LTU/Undulator Commissioning Plans Heinz-Dieter Nuhn, SLAC / LCLS June 16, 2008 Overview Pre-Beam Checkouts LTU to Dump Commissioning (No Undulator Segments) Undulator Segments Commissioning Characterization of Spontaneous Synchrotron Radiation Characterization of SASE June 16, 2008 LTU/Undulator Commissioning Plans 1 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Related Presentations Paul Emma, Commissioning Results and Plans H. Tompkins, FEE/FEL Commissioning Overview Richard Bionta, FEE Diagnostics and Commissioning June 16, 2008 LTU/Undulator Commissioning Plans 2 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu First Light in FEH CD-4 (7/31/2010) X-Rays in NEH FEH Hutch BO FEH Install First Light in FEE Undulator Seg. Install PPS Cert. LTU/Dump FEE/NEH Install LTU/Und/Dump Install now PEP-II run ends LCLS Installation and Commissioning Time-Line PPS J F M AM J J A S ON D J F MAM AM J J A S ON D J F M A M J J Down 2008 2009 2010 Linac/BC2 Commissioning Re-commission Inj/BC2 to SL2 June 16, 2008 LTU/Undulator Commissioning Plans LTU/Und NEH Operations/ Comm. FEE Commissioning Comm. 3 May 2, 2008 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu 2008 2009 Beam-Based Commissioning A B C A: LTU – Dump B: Undulator Segments C: Spontaneous X-Rays D: SASE June 16, 2008 LTU/Undulator Commissioning Plans e--Beam D X-Ray 4 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu LTU/Undulator e--Beam Commissioning Blocks Installation and Conventional Alignment (=>Nov 08) All beamline components except Undulator Segments Pre-Beam Checkouts (Checklists will be prepared) (Oct-Dec 08) LTU Section Magnet Polarities / Motion (OTR, Collimators, Wire-scanners) / etc. Undulator Section Magnet Polarities / Motion (Girder, BFW, Slide) / ADS Calibration / etc. Pre-Undulator Commissioning with Beam (Jan 09 – Mar 09) A LTU Section Undulator Section (w/o Undulator Segments) Motion Control / Beam Containment / Beam-Based Alignment / etc. Beam Dump Section Installation of Undulator Segments (Mar 09) Undulator Commissioning with Beam (Mar 09 – Apr 09) B Beam Based Alignment / Undulator Slide Functions / Beam Stability June 16, 2008 LTU/Undulator Commissioning Plans 5 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu LTU-to-Dump Pre-Beam Checkouts (Oct-Dec 08) Undulator Hall HVAC System checkout (before Girder installation) ADS (WPM & HLS) Control System checkout ADS commissioning EPICS Control System Checkout Network Configuration of IOC's Timing System Communication with ADS Checkout Verification of individual Device Operation Magnet Power Supplies and Interlocks Magnet Polarity Checkout Dipoles Quadrupoles Correctors (where power supplies available) BPM Cable Checkout Motion Checkouts Movable Collimator motion Wire Scanner motion & calibration Beam Finder Wire In/Out motion (BFW01 – BFW33) Girder Motion Control checkout (33 Girders using external pos. sensors) CAM Mover motion checkout Transverse slide motion checkout Compound motion checkout (Smooth beamline motion, System re-pointing) June 16, 2008 LTU/Undulator Commissioning Plans 6 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu LTU Commissioning with Beam (Jan-Mar 09) A Perform radiation surveys in BTH/FEE, etc with beam in the dump (Stan Mao, et al.) Checkout BPMs (timing, scale, sign errors, etc.) Test MPS (toroid collimators, BPMs, loss monitors, magnets, trip the beam, etc?) Checkout optics using beam oscillation data (does a betatron oscillation fit the model well everywhere? – backwards quads?) Test/checkout BYKIK and its abort dump and logic (MPS). Test/checkout new OTR screens/cameras (OTR30, OTR33, and OTRDMP). Test/checkout new wire scanners (WS31, 32, 33, 34). Test/checkout new adjustable collimators (CEDL1, CEDL3, CX31, CY32, CX35, CY36) Commission new energy and launch feedback loops. Characterize beam, etc. June 16, 2008 LTU/Undulator Commissioning Plans 7 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Undulator Beamline Commissioning to Main Dump with Beam but without Undulator Segments (Jan-Mar 08) A Commission Radiation Monitors Get Beam through Undulator vacuum pipe with minimum losses. Checkout