The switch from tOPV to bOPV Implementation guidelines A handbook for national decision makers, programme managers, logisticians, and consultants Version date: 13 March 2016 Please note: This document is an update of a version released in August 2015. The main changes in the March 2016 version concern the following new content: Guidance on the tOPV disposal strategy in section 3.4.4; Suggested steps on process monitoring in section 3.5; and Suggested steps and forms on validation provided in Annex 4. 0 Table of Contents 1 Introduction.............................................................................................................................. 4 1.1 1.2 1.3 2 Phase one: PLAN ....................................................................................................................... 9 2.1 2.2 2.3 2.4 3 Complete tOPV inventory and procurement plan ........................................................................ 13 Plan bOPV procurement and distribution .................................................................................... 15 Establish support mechanisms .................................................................................................... 16 Manage logistics ........................................................................................................................ 17 Monitoring of the switch ............................................................................................................ 22 Phase three: IMPLEMENT ........................................................................................................ 25 4.1 4.2 4.3 4.4 4.5 5 Establish a management structure ................................................................................................ 9 Establish national switch validation committee ........................................................................... 10 Conduct situation analysis .......................................................................................................... 10 Draft a national switch plan ........................................................................................................ 12 Phase two: PREPARE ............................................................................................................... 13 3.1 3.2 3.3 3.4 3.5 4 1.1 Background ............................................................................................................................ 4 Switch calendar ............................................................................................................................ 6 Overview of key country activities ................................................................................................ 7 Train switch monitors ................................................................................................................. 25 Distribute bOPV to all peripheral levels....................................................................................... 25 Train health workers .................................................................................................................. 25 Organize communications and media events .............................................................................. 26 Implement National Switch Day.................................................................................................. 26 Phase four: VALIDATE ............................................................................................................. 27 5.1 5.2 Validate tOPV removal ............................................................................................................... 27 Report validation ....................................................................................................................... 28 Annex 1: Sample Terms of Reference for Switch Management Committees and Support Teams .... 29 Annex 2: Briefing note on the switch ............................................................................................ 31 Annex 3: Sample key messages for health staff ............................................................................. 33 Annex 4: Sample validation forms for tOPV................................................................................... 41 Annex 5: Template and chronogram for developing a national switch plan ................................... 46 Annex 6: Budget template for the national plan ............................................................................ 48 1 List of abbreviations bOPV Bivalent Oral Polio Vaccine EPI Expanded Programme on Immunization GPEI Global Polio Eradication Initiative ICC Interagency Coordinating Committee IPV Inactivated Polio Vaccine MOH Ministry of Health NSVC National Switch Validation Committee OPV Oral polio vaccine RI Routine immunization SAGE Strategic Advisory Group of Experts on Immunization SM Independent switch monitor SST Switch support team tOPV Trivalent oral polio vaccine WHA World Health Assembly WHO World Health Organization 2 NOTE: This document does not discuss the technical rationale or questions related to the global decision on the timing of the switch. 3 1 Introduction 1.1 1.1 Background 1.1.1 Why this document? In May 2012, the World Health Assembly declared the completion of poliovirus eradication to be a “programmatic emergency for global public health” and called on the Director General of WHO to develop a comprehensive polio endgame strategy. The Global Polio Eradication Initiative’s Polio Eradication and Endgame Strategic Plan 2013-2018, approved by the Executive Board of WHO in January 2013, requires the removal of all oral polio vaccines (OPVs). The removal of OPVs must be done in a phased manner, from both routine programmes and campaigns, to minimize the risk of new polio cases. The first phase of OPV removal is a switch from the current trivalent oral polio vaccine (tOPV), containing antigens for poliovirus types 1, 2, and 3, to bivalent OPV (bOPV), containing only types 1 and 3. The use of tOPV led to the eradication of wild poliovirus type 2, with the last detected case occurring in 1999. The global switch from tOPV to bOPV is expected to occur in April 2016. It is proposed that the switch be carried out during a 2 week window from 17 April to 1 May. This will be put forward to SAGE in October 2015 for final endorsement. Prior to the switch, manufacturers will cease production of tOPV. The supply of tOPV will be finite leading up to the switch, and no tOPV will be available after the switch. The switch also must be a globally coordinated process. Any use of tOPV after April 2016 could jeopardize polio eradication by generating circulating vaccine-derived polioviruses from the type 2 component of the vaccine. To prepare for the switch in April 2016, it is imperative that all OPV-using countries begin switch planning during Q1-Q2 2015 and finalize a budgeted national switch plan by September, 2015. Timely planning and implementation of a switch plan will increase the probability of a successful removal and disposal of tOPV, minimize tOPV wastage, and ensure a world free of circulating vaccine-derived polioviruses type 2. 1.1.2 What is included in this document? This document provides guidelines and a framework for countries to consider when developing and implementing their national switch plans. Country needs will vary and national switch plans should be adapted to meet local implementation needs. 1.1.3 Who is the target audience? These guidelines were created for policy makers, programme managers, logisticians, and consultants. The guidelines may be adapted to become a field guide for training based on local needs. 1.1.4 Where can I get more information on the switch? The following documents are available to help countries plan, prepare for, and implement the switch. SAGE position & WHO position paper [http://www.who.int/wer/2014/wer8901/en/index.html ] A briefing note on the switch, frequently asked questions and Powerpoint decks: http://www.who.int/immunization/diseases/poliomyelitis/endgame_objective2/oral_polio_vaccine/en/ 4 Dates of switch: April 17-May 1 2016 Initiate planning: Quarter 2, 2015 Finalize national switch plans: by September, 2015 Primary objectives of the switch Successfully recall tOPV and introduce bOPV in April 2016 Minimize tOPV wastage after switch Ensure all children are vaccinated (avoid tOPV stockouts before and bOPV stockouts after the switch) Validate that the country is free of tOPV 5 1.2 Switch calendar By June 2015 Plan - Establish management structure - Establish National Switch Validation Committee (NSVC) - Conduct situation analysis - Draft national switch plan (budgeted and finalized by Sept 2015) May to September 2015 - Complete detailed tOPV inventory; adjust tOPV delivery (may vary per country) - Secure funding and finalize national switch plan - Develop monitoring plan October to November 2015 Prepare - Complete second tOPV inventory; adjust tOPV orders and/or delivery - Order bOPV - Develop waste management protocol - Hire switch support staff December 2015 to January 2016 - Receive last tOPV delivery to country; - Redistribute remaining tOPV stock within country as required - Prepare training materials and implement communications strategy - Begin bOPV deliveries to countries February to March 2016 - Deliver last 1-2 months of tOPV to periphery; redistribute as needed - Identify switch monitors Two to four weeks prior to the switch Implement National Switch Day Validate - Train switch monitors - Train health workers - Distribute bOPV to periphery and service points A day chosen during the period of 17 April to 1 May, 2016 - Stop use of tOPV and remove tOPV from cold chain - Begin use of bOPV In a two week period after the Switch Day - Validate tOPV disposal at selected sites (switch monitors) - Collect and review data and validate switch (NSVC) 6 1.3 Overview of key country activities Countries are responsible for: 1. Setting a National Switch Day: National decision-makers must establish a switch day within the period from 17 April to 1 May 2016. This is the date when tOPV is removed from all facilities, sent for proper disposal, and replaced with bOPV. 2. Establishing management structures: By mid-2015, countries are encouraged to establish switch coordination committees (e.g., ICC) at national and subnational levels. These committees are responsible for developing the switch plan and providing implementation oversight. 3. Developing a switch plan: All OPV-using countries should finalize a national switch plan by September 2015 using the recommended template, leaving approximately six months to prepare and implement all activities. 4. Preparing for the switch: Countries are expected to implement their national switch plans, complete training; distribute bOPV to periphery; withdraw and dispose of tOPV according to the timelines outlined in their plan. Countries are encouraged to hire staff (i.e. switch support teams) assigned specifically to prepare and implement the switch plan. 5. Implementing the switch: All countries should stop using tOPV and destroy remaining stocks of tOPV after their designated switch day in April 2016 to avoid re-emergence of circulating vaccine-derived polioviruses type 2. Ongoing use of tOPV after April 2016 may threaten or postpone the global eradication of polio. 6. Validating absence of tOPV: During the two weeks following the Switch Day, countries must validate that facilities are free of tOPV as recommended in this document. 7. Completing national validation: Countries are encouraged to delegate authority to an independent body (e.g. National Switch Validation Committee) to review disposal data and validate the country free of tOPV within two weeks of the National Switch Date. Personnel involved in validation should be independent of the Ministry of Health and the Switch Implementation Team. Minimizing tOPV wastage is a priority at global, regional, and country levels. Ultimately, countries are responsible for minimizing the quantity of tOPV stocks remaining in the country after the switch. Residual stocks of tOPV increase the risk that they will be used after the switch and increase costs to countries associated with destruction of vaccine. While reducing tOPV stocks to zero (0) will be difficult without risking stock-outs prior to the switch, countries can minimize the risk of residual stocks of tOPV after April 2016 by conducting nationwide inventories of tOPV stocks at least two times prior to the switch and incorporating this information into vaccine procurement plans. 