LUSI Coherent X-ray Imaging Instrument WBS 1.3

advertisement
LUSI
Coherent X-ray Imaging Instrument
WBS 1.3
Sébastien Boutet – CXI Instrument Scientist
Paul A. Montanez, P.E. – CXI Lead Engineer
LUSI DOE Review
August 20, 2008
Team Leader: Janos Hajdu
Engineer: Jean-Charles Castagna
Engineer: Armin Busse
Designer: Richard Jackson
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 1
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Outline
Physics Requirements
Safety
Instrument Configuration
Engineering/Design Status
Value Engineering
Basis Of Estimate
Procurement Strategy
Cost & Schedule
Critical Path
Risk Analysis
Summary
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 2
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Science Team
Specifications and instrument concept developed
with the science team.
The CXI team leaders
Janos Hajdu, Photon Science-SLAC, Uppsala University
(leader)
Henry Chapman, DESY, University of Hamburg
John Miao, UCLA
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 3
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
CXI SCOPE - WBS 1.3
WBS Scope/CD-2 Cost Includes:
1.3.1
CXI System Integration & Design
1.3.2
CXI X-ray Optics - 2 KB mirror systems
1.3.3
CXI Lasers - Reference Laser
1.3.4
CXI Coherent Imaging Injector
1.3.5
CXI Sample Environment – 2 Sample Chambers, 2 Stands, Detector Stage &
Sample diagnostics
1.3.6
CXI Hutch Facilities
1.3.7
CXI Vacuum system
1.3.8
CXI Installation
Other Related WBS
1.5
Diagnostics & Common Optics
1.6
Controls and Data Acquisition
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 4
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.2.1 CXI 0.1 micron KB
System
Purpose
Produce a 100 nm focal spot at
sample
Located 0.8 meters upstream of
sample
For samples smaller than 50 nm
ESRF KB Design
1.3.2.2 CXI 1 micron KB
System
Purpose
Produce a 1 micron focal spot at
sample
Located 8 meters upstream of
sample
For samples smaller than 0.5
micron
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 5
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.2 CXI KB Systems
Requirements
>75% reflectivity over the widest
energy range possible
Energy Range
At least up to 4-8.5keV
Goal: 2-15 keV
Accept 5 sigmas or more over the
widest energy range possible
Withstand full power of the LCLS
beam without damage
Preserve coherence
Meet at least the Maréchal criterion
at 8.3 keV, the highest fundamental
energy
>80% of incident intensity in the
central peak at the focal plane
hrms= rms height error over entire
length of the mirror
l=wavelength
N=number of reflective optics (2 in
this case)
a=incidence angle
hrms 
l
14 N 2a
Ultra-High vacuum
< 10-9 Torr
Interface with Sample Chamber
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 6
Solution
350 mm mirrors
3.6 mrad incidence angle
Rh/B4C bilayer
0.75 nm rms height error over
entire mirror
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
100 nm focus is required
for imaging small particles
Focal length
First mirror
900 mm
Second mirror
500 mm
Focus
68 x 120 nm spot
Requires reentrant KB
design
Closest point of approach
to interaction region
300 mm
Final sample chamber
design cannot occur until
we have a final KB design
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 7
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.3.1 CXI Reference
Laser
Purpose
Rough alignment of the
experiment without the Xray beam
Requirements
On/Off states
Beam size
Smallest possible at the
end of the hutch
Stability
5% of FWHM (short
term)
15% of FWHM (long
term)
Useable with any part of
the instrument vented to
air
Window valves
Aligned to the unfocused
FEL beam to within 100
microns
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 8
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.4.1 CXI Coherent Imaging
Injector
Purpose
Deliver support-free single
particles to the LCLS beam
Requirements
Particle beam focus
< 250 microns
Transmission
> 50 %
Translation (XZ)
10 mm
Particle size range
10 – 1500 nm
Aerodynamic lens
Stack of concentric orifices
with decreasing openings.
