229 IEEE Transactions on Power Systems, Vol. 10,No. I, February 1995 DISTRIBUTION SYSTEM STATE ESTIMATION C. N. Lu J. H. Teng W.-H. E. Liu Department of Electrical Engineering National Sun Yat-Sen University Kaohsiung, Taiwan, ROC - Abstract A three-phase distribution system state estimation algorithm is proposed in this paper. Normal equation method is used to compute the real-time states of distribution systems modeled by their actual a-b-c phases. A current based formulation is introduced and compared with other formulations. Observability analysis for the proposed distribution system state estimation is discussed. Test results indicate that the normal equation method is applicable to the distribution system state estimation and the current based rectangular form formulation is suitable for this application. - Keywords State Estimation. Distribution Automation, Distribution System Operation. Energy Management Systems 1. INTRODUCTION In the modern Energy Management System (EMS), State Estimation (SE) program processes a set of raw measurement data and provides a real-time load flow solution which is the basis of the advanced functions for system security monitoring and control. SE is based on the mathematical relations between the system state variables (e.g. bus voltage magnitudes and angles) and the measurements. Various techniques have been used to obtain an SE solution, excellent surveys on SE algorithms can be found in [l-31. Measurements used to compute the realtime system states are bus injections, line flows and bus voltages. In some estimators current magnitude and voltage angle measurements are also used [4]. In addition to a real-time load flow solution, state estimator also provides functions such as bad measurement data detection, modeling error detection, meter placement and observability test. Real-time control of the distribution system reqbires an estimate of the system stales. In the past most distribution systems were not monitored, therefore, there was no need for SE. Under this condition, distribution system load flow program is often used for planning purposes, such as in computing system losses Of different feeder configurations for system loss reduction. Various techniques have been proposed to obtain distribution system load flow solutions (5-131. 9 4 WM 098-4 PWRS A paper recommended and approved by the IEEE Power System Engineering Committee of the IEEE Power Engineering Society for presentation at t h e IEEE/PES 1994 Winter Meeting, New York. New York, January 30 - February 3, 1994. Manuscript submitted December 28, 1992; made available for printing January 11, 1994 Pacific Gas and Electric Company San Francisco, CA 94111, USA Nowadays, the technology to autoinatically monitor and control a distribution system is available [141. In an automated distribution system, many meters are installed. Similar 10 those in the transmission system automation, real-time measurements are noisy, thus, techniques have to be developed to screen the measurement data. Due to the requirements of filtering measurement data and having real-lime system states for on-line operation. the need for a distribution system slate estimator may soon be justified. In this view, Wu and Neyer [IS]proposed an asynchronous dislribution system SE technique. The SE was formulated as a equality consuained weighted least squares problem. A dismbution system SE that uses a minimum number of remote measurements was presented in [ 161. An ilerative procedure based on Kirchhoffs current law was used U, o w n the distribution system SE. Two types of data are required for S E they are the network data and the measurement data. A transmission system has a relatively balanced nature which allows the decoupling of the three phase system and the positive sequence network is used for the analysis. In reality. power systems are unbalanced when the power lines are not fully uansposed andor the loads are not balanced. The unbalanced nature of the distribution system prohibits the use of symmevical component transformation. and due lo various combinations of single-phase. two-phase, and three-phase loads encountered in the distribution system. accurate study can be accomplished only with distribution lines modeled in their actual a-b-c phase representation I5-81. In addition to the network dam, we also need a set of redundant measuremenb to obtain an estimate of the system states. In a f u l l y automated system the measurements are sufficient for SE. However, in the current stage of distribution system automation. the number of meters installed in the system is low and may not be sufficient for SE, i.e. the system may not be completely observable. In order to obtain an SE under this condition, techniques have to be developed Lo provide additional data (i.e. pseudo measurements) to the estimator. Intuitively. one would use the historical dala of the feeders and distribution transformer loadings to provide such information. Pseudo measuremenls estimated by using historical dala may not match exacuy the real-time actual values. but they increase the data redundancy of SE. If Uiis approach is adopted care must be taken in assigning weights to various types of measurements. Techniques lhai can be used to determine lhe meter or pseudo measurement locations for oblaining a complete observability of the system are available in [17-211. A three-phase SE algorithm based on normal equation method is proposed in this paper. A new reclangular form SE based on currenc instead of power, is introduced. The proposed algorithm can be used U, handle many types of measuremenb. It is applicable to the current magnitude measurements that are often found in the distribution sysrem telemeuy. The three-phase network models and mathematical formulation of the method are described in this paper. The suitability of the proposed 0885-8950195/504.000 1994 IEEE 230 Bus7 Bus6 Bus8 Bus9 Bus10 15 e :Feeder Terminal Unit :Pseudo measurement Figure 1: A Distribution System Feeder formulation in the unbalanced