7 Figure 1: Overview of key activities related to a successful switch Phase 1 PLAN (by end Q2 2015) Phase 2 PREPARE (Q2 2015-Q1 2016) -Switch commitment made -Funding secured -Management committees established (e.g., ICC) -tOPV inventories calculated -National Switch Validation Committee (NSVC) -Situational analysis completed -National switch plan with budget finalized (by September 2015) -Staff hired -bOPV orders subitted Phase 3 IMPLEMENT (2 weeks before Switch Day) NATIONAL SWITCH DAY - Switch Monitors trained -bOPV-only use begins - HCWs trained -tOPV recalled - bOPV delivered to all service points -tOPV disposal begins -cold chain and logistics needs assessed -Communication prepared Phase 4 VALIDATE (during 2 weeks post switch) - Validation data collected on tOPV removal and reported to NSVC NATIONAL VALIDATION DAY - Switch validated and reported from the Ministry of Health to the WHO Country Office. The WHO Country Office will report this to the WHO Regional Office. -Training prepared -Waste management capacity assessed -Monitoring plans finalized -Information systems updated Note: The above outline may be adapted to meet local needs. 8 2 Phase one: PLAN PLAN PREPARE IMPLEMENT VALIDATE by end Q2 2015 Establish management structure Establish national switch validation committee Conduct situation analysis Draft national switch plan 2.1 Establish a management structure Countries are encouraged to establish national and regional switch management committees (see sample terms of reference in Annex 1) to plan, manage, and oversee all activities related to the switch. This management body could be the Interagency Coordination Committee (ICC) or a similar body. Finance, procurement, regulatory, legal authorities outside MOH should be included in the switch management committee, particularly in self-procuring countries where disposal of state-procured vaccine may become a problem. The structure, roles and responsibilities will vary depending on the country situation. Initial actions by the national switch management committee include: Select a National Switch Day: o A National Switch Day should occur within the period of 17 April to 1 May 2016. It is the day that tOPV will stop being used in the country and will be replaced with bOPV. Form subcommittees o Subcommittees on vaccine supply, communications, logistics, process monitoring and reporting should be formed at the national and sub-national levels. Subcommittees should include all relevant stakeholders in discussions (e.g., manager of national cold stores or central medical stores, national regulatory authority, procurement unit, ministry overseeing private sector vaccine procurement, etc.). Identify points of contact: o Focal points should be identified for all national and regional committees and their contact information (names, telephone numbers, email addresses) circulated to members. o A central telephone number and email address should be made available to answer questions from public or professionals. Establish operations center: o Countries should consider establishing an operations center to coordinate national, regional activities with up-to-date status of activities related to the switch. 9 2.2 Establish national switch validation committee Validating that a country is tOPV free is crucial. Validating the removal of tOPV from the vaccination programme follows a different timeline and process than containment of wild and Sabin polioviruses according to the Global Action Plan III (GAPIII). According to the Global Action Plan III (GAPIII), primary and secondary safeguards are required within 3 months of the switch for essential facilities handling and storing only OPV2/Sabin2 materials. These containment activities could provide an additional check for validation of the switch but are not within the scope of the activities proposed in this document. The removal of tOPV from all delivery facilities is a country responsibility. The chain of reporting and accountability for tOPV withdrawal is within the existing MOH structure – e.g., from Immunization Officer at the Service Delivery the District Immunization Officer Regional Officer MOH. The MOH reports confirmation of validation to the WHO country office which reports through the appropriate chains to the World Health Assembly. To assure rigour and support the MOH in the validation process, WHO recommends MOH establish a national switch validation committee (NSVC) which is authorized by the government to collect and validate data on tOPV removal (see section 3.4.4 and Annex 8: Monitoring Guidelines). After verifying tOPV removal, the NSVC submits country documentation to the WHO country office. Countries with existing NSVCs (e.g., for polio) are encouraged to enlist their help with the switch rather than forming new committees. Countries without existing or functional independent national switch validation committees (e.g., the national eradication certification committee) are encouraged to establish them. NSVC personnel and switch monitors must be independent from those responsible for managing or implementing the switch (see Sections 2.1 and 3.3.2). Countries have flexibility in implementing these structures and balancing the rigor obtained through independent data collection and available mechanisms and resources. NSVC members could include experts in public health, epidemiology, logistics, and clinical medicine. 2.3 Conduct situation analysis While management structures are established, key structures, systems, and policies should be identified and understood. The questions below can be used to assess appropriate structures, systems and policies: Supply and distribution of OPV: How is vaccine procurement organized: through procurement agency, directly by MOH, or a mix? What is the tOPV stock status at national, regional, and district levels one year prior to the switch? How often is tOPV supplied to the country, regions and district? 10 Vaccine licensing: Does the country accept bOPV for routine use based on WHO prequalification or is national licensure required? Is an expedited procedure acceptable or is full national licensure required? If licensure is required, has the process for NRA licensing of bOPV for routine use begun? What is the standard timeline for licensure? Is the country willing to provide an emergency waiver for initial importation if licensure is not initiated or completed before the switch? Private sector provision of OPV: Is tOPV offered in the private sector and in which facilities (NGOs, hospitals, private clinics, and/or pharmacies)? Is there informal delivery of tOPV in the private sector (e.g., unregulated pharmacies/dispensaries, traditional healers, local untrained pharmacy dealers)? What percentage of tOPV is currently delivered in the private sector? Is it possible that private sector providers will exit from offering OPV products due to financial risk? If so, what increased demand may occur in the public sector? How and from where does the private sector source and procure their tOPV (from local agents/suppliers, directly from suppliers)? Does the National Regulatory authority or other relevant agency have regulatory oversight over medical supplies imported into the country and delivered through the private sector? How can countries engage the private sector in participating in the switch and through which associations/agencies (e.g., NRA, National Medical Council, ministry of commerce, etc.)? Vaccine communications: What are the barriers and enablers to the switch among key stakeholders, e.g. health workers, medical specialists and scientists, specific interest groups, public and media? Waste management: How is vaccine waste disposal organized in both public and private sector, if applicable, and how can disposal of tOPV be aligned with these guidelines while also considering WHO guidance? Existing expertise: Do any of the national staff have experience with previous vaccine switches or vaccine recalls? Are there any lessons to be learned from those experiences? Funding: What additional funding will be required for managing implementation of the switch, including procurement of bOPV for routine, logistics for implementation/distribution, disposal of vaccines, etc.? What resources within a national vaccination program are available to help with the switch? Are any resources external to the vaccination program available to help with the switch? External environment: What other demands will be placed on vaccination program resources before and during the switch? Are any predictable events, such as elections, going to occur that could complicate the switch? All points requiring action should be included in the national switch plan. 11 2.4 Draft a national switch plan All countries should begin drafting a national switch plan, including a budget by end of Q2-2015 to meet country needs (see Table 1). A plan should be finalized and approved by the ICC by September 2015. Table 1. Checklist of the components of a sample national switch plan Section Key components Executive Summary (2 pages) Management and operational oversight of switch – national coordination mechanisms Organizational chart with roles and responsibilities • ICC or national switch committee • Sub-national switch committees • Switch support teams Information flow – who informs whom and with what frequency Budget for switch activities Work plan and timeline Validation Committee Roles and responsibilities Validation and reporting process Situation Analysis Preparation Switch support o Available budget o Composition of switch support team o Communications materials and dissemination Supply assessment o National inventory of tOPV o Plan for tOPV procurement o Plan for bOPV procurement, storage, and distribution Logistics o Plan for healthcare worker training and supervision o Plan for updating information systems (paper and software) o Plan for delivering bOPV to service points o Plan for tOPV recall and disposal Monitoring o Process monitoring: assessing switch activities/milestones o Outcome monitoring: collecting monitoring data and validating tOPV removal Summary of the switch plan activities Date selected for the National Switch Day Overview of national coordination mechanism Capacity to implement the switch (e.g., financial needs and resources) List of preparatory activities, including plans for tOPV inventory tOPV disposal and validation strategy Key risks and mitigating strategies: supply, logistics, validation Key milestones and activities Supply and distribution process for OPV (public and private sector) Licensing and regulatory approvals needed for bOPV Capacity of existing medical waste management system Stock of tOPV and bOPV to date 12 3 Phase two: PREPARE PREPARE PLAN May 2015 to March 2016 IMPLEMENT VALIDATE Complete tOPV inventory and procurement plan Plan bOPV procurement and distribution Establish support mechanisms Manage logistics Establish monitoring system 3.1 Complete tOPV inventory and procurement plan Three principles should guide tOPV procurement in the final year prior to the switch: 1. Unlike other product transitions, where countries are allowed to exhaust the existing stocks of the old product before using the new product, this will not be the case for a global cessation of tOPV and synchronised switch to bOPV. 2. All tOPV that remains in countries after the switch date will need to be removed and destroyed, which will incur additional costs for disposal. 3. Accurate forecasting and procurement planning, close inventory management, and regular monitoring of stock levels will be critical for countries to minimize wastage of vaccine after the switch. 