iSa MANAGEMENT PLAN TEAM Blue

advertisement
iSa MANAGEMENT PLAN
TEAM Blue
Blue Team
Milestone
December 10, 2007
The purpose of this plan is to describe the management philosophy, program
organization, schedule, and major milestones that serve as the guidelines for
execution of ISa.
Program Identification
This program management plan (PMP) is for iSa. This program will deliver
ISa hardware, software, and documentation. Team Blue is responsible for the
integration, acceptance testing, and training for this project.
Program Management Overview
Execution of this program will be performed in accordance with the
procedures defined by the set of planning documents. These documents include
Program Management Program (PMP), Resource Plan (RP), Funding Plan (FP),
Marketing Plan (MP), Staff Plan (SP), and Risk Management Plan (RMP). The
responsibilities of each team member, the capabilities of the system, and the
Program deliverables are detailed under the contractual provisions, as well as
BlueTeam’s technical, management, and cost proposals.
This Program Management Plan (PMP) describes the management
philosophy, program organization, schedule, and major milestones that serve as
the guidelines for execution of this project. The PMP also provides the customers
and the team with the information needed to monitor and evaluation the
progress. This plan provides the following information:







Corporate organization
Areas of responsibilities of each member of the organization
Work breakdown structure (WBS)
Program planning
Progress reporting and team management
Detailed schedule and major milestones
Program overviews





This PMP also provides the guidelines for these followings:
Risk Management
Evaluation Plan
Testing Plan
Resource Management Plan
Funding Plan
2
Blue Team


Milestone
December 10, 2007
Marketing Plan
Installation Plan
Corporate Structures
Blue team was formed in spring 2008 at Old Dominion University. Blue
team’s members are responsible for the planning and development of the iSa
System. We will be either directly involved in the entire process or outsource the
responsibilities to other entity. The corporate structures are:



CEO & President, Blue Team corporation
Vice President
iSa System Program Office that will execute the program and provide dayto-day management, engineering, and administrative resources necessary
to management and maintain the program.
Management Approach
Blue Team’s goal is to work closely with the customers and specialists to
fully understand the system requirements. The management approach, therefore,
is based on the philosophy that successful Programs are delivered by goaloriented teams. A program manager (PM) will lead the team toward this goal. A
PM is responsible for all planning, programmatic, technical and financial aspects
of the program. The PM will assigned and distribute tasks among each team
member to assure that the project is carried out effectively and successfully. The
primary duties of the PM include these aspects:





Planning
Scheduling
Technical activities
Customer liaison
Program related decisions (with the approval and suggestion from team
members)
A key element of Blue Team project is specialist and customer
involvement. Blue Team seeks specialists’ opinions during the development and
installation process as well as customer active involvement to create a product
that meets that customers’ goal.
Project Team
Blue Team’s goal is to provide an effective, low cost COTS system.
Through strategic planning and an extensive selection process, Blue Team has
assembled a cohesive Program Team that will work together to develop and
implement each component that is needed to comprise the ISa System.
3
Blue Team

Milestone
December 10, 2007
Program Manager (PM)
Matthew D Salyer
 Senior at Old Dominion University, expected graduation date:
December 2009
 Major in Computer Science with a minor in Information Technology
 Interest :graphics design, web design, web database
 Skills: Programming (C++, Java, Visual Basic), graphic design and web
design (Dreamweaver), web design,
Responsibility
The PM will manage the Blue team and is responsible for the planning and
coordination of the day-to-day technical, contractual, and financial aspects
of the program. She/he is responsible for the development and
management of all program schedules, the coordination of all team
members and all program activities.


Hardware Specialist (HS)/ Risk Specialist (RS)
Scott Wood
 Senior at Old Dominion University, expected graduation date:
December 2008
 Major in Computer Science with a minor in Computer Engineering
 Interest : Networking, Programming
 Skills: Programming (C++, ASP, VBasic), Networking
Responsibility
The RS is responsible for identifying all possible risks that are associated
with the iSa. All identified risks will need mitigating actions to reduce or
eliminate the risks.
The HS is responsible for evaluating existing hardware options that are
available to the team. The HS is in charge of determining where and when
COTS are acceptable and when new hardware must be developed. The
HS must evaluate available hardware options and advise the team on
which options are best for the fulfillment of the team’s goals
.
Senior Engineer (SE)
Dominic Eldridge
 Junior at Old Dominion University, expected graduation date:
December 2008
 Major in Computer Science
 Interest: Database, Network Security
 Skills: Database Administration, Network Security, UNIX/LINUX System
Administration, Web design, Programming (Perl, C++, HTML)
Responsibility
4
Blue Team
Milestone
December 10, 2007
The SE is responsible for the development and implementation of the
system software function as defined in the system specification. She/he
will assure that the integration for all systems components meet the
performance requirement for the system.

Financial Director (FD) / Webmaster (WB)
Scott Seto
 Senior Old Dominion University, expected graduation date: May 2008
 Major in Computer Science
 Interest and Skills: Software engineering, computer network, military
history
Responsibility
FD is primarily responsible for managing the financial risks of the ISa
System project. She/he is also responsible for financial planning and
record-keeping, as well as defining and reporting the budget for each
project phase (defined in staffing plan). He will work closely with the
technical director to ensure that the project meet budget requirement for
each phase.
The WM is responsible for determining the functionality and look of the
website that will house the rate-it engine. As WB, the responsibilities
include creating the team and product websites, as well as managing the
web developers in future phases.





