LCLS Undulator System Status and Schedule Geoff Pile 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Safety Minute Even though you wear your PPE you’re not always as safe as you might think. This guy is wearing his face mask while arc welding. In this case, it’s almost as useful as an ashtray on a motorbike. Two really important statements – 1. Never Underestimate the Power of Co-incidence (There could be more safety issues less obvious than the one you are trying to negate) 2. ISM – Do what you say you do! Define the scope Analyze (ALL) hazards Develop/implement controls Perform the work within controls Feedback & improvement 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Schedule Considerations All Argonne girder components are planned to be available at least 1 month before the P3 “Early Start” of Girder Assembly 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Controls Status and Schedule Controls -1.4.2 – Work Remaining Undulator In-tunnel Rack (UIR) Intra Undulator Cables Electronic Interface Assembly (EIA) 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov 1.4.2 - Controls Ongoing Work Completed 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Undulator In-tunnel Rack (UIR) 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Undulator In-tunnel Rack (UIR) 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Electronic Interface Assembly (EIA) ~1800 Intra Undulator Cables (pre-made/pre-tested) 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Undulator Magnets and Supports 1.4.3 Undulators (39 @ SLAC 7/2007) Support & Motion System - girder, cam movers & fixed supports (37@SLAC 3/2008) X translation issue Quads and Correctors (36 @SLAC 4/2008) 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov 1.4.3 - Magnets and Supports Ongoing Work Completed 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov All 40 undulators were completed by July 2007 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Girders Assembled and Packed at Hi-Tech Girder Manufacture at Metalex Critical Engineering and QA Oversight by Argonne 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov X Translation Stage, Limit Switches, and Adjustable Switch Actuator 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Obtaining X Translation Limits & Stops 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Tuning block modification 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov 1.4.3.5 - Quads and Correctors 37 magnets and 2 sets of spare coils completed 4/08 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Vacuum Systems 1.4.4 46 Vacuum Chambers produced Manufacture started September 2007 & ended May 2008 33 required 7 spares 1 LTT 5 sacrificed for surface finish measurements Monumental task, huge effort, successful ending. Interest has already been expressed in this technology by other projects around the world. 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov 1.4.4 - Vacuum 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Inspection of the total length of the LCLS Vacuum Chamber 17 June 2008 FAC Review - Undulator System Inspection and correction of the LCLS VC end flange perpendicularity Geoff Pile pileg@aps.anl.gov Surface Finish Data of 46 Chambers… 33 required (7 spare – 5 sacrificed – 1 LTT) Extrusion # 1 2 3 4 5 6 8 9 11 h (mm) 353.57 216.02 248.52 236.10 261.25 271.06 302.81 251.17 230.72 rms transverse slope (mrad) 45.45 20.03 27.78 23.69 23.03 37.19 32.23 31.14 25.14 rms longitudinal slope (mrad) 17.36 7.98 8.53 12.29 9.47 13.52 14.06 19.12 9.82 12 13 14 15 17 18 19 20 21 22 23 24 25 26 27 29 30 31 32 33 34 36 37 38 39 40 41 42 43 44 45 46 294.41 308.75 350.85 306.37 324.34 341.19 246.35 244.29 331.53 268.19 275.33 229.15 258.43 325.92 327.66 327.50 317.95 334.76 230.19 230.15 294.70 245.60 198.97 345.21 311.58 311.04 341.13 233.57 342.60 321.34 332.56 254.38 27.43 26.59 38.58 34.49 26.67 50.46 24.78 18.58 34.12 36.40 40.43 23.36 28.51 46.87 53.97 38.76 45.59 47.89 25.44 21.74 44.42 23.85 17.83 48.72 51.02 35.81 49.27 22.24 56.25 52.82 52.82 29.50 15.57 12.64 19.37 15.04 16.20 20.50 11.62 8.08 15.48 14.26 18.56 10.83 10.14 18.46 23.10 20.36 18.91 19.96 12.65 10.27 16.32 8.93 6.85 22.86 18.62 15.33 15.58 10.99 21.74 18.67 19.04 10.34 Totals (rms) 36.94 15.52 17 June 2008 FAC Review - Undulator System Transverse: The transverse rms slope tolerance is 60 mrad Longitudinal: Slope Criteria from H-D Nuhn adjusted for the oval shape Desirable Acceptable Not Desirable Should Avoid Geoff Pile pileg@aps.anl.gov Diagnostic Systems 1.4.5 BPM – 1.4.5.5 BFW – 1.4.5.6 BLM – 1.4.5.8 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov 1.4.5.5 - Diagnostics - BPM 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov BPM Testing at Argonne 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Beam Position Monitor Large effort- solved serious production problems Many brazing issues (differential thermal expansion) Window QA problems Multi-step Process now understood 8 now delivered to SLAC -remainder on track Promising World Class Diagnostic 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov 1.4.5 - Diagnostics – BFW & BLM 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Beam Finder Wire All production problems are resolved at this point, but we were somewhat delayed due to issues with repeatability, chamber coating, and electronic modules. Two units that should have shipped last week are on the way to SLAC at this time. Details in Dean Walters’ talk 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Beam Loss Monitor Five production BLMs will be used to protect the undulators by inhibiting beam bunches following an “above-threshold” radiation event. A joint R&D effort is aimed at enhancing these 5 units to enable LCLS to track each undulator’s accumulated radiation dose. Undulator protection is the highest priority. The BLM will be integrated into the Machine Protection System (MPS) and requires only limited dynamic range from the detectors. Dose tracking will enable long-term magnet damage to be characterized, but requires a radiation detector with large dynamic range (order of 106) and sophisticated diagnostics hardware and software. 30 production BLMs may be built in FY09 if R&D is successful 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Beam Loss Monitor Interface Module 17 June 2008 FAC Review - Undulator System BLM in Inserted Position (Can be easily made to track out with Undulator) Geoff Pile pileg@aps.anl.gov Long Term Test 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Long Term Test 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Long Term Test 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Status and Schedule Undulator System Management and Integration CPR & Costs to go – Generally in good shape. Some unplanned effort has been required in the last two months to solve problems and meet production schedules. Most spares costs were moved to OPC. Final spares costs will be recalculated using actuals and any required adjustments will be made. Green Sheet System A Web-based, almost real time, method of managing ArgonneAPS cross- matrixed effort – (up to 60 staff 18FTE’s/year) ASK System A Web-based method of managing deliveries and technical documentation. A dictionary/index style look-up system. 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov Summary Almost all deliveries complete by July 2008! Production BLMs? TBD (2009) Argonne Construction team rolls off the project in July Argonne Management team drops to halftime in mid-July, and rolls off the project in September. FY09 – a small budget is included for installation and commissioning support 17 June 2008 FAC Review - Undulator System Geoff Pile pileg@aps.anl.gov