3.1.1 Assess and manage tOPV inventories Inventory control is critical to avoid stockouts of tOPV prior to the switch and minimize excess tOPV stock after the switch. WHO recommends that countries conduct at least two inventories with at least one down to the district level (or lower): First inventory: Approximately 1 year prior to the switch (as soon as possible in 2015) Second inventory: Approximately 6 months prior to the switch (October-November 2015) 13 The inventory should be exhaustive and include stock located in: Central medical/cold chain stores, including regional warehouses/depots in both government-owned and autonomous agencies Provincial warehouses District warehouses Any hospital at district, provincial, and tertiary level where immunization services are provided Private sector, including pharmacy stores, warehouses, or other location that provides OPV to customers Supply balances from recent SIA activities Pipeline deliveries (recently received but not yet registered, or supply already on order and pending delivery) 3.1.2 Decide timeline for tOPV forecasting, ordering, and shipment General guidance for tOPV procurement for all countries: Review current procurement plans, orders, and requests for tOPV and their delivery schedules. Ensure that quantities forecasted are sufficient to meet tOPV routine immunization requirements until April 2016. Plan to deplete most buffer stock by April 2016 at all levels, leaving sufficient supply (e.g., 1-2 weeks) to respond to localized stockouts. Ordering cycles: Countries have different ordering cycles, lead times and processes for vaccine procurement1. Procurement may be done by countries directly with manufacturers or through an intermediary/local supply agent; or through UNICEF, PAHO, or other UN agency. Countries should coordinate directly with their relevant procurement agency for specific guidance around ordering vaccine supply in the context of the switch. Below is guidance on tOPV procurement (also elaborated in Figure 1 below). Countries are encouraged to maintain existing ordering processes and cycles as much as possible. However, a risk assessment should be completed based on the situation analysis described in Section 2.3 to determine if any adjustments are required to minimize risk of overstock and associated financial loss. If possible, split annual orders into at least 2 deliveries during the year before the Switch. These deliveries can be smaller in the last few months prior to the switch. Then the FINAL delivery can be adjusted to meet stock needs for the switch while avoiding excess tOPV stock after April 2015. Once an order is placed with a supplier, the order is binding and cannot be changed. o Countries procuring through PAHO and/or UNICEF may have several opportunities to adjust their requirements prior to an order being placed with a supplier. o Procurement processes for self-procuring countries may not allow for such adjustments, depending on contractual arrangements. Countries that conduct an annual procurement and receive a single delivery of their annual supply requirements are advised to split their procurement into a minimum of two orders (and a minimum of two deliveries) to allow for adjustments in requirements prior to placing the last order. Feasibility will depend on procurement mechanism, procurement lead times, payment processes, and incountry procurement laws. Additional funding may need to be allocated to cover any additional costs associated with additional shipment costs and import fees. 1 “Ordering”, “placing an order” or “issuing a purchase order” as described in this guide is defined as a legally-binding contract with a supplier. In these cases, such binding contractual arrangements with suppliers often entail payments made to a supplier to produce the vaccine and may incur financial losses if changed or cancelled. 14 Figure 1. Sample tOPV order cycle NOTE: this is just an example and should be aligned with the COUNTRY ORDERING PROCESS First tOPV inventory: Conduct a thorough tOPV inventory ~12 months before the switch (March or April 2015) and adapt deliveries accordingly. o Calculate tOPV stock down to the district level, if possible. o Include inventory held by private-sector suppliers. Adjust delivery: Based on the first inventory, adjust the next delivery from the tOPV supplier so there is enough tOPV to last until end of February 2016. Final tOPV inventory: Conduct a second tOPV inventory ~6 months before switch (Oct/Nov, 2015). Adjust final delivery: Based on the second inventory, make any additional orders and adjust the final tOPV delivery for Feb to April, and redistribute tOPV in-country, as needed. o Buffer: Include 2 weeks of buffer (one week central and one week district) o Lead time: The timing of the order should be in line with supplier’s advice to arrive at least two months prior to the switch o Horizontal re-distribution: Consider redistribution of tOPV from regions with excess stock to regions with insufficient stock. bOPV: Order bOPV ~6 months before the switch so there is ~3-6 months supply to use after the switch (see Section 3.2). 3.2 Plan bOPV procurement and distribution 3.2.1 Countries procuring bOPV through UNICEF In most cases, countries will receive 3-6 months of supply for the first order of bOPV. Countries receiving only 3 months’ supply will need to receive several more shipments of bOPV to fill the supply chain. This will need to be treated as a new vaccine introduction with additional deliveries to fill the supply chain. During the two-week period prior to National Switch Day, both bOPV and tOPV may be together in the vaccine cold chain at the periphery. Presence of both vaccines will be longer (~2 months) at major storage points at the central level. 15 To minimize the time that both tOPV and bOPV will be in the cold chain at the periphery, some countries may consider exchanging bOPV for tOPV a few days prior to the switch. For example, staff responsible for maintaining vaccine stock at the periphery would go to the district level to return residual tOPV and collect bOPV. Countries should have sufficient financing to procure bOPV by March 2016 latest while maintaining tOPV requirements through Q1/April 2016. Countries that have bOPV stock from prior campaigns could consider using this stock in the routine program. To minimize the time that both tOPV and bOPV have to be in the cold chain together, the following steps are suggested: Procure bOPV 6 months prior to the switch (Oct-Nov 2015)*: order at least 3-6 month supply of bOPV (e.g., first 3 month supply + 1 month of buffer) Plan for bOPV to be delivered 1-3 months prior to the switch Distribute bOPV to the periphery two weeks prior to the Switch Remove all tOPV from the cold chain on the switch day NOTE: Self-procuring countries have completely different timelines than UNICEF and their procurement laws may not be conducive to flexible procurement. 3.2.2 Self-procuring countries Self-procuring countries may need to conduct additional activities when developing their procurement plans, tenders and contracts with suppliers: Determine tOPV supply needs through April 2016. Determine lead times required for changing product type. Determine payment schedules (100% upon signature with supplier or partial payment upon delivery). Investigate procurement laws and determine the feasibility of submitting amendments to contracts to convert tOPV to bOPV in line with the switch. Notify the department responsible for procuring vaccines as soon as possible so orders can be adjusted. For new tenders and contracts with suppliers, build in flexibility with suppliers to adjust and change product type (e.g. convert any excess tOPV orders into bOPV). 3.3 Establish support mechanisms 3.3.1 Secure funds The national switch management committee is responsible for securing funds to implement national switch plan activities. These activities include hiring additional staff, managing logistics, assessing tOPV inventories and determining tOPV and bOPV supply needs, and covering costs associated with additional shipments to countries, waste management, and training. 3.3.2 Establish a switch support team National authorities will need to hire or delegate staff at national and regional levels to conduct preparatory and implementation activities related to the switch. These staff will comprise the switch support team (SST). The primary function of the SST is to support the MOH and switch management committee in: 1. Making reliable inventories of tOPV at regional, district and service provider level 16 2. Strengthening vaccine management 3. Assisting with the switch in all relevant domains: logistics, social mobilization, training, etc. The number of members on the SST can evolve during the process, with more members at a central level in the initial phases and increasing number of persons at peripheral levels closer to the switch. Staff at the central level will require strong communication skills. Staff at regional and peripheral levels should be literate and credible candidates such as teachers and students. 3.3.3 Develop and implement a communications strategy A strategic communications and advocacy plan should be a key component of the national switch plan. This plan should describe key stakeholders and elaborate on how the country will share information with them. Stakeholder consultations: As soon as possible, the communications sub-committee should organize meetings and consultations to inform health staff, partners, NGO, private sector and other groups potentially involved or affected by the switch. Consultations with key decision-makers and scientific community should be organized early to obtain buy-in before the switch. Materials: In parallel, the sub-committee can adapt or create contextually appropriate messages and materials to support meetings and consultations on the switch. Existing tools including global and regional materials can be leveraged (see Annex 3 for an example), such as FAQs, fact sheets, training materials, videos, posters, and labels. Cold chain personnel, logisticians, and health worker training: staff responsible for developing communications materials and strategy should closely link with those developing the training materials for health workers to ensure that switch dates, procedures, and messages about the rationale for the switch are coordinated. Materials to support national planning of communication activities are available at: http://www.who.int/immunization/diseases/poliomyelitis/endgame_objective2/oral_polio_vaccine/implementation /en/ 3.4 Manage logistics 3.4.1 Develop training materials Training EPI Logisticians Training EPI logisticians will be an important component of a successful switch. This should occur ~6 months prior to the switch, around 4Q 2015 but may occur in several phases depending on the country and the target groups identified for training. Using the Logistics guide, develop training materials that cover: Stock Inventory Estimating tOPV needs until switch and bOPV after the switch Distribution of last shipment of tOPV and first shipment of bOPV to lower levels Continegency plans (eg buffer stocks, availability of surge transport mechanisms) Use of push of pull mechanism for exchange of tOPV and bOPV Handling of tOPV after the switch tOPV disposal 17 Training health workers Because health staff will likely be confronted with many questions regarding the switch, they should also be prepared to offer answers to basic questions. Training activities should address both the rationale and the practical implications of the switch, leveraging existing materials where possible. Rationale for the switch and relevance to polio eradication Date to start using bOPV and stop using tOPV (National Switch Day) Suggestions for how to make best use of storage capacity in the weeks prior to the switch when both tOPV and bOPV will be in the cold chain together Strategies to ensure bOPV is not used prior to the switch and tOPV is not used after the switch Procedure for handling tOPV after the National Switch Day o Remove from cold chain o Mark with sticker o Send to nearest disposal site according to procedure An information packet for health workers could be used to reinforce training. Basic materials to consider including in the information pack are listed below (and see Annex 3): Powerpoint overview with key messages FAQs Guidelines on collection and disposal of tOPV and data recording Job aid to support tOPV removal and interactions Global templates that may be adapted for training are available at: http://www.who.int/immunization/diseases/poliomyelitis/endgame_objective2/oral_polio_vaccine/implementation /en 3.4.2 Assess cold chain capacity Cold chain capacity to store both bOPV and tOPV during these 2 weeks prior to the switch will be short-term in nature, and for this reason renewal of equipment will likely be unnecessary, specifically since many countries will likely have increased capacity for IPV introduction. Countries that have done regular SIAs have a storage capacity sufficient to cover a National Immunization Day (NID) equaling five birth cohorts. These countries should have sufficient capacity to store one-quarter of a cohort (3 months of bOPV) for the switch. In some situations, such as when countries may need to do a pre-switch tOPV campaign, cold chain capacity may be insufficient. The following steps may offer relief: Use the WHO forecasting tool for cold chain capacity in “scenario mode” showing an overlap of tOPV and bOPV to spot the potential gaps in cold chain capacity. Increase the frequency of deliveries and reduce the size of each shipment. Make best use of existing vaccine cold chain capacity by removing expired products and products not related to vaccination. Minimize excessive cold-water storage and limit suboptimal use of refrigerators and freezers. Repair equipment with minor defaults. Reallocate equipment to ensure that each service point has adequate temporary storage capacity. 