BPMs (timing, scale, sign errors, etc.) Commission Girder Motion with Beam Verify and calibrate steering effect of quadrupole motion Calibrate motion parameters (gain, pivot points etc.) Check BPM offset tracking Commission RF Cavity BPMs Check charge dependent response over entire charge range Use Girder Motion to calibrate position vs. readings Check and correct optics matching over entire operational energy range Commission Beam Based Alignment (BBA) Develop saved configurations for three different energies. Commission BBA GUIs and BBA procedure. Commission Beam Finder Wires Calibrate PMT signals. Commission BFW GUIs (Alignment and scanning capabilities) Commission ADS-based girder position stabilization feedback systems. Commission Tune-Up Dump in preparation for commissioning with Undulator Segments June 16, 2008 LTU/Undulator Commissioning Plans 8 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Install Undulator Segments (Mar 09) Mount Undulator Segments onto girders Segments will be stored in Undulator Hall before installation System is designed to be Self-Aligning Re-check slide motion clearance Expect to install 3 Segments / day June 16, 2008 LTU/Undulator Commissioning Plans 9 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu First Beam Through Undulator Segments (Mar 09) B Conditions for First Beam: All Undulator Magnets Rolled-Out Single Shot Operation (low charge) Send single electron bunch through undulator Read and evaluate as much diagnostics as possible along undulator (such as BPMs, beam loss monitors, toroids) Identify and remove sources of beam loss – if any Iterate Goal: Get beam through vacuum chamber with minimum losses. Reminder: Main Constraint is to Protect Undulator from Radiation Damage June 16, 2008 LTU/Undulator Commissioning Plans 10 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu First Undulator Segments Commissioning (Mar – Apr 09) Undulator Segments still in Roll-Out position B Run BBA Roll-In Individual Undulator Segments Transport beam through individual Undulator Segments Start at slot #33 (last Undulator Segment) Check and correct trajectory change. Run BBA with Undulator Segments inserted. Check Segment alignment with BFWs June 16, 2008 LTU/Undulator Commissioning Plans 11 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Commissioning of X-Ray Diagnostics (May – Jun 09) Minimum Requirement Direct Imager Slit X-Ray Diagnostics is located Solid Attenuator after last Undulator Segment in Front-End Enclosure (FEE) Gas Attenuator Gas Detector Beam-Based K Measurement Components See presentations by Tompkins and Bionta June 16, 2008 LTU/Undulator Commissioning Plans 12 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu X Ray Diagnostics (FEE) 5 mm diameter collimators Gas Detector Hard x-ray Monochromator (K Spectrometer) Direct Imager Solid Attenuator e- Slit Gas Detector Muon Shield system NFOV Total Energy Thermal Detector WFOV Hard X-Ray Offset mirror system Start of Experimental Hutches Gas Attenuator June 16, 2008 LTU/Undulator Commissioning Plans Soft X-Ray Offset mirror See 13 Nuhn,and SLAC / LCLS presentationsHeinz-Dieter by Tompkins Bionta nuhn@slac.stanford.edu Characterization of Spontaneous Radiation (May – Jun 09) Initially at 1.5 Å to reduce damage issue Start at low charge Repetition rate of 10 Hz or lower will be sufficient Start to characterize radiation at last undulator Measure: C total spontaneous energy / pulse spontaneous beam direction temporal variation in spontaneous beam parameters spatial distribution around first spontaneous harmonic Limited capability spontaneous radiation spectrum using K wavelength of first harmonic Spectrometer first harmonic wavelength spread Characterize radiation from each individual Undulator Measure relative K of Undulator pair. June 16, 2008 LTU/Undulator Commissioning Plans 14 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu K Measurement: 2-Segment Scheme Measure synchrotron radiation spectrum produced by two undulator segments, and scan K of one segment K’s are matched when spectrum has the steepest slope on high energy side of 1st harmonic peak. Match segments