Particle beam
diagnostics
Charge detectors
Design builds on recent work
at LLNL
Bogan et al, Nanoletters 8, 310-316 (2008)
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 9
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.5.1.1 CXI Sample Chambers
Purpose
Position samples on grids and
apertures
Maintain high vacuum
Requirements
Accommodate multiple experiments
configurations
Fixed targets
Injected particles
Interface with
KB mirrors upstream
Detector Stage downstream
Ports for
Injector
Ion TOF
Lasers
Vacuum better than 10-7 torr
Rapid access
Large volume for flexibility
1 micron Sample Chamber
Compatible only with 1 micron KB
System
Delivered at CD-4B
0.1 micron Sample Chamber
Similar to 1 micron Sample Chamber
Plus
Compatible both KB Systems
Delivered at CD-4C
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 10
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.5.1.1 CXI Sample Chamber
(Fixed targets)
Multiple apertures
Aperture Purpose
Remove beam halo
Remove slit scatter from
upstream slits
Particle Beam Aperture
Aperture Requirements
Apodized edges
Positional resolution and
repeatability : <1 µm
Easily replaced if destroyed
by the beam
Multiple samples held on
multiple grids
Sample pitch and yaw
High resolution telescope for
sample viewing
1.3.5.1.1 CXI Sample Chamber
(Injected Particles)
Sample stage can be
translated and used as an
aperture
Utilize the same setup for
fixed samples and particle
injection
Particle beam comes in from
the top
Particle beam aperture
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 11
Apertures
Sample
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.5.1.1 CXI Ion Time-ofFlight
Purpose
Design will be a scaled
down version of the AMO
Ion TOF
Detect ions produced
by exploding sample
Provide a veto trigger
signal when a particle
was hit by the beam
Identify unwanted
particles
Requirements
1 Atomic Mass Unit
resolution
Up to 100 AMU
detection
1 GHz digitization
Does not interfere with
imaging detector
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 12
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.5.1.2 CXI Precision Instrument Stands
Purpose
Position the chamber at the interaction region
Requirements
Positioning accuracy
100 microns
Short term stability
0.1 microns
5 µrad
1 micron Precision Instrument Stand
Support the 1 micron Sample Chamber and Detector Stage
0.1 micron Precision Instrument Stand
Support the 0.1 micron KB System, 0.1 micron Sample Chamber and Detector Stage
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 13
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.5.1.3 CXI Detector Stage
Purpose
Center the detector hole on
the direct beam
Position the detector at the
appropriate distance from
the interaction region
Requirements
Range along the beam : 502400 mm
Non-continuous
Vacuum better than 10-7 torr
Diagnostics behind the
detector for alignment
Valve to isolate the detector
vacuum
Short term stability
1 micron
10 µrad
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 14
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.5.1.3 CXI Detector Stage
Purpose
Center the detector hole on
the direct beam
Position the detector at the
appropriate distance from
the interaction region
Requirements
Range along the beam : 502400 mm
Non-continuous
Vacuum better than 10-7 torr
Diagnostics behind the
detector for alignment
Valve to isolate the detector
vacuum
Short term stability
1 micron
10 µrad
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 15
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Component Physics Requirements
1.3.6 CXI Hutch facilities
Raised flooring
Storage cabinets, work benches and tool chests
Utilities distribution
1.3.7 CXI Vacuum system
Requirements
Vacuum better than 10-7 Torr
Better than 10-9 Torr for KB Systems
10 year lifetime for ion pumps
Support stands
1.3.8 CXI Installation
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 16
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Safety
LUSI Hazard Analysis Report (PM-391-001-34) complete
Safety issues are considered at every stage of the
design, fabrication and installation process
Safety considerations (some examples)
Ionizing Radiation
Hutch walls will comply with SLAC Radiation Safety memo RPRPG-080606-MEM-01
Hutch PPS
Pressure/Vacuum Vessel Safety
Compliant with 10CFR851
Seismic Safety
Designs compliant with: Seismic Design Specification for
Buildings, Structures, Equipment, and Systems, SLAC-I-7200A24E-002-R002
Mechanical
Engineered solutions that prevent potential “pinch-points”
with moving machinery
Hoisting and Rigging
Positioning of devices that require the use of the FEH H5
overhead crane shall be performed by qualified personnel
only with an approved lift plan.