18 3.4.3 Update information systems Switching from tOPV to bOPV may require updating the forms, vaccination cards, or electronic databases used for recording and reporting OPV administration, forms for ordering vaccines, and vaccine stock ledgers, and any other forms that list the national immunization program vaccines. The following materials may need to be updated prior to the switch: Patient registers Vaccination cards Tally sheets Stock ledgers Electronic databases Vaccine management systems 3.4.4 Develop disposal strategy A tOPV disposal strategy should be informed by current waste management capacity and expected disposal volume. Countries are advised to assess their waste management systems and estimate disposal volume before developing a disposal strategy. The following formula can be used to estimate disposal volume: Estimating tOPV disposal volume. For regions applying the multi-dose vial policy (MDVP): Total litres of tOPV for disposal = 0.005 x wks of tOPV supply to dispose x target population/1000 For regions not applying the MDVP: Total litres of tOPV for disposal = 0.0075 x wks of tOPV supply to dispose x target population/1000 Assumptions: Based on 3.5% newborns, 4 dose EPI calendar, 85% coverage, 30% wastage and 1.5 cc volume per dose including packaging, disposal volume is 0.005 L per 000' population for regions applying the MDVP, 0.0075 L per '000 for others not applying the MDVP. Determine appropriate disposal strategy: Disposal of tOPV after the switch should follow national legislation. If national legislation does not provide clear guidance, this section of the guide discusses safe approaches for the disposal of tOPV. tOPV MUST be inactivated 2 prior to disposal. . The following are the recommended methods for the inactivation and subsequent disposal of tOPV: • Inactivation by: autoclaving, boiling, chemical inactivation, encapsulation or incineration • Disposal by: transporting to waste facility or burying The inactivation and disposal of tOPV can be summarized through the following four steps: Step 1: Evaluate volumes of tOPV vials to be destroyed Step 2: Determine materials of tOPV vials to be destroyed Step 3: Choose appropriate method to inactivate tOPV Step 4: Dispose of the inactivated tOPV vials 2 Inactivation of tOPV is defined as eliminating the infectious nature of poliovirus in tOPV or otherwise rendering the tOPV vials unusable and inaccessible (encapsulation) 19 Step 1: Evaluate volumes of tOPV vials to be destroyed Volume of tOPV to be disposed Small volume of tOPV defined as 20 vials or less, allow for local level disposal at facility level Large volume of tOPV defined as 20 vials or more, may require additional capacity for disposal of tOPV Step 2: Determine materials of tOPV vials to be destroyed Glass vials- may shatter and harm the operator or may melt and cause damage to the incinerators Plastic vials- incineration or burning of plastics is prohibited in some countries3 Sealed vials -may explode under pressure (incineration & autoclaving) and endanger the operator4,5 Open vials- will allow for safe inactivation of tOPV by any method. However, staff should handle open vials as hazardous infectious waste and take precautions (e.g. wearing personal protective equipment) Step 3: Choose appropriate method to inactivate tOPV tOPV inactivation can be achieved by, autoclaving, boiling, chemical inactivation, encapsulation or incineration of the tOPV waste. The ideal use and drawbacks for each of these methods of inactivation is summarized in the table below: Method Autoclaving Ideal Use Boiling Autoclaving should be done in a large autoclave with integrated shredder. Alternatively, vials can be opened and treated in any autoclave. Boil unopened vials Drawbacks Chemical Inactivation Encapsulation Incineration Chemically inactivate opened vials using bleach or other chlorine solution at the recommended concentrations (0.5%). Encapsulate unopened vials in containers filled with concrete. Incinerate in a high-temperature incinerator capable of safely handling glass (such as a rotary kiln incinerator). Unopened/unshredded vials may not be fully inactivated in an autoclave, especially if the autoclave has been densely packed with other waste that could act as an insulator. Closed glass vials may explode under pressure if unopened. Boiling may be impractical for treating large quantities of vials. Operators must be careful to avoid scalding Expensive for processing large quantities of vials and requires operators to be trained in using chlorine solution. Chlorine solution must be safely disposed of Concrete-filled containers must still be securely buried. Melted glass can damage incinerators at temperatures <1100°. Closed glass vials can explode under pressure if unopened Plastic vial incineration is prohibited in many countries due to toxic emissions. 3 Stockholm Convention, Article 5 & Annex C, Part II, (a): http://www.pops.int/documents/convtext/convtext_en.pdf 4 Guidelines for Safe disposal of Unwanted Pharmaceuticals in and after Emergencies, WHO 1999 Safe management of wastages from health-care activities, WHO 2013 5 20 How each method works: Autoclaving uses high-temperature steam. It is the most environmentally friendly method. Glass vials full of liquid (i.e. not opened) should be “loosened” before autoclaving to avoid rupture, unless the autoclave has an integrated shredder. However, vials (plastic or glass) that contain little liquid do not need to be open. After autoclaving, vials will be sterile but must still be disposed of following national or local waste management guidelines for municipal waste. Boiling involves immersing vials in boiling water for approximately 30 minutes, which destroys pathogenic microorganisms6. Both glass and plastic vials can be safely boiled. Glass vials can be boiled without opening. After boiling, the inactivated vials should be disposed of following national or local waste management guidelines. Chemical inactivation of tOPV involves opening and immersing tOPV vials in 0.5% chlorine solution for at least 30 minutes. The solution should be 9 parts clear water to 1 part household bleach. Immersing 20 vials in 4 liters of solution will safely inactivate tOPV. After this treatment, vials and leftover chlorine solution must both be disposed of following national or local waste management guidelines. Incineration should be done, at 1100°C or more for safe destruction of glass vials with tOPV (e.g. rotary-kiln incinerators and industrial furnaces). It is important to note that Incinerators vary in temperatures reached in primary waste chamber. For instance, low temperature burning (<800°C), which is not recommended because it is environmentally hazardous (e.g. single chamber cement or brick covered incinerators). Additionally, medium temperature burning (800-1100°C) using dual-chamber incinerators may cause glass vials to explode or partially melt, and it is not recommended. Plastic vial incineration may be prohibited in some countries due to toxic emissions but is possible at medium and higher temperatures (>800°C) if permitted by national emissions guidelines. Also, co-incineration in industrial furnaces (e.g. cement kilns) will both inactivate and destroy tOPV vials and can be done in partnership with an industrial facility. The resulting ash and any other post-incineration residue must be treated as toxic waste and disposed of according to national or local waste management guidelines Open pit burning of plastics can have a severe negative environmental impact should not be used as an inactivation method Encapsulation disposes of tOPV without immediate inactivation (and without opening the vials) but makes it inaccessible and puts it beyond use. This method involves filling containers ¾ full with tOPV vials, adding an immobilizing material (e.g. sand, cement, or clay) and sealing and burying the containers. The encapsulated waste must be disposed of following National or local waste management guidelines for municipal waste Step 4: Dispose of the inactivated tOPV vials Countries should select appropriate sites for the disposal of remaining inactivated tOPV using one of the following two approaches: 6 Transport the waste materials to a waste facility (e.g. sanitary land fill, municipal dump, industrial waste site, or other facility meeting national and local waste guidelines); or Bury the waste materials on-site in a secured and fenced-off burial site http://www.cdc.gov/hicpac/pdf/guidelines/disinfection_nov_2008.pdf 21 3.5 Monitoring of the switch 3.5.1 Monitor planning and implementation process Process monitoring should be done at the national and regional level. The national and regional switch management committees or ICC are responsible for selecting, monitoring, and reporting on indicators (see box on right) and milestones (see below) based on the country situation. All sub-national monitoring efforts should feed back to the national switch management committee. This committee or the ICC then can report to the WHO and UNICEF country offices on a few agreed upon indicators relevant to global planning such as developed plan, completed tOPV inventory, and vaccine delivery as requested. A sample process monitoring tracking sheet and road map is available on: Process Monitoring Purpose: Monitoring switch planning and implementation Responsibility: Switch Management Committees or ICC Potential indicators: o National plan completed o Budget determined o OPV procurement plan completed o tOPV inventories completed o Disposal plan completed o Vaccine delivered o Training completed Reporting: o Monthly to ICC, until Feb 2016 o Weekly from March 2016 http://www.who.int/immunization/diseases/poliomyelitis/endgame_objective2/oral_polio_vaccine/monitoring/en/ Suggested key milestones to track in process monitoring: tOPV procurement plan drafted; first tOPV inventory completed (Mar-Apr 2015)* Switch budget submitted to national authorities (June 2015)* bOPV is licensed/registered or country accepts pre-qualified product (July 2015)* Budgeted national switch plan is endorsed (by Sept 2015) Country budget approved (Oct 2015) Switch Support Team established (Oct 2015) Second tOPV inventory completed (Oct-Nov 2015) bOPV ordered (Oct-Nov 2015) Funds arrive at sub-national level (Feb 2016) bOPV delivered at national level (Jan-Mar 2016) Switch monitors trained (March 2016) bOPV use starts at all vaccination points on National Switch Day (April 2015) Validation data reviewed (April 2016) *NOTE: these activities must begin in parallel with drafting and finalization of the national switch plan 22 3.5.2 Monitor outcomes The removal of tOPV from all delivery facilities is a country responsibility. The chain of reporting and accountability for tOPV withdrawal is within the existing MOH structure – e.g., from Immunization Officer at the Service Delivery the District Immunization Officer Regional Officer MOH. The MOH reports confirmation of validation to the WHO country office which reports through the appropriate chains to the World Health Assembly. To ensure rigour and support the MOH in the validation process, WHO recommends MOH establish a National Switch Validation Committee (NSVC) which is authorized by the government to independently collect and validate data on tOPV removal. The NSVC validates removal of tOPV from the cold chain. Validation involves evaluating data collected by staff hired by the MOH (i.e., Switch Monitors) who are independent from the switch process to the extent feasible by the MOH. Independent Monitoring and Validation Purpose: validate tOPV recall Responsibility: National Switch Validation Committee (NSVC) and MOH Potential indicators: o Absence of tOPV in certain proportion of storage and service facilities validated by switch monitors Reporting: o NSVC and MOH to submit validation to WHO within 2 weeks of the Switch Validation will occur during the 2 weeks after the National Switch Day. Identify switch monitors: Switch monitors are responsible for visiting storage facilities to confirm recall and disposal