LCLS Ultrafast Science Instruments (LUSI) Project Management Control System Felix B. Fernandez – Project Controls August, 2008 LUSI DOE Review August 20, 2008 PMCS Overview p. 1 Felix B. Fernandez fbf@slac.stanford.edu PMCS Topics: System Overview PMCS Development Process PMCS Current Status Summary and Questions LUSI DOE Review August 20, 2008 PMCS Overview p. 2 Felix B. Fernandez fbf@slac.stanford.edu PMCS Overview The LUSI Project Management Control System: Complies with DOE Order 413.3A Complies with the 32 criteria from ANSI/EIA-748-A Complies with the LUSI Project Execution Plan Modeled after the LCLS Project PMCS LUSI DOE Review August 20, 2008 PMCS Overview p. 3 Felix B. Fernandez fbf@slac.stanford.edu PMCS Overview LUSI DOE Review August 20, 2008 PMCS Overview p. 4 Felix B. Fernandez fbf@slac.stanford.edu PMCS Overview SLAC/LCLS PMCS Procedures SLAC Accounting System Schedule Baseline Schedule Reports LUSI DOE Review August 20, 2008 PMCS Overview p. 5 Analysis Tool “Hammer” Cost Reports Felix B. Fernandez fbf@slac.stanford.edu PMCS Overview LUSI PMCS is defined and controlled by LCLS Procedures: Earned Value Management System Description – LCLS 1.1-015 CA and WP Planning Procedure – LCLS 1.1-018 Change Control Procedure – LCLS 1.1-019 Project Schedule Procedure – LCLS 1.1-020 Cost Estimating Procedure – LCLS 1.1-021 Monthly Status and Reporting Procedure – LCLS 1.1-022 Subcontract Management Procedure – LCLS 1.1-023 LUSI DOE Review August 20, 2008 PMCS Overview p. 6 Felix B. Fernandez fbf@slac.stanford.edu PMCS Overview Using Primavera (P3) as the Scheduling tool Have established a Project group with supporting project files maintained independently: LUSI Project Group Project Management (SLAC) XPP Instrument (SLAC) CXI Instrument (SLAC) XCS Instrument (SLAC) Diagnostics and Common Optics (SLAC) Controls and Data Acquisition (SLAC) XPP and XCS Detector Systems (BNL) LUSI DOE Review August 20, 2008 PMCS Overview p. 7 Felix B. Fernandez fbf@slac.stanford.edu PMCS Overview Using Cobra as the Budgeting tool Have created a Cobra project file for MIE funded effort. The project also uses a web based tool called the “PMCS Hammer” that integrates Primavera, Cobra and Accounting data. The “PMCS Hammer” is updated monthly following the month end cycle and provides team members a way of accessing/analyzing their data and writing their VARs. LUSI DOE Review August 20, 2008 PMCS Overview p. 8 Felix B. Fernandez fbf@slac.stanford.edu PMCS Overview LUSI DOE Review August 20, 2008 PMCS Overview p. 9 Felix B. Fernandez fbf@slac.stanford.edu PMCS Overview Jeff Chan LCLS Project Office Conv Facilities Controls Linac XE Controls XTOD Controls Undulator Installation Commisioning Database LUSI Project Office XPP CXI XCS DCO Controls BNL Database LUSI DOE Review August 20, 2008 PMCS Overview p. 10 Craig Brackett Jay Doubrava Pat Dunn Hok Leung Cathy Lavelle X X x X X x X X X X X X x X X x X X X x X X X X X x Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process LUSI DOE Review August 20, 2008 PMCS Overview p. 11 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Define Schedule and Budget assumptions Finalize the WBS, WBS Dictionary Finalize a Responsibility Assignment Matrix (RAM) Finalize the Milestone Hierarchy and Dictionary Finalize the set of SLAC/BNL Resources and Rates Finalize the resource loaded Integrated Master Schedule Use the Schedule baseline to create a Budget baseline Establish a prelim Performance Measurement Baseline LUSI DOE Review August 20, 2008 PMCS Overview p. 12 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Schedule Assumptions Within the funding limitations, get to an Early Science capability with the Instruments as early as possible. Establish priority order of Instruments as XPP, CXI and XCS. Establish multiple CD-4 milestones, one for each Instrument. Components not required for Early Science operations can be installed for final CD-4 milestone. Establish multiple CD-3 milestones to allow procurement of components for each Instrument as early as possible. Establish a complete performance measurement baseline for all project equipment and conduct one CD-2. Assume a Long Lead Authorization approval for Key critical components following CD-2 and prior to CD-3. LUSI DOE Review August 20, 2008 PMCS Overview p. 13 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Budget Assumptions Plan for an MIE funding profile of: Plan for a Continuing