system is tested by comparing it with polar form coupled and decoupled formulations. Observability analysis for the distribution system SE is discussed. Effects of measurement types and redundancy on the performance of estimation are investigated. Va Va -Y ac ac-8 Vb Vb 2. SYSTEM MODEL AND MEASUREMENTS Figure 1 shows a portion of a distribution system feeder in the Taiwan Power Company (TPC) Kaohsiung District. The three-phase primary feeder operates at 22.8 KV. The circuit is represented on a per-phase basis. As can be seen from Figure 1, there are three-phase and single-phase laterals involved in the circuit. Feeder Terminal Units (FIT0 on the feeder will be used to collect real-time data and communicate with the master station. They also perform some control actions. The methods developed by J. R. Carson and W. A. Lewis [51 can be used to compute the impedances of circuits with neutral and ground return paths. Line charging is ignored in the study since it is relatively insignificant at distribution voltage levels. We use the approach proposed in [5-8] to build the admiWce matrix of the unbalanced three-phase system. Figure 2 shows the phase and neutral impedance of a three-phase feeder section. For such a feeder section we can build a 4x4 impedance matrix including the a-b-c phases and ground node. The impedance matrix relates the line currents and impedances to voltage drop of the line section. Figures 3 shows the equivalent Circuits after the elimination of the reference (ground) node in the impedance matrix of a three-phase feeder section. The circuit in Figure 3 can be described by a 3x3 admittance matrix that inc~udesthe mutual effects and relates the branch admiuances, and node voltages to branch currents. The effects of neutral and ground return paths are accounted for in the calculation procedure. Zaa Va' Vb' VC' Vn Figure 2: Impedances of a Three-phase Feeder Section vc vc -Ybc-g Figure 3: ycc-g An Equivalent Circuit Phase Feeder Section -Ybc-g of a Three- In an automated distribution system, measurements may include bus power injections, branch power flows, bus voltages and line currents. However. in the present stage. the distnbution system is still rarely measured. and this results in several buses that are unobservable, i.e. only the state of a portion of the system can be computed. Fonunately, historical data are available and can be utilized to forecast the loadings of feeders and distribution transformers. These data are treated as pseudo measurements. Loads in a distribution system are usually classified as three general types of customers. they are the residential. industrial and commercial customers. Typical load pattern or daily load curve of each type of customer can be obtained by elecuic load synlhesis or load survey technique [5.13]. The load composition of each distribution transformer can be calculated according to the energy consumption of all customers served by the transformer. B y using the load patterns and the derived load composition. an hourly load of distribution transformer can be estimated and used as a pseudo measurement. The quality and quantity of information concerning loads vary among utilities. In TPc, the energy consumption of each customer is determined by the billing data stored in the Customer Information System (CIS) [W. In this study. the measurement set includes the actual measurements on the feeders and substations (e.g. branch currents. bus voltages and branch power flows), and the pseudo measurements (e.g. distribution transformer loadings) obtained from historical data. The weights assigned for the pseudo measurements are lower than those for the actual measurements. In this case, the SE solution tends to match the real-time measurements and the transformer loading data can be adjusted accordingly. This, indeed, is an important benefit of the 23 1 distribution system SE. Based on the estimated real-time system states, the solutions obtained from many of the distribution system advanced application software would become more realistic. ...... ....,. 15 ...... :::::: 3. NORMAL EQUATION METHOD In SE,the model used to relate the measurements and the state variables is 2 = h(X,Y) + N W (1) k 2 = vector of measurements X,Y = vectors of state variables N = measurement noise h = functions relating state variables to measurements 0 IO 15 20 25 30 35 40 45 Bus No. We choose bus voltages as state variables. We can choose to express bus voltages in polar form (X=O and Y=IVI) or in rectangular form (X=IVkosO and Y=IVlsinB). N is assumed to be a Gaussian distribution with zero mean and variance 02.u - is~ used to weight each individual measurement. More accurate measurements will have lower 0 ' s . while the pseudo measurements are assigned with higher U'S to highlight the lower confidence given to these measurements. The noise elements are assumed to be independent. Let R be the covariance of N, then ~ i= iai2, the variance of the i-th measurement. Weighted Least Square (WLS) estimation computes the state variable vectors X and Y which minimize the following function J(X,Y) = l12[Z-h(X,Y)lTR-1[Z-h(X,Y)] 5 (2) J(X,Y) is minimized by differentiating it with respect to X and Y,and setting the resulting nonlinear equation to zero. 