 6/23/2006 10/30/2006 - 38.258 2 130.00 ETB 1.00 1.00 147,148.04 AfDB 2007 Kigoma-Lusahunga 0 (upgrade to paved) China 9/1/2001 21.410 33.652 2 154.00 UA 1.47 1.01 161,981.84 Cameroun Benin Tanzania 1/1/2006 4/1/2007 3/1/2006 39 A f r i c a n D e v e l o p m e n t B a n k Study on Road Infrastructure Costs: Analysis of Unit Costs and Cost Overruns of Road Infrastructure Projects in Africa African Development Bank Group / Chief Economist Complex . May 2014 Dates Source Class Project Title AfDB 2007 5. Butajira0 Hossaina-Sodo (upgrade to paved) AICD 2008 Inter-urban Upgrade to Paved Contractor Nationality Country/ies Ethiopia PAR China, South Korea Contract Price Contract Completion PCR Dimensions USD Original Exchange CPI Rate Lanes Length Currency Factor PAR PCR 45.900 35.719 2 189.00 UA 1.48 25.298 2 211.50 USD 1.00 1.00 59,806.83 10/1/2001 7/1/2004 AfDB USD/lkm 1.06 149,233.84 ADB Mauritanie P-MR-DB0-006 Construction du tronçon Mbignik - Boghe Lot II de la route Rosso Mauritania Boghe’ China 12/3/2003 AfDB 2010 Trans-Kgalagadi Road Project Construction Botswana of 589km road between Sekoma and Mamuno Section II: Kang to Ghanzi Junction (221 km) Kuwait 11/25/1991 12/16/1994 7/1/1998 3/1/2005 30.790 21.920 2 221.00 UA 1.42 1.35 94,605.05 AfDB 2010 Road Project III Construction of secondary roads (257km) ? 12/15/1994 11/1/1995 8/31/2001 9/1/2002 19.780 22.091 2 237.00 UA 1.52 1.31 93,084.54 AfDB 2010 Classified State Road Network Development Project - Phase I Tunisia – Classified Tunisia State Road Network Development Project - Phase I Tunisia 26/11/1997 30/06/2002 12/1/2002 50.158 41.249 2 433.00 UA N/A N/A - Morocco - various 40 A f r i c a n D e v e l o p m e n t B a n k