Resolution for the first half of FY2009 (approx. $500k/month). The balance of FY2009 funding will be available in the third quarter($12M). Use Resources and Rates (Direct/Indirect) provided by SLAC and BNL. LUSI DOE Review August 20, 2008 PMCS Overview p. 14 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Project WBS and WBS Dictionary The Work Breakdown Structure has been placed under change control PM-391-000-96 The WBS Dictionary has been updated to reflect the latest structure and has been placed under change control PM-391-001-12 The Responsibility Assignment Matrix (RAM) has been developed that identifies Control Accounts and CA Managers LUSI DOE Review August 20, 2008 PMCS Overview p. 15 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Control Account Managers T. Fornek - WBS 1.1 Project Management J. Langton - WBS 1.2 XPP Instrument * P. Montanez - WBS 1.3 CXI Instrument E. Bong - WBS 1.4 XCS Instrument * E. Ortiz - WBS 1.5 Diagnostics & Common Optics G. Haller - WBS 1.6 Controls & Data Acquisition Niels van Bakel - WBS 1.2.03 & 1.4.03 BNL Detectors * Except for BNL Detector effort LUSI DOE Review August 20, 2008 PMCS Overview p. 16 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Project Milestone Hierarchy and Dictionary The Milestone Hierarchy has been created and defines the relationship between the levels of milestones. Six levels of milestones have been identified Level 1 & 2 - DOE Level 3 – Project Level 4 – Instruments/Systems Level 5 – Interface / Handoff Level 6 – Commitments / Awards The Milestone Dictionary has been developed to assure a thorough understanding of agreements LUSI DOE Review August 20, 2008 PMCS Overview p. 17 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Several types of Level 5, Interface / Handoff Milestones have been defined and represent contractual agreements. LUSI is currently monitoring 904 Interface Milestones LUSI DOE Review August 20, 2008 PMCS Overview p. 18 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process LUSI DOE Review August 20, 2008 PMCS Overview p. 19 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Level 6 milestones have been identified as the Awards of subcontracts / procurements and supports funding reconciliations efforts. Planning when the budget is to be spent will support performance measurement. LUSI is currently monitoring 224 Award Milestones. LUSI DOE Review August 20, 2008 PMCS Overview p. 20 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process LUSI DOE Review August 20, 2008 PMCS Overview p. 21 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Project Resources and Rates Define a set of Resources for effort to be performed by SLAC with the appropriate planning rates. Define a set of Resources for effort to be performed by BNL with the appropriate planning rates. Use the appropriate indirect rates, as defined by SLAC/BNL, and apply to the direct rates as defined. Apply a consistent escalation to activities as they get scheduled. The Bay Area uses a 4% escalation rate for labor Used standard 2.3% escalation for non-labor LUSI DOE Review August 20, 2008 PMCS Overview p. 22 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Integrated Schedule Development Process Use WBS as foundation to assure 100% of scope covered Define the detailed tasks required to accomplish the scope Define the required resources to accomplish the tasks Based on the detailed Basis of Estimates Define the optimal logic relationships between tasks Incorporate all levels of DOE and Project milestones Incorporate all Interface / handoff milestones. LUSI DOE Review August 20, 2008 PMCS Overview p. 23 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Integrated Schedule Development Process (cont.) Validate links to confirm timephasing and float calculations are accurate and appropriate. Where applicable, base activity durations on recent LCLS and/or related experience. Define and use standard calendars throughout with all the appropriate non-work days. Plan for a standard work week (8 hours/day & 5 days/week) except where appropriate. Develop flexible and appropriate activity coding for reporting and summarizations LUSI DOE Review August 20, 2008 PMCS Overview p. 24 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Integrated Schedule Development Process (cont.) Because the project recognizes the importance of managing schedule contingency like it manages money contingency, blocks of