of tOPV. One month prior to the switch, switch monitors should be identified. Switch monitors should be independent from the MOH and must have credibility. A national or partner health official can recommend switch monitors and verify that person has performed well in a previous activity in a similar capacity. Once all switch monitors are identified, a roster of Independent Switch Monitors (SM) should be created in line with the independent monitors of SIA. Develop a micro-plan for the SMs: o Site selection: The recommended monitoring strategy includes verification that tOPV is removed from the cold chain at all vaccine stores down to the district level. Due to a large number of service points, higher risk facilities will be selected (10% recommended) by the Monitoring Coordinator/Supervisor to be visited by the SMs. o Data collection and reporting (see example forms in Annex 4): Flow of data from SMs to NSVC using these forms entails: Form 1: An independent monitoring data collection tool Completed by independent monitors Submitted to supervisor/coordinator at the administrative level on a daily basis Form 2: A National Switch Validation data aggregation tool Completed by coordinator after independent monitoring at all subnational and national levels Submitted for review by the National Switch Validation Committee (NSVC) or National Certification Committee (NCC) or other designated Committee Form 3: A National Validation Report After review by the NSVC/NCC or Form 2, this form should be completed by the National authorities and signed by the designated government authority and NSVC Government should submit form WHO Country Office 23 o Develop contingency plans: Protocols should be developed for follow-up of sites that cannot be visited on schedule and for corrective action if tOPV is found by independent monitors. Monitoring guidelines7 are available to offer more guidance for decision makers. More information on developing a national monitoring plan, training independent monitors and reporting validation of tOPV recall available at: http://www.who.int/immunization/diseases/poliomyelitis/endgame_objective2/oral_polio_vaccine/monitoring/en/ 7 Guidelines for developing a national monitoring plan http://www.who.int/immunization/diseases/poliomyelitis/endgame_objective2/oral_polio_vaccine/implementation/ en/ 24 4 Phase three: IMPLEMENT IMPLEMENT PLAN PREPARE (2 weeks before Switch to Switch day) VALIDATE Train switch monitors Distribute bOPV to peripheral Train health workers Organize communications and media events Implement National Switch Day 4.1 Train switch monitors Two weeks prior to the switch, initiate training of the previously-selected independent switch monitors. The monitors should be trained on: Roles and responsibilities Verifying the absence of tOPV at selected facilities Following country protocols for corrective action if tOPV is found Communicating and reporting outcome of facility visits to supervisor through data collection tool 4.2 Distribute bOPV to all peripheral levels Two weeks prior to the switch, begin distributing bOPV to all service facilities. During this period, both bOPV and tOPV will be in the cold chain across the country. To ensure sufficient cold space, service points should be encouraged to remove expired products, and products not related to vaccination. 4.3 Train health workers Use approaches similar to other vaccine introductions and SIAs (e.g., cascade training) to train health workers on relevant aspects of the switch. To prepare for the training: Develop materials in advance (see Section 3.3.1) Reserve a full day for training Notify participants in advance 25 Book a venue Set a training agenda Invite at least one health worker per facility Set a maximum limit per training session Ensure objectives are understood 4.4 Organize communications and media events On the National Switch Day, countries may want to broadly disseminate key reminders related to the tOPV removal and disposal from all service facilities. Organizing media and press activities as a strategy to remind and motivate vaccinators could also be considered. 4.5 Implement National Switch Day On switch day all tOPV should be taken out of the cold chain so that it no longer claims storage capacity. Although tOPV will lose its potency quickly outside the cold chain, precautions should be taken to ensure that nobody could inadvertently get a dose of tOPV that has been outside the cold chain. Place a sticker (see below example figure) on the tOPV primary packaging and transport vaccine out of the cold chain to the agreed site for disposal (see Section 3.4.4). 26 5 Phase four: VALIDATE PLAN PREPARE VALIDATE IMPLEMENT (during 2 weeks post switch) Validate tOPV removal Report validation to WHO 5.1 Validate tOPV removal Trained switch monitors are responsible for validating the appropriate disposal of tOPV at randomly selected sites according to independent monitoring micro-plans (see Section 3.5.2). Validation should occur during the two weeks following the National Switch Date. MOH should obtain confirmation of tOPV withdrawal from the country through their standard chain of accountability (e.g., district and regional immunization officers). In addition, WHO recommended independent monitoring should be employed to independently confirm a successful switch. Select and visit sites to validate tOPV free Record tOPV information Properly dispose of residual tOPV Report validation results to NSVC by the National Validation Day, exactly two weeks after the National Switch Day (see figure below) 27 5.2 Report Validation During the two weeks after the National Validation Day, the NSVC is responsible for collating and analyzing the validation data collected by the SMs. Following data analysis, the NSVC will either: Validate the country tOPV free and report status to the WHO country office OR Recommend activating contingency plans for addressing remaining stocks of tOPV 28 Annex 1: Sample Terms of Reference for Switch Management Committees and Support Teams Sample Terms of Reference (TORs) for the National Switch Management Team or ICC Inter Agency Coordination Committee (ICC) Members Responsibility - Presided by high-level staff from the Ministry of health, the ICC should be composed of high-level staff from relevant ministries (communication, sanitation, etc.), partners, and major NGOs. - Elaborate the national switch plan with clear functions, responsibilities and deadlines - Establish an operations room for coordination, information and communication Meeting Frequency With increasing frequency from monthly in the early phase to daily during the switch. - Take final responsibility for implementation - At least one SST member (see below) should be invited - Report to higher-level authorities to the ICC to ensure - Communicate with partners and the adequate information flow press between the planning and - Monitor progress using a dashboard implementation levels. with key indicators (e.g., vaccine ordered and supplied, funds arrived, etc.) - Take corrective action when needed 29 Sample TOR for Switch Support Team 6-12 months prior to switch 2 months prior to switch During the switch After the switch National and Regional level District level District level District, regional and national level National level: - Co-organize with the ICC a full day meeting with regional health staff and administrative authorities to explain the switch. - Help compile stock inventories. - Participate in ICC meetings. - Ensure adequate information flow between national and regional levels. Co-organize with the ICC subcommittee and the RSC an information meeting with all service providers. Service providers should be asked to bring their vaccine stock records. - Same activities as before, but focused on risk areas. - Ensure availability of enough vaccine carriers on the day of the switch. - Confirm disposal sites are ready. - Ensure availability of updated stationary and forms. - Inform higher-level officials of anything that could derail the switch. - Visit an agreed proportion of service points to confirm the absence of tOPV. - Assist at district level to ensure all tOPV (routine and SIA) is sent back to regional level within 6 days. - Make a simple report on the switch at district level and share the report with superiors. - Move to the regional level and support all activities related to the tOPV removal. Regional level (visits to all districts in a region): - Organize a half-day meeting with local health staff and administrative authorities to explain the switch. - Make a tentative inventory of tOPV stocks. - Make an estimate of monthly consumption. - On that basis, estimate remaining tOPV requirements (plus a margin of two weeks), and bOPV requirements for the first three months after the switch. - Share the data with the EPI focal point and UNICEF. - Discuss stock management procedures with the EPI focal point and stock manager using a simple checklist. Visit all districts as well as an agreed proportion of immunization service points to: 1. Ensure the district and service points are aware of the switch and have the necessary communication materials. 2. Ensure the district received the necessary stationary for bOPV. 3. Confirm that all service providers including private clinics or whoever else might give polio vaccine have been informed about and are prepared for the switch. 4. Refine the OPV inventory and share inventory data with the EPI focal point and UNICEF. 5. Ensure districts storage capacity is sufficient when both products are present and adequate steps are taken when it is not. 6. Discuss stock management procedures with the EPI focal point and stock manager using a simple checklist. 30 Annex 2: Briefing note on the switch Preparing for the withdrawal of all oral polio vaccines (OPVs): Replacing trivalent OPV (tOPV) with bivalent OPV (bOPV) In May 2012, the World Health Assembly declared the completion of poliovirus eradication to be a “programmatic emergency for global public health” and called on the Director General of WHO to develop a comprehensive polio endgame strategy. The Global Polio Eradication Initiative’s Polio Eradication and Endgame Strategic Plan 2013-2018, approved by the Executive Board of WHO in January 2013, requires the phased removal of all oral polio vaccines (OPVs). This will eliminate the risks of vaccine-associated paralytic polio (VAPP) and circulating vaccine-derived poliovirus (cVDPV). If not already underway, planning for OPV cessation must start now, while efforts are being intensified to interrupt transmission of the remaining strains of wild poliovirus. Preparation for the removal of OPVs includes introducing at least one dose of inactivated polio vaccine (IPV) into routine immunization programmes in all countries by the end of 2015. The Endgame Plan requires the removal of all OPVs in the long term, beginning with a switch from trivalent OPV (tOPV) to bivalent OPV (bOPV), removing the type 2 component (OPV2) from immunization programmes. After all wild polioviruses have been fully eradicated, then all OPVs will be withdrawn. The current target date for the switch to bOPV is April 2016, during the ‘low’ season for poliovirus transmission in many countries with endemic polio or recent polio cases. The rationale for OPV withdrawal 2014-2015 April 2016 Introduce IPV Replace tOPV with bOPV 2019-2020 Withdraw OPV Ongoing routine immunization strengthening Currently, 145 countries use tOPV to vaccinate children against polio in their routine immunization programmes. tOPV contains all three poliovirus serotypes (1, 2 and 3), and the use of this vaccine has led to the eradication of wild poliovirus type 2 (WPV2), with the last case occurring in 1999. The last detected case of WPV3 was in 2012. Furthermore, four of the six WHO regions have been certified as polio-free. Even as the remaining strains of wild poliovirus are being eradicated, the switch from tOPV to bOPV will be a major step to combat cVDPV and VAPP. Over 90% of cVDPV cases, and approximately 40% of VAPP cases, are due to the type 2 component of tOPV. The type 2 component of tOPV also interferes with the immune response to poliovirus types 1 and 3. Given the risk the type 2 component of tOPV poses to a world free of WPV2, tOPV will be replaced in routine programmes and supplementary immunization activities (SIAs) by bOPV. bOPV contains type 1 and 3 serotypes only, to help stop transmission of WPV1 and 3, and to reduce the risk of VAPP and cVDPVs. The introduction of IPV will help to reduce risks associated with the withdrawal of OPV type 2, facilitate interruption of transmission with the use of monovalent OPV type 2 in the case of outbreaks, and hasten eradication by boosting immunity to poliovirus types 1 and 3. 