Report to the LCLS Facilities Advisory Committee Mark Reichanadter LCLS Deputy Project Director Project Management Status Cost and Schedule Performance Funding, Obligations & Costs Milestones & Critical Path Procurement Status Integration Management Risks & Mitigations Summary 16-18 June 2008 FAC Meeting LCLS Project Management M. Reichanadter reich@slac.stanford.edu Review Documentation LCLS Project Review information: http://www-ssrl.slac.stanford.edu/lcls/fac/2008june/index.html Thumb drives of presentations and back-up documents Responses to Oct07 FAC Recommendations April 2008 Monthly Report Current LCLS Risk Registry Questions? Contact: Helen O’Donnell X3368, heleno@slac.stanford.edu Daphne Mitchell X5377, dmitchell@slac.stanford.edu 16-18 June 2008 FAC Meeting LCLS Project Management 2 M. Reichanadter reich@slac.stanford.edu Project Status LCLS reporting against a new Baseline Approved by DOE Deputy Secretary in January Addresses impacts of the FY07 CR TPC = $420M (TEC = $352M, OPC = $68M) CD-4 = July 2010 TPC >78% Complete, TEC >82% Complete Contingency on TEC = $21.3M 35% on remaining work Management Reserve on OPC = $9.5M 35% on remaining work FY08 contingency tight but is being managed 16-18 June 2008 FAC Meeting LCLS Project Management 3 M. Reichanadter reich@slac.stanford.edu TEC Project Status Summary Technical Systems well advanced Injector & Linac complete through Sector 30 Undulator components mostly in hand. XTOD in procurement phase. XES in final design. Turner Construction >90% Complete Powering equipment & Tunneling activities complete. BO through NEH in June. BO through FEH in August. SLAC installing technical equipment prior to BO “co-occupancy” LCLS Facilities turned over to Operations Injector Facility (w/Drive Laser) Linac (w/BC-1, BC-2) through Sector 30 Magnetic Measurement Facility 16-18 June 2008 FAC Meeting LCLS Project Management 4 M. Reichanadter reich@slac.stanford.edu LCLS Project Performance (Apr08) LCLS Baseline Performance - April 2008 (AYK$) Work Accomplished % Complete Total Budget at Completion 1.1 Project Management 19,171 84.0% 22,822 1.2 Injector 20,239 100.0% 20,239 1.3 Linac 24,168 85.5% 28,257 1.4 Undulator 40,455 89.2% 45,355 1.5 X-ray Transport 20,827 75.8% 27,494 1.6 X-ray Endstations 2,734 30.0% 9,115 1.9 Conventional Facilities 113,902 83.7% 136,040 1.X Controls 1 LCLS Total Base Cost 28,926 270,422 69.9% 81.8% 41,369 330,691 WBS 2 LCLS Other Project Cost LCLS Total Project Cost (TPC) 16-18 June 2008 FAC Meeting LCLS Project Management LCLS Total Estimated Cost (TEC) 352,000 Available Contingency 21,309 % Contingency on ETC 35.4% 31,260 53.5% 58,463 LCLS Total Other Project Costs (OPC) 68,000 Available Mgmt Reserve 9,537 % Mgmt Reserve on ETC 35.1% 301,682 5 77.5% 420,000 M. Reichanadter reich@slac.stanford.edu Project Performance (Apr08) TPC BCWS BCWP ACWP Obligations (cum) $304.5M $301.7M $301.4M $309.6M TEC (Line Item) Remaining Work (ETC) $ 60.3M ~$14M is under contract Est at Complete (EAC) $332.7M EAC includes variances and Pending BCRs 16-18 June 2008 FAC Meeting LCLS Project Management 6 M. Reichanadter reich@slac.stanford.edu TEC Remaining Work ~$60.3M LCLS Scope of Work (AYM$) LN, 4,089 UN, 4,900 IJ, 0 XTOD, 6,667 PM, 3,651 LCLS Remaining Work Type (TEC) XES, 6,381 CF, 22,138 13% 15% CT, 12,443 15% Admin/Mgmt Design/Engr Proc/Fab/Assy Installation Work Complete, 270,422 16-18 June 2008 FAC Meeting LCLS Project Management 57% 7 M. Reichanadter reich@slac.stanford.edu LCLS Earned Value