time will be built into the schedule to mitigate the inevitable schedule issues. These reserves of time will be planned as activity relationship lags between the Project controlled Level 3 milestones and the DOE controlled Level 2 milestones. These blocks of schedule contingency were used during the development of the detail schedules and were removed to set preliminary baseline dates. The blocks will be added back into the schedule to impose control over float utilization. LUSI DOE Review August 20, 2008 PMCS Overview p. 25 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process The project has reserved time between DOE level 2 milestones and DOE level 1 milestones to allow for DOE processing: “Project Ready” + 40 days = DOE Review + 40 days = CD-3a “Project Ready” + 60 days = DOE Review + 40 days = CD-4a “Project Ready” + 40 days = DOE Review + 40 days = CD-3b “Project Ready” + 60 days = DOE Review + 40 days = CD-4b “Project Ready” + 40 days = DOE Review + 40 days = CD-3c “Project Ready” + 60 days = DOE Review + 40 days = CD-4a LUSI DOE Review August 20, 2008 PMCS Overview p. 26 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process For the purposes of managing Total Float, time reserves will be set aside between project level 3 milestones and DOE level 2 milestones: “Project Ready” + 40 days = DOE Review + 40 days = CD-3a “Project Ready” + 60 days = DOE Review + 40 days = CD-4a “Project Ready” + 40 days = DOE Review + 40 days = CD-3b “Project Ready” + 60 days = DOE Review + 40 days = CD-4b “Project Ready” + 40 days = DOE Review + 40 days = CD-3c “Project Ready” + 60 days = DOE Review + 40 days = CD-4a LUSI DOE Review August 20, 2008 PMCS Overview p. 27 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Each one of the 3 Instruments will have 100 days of schedule contingency controlled by the project office. LUSI DOE Review August 20, 2008 PMCS Overview p. 28 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process In addition to the WBS, project phase coding for each activity will facilitate the creation of summary schedules as well as define the budget work packages. Management / Administration Design / Engineering Procurement Subcontract Fabrication / Assembly Testing Installation LUSI DOE Review August 20, 2008 PMCS Overview p. 29 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Additional activity coding will facilitate sorting, filtering and additional summarizations Work Breakdown Structure Control Account number Work Package number Project Phase Milestone Level Control Account Manager name Performance Measurement Technique Earned Value Milestone (EVM) ID number EVM Weight Design Maturity Judgment Factor LUSI DOE Review August 20, 2008 PMCS Overview p. 30 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Funding Reconciliation The project started with a “bottom-up” planning approach which required budget authority inconsistent with the levels that were established. Reconciliation required the identification of opportunities and the prioritizations of effort to adjust for funding issues at the lowest level. The project next used a iterative “top-down” approach to shift entire blocks of effort to optimize the schedule flow while accelerating the Instrument availability. LUSI DOE Review August 20, 2008 PMCS Overview p. 31 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Once the schedule was iterated and a reasonable schedule was achieved that met the project objectives and stayed within the available funding, the preliminary schedule baseline was established. With a baseline established in the Primavera file, the next step was to import the schedule data into Cobra to create the budget baseline and to establish a preliminary performance measurement baseline (PMB). LUSI DOE Review August 20, 2008 PMCS Overview p. 32 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process Control Account and Work Package planning is based entirely on the time-phasing as defined by the schedule. Work packages are based on the project phase and represents the cost collection intersection with the SLAC accounting system. The work package is the lowest level at which earned value is calculated. LUSI DOE Review August 20, 2008 PMCS Overview p. 33 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process The majority of the near term effort for the project will be focused on Engineering and Design. Procurement, Subcontract, Fabrication & Assembly, Testing