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 17
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Instrument Configuration
CXI is comprised of five major subsystems
Focusing Optics (WBS 1.3.02)
Provide focal spot sizes on the order of 100 nm x 100 nm and 1 µm x 1 µm
for the CXI instrument
Reference Laser (WBS 1.3.03)
Provides a visible, low power laser beam collinear with the LCLS X-ray
beam to align the components of the CXI instrument without use of the Xray beam
Sample Environment (WBS 1.3.04 & 1.3.05)
To measure the coherent diffraction pattern of any submicron sample of
interest
(1) sample chamber, (2) ion time-of-flight mass spectrometer, (3) particle
injector, (4) detector stage and (5) precision instrument stand
Vacuum System (WBS 1.3.07)
Create and support a vacuum environment with pressure better than 10-9
Torr for each KB system and better than 10-7 Torr along the CXI beamline
Diagnostics/Common Optics (WBS 1.5)
Analyze and optimize the X-ray beam properties
Located in both the XRT and FEH H5 and consist of a suite of X-ray optic
and diagnostic components that are common with the other LUSI
instruments as well as CXI specific hardware, i.e. Wavefront Monitor
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 18
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Instrument Configuration (2)
CXI Components in the X-ray Transport Tunnel (XRT)
Reference Laser
(WBS 1.3.03)
Beam Direction
Diagnostics
(WBS 1.5)
CXI Components in Far Experimental Hall Hutch 5 (FEH H5)
FEH Common Room
CXI Control Room
2X Double Racks
Gas Cabinet
FEH H5
Laser Table
Beam Direction
Focusing Optics
(WBS 1.3.02)
Sample Environment (WBS 1.3.04 & 1.3.05)
5X Single Racks
Note: Overhead crane in
H5 not shown for clarity
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 19
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status
CD-2 Documentation Activities
Overall CXI Instrument Physics Requirements Document (PRD) reviewed and approved
by team leaders in Dec 07
CAD system model documentation hierarchy (CAD Drawing Tree/File Structure) in
review
Initial XRT/FEH H5 beamline layout complete
13 PRDs/ESDs released, 9 ESDs in-work/draft-review/released status
1µm KB system ESD/Technical Specification in review
Hutch Design (FEH H5)
ESDs/Room Data sheets released
Hutch Layout Drawings
Stay Clears
Utilities
Hutch Layout
APP and Risk Identification/Registry complete and up to date
All Basis of Estimates complete and up to date
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 20
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (2)
PDR: Preliminary Design
Review
CXI Reference Laser &
Detector Stage nearing
PDR
Instrument Equipment List/Review Checklist
FDR: Final Design Review
Seismic: Seismic Review
Components > 400lbs
Additional Reviews that may
be applicable:
Electrical Safety
Fire Safety
Hazardous Experimental
Equipment
Hoisting and Rigging Safety
Laser Safety
Radiation Safety
Preliminary and Final
Instrument Design Reviews
(PIDR & FIDR)
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 21
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (3)
CXI 0.1µm KB system (WBS 1.3.02.01)
0.1µm spot size for samples less than 50nm in size
State of the art focusing optic
One potential vendor identified
Osaka U/JTEC – actively pursuing and pushing the technology
Pre-figured/mechanically bent/bimorph solutions acceptable
PRD released June 2008
Vendor PDR scheduled for November 2009
Overall system PDR scheduled for February 2010
~$1,400K
ESRF KB Design
CXI 1µm KB system (WBS 1.3.02.02)
1µm spot size for samples between 50nm and 1µm
Technology is proven
Pre-figured/mechanically bent/bimorph solutions acceptable
PRD released June 2008
ESD/ Technical Specification draft completed (in work-finalize)
Draft of ESD sent to multiple vendors for Request for
Information (RFI):
Engineering feasibility study
Budgetary Inquiries
Vendor PDR scheduled for August 2009
Overall system PDR scheduled for October 2009
~$1,390K ($970,000 in long lead procurement – July 2009)
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 22
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (4)
CXI Reference Laser (WBS 1.3.03.1)
Installed in the X-ray Transport tunnel
Used to align components without requiring
FEL beam
Pointing stability critical
Preliminary design nearly complete
Detailed engineering analysis required to
ensure pointing stability
PRD released June 2008
ESD draft completed (in review)
PDR scheduled for October 2008
~$115K
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 23
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (5)
Particle Injector (WBS 1.3.04.01)
Injector design exists from LLNL
LUSI project will advance the design
Recently hired LLNL physicist who was
primarily responsible for the design,
fabrication and testing of the injector
Work on the injector scheduled to begin
July 2008
PDR scheduled for August 2009
~$1,005K
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 24
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (6)
CXI Sample Chambers (WBS
1.3.05.01.01)
1µm Sample Chamber
Significant design work completed on
the sample chamber for all of its
required configurations
Fixed target, particle injection set-ups
and options for detector position –