'hen the nonlinear equation is solved iteratively by Newton's method. Let Hi bethe measurement Jacobian matrix at the i-th iteration, then update of the state variables can be found by solving the following equation Figure 4: Jacobian Matrix Structure 0 10 0 20 30 3 40 wY 70 z 'E 50 > 1* 80 on 0 IO 20 30 40 50 60 70 80 90 Slate Variable No. Figure 5: Gain Matrix Structure Current Based SE Formulation Equation (3) is called the normal equation of the W S problem. HiTR-lHi is called the gain matrix. A solution of [X,Y] can be obtained by solving Equation (3) iteratively until the vector components of the right-hand side are sufficiently small. Readers should be reminded that since we model the feeder on a per-phase basis, each three-phase bus will have six state variables, with two state variables for each phase. There are several 3x3 blocks that locate at the diagonal and off-diagonal of the Jacobian and gain matrices.The structures of the Jacobian and gain matrices of the 15 bus system shown in Figure 1 are given in Figures 4 and 5. A dot in Figures 4 and 5 indicates a nonzero enay. Figure 4 shows the nonzero terms of JNJx. In the following, a new SE formulation based on curreni instead of power. is proposed. The proposed formulation can handle all types of measurements. In each iteration of SE, power measurements are converted into their equivalent currents. In addition, current based SE uses rectangular voltage/currenr coordinates. It can be shown that the gain matrix derived from nodal admiaance matrix is constant. From Equation (3) it can be seen that the gain matrix of SE is composed of the measurement Jacobian and the covariance matrices. For a pair of phax-a power injection measurements Pa and Qa, at a bus of Figure 3. they can be expressed as : 232 where Gkm + JBkm = Ykm, Gmand Bkm are 3x3 block elements of nodal admittance matrix. Since the current injection at phase-a of Figure 3 can be expressed in rectangular form as : I' a = .@ s ( e a - e a . ) - b , ( f a - f , . ) + g a b ( e b - e b . ) -b ab (f b -fb,)+g,(ec-ec.)-b,(fc-fc.)l lia = @ , ( f a - fa.)+ b,(ea- +bab(eb - e b , ) + g,(f, ea.)+ g a b ( f b - f b , ) - fc.)+ b,k, - ecJl the Jacobian wms are Therefore, if bus injection measurements are transformed to equivalent currents. and bus voltages are expressed in rectangular form, then the Jacobian matrix smcture of injection measurements with respect to the state variables in a three bus system are in the following form: G31 - B31 I '32 - B32 I B31 G31 I G 3 3 - B33 I B32 G3Z B33 '33 Where ej. fj. Ijr and Iji are 3x1 vectors. Using the same idea, if we converl other types of measurements, such as branch power flows and current magnitudes, into equivalent currents and expressed them in rectangular form then the Jacobian terns of these measurements are constant and equal to the branch Polar form Rectangular form These power measurement Jacobian terms are state dependent, i.e., they have to be. computed in each iteration of SE. The Jacobian terms of bus current injections with respect to node voltages exp :ssedin rectangular form are as follows: admittances. With these background in hand, let's see how to find the equivalent currents of branch power flow and bus injection measurements. The branch power flow measurements P h m e a and &,mea can be converted into measurement equivalent current I h m e a ~ by v the following equation: m where v k is the estimated bus voltage at the k-th iteration. Current flow calculaled in each iteration is 233 Observability Analysis where y h is the admittance of the branch. Note that I h m e a W' and &d are complex values and expressed in rectangular forms. The conversion of bus injection measurements to tbeir equivalent currents is the same. = ((P+jQ)kmea / vk)* = h(Ikmea-eqv) + j h(Ikmea*qv) (7) Where (P+jQ)kmea are bus injection measurements at bus k. The bus injection calculated at each itelation is Ikd = z = Re&d) + J h(Ikcal) (8) In addition to the power measurements, other types of measurements such as current and voltage magnitude measurements can also be used in the rectangular formulation. For the current and voltage magnitude measurements, due to the lack of phase information, we use a slightly different procedure to obtain their equivalent complex currents and voltages. The equivalent currents and voltages are equal to the measured magnitude values (IVklmea, IIhlmea) multiplied by the ratio of the ca~culatedcomplex values (Vkcal = lVkCall LeV, ~ h c a=l I I ~ LeI) ~ Ito the magnitudes of the calculated values (IVkcall, I I ~ ~ Ii.e., ) , let ~ h c a =l [(P+jQ)hCa' / vkcal]* (9) When sufficient measurements are available the state vector of the whole system can be obtained by SE. In this case the network is said to be observable. This is m e when the rank of measurement Jacobian matrix is equal to the number of unknown slate variables. The rank of the measurement Jacobian matrix is dependent on the locations and types of available measurements as well as on the network topology. In the threephase formulation, the rank may also be affected by the coupling terms between phases. In certain cases, one phase may be observable while the others are not. Thus, the relationship between numerical observability [ZO] and topological observability [21] is not obvious under these conditions. It Seems not very straightfonuard to define topological observability for three-phase SE formulation. Consequently. a numerical observability approach m a y be preferable for the proposed threephase SE. The numerical observability analysis based on viangular factorization of the gain matrix can be applied to the three-phase SE without major moditications. If any zero pivot is encountered during the factorization of the gain malrix. it indicates that the corresponding sme variable is not observable. In the three-phase formulation, the zero pivot may correspond to one specific phase of a bus. This numerical observability algorithm can be extended to suggest additional meter placement. 