LUSI X-ray Pump-Probe Instrument WBS 1.2 David Fritz – XPP Instrument Scientist J Brian Langton – XPP Lead Engineer LUSI CD-2 Review August 20, 2008 Team Leader: Kelly Gaffney Second Scientist: Marc Messerschmidt Designer: Jim Defever Designer: Jim Delor LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 1 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Outline Physics Requirements Safety- XPP Unique Hazards & Mitigations Instrument Configuration Engineering / Design Status Value Engineering / Management Basis Of Estimate Procurement Strategy Cost & Schedule Critical Path Risk Analysis Summary LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 2 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu XPP Staff Instrument Scientist -David Fritz Engineering Staff J Langton - Lead Engineer Jim Defever – Mechanical Engineer Jim Delor – Mechanical Engineer Don ArnettDesign Supervision LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 3 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Science Team Specifications and instrument concept developed with the science team. The XPP team leaders Kelly Gaffney, Photon Science, SLAC (leader) Jorgen Larsson, Lund Institute of Technology, Sweden David Reis, University of Michigan Thomas Tschentscher, DESY, Germany LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 4 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu XPP Scope - WBS 1.2 WBS Scope/CD-2 Cost Includes: 1.2.1 XPP System Integration & Design 1.2.2 XPP X-ray optics and diagnostics support tables 1.2.3 XPP Ultrafast laser system 1.2.4 XPP 2D Detector from BNL by MOU 1.2.5 XPP Sample goniometer 1.2.5 XPP Detector mover 1.2.6 XPP Hutch Facilities 1.2.7 XPP Vacuum system 1.2.8 XPP Installation Other Related WBS 1.5 Diagnostics & Common Optics 1.6 Controls and Data Acquisition LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 5 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu XPP Physics Requirements Goals Perform time resolved experiments at the highest temporal resolution achievable (80 fs rms) Accommodate as many classes of experiments are reasonable achievable Capable of running in a shared beam mode using a future beam splitting monochromator Instrument must be accessible while beam is delivered to FEH Tailor and characterize X-ray and optical beam parameters Spatial profile Intensity Repetition rate Spectral bandwidth Wavelength (optical laser) Temporal profile (optical laser) Key Performance Parameters 4-20 keV Using fundamental and third harmonic 0.1-0.01% energy resolution 1000 x 1000 pixel detector LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 6 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Component Physics Requirements 1.2.2 XPP X-ray Optics and Supports Fixed table (hutch 2) and 2 translating tables (hutch 3) Rigid support structures that will define the x-ray optical axis Design goals in priority order 1. Stabilize optics with respect to each other (short & long term) 2. Stabilize optics with respect to global coordinate system LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 7 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Component Physics Requirements 1.2.3 XPP Laser System Will utilize and expand upon AMO laser system AMO Laser Requirements > 3 mJ per pulse energy at sample (800 nm) < 50 fs pulse duration 120 Hz < 100 fs phase jitter to LCLS RF Multipass amplifier >20 mJ per pulse energy (800 nm) < 50 fs pulse duration 120 Hz Frequency conversion capability OPA Harmonic generation Temporal pulse shaping capability Diagnostics suite System designed such that a non-laser trained user can perform an XPP experiment Sufficient automation to control laser parameters Sufficient engineering controls to provide safe working environment LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 8 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Component Physics Requirements 1.2.4 XPP Detector System Developed at BNL via MOU High detector quantum efficiency Single photon sensitivity Large dynamic range >103 104 photon dynamic range per pixel 120 Hz readout rate 1024 x 1024 square pixels 90 µm pixel size LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 9 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Component Physics Requirements 1.2.5 – Sample Goniometer Flexibility to accommodate a wide variety of sample environments (50 