complex design
Design should be sufficiently flexible to
allow for potential use of Particle
Injector/IToF before CD-4C if available
Allow for interface with Detector Stage
PRD released July 2008
ESD draft completed (in review)
PDR scheduled for December 2008
~$750K
0.1µm Sample Chamber
Design should accommodate all of
required experimental configurations
Fixed target, particle injection set-ups
and options for detector position
Allow for interface with 0.1µm KB
System, Detector Stage, Particle
Injector and IToF
PRD released July 2008
ESD draft completed (in review)
PDR scheduled for March 2010
~$500K
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 25
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (7)
CXI Precision
Instrument Stands (WBS 1.3.05.01.02)
1µm Precision Instrument Stand
Conceptual design based on LCLS AMO Instrument Stand (similar stability/
precision motion requirements)
Support /Interface with 1µm Sample Chamber and Detector Stage
Motorized motions for KB offsets
PRD released July 2008
ESD draft completed (in review)
PDR scheduled for December 2009
~$240K
0.1µm Precision Instrument Stand
Design similar to 1µm Precision Instrument Stand
Support 0.1µm Sample Chamber, Detector Stage and 0.1µm KB System
Motorized motions for KB offsets
PRD released July 2008
ESD draft completed (in review)
PDR scheduled for May 2010
~$240K
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 26
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (8)
Detector Stage (WBS 1.3.05.01.03)
Centers the detector on the beam and
positions it in “Z” relative to the
interaction point
Concept completed
Analysis required to ensure detector
stability
Design waiting
detector packaging details
PRD released
ESD draft completed (in review)
PDR scheduled for September 2008
~$325K
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 27
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (9)
CXI Hutch Facilities (WBS 1.3.06.0.1 & 1.3.06.02)
Hutch layout design
Raised flooring
Storage cabinets, work benches and tool chests
Utilities distribution
~$380K
CXI Vacuum System (WBS 1.3.07.01 & 1.3.07.02)
Requirements
Beamline vacuum better than 10-7 Torr
Better than 10-9 Torr for KB Systems
10 year lifetime for ion pumps
Vacuum equipment: pumps, valves, gauges, etc.
Bellows and Spools
Support stands
PDRs
Vacuum Equipment – scheduled for November 2008
Vacuum Supports – scheduled for May 2009
~$700K
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 28
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (10)
Installation (WBS 1.3.08.01)
CXI has a “phased installation”
CD-4B
Diagnostics/Common Optics
Reference Laser
1µm Sample Chamber & Precision Instrument Stand
1µm KB System
Detector Stage
Vacuum
Equipment/Hardware/Supports
Early Finish – March 2011
CD-4C
Diagnostics/Common Optics
0.1µm Sample Chamber & Precision Instrument Stand
0.1µm KB System
Particle Injector/IToF
Vacuum
Equipment/Hardware/Supports
Early Finish – November 2011
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 29
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (11)
Preliminary component designs
Reference Laser
Preliminary design ~90% complete
Engineering analysis required to evaluate stability criteria
CXI 1µm Sample Chamber
Preliminary design ~75% complete
CXI 1µm Precision Instrument Stand
Conceptual design based on AMO instrument
Detector Stage
Preliminary design ~75% complete
Awaiting more information on detector packaging and stability
analysis
Engineering Specification Document for the 1µm KB system
Currently in “draft-review” status
Multiple vendors evaluating draft specifications
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 30
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Engineering/Design Status (12)
6 month “look-ahead” at Level 4/5 Milestones
ESDs released
CXI Detector Stage – Sept 08
CXI Reference Laser – Sept 08
CXI 1.0µm KB System – Sept 08
CXI 1.0µm Precision Instrument Stand – Sept 08
CXI 1.0µm Sample Chamber – Oct 08
CXI 0.1µm KB System – Oct 08
PRDs released
CXI Injector – Jan 09
Preliminary Design Reviews
CXI Detector Stage – Sept 08
CXI Reference Laser – Oct 08
CXI Vacuum Equipment – Nov 08
CXI 1.0µm Sample Chamber – Dec 08
Final Design Reviews
CXI Reference Laser – Dec 08
Vacuum System Equipment – Jan 09
Cornell Detector Packaging (Participate in) – Feb 09
Vendor Related
Release CXI KB Systems RFP – Jan 09
Receive CXI KB Systems Vendor Proposals – Feb 09
Far Experimental Hall Hutches
FEH H5 Preliminary Layout – Sept 08
LCLS 30%, 60%, 90% hutch drawing review – Sept 08, Oct 08 and Jan 09
LCLS FEH FDR – Jan 09
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 31
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Value Engineering
Many trade-offs
have been
considered in the
CXI Preliminary
Design
The CXI team will
continue to purse
cost effective
approaches for all
aspects of the
instrument
design/fabrication
/installation
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 32
Component
Value Management /Design Alternatives
Considered
Diagnostics
All the diagnostics requirements were optimized to meet the
experimental needs for all the instruments. Significant cost
savings can be realized from common designs, both in PED,
as well as in manufacturing.