pair-wise until all segments are measured. undulator segments (33 total) segments under test June 16, 2008 LTU/Undulator Commissioning Plans C 15 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Angle-Integrated Spontaneous Spectrum for 2 Undulators with DK/K = -0.2 to +0.2% C Dj = 0 ~106 photons/nC/0.01%BW Dx = 3 mm DK/K = +0.2% 0.1% rms e- energy jitter 0.003% rms e- energy meas. resolution 2% rms charge jitter 0.5% charge meas. res. 0.5s rms angle jitter 105 photons/pulse/0.01% 100 photon noise 100 beam pulses with natural energy jitter only June 16, 2008 LTU/Undulator Commissioning Plans DK/K = 0% DK/K = -0.2% 16 Heinz-Dieter Nuhn,Simulations SLAC / LCLS P. Emma nuhn@slac.stanford.edu Characterization of SASE (Jul – Aug 09) D Initially at 15 Å to maximize SASE gain Start with reduced number of undulators Redo BBA after change of undulator configuration Verify that electron beam meets requirements Find SASE signal using Direct Imager Use Laser-Heater modulation to control gain (7 Hz Lock-In Detection) if necessary Repetition rate of 30 Hz (to support Lock-In Detection) Optimize gain (through electron beam quality and BBA) Measure gain length etc… June 16, 2008 LTU/Undulator Commissioning Plans 17 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu FEL Measurements D Measurements along undulator Saturation Intensity (LG, Saturation) Exponential Gain Regime Measurements after undulator Photon wavelength Photon wavelength spread Undulator Regime Pulse intensity Pulse duration 1 % of X-Ray Pulse Pulse centroid and direction Spatial distribution Jitter June 16, 2008 LTU/Undulator Commissioning Plans Electron Bunch Micro-Bunching 18 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu SASE Characterization with FEE Diagnostics D X-ray beam diagnostics located in FEE, down stream of last Undulator Segment Obtain necessary z-dependent information through SASE gain shut-off at selectable points along undulator line by Introduction of trajectory distortion or Roll-out of individual undulator segments June 16, 2008 LTU/Undulator Commissioning Plans 19 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Measurement of SASE Gain Length Using Rollout D Undulator Segments can be rolled-out by remote control. Roll-out will start at the last Segment. Rolled-out Segments will not effect radiation produced by earlier segments. June 16, 2008 LTU/Undulator Commissioning Plans 20 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Summary Plans for LTU/Undulator commissioning have been worked out and include A B C Detailed pre-beam checkout LTU-Main Dump commissioning without Undulator Segments installed. Installation of Undulator Segments. Undulator Segment Commissioning Characterization of Spontaneous Radiation will be combined with commissioning of X-Ray diagnostics suite in FEE Beam based K-measurement method included. Characterization of SASE will start at 15 Å D Gain length measurements will use FEE x-ray diagnostics combined with z-dependent SASE gain cut-off June 16, 2008 LTU/Undulator Commissioning Plans 21 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu End of Presentation June 16, 2008 LTU/Undulator Commissioning Plans 22 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Application Software Development LTU Emittance Measurement (Loos – extension of existing GUI) Undulator Steering and re-Pointing (Nuhn) Beta-Matching into the Undulator – with variable mean beta (Loos) Beam-Based Alignment of the FEL Undulator (Loos) Beam-Finder Wire Application – Centering & Emittance (Loos/Nuhn) K-Measurement Application (Welch/Nuhn) There will probably be more … June 16, 2008 LTU/Undulator Commissioning Plans 23 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Undulator Segment and TLD Replacement Program 2009 June 16, 2008 LTU/Undulator Commissioning Plans 2010 24 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu Measurement of SASE Gain Length with Trajectory Distortion D Quadrupole Displacement at Selectable Point along Undulator GENESIS Simulations by Z. Huang June 16, 2008 LTU/Undulator Commissioning Plans 25 Heinz-Dieter Nuhn, SLAC / LCLS nuhn@slac.stanford.edu