Approved UNIVERSITY OF ESSEX PROJECT COORDINATION GROUP 24 October 2013 (2pm – 4pm) MINUTES Chair Bryn Morris (OBM) Present Marc Albano (MA), Nicola East (NE) (permanent replacement of Vanessa Potter), Emma Hardy (EH), Richard Harrison (RH), Zoe Manning (ZM), Richard Murphy (RM), Linda Pearsall (LP) (replacing Jo Andrews), Tracy Robinson (TR), Richard Stock (RS), Sonia Virdee (SV) Secretary Clare Hornsby (CH) 1 Apologies Noted 2 256/13 Minutes of the last meeting, 18 September 2013 (PCG/13/52) Agreed 3 Jo Andrews (JA), Bernarde Hyde (BH), Jane Wright (JW) The minutes from the 18 September 2013 meeting of PCG were approved as a correct record of the meeting. 257/13 Matters arising from the minutes (PCG/13/53) Noted The matters arising from the 18 September 2013 meeting of PCG were approved as correct and progress was noted. 258/13 4 An update on the development of an institutional business process review capacity (PCG/13/54) Noted Agreed The proposed programme of activity was noted. It was suggested that the new course approval process should be added, as a lean review in this area might improve the synergies between contributing departments. The Group noted that the course approval process had already been revised for 2013-14, and as such, a further review at this point might not be appropriate. 259/13 The SOFACX project had considered the new course approval process from a course marketing-dataflow perspective, rather than a full process review looking at all elements of the process. An IT solution had been recommended to deliver the desired process improvements, however this was not progressed as the required resources were not available. It was suggested that a number of issues could be addressed through the delivery of an interim solution. 260/13 Capacity within the Change Hub and departments would limit the number of lean reviews that could be successfully delivered in 2013-14. Two bespoke lean reviews had been identified. Case studies would be developed to help communicate the benefits of lean, which would be important going forward. 261/13 The Education and Research action plans may highlight additional lean review opportunities. 262/13 In addition to the proposed programme of activity, many departments would review their processes less formally throughout the academic year. 263/13 The Education and Research action plans should be considered for the purpose of identifying additional lean review opportunities 264/13 Action: RH 3 Potential issues for consideration in a lean review of the course approval should be identified, and the value of conducting such a review in 2013-14 should be discussed with the Academic Section. 265/13 Action: EH/NE/RH PCG endorsed the approach to undertaking institutional business process reviews. 266/13 5 2013-14 SUMS reviews (PCG/13/55) Noted Agreed The SUMS reviews for 2013-14 were confirmed and it was noted that 50 days of SUMS consultancy was required against a normal entitlement of 40 days. 267/13 The SUMS work on the shape and structure of the academic year would largely focus on gathering data to help identify the options and opportunities available to the University, which could inform any development or review of the academic year that the University might subsequently choose to undertake. 268/13 At the September 2013 meeting of PCG it had been suggested that SUMS should provide some consultancy support to the data governance project. A five day project specification was required. 269/13 There were synergies between the occupational health project, the opportunity and client management project and the SUMS review of student placements. These should be explored further. The student placement review would benefit from consultation with HHS on matters relating to employability. 270/13 The Academic Registrar should ensure that HHS is consulted in relation to the student placement review. 271/13 Action: Stephen McAuliffe (SM) A five day project specification should be drawn up in relation to the data governance project. 272/13 Action: MA The data governance project should be added to the list of SUMS reviews scheduled for 2013-14. 273/13 Action: RH 6 Progress report on the Strategic Projects Portfolio (SPP) (PCG/13/56) Noted All approved projects were progressing well and had been assigned green or amber ratings. This positive state of affairs was in part due to the adoption of a more stringent approach to the approval of projects for implementation. A number of projects were also nearing completion and it was expected that this should increase capacity to undertake new projects. 274/13 There was a need to communicate the importance of forward planning, together with the benefits of working with PCG to deliver strategically important projects. Projects could be proposed to PCG significantly before they were due to commence. Such advanced preparation supported effective management of the SPP as a whole, and of resources. 275/13 A number of project progress reports had been submitted to the September 2013 meeting of CBSSG, all of which had been assigned green or amber ratings. 