kg) Capable of orienting small samples (~ 50 μm) over a wide range of reciprocal space Sphere of confusion < 30μm Open access to allow close proximity laser optics Operate in direct or future monochromatic beam No interference with direct beamline while in monochromatic mode LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 10 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Component Physics Requirements 1.2.5 – Detector Mover 10 cm – 100 cm sample to detector distance in forward-scattering upper hemisphere quadrant 10 cm – 50 cm sample to detector distance in backscattering upper hemisphere quadrant Repeatable position the XPP detector pixels to a fraction of the pixel size Definitively know the position of all detector pixels to a fraction of the pixel size Operate in both interaction points No interference with direct beamline while in monochromatic mode LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 11 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Component Physics Requirements 1.2.6 XPP Hutch facilities Raised flooring Storage cabinets, work benches and tool chests Utilities distribution 1.2.7 XPP Vacuum system < 10-7 Torr > 10 year pump lifetime 1.2.8 XPP Installation LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 12 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Safety - Hazard Analysis (1) XPP unique hazard: non-ionizing radiation PM-391-001-34 Appendix A, Item 3 Optical pump laser system Unmitigated Severitycatastrophic critical marginal negligible Probability frequent 1 3 7 13 probable 2 5 9 16 occasional 4 6 11 18 remote 8 10 14 19 improbable 12 15 17 20 mitigated ITEM 3 HAZARD Non-ionizing radiation exposure UNMITIGATED RISK LEVEL Laser room connected to experimental Level 7 hutch Marginal Class IV laser in experimental hutch Frequent CAUSE LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 13 PREVENTION / MITIGATION POTENTIAL IMPACT Engineered controls including opaque barriers, Personnel injury – eye laser safety system, beam containment during damage or skin burns routine operation PPS equipment: appropriate laser goggles for wavelengths in use. Administrative controls including laser safety training, alignment mode with only trained personnel in hutch Ref: SLAC ES&H Manual, Chapter 10, Laser Safety MITIGATED RISK Level 20 Negligible Improbable D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Safety - Hazard Analysis (2) XPP unique hazard: remote controlled robot arm PM-391-001-34 Appendix A, Item 14 Diffractometer system detector mover Severitycatastrophic critical marginal negligible Probaibility frequent 1 3 7 13 probable 2 5 9 16 occasional 4 6 11 18 remote 8 10 14 19 improbable 12 15 17 20 Unmitigated mitigated ITEM 3 HAZARD remote controlled robot arm CAUSE software or hardware failure LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 14 UNMITIGATED RISK LEVEL Level 10 critical remote PREVENTION / MITIGATION POTENTIAL IMPACT Robot arm will be designed to be compliant Personnel injury with OSHA technical manual, section IV, chapter4; “Industrial Robot and Robot System Safety” and ANSI/RIA R15.-06; “American National Standard for Industrial Robots and Robot Systems.” The safety measures will include, but are not limited to the following: 1. Personnel Protection Systems – proximity sensors, light curtains, pressure mats, emergency stops.. 2. Hardware systems - docking interlocks to robot power and control systems switching, force sensor interlocks. 3. Software system - training & maintenance modes. SLAC safety reviews and acceptance testing of device hardware and controls. MITIGATED RISK Level 20 Negligible Improbable D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Instrument Configuration (1) The up-beam vacuum drift section: This area extends up-beam into NEH hutch 2 and includes a small suite of x-ray optic and diagnostic components. Hutch 3 space is primarily intended for future upgrades to enhance beam sharing between experimental hutches. Includes elements from WBS 1.2.2.2, 1.2.2.7 & 1.5.X.X (DCO scope) LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 15 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Instrument Configuration (2) The upbeam x-ray optics-diagnostic suite: This area is for analysis and optimization of x-ray beam properties. The Area also provides x-ray vertical steering capabilities for special