Major Facilities Projects Dave Riker, AVP for Facilities Paul Goodman, Director, E&PM May 19, 2010 Sculpture & Ceramics Combined Science Facility Student Housing Phase 3 UTSA North Paseo Building The University of Texas at San Antonio Office of Facilities East Parking Garage Combined Science Facility Renovations 23,111 original GSF $23,876,000 Total Project Cost (PUF and RFS) September 2010 Operational Occupancy Combined Science Facility Renovations • SCOPE – Complete demolition of PSL and LSL interiors. Installation of modern Biology, Chemistry, and Physics research labs. – Installation of life safety systems in the Science Building including fire alarm, emergency generator, and fire sprinkler (with associated ceiling and lighting). • FUNDING – $21,626,000 PUF Bond Proceeds – $2,250,000 RFS Bond Proceeds • SCHEDULE – – – – Work is in progress. Return SAL to regular operation in June 2010. Move occupants into PSL and LSL September 2010. Complete Science Building work December 2010. North Paseo Building 76,000 GSF $15,250,000 Total Project Cost Summer 2011 Operational Occupancy North Paseo Building • SCOPE – Two story tilt-wall building with office space to accommodate ROTC, Research administration, Vice Provosts, Library Technical Services, and more. • FUNDING – $15,250,000 Institutional Funds • SCHEDULE – Work is being scheduled to begin first week of June 2010. – Move occupants into space late summer 2011. PROJECT LOCATION UTSA BOULEVARD Vicinity Map 7 Master Plan Graduate Sculpture and Ceramics Building 18,000 GSF $3,195,861 Total Project Cost Summer 2011 Operational Occupancy Graduate Sculpture and Ceramics Building • SCOPE – One story metal building includes graduate studios, offices, and support space. • FUNDING – $3,195,861 Institutional Funds • SCHEDULE – Work is scheduled to begin June 2010. – Move occupants into space late summer 2011. Existing Campus Plan Master Plan UTSA Facilities Planning and Development Conceptual Representation East Parking Garage 1200 Car Garage with Parking Office and Coffee Kiosk $30,000,000 Total Project Cost Fall 2012 Operational Occupancy East Parking Garage • SCOPE – Four floor concrete parking garage including a parking staff office and coffee kiosk. • FUNDING – $22,000,000 RFS Bond Proceeds – $8,000,000 Auxiliary Enterprise funds • SCHEDULE – Contract negotiation is in progress with the design firm. – Fully operational by fall semester 2012. Existing Campus Plan Master Plan UTSA Facilities Planning and Development Conceptual Representation Student Housing Phase 3 600 Bed (168,000 GSF) $39,900,000 Total Project Cost Fall 2013 Operational Occupancy Student Housing Phase 3 • SCOPE – Two story traditional dorm with rooms accessible from an interior corridor. Community kitchen, lounges, and laundry will be included. • FUNDING – $37,100,000 RFS Bond Proceeds – $2,800,000 Auxiliary Enterprise funds • SCHEDULE – Committee is being formed to select design firm. – Fully operational by fall semester 2013. Existing Campus Plan Master Plan Athletics Complex Phase 1 Portion of 125 acres $22,050,000 Total Project Cost Spring 2013 Operational Occupancy Athletics Complex Phase 1 • SCOPE – Utility Infrastructure, Track and Field Stadium, Soccer Stadium, Surface Parking Lot, Water Quality Basin. • FUNDING – $15,000,000 City Venue Tax Proceeds – $5,550,000 County Bond Proceeds – $1,500,000 City Bond Proceeds • SCHEDULE – Schedule depends on successful negotiation of City and County agreements and subsequent approval by the UT System Board of Regents. – Assuming BOR approval in August 2010, project would be complete in spring 2013. FACILITIES PROJECT MANAGEMENT FEE Project management fees are not adequate and fee service account balance will continue to decline to no remaining funding by late 2010. Staffing levels have not kept pace with the increase in institutional projects, causing service to suffer. 1 Historical and projected balance $300,000 $275,000 Trend $250,000 Historical $225,000 Projection $200,000 $175,000 Actual $150,000 $125,000 Revenue $100,000 Expense Balance $75,000 $50,000 $25,000 $$(25,000) Aug-10 Jul-10 Jun-10 May-10 Apr-10 Mar-10 Feb-10 Jan-10 Dec-09 Nov-09 Oct-09 Sep-09 Aug-09 Jul-09 Jun-09 May-09 Apr-09 Mar-09 Feb-09 Jan-09 Dec-08 Nov-08 Oct-08 Sep-08 Beg. Bal. $(50,000) 4 Jan-10 Sep-09 May-09 Jan-09 Sep-08 May-08 Jan-08 Sep-07 May-07 Jan-07 Sep-06 May-06 Jan-06 Sep-05 May-05 Jan-05 Sep-04 May-04 Jan-04 Sep-03 May-03 Jan-03 Sep-02 May-02 165 Jan-02 Sep-01 May-01 Jan-01 Sep-00 UTSA Institutional PROJECT & staffing HISTORY 195 13 180 12 Number of Projects Number of Project Coordinators 11 150 10 135 9 120 8 105 7 90 6 75 5 60 4 45 3 30 2 15 1 0 0 5 Number of Projects vs. Total Project Cost 80 70 60 69 35% 50 40 29 28 30 23 14% 20 25 13% 12% 15% 14 10 7% 10 5% 0 $0 - $25,000 $25,000 $50,000 $50,000 $150,000 $150,000 $500,000 $500,000 $1,000,000 Over $1,000,000 169 projects with cost estimates totaling $40.4 million for average project cost of $239,000. To Be Determined 3 FACILITIES PROJECT MANAGEMENT FEE Increase Project Management Fees from 3% of Construction Cost to 4% of Total Project Cost (TPC) Proposed fee increase will take effect 9/1/2010, and apply to all new projects after 4/30/2010. 1 FY11 Shop Rates Hourly Rate (Straight Time) Services FY10 FY11 Housekeeping $ 19.50 $ 19.00 Grounds $ 22.50 $ 22.50 Events & Setups $ 22.00 $ 22.00 Auto Shop $ 30.00 $ 30.00 Maintenance $ 31.50 $ 32.50 FY11 Shop Rates Methodology • Average base wages by trade group • Average cost of fringe benefits for Facilities • Nominal consumable materials and supplies • Overtime billed at 1½ times hourly rate Questions?