LUSI X-ray Pump-Probe Instrument WBS 1.2

advertisement
LUSI
X-ray Pump-Probe Instrument
WBS 1.2
David Fritz – XPP Instrument Scientist
J Brian Langton – XPP Lead Engineer
LUSI CD-2 Review
August 20, 2008
Team Leader: Kelly Gaffney
Second Scientist: Marc Messerschmidt
Designer: Jim Defever
Designer: Jim Delor
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
1
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Outline
Physics Requirements
Safety- XPP Unique Hazards & Mitigations
Instrument Configuration
Engineering / Design Status
Value Engineering / Management
Basis Of Estimate
Procurement Strategy
Cost & Schedule
Critical Path
Risk Analysis
Summary
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
2
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
XPP Staff
Instrument Scientist
-David Fritz
Engineering Staff
J Langton - Lead
Engineer
Jim Defever –
Mechanical
Engineer
Jim Delor –
Mechanical
Engineer
Don ArnettDesign Supervision
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
3
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Science Team
Specifications and instrument concept developed
with the science team.
The XPP team leaders
Kelly Gaffney, Photon Science, SLAC (leader)
Jorgen Larsson, Lund Institute of Technology, Sweden
David Reis, University of Michigan
Thomas Tschentscher, DESY, Germany
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
4
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
XPP Scope - WBS 1.2
WBS Scope/CD-2 Cost Includes:
1.2.1
XPP System Integration & Design
1.2.2
XPP X-ray optics and diagnostics support tables
1.2.3
XPP Ultrafast laser system
1.2.4
XPP 2D Detector from BNL by MOU
1.2.5
XPP Sample goniometer
1.2.5
XPP Detector mover
1.2.6
XPP Hutch Facilities
1.2.7
XPP Vacuum system
1.2.8
XPP Installation
Other Related WBS
1.5
Diagnostics & Common Optics
1.6
Controls and Data Acquisition
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
5
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
XPP Physics Requirements
Goals
Perform time resolved experiments at the highest temporal resolution
achievable (80 fs rms)
Accommodate as many classes of experiments are reasonable achievable
Capable of running in a shared beam mode using a future beam
splitting monochromator
Instrument must be accessible while beam is delivered to FEH
Tailor and characterize X-ray and optical beam parameters
Spatial profile
Intensity
Repetition rate
Spectral bandwidth
Wavelength (optical laser)
Temporal profile (optical laser)
Key Performance Parameters
4-20 keV
Using fundamental and third harmonic
0.1-0.01% energy resolution
1000 x 1000 pixel detector
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
6
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Component Physics Requirements
1.2.2 XPP X-ray Optics and Supports
Fixed table (hutch 2) and 2 translating tables (hutch 3)
Rigid support structures that will define the x-ray optical axis
Design goals in priority order
1. Stabilize optics with respect to each other (short & long term)
2. Stabilize optics with respect to global coordinate system
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
7
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Component Physics Requirements
1.2.3 XPP Laser System
Will utilize and expand upon AMO laser system
AMO Laser Requirements
> 3 mJ per pulse energy at sample (800 nm)
< 50 fs pulse duration
120 Hz
< 100 fs phase jitter to LCLS RF
Multipass amplifier
>20 mJ per pulse energy (800 nm)
< 50 fs pulse duration
120 Hz
Frequency conversion capability
OPA
Harmonic generation
Temporal pulse shaping capability
Diagnostics suite
System designed such that a non-laser trained user can perform an XPP
experiment
Sufficient automation to control laser parameters
Sufficient engineering controls to provide safe working environment
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
8
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Component Physics Requirements
1.2.4 XPP Detector System
Developed at BNL via MOU
High detector quantum efficiency
Single photon sensitivity
Large dynamic range >103
104 photon dynamic range per pixel
120 Hz readout rate
1024 x 1024 square pixels
90 µm pixel size
