STATE OF VERMONT PUBLIC SERVICE BOARD Petition of Vermont Transco, LLC, and Vermont Electric Power Company, Inc. (collectively, “VELCO”), and Central Vermont Public Service Corporation (“CVPS”) for a Certificate of Public Good, pursuant to 30 V.S.A. § 248, for the “Southern Loop Project,” located in Vernon, Guilford, Brattleboro, Dummerston, Newfane, Brookline, Townshend, Grafton, Windham, Andover, Chester, Ludlow and Cavendish, Vermont, consisting of the following elements: (1) a new, approximately 51-mile, 345 kV transmission line between Vernon-Cavendish, to be built parallel to and within the same utility right-of-way as VELCO’s existing Vernon-Cavendish 345 kV line; (2) a new VELCO 345/115 kV Vernon substation, to be located just north of the Vermont Yankee Nuclear Power Station; (3) a new 345/115/46 kV Newfane substation; (4) a new, approximately one-mile, 345 kV transmission line loop between the new Newfane substation and the new VernonCavendish 345 kV line; (5) expansion of VELCO’s Coolidge substation in Cavendish, Vermont; and (6) the implementing of incremental energy efficiency to defer transmission upgrades in Southern Vermont ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) Docket No. ____ PREFILED TESTIMONY OF RALPH ROAM ON BEHALF OF PETITIONERS November 8, 2007 The purpose of Mr. Roam’s testimony is to present the cost estimate for the Southern Loop Project. TABLE OF CONTENTS 1. Introduction ........................................................................................................... 1 2. Cost Estimate Summary ....................................................................................... 8 3. Cost Estimate Details ............................................................................................ 8 4. Cost Estimate Risks & Assumptions ................................................................... 9 EXHIBITS Exhibit Petitioners RR-1 Resume of Ralph Roam Exhibit Petitioners RR-2 Southern Loop Cost Estimate Summary Exhibit Petitioners RR-3 Milestone Schedule for Spending Plan Exhibit Petitioners RR-4 Cost Estimate Spending Plan Exhibit Petitioners RR-5 Handy-Whitman Cost Index Trend Exhibit Petitioners RR-6 Summary of Project Costs Under Three Different Commissioning Scenarios Exhibit Petitioners RR-7 Summary of Incremental Deferral Costs Exhibit Petitioners RR-8 Summary of Planned ISO NE and PJM Projects STATE OF VERMONT PUBLIC SERVICE BOARD Petition of Vermont Transco, LLC, and Vermont Electric Power Company, Inc. (collectively, “VELCO”), and Central Vermont Public Service Corporation (“CVPS”) for a Certificate of Public Good, pursuant to 30 V.S.A. § 248, for the “Southern Loop Project,” located in Vernon, Guilford, Brattleboro, Dummerston, Newfane, Brookline, Townshend, Grafton, Windham, Andover, Chester, Ludlow and Cavendish, Vermont, consisting of the following elements: (1) a new, approximately 51-mile, 345 kV transmission line between Vernon-Cavendish, to be built parallel to and within the same utility right-of-way as VELCO’s existing Vernon-Cavendish 345 kV line; (2) a new VELCO 345/115 kV Vernon substation, to be located just north of the Vermont Yankee Nuclear Power Station; (3) a new 345/115/46 kV Newfane substation; (4) a new, approximately one-mile, 345 kV transmission line loop between the new Newfane substation and the new VernonCavendish 345 kV line; (5) expansion of VELCO’s Coolidge substation in Cavendish, Vermont; and (6) the implementing of incremental energy efficiency to defer transmission upgrades in Southern Vermont ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) Docket No. ____ PREFILED TESTIMONY OF RALPH ROAM ON BEHALF OF PETITIONERS 1 1. Introduction 2 Q1. Please state your name, occupation, and business address. 3 A1. My name is Ralph Roam. I am employed by McMillin & Associates as a Capital 4 Project Consultant. I have been retained by Vermont Electric Power Company, Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 2 of 13 1 Inc. (“VELCO”) as the Project Manager for the Southern Loop Project 2 (“Project”). My business address is 366 Pinnacle Ridge Road, Rutland, Vermont 3 05701. 4 5 Q2. Please describe your education and employment background. 6 A2. I have a bachelor’s degree from Dickinson College in Policy Studies with a focus 7 in Private Sector Policy. I have worked in the utility industry since 1999 and held 8 numerous positions in the areas of Project and Contract Management, Asset 9 Management, and Operations. My resume is included with this filing as Exhibit 10 Petitioners RR-1. 11 12 Q3. What is the purpose of your testimony? 13 A3. The purpose of my testimony is to present and summarize the cost estimate for the 14 Southern Loop Project. 15 16 Q4. 17 18 Mr. Roam, please describe the approach for developing the Southern Loop Project cost estimate. A4. There are five (5) principal Project elements: 19 1) a 51 mile 345 kV line from Vernon to Coolidge; 20 2) a new 345/115/46 kV substation in Vernon; 21 3) expansions to VELCO’s existing Coolidge Substation; 22 4) a 1 mile 345 kV loop in Newfane; and 23 5) a new 345/115/46 kV substation in Newfane. Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 3 of 13 1 2 Our first step was to identify the resources required to plan, design, and construct 3 each of the five Project elements. The cost estimate was developed utilizing 4 seven (7) resources categories to establish the total cost for each Project element. 5 The seven (7) resource categories are as follows: 6 7 1) Material; 8 2) Labor; 9 3) Equipment; 10 4) Indirects; 11 5) Escalation; 12 6) Capital Interest; and 13 7) Contingency. 14 15 The Direct Costs were developed utilizing cost data from VELCO projects 16 recently completed or currently in progress. Specifically, cost data associated 17 with VELCO’s West Rutland to New Haven 345 kV line (the 370 Line) and the 18 New Haven and Granite substations were utilized to develop the material, labor 19 and equipment costs. Scopes of work for this Project for which VELCO did not 20 have recent actual cost data from its prior projects were estimated by PLM 21 Electric Power Engineering, Inc. (“PLM”), R.G. Vanderweil Engineers LLP 22 (“Vanderweil”), and Commonwealth Associates, Inc. utilizing cost data from 23 other projects recently constructed in the New England area. 24 Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 4 of 13 1 PLM and Vanderweil provided direct cost estimates for substation and 2 transmission line elements, respectively. Both companies were provided access to 3 VELCO’s actual costs data to develop material costs for each Project element. 4 Labor and equipment costs were estimated by the respective parties utilizing the 5 preliminary detailed designs discussed in the testimonies of Michael Barrett and 6 William F. McNamara. The detailed line items for each Project element were 7 estimated by the Federal Energy Regulatory Commission (“FERC”) code. 8 Developing the cost estimates by FERC code enhances VELCO’s ability to track 9 costs in a manner consistent with the reporting format of actual costs as required 10 by FERC. Also, escalation costs can be more accurately calculated by applying 11 the Handy-Whitman cost index to the estimated costs by FERC code. The 12 Handy-Whitman cost index is discussed later in this section of my testimony 13 where I present the method used to calculate Project escalation costs. 14 15 Upon receipt of the third party Direct Cost estimates, VELCO’s Project Controls 16 analyzed the estimates by comparing them to actual costs VELCO incurred for the 17 recently completed comparable scopes of work. Variances were addressed in 18 discussions between the third party firms, VELCO’s Project Controls and 19 VELCO’s Construction team to determine the most accurate approach on a case- 20 by-case basis. 21 Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 5 of 13 1 VELCO’s Project Controls developed the cost estimate for Indirects, Escalation, 2 and Capital Interest. Indirect costs are defined by Association for the 3 Advancement of Cost Engineering (AACE) as follows: 4 5 (1) Costs not directly attributable to the completion of an activity. Indirect 6 costs are typically allocated or spread across all activities on a 7 predetermined basis. 8 (2) In construction, all costs which do not become a final part of the 9 installation, but which are required for the orderly completion of the 10 installation and may include, but are not limited to, field administration, 11 direct supervision, capital tools, startup costs, contractors’ fees, insurance, 12 taxes, etc. Site: “Cost Engineering Terminology” No. 10S-90 AACE 13 14 15 Q5. Please summarize the process used to develop the Indirect Costs. 16 A5. The Indirect Costs were estimated based on the resources required to support the 17 completion of the Project by resource category. Resource categories included in 18 the Indirect estimated costs are: 19 20 1) Engineering and Design; 21 2) Operations; 22 3) Planning; 23 4) Communications; 24 5) Environmental Engineering; 25 6) Archeological Studies, Field Surveys, Impact Mitigation; 26 7) Aesthetic Impact; Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 6 of 13 1 8) Legal Expenses; 2 9) Regulatory Permitting and Filings, Administration, etc.; 3 10) Mobilization and Demobilization; 4 11) Direct Supervision – Project Management; 5 12) Construction Supervision; and 6 13) Project Support. 7 8 The Indirect estimated costs of project support services are based on the number 9 of people/hours (Level of Effort or LOE) required to support the particular 10 function as well as outside consulting services for each resource category (e.g. 11 archeology studies, engineering, and surveying, etc.). The legitimacy of the total 12 cost of Indirects was validated by calculating their relative percentage to the 13 estimated direct transmission line and substation Direct Costs. In recently 14 completed projects, VELCO’s Indirects for transmission lines range from 15 approximately 40-60% of the lines’ Direct Costs, and Indirects for substations 16 range from 20-40% of the substations’ Direct Costs. 17 18 Q6. How were Escalation costs developed? 19 A6. Escalation costs were developed by VELCO Project Controls utilizing an 20 anticipated 2007-2011 spending plan and projected Handy-Whitman cost index. 