Marketing Manager (MM)
Brad Travalgio
Senior at Old Dominion University, expected graduation date: December
2008
Major in Computer Science
Interest: Network, web database, web design, web programming
Skills: Web database and programming (PHP, HTML, XML, mySQL,
pl/SQL),
Skills: programming (Java, C/C++)
Responsibility
MM is primarily responsible for managing contact with subcontractors. This
person is responsible for strengthen and expand ISa System awareness and
develop new marketing channels that are critical for the successful of the
product. As a guardian for brand values, the MM will develop, implement and
evaluate the annual strategic plan and oversee various marketing programs
including developing market research programs. Finally, the MM will build the
framework for marketing initiatives and devise marketing and PR campaigns.

Documentation Specialist (DS)
Mark Mahn
5
Blue Team
Milestone
December 10, 2007
 Senior at Old Dominion University, expected graduation date: December
2008
 Major in Computer Science
 Interest: Artificial Intelligence
 Skills: Programming (Java, C++, ANSI C, Perl, and SQL)
Responsibility
The DS provides overall documentation direction for the Program Team. The
DS will ensure that everyone on the team has met the required
documentation specifications, and that each person is aware of the tasks
he/she has been assigned. The DS will also provide documentation of each
meeting in which an overview of tasks assigned is given.
Program Duration
The ISa System program is a 3-year duration project, from initializing the
project to delivering the first product. The schedule consists of the preliminary
design phase which will last through May of the year 2008, the construction and
development process will be completed around the last quarter of 2009, the
evaluation and testing process will last though the third quarter of 20010 and the
first delivery of the product will be in April of 2011.
Work Breakdown Structure (WBS)
Constructed using Microsoft Visio, WBS1 reflects the budgeted cost versus
resources required to complete each task. The WBS phase (see staffing plan)
numbers are integrated as part of the master program schedule. For each WBS
element, budgets for work planned, actual cost and estimates to complete are
managed by the Project Manager with the assistance of the Funding Director.
The WBS is an essential tool used to track program costs, progress, and earned
values relative to master program schedule.
Program Planning
The Blue program team will maintain the program master schedule. The
master schedule contains a line item for each WBS element and will be used to
track the progress of each element. All deviations from the master schedule
must be coordinated with the program office It is the responsibility of each team
member to call attention to possible schedule deviation at the earliest
1
For detailed WBS see Work Breakdown Structure document
6
Blue Team
Milestone
December 10, 2007
opportunity. The program will be develop in phases2, formal review will play an
integral part in monitoring program progress.
Team Blue will use the “top-down approach” for our schedule. This means
that we will start with the largest items of the project and break them into their
subordinate items. This helps make constructing the WBS more convenient.
Progress Performance Assessment (PPA)
All members of the Blue Team will participate in the PPA. As a team, all
members will track technical and financial progress of the project. Reviews will
be held Weekly to assure the project’s goals will be met. The PPA contains the
followings,




Report of progress to date
Present work to be performed for the next period
Present status of all the deliverable
Discussion of technical and programmatic issues (if exist)
In preparation for each meeting, the PM will collect the current status of
on-going activities, progress against schedule and budget, and plan the activities
for the next meeting. Quality reviews for all documentations and activities will be
performed periodically.
Technical Progress and Report
The schedule of the program is established during the planning phase and
monitored throughout the performance period. The schedule contains an entry
for each WBS element. The percentage of completion for each WBS element is
determined as necessary to manage program progress and is reviewed at least
quarterly.
Financial Management and Report
The financial management for the program is established during the
planning phase and is monitored throughout the performance period. A budget
representing labor costs, material purchase, overhead cost, travel expenses, and
other expenditures is prepared and implemented for each phase.
The Project Manager with the assistance of the Financial Manager will
oversee the overall spending profile of the program. They will use the financial
summary provided by the Contracts Administrator to assess the technical
progress in order to track the overall status of efforts.
2
For detailed phase information see Staffing Plan and WBS document
7
Blue Team
Milestone
December 10, 2007
Earned Value Ratio (EVR)
EVR will be reported quarterly. The EVR will be reported in form of
Schedule Performance Index (SPI) ratio and the Cost Performance Index (CPI)
ratios. If the ratios are below 0.90, further explanation is needed. SPI and CPI
are defined below:
SPI = BCWP/BCWS
CPI = BCWP/ACWP
Where BCWP = Budgeted Cost of Work Performed
BCWS = Budgeted Cost of Work Scheduled
ACWP = Actual Cost of Work Performed
Quality Process and Reporting
Quality management on the program will be a team effort. It is the
responsibility of the quality system manager to coordinate conduct, quality
reviews, and audits. The Project Manager task is to oversee the development
and implementation of the System Quality Program Plan.
Monthly Progress Report
In order to ensure the goals of the project to be met, Blue Team will
produce a monthly progress report. The report should include, but not limited to
the followings,









Progress summary
Milestone deliverables, planned, actual, and forecast
Earned value schedule and cost performances indices
Critical list of all items, responsibilities, and activities
Risk status
Resource profile
Milestones/deliverables planned, actual, and forecast status
Quality Actions
Configuration change control issues
Reviews
Reviews will play an integral part in the management and monitoring of all
phases of the ISa System project. Informal reviews with the program team
8
Blue Team
Milestone
December 10, 2007
members will be held on a weekly basis to ensure that the project stay on track
and meet the planned deadlines. Reviews includes the followings,



Program management review
Technical reviews
 Software requirement review
 Hardware requirement review
 Preliminary design review
 Critical design review
Quality review
9