and Installation work packages are coded as Planning Packages. The detail planning for work packages coded as planning packages will be reassessed at the appropriate time. LUSI DOE Review August 20, 2008 PMCS Overview p. 34 Felix B. Fernandez fbf@slac.stanford.edu PMCS Development Process LUSI uses only a subset of the Performance Measurement Technique (PMT) codes used by Cobra to calculate Earned Value are coded into the schedule as a reference LUSI DOE Review August 20, 2008 PMCS Overview p. 35 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 36 Felix B. Fernandez fbf@slac.stanford.edu Critical Decision Requirements • Employ an Earned Value Management System that is compliant with ANSI/EIA-748-A-1998 for projects with a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $20M. Projects having a Total Project Cost or Environmental Management Total Project Cost between $20M and $50M must have an Earned Value Management System that is self-certified by the contractor as ANSI/EIA748-A-1998 compliant. Projects having a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $50M require an ANSI/EIA-748-A-1998 compliant system certified by the Office of Engineering and Construction Management. For projects not required to utilize an Earned Value Management System (e.g., firm fixed-price contract projects), an alternative performance management system must be described in the Project Execution Plan. • Completed – SLAC/LCLS Project was reviewed and successfully demonstrated compliance at a review in June 2008 • Subsequent to the June review a formal letter from DOE was received confirming the compliance of the SLAC Earned Value Management System. LUSI DOE Review August 20, 2008 PMCS Overview p. 37 Felix B. Fernandez fbf@slac.stanford.edu Critical Decision Requirements LUSI DOE Review August 20, 2008 PMCS Overview p. 38 Felix B. Fernandez fbf@slac.stanford.edu Critical Decision Requirements • Perform a Performance Baseline Validation External Independent Review or a Performance Baseline Validation Independent Project Review. External Independent Reviews are conducted by the Office of Engineering and Construction Management to validate the Performance Baseline for projects with a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $100M. Independent Project Reviews are conducted by the Project Management Support Office to validate the Performance Baseline for projects with a Total Project Cost or Environmental Management Total Project Cost less than $100 M. • The Independent Review is to be accomplished as part of the CD-2 review LUSI DOE Review August 20, 2008 PMCS Overview p. 39 Felix B. Fernandez fbf@slac.stanford.edu EIR Lines of Inquiry EIR ELEMENT COMMENT 1. Work Breakdown Structure PM-391-000-96 (Structure) 2. Project Cost & Resource Loaded Schedule Working baselines set as of month end March 2008 for both the schedule in P3 and the project cost in Cobra 3. Cost & Schedule Assumptions Covered in this presentation 4. Critical Path Critical paths for CD-4a, CD-4b and CD-4c available 5. Risk Management Mgmt presentation 6. Funding Profile Mgmt presentation 7. Project Controls/EVMS Overview and status covered in this presentation 8. Basis of Design Engineering presentation 9. Design Review Engineering presentation 10. System Functions & Reqs Engineering presentation 11. Sustainability Not applicable 12. Hazards Analysis PM-391-001-01 13. Value Management/Engineering LUSI Value Management Plan (Doc No. PM-391-000-02) 14. Start-up Test Plan SP-391-001-15, -16, -17 (XPP, CXI, XCS) 15. Project Execution Plan Draft ready for signature pending CD-2 review changes 16. Acquisition Strategy 17. Integrated Project Team LUSI DOE Review August 20, 2008 PMCS Overview p. 40 CD2 Ready This presentation & the PEP Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 41 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status Using Primavera (P3) as the Scheduling tool Currently the statistics for the LUSI Project group with supporting project files are: LUSI Project Group - 4131 activities & 6159 relationships Project Management (SLAC) - 191 activities XPP Instrument (SLAC) - 531 activities CXI Instrument (SLAC) - 899 activities XCS Instrument (SLAC) - 539 activities Diagnostics and Common Optics (SLAC) - 599 activities Controls and Data Acquisition (SLAC) - 1297 activities XPP and XCS Detector Systems (BNL) - 75 activities LUSI DOE Review August 20, 2008 PMCS Overview p. 42 