31 Preparing for the switch The primary risk associated with the cessation of use of type 2 OPV is the re-introduction of disease-causing type 2 poliovirus into a population with increasing susceptibility to type 2 poliovirus. The switch from tOPV to bOPV must therefore be globally synchronized to minimize the risk of new cVDPV type 2 emergence. As soon as possible, countries are advised to develop operational plans for implementing the switch, involving all relevant national entities (for example, the Inter-agency Coordination Committee). Early preparation of national plans will help establish clear timelines for: Vaccine supply planning, including close ongoing management and monitoring of tOPV inventories and requirements up to April 2016 Calculating projections of bOPV needs Procuring bOPV (for self-procuring countries) Planning and budgeting the collection, transport, storage, and proper disposal of tOPV once withdrawn from the cold chain Training health workers on the rationale and process of the switch Communicating with local experts and other stakeholders Registration of bOPV for routine use Currently, bOPV is only licensed for use in supplementary immunization activities. Based on clinical data, the labelling of bOPV is expected to be revised by mid-2015 to enable use of this vaccine in routine immunization. While formal licensing and national registration procedures are underway, countries will be encouraged to accept the use of this vaccine on the basis of WHO prequalification. Planning for a final procurement of tOPV Countries should plan their forecasts and procurement in a way that aims to minimize any residual tOPV stocks on hand by April 2016, while avoiding stock-outs prior to the switch. Minimal tOPV stocks will reduce the costs and logistics of disposal of all remaining unused tOPV after the switch. KEY DATES March 2015 National authorities begin operational planning. May 2015 The World Health Assembly considers a resolution on the switch. September 2015 National plans are finalized. October 2015 SAGE will assess the epidemiology of persistent type 2 cVDPVs as part of a readiness review. April 2016 Expected date for switch from tOPV to bOPV. April and May 2016 Validation of the removal of all tOPV from the cold chain. From May 2016 tOPV will no longer be used globally, neither in routine immunization, nor in SIAs. For countries procuring through UNICEF or PAHO Revolving Fund, close coordination and sharing of stock levels with UNICEF and PAHO country offices is critical to minimizing excess stocks of tOPV remaining in April 2016. For self-procuring countries, forecasts should be shared and jointly reviewed with vaccine suppliers to help facilitate the timely procurement of appropriate amounts of tOPV and bOPV for the transition. WHO and UNICEF will be available to facilitate this process as required. Technical assistance and guidance on aspects such as operational planning, stock management, and communications will be shared in due course. 32 Annex 3: Sample key messages for health staff The success of the switch will largely depend on the understanding health staff at various levels has concerning the event and the crucial role they play in it. It is therefore of the uttermost importance that the MOH issues a memo or brief guideline to all health professionals (including the private sector) in which the following key messages appear: Within the context of the Global Polio Eradication Initiative, the World Health Assembly has issued a resolution stipulating that all tOPV (containing types 1, 2 and 3) used for routine immunization or SIA should be replaced by bOPV (types 1 and 3). This event is called the switch. It is a global event, which in our country will take place {insert National Switch Date}. This means that beginning on that date, no more tOPV will be used anywhere and for any progamme, neither private nor public, in the country. Distribution of bOPV will begin 2-4 weeks prior to the switch. You will be informed when you will be supplied. On switch day you will: o Stop using tOPV and start using bOPV instead; o Take all tOPV out of the cold chain; o Mark all tOPV with the stickers supplied with for that purpose. All tOPV will be removed from the cold chain and safely disposed of in approved disposal sites. You will be given separate guidance on how to dispose of tOPV. It is strictly prohibited to immunize children with tOPV on or after switch day in any circumstance, whether it is to finish remaining stocks or because you were not supplied with bOPV. Independent Switch Monitors will visit all health structures with potential stocks of tOPV for routine or SIA to verify the absence of tOPV stocks. If 2 weeks after the switch you still have tOPV and/or you were not visited by a Switch Monitor, you must inform your superior immediately. 33 Annex 4: Sample validation forms for tOPV Form 1: Sample Independent Monitoring Data Collection Tool Date of Monitoring: ____________________ Name of Monitor: _____________________________ Level of cold chain: Primary: _____ Sub-National (Regional/Provincial): _______ Lowest distribution level (District): ______ Service Delivery Point (Fixed site): ________ Name of administrative level: ____________________________ Store Location or Name tOPV in cold chain (Yes = 1 No = 0) tOPV out of cold chain without label “Do not use” (Yes = 1 No = 0) bOPV in cold chain (Yes = 1 No = 0) IPV in cold chain (Yes = 1 No = 0) # vials disposed or pending disposal at time of monitorin g # vials destroyed at service point by report date Disposal method (Multiple codes okay)* A B C D E F G H Corrective actions** (Multiple codes okay) Status (ongoing or complete d Due date, if ongoing I J K 1 2 3 4 5 6 7 8 9 10 TOTAL # stores *Codes for disposal method: (1): Autoclave (2): Boiling (3): Incineration (4): Encapsulation (5): Burial (6): Burning (7): Other **Codes for corrective action: (1): tOPV withdrawn (2): Onsite re-training (3): Officials at higher administrative level notified (4): Other (please specify) 41 Draft National Switch Data Aggregation Tool & Report_11 Feb 2016 Form 2: Sample NATIONAL Switch Validation Data Aggregation Tool SECTION 1 – Vaccine Stores Table 1: Aggregate INDEPENDENT MONITORING data for vaccine stores to lowest distribution level (excluding service points) Vaccine Stores Monitored Indicators tOPV in cold chain Total # stores Administrative Level A B # stores C % # store s D E tOPV out of cold chain without label “Do not use” %* # stores F G bOPV available % # stores H I IPV available %* # stores J K Disposal of tOPV %* # vials withdrawn for disposal by report date Disposal method (Multiple codes okay)** L M N Primary (National) Sub-National (Regional or Provincial) Lowest distribution level (District) *denotes percent of monitored stores **Codes for disposal method: (1): Autoclave (2): Boiling (3): Incineration (4): Encapsulation (5): Burial (6): Burning (7): Other Table 2: Corrective action (to the lowest distribution level, excluding service points) If tOPV is found in the cold chain or outside it without labeling Level of cold store Location of cold store Corrective actions implemented*** (Multiple codes okay) Status (ongoing or completed) Due date, if ongoing 1 2 3 4 5 1. 2. 3. 4. 5. 6. ***Codes for corrective action: (1): tOPV withdrawn (2): Onsite re-training (3): Officials at higher administrative level notified (4): Other (please specify) 42 Draft National Switch Data Aggregation Tool & Report_11 Feb 2016 SECTION 2 – Service Delivery Points (ie, health centers with fixed vaccination services): Table 3: Aggregate INDEPENDENT MONITORING data for service delivery points by region (or district if desired by country) Indicators # Monitored tOPV in cold chain Total # Region A B # points C % # points D E tOPV out of cold chain without label “Do not use” %* # point s F G bOPV in cold chain % # point s H I IPV in cold chain Disposal of tOPV %* # point s % * # vials withdrawn for disposal by report date # vials destroyed at service point by report date J K L M N Region 1 Region 2 Region 3 *denotes percent of monitored stores Table 4: If tOPV sweep is required in district, list corrective action: District Number of service points swept Corrective actions implemented** Status (ongoing or completed) Due date, if ongoing B B C D E 1. 2. 3. 4. 5. 6. 7. 8. **Codes for corrective action: (1): tOPV collected from all facilities (2): Onsite retraining at sites with tOPV in cold-chain or unlabeled for destruction (3): Officials at higher administrative level notified (4): Other (please specify) 43 Form 3: NATIONAL VALIDATION REPORT: Switch from tOPV to bOPV Action: Complete form and submit to WHO Country Office Responsible authority: Ministry of Health supported by National Switch Validation Committee Reporting deadline: 2 weeks after National switch date or latest 15 May 2016 Country: Date of Switch: Table 1: For each indicator identified below, check Yes or No. Please insert comments as appropriate: Indicators A B Yes No Comments Switch has been validated* by country If Yes, report date; If No, report additional corrective action needed & expected date of validation** C Independent monitoring used for Switch D Switch will continue to be monitored through routine EPI reporting E Switch Validation Committee reviewed validation data *Defined as 0% detection of tOPV in cold chain or outside without appropriate label **Codes for corrective action (multiple may be listed): (1) Region sweep (2) District(s) sweep (3) Re -training (4) Request for additional data (5) Other (please specify) Table 2: For each cold chain level, report aggregate INDEPENDENT national monitoring data on tOPV and bOPV after National Switch Day. Indicators Site monitoring Administrative Level Total # Monitored % A B C D tOPV in cold chain or outside without proper label bOPV at site IPV at site*** %* %* %* E F G Excess # tOPV vials disposed or needing disposal (at time of report) H Primary (National) Sub-National (Regional or Provincial) Lowest distribution level (District) Service delivery point (fixed vaccination services) ***If IPV has been introduced *Denotes percent of monitored sites National Switch Validation Committee Chairperson or designee (Name, signature, & date) Minister of Health or government designee (Name, signature, & date) 41 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 Instruction Sheet: National Switch Data Aggregation Form & Validation Report “Validation” of the Switch: Two forms are used to aggregate and report independent monitoring data collected within 2 weeks of the National Switch date and validation of the switch. The primary data indicators for validating the switch are 0% detection of tOPV in the cold chain or outside cold chain without appropriate label (fore example, “Do not use/Destroy”) at any level of monitored stores (as recommended in the WHO Monitoring Guidelines). If problems with the switch are detected, corrective action should be taken by the government. In addition, the monitoring and validation process is also an opportunity to ensure bOPV and IPV availability (if introduced). It is important to note that disposal is not expected to be complete before validation but receiving available data at the time of report is still useful. Form 1: Independent Monitoring Data Collection Tool: to be completed by independent monitors and submitted to reporting official at the administrative level on a daily basis Form 2: National Switch Data Aggregation Tool: to be completed by National authorities after independent monitoring at subnational levels. Data form should be submitted for review by the National Switch Validation Committee (NSVC) or National Certification Committee (NCC) or other designated Committee Form 3: National Switch Validation Report: After review by the NVSC or NCC of Form 2, this form should be completed by the National authorities and signed by the designated government authority. Government should submit form to WHO Country Office. Responsible Authority: National Government Action: Complete the two attached forms within 2 weeks of the National Switch Date, starting with Forms 1 and 2 which will inform Form 3. Forms 1 & 2: Independent Monitoring Data Collection & National Aggregation Tool Purpose: National EPI Program to aggregate data on Switch monitoring indicators submitted by subnational levels. Note: Subnational levels Form 