276/13 Although the Student Projection and Analysis Model project (SPAM) had reported an amber-red rating, the majority of the required functionality had been delivered. A project closure report was expected to be available for consideration at the December 2013 meeting of PCG. 277/13 4 Agreed The proposed revised reporting schedules and estimated delivery dates for projects 1214, 1219, 1221 and 1262 were considered. 278/13 The method by which project extensions were requested was still in the process of being embedded. Requests would continue to be detailed in future SPP progress reports. 279/13 The Internal Communications Officer should be contacted and asked to provide a list of opportunities for promoting projects that were successfully delivered under the guidance of PCG. 280/13 Action: CH Case studies of projects that were successfully delivered with the support of PCG should be considered at a meeting of the Change Network. 281/13 Action: RH/CH The annual report to USG should communicate the successful delivery of projects. 282/13 Action: RH The proposed reporting milestones for projects 1219, 1221 and 1262 were approved, as were the revised completion dates of projects 1214, 1219 and 1221. The SPP should be updated. 283/13 Action: CH 7 Requests for Project Mandate a) The criteria for determining a projects priority ranking (PCG/13/57) Noted The criteria for determining a projects priority ranking was noted. 284/13 Agreed Grid references should be added to the chart for improved ease of reference. 285/13 Action: CH b) KPI Reporting - Phase 2 (PCG/13/58) Noted Agreed It was confirmed that the scope of the project had been narrowed in response to feedback from PCG. 286/13 It was originally anticipated that the £20,000 consultancy fees would be drawn from the ISS budget, however it was not clear whether the availability of this funding had been confirmed. This would need to be resolved before the project would be approved for implementation. 287/13 Thought had already been given to the third phase of the project, which would endeavour to improve the system architecture and interface. 288/13 The Group discussed the strategic contribution and time criticality of the project for the purpose of determining a priority ranking. Although the project would improve the production of, and accessibility to KPI data, it was acknowledged that the current system could continue to produce the necessary data despite employing sub-optimal methods. 289/13 The project be mandated and assigned a score of three for strategic importance, and two for time criticality. 290/13 The outstanding budgetary issue should be considered and addressed as a matter of urgency. 291/13 Action: SV/RM 5 c) Occupational Health (PCG/13/59) Noted Agreed 8 The £45,000 required to deliver the project was not currently available within the Human Resources revenue budget for 2013-14. This issue would need to be resolved before a full project proposal was brought forward for consideration for approval for implementation. 292/13 Consideration should be given to the boundaries of the Occupational Health system, and the initial and on-going requirements for integration and interface between existing corporate systems. 293/13 The system had the potential to support other health and employment related activities and this should be considered. 294/13 The project was mandated with a 2-2 ranking for strategic contribution and time criticality. 295/13 Projects for Approval for Implementation a) Opportunity and Client Management System (PCG/13/60) Noted Agreed 9 The project proposal was considered at the September 2013 meeting of CBSSG. The Group agreed that the project should be endorsed to PCG for approval for implementation, subject to slight amendment. The list of stakeholders was subsequently extended to include a Faculty Employability Coordinator. 296/13 Concerns were expressed as to how employer engagement would be measured; it was suggested that qualitative data could be an appropriate indicator in this instance. 297/13 The project was approved for implementation. 298/13 Reports on completed projects a) e-Portfolio Noted Agreed The project closure report had been circulated electronically to members of ASSG for consideration and referral to the October 2013 meeting of PCG. The decision was taken to delay the submission of the closure report to allow further discussion between members of ASSG. It was indicated that ASSG was considering recommending that that project should be suspended rather than closed, although a final decision was still to be made. 299/13 In line with the University’s Project Management Framework, PCG advised that the project should be closed. 300/13 A project closure report should be submitted to the December 2013 meeting of PCG for consideration for approval. 301/13 Action: Elizabeth Guyar-Brown (EGB) 10 Any Other Business Noted It was important to develop and maintain clear and consistent channels of communication between PCG and its sub-groups. 302/13 Agreed The Chair of ASSG should be contacted to discuss the regular attendance of an ASSG representative at future meetings of PCG. 303/13 Action: OBM 6 11 Date of Next Meeting Noted 05 December 2013, 2pm to 4pm in the Vice-Chancellors Boardroom. Clare Hornsby Project Officer Strategic Planning and Change Section October 2013 7 304/13