From: To: Date: Subject: Chris Burns Michael Wickenden, Contract Administrator 6/05/07 BED’s April 2007 Report Dear Michael, We are pleased to submit the following report covering the period of April 1, 2007 to April 30, 2007. The report includes highlights over the period and the attached table covers costs and savings for the period. Please let me know if you have any questions. Sincerely, Chris Burns CC: Carole Welsh, John Becker of the VT DPS, Ann Bishop and Ed McNamara of the VT PSB BED Energy Efficiency Highlights Large Commercial services BED Energy Services hosted a learning session with VGS Energy Services technical staff to review DOE’s new energy modeling software, eQuest. It was quite informative in showing the strong and weak points of this software, which is freeware and was developed with public monies. We are also looking at a Trane product called System Analyzer. Staff attended an all-day Pneumatic & DDC (direct digital control) Controls Workshop in Montpelier hosted by Vermont State Buildings. ASHRAE – Attended monthly ASHRAE chapter meeting where a walking tour of the IBM – Essex chillers, high temperature boilers, and central control room. This is truly a city within the Village of Essex Jct., with a Peak Demand Load on par with the entire city of Burlington. Also, congratulations to Ron Lafountain of BED who was elected for the treasurer’s position and a seat on the Board of Governors Committee. AFE – Attended a monthly AFE chapter meeting where a formal presentation of a relatively new frictionless compressor technology was presented. Champlain College – Continue to work with this customer to implement the chiller plant piping rearrangement project which will limit operation of primary chilled water pump to only hours when the chiller operating. BED has offered a financial incentive for this project. We also continue to work with this customer to retrofit a liquid pressure amplification system to an existing chiller. These projects will be completed later this spring. Hinds Building – Continue to work with the project team to develop the conceptual efficiency and conservation features of this block development project. A ground source heat pump (GSHP) system has been considered but most likely will not be incorporated due to uncertainty of the geology at the project sight. UVM – various projects – Met with customer to go over outstanding information for over 40 projects throughout the campus where efficiency rebates may be available from BED. Continue to work with customer to finalize these rebates. Several projects have been completed and many are in progress and expected to be completed this year. UVM – PFG (Sports Complex) - A walk through lighting survey was conducted of the eight racquetball courts and two squash courts for the proposed energy efficient lighting upgrade at the request of UVM Physical Plant department. A complete fixture replacement design/retrofit and cost benefit analysis will follow. Fletcher Allen Health Care – Air Handler Cleaning Savings – At the request of Facilities, assisted them in determining the potential electrical savings gained by cleaning the McClure air handlers. Based on drive speed reduction in (3) 125hp fans, annual savings were estimated at over $50,000. o FAHC (UHC Campus) – The lighting retrofit for replacing existing T8 ballast and lamps to “super” T8 ballast and lamps of Phase II is now complete. The phase included a total of 479 fluorescent fixtures to be retrofitted. An inspection of the work was completed and the rebate amount was processed for payment. City Market – They are still pursuing their planned energy savings measures. During the first week or so of May, they hope to be installing an innovative GE Lexan glass-coating product which is said to completely eliminate the need for door and frame heaters in their reach-in coolers and freezers. The trial installation is planned on 7 doors, to see how the system performs. Burlington Free Press – Building control system upgrade: Attended a second audit with VGS. The purpose is to determine potential gas savings gained by upgrading their pneumatic temperature control system to a modern DDC system. Some duct temperature data may need to be gathered to help determine potential savings, and thus sell the project to their corporate headquarters. Burlington High School - Kilawatt / Hallam Contract - Attended a meeting between Hallam and the Burlington School District involving status updates on action items for BHS efficiency improvements. Rhino Foods – Delivered an audit report to the customer after a walk through. They have determined that they are interested in moving ahead with some improvements; the first focus being a compressed air system upgrade. Mater Christi – Attended a meeting at the school with VGS, involving replacement of one of their electric gym heaters, which has just failed. They are looking