experiment configurations. Beamline components are designed to translate 0.6 meter (nominal) in “X” to facilitate early science beam sharing. Also includes final pump laser optics. Includes elements from WBS 1.2.2.1, 1.2.7 & 1.5.X.X (DCO scope) LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 16 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Instrument Configuration (3) The optical pump laser system: System used to deliver excitation energy to experimental samples. Includes Optical support system and laser containment hardware. Includes elements from WBS 1.2.3 LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 17 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Instrument Configuration (4) The diffractometer system: Is composed of the sample goniometer (“tilt” and “kappa” goniometer) and the detector mover subsystems. This hardware provides for the positioning and rotation of the experimental sample and the array detector. Includes elements from WBS 1.2.5 LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 18 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Instrument Configuration (5) The down-beam diagnostic-drift section: This area is used for x-ray beam parameters analysis and diffractometer system alignment. Beamline components are designed to translate 0.6 meter (nominal) in “X” for early science beam sharing. Includes elements from WBS 1.2.2.1, 1.2.7 & 1.5.X.X (DCO scope) LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 19 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Engineering Status - Q3 FY08 Goals Establish CAD System – file structure – Drawing Tree (complete) Generate Higher Level models - drawings Hutch 3 Definitive Lay-out (complete, released) MIE Stay Clear models, documentation (complete, released) Detector Mover ESD Complete, released Vendor review (complete) Detector Mover “proof of concept” (complete) Measurements completed week of Aug 11th Sample Goniometer ESD Complete, released Vendor Review (complete) >50% complete on long support table eng –design (now >85%) LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 20 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Engineering Status – Configuration Control CAD-CAE system model-documentation hierarchy established “Drawing Tree” Hutch Level definitive lay-out and MIE stayclears established and released. MIE interface models defined Component “masterbeam” model defined. LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 21 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Engineering Status - WBS 1.2.5.1 Diffractometer System – Detector Mover ESD in release Meeting with robotic integration engineering firm conducted May 16th Reviewed and agreed draft ESD Vendor preliminarily agreed to design-build of integrated assembly. Extensive effort in development of characterization -measurement program. Statement of work complete, PO approved. Tests conducted wk Aug 11th at Staubli-USA facility. LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 22 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Engineering Status - WBS 1.2.5.1 Diffractometer System - Sample Goniometer Sample goniometer ESD in release Meeting with potential vendor conducted June 16th Reviewed and agreed draft ESD, revisions suggested. Vendor preliminarily agreed to design-build of integrated assembly. ESD completed “stake holders review” of controls-mechanical integration requirements and has been released. SLAC designed mounting base preliminary design advanced Need preliminary vendor component designs to proceed. LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 23 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Engineering Status - WBS 1.2.2.1 Long Table, Supports & Shielding Main support system for XPP diagnostics-optics Significant progress complete toward PDR Requirements established-agreed (ESD SP-391-000-84) Configuration defined – requirements met Design elements directly exportable to WBS 1.2.2.2 Combined 1.2.2.1 & 1.2.2.2 PDR to be conducted during Q4 FY08 (~per schedule) LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 24 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Value Management - WBS 1.2.2.1 All configurations compared against physics / engineering / ESH requirements / cost / schedule Materials used in each case / for each element selected for optimization of requirements “exportability” to 1.2.2.2, and other instruments, a significant consideration CONFIGURATION OPTION PRO CON 2 leg / 1 Strong-Back Possible low leg cost Transport easy Possibly reduced seismic loads Rail alignment difficult S'back grad temp deflection Torsional stiffness Potential high mass to move Motion control problematic S'back fab expensive 3+ leg / 1 Strong-Back Possible low leg cost Transport easy Flexibility of rail placement Possibly reduced seismic loads Rail alignment extremely difficult Over-constrained system Motion control problematic S'back fab expensive 3+ leg / 2+ Strong-Back Possible low leg cost Transport easy Flexibility of rail placement Extremely stiff s'back easy / cheap Possibly reduced seismic loads Rail alignment difficult Motion control problematic Surface Plate / 1 Strong-Back Easy rail alignment Absolute alignment easy Seismic constraint easy High "thermal mass" S'back grad temp deflection Torsional stiffness Potential high mass to move Expensive s'back fab Rail placement not optimum Possibly high transport cost ? Surface Plate / 2+ Strong-Back Easy rail alignment Absolute alignment easy Seismic constraint easy High "thermal mass" Possibly high transport cost ? LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 25 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Engineering – Milestone Look-Ahead Near Term XPP PDR Long Table…………………………………………..Q4 FY’08 XPP PDR Optical Support Table…………………………….Q4 FY’08 XPP PDR Hutch Optical Table Location …………………..Q4 FY’08 XPP PDR - Short Table ………………………………………..Q4 FY’08 XPP Seismic Review - Support & Shielding ………………Q4 FY’08 XPP Seismic Review - Optics Support……………………..Q4 FY’08 All systems are on schedule for review as planned. Plan to combine all PDR’s into one event due to excellent design progress and achieved commonality . Milestones Through End Q2 FY’09 >15 XPP specific (L 4,5,6) Not counting “near term” Includes: PDR Sample Goniometer PDR Detector Mover PDR Vacuum System FDRs of all Supports “XPP PRELIMINIARY DESIGNS COMPLETE” LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 26 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu XPP SCOPE, CD-4 DELIEVERY SCHEDULE CD-4A COMPONENT TRAVERSING SUPPORTS FIXED SUPPORTS XPP CD-4C WBS 1.2.2.1 COMPONENT LASER POWER AMP MISC PARTS WBS 1.2.3.1.2 1.2.2.2 LASER POWER AMP PUMP 1.2.3.1.2 LASER COMPRESSOR MISC PARTS 1.2.3.1.2 LASER POCKEL CELL 1.2.3.1.2 LASER OPTICS AND OPTOMECHANICS 1.2.3.2.1 LASER TEMPORAL PULSE SHAPER 1.2.3.1.3 LASERFAST OSCILLOSCOPE 1.2.3.2.2 LASER OPTICAL PARAMETRIC AMPLIFIER 1.2.3.1.4 LASER GRENOUILLE 1.2.3.2.2 LASER 3RD ORDER CORRELATOR 1.2.3.2.2 LASER SAMPLING SCOPE 1.2.3.2.2 LASER OPTICAL EXPERIMENTS 1.2.3.2.4 LASER DIAGNOSTIC EQUIPMENT 1.2.3.2.2 HUTCH OPTICAL TABLE SYSTEM 1.2.3.2.3 LASER CONTAINMENT 1.2.3.2.5 BNL DETECTOR SENSOR 1.2.4.2 BNL DETECTOR ASIC 1.2.4.3 BNL DETECTOR CONTROLS AND DAQ 1.2.4.4 DIFFRACTOMETER GONIOMETER 1.2.5.1 DIFFRACTOMETER DETECTOR MOVER 1.2.5.1 HUTCH DROP FLOOR 1.2.6.2 HUTCH BEAMLINE CABLE TRAYS 1.2.6.2 VACUUM EQUIPMENT 1.2.7.1 ION PUMPS GAUGES VALVES LEAK DETECTOR DCO LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 27 SPOOLS & BELLOWS 1.2.7.2.1 SUPPORTS POP-IN PROFILE MONITOR 1.2.7.2.2 1.5.X.X HARMONIC REJECTION MIRRORS 1.5.X.X POP-IN INTENSITY MONITOR 1.5.X.X X-RAY FOCUSING LENS 1.5.X.X INTENSITY POSITION MONITOR 1.5.X.X ATTENUATOR 1.5.X.X SLIT SYSTEM (COARSE GUARD) 1.5.X.X SLIT SYSTEM (PRECISE PRIMARY) 1.5.X.X SLIT SYSTEM (PRECISE MONO) 1.5.X.X PULSE PICKER 1.5.X.X D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Basis of Estimates (1) All WBS level 2 BOE packages use identical format All BOE packages contain: Detailed description of each itemized part or component. Part number, drawing number, qty, vendor, notes, weight. Detailed cost estimate cost, labor hrs & rate, material handling charges, etc. Supporting quotations, drawings, vendor catalog info, etc. 3D model if applicable and available All BOE packages are configuration controlled at the CD2 baseline Cross referenced to P3 activity ID’s LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 28 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Basis of Estimate (2) Detailed Engineering & Design Estimates Instrument – engineer unique Not controlled documents BOE detail LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 29 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Procurement