Optics
The following optical components requirements were
optimized to meet the experimental needs for all the
instruments: Pulse Picker, Attenuator, Harmonic Rejection
Mirror and Be Lenses. Significant cost savings can be
realized from common designs.
1µm Sample
Chamber
Design alternatives were studied to accommodate various
detector locations, allow for rapid access to internal chamber
hardware and to maximize the reconfiguration capability of
experimental hardware in the same chamber.
1µm Sample
Chamber
Worked with a vendor to provide in-vacuum nanopositioning
piezo stages capable of sustaining a higher load capacity.
This collaboration lead to a gain in the flexibility of hardware
reconfiguration by utilizing smaller stages.
1µm Precision
Instrument Stand
Utilized the same concept as the LCLS AMO Instrument to
save design costs due to similar stability and precision motion
requirements. Significant cost savings can be realized from
common designs.
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Procurement Strategy
A variety of sources are
used to
design/build/install CXI
components
CXI Work Breakdown Structure - PM-391-000-96
WBS
Previous Design/OTS
1.3
1.3.01
1.3.02
1.3.02.01
1.3.02.02
1.3.03
1.3.03.01
1.3.03.02
1.3.04
1.3.04.01
1.3.05
1.3.05.01
1.3.05.01.01
1.3.05.01.02
1.3.05.01.03
1.3.05.02
1.3.05.02.01
1.3.06
1.3.06.01
1.3.06.02
1.3.07
1.3.07.01
SLAC
1.3.07.02
Domestic Vendor
1.3.07.02.01
Foreign Vendor
1.3.07.02.02
Long Lead Procurement
1.3.08
SLAC effort where skill
set exists.
Vendor design/build
used where required.
Previous designs and
off-the-shelf
components are used
whenever available
1.3.08.01
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 33
TITLE
Resource Source
Design
Build
Install
COHERENT X-RAY IMAGING (CXI)
CXI System Integration & Design
CXI X-ray Optics
CXI KB System (0.1 micron)
CXI KB System (1 micron)
CXI Lasers
CXI Reference laser
RESERVED
CXI Coherent Imaging Injector
Coherent Imaging Injector System
CXI Sample Environment
CXI Room Temperature Environment
CXI Sample Chamber & Ion ToF
CXI Precision Instrument Stand
CXI Detector Stage
RESERVED
RESERVED
CXI Hutch Facilities
CXI Hutch Specification
CXI Utilities & Hutch Equipment
CXI Vacuum System
CXI Vacuum Equipment
CXI Vacuum Hardware
CXI Bellows & Spools
CXI Vacuum Supports
CXI Installation
CXI Installation Phase
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Cost & Schedule
Resource loaded schedule
completed and has been
fully implemented into
Primavera P3
CXI (WBS 1.3)
231 milestones specific to
CXI
197 L4/L5 milestones
L4: Systems (COMP/RCV)
L5: Interface/Handoff
(AVAIL/REQD))
34 L6 milestones
L6: Commitments/Awards
(AWARD)
Duration to “Project Ready
for CD-X Approval”
3B – 14m (Oct 09)
4B – 31m (April 11)
4C – 42m (March 12)
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 34
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Cost & Schedule (2)
BoE & Manpower Loaded
Schedule developed in a
manner similar to the
other LUSI instruments
CXI L3 Planned Budget by
Control Acct & FY
Labor – ~ 58%
“Labor” means ALL
labor including LOE
Non-Labor – ~ 42%
Peak expenditure in FY10
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 35
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Cost & Schedule (3)
8.0
1.3.08.01 - CXI Installation Phase
1.3.07.02 - CXI Vacuum Hardware
1.3.07.01 - CXI Vacuum Equipment
7.0
1.3.06.02 - CXI Utilities & Hutch Equipment
Engineers & Designers/Person Quarter
1.3.06.01 - CXI Hutch Specification
6.0
1.3.05.01 - CXI Room Temperature Environment
1.3.04.01 - Coherent Imaging Injector System Integ
5.0
1.3.03.01 - CXI Reference laser
1.3.02.02 - CXI KB System (1 micron)
1.3.02.01 - CXI KB System (0.1 micron)
4.0
1.3.01 - CXI System Integration & Design
3.0
2.0
1.0
Person quarter = 444h
FY12-2
FY12-1
FY11-4
FY11-3
FY11-2
FY11-1
FY10-4
FY10-3
FY10-2
FY10-1
FY09-4
FY09-3
FY09-2
Durations
FY09-1
0.0
Fiscal Quarters
Person year = 1776h
Person month = 148h