into the possibility of replacing it with a natural gas fired unit. Also did an analysis of electrical savings to replace their gym lighting (400W metal halide) with T5 high bays. The lighting levels in the gym are marginal now, at best. We will be completing a general audit of their two buildings, in conjunction with VGS, at the end of April. Wyndham / Hilton Renovation – We have been working with the HVAC contractor to gather sufficient paperwork and background to complete the rebate process related to several energy savings measures that were implemented. The mechanical portions of the project have been installed, and are up and running. We are also working with the local project manager on finalizing their lighting plans to ensure compliance with the VT Energy Efficiency Code. Some last minute changes will be required in their design. Lake Champlain Chocolates – 750 Pine St. – We are working with the owner and contractors as they address some cooling issues in their production area. Some changes must be made to ensure adequate cooling of the area, so that the product quality is not compromised. A meeting is scheduled on-site at the end of April. Fortieth Burlington LLC – The BED rebate agreement for the proposed installation of several occupancy motion sensors to control all the lighting through most of the Building #21 was signed. The project is presently in-progress. The three electric heat duct coils serving 9,000 square feet of office space proposed to be removed with steam heat coils piped from the main boiler is now in-progress. A BED rebate agreement for this EEM was singed and is scheduled to be completed in two weeks. General Dynamics – the electric re-heat coil from the air to air heat pump was removed and replaced by piping steam to a fan coil to heat an office area of the General Dynamics 4th floor. In addition, this three-ton air to air heat pump was replaced with a high efficient twoton Carrier rooftop a/c unit to cool the same space. The project was inspected and the rebate was processed for payment. Smaller Commercial Services Visited the Champlain College Carriage House mechanical room with VGS staff to assess the location as a beta demonstration site for a”FreeWatt Climate Systems micro CHP”. This micro CHP is the type inspected last month in MA by BED and VGS. St Josephs Parish – Met with this customer to review various lighting energy efficiency measures that would reduce their annual electric cost. Several 100- 500-watt incandescent lamps are currently installed in the church that could be replaced with energy efficient lamps. A test run is expected to be completed in the next few months which will help this customer to decide which proposed energy efficiency measure works best for operating cost reduction and aesthetics. Select Design - BED monitored their air compressor system for one week in preparation for possible upgrade of two 10hp compressors to one 20hp variable drive compressor. We have supplied them with an estimated savings and rebate if they choose to upgrade the system, including the addition of a new air receiver. Adriana’s Restaurant – A meeting with the owner and P.F. Bailey Associates was conducted to take a look at the existing 50-ton chiller. A BED rebate agreement was prepared and signed by both parties for the installation of the new high efficient 50-ton A/C chiller as a retrofit EEM. The rebate has been processed for payment. First Unitarian Society – Installed the Ideal meter to the elevator for four days and the main supply service electrical panel as part of demand study analysis to try and help them control or limit their demand usage which has been increasing over the past year. The results of the tests were e-mailed to the facility manager along with suggestions on how to reduce their kW. Worked with Everyday Bookstore to find reason for high electrical consumption. Found large A/C unit on due to misadjusted thermostat. Store was being heated and cooled simultaneously. Worked with Metering to arrange for meter pulse output connection for Draker Solar Design load monitoring system at 22 North Street. New Construction/Equipment Replacement Services Lund Family Center Expansion – Assisted the center in getting support from VGS to visit and evaluate the building's envelope. The idea is to target any wall / roof areas that could benefit from additional sealing / insulating before the open portions of the envelope are buttoned up. Jeremy King, of VGS, did an excellent job of pinpointing problem areas and explaining the best actions to take. Dealer.COM – Attended one of the initial meetings with the design and construction team for 444 Pine St. North. Had a chance to summarize BED's responsibilities with energy code compliance, and the role we play in supplying rebates for energy savings measures. We also emphasized the importance of commissioning to ensure the building systems