4. TEST RESULTS AND DISCUSSIONS The described distribution system SE formulation has been tested by using three feeders in the TPC disvibution system. Table 1 shows the peninent data of these feeders. Note tha each bus of the feeder involves 3 single-phase pseudo measurements and 3 single-phase line flow or current magnitude real-Lime measurements if there is an Flll at the bus. The average rlx ratio of the line is 1.88. The impedance and admimce matrices, given in ohm/mile, are as follows: then 1 b r n e - P = lIbmea I (1hCal I IIhcall) = Re(Ihmea-W) + j h(1hmea-W') 1 (10) ad v k r n a q v = lvkmea I (vkcal / Ivkcall) = Re(Vkmeaeqv) + J h(Vkmea-eqv) 2.7834 + 11.4794 0.2352 + 10.6561 0.2334 + j0.5827 0.2352+p.6561 2.7871 +jl.4761 0.2352+p.6561 0.2334 +j0.5827 0.2352 + j0.6561 2.7834 + 11.4794 0.2951 -j0.1297 -0.0597 -p.0136 -0.0538 -p.0071 (11) By using Equations (5). (7). (9) and (IO) we can convert power measurements and current magnitude measurements into their equivalent currents. Based on equivalent currents the Jacobian tern are constant and equal to the admittance matrix elements. The equivalent currents of the measurements 1mea-W. calculated currents IC', measurement Jacobian matrix H, and the covariance matrix R are used to compute the right-hand side vector of Equation (3). In addition to power and current measurements, the voltage magnitude measurements, Equation (11). can also be used. The first derivative of equivalent voltage expressed in rectangular form with respect to the state variable is unity. Based on constant Jacobian matrix H, the gain matrix HTR-lH is constant, and it needs to be built and factorized only once. Great improvement in the SE execution time can be obtained by using this new scheme. Figure 7 shows the flow diagram of the proposed three-phase SE algorithm. -0.0597 -j0.0136 -0.0538 -p.0071 0.2956 -j0.1261 -0.0598 -10.0136 -0.0598 -j0.0136 0.2952-p.1298 Table 1: Measurement and Feeder Data 1 I 1 1 I Feeder No. of No. Buses Length No.of FlU's I No. of Pseudo MeasurementS 93 48 48 ~ I No. of Actual Measurernents 12 18 1 234 Estlmatc pseudo measurcmcnts at distnbuuon bansformers & Assign weights for pseudo mCaSurcments 4 Use equations (5).(7).(9),(IO).( I t ) IO convert mcaswmcnts data into equivalent mcajurements expressed in rectangular form Jm Compute and factorize the gain matrix nght-hand side vector of equauon (3) + Solve equation (3) and update (X,Y) A, SE formulation (method 3) has the best performance in all tests conducted. Iteration number required by the decoupled version is higher. Test results indicate that the decoupled formulation has difficulty in handling current magnitude measurements. Fully coupled formulation is more stable than the decoupled formulation. It is also shown in Table 2 that if the measurement set includes current magnitude measurements, all three formulations require a higher execution time to obtain the solution. This is due to the lack of phase information in the current magnitude measurements. During the testing of the proposed method, it was found that if the current magnitude measurements that have high weights are involved. a special procedure should be followed when a flat s m is used. From equations (9) and (10). i t can be seen that the equivalent complex currents obmned from a flat start would be far away from the solution. this might result in a convergence to an incorrect solution. To resolve this problem, a tentative solution obtained by greally reducing the weights of current magnitude measuements in the first and second ilerations of SE, is found first. After that the weights of current magnitude measurements are restored back to their original values, and the solution procedure continues. For instance. in Table 3, for the case of 60 bus system with current measurements, i t requires two iterations to obtain the tentative solution and another three iterations to get the final solution. In this case. the gain matrix needs to be built and factonzed twice. Using this procedure. it seems that method 3 handles current magnitude measurements more effectively than other methods. The above mentioned procedure is not required if no current magnitude measurement is involved or when a previous SE solution is available. Table 4 shows the final J(X) values of the reponed cases. Since method 3 has converted the power measurements into the equivalent current measurements. the equation used to calculate the J(x) is redefned as: Figure 7: Flow Diagram or the Proposed Algorithm The measurement data are simulated by using a three-phase load flow solution. Noise is added to each measurement and weights of measurements are given. Noise is added randomly to the actual and pseudo measurements and is at the ranges of *IO% and f30% respectively. Two different weights are given to the measurements, one for the actual measurementsand the other one for the pseudo measurements. The weights are 1/3 and 1/50 respectively. Three different methods are tested, they are : Method 1 : Fully coupled version of normal equation method expressed in polar form. Method 2 : Decoupled version of normal equation method expressed in polar form. Method 3 :The proposed current based method. In method 2, tbe gain matrix is approximated by a block diagonal matrix, i. e. ignoring the off-diagonal terms to get the decoupled gain matrices correspondingto real and reactive power, thus, decoupling the angle and voltage components. Various tests which use different types and numbers of measurements are conducted. Some of them are reported here. Tests are conducted on a SUN IPC workstation. Tables 2 and 3 show the normalized execution time and number of iterations required in each case.NC indicates the non-converged case. In addition to voltage magnitude measurements, two types of actual measurements are tested, they are the power flow measurements and iurrcnt magnitude measurements. The execution time of method 3 with P, Q measurements is used as a reference and normalized to 1. It can be seen from Tables 2 and 3 that the current based The a's used in the above cquauon are computed from a's of real and reacuve power measurements Table 5 shows the deviauons of the estimated solution from the load flou solution which is used to probide the measuremen1dam The demauon is defined as where PkmSe is Ihe estimated branch flow and pkmload is the corresponding value in the load flow solution. I t should be reminded that since measurement noise is included randomly iii the measurements. 