Felix B. Fernandez fbf@slac.stanford.edu LUSI Project Summary Schedule FY07 FY08 FY09 FY10 FY11 FY12 =Level 1 & 2 DOE CD-1 Approval Sep 2007 CD-2 Review Aug 2008 =Level 3 Project Ready Design (Components not part of CD-4a) Procure / Fab / Assy / Install XPP Ready for CD-3a Feb 2009 Ready for CD-4a Jul 2010 Design Procure / Fab / Assy / Install (Comp. not part of CD-4b) CXI Ready for CD-3b Oct 2009 Design Ready for CD-4b Apr 2011 Procure / Fab / Assy / Install XCS Ready for CD-3c Feb 2010 LUSI DOE Review August 20, 2008 PMCS Overview p. 43 Ready for CD-4c Mar 2012 Felix B. Fernandez fbf@slac.stanford.edu LUSI Critical Paths/Envelopes Schedule Critical Path(s) Because each Instrument represents a separate major deliverable, critical paths have been identified and are being monitored to the Approve Start of Operations milestones: CD-4a for the XPP Instrument CD-4b for the CXI Instrument CD-4c for the XCS Instrument As a general rule, critical paths/envelopes are regularly monitored for all three instruments and the two supporting systems. LUSI DOE Review August 20, 2008 PMCS Overview p. 44 Felix B. Fernandez fbf@slac.stanford.edu XPP Schedule Critical Path Driving Milestones LL Approval, CD-3 & CD-4 Diffractometer Design Effort Diffractometer Awards & Vendor effort LUSI DOE Review August 20, 2008 PMCS Overview p. 45 Felix B. Fernandez fbf@slac.stanford.edu XPP Schedule Critical Path Diffractometer deliveries to the Installation effort LUSI DOE Review August 20, 2008 PMCS Overview p. 46 Felix B. Fernandez fbf@slac.stanford.edu CXI Schedule Critical Path KB Mirrors Reqmts/Design Effort Driving Milestones LL Approval, CD-3 & CD-4 KB Mirrors AWARD & Vendor Design Post Vendor Effort and Installation LUSI DOE Review August 20, 2008 PMCS Overview p. 47 Felix B. Fernandez fbf@slac.stanford.edu CXI Schedule Critical Path LUSI DOE Review August 20, 2008 PMCS Overview p. 48 Felix B. Fernandez fbf@slac.stanford.edu XCS Schedule Critical Path Driving Milestones LL Approval, CD-3, CD-4 & Funding M/S Delayed Design Start due to Funding XCS Path moves to DCO Procurements XCS Instrument Installation effort LUSI DOE Review August 20, 2008 PMCS Overview p. 49 Felix B. Fernandez fbf@slac.stanford.edu XCS Schedule Critical Path Design & initial procurement was completed for the XPP Instrument Procurement of DCO components delayed to FY11 due to funding LUSI DOE Review August 20, 2008 PMCS Overview p. 50 Felix B. Fernandez fbf@slac.stanford.edu XCS Schedule Critical Path LUSI DOE Review August 20, 2008 PMCS Overview p. 51 Felix B. Fernandez fbf@slac.stanford.edu DCO Schedule Critical Envelope DCO has one design effort and multiple procurements to support the Instrument reqmts. The project will monitor strings of activities with the least float LUSI DOE Review August 20, 2008 PMCS Overview p. 52 Felix B. Fernandez fbf@slac.stanford.edu DCO Schedule Critical Envelope LUSI DOE Review August 20, 2008 PMCS Overview p. 53 Felix B. Fernandez fbf@slac.stanford.edu CDA Schedule Critical Envelope CDA has multiple deliveries to the instruments and is heavily driven by their needs. The project will monitor strings of activities with the least float LUSI DOE Review August 20, 2008 PMCS Overview p. 54 Felix B. Fernandez fbf@slac.stanford.edu CDA Schedule Critical Envelope LUSI DOE Review August 20, 2008 PMCS Overview p. 55 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 56 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 57 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status M easurable Effort Level of Effort LUSI DOE Review August 20, 2008 PMCS Overview p. 58 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status Labor Non-Labor LUSI DOE Review August 20, 2008 PMCS Overview p. 59 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 60 Felix B. Fernandez fbf@slac.stanford.edu PMCS Hammer LUSI DOE Review August 20, 2008 PMCS Overview p. 61 Felix B. Fernandez fbf@slac.stanford.edu Statusing and Reporting SLAC/LCLS PMCS Procedures SLAC Accounting System Schedule Baseline Schedule Reports LUSI DOE Review August 20, 2008 PMCS Overview p. 62 Analysis Tool “Hammer” Cost Reports Felix B. Fernandez fbf@slac.stanford.edu Statusing and Reporting LUSI Project data is now stored on the LCLS website. https://slacspace.slac.stanford.edu/sites/LCLS%20Document%20Storage/default.aspx Toward the bottom there’s a PMCS section. LUSI DOE Review August 20, 2008 PMCS Overview p. 63 Felix B. Fernandez