3: National Switch Validation Report Purpose: To summarize findings of Switch Validation review by NSVC/NCC and MOH may modify the form for their own use. Action: Submit aggregation forms to NSVC/NCC within 1-2 weeks of the National Switch Date. Action: Complete after NSCV/NCC review, obtain relevant signatures, and submit to WHO Country Office within 2 weeks of National Switch Date (or latest by 15 May 2016) 42 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 Instructions for FORM 1 – Independent Monitoring Data Collection Tool: NOTE: These forms are intended to be used by the Independent Monitors. Complete separate form for each administrative level (primary, subnational, district, and service delivery points with fixed vaccination services). Complete a separate table for each administrative level being monitored. List: -Date of monitoring -Name of monitor -Select level of cold chain: Primary (National; Sub-National (Regional or Provincial); Lowest distribution level (District); or Service delivery point (Health post with fixed vaccination services) -List name or location of the administrative level: (eg, State Name, District Name) Column A: Location or Name of the cold store or service delivery point Column B: Is tOPV found in the cold chain? Yes = 1; No = 0 Column C: Is with tOPV outside cold chain, not properly packed in plastic bag or container labeled (eg, “Do not use/Destroy”)? Yes = 1; No = 0 Column D: Is bOPV found in the cold chain? Yes = 1; No = 0 Column E: Is IPV found in the cold chain? Yes = 1; No = 0 Column F: Total number of tOPV vials disposed or pending disposal at that level, by monitoring date. For service deliver points, this may be the number of tOPV vials returned (or planned) for destruction either to district cold chain store or to off-site waste management facility. The best estimate for this is likely the excess tOPV withdrawn based on the stock ledger. NOTE: To avoid double counting, do not include tOPV vials sent in to this level after the Switch Date from other levels for disposal. Column G: Number of tOPV vials that were destroyed on-site by report date, if any. Column H: Enter methods used for tOPV disposal using the codes provided, multiple methods can be recorded. Column I: List the corrective actions implemented**, in any, using provided codes. Column J: List the status of the corrective action as ongoing or completed Column K: If corrective action is ongoing, list anticipated due date of completion. Tally the totals for Columns B-G. Submit these forms on a daily basis to the reporting official for the administrative level being monitored. ** Note: According to the WHO Monitoring Guidelines: 1) Cold stores from National to the Lowest Distribution Level (District): 100% of the cold stores should be independently monitored. Corrective action should be taken for any tOPV in the cold chain or not properly packed in plastic bag or container labeled (eg, “Do not use/Destroy”). tOPV should be withdrawn from the cold chain and reported to the administrative official. 2) Service Delivery Points: Use the risk-based purposive sampling to monitor selected service delivery points or health posts with fixed vaccination services. If tOPV is found in the cold chain of the initial 10% of the selected monitoring sites and again in the subsequently selected 5% of the sites, then sweep (tOPV monitoring) of all service delivery points in the district is required in coordination with the administrative official for the district. 43 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 Instructions for FORM 2 -- National Switch Aggregation Tool: NOTE: These forms are intended to be used by the NATIONAL AUTHORITIES, using data from independent monitoring (Form 1), and may be modified for each administrative level (subnational and district) as deemed appropriate Step 1: Complete Section 1, Table 1: Aggregate INDEPENDENT MONITORING data for vaccine stores to lowest distribution level (excluding service points) Column A: Type of vaccine store, if the country have more that 3 levels of vaccine store then add more lines Column B: Total number of stores by level in the country Column C: Number of stores independently monitored Column D: Percent of stores independently monitored: (C/B)*100 Column E: Number of stores with tOPV in cold chain Column F: Of those monitored, % of stores with tOPV in cold chain: (E/B)*100 Column G: Number of stores with tOPV outside cold chain, not properly packed in plastic bag or container labeled (eg, “Do not use/Destroy”) Column H: Of those monitored, % of stores with tOPV outside cold chain not packed without label: (G/B)*100 Column I: Number of stores with bOPV in cold chain among those monitored Column J: Of those monitored, percent of stores with bOPV: (I/B)*100 Column K: Number of stores with IPV in cold chain (if IPV has been introduced in the country) Column L: Of those monitored, percent of stores with IPV among those monitored: (K/B)*100 Column M: Total number of tOPV vials disposed or pending disposal at that level, by report date. The best estimate for this is likely the excess tOPV withdrawn based on the stock ledger. NOTE: To avoid double counting, do not include tOPV vials sent in to this level after the Switch Date from other levels for disposal. Column N: List all methods of disposal used by this level for tOPV destruction using provided codes. Multiple codes may be selected. If other, please specify. Step 2: Complete Section 1, Table 2 -- Corrective Action: For corrective action taken at stores in each level, list the level of cold chain, location of the cold chain and the corrective actions implemented using provided codes. List the status of the corrective action (ongoing or completed) and if ongoing, due date of completion. Step 3: Complete Section 2, Table 3 Aggregate INDEPENDENT MONITORING (WHO Monitoring Guidelines) and DISPOSAL data for service delivery facilities with fixed vaccination services, by Region Column A: Region or Province name (if desired by country, these may be aggregated by District) Column B: Total number of total Service delivery facilities in country Column C: Number of service delivery facilities that were independently monitored Column D: Percent of independently monitored service delivery facilities: (C/B)*100 Column E: Number of sites with tOPV in cold chain Column F: Of those monitored, percent with tOPV in cold chain: (E/B)*100 Column G: Number of sites with tOPV outside cold chain, without proper label Column H: Of those monitored, percent with tOPV outside cold chain without proper label: (G/B)*100 Column I: Number of sites with bOPV in cold chain Column J: Of those monitored, percent with bOPV in cold chain: (I/B)*100 Column K: Number of sites with IPV in cold chain (if IPV has been introduced in country) Column L: Of those monitored, percent with IPV in cold chain: (K/B)*100 Column M: Number of tOPV vials returned (or planned) for destruction either to district cold chain store or to off-site waste management facility. Best estimate for this may be excess tOPV based on stock ledger Column N: Number of tOPV vials that were destroyed on-site by the service delivery facility by report date Step 4: Complete Section 2, Table 4: For corrective action taken at the service delivery level, list all districts that required sweep of tOPV according to the independent monitoring guidelines (eg, tOPV was found in the initial 10% of the selected monitoring sites and again in the subsequently selected 5% of the sites). For each sweep, list the district, 44 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 number of service points swept, and corrective actions implemented. Note: the form may be modified at district level to list the individual service points that had tOPV in the cold chain. Instructions for FORM 3 – National Switch Validation Report Responsible Authority: After review by NSVC/NCC of Form 2, Ministry of Health will complete this form and obtain the appropriate signatures from the Government designee and Chairperson of the NSCV/NCC Outcome of this report: is to Validate that tOPV is appropriately removed from the cold chain in the National EPI Program; secondary objective is to ensure bOPV is available at all levels. Reporting deadline: is within 2 weeks of the National Switch Date or latest 15 May 2016 Step 1: Complete Table 1: Check ‘Yes’ or ‘No’ for each indicator for the National Validation of the Switch. Insert comments as appropriate. Row A: Select if Switch has been validated by country after review by the NSVC/NCC or other designated Committee. The primary data indicators for validating the switch includes 0% detection of tOPV in the cold chain or outside cold chain without appropriate label (for example, “Do not use/Destroy”) at any level (as recommended in the WHO Monitoring Guidelines) with the locally implemented corrective action if necessary. Row B. If switch is validated, provide date of validation; if not validated, list planned corrective actions using provided codes and expected date of validation by country. Examples of corrective actions may include additional sweep of district(s) or region(s), or request for collection of additional data. Row C: State if independent monitoring was used to validate the switch. Row D: State whether the switch indicators will continue to be monitored through ongoing routine EPI reporting and supportive supervision. Examples may include: adding switch indicators to the monthly reports from health facilities to districts, and from districts to the next administrative level, as well as ensuring that supervisors and managers are monitoring for tOPV absence and availability of bOPV and IPV when assessing health facility’s information system. Row E: Select if the NSVC, NCC, or other designated committee reviewed switch validation data Step 2: Complete Table 2: Summarize the aggregated national data on tOPV using Form 1 (National Switch Data Aggregation Tool) and accompanying instructions. Column A: Administrative level for vaccine stores and service delivery points Column B: Total number of sites (vaccine stores and service delivery points) at each administrative level in country Column C: Number of sites (vaccine stores and service delivery points) that were independently monitored Column D: Percent of independently monitored sites: (C/B)*100 Column E: Of those monitored, percent of sites with tOPV in cold chain or without proper label: (E/C)*100 Column F: Of those monitored, percent of sites with bOPV: (F/C)*100 Column G: Of those monitored, percent of sites with IPV: (G/C)*100 Column H: Of those sites monitored, total number of vials of tOPV disposed or needing to be disposed Step 3: Obtain signatures from Chairperson of the NSVC/NCC (or designated committee) and the MOH designee who affirms National validation of the switch Step 4: Submit form electronically to the WHO Country Office. [Print these instructions on the backside of each accompanying form] 45 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 Annex 5: Template and chronogram for developing a national switch plan This generic template is to guide countries in developing a practical national plan for the tOPV-bOPV Switch. It is intended to provide suggestions for key areas to be considered, and as such, may be missing some items relevant to a particular country, or equally may contain some items that are not relevant. Executive summary of the National Switch plan Summary of the switch activities Date selected for the National Switch Day Overview of national coordination mechanism to ensure a successful switch Overview of monitoring and supervision mechanism Overview of validation mechanism Current procurement process (UNICEF or self-procuring) Budget and funding sources 1. Management, coordination and validation mechanisms 1.1. National management/coordination mechanism to ensure a successful switch Describe the national and sub-national level management structure and process to oversee and implement the switch, including any national and sub-national switch committees and/or subcommittees. Provide an organizational chart with roles and responsibilities for: o National and sub-national Switch Committees o Interagency Coordination Committees o Switch Support Teams Outline reporting and information flows and frequency Provide a workplan and timeline o Select the National Switch Day o Include the timeline/date for the withdrawal of tOPV and delivery of bOPV at each distribution level Explain how the switch activities are synergized with other planned public health and immunization activities, including new vaccine introductions. 