2 1070. and 230% respectively for actual and pseudo measurements, thc final SE solutions will not be the same as the load flow solution. The results shown in Table 5 indicate that even with only the pseudo measuremen& the proposed algorithm can provide an S E solution. However, due to the low accuracy of me pseudo measurements. the solution is bad when we compare i t with the base case load flow solution. This estimated solution can be improved by adding real-time measurements to the measurement set. As can be seen from Table 5, cases with higher number of actual measurements have lower deviations, i.e.. they match more closely with the assumed real-time solution. Test results have indicated that when current magnitude measurements are involved, due to the lack of phase information. the deviations are higher, but the percentage differences between different methods are still small. To verify that all three formulations have the simi!ar solutions, using the solution obtained from method 1 as a reference. we compute the summation of differences in branch flows of solutions obtained from different methods. It was found that the differences of the case of 60 bus system with only pseudo measurements are within 1.1%. When the real-time measurements are added. the deviations are within 0.4%. This result indicates that the three tested methods did not converge exactly to the same solution, but they have very similar solutions. With the aid of the actual measurements the proposed distribution system SE is able to provide a load flow solution for real-time operation. An accurate real-time update of the bus load forecast can also be performed by using SE solution. It can be seen from Figure 5 that the gain mamx is sparse, thus, sparse maUix technique should be used in solving the problem. Since individual feeder SE can be handled separately and the problem size is generally small, the distribution system SE can be performed on smaller machines or processed simultaneously by different machines. The tests are also conducted on a 486 PC and similar results have been obtained. Table 2: Normalized Execution Time -mcnts p,~' 15 BUS Plows 1.900 1.900 ancal+ 1.450 1.000 4 1.450 1.050 2.150 6 2.150 6 3.100 PE PE PO' 2.071 1.119 1.000 5 N0.M Actual Metbod measure 1 Method 2 Metbod bU6CS N0.M Fmr 3.050 Execution 3 Soluliaos wtlb only p c u d o Solutlws wilh re~l-lmmcand pseudo mesiurernenli Method M e l b o d M e ~ D o d M i l h o d I 1 2 3 12.514 14 I14 13.584 % e % 12.514 14 I 1 4 13 SU4 e e e measuremenis Melhod Mclbod Number 2.224% 3 2.195% OlFrLIS I82S8 11126 2.1WB 2.0378 10 2 5 4 No. of Ilcralioas 7. REFERENCES 60 Bus Rows 2 I IO cumcot+ 6 6 1 NI K I I I 2 5 10 5 IO 5 F. F. Wu. "Power System State Estimation: A Survey," Electrical Power & Energy Systems, Vol. 12, No. 2, April 1990. M. B. Do Coutto Filho. A. M. Leite da Silva, and D. M. Falcao, "Bibliography on power system state estimation (1968-1989)," lEEE Trans. on Power Systems. Vol. 5, No.3 Aug. 1990. A. Bose, and K . Clements. "Real-Time Modeling of Power Networks." IEEE Proceedings, pp. 1607-1622. Dec. 1987. K. I. Geisler, "Ampere Magnitude Line Measurements for Power System Stare Estimation," IEEE Trans. on Power Apparatus and Systems, Vol. PAS-103, No. 8, Aug. 1984. D. I. H. Sun, Distribution System Loss Analysis and Optimal planning, Ph. D. Dissertation, University of Texas at Arlington, May 1980. D. I. H. Sun, S. Abe, R. R. Shoults, M. S . Chen, P. Eichenberger, D. Farris, "Calculation of Energy Losses in a Distribution System," IEEE Trans. on Power Apparatus and Systems, Vol. PAS-90, No. 4, pp. 1347-1356, July/Aug 1980. N. Vempati, R. R. Shoults. M. S . Chen, L Schwobel, "SimplifiedFeeder Modeling for Load Flow Calculations," IEEE Trans. on Power Systems, Vol. PWRS-2, No. 1, Feb. 1987, pp. 168-174. T.-H. Chen, M.-S. Chen K.-J. Hwang, P. Kotas, and E. A. Chebli, "Distribution System Power Flow Analysis A Rigid Approach," LEE Trans. on Power Delivery, Vol. ,NO. 3, July 1981, pp.1146-1152. K. A. Birt, J. J . Graffy, J. D. McDonald, and A. H. ElAbiad," Three phase load flow program," IEEE Trans. on Power Apparatus and Systems, Vol. PAS-95, No. 1, Jan/Feb 1976, pp. 59-65. M. E. Baran, F. F. Wu, "Network Reconfiguration in Distribution System for Loss Reduction and Load Balancing," IEEE Trans. on Power Delivery, Vol. 4, No. 2, pp. 1401-1407, 1989. C. C. Liu, S. 1. Lee, K. Vu, "Loss Minimization of Distribution Feeder: Optimality and Algorithm," IEEE Trans. on Power Delivery, Vol. 4, No. 2, pp. 1281-1289. 1989. H. D. Chiang. R. J. Jumeau, "Optimal Network Reconfigurations in Distribution Systems: Pan 1: a New Formulation and a Solution Methodology," IEEE Trans. on Power Delivery, Vol. 5, No. 4. pp. 1902-1909, 1990. C. S. Chen, and M. Y. Cho, "Determination of Critical Switches in Distribution System,'' IEEE Trans. on Power Delivery, Vol. 7, No. 3, July 1992. pp. 143-1449, "Distribution Automation: A practical tool for shspinp a more profitable future," Special Report, Electrical World, Dec. 1986, pp. 43-50. F. F. Wu and A. F. Neyer, "Asynchronous Distributed State Estimation for Power Distribution Systems." Proceeding of 10th Power Systems Computation Conference, Aug. 1990. I. Roytelman, and S. M. Shahidehpour, "State Estimation for Electric Power Distribution Systems in Quasi RealTime Conditions," EEE paper 93 WM 090-1 PWRD. F. Mafaakher, A. Brameller, J. F. Bermudez, "Optimum metering design using fast decoupled state estimator," IEEE Trans. on Power Apparatus and Systems, Vol. PAS98, Jan. 1979, pp. 62-68. K. A. Clement, G. R. Krumpholz, P. W. Davis, "Power system slate estimation with measurement deficiency: an observability measurement placement algorithm," IEEE Trans. on Power Apparatus and Systems, Vol. PAS-102, July, 1983, pp. 2012-2020. M. K. Celik, and W.