work properly, and interact smoothly as a whole. Westlake Marriott Hospitality –The final inspection was completed and a BED rebate agreement was signed by both parties. The rebate was processed for payment. Merrill Lynch – A Vermont Energy Guideline code compliance review was completed and a DPW approval memo was e-mailed to all city building inspectors and the project manager of the fit-up new construction project. The proposed lighting design has been analyzed for possible energy savings that exceed beyond the Vermont Energy Guideline compliance codes. Hope Lodge – Continue to work with this customer on this LEED-NC project. This project is currently under construction and is expected to be completed this summer. Continued to work with the project team for the 31-unit co-housing project located at 166 East Ave. Construction has begun and insulation work is almost completed. The presheetrock inspection found that the insulation and air sealing work is being well done. 354 Manhattan Dr 15-units by Rouille Construction. Final inspections will be completed in early may 2007 72 Cherry Street BHA Transitional Housing – Construction is well underway. Insulation and air sealing work was completed by CVWS. Completed the final inspection of new homes at 167 and 168 Venus Ave and 21 Crowley Street. The following projects remain in the Planning & Zoning approval process and we have been in contact with each regarding energy code compliance and BED\VGS efficiency services: South Cove Road 8-lot subdivision; 25 unit building at 181-187 St Paul Street; 1162 North Ave 5-units; 237 North Ave 25 units and 40 seat café; 207 Riverside 2-units, Ice’s 50 unit project at 114 College Street, 8 units at 361 Pearl Street, 12 units 131 Battery St. Cornell, 7 units at 168 Pine St. and 20 units at 88 King St. Efficient Retail Products Advised 5 walk-in customers on compact fluorescent lamp applications. Clothes Washers rebates for 2007 – 21 Screw-in CFL rebates for 2007 –4,735 Compact fluorescent Hardwired fixture rebates (including floor and table lamps) for 2007 46 Residential screw-in CFL’s leased through Smartlight for 2007 – 41 Commercial screw-in CFL’s leased through Smartlight for 2007 –278 ENERGY STAR and CEE Tier 1 incentives for refrigerators, window AC units and dehumidifiers will begin over the next few months. Existing Residential Buildings Since Jan 1, 2007, 2 electric space heat conversions have been completed. Since Jan 1, 2007, 18 electric hot water conversions have been completed. Since Jan 1, 2007, 4 high efficiency\ECM motor ENERGY STAR furnaces have been installed. Since Jan 1, 2007, 0 ENERGY STAR Central AC systems have been installed. Since Jan 1, 2007, CVWS has submitted invoices for 9 completed projects BED continues to promote the LISF program to customers to increase participation. Working with five customers that are planning to switch to gas domestic hot water systems. Multi-Family Apartments Program – Administrator worked with Finance to create a new project number for the program and worked with ES staff distributing bulbs to the first of many landlord requests. Completed high consumption cases for 15 customers. Found various loads such as electric space heaters, dehumidifiers in damp places or freezers in unheated spaces. BED and EVT now offer $100 toward replacing electric clothes dryers with natural gas units. Also, new incentives for replacing older existing refrigerators with ENERGY STAR units ($150 for rental apartments and $100 for owner occupied). Champlain Valley Weatherization Service has completed 25 low-income weatherization projects so far in 2007 and has requested billing history data on 18 additional accounts. We processed 15 completions this month. Communications & Public Relations Burlington Business Association – Staff attended the Annual BBA dinner at the Wyndham. BED hosted the Vermont Council on World Affairs group. Staff presentations were given on power supply and energy efficiency services along with tours of the wind turbine and McNeil Plant. Load Response Program BED / ISO New England Demand Response Program – EnerNOC, our partner in delivering the ISO NE Demand Response Program to our customers, is now actively obtaining signed contracts from our major electrical users (FAHC, UVM, Verizon, 128 Lakeside Avenue properties and DPW Water Division). After setting up appointment with these major players, BED’s Commercial Energy Services Engineer spent three days this month traveling with EnerNOC to the customers to outline the program and explain its direct benefits to them. BED's support has made EnerNOC's efforts much more effective, and we have had a very good response. We are now focusing on the Tier 2 customers, the effort being to line up another series of customer visits sometime early in May. The goal is to have 5 MW under contract by June 15th in time for the beginning of BED’s peak season.