1.2. Validation mechanism A description of the validation of tOPV withdrawal from routine immunization system including from the stores at the national and sub-national levels; All tOPVs are recalled including unopened intact vials, expired vials, partially used and empty vials; validate that no tOPV is left out or stored in a cold chain for use at any level; validate through review reports from programme/administrative reports, switch monitors reports, independent survey reports, etc. Describe the validation structure and process. Develop an organizational chart with roles and responsibilities and reporting structures of the: 46 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 o o o Independent National Validation Committee (can be the existing National Certification Committee for Polio Eradication (NCCPE) where it already exists or form a new committee of independent experts where it doesn’t). Should report to the Regional Validation Committee or the existing Regional Certification Commission for Polio Eradication (RCCPE). Switch Monitors (can be at different levels and composed of individual experts from partners, members of the pediatric association and other medical professional bodies, members of the national task force for laboratory containment for polioviruses, members of the national Expert Review Committee for Polio Eradication, former EPI managers, former EPI cold chain managers, former EPI cold chain engineers, faculty from public health schools/universities, representatives of private clinics, hospitals, laboratories, pharmacies, former SIA monitors and SIA monitor supervisors, etc.). Switch monitors may report back to the National Switch Committee. Develop a workplan and timeline for monitoring and validation activities. 2. Budget Summarize the budget and financing of the national switch. A template is provided in Annex 6. 3. Supply Analysis and Procurement Plan 3.1. tOPV supply analysis Indicate current tOPV supply mechanism (e.g., through UNICEF or self-procuring, identity of suppliers). Provide current tOPV stocks by primary, sub-national, and lowest distribution levels. Indicate whether an initial tOPV inventory has been completed or timeline for completion. Include private sector in supply analysis. Provide overview of current tOPV ordering and delivery schedules. 3.2. bOPV licensure and procurement State whether national vaccine licensure will be needed for bOPV for use in routine immunization, in addition to WHO prequalification, and if so, describe the procedure and its duration. State whether the country plans to accept the Expedited Procedure for national registration of WHOprequalified vaccines. Provide the actual licensure status of the bOPV that will be used. Indicate whether specific requirements apply with reference to local customs regulations, requirements for pre-delivery inspection, special documentation requirements that may potentially cause delays in receiving the vaccine. If such delays are anticipated, explain what steps are planned to handle these. Indicate the quantity of bOPV that will be required and whether procurement will take place through UNICEF or directly with suppliers. 47 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 4. Implementation preparation 4.1. Learning from past vaccine switches Indicate whether country has done a vaccine switch before and, if so, include any lessons learned. 4.2. Logistics Overview of cold chain capacity at district (3rd administrative level), provincial/regional (2nd administrative level) and central levels (national level). o Describe adequacy of storage and distribution capacity for tOPV and bOPV at each level of the cold chain, taking into account other planned vaccine introductions. Take into account the period during which both tOPV and bOPV will be stored simultaneously at national and some sub-national levels. o Where capacity is deficient, provide a plan to address. o Identify private sector facilities for vaccine storage. Provide a description of the transport system available for withdrawal of tOPV from public and private sectors. Describe transport system for delivery of bOPV to the periphery. Please address whether the frequency of deliveries needs to be increased or type of vehicle and vaccine carrier must be changed, and if so, whether there are sufficient funds, e.g. for vehicles, drivers, fuel, and per diem for distribution of the new vaccine at all levels. tOPV disposal: o Describe existing biological waste management processes and facilities at all levels. o Develop a plan for disposal of tOPV after withdrawal (follow the national guidelines for unused vaccine vials and empty vial disposal) 4.3. Updating information systems Review current recording of polio vaccination/vaccination card/health card and indicate whether cards will need to be updated. If cards currently refer to OPV, updating may not be required. 4.4. Communication materials and dissemination, partner and stakeholder engagement Develop a communications plan. Describe plans to sensitize political and opinion leaders at national, regional, and district levels on the switch, benefits to the population, and contribution to the Polio Endgame Strategy. Describe plans for addressing potential issues, including an outlined process for determining what constitutes an issue, who can respond to inquiries, particularly from the media, training spokespeople and identifying a point person to handle communication issues. Identify monitoring mechanism for communication activities. 4.5. Health worker training and supervision Describe how human resources will be trained for smooth implementation of tOPV withdrawal and bOPV introduction across all sectors of the immunization programme (e.g. for vaccine storage and 48 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 management, in-country distribution, supervision, delivery both for public and private sectors, NGOs involved in routine immunization, etc.) Consider whether or not health workers have previous, recent experience with vaccine recalls. If so, use that experience in developing switch-related materials. Describe how health workers will be oriented about the switch and use of bOPV instead of tOPV, especially ensuring no use of tOPV after the switch date as well as the process for disposal of tOPV. Outline any plans for increased supervision activities before, during and after the switch day. 4.6. Monitoring Explain how all aspects of the switch will be monitored: Preparedness Implementation of switch Withdrawal and disposal of tOPV Reporting mechanisms Identify whether any additional staff will be recruited for these monitoring activities. 4.7. Risk identification and mitigation Identify risks and challenges to the switch, e.g. financial and programmatic (including those issues identified in previous vaccine switches) and outline the plans to address them. Mention whether a switch control room will be established at national and sub-national level for close supportive supervision and crisis management. 49 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 Chronogram example for switch planning Table: Indicative timeline used to visualize and track a number of tasks, milestones, deadlines, persons or agencies responsible. National Logistics Milestone Regional National National Logistics Funding Management Milestone National National 1 Apr 8 Apr 15 Apr 22 Apr 29 Apr Apr 15 Develop a procurement plan Jun 15 First tOPV stock inventory 1 Jun 15 Country budget proposal submitted 1 Jun 15 Conduct ICC to oversee all activities relating to The Switch 1 Management Training Jun 15 Establish an operations room for coordination, information and communication 1 Oct 15 Development of appropriate training materials for The Switch National National National Logistics Management Logistics Jul 15 Order to cover use tOPV needs from Sept. 15 till Feb. 16 1 Milestone Jul 15 National switch plan is developed and endorsed 1 Milestone Jul 15 bOPV is licensed and registered with NRA 1 Regional global Training Management Oct 15 Conduct workshops on The Switch Milestone Sep 15 Positive Switch decision by SAGE 1 National National National Funding Management Management Milestone Sep 15 Country budget proposal accepted 1 Oct 15 ICC meeting with regional (health) authorities to explain The Switch 1 Oct 15 Establish a Switch Support Team (SST) 1 National Management Oct 15 Forms and software affected by The Switch are listed 1 National Training Oct 15 Train SST 1 National Training Oct 15 Develop training material for health staff 1 Regional District Management Logistics Oct 15 Meeting with health staff and authorities to explain The Switch. 1 Oct 15 Ensure districts storage capacity is sufficient 1 Regional National Logistics Logistics Nov 15 Second tOPV stock inventories 1 Nov 15 Develop a recall plan for tOPV (including private sector if applicable) 1 Regional District Logistics Logistics Dec 15 Place bOPV order for the first 3 months after The Switch. Dec 15 Place tOPV order for the period until the switch National Management Dec 15 Printing of new stationary, adapted to the use of bOPV National National Management Monitoring Dec 15 Design of simple "tOPV, do not use" sticker 1 Dec 15 Develop monitoring plan 1 District National National Funding Logistics Monitoring Milestone Feb 16 Funds arrive at regional level 1 Feb 16 Develop distribution plan for bOPV 1 Mar 16 Select and train Switch Monitors 1 National National Logistics Logistics Milestone Mar 16 All vaccine delivered at national level 1 Mar 16 Inform regions and districts of the nearest disposal sites 1 District District District Logistics Training Logistics District Milestone Milestone Milestone 1 1 1 1 1 1 1 1/04/2016 Distribution of bOPV and tOPV to the regions 1 1/04/2016 Training medical staff 1 8/04/2016 Districts received OPV and stationary 1 Logistics 8/04/2016 Confirm disposal sites are ready. 1 Service point Logistics 15/04/2016 District Logistics 22/04/2016 Return all tOPV to the nearest agreed disposal site 1 Service point Service point Logistics Logistics 22/04/2016 Final inventory for tOPV 1 22/04/2016 Mark all tOPV with stickers and remove from cold chain 1 1 Service point Service point Logistics Monitoring 22/04/2016 Return all tOPV to the district 1 1 22/04/2016 Switch monitors assist and check recall of routine tOPV 1 1 National National Monitoring Management 29/04/2016 Compile reports from Switch Monitors Milestone May 16 May 16 Mar 16 Feb 16 Jan 16 Dec 15 Activity Nov 15 Month / week Oct 15 Status Sep 16 End date Aug 15 Start date Jul 15 In charge Jun 15 Categories Milestone Apr 15 Level May 15 An Excel version of this chronogram is available: www.who.int/immunization/diseases/poliomyelitis/endgame_objective2/oral_polio_vaccine/implementation/en/ The Switch 1 1 Produce the statement confirming the absence of tOPV 1 46 Draft National Switch Data Aggregation Tool & Report_29 Jan 2016 National National National National Logistics Funding Management Logistics Milestone Apr 15 Develop a procurement plan Milestone Jun 15 Country budget proposal submitted Milestone Jul 15 National switch plan is developed and endorsed 1 Milestone Jul 15 bOPV is licensed and registered with NRA 1 global National National Regional Management Funding Management Logistics Milestone Sep 15 Positive Switch decision by SAGE 1 Milestone Sep 15 Country budget proposal accepted 1 Milestone Oct 15 Establish a Switch Support Team (SST) Milestone Nov 15 Second tOPV stock inventories 1 National District National District Management Funding Logistics Logistics Milestone Dec 15 Printing of new stationary, adapted to the use of bOPV 1 Milestone Feb 16 Funds arrive at regional level Milestone Mar 16 All vaccine delivered at national level Milestone 8/04/2016 Districts received OPV and stationary 1 Apr 8 Apr 15 Apr 22 Apr 29 Apr 1 1 1 1 1 1 1 47 May 16 Mar 16 Feb 16 Jan 16 Dec 15 Activity Nov 15 Month / week Oct 15 Status Sep 16 End date Aug 15 Start date Jul 15 In charge Jun 15 Categories Milestone Apr 15 Level May 15 Table: Key milestones as listed in the timeline Annex 6: Budget template for the national plan Table: Sample budget for non-vaccine costs associated with the switch. Total Budget WHO Amount by funding source UNICEF Govt. Other Document production Human resources Immunisation session supplies Logistics Planning and preparations Communications and stakeholder engagement Training and meetings Transport for implementation and supervision Waste management Additional items (specify) Miscellaneous Contingency Grand total 48