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 36
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
CXI Critical Path
KB Mirrors
Design Effort
Driving
Milestones:
LL Approval, CD3 & CD-4
KB Mirrors
AWARD &
Vendor Design
Post Vendor
Effort and
Installation
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 37
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
CXI Critical Path (2)
Installation
Effort
KB systems are “long duration procurement” items – requesting DOE
long lead approval for 1µm KB system prior to CD-3B
Critical path (through 1µm KB System) has 117d of schedule
contingency
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 38
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Risk Identification & Mitigation
Risk Identification/Registry complete and up to date as per “LCLS Risk
Management Plan” PMD 1.1-002-r4
KB Mirror Systems
No vendor willing to bid on systems – Technical & Schedule
Mitigation
Start discussions with vendors early to guarantee their capabilities are consistent with our needs
Iterate specs with vendors early to find a workable solution before bid process
Vendor doesn’t meet specifications – Technical
Mitigation
Travel to vendor sites during fabrication
Have a quality control person supervise their final fabrication process and final surface characterization
Identify vendors with proven capabilities
Delays impact other systems – Schedule
Mitigation
Break the link between the KB0.1 KB mirror and the chamber by building a second chamber to be used
early with the KB1 system only. Risk has been alleviated with BCR-2008-06-004: Addition of Second
Chamber and Precision Instrument Stand for the CXI Instrument
Sample Chamber
Lack of information regarding 0.1µm KB delays engineering effort – Schedule
Mitigation
Same as “Delays impact other systems” above. Risk retired with BCR-2008-06-004: Addition of Second
Chamber and Precision Instrument Stand for the CXI Instrument
Particle Injector
Remote operation – Technical & Schedule
Mitigation
Leverage institutional efforts to solve this problem
Move injector to a CD-4C deliverable
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 39
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
CXI CD-2 Project Readiness
CXI designs are
mature and
technically meet the
requirements for
CD-2
All CD-2 criteria met
Management






WBS Dictionary
Milestone Dictionary
Risk Registry
Resource Loaded Schedule
Basis of Estimate
Hazard Analysis Report
Technical
Fully define scope of project, document & review
Instrument Physics Requirement Document (PRD)
Instrument Engineering Specification Document (ESD)
Instrument Start-Up Plan
Component PRDs - Released
Component ESDs - Pre-released
Advance technical designs meet the CD-2 requirement to
provide sufficient information to develop performance
baseline
Preliminary Instrument Design Review
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 40








S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
Summary
CXI designs are mature and concepts are based on
proven developments made at FLASH and SR sources
CXI has an established design with a consistent cost
estimate. Approximately 90% of the materials costs
based on vendor quotations, catalogs, or previous
orders (Total procurements:3,467K$, Total based on
quotes:3,164K$)
Critical Design Thrust
Kirkpatrick-Baez Mirror Systems
Required Long Lead Procurement
1µm Kirkpatrick-Baez Mirror System
Critical Path “float” reasonable for total schedule
duration
Major Risks are mitigated with an implemented BCR to
the “preliminary baseline” which includes a second
dedicated Sample Environment for the 1µm KB system
CXI and LUSI ready for CD-2 Approval!
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 41
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)
End of presentation
LUSI DOE Review
August 20 2008
Coherent X-Ray Imaging (WBS 1.3) 42
S. Boutet (sboutet@slac.stanford.edu)
P. Montanez (montanez@slac.stanford.edu)