21 22 The 2007-2011 spending plan is based on the execution of activities required to 23 have the Project in service by the end of first quarter of 2011 to address reliability 24 issues as identified in Dean L. LaForest’s and Christopher Diebold’s testimonies. Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 7 of 13 1 The milestones’ schedule associated with this spending plan is attached in Exhibit 2 Petitioners RR-3, and the spending plan for Capital Interests and Escalation 3 calculation is presented in Exhibit Petitioners RR-4. 4 5 The Handy-Whitman cost index reflects the costs of different types of utility 6 construction, including electric transmission and distribution. The cost index 7 started in 1912, and is a widely recognized publication used by many entities in 8 the utility industry, including regulatory bodies, operating bodies, and valuation 9 engineering. The cost index conforms to FERC’s classification and follows its 10 categorization. Utilization of the Handy-Whitman index provides a yearly rate of 11 increase for specific cost categories in the utility industry instead of a generic 12 inflation rate such as the Consumer Price Index (CPI). Only Indirect costs were 13 escalated using CPI as the Handy-Whitman index does not provide information 14 on the Indirect costs. A graph showing the Handy-Whitman cost index trend 15 compared to CPI is presented in Exhibit Petitioners RR-5. 16 17 Capital Interest (Interest cost during construction) was applied at a yearly 18 compounded rate of 6% and follows the Project spending plan presented in 19 Exhibit Petitioners RR-4. The Capital Interest rate is based on the company’s 20 credit rating and is subject to change based on the financial market. 21 Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 8 of 13 1 The project cost estimate also accounts for a contingency of twenty-percent (20%) 2 due to the preliminary detailed designs and the uncertainty and risk associated 3 with the Project level of definition. Details are provided in section 4 of my 4 testimony. 5 2. 6 7 Q7. 8 9 Cost Estimate Summary What is the total cost estimate for the Project based on the various cost elements and resource categories described? A7. The total cost of the Project is estimated at $264,813,321. The total cost estimate 10 is comprised of $114,544,449 of Direct Costs, $51,269,359 of Indirect Costs, 11 $32,056,099 in Escalation, $22,807,861 in Capital Interest, and $44,135,553 in 12 Contingency. Please refer to Exhibit Petitioners RR-2 for a cost summary by 13 resource category and Project element. 14 15 16 3. Q8. Cost Estimate Details What is the design basis for the Direct Construction 345 kV Line estimates 17 associated with the 51-mile Vernon-Cavendish 345 kV line and the 1-mile 18 Newfane Loop? 19 A8. 20 The 345 kV Line Direct estimate is based on the Plans and Profiles as presented in Exhibit Petitioners WM-2 and WM-3. 21 22 Q9. What is the design basis for the Vernon substation Direct Construction estimate? Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 9 of 13 1 A9. The Vernon substation Direct estimate is based on the General Arrangement Plans 2 and the One-Line Diagrams as presented in Exhibit Petitioners MB-3, MB-4 and 3 MB-5. 4 5 Q10. What is the design basis for the Newfane substation Direct Construction estimate? 6 A10. The Newfane substation Direct estimate is based on the General Arrangement 7 Plans and the One-Line Diagrams as presented in Exhibit Petitioners MB-8, MB-9 8 and MB-10. 9 10 Q11. What is the design basis for the Coolidge substation Direct Construction estimate? 11 A11. The Coolidge substation Direct estimate is based on the General Arrangement 12 Plans and the One-Line Diagrams as presented in Exhibit Petitioners MB-13, MB- 13 14 and MB-15. 14 15 4. Cost Estimate Risks & Assumptions 16 Q12. What known factor(s) have the potential to impact the cost estimate? 17 A12. The timeframe in which the Project is executed has a substantial impact on the 18 estimated cost of the Project. As shown in the Handy-Whitman cost index trend, 19 Exhibit Petitioners RR-5, escalation costs for FERC codes associated with the 20 Project estimate increased at an average of 7.7% per year between 2004 and 2007. 21 Using the average yearly rate of increase between 2004 and 2007 from the 22 Handy-Whitman index for escalation as well as the incremental capital interest Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 10 of 13 1 and indirect costs, a project completion at the end of 2011 would result in an 2 estimated $26,097,999 of incremental costs compared to a project completion in 3 the first quarter of the same year. Furthermore, a completion of the Project at the 4 end of 2012 would result in an estimated $63,814,908 of incremental costs 5 compared to a completion at the end of the first quarter of 2011. Please refer to 6 Exhibit Petitioners RR-6 for the summary of Project costs under these three 7 different commissioning scenarios. 