Indices LCLS Cost and Schedule Indices (TEC Only) 1.5 BCWP/BCWS (SPI) BCWP/ACWP (CPI) 1.4 1.3 1.2 1.1 1.0 0.9 0.8 0.7 0.6 0.5 8 -0 pr A 8 0 bFe 7 -0 ec D 7 -0 ct O 7 -0 ug A 7 0 nJu 7 -0 pr A 7 0 bFe 6 -0 ec D 6 -0 ct O 6 -0 ug A 6 0 nJu 6 -0 pr A 6 0 bFe 5 -0 ec D 5 -0 ct O 5 -0 ug A 5 0 nJu 5 -0 pr A 5 0 bFe 4 -0 ec D 4 -0 ct O • Not much trend data with the resetting of CPI & SPI. 16-18 June 2008 FAC Meeting LCLS Project Management 8 M. Reichanadter reich@slac.stanford.edu LCLS TEC Progress LCLS SPAOF Chart 400,000 ~$4.1M uncommitted BA on ~$24M of planned work 350,000 300,000 Data for chart BCWS BCWP ACWP BA OBLG (AY$K) 250,000 200,000 150,000 100,000 50,000 16-18 June 2008 FAC Meeting LCLS Project Management 9 FY 10 FY 09 FY 08 FY 07 FY 06 FY 05 FY 03 FY 04 0 M. Reichanadter reich@slac.stanford.edu FY08 Contingency Estimate Millions LCLS Project Cumulative Obligations (TEC) $305 Sep-08 remaining budget authority = $ 4.1 M $295 Cumulative Obligations (TEC) $285 FY08 Budget Authority (TEC) Cumulative BCWS (TEC) $275 Estimate ~$1.4M draw on contingency through 30Sep08 $265 $255 ACWP ACWP ACWP Estimate Estimate Estimate Estimate Estimate Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 16-18 June 2008 FAC Meeting LCLS Project Management 10 M. Reichanadter reich@slac.stanford.edu FY09 CR Impact & Mitigation 9,000,000 8,000,000 7,000,000 6,000,000 1 LCLS PROJECT TEC BCWS 5,000,000 •TEC base plan exceeds a strict 1/12th monthly CR allocation ~$2.6M. 4,000,000 TEC CR Funding (1/12 of 36.94M) 3,000,000 2,000,000 Worst case: Delay procurements to match CR BA. Early science in FY09 is at risk. 1,000,000 0 Oct Nov Dec Jan Feb Mar Apr Assumes $0 carry-forward 9,000,000 8,000,000 •Preferred solution: Request $8.1M in Oct08, with $3.1M in subsequent months. 7,000,000 6,000,000 5,000,000 1 LCLS PROJECT TEC BCWS 4,000,000 TEC Proposed CR Funding 3,000,000 2,000,000 1,000,000 0 Oct Nov Dec Jan Feb Mar 16-18 June 2008 FAC Meeting LCLS Project Management •Award schedule-critical procurements. Adequate contingency is available to address unexpected costs. Turner close out scheduled for Dec08. 11 M. Reichanadter reich@slac.stanford.edu DOE (Level 2) Milestone Performance LCLS DOE (Level 2) Milestones Delivery of Undulator 1st Articles to MMF Sector 20/Alcove Beneficial Occupancy MMF Qualified & Ready to Measure Prod Undulators Start Injector Commissioning (Drive Laser) Injector Accelerator Readiness Review (ARR) Comp Start Injector Commissioning(UV Beam to Cathode) Linac Water/Power Available Linac (Li20-Li30) Ready for Commissioning Start Installation of Undulator Facility BTH-UN-FEE-NEH-CUP Beneficial Occupancy Linac (Li20-Li30) Commissioning Complete Safety Analysis Document (SAD) Approved XT-FEH Beneficial Occupancy XT Start FEE Installation LCLS ARR Complete (BTH thru FEH) Start Linac-to-Undulator (LTU) Commissioning XT Start Tunnel Installation Start Undulator Commissioning (1st Light) 2-D Detector Shipped to SLAC Start FEE Commissioning with Beam First X-Rays into NEH - Initiate Early Ops XE Start Installation in FEH First X-Rays into FEH 16-18 June 2008 FAC Meeting LCLS Project Management Baseline Date Actual 3-Jul-06 15-Jun-06 21-Jul-06 14-Apr-06 28-Aug-06 28-Aug-06 29-Jan-07 15-Dec-06 31-Jan-07 30-Mar-07 9-Apr-07 5-Apr-07 11-Jul-07 29-Mar-07 1-Dec-07 1-Dec-07 16-May-08 21-Jul-08 30-Jul-08 2-Apr-08 29-Aug-08 22-Oct-08 13-Jan-09 17-Apr-09 20-Apr-09 27-May-09 6-Jul-09 30-Jul-09 6-Aug-09 10-Sep-09 17-Sep-09 26-Feb-10 12 Variance -12 days -70 days 