Sycamore to Peñasquitos 230 kV Transmission Line ••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••• Did you know? • The California Independent System Operator (CAISO) identified this proposed line as a SDG&E® submitted an application to the California Public Utilities Commission (CPUC) for approval to construct a new 230 kV transmission line that would run between the Sycamore Canyon and Peñasquitos Substations. The new line will help improve reliability and integrate more renewable energy into our system which helps meet state mandated goals. priority in its 2012-2013 Transmission Plan. SDG&E’s proposed Sycamore to Peñasquitos Through a competitive 230 kV line is divided into the following solicitation process, primary components: SDG&E was selected to design, construct and own the line. • SDG&E’s plans for the proposed line • Segment A – Replace existing 138 kV wood H-frame structures with new 230 kV steel poles (8.3 miles, all located in SDG&E’s existing right-of-way). includes using existing • Segment B - Install new 230 kV underground right-of-way as well as transmission line along Carmel Valley Road constructing a new (2.8 miles, all located in SDG&E’s existing underground section franchise position). along Carmel Valley Road. • Along the proposed line, existing wood poles will be replaced with galvanized steel poles. The proposed transmission line will help us maintain reliability in neighborhoods throughout the region. • Segment C - Install new 230 kV conductor on existing 230 kV steel structures (2.2 miles, all located in SDG&E’s existing right-of-way). • Segment D - Install new 230 kV conductor Project purpose and need A 230 kV transmission line connecting the Sycamore Canyon and Peñasquitos Substations is critically needed. As originally identified by CAISO as well as Governor Brown’s statewide task force, this new line is necessary to ensure the region has a reliable transmission grid due to the unexpected loss of generation at the San Onofre Nuclear Generating Station. The new transmission line is also needed to deliver increasing amounts on existing 230 kV steel lattice towers and of renewable energy and to deliver power relocate two existing 69 kV power lines to safely and reliably to regional load centers. new tubular steel poles (3.3 miles, all in The proposed project will improve the SDG&E’s existing right-of-way). delivery of renewable energy to the • Minor modifications of the existing Sycamore San Diego coastal area and help meet the Canyon and Peñasquitos Substations to forecasted increase in electricity demand allow for connection of the new 230 kV in the San Diego region. transmission line. Upgrades to several additional substations will also be required. continued on back ••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••• Benefits SDG&E’s proposed project that would connect the Sycamore Some of the key benefits of the proposed project are: Canyon and Peñasquitos Substations in a different manner than SDG&E’s proposed project. • Improved reliability and integration of existing renewable energy into our system. Proposed Project Schedule • Use of existing electric utility corridors, structures, access (CPUC alternatives would result in a longer schedule) roads and work areas. Construction start date: June 2016 In-service date: May 2017 • Fire “hardening” by replacing existing wood structures with steel. Public Affairs contact Permitting Todd Voorhees The CPUC has jurisdiction over the final design, construction Regional Public Affairs Manager and route location of this proposed project. In April 2014, sxpq@semprautilities.com SDG&E filed an application with the CPUC for a Certificate 1-844-765-6388 of Public Convenience and Necessity. The application Additional information included a Proponent’s Environmental Assessment. The For more details about this project, please proposed project may require additional agency approvals visit sdge.com/key-energy-initiatives. including, approval from MCAS Miramar since the Sycamore Canyon Substation is located on the base and the Coastal For information about the CPUC’s environmentally preferred Commission for the portion within the coastal zone. alternative as outlined in its Draft Environmental Impact Report, please visit www.cpuc.ca.gov/Environment/info/ On September 17, 2015, the CPUC issued its Draft panoramaenv/Sycamore_Penasquitos/index.html. Environmental Impact Report articulating alternatives to Existing Transmission Lines Proposed Project Segments 15 m Cami no De l Existing Substation Rd. ley l a el V Sur LEGEND Car rm el Va ll Ca r me ey Rd . lM tn Rd . B Ca C Poway Rd. Black Moun d tain R d. tain R oun mel M 15 D Peñasquitos Substation Mira Mesa Blvd. P.O. Box 129831 | San Diego, CA 92112-9831 | 1-800-411-7343 | Connect at sdge.com © 2016 San Diego Gas & Electric Company. All copyright and trademark rights reserved. S1610006 0216 200 Segment (3.3 miles) Replacement of existing wood D H-frames with new 69 kV steel poles Scripps Poway Pky. . Car Segment (2.8 miles) New underground 230 kV line B in existing franchise position (Carmel Valley Road) Segment (2.2 miles) New 230 kV conductor on existing C steel lattice towers 56 56 Segment (8.3 miles) Replacement of existing wood A H-frames with new 230 kV steel poles A Sycamore Canyon Substation