8 9 Temporary deferral of the Project is another risk that could potentially have a 10 significant impact on the cost of the Project. Temporary deferral of the Project is 11 considered herein to be a deferral of the Project for some period of time, but not 12 indefinitely. In order to estimate the incremental cost of temporary deferral, we 13 assumed that the Project would be stopped immediately effective December 31, 14 2008. The Project costs incurred to date would ultimately be carried and has been 15 included in the Project total estimated cost. No additional project development 16 costs are assumed to be added during the deferral period but for the cost of capital 17 interest during construction since the project need will remain. The incremental 18 Project cost of deferral was then estimated for a deferral of two (2) to five (5) 19 years using a three (3) year timeframe to complete the Project prior to the 20 assumed completion date. Again, using the extrapolation of the 2004 to 2007 21 Handy-Whitman index escalation rates in addition to incremental indirect and 22 capital interests cost, the estimated cost of Project deferral ranges from an Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 11 of 13 1 estimated $68,449,806 to $140,896,622 for a two (2) to five (5) year deferral, 2 respectively. Based on these estimated incremental costs of deferral, the total cost 3 estimates increases from $264,813,321 to $333,263,127 and $405,709,943 for a 4 two (2) to five (5) year Project deferral, respectively. Please refer to Exhibit 5 Petitioners RR-7 for a summary of the incremental cost of deferral. 6 7 Q13 What justifies the extrapolation of the 2004-2007 Handy-Whitman Index trend 8 assumption is valid to calculate Escalation costs in the Project cost estimate as 9 well as in the three (3) commissioning scenarios and in the three (3) deferral 10 11 scenarios? A13. In order to validate this assumption, a study was conducted on transmission 12 projects identified in the Independent System Operator of New England (“ISO- 13 NE”) service territory. The purpose of this assessment was to determine if 14 Escalation costs currently driven by the increased level of capital expenditures on 15 transmission infrastructure will continue. Exhibit Petitioners RR-8 provides an 16 overview of the projects planned in ISO-NE service territory. The EEI “Survey of 17 Transmission Investment, Historical and Planned Capital Expenditures (1999- 18 2008)” published in May 2005 further validates the assumption that increased 19 demand for resources associated with transmission infrastructure investments will 20 continue through at least 2008. The report sites a projected 60% or $28 billion 21 increase in transmission infrastructure investment for the 2004-2008 period Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 12 of 13 1 compared to the previous five year period. Exhibit Petitioners RR-8 depicts this 2 trend. 3 4 In addition, NERC projects that 12,873 miles of new transmission will be added 5 by 2015, an increase of 6.1 % in the total miles of installed extra high-voltage 6 (“EHV”) transmission lines (230 kV and above) in North America over the 2006 7 to 2015 period. NERC notes that this expansion lags demand growth and 8 expansion of generating resources in most areas. However, NERC’s figures do 9 not include several major new transmission projects proposed in the PJM 10 Interconnection LLC, such as the major new lines proposed by American Electric 11 Power, Allegheny Power, and Pepco. 12 13 Q14. 14 15 What risk elements were considered when developing the cost estimate and how were the risks addressed in the cost estimate? A14. Risk elements considered are the Project duration, level of certainty regarding 16 structure locations, required aesthetic, environmental, archeology mitigation 17 measures, higher escalation rate and potential resource constraints at the 18 anticipated time of construction. Per standard project management practices 19 widely recognized by organizations such as the Project Management Institute 20 (“PMI”), contingency was applied to the estimate to account for these risks. 21 Contingency is defined by AACE as: Southern Loop Project, PSB Docket No._____ Prefiled Testimony of Ralph Roam November 8, 2007 Page 13 of 13 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 [a]n amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, and/or effect is uncertain and that experience shows will likely result, in aggregate, in additional costs. Typically estimated using statistical analysis or judgment based on past asset or project experience. Contingency usually excludes: 1) Major scope changes such as changes in end product specification, capacities, building sizes, and location of the asset or project; 2) Extraordinary events such as major strikes and natural disasters; 3) Management reserves; and 4) Escalation and currency effects. Some of the items, conditions, or events for which the state, occurrence, and/or effect is uncertain include, but are not limited to, planning and estimating errors and omissions, minor price fluctuations (other than general escalation), design developments and changes within the scope, and variations in market and environmental conditions. Contingency is generally included in most estimates, and is expected to be expended. 17 As described in Section 1 of my testimony, a contingency of 20% was applied to 18 the total estimated cost based on the current level of Project definition. 19 20 Q15. Does this conclude your testimony at this time? 21 A15. Yes, it does.