0 days -22 days 42 days -2 days -74 days 0 days On Schedule On Schedule -76 days On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule L2 milestones include ~2 months float from early finish dates M. Reichanadter reich@slac.stanford.edu LCLS Schedule Critical Path (CP) to CD-4 Undulator/FEE C.O. – install – FEL commission – Photons in FEH Total float 108 working days (~5months) K-measurement = 108 days Soft X-ray Mirror System = 109 days Undulator Girder Assembly = 111 days Pop-Up Camera System = 113 days Space Renovation BO = ~90 days Renovation of existing space (low risk). Construction planned in FY10 but can be advanced if necessary. “Co-occupancy” installation of technical equipment prior to BO. Turner activities have priority. Co-mingled work is proceeding smoothly due to advance planning. Track Turner EV in LCLS PMCS, site walk validation, OAC meetings 16-18 June 2008 FAC Meeting LCLS Project Management 13 M. Reichanadter reich@slac.stanford.edu LCLS Procurements LCLS using co-located procurement group 1 Manager 2 Buyers (technical components) 1 Contract Administrator (A/E, CM/GC contracts) 1 Construction Buyer (Davis-Bacon contracts) Administer field changes and submittals 2 P/T Consultants (price and change negotiations) Weekly technical/procurement staff meetings Advance procurements monitored via APP’s DOE increased SLAC authority to $500K Starting pre-planning of LUSI procurements. 16-18 June 2008 FAC Meeting LCLS Project Management 14 M. Reichanadter reich@slac.stanford.edu Recent Procurements >$100K Description Estimate Award Price Award Date Delta Model VME-EVR-230 Event Receiver Module 175,920 175,920 21-Aug-07 0 Muon Shield Plates for Wall 2 Quad Stands 214,500 471,450 282,110 251,612 19-Dec-06 28-Jun-07 -67,610 219,838 MCOR Power Modules MCOR Power Modules 254,300 369,013 238,420 341,447 24-Apr-07 24-Apr-07 15,880 27,566 Intermediate Power Supplies 348,000 270,500 22-Feb-07 77,500 Double Bay Racks BYD Magnet 130,000 250,000 132,125 173,400 5-Feb-08 2-Nov-07 -2,125 76,600 350,000 1,900,000 228,900 1,852,097 19-Oct-07 10-Jul-07 121,100 47,903 125,000 162,380 23-Jan-08 -37,380 1,100,000 1,111,000 761,513 921,230 25-Jul-07 28-Feb-08 338,487 189,770 BTH Switchboard Installation BTH West Tunnel Upgrade 362,000 400,000 412,698 619,918 10-May-07 20-Nov-07 -50,698 -219,918 Cable Plant Phase 5 468,000 398,503 10-Apr-08 69,497 Commisioning Services - CUP Substation 522 Project install LTU Stands and grout Cable Plant Phase 3 Cable Plant Phase 4 •Recent performance on estimating contracted work has been good. •~$11M of large procurements remain (~4.5M Space Renovation, $2.8M D/B FEH Hutches) 16-18 June 2008 FAC Meeting LCLS Project Management 15 M. Reichanadter reich@slac.stanford.edu Integration Management Integration Management Team (staff of 8) Directed by R Boyce Meets weekly to review interfaces, resolve gaps, conflicts Representation from all LCLS L2 WBS (includes LUSI) Monitor installation readiness, planning and coordination Design reviews continue to play important role in advancing design and vetting integrated solutions Risk Registry now mostly a tactical document Punch list managed by System Managers Often involves integrated mitigation actions 16-18 June 2008 FAC Meeting LCLS Project Management 16 M. Reichanadter reich@slac.stanford.edu LCLS Technical Specifications •LCLS technical specs flow down from GRD-PRDs •LUSI beginning to finalize its design specs •LUSI interface captured in ICDs + Interface Working Group 16-18 