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
9
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Component Physics Requirements
1.2.5 – Sample Goniometer
Flexibility to accommodate a wide variety of sample
environments (50 kg)
Capable of orienting small samples (~ 50 μm) over a
wide range of reciprocal space
Sphere of confusion < 30μm
Open access to allow close proximity laser optics
Operate in direct or future monochromatic beam
No interference with direct beamline while in
monochromatic mode
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
10
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Component Physics Requirements
1.2.5 – Detector Mover
10 cm – 100 cm sample to detector distance in
forward-scattering upper hemisphere quadrant
10 cm – 50 cm sample to detector distance in backscattering upper hemisphere quadrant
Repeatable position the XPP detector pixels to a
fraction of the pixel size
Definitively know the position of all detector pixels to
a fraction of the pixel size
Operate in both interaction points
No interference with direct beamline while in
monochromatic mode
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
11
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Component Physics Requirements
1.2.6 XPP Hutch facilities
Raised flooring
Storage cabinets, work benches and tool chests
Utilities distribution
1.2.7 XPP Vacuum system
< 10-7 Torr
> 10 year pump lifetime
1.2.8 XPP Installation
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
12
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Safety - Hazard Analysis (1)
XPP unique hazard: non-ionizing
radiation
PM-391-001-34 Appendix A, Item 3
Optical pump laser system
Unmitigated
Severitycatastrophic critical marginal negligible
Probability
frequent
1
3
7
13
probable
2
5
9
16
occasional
4
6
11
18
remote
8
10
14
19
improbable
12
15
17
20
mitigated
ITEM
3
HAZARD
Non-ionizing
radiation exposure
UNMITIGATED RISK
LEVEL
Laser room connected to experimental Level 7
hutch
Marginal
Class IV laser in experimental hutch Frequent
CAUSE
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
13
PREVENTION / MITIGATION
POTENTIAL IMPACT
Engineered controls including opaque barriers, Personnel injury – eye
laser safety system, beam containment during damage or skin burns
routine operation
PPS equipment: appropriate laser goggles for
wavelengths in use.
Administrative controls including laser safety
training, alignment mode with only trained
personnel in hutch
Ref: SLAC ES&H Manual, Chapter 10, Laser
Safety
MITIGATED RISK
Level 20
Negligible
Improbable
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Safety - Hazard Analysis (2)
XPP unique hazard: remote controlled
robot arm
PM-391-001-34 Appendix A, Item 14
Diffractometer system detector mover
Severitycatastrophic critical marginal negligible
Probaibility
frequent
1
3
7
13
probable
2
5
9
16
occasional
4
6
11
18
remote
8
10
14
19
improbable
12
15
17
20
Unmitigated
mitigated
ITEM
3
HAZARD
remote controlled
robot arm
CAUSE
software or
hardware failure
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
14
UNMITIGATED RISK
LEVEL
Level 10
critical
remote
PREVENTION / MITIGATION
POTENTIAL IMPACT
Robot arm will be designed to be compliant
Personnel injury
with OSHA technical manual, section IV,
chapter4; “Industrial Robot and Robot System
Safety” and ANSI/RIA R15.-06; “American
National Standard for Industrial Robots and
Robot Systems.” The safety measures will
include, but are not limited to the following:
1. Personnel Protection Systems – proximity
sensors, light curtains, pressure mats,
emergency stops..
2. Hardware systems - docking interlocks to
robot power and control systems switching,
force sensor interlocks.
3. Software system - training & maintenance
modes.
SLAC safety reviews and acceptance testing
of device hardware and controls.
MITIGATED RISK
Level 20
Negligible
Improbable
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Instrument Configuration (1)
The up-beam vacuum drift section: This area extends up-beam into
NEH hutch 2 and includes a small suite of x-ray optic and diagnostic
components. Hutch 3 space is primarily intended for future upgrades
to enhance beam sharing between experimental hutches.