Strategy A variety of sources are used to design – build - install XPP. SLAC effort where skill set exists. Vendor design – build used where available. Previous designs and Off-The-Shelf components are used whenever available. XPP Work Breakdown Structure WBS 1.2 TITLE XPP System Integration & Design 1.2.02 XPP X-ray Optics & Support Table 1.2.02.02 1.2.03 1.2.03.01 XPP Optics Support Table & Supports XPP Ti:Sapphire Laser Ti:Sapphire Amplifier(s) System/Pumps Temporal Pulse Shaper Optical Parametric Amplifier XPP Optics, Optomechanics & Diagnostics 1.2.03.02.01 Optics & Optomechanics 1.2.03.02.02 Laser Diagnostics 1.2.03.02.03 Hutch Optical Table System 1.2.03.02.04 Optical Experiments 1.2.03.02.05 Laser Containment System 1.2.03.02.06 1.2.04 Laser Hall Optical Table System XPP Detector System (BNL) 1.2.04.01 Detector Support and Integration 1.2.04.02 Detector Sensor 1.2.04.03 Detector Application Specific Integrated Circuits (ASIC) 1.2.04.04 1.2.05 1.2.05.01 Detector Controls, Electronics and DAQ XPP Sample Environment & Diffractometer System XPP Diffractometer System Previous Design/OTS 1.2.06 SLAC 1.2.06.01 BNL 1.2.06.02 Domestic Vendor 1.2.07 Foreign Vendor 1.2.07.01 XPP Vacuum Equipment Long Lead Procurement 1.2.07.02 XPP Vacuum Hardware 1.2.07.02.01 1.2.07.02.02 1.2.08 LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 30 Install XPP Laser System 1.2.03.01.03 1.2.03.02 Build XPP Support Table, Supports & Shielding 1.2.03.01.02 1.2.03.01.04 Design X-RAY PUMP PROBE (XPP) 1.2.01 1.2.02.01 Resource Source XPP Facilities XPP Hutch Specification XPP Utilities & Hutch Equipment XPP Vacuum System XPP Spools & Bellows XPP Vacuum Supports XPP Installation D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Cost & Schedule Resource loaded schedule completed and has been fully implemented into EVMS TYPICAL DESIGN FLOW WITH L5 MILESTONES SLAC EVMS certified All WBS level 2 Engineeringdesign flows use similar format XPP Milestone Stats 140 Level 4 & 5 milestones L4 = systems L5 = interface-handoff 35 Level 6 milestones L6 = commitments-awards ~100 week duration to CD-4A >1.5 milestone / week nominal LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 31 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Cost & Schedule XPP budget stats Peak spending = FY09 Peak Resource = Q4 FY08 Labor = ~58% M&S = ~42% WBS 1.2 Resource Type Value Labor-SLAC Non-Labor-SLAC Labor-BNL Non-Labor-BNL Total BAC $2,454,983 $2,189,886 $1,018,849 $278,767 $5,942,485 W BS 1.2 1.2.01 Sy s te m Inte g ra tio n & D e s ig n 1.2.02 X-ra y Op tic s & Sup p o rt T a b le 1.2.03 La s e r Sy s te m 1.2.04 D e te c to r 1.2.05 D iffra c to me te r Sy s te m 1.2.06 Fa c ilitie s 1.2.07 Va c uum Sy s te m 1.2.08 Ins ta lla tio n W BS T o ta ls : FY07 FY08 FY09 FY10 FY11 FY12 Cumula tiv e $ - $ 417,622 $ 240,979 $ 220,436 $ 166,956 $ 83,060 $ 1,129,054 $ - $ 177,268 $ 199,482 $ 14,138 $ - $ - $ 390,888 $ - $ 63,099 $ 102,144 $ 434,401 $ 566,885 $ - $ 1,166,529 $ - $ 727,502 $ 698,306 $ 26,032 $ 16,053 $ - $ 12,110 $ 137,429 $ 613,012 $ 321,652 $ - $ - $ 1,084,203 $ - $ - $ 82,837 $ - $ - $ - $ 82,837 $ - $ 12,561 $ 79,028 $ 176,237 $ - $ - $ 267,825 $ - $ - $ 87,147 $ 250,114 $ 15,995 $ - $ 353,256 $ 12,110 $ 1,535,481 $ 2,102,935 $ 1,443,011 $ 765,889 $ 83,060 $ 5,942,486 XPP Resource Requirements LaborSLAC Non-LaborSLAC Labor-BNL Non-LaborBNL LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 32 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu XPP Critical Path (1) Driving Milestones LL Approval, CD-4 Diffractometer Design Effort Diffractometer Awards & Vendor effort LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 33 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu XPP Critical Path (2) Diffractometer Installation effort Sample goniometer is critical path item for XPP Goniometer is long lead procurement Seek procurement authorization before CD-3A XPP Schedule has sample goniometer at 75 days float ~500 days duration / 75 days float = ~6.5 effort day per day of float LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 34 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Risk Identification & Mitigation LUSI – XPP risk addressed per “LCLS Risk Management Plan” document number PMD 1.1-002-R4 WBS items with risk analysis – risk severity of medium or high forwarded for inclusion in LUSI