-H. E. Liu, "A Meter Placement Algorithm for the Enhancement of State Estimation Function in an Energy Management System," Paper prepared for the Third International Symposium on Electricity Distribution and Energy Management, 1993. A. Monticelli and F. F. Wu, "Network Observability: Identification of Observable Islands and Measurement Placement," IEEE Trans. on Power Apparatus and Systems, Vol. PAS-104, May 1985, pp. 1035-1041. K. A. Clement, G. R. Krumpholz, and P. W. Davis, "State Estimator Measurement System Reliability Evaluation - An Efficient Algorithm Based on Topological Observability Theory," IEEE Trans. on Power Apparatus and Systems, April 1982, pp. 997-1004. Chan-Nan Lu received B.S. degree from National Taiwan University, M.S. degree from Rensselaer Polytechnic Institute, and Ph. D. degree from Purdue University. He has held positions at General Electric Co. Pittsfield. Mass., and Harris Corp. Controls and Composition Division, Melbourne, FI.. Currently. he is with Department of Electrical Engineering. National Sun Yat-Sen University, Kaohsiung, Taiwan. He is a senior member of IEEE. J. H. Teng received his BS and MS degrees froin National Sun Yat-Sen University in 1991 and 1993. Currently, he is pursuing his PH. D degree in the same University. W.-H. Edwin I.iu received the B.S. degree from National Taiwan University in 1981, the M.S. degree in 1984 and Ph.D. degree in 1987 bo& from the University of California Berkeley, in Electrical Engineering and Computer Sciences. He was a research assistant at U. C. Berkeley from 1983 to 1987 and worked for Bonneville Power Administration during the Summer of 1986. From September 1987 to June 1991, he worked for Empros Systems International as a Senior Engineer in the Network Applica*ion group and developed solfware for power system computer applications. Since J u l y 1991, he has been with the Applications and Systems Integration Department of PG&E where he is respondible for several research and development projecls in both analytical melhodology and computer applicauons. Dr. Liu also leaches graduate courses in the Engineering Division of San Francisco S w e University. 237 DISCUSSION Siemens Energy Br Automation, Plymouth, SLUTSKER, Minnesota. W.F. TINNEY. Consultant, podand, Oregon: The authors are congratulated on the development of a new method of Slate estimation for distribution svstems. we would like to s o k i t In the authors' method. power flow measurements are translated into equivalent current values that are then used in the state estimator solution. While it is easy to convert power measurements into currents. it is much less clear how to compute weights of current measurements to ensure that the solutions of the original and derived problems are identical. It can be shown that, if real and reactive power measurements have different weights, the error terms in real and imaginary components of the derived currents are distributed normally with variances which are functions of voltage components used in current computation. This means that weights of current measurements, which must be computed as inverses of variances to guarantee the equivalence between the original and derived formulation. will fluctuate between iterations and the gain matrix will no longer be constant.. The need to recompute and refactorize the gain matrix in each iteration will make the proposed method no more advantageous than the fully coupled formulation. Of course, the gain matrix can be held constant at some value of current measurement weights, and this will produce a solution but it won't be the solution of the original problem. It appears that the authors used measurements with equal weights of real and reactive components in their tests. This, however, will not be true in many practical situations. How do the authors intend to deal with cases bf unequal weights of real and reactive measurements? Can the authors explain their approach to the calculation of weights of the derived currents? Again, the authors are commended on a new method of solving a state estimation problem. Their answers to our questions will be awaited with great interest. Manuscnpl received February 17, 1994 of the transmission systems weighted least square state estimator method to distribution systems. Distribution systems control and operation have fundarnedtal differences with t h k e of transmission systems which make it diffcult to apply the transmission Systems state estimation techniques directly to distrihution systems. The differences include unbalanced conditions, current magnitude measurements and the applications of historical (statistical) load data as pseudo measurements. The authors have proposed reasonable ideas and proved by test results that the p r o p i d ideas work. We have a few questions and comments regarding the practical implementation of the proposed method and presented results. 1. Modeling of unbalanced distribution systems: The authors have based their algorithm on three wire presentation of four wire systems. The elimination of neutral wire may he. done according to [a], using one of the following two methods. the first one, refereed to as the Kron reduction method, makes an assumption that the ground wire is at zero potential at both ends of a branch (feeder section), or, zi,* znj I ,z The second method, refereed to as the neutral return reduction method, makes the assumption that the return current follows the path through the neutral and all loads are grounded, or, muation These have Opposite impacts On the (1) decreases self impedances slightly and decreases mutual imoedances simificantlv. Euuation 121 increases both series and m;tual impedances. Hdwevir, some bi the simplifying assumptions may not work for practical Cases. Neutral wire may not always represent zero potential, and there are delta connected loads in every distribution feeder. In general, unbalanced 4-wire distribution systems should be simulated as 4 wires without elimination of neutral wire using a 4x4 matrix 2. Branch current magnitude measurements: Wayne Hong Opercon Systems, Inc : The authors are to be commended for their interesting development of DSE. This paper presented a thorough mathematical framework and described some potential applications, including those for real-time operation. I would appreciate if the authors can comment on the following: I ) A separate paper [AI in the '94 Winter Meeting also described DSE. How do these two paper differ in their approaches and applications? 