fbf@slac.stanford.edu Statusing and Reporting PMCS data will be stored and available in the folders as described. The PMCS Hammer is an interactive tool team members will use to view, analyze data and write VARs LUSI DOE Review August 20, 2008 PMCS Overview p. 64 Felix B. Fernandez fbf@slac.stanford.edu Statusing and Reporting The PMCS Hammer is a utility that was customized for SLAC/LCLS that integrates Primavera, Cobra and Accounting data for any team member to use. The LCLS Hammer and LUSI Hammer pages are access controlled and access is granted as appropriate. LUSI DOE Review August 20, 2008 PMCS Overview p. 65 Felix B. Fernandez fbf@slac.stanford.edu Statusing and Reporting The Drilldown CPR and DCE will probably be the most often used utilities, but other information is available. LUSI DOE Review August 20, 2008 PMCS Overview p. 66 Felix B. Fernandez fbf@slac.stanford.edu Statusing and Reporting The CPR Drilldown identifies areas that have broken a threshold that requires a VAR. LUSI DOE Review August 20, 2008 PMCS Overview p. 67 Felix B. Fernandez fbf@slac.stanford.edu Statusing and Reporting By double-clicking on the highlight variance, the VAR form will be enabled. LUSI DOE Review August 20, 2008 PMCS Overview p. 68 Felix B. Fernandez fbf@slac.stanford.edu In Conclusion The project set preliminary schedule and budget baselines as of March 2008. The project team is ready for CD-2. We are ready to formally establish a performance measurement baseline and to proceed with the project. Thank you for your participation LUSI DOE Review August 20, 2008 PMCS Overview p. 69 Felix B. Fernandez fbf@slac.stanford.edu PMCS Backup LUSI DOE Review August 20, 2008 PMCS Overview p. 70 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 71 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status Labor Non-Labor LUSI DOE Review August 20, 2008 PMCS Overview p. 72 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 73 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LaborSLAC Non-LaborSLAC Labor-BNL Non-LaborBNL LUSI DOE Review August 20, 2008 PMCS Overview p. 74 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 75 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status Labor Non-Labor LUSI DOE Review August 20, 2008 PMCS Overview p. 76 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 77 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status Labor-SLAC Non-LaborSLAC Labor-BNL Non-LaborBNL LUSI DOE Review August 20, 2008 PMCS Overview p. 78 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 79 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status Labor Non-Labor LUSI DOE Review August 20, 2008 PMCS Overview p. 80 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status LUSI DOE Review August 20, 2008 PMCS Overview p. 81 Felix B. Fernandez fbf@slac.stanford.edu PMCS Status Labor Non-Labor LUSI DOE Review August 20, 2008 PMCS Overview p. 82 Felix B. Fernandez fbf@slac.stanford.edu Milestones with PO Contingency Activity ID Activity description MS Level Early Finish Late Finish Total float PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 3/2/2009 88 L2 8/18/2008 1/5/2009 88 L3 7/28/2008 12/1/2008 88 L1 12/10/2008 4/27/2009 88 PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS PM002150 PM002200 PROJECT READY FOR CD-2 APPROVAL LONG LEAD PROCUREMENT APPROVED-Early Science PM002210 PM002220 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS 7/1/2009 7/21/2009 14 L3 7/6/2009 12/8/2009 109 PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 5/28/2009 7/2/2009 25 PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 4/2/2009 5/7/2009 25 L3 2/5/2009 3/12/2009 25 PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 3/8/2010 4/1/2010 18 PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 1/11/2010 2/4/2010 18 L3 10/29/2009 11/24/2009 PM003050 PM003060 PROJECT READY FOR CD-3b APPROVAL - CXI CD-3c CONSTRUCTION START APPROVED - XCS PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS PM003080 PM004000 PROJECT READY FOR CD-3c APPROVAL - XCS CD-4a START OF OPERATIONS APPROVED XPP PM004010 APPROVED: Instrument Readiness Review - CD-4a 18 L1 6/9/2010 10/5/2010 84 L2 4/14/2010 8/10/2010 84 L3 2/17/2010 6/15/2010 84 L1 12/17/10* 12/17/10* 0 L2 9/30/2010 10/20/2010 14 PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/8/2010 7/28/2010 14 PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0 L2 7/12/2011 8/5/2011 18 L3 4/19/2011 5/13/2011 