Includes elements from WBS 1.2.2.2, 1.2.2.7 & 1.5.X.X (DCO scope)
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
15
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Instrument Configuration (2)
The upbeam x-ray optics-diagnostic suite: This area is for analysis and
optimization of x-ray beam properties. The Area also provides x-ray vertical
steering capabilities for special experiment configurations. Beamline
components are designed to translate 0.6 meter (nominal) in “X” to facilitate
early science beam sharing. Also includes final pump laser optics.
Includes elements from WBS 1.2.2.1, 1.2.7 & 1.5.X.X (DCO scope)
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
16
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Instrument Configuration (3)
The optical pump laser system: System used to deliver excitation
energy to experimental samples. Includes Optical support system and
laser containment hardware.
Includes elements from WBS 1.2.3
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
17
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Instrument Configuration (4)
The diffractometer system: Is composed of the sample goniometer
(“tilt” and “kappa” goniometer) and the detector mover subsystems.
This hardware provides for the positioning and rotation of the
experimental sample and the array detector.
Includes elements from WBS 1.2.5
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
18
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Instrument Configuration (5)
The down-beam diagnostic-drift section: This area is used for x-ray
beam parameters analysis and diffractometer system alignment.
Beamline components are designed to translate 0.6 meter (nominal)
in “X” for early science beam sharing.
Includes elements from WBS 1.2.2.1, 1.2.7 & 1.5.X.X (DCO scope)
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
19
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Engineering Status - Q3 FY08 Goals
Establish CAD System – file structure – Drawing Tree (complete)
Generate Higher Level models - drawings
Hutch 3 Definitive Lay-out (complete, released)
MIE Stay Clear models, documentation (complete, released)
Detector Mover ESD
Complete, released
Vendor review (complete)
Detector Mover “proof of concept” (complete)
Measurements completed week of Aug 11th
Sample Goniometer ESD
Complete, released
Vendor Review (complete)
>50% complete on long support table eng –design (now >85%)
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
20
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Engineering Status – Configuration Control
CAD-CAE system
model-documentation
hierarchy established
“Drawing Tree”
Hutch Level definitive
lay-out and MIE stayclears established and
released.
MIE interface models
defined
Component “masterbeam” model defined.
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
21
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Engineering Status - WBS 1.2.5.1
Diffractometer System –
Detector Mover
ESD in release
Meeting with robotic integration
engineering firm conducted May
16th
Reviewed and agreed draft ESD
Vendor preliminarily agreed to
design-build of integrated assembly.
Extensive effort in development of
characterization -measurement
program.
Statement of work complete, PO
approved.
Tests conducted wk Aug 11th at
Staubli-USA facility.
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
22
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Engineering Status - WBS 1.2.5.1
Diffractometer System - Sample
Goniometer
Sample goniometer ESD in release
Meeting with potential vendor
conducted June 16th
Reviewed and agreed draft ESD,
revisions suggested.
Vendor preliminarily agreed to
design-build of integrated assembly.
ESD completed “stake holders
review” of controls-mechanical
integration requirements and has
been released.
SLAC designed mounting base
preliminary design advanced
Need preliminary vendor component
designs to proceed.