2 ) In most distribution systems, there are never enough real-time measurements. As such, the networks are in general not observable. You have suggested to use historical data as pseudo measurements. Could you quantify the relationship between mors in the historical data and those in the resulted system states obtained from DSE? 3) According to your paper, a DSE with added real-time readings can provide a better estimate of the state of dishibution system operation. How does DSE then fit into the overall goal of Distribution Automation? [AI M.E.Baraa A.W. Kelley, "State Estimation for real-time Monitoring of Disnibution Systems". 94 W M 235-2 PWRS The problem with current magnitude measurement is that the only way we can obtain current angle is to use preliminary power flow results based on load pseudo measurements. Our experience with this method indicates that the weight coefficients for current magnetite and angle should be different as magnitude is directly measured and is more reliable, however, angle is estimated using historical data. Another problem with weights for current magnitude is that they are less than weights for active and reactive power measurements in distribution substations, as the corresponding power is determined by state estimation in transmission systems. 3. Weights for pseudo measurements: The authors use different weights for real and pseudo measurements. But for different type pseudo measurements different values of weights are to he used. Another observation is that loads (pseudo measurements) power factor is more reliable than active power or current magnitude. The power factor is used as a measure of results (loads) feasibility and should be kept within its permissible range [b]. Manuscnpl received FCbruary 24, 1994 4. Proposed simplifications: I. Roytelman (SiemensEmprus) and S.M. Shahidehpour (Illinois Institute of Technology)-- The topic of this paper is extremely important from the standpoint of future development of distribution management systems. The authors have proposed the implementation The authors assume that the phase angles of voltages are less than 10 degrees. Our experience with distribution systems indicates that this assumption is correct only for the primary voltage level and in cable systems. Since loads are connected to the secondary voltage level, distribution transformers voltage drop should be. taken into account. In heavily loaded overhead lines, line voltage drop gives additional angle shift. These assumptions may provide a more simple model for 238 distribution systems, however, the simulation results may turn out to be different from actual practice. Let 5. Test results: Test results are presented for relatively small systems. To our knowledge, it is better to apply state estimation to portions which are supplied from distribution substation transformers rather than feeders. The reason is that p e r flows are measured at substation transformers and current magnitudes are measured at corresponding feeders. O n the average, one feeder supplies 150-200distribution transformers and the number of feeders connected to one substation transformer is 7-10. So the average size of a portion entails to 1500-2000transformers. If we consider unbalanced conditions as well, the state estimation problem will be a complicated problem for distribution systems and it would be interesting to see the results of the proposed techniques on more practical cases. The authors should be congratulated for a well-written paper on distribution systems. [a] IEEE Tutorial on Power Distribution Planning, 92 E H 0 361-6PWR. p] I. Roytelman and S.M. Shahidehpour, "Practical Aspects of Distribution Automation in Normal and Emergency Conditions," IEEE Trans. on Power Delivery, Vol. 8, No. 4,pp. 2002-2008,October 1993 Manuscript receivrd March 4, 1994. C. N. Lu, J. H. Teng and W. H. E. Liu : W e wish to thank the discussants for their interest in our paper and thoughtful comments. In the following, we will respond to each of the discussants' comments. Messrs Slutsker and Tinney In order to obtain a constant Jacobian matrix and to incorporate current measurements in the formulation, all measurements are converted into equivalent current measurements. The advantage of the formulation has been clearly shown in the test results of the paper. The conversion process is explained in further detail in the following. As we have stated in the paper, at each iteration, the equivalent current measurements are calculated based on the active and reactive power measurements and the solved voltages from the previous iteration. Assuming that the complex voltages used in the conversion are deterministic and the active and reactive power measurements are statistically independent, then, the variances of the converted complex currents can be derived as follow: Var(Re(Iimea-eqv)) = Var(aPimea+bQjmea) = a2Var(Pimea) + b2Var(Qimea) ('44) Var(Im(Iimea-eqv)) = Var(bPimea-aQimea) = b2Var(Pimea) + a2Var(Qimea) (A3 In the case where Var(P) = Var(Q), the equations can be simplified as Var (Re(Iimea-eqv)) = Var(Pi)Ni2 = Var(Pi) (A6) VW (Im(Iimea-eqv)) = Vw(Qi)Ni2 = Var(Qi) (A7) In our implementation, by using a distribution system load flow or a previous state estimation solution, an initial set of e and f is obtained. This set of e and f is then used to compute the variances of equivalent measurements and form the gain matrix. The gain matrix is kept constant while the right hand side of equation (3) in the paper are computed by the solution from the previous iteration including the weights. Note that the weights for the measurements are set to be equal to the inverse of the variances. Strictly speaking, the voltages used in the calculation of the right-hand-side vector of equation (3) do carry certain randomness through the iterative process. However such randomness is neglected in the traditional WLS state estimation. The variance of each component of the vector [z-h(xi,yi)] is assumed to be equal to the variance of the corresponding component of z, i.e. Var(Zk-hk(Xi,Yi))'Va(Zk). This is based on the assumption that xi and yi from the previous iteration are deterministic, and hence h(xi,yi) is