18 PM004110 APPROVED: Instrument Readiness Review - CD-4b PM004120 PROJECT READY FOR CD-4b APPROVAL PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0 PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 6/8/2012 7/6/2012 20 L3 3/16/2012 4/13/2012 20 PM004220 LUSI DOE Review August 20, 2008 PMCS Overview p. 83 PROJECT READY FOR CD-4c APPROVAL Felix B. Fernandez fbf@slac.stanford.edu Milestones without PO Contingency MS Level Early Finish Late Finish PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 7/17/2009 187 PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS L2 8/18/2008 5/22/2009 187 PM002150 PROJECT READY FOR CD-2 APPROVAL L3 7/28/2008 5/1/2009 187 PM002200 LONG LEAD PROCUREMENT APPROVED-Early Science L1 12/10/2008 9/11/2009 187 PM002210 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 6/23/2009 10/6/2009 75 PM002220 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS L3 7/6/2009 3/16/2010 169 PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 4/2/2009 9/24/2009 125 PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 2/5/2009 7/30/2009 125 PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP L3 2/5/2009 7/30/2009 125 PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 1/11/2010 6/24/2010 118 PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 10/29/2009 4/29/2010 118 PM003050 PROJECT READY FOR CD-3b APPROVAL - CXI L3 10/29/2009 4/29/2010 118 PM003060 CD-3c CONSTRUCTION START APPROVED - XCS L1 4/14/2010 1/13/2011 184 PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS L2 2/17/2010 11/2/2010 184 PM003080 PROJECT READY FOR CD-3c APPROVAL - XCS L3 2/17/2010 11/2/2010 184 PM004000 CD-4a START OF OPERATIONS APPROVED XPP L1 12/17/10* 12/17/10* 0 PM004010 APPROVED: Instrument Readiness Review - CD-4a L2 7/7/2010 10/20/2010 75 PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/7/2010 10/20/2010 75 PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0 PM004110 APPROVED: Instrument Readiness Review - CD-4b L2 3/25/2011 8/5/2011 95 PM004120 PROJECT READY FOR CD-4b APPROVAL L3 3/25/2011 8/5/2011 95 PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0 PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 3/16/2012 7/6/2012 80 PM004220 PROJECT READY FOR CD-4c APPROVAL L3 3/16/2012 7/6/2012 80 Activity ID LUSI DOE Review August 20, 2008 PMCS Overview p. 84 Activity description Total float Felix B. Fernandez fbf@slac.stanford.edu Milestones with no Funding Limits Total float MS Level Early Finish Late Finish PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 7/17/2009 187 PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS L2 8/18/2008 5/22/2009 187 PM002150 PROJECT READY FOR CD-2 APPROVAL L3 7/28/2008 5/1/2009 187 PM002200 LONG LEAD PROCUREMENT APPROVED-Early Science L1 12/10/2008 9/11/2009 187 PM002210 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 6/23/2009 10/6/2009 75 PM002220 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS L3 4/2/2009 3/16/2010 236 PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 4/2/2009 9/24/2009 125 PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 2/5/2009 7/30/2009 125 PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP L3 2/5/2009 7/30/2009 125 PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 1/11/2010 6/24/2010 118 PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 10/29/2009 4/29/2010 118 PM003050 PROJECT READY FOR CD-3b APPROVAL - CXI L3 10/29/2009 4/29/2010 118 PM003060 CD-3c CONSTRUCTION START APPROVED - XCS L1 1/11/2010 1/13/2011 251 PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS L2 10/29/2009 11/2/2010 251 PM003080 PROJECT READY FOR CD-3c APPROVAL - XCS L3 10/29/2009 11/2/2010 251 PM004000 CD-4a START OF OPERATIONS APPROVED XPP L1 12/17/10* 12/17/10* 0 PM004010 APPROVED: Instrument Readiness Review - CD-4a L2 7/7/2010 10/20/2010 75 PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/7/2010 10/20/2010 75 PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0 PM004110 APPROVED: Instrument Readiness Review - CD-4b L2 2/23/2011 8/5/2011 117 PM004120 PROJECT READY FOR CD-4b APPROVAL L3 2/23/2011 8/5/2011 117 PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0 PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 10/6/2011 7/6/2012 182 PM004220 PROJECT READY FOR CD-4c APPROVAL L3 10/6/2011 7/6/2012 182 Activity ID LUSI DOE Review August 20, 2008 PMCS Overview p. 85 Activity description Felix B. Fernandez fbf@slac.stanford.edu