Risk Registry for detailed treatment XPP RISK ANALYSIS WBS Element Description 1.2.02.01 Support Table, Supports & Shielding 1.2.02.02 Optics Table & Support 1.2.03.01.02 Ti:Sapphire Amplifier System/Pumps 1.2.03.01.03 Temporal Pulse Shaper 1.2.03.01.04 Optical Parametric Amplifier 1.2.03.02.01 Optics & Optomechanics 1.2.03.02.02 Laser Diagnostics 1.2.03.02.03 Hutch Optical Table System 1.2.03.02.04 Optical Experiments 1.2.03.02.05 Laser Containment System 1.2.03.02.06 Laser Hall Optical Table System 1.2.04 XPP Detector System 1.2.05.01 Diffractometer Tilt Platform 1.2.05.01 Diffractometer Kappa 1.2.05.01 Diffractometer Support Structure 1.2.05.01 Detector Mover 1.2.06.02 Huch Cabinets 1.2.06.02 Raised Floor & Cable Trays 1.2.07.01 Vacuum Equipment 1.2.07.02.01 Spools & Bellows 1.2.07.02.02 Vacuum Supports LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 35 Technologic Work Scope al Maturity Definition NA 1 1 1 1 1 1 1 1 1 1 3 2 2 2 3 1 1 1 1 1 NA 2 2 2 2 2 2 2 2 2 2 2 2 2 1 2 2 2 2 2 2 Inter-Organizational Dependence Probablity of Risk 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 3 1 1 1 1 1 Very Unlikely Unlikely Unlikely Unlikely Unlikely Unlikely Unlikely Unlikely Unlikely Unlikely Unlikely Likely Unlikely Unlikely Unlikely Likely Unlikely Unlikely Unlikely Unlikely Unlikely Risk Risk Severity Consequences Marginal Marginal Marginal Negligible Marginal Negligible Marginal Marginal Marginal Marginal Marginal Significant Significant Significant Significant Significant Negligible Negligible Negligible Negligible Negligible Low Low Low Low Low Low Low Low Low Low Low High Medium Medium Medium High Low Low Low Low Low D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Risk Identification & Mitigation Diffractometer System Sample Goniometer & Detector Mover sub-systems share similar risks. Both systems are design –build by vendor. Both systems use same LUSI specified eng-design-fab flow. Risk Assessment: schedule delay : late placement of PO to vendor. Seek pre-approval of elements prior to BA. Insure all stake holders are aware of status and their requirements. Closely track document flow to insure timely sign-off / forwarding. schedule delay: late vendor engineer-design review approval. Insure initial vendor buy in of timeline. Closely track vendor progress during design stage. Establish contact with sub-vendors to insure timely deliveries. Complete periodic spot review of designs to insure suitability. schedule delay: late fabrication-assembly. Request periodic status updates. Start partial acceptance testing as soon as suitable sub-assemblies are completed. schedule delay : requirements not met during vendor site acceptance testing. Replace individually deficient element. Temporally immobilize deficient element. Deploy interim hardware with reduced capability. Technical requirements not met in commissioning. Investigate alternative hardware for interim use. LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 36 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu XPP CD-2 Project Readiness XPP designs are mature and technically meet or exceed the requirements for CD-2 All CD-2 criteria met Management WBS Dictionary Milestone Dictionary Risk Registry Resource Loaded Schedule Basis of Estimate Hazard Analysis Report Technical Fully define scope of project, document & review Instrument Physics Requirement Document (PRD) Instrument Engineering Specification Document (ESD) Instrument Start-Up Plan Component PRDs - Released Component ESDs - Pre-released Advance technical designs to exceed the CD-2 requirement to provide sufficient information to develop performance baseline Preliminary Instrument Design Review LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 37 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu Summary XPP designs are mature and the instrument team has made significant design progress since the CD-1 Review XPP has an established design with a consistent cost estimate. Over 80% of the materials estimates came from vendor quotations, catalogs, or previous orders Critical Path “float” reasonable for total schedule duration Significant effort , and progress, to date in technical system risk reduction. XPP ready for CD2 approval. LUSI DOE Review August 20, 2008 X-ray Pump-Probe (WBS 1.2) 38 D. Fritz & J. Langton dmfritz@slac.stanford.edu langton@slac.stanford.edu