deterministic. Such assumption has been widely accepted in practical implementation. Similarly, in our derivation of equivalent measurement variances, the voltages are considered as deterministic. Statistically, with the approximated variances, the estimator is still an unbiased estimator. Practically, we think, it is not necessary to get into detailed derivation for the randomness in the nonlinear 239 iterative process. Based on our experience, slight approximation in the variances (i.e. weights) does not affect the estimation solutions too much. In order to validate the approximation, a 15-bus system example is tested under various conditions, and results are shown in the following Table. ~~~~ ~~ ~~~ ~ Method 1 -Weights -15.7151 P5a,mea- p=2 Q=2 est P~~ Q5a p5= mea--3.10072 P=20 Q.20 P5aest QSa P.200 Q=20 est est Psa est Q5a est Method 3 14.20619 P5aest 2.45973 Q5= est = 2.47091 = 14.70647 PSaest - 14.7011 = 2.67225 Qsaest = 15.48135 P5aest =15.47671 = 2.67230 Q5aest =2.68651 ~ = = 14.2041 ~ = 2.68437 mea: measurement est: estimated value Methods 1 and 3 correspond to the fully coupled polar form method which uses the original measurements and weights, and the proposed current based method, respectively. Method 3 uses the above mentioned method to determine the weights of equivalent measurements. As can be seen from the Table, for both methods, when the original weights are increased (variances are decreased) the estimated injections match the measurements more closely, and their results are very similar. Resembling results are observed at different phases and nodes of the feeder. These results indicate that the measurement and weight conversion is properly handled by the proposed method. Mr. Wayne Hong 1. Both [A] and our paper use weighted least square technique and a three-phase model to estimate the distribution system states. The major difference between these two papers is in the approach used to obtain the constant gain matrix. In [A], some approximations and transformation are used to simplify the Jacobian matrix while in our method, constant Jacobian matrix is obtained by converting power measurements into equivalent currents and expressing bus voltages in rectangular form. Both methods are designed to provide an estimate of the real-time system states for distribution system operation. 2. Due to the cost of measurement and communication equipments, real-time load data of each node in the feeder are not available at the present time. Load data are often obtained based on historical data collected by utilities. Since these data are used in the estimation process, thus, the accuracy of load data affects the estimation of the real-time system states. Based on some assumptions on the measurements and load data, Table 5 provides some quantitative results of the errors existing in the historical load data and the estimated results. 3. State estimation can provide a good estimate of the system states that can then be used by many distribution automation applications, such as feeder reconfiguration, v o l t a g e h a r control, etc.. T h e usefulness of these applications requires a reasonable accurate estimate of the system states. As can be seen in the paper, the quality of the forecasted load data are improved by the distribution state estimation using available real-time measurements. The state estimation can be used to check the validity of the forecasted load and to make necessary corrections. Hence, the system states provided by state estimation is better than what is available from an off-line power flow study. Furthermore, if more real-time measurements become available in some key locations and the distribution network becomes observable, the system states can be estimated directly from the real-time data. This can highly improve the solutions of all network applications. A fully automated distribution system may become feasible. Drs Roytelman and Shahidehpour 1. We agree that different model should be used if the line under study does not have a multi-grounded neutral which is the basic assumption of the Kron reduction method adopted in this paper. 2. In our method the current magnitude measurements are treated as regular measurements except for the special treatment in a flat start case. The estimated phase angles of the corresponding branch currents are obtained at each iteration of the estimation process. W e did not use current phase angle measurements in the estimation. 3. U n d e r t h e c i r c u m s t a n c e s that r e a l - t i m e measurements are not sufficient for a state estimation, any available historical data related to the feeder loading should be used as pseudo measurements. Certainly, due to different confidence on various histoiical data, different weights are given to different types of data. Since weight disparity has beeil identified as one of the factors that could cause numerical problems in state estimation. The effects of weight assignment should be carefully investigated. In this paper, we do not explicitly address the issue of weight assignment. The purpose of the paper is to present an effective formulation to solve distribution system state estimation. Further research and development in many important subjects in this area, such as meter placement, observability analysis, bad data processing, weights selection, etc., are certainly welcome. 4. In this paper we did not assume that the phase angles of voltages are less than 10 degrees. 5. To be useful in the feeder automation, we tested the proposed method on individual feeder. Since data 240 accuracy and sufficiency of different feeders may be different, the strategy used in this paper is to estimate the states of all feeders sequentially one after another. Therefore, the test system size is relatively small. If sufficient data are available then a complete state estimation covering all feeders simultaneously can be performed. Once again the authors would like to thank all the discussants for their comments and contributions. Manuscript received April 29, 1994