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
23
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Engineering Status - WBS 1.2.2.1
Long Table, Supports & Shielding
Main support system for XPP diagnostics-optics
Significant progress complete toward PDR
Requirements established-agreed (ESD SP-391-000-84)
Configuration defined – requirements met
Design elements directly exportable to WBS 1.2.2.2
Combined 1.2.2.1 & 1.2.2.2 PDR to be conducted during Q4
FY08 (~per schedule)
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
24
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Value Management - WBS 1.2.2.1
All configurations
compared against
physics /
engineering / ESH
requirements /
cost / schedule
Materials used in
each case / for
each element
selected for
optimization of
requirements
“exportability” to
1.2.2.2, and other
instruments, a
significant
consideration
CONFIGURATION OPTION
PRO
CON
2 leg / 1 Strong-Back
Possible low leg cost
Transport easy
Possibly reduced seismic loads
Rail alignment difficult
S'back grad temp deflection
Torsional stiffness
Potential high mass to move
Motion control problematic
S'back fab expensive
3+ leg / 1 Strong-Back
Possible low leg cost
Transport easy
Flexibility of rail placement
Possibly reduced seismic loads
Rail alignment extremely
difficult
Over-constrained system
Motion control problematic
S'back fab expensive
3+ leg / 2+ Strong-Back
Possible low leg cost
Transport easy
Flexibility of rail placement
Extremely stiff s'back easy / cheap
Possibly reduced seismic loads
Rail alignment difficult
Motion control problematic
Surface Plate / 1 Strong-Back
Easy rail alignment
Absolute alignment easy
Seismic constraint easy
High "thermal mass"
S'back grad temp deflection
Torsional stiffness
Potential high mass to move
Expensive s'back fab
Rail placement not optimum
Possibly high transport cost ?
Surface Plate / 2+ Strong-Back
Easy rail alignment
Absolute alignment easy
Seismic constraint easy
High "thermal mass"
Possibly high transport cost ?
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
25
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Engineering – Milestone Look-Ahead
Near Term
XPP PDR Long Table…………………………………………..Q4 FY’08
XPP PDR Optical Support Table…………………………….Q4 FY’08
XPP PDR Hutch Optical Table Location …………………..Q4 FY’08
XPP PDR - Short Table ………………………………………..Q4 FY’08
XPP Seismic Review - Support & Shielding ………………Q4 FY’08
XPP Seismic Review - Optics Support……………………..Q4 FY’08
All systems are on schedule for review as planned.
Plan to combine all PDR’s into one event due to excellent design
progress and achieved commonality .
Milestones Through End Q2 FY’09
>15 XPP specific (L 4,5,6)
Not counting “near term”
Includes:
PDR Sample Goniometer
PDR Detector Mover
PDR Vacuum System
FDRs of all Supports
“XPP PRELIMINIARY DESIGNS COMPLETE”
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
26
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
XPP SCOPE, CD-4 DELIEVERY SCHEDULE
CD-4A
COMPONENT
TRAVERSING SUPPORTS
FIXED SUPPORTS
XPP
CD-4C
WBS
1.2.2.1
COMPONENT
LASER POWER AMP MISC PARTS
WBS
1.2.3.1.2
1.2.2.2
LASER POWER AMP PUMP
1.2.3.1.2
LASER COMPRESSOR MISC PARTS
1.2.3.1.2
LASER POCKEL CELL
1.2.3.1.2
LASER OPTICS AND OPTOMECHANICS
1.2.3.2.1
LASER TEMPORAL PULSE SHAPER
1.2.3.1.3
LASERFAST OSCILLOSCOPE
1.2.3.2.2
LASER OPTICAL PARAMETRIC AMPLIFIER
1.2.3.1.4
LASER GRENOUILLE
1.2.3.2.2
LASER 3RD ORDER CORRELATOR
1.2.3.2.2
LASER SAMPLING SCOPE
1.2.3.2.2
LASER OPTICAL EXPERIMENTS
1.2.3.2.4
LASER DIAGNOSTIC EQUIPMENT
1.2.3.2.2
HUTCH OPTICAL TABLE SYSTEM
1.2.3.2.3
LASER CONTAINMENT
1.2.3.2.5
BNL DETECTOR SENSOR
1.2.4.2
BNL DETECTOR ASIC
1.2.4.3
BNL DETECTOR CONTROLS AND DAQ
1.2.4.4
DIFFRACTOMETER GONIOMETER
1.2.5.1
DIFFRACTOMETER DETECTOR MOVER
1.2.5.1
HUTCH DROP FLOOR
1.2.6.2
HUTCH BEAMLINE CABLE TRAYS
1.2.6.2
VACUUM EQUIPMENT
1.2.7.1
ION PUMPS
GAUGES
VALVES
LEAK DETECTOR
DCO
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
27
SPOOLS & BELLOWS
1.2.7.2.1
SUPPORTS
POP-IN PROFILE MONITOR
1.2.7.2.2
1.5.X.X
HARMONIC REJECTION MIRRORS
1.5.X.X
POP-IN INTENSITY MONITOR
1.5.X.X
X-RAY FOCUSING LENS
1.5.X.X
INTENSITY POSITION MONITOR
1.5.X.X
ATTENUATOR
1.5.X.X
SLIT SYSTEM (COARSE GUARD)
1.5.X.X
SLIT SYSTEM (PRECISE PRIMARY)
1.5.X.X
SLIT SYSTEM (PRECISE MONO)
1.5.X.X
PULSE PICKER
1.5.X.X
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Basis of Estimates (1)
All WBS level 2 BOE packages
use identical format
All BOE packages contain:
Detailed description of each
itemized part or component.
Part number, drawing number,
qty, vendor, notes, weight.
Detailed cost estimate
cost, labor hrs & rate, material
handling charges, etc.
Supporting quotations,
drawings, vendor catalog info,
etc.
3D model if applicable and
available
All BOE packages are
configuration controlled at the
CD2 baseline
Cross referenced to P3 activity
ID’s
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
28
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Basis of Estimate (2)
Detailed Engineering
& Design Estimates
Instrument –
engineer unique
Not controlled
documents
BOE detail
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
29
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Procurement Strategy
A variety of sources
are used to design –
build - install XPP.
SLAC effort where
skill set exists.
Vendor design – build
used where available.
Previous designs and
Off-The-Shelf
components are used
whenever available.
XPP Work Breakdown Structure
WBS
1.2
TITLE
XPP System Integration & Design
1.2.02
XPP X-ray Optics & Support Table
1.2.02.02
1.2.03
1.2.03.01
XPP Optics Support Table & Supports
XPP Ti:Sapphire Laser
Ti:Sapphire Amplifier(s) System/Pumps
Temporal Pulse Shaper
Optical Parametric Amplifier
XPP Optics, Optomechanics & Diagnostics
1.2.03.02.01
Optics & Optomechanics
1.2.03.02.02
Laser Diagnostics
1.2.03.02.03
Hutch Optical Table System
1.2.03.02.04
Optical Experiments
1.2.03.02.05
Laser Containment System
1.2.03.02.06
1.2.04
Laser Hall Optical Table System
XPP Detector System (BNL)
1.2.04.01
Detector Support and Integration
1.2.04.02
Detector Sensor
1.2.04.03
Detector Application Specific Integrated Circuits (ASIC)
1.2.04.04
1.2.05
1.2.05.01
Detector Controls, Electronics and DAQ
XPP Sample Environment & Diffractometer System
XPP Diffractometer System
Previous Design/OTS
1.2.06
SLAC
1.2.06.01
BNL
1.2.06.02
Domestic Vendor
1.2.07
Foreign Vendor
1.2.07.01
XPP Vacuum Equipment
Long Lead Procurement
1.2.07.02
XPP Vacuum Hardware
1.2.07.02.01
1.2.07.02.02
1.2.08
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
30
Install
XPP Laser System
1.2.03.01.03
1.2.03.02
Build
XPP Support Table, Supports & Shielding
1.2.03.01.02
1.2.03.01.04
Design
X-RAY PUMP PROBE (XPP)
1.2.01
1.2.02.01
Resource Source
XPP Facilities
XPP Hutch Specification
XPP Utilities & Hutch Equipment
XPP Vacuum System
XPP Spools & Bellows
XPP Vacuum Supports
XPP Installation
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Cost & Schedule
Resource loaded schedule
completed and has been fully
implemented into EVMS
TYPICAL DESIGN FLOW WITH L5 MILESTONES
SLAC EVMS certified
All WBS level 2 Engineeringdesign flows use similar format
XPP Milestone Stats
140 Level 4 & 5 milestones
L4 = systems
L5 = interface-handoff
35 Level 6 milestones
L6 = commitments-awards
~100 week duration to CD-4A
>1.5 milestone / week nominal
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
31
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Cost & Schedule
XPP budget stats
Peak spending = FY09
Peak Resource = Q4 FY08
Labor = ~58%
M&S = ~42%
WBS 1.2
Resource Type
Value
Labor-SLAC
Non-Labor-SLAC
Labor-BNL
Non-Labor-BNL
Total BAC
$2,454,983
$2,189,886
$1,018,849
$278,767
$5,942,485
W BS 1.2
1.2.01
Sy s te m Inte g ra tio n &
D e s ig n
1.2.02
X-ra y Op tic s & Sup p o rt
T a b le
1.2.03
La s e r Sy s te m
1.2.04
D e te c to r
1.2.05
D iffra c to me te r Sy s te m
1.2.06
Fa c ilitie s
1.2.07
Va c uum Sy s te m
1.2.08
Ins ta lla tio n
W BS T o ta ls :
FY07
FY08
FY09
FY10
FY11
FY12
Cumula tiv e
$
-
$
417,622
$
240,979
$
220,436
$
166,956
$
83,060
$
1,129,054
$
-
$
177,268
$
199,482
$
14,138
$
-
$
-
$
390,888
$
-
$
63,099
$
102,144
$
434,401
$
566,885
$
-
$
1,166,529
$
-
$
727,502
$
698,306
$
26,032
$
16,053
$
-
$ 12,110
$
137,429
$
613,012
$
321,652
$
-
$
-
$
1,084,203
$
-
$
-
$
82,837
$
-
$
-
$
-
$
82,837
$
-
$
12,561
$
79,028
$
176,237
$
-
$
-
$
267,825
$
-
$
-
$
87,147
$
250,114
$
15,995
$
-
$
353,256
$ 12,110
$
1,535,481
$
2,102,935
$ 1,443,011
$
765,889
$
83,060
$
5,942,486
XPP Resource Requirements
LaborSLAC
Non-LaborSLAC
Labor-BNL
Non-LaborBNL
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
32
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
XPP Critical Path (1)
Driving Milestones
LL Approval, CD-4
Diffractometer
Design Effort
Diffractometer
Awards & Vendor
effort
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
33
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
XPP Critical Path (2)
Diffractometer
Installation
effort
Sample goniometer is critical path item for XPP
Goniometer is long lead procurement
Seek procurement authorization before CD-3A
XPP Schedule has sample goniometer at 75 days float
~500 days duration / 75 days float = ~6.5 effort day per day of float
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
34
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Risk Identification & Mitigation
LUSI – XPP risk addressed per “LCLS Risk Management Plan”
document number PMD 1.1-002-R4
WBS items with risk analysis – risk severity of medium or high
forwarded for inclusion in LUSI Risk Registry for detailed
treatment
XPP RISK ANALYSIS
WBS
Element
Description
1.2.02.01
Support Table, Supports & Shielding
1.2.02.02
Optics Table & Support
1.2.03.01.02 Ti:Sapphire Amplifier System/Pumps
1.2.03.01.03 Temporal Pulse Shaper
1.2.03.01.04 Optical Parametric Amplifier
1.2.03.02.01 Optics & Optomechanics
1.2.03.02.02 Laser Diagnostics
1.2.03.02.03 Hutch Optical Table System
1.2.03.02.04 Optical Experiments
1.2.03.02.05 Laser Containment System
1.2.03.02.06 Laser Hall Optical Table System
1.2.04
XPP Detector System
1.2.05.01
Diffractometer Tilt Platform
1.2.05.01
Diffractometer Kappa
1.2.05.01
Diffractometer Support Structure
1.2.05.01
Detector Mover
1.2.06.02
Huch Cabinets
1.2.06.02
Raised Floor & Cable Trays
1.2.07.01
Vacuum Equipment
1.2.07.02.01 Spools & Bellows
1.2.07.02.02 Vacuum Supports
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
35
Technologic Work Scope
al Maturity
Definition
NA
1
1
1
1
1
1
1
1
1
1
3
2
2
2
3
1
1
1
1
1
NA
2
2
2
2
2
2
2
2
2
2
2
2
2
1
2
2
2
2
2
2
Inter-Organizational
Dependence
Probablity of
Risk
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
3
1
1
1
1
1
Very Unlikely
Unlikely
Unlikely
Unlikely
Unlikely
Unlikely
Unlikely
Unlikely
Unlikely
Unlikely
Unlikely
Likely
Unlikely
Unlikely
Unlikely
Likely
Unlikely
Unlikely
Unlikely
Unlikely
Unlikely
Risk
Risk Severity
Consequences
Marginal
Marginal
Marginal
Negligible
Marginal
Negligible
Marginal
Marginal
Marginal
Marginal
Marginal
Significant
Significant
Significant
Significant
Significant
Negligible
Negligible
Negligible
Negligible
Negligible
Low
Low
Low
Low
Low
Low
Low
Low
Low
Low
Low
High
Medium
Medium
Medium
High
Low
Low
Low
Low
Low
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Risk Identification & Mitigation
Diffractometer System
Sample Goniometer & Detector Mover sub-systems share similar risks.
Both systems are design –build by vendor.
Both systems use same LUSI specified eng-design-fab flow.
Risk Assessment:
schedule delay : late placement of PO to vendor.
Seek pre-approval of elements prior to BA.
Insure all stake holders are aware of status and their requirements.
Closely track document flow to insure timely sign-off / forwarding.
schedule delay: late vendor engineer-design review approval.
Insure initial vendor buy in of timeline.
Closely track vendor progress during design stage.
Establish contact with sub-vendors to insure timely deliveries.
Complete periodic spot review of designs to insure suitability.
schedule delay: late fabrication-assembly.
Request periodic status updates.
Start partial acceptance testing as soon as suitable sub-assemblies are completed.
schedule delay : requirements not met during vendor site acceptance testing.
Replace individually deficient element.
Temporally immobilize deficient element.
Deploy interim hardware with reduced capability.
Technical requirements not met in commissioning.
Investigate alternative hardware for interim use.
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
36
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
XPP CD-2 Project Readiness
XPP designs are
mature and
technically meet
or exceed the
requirements for
CD-2
All CD-2 criteria
met
Management






WBS Dictionary
Milestone Dictionary
Risk Registry
Resource Loaded Schedule
Basis of Estimate
Hazard Analysis Report
Technical
Fully define scope of project, document & review
Instrument Physics Requirement Document (PRD)
Instrument Engineering Specification Document (ESD)
Instrument Start-Up Plan
Component PRDs - Released
Component ESDs - Pre-released
Advance technical designs to exceed the CD-2
requirement to provide sufficient information to develop
performance baseline
Preliminary Instrument Design Review
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
37








D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Summary
XPP designs are mature and the instrument
team has made significant design progress
since the CD-1 Review
XPP has an established design with a
consistent cost estimate. Over 80% of the
materials estimates came from vendor
quotations, catalogs, or previous orders
Critical Path “float” reasonable for total
schedule duration
Significant effort , and progress, to date in
technical system risk reduction.
XPP ready for CD2 approval.
LUSI DOE Review
August 20, 2008
X-ray Pump-Probe (WBS 1.2)
38
D. Fritz & J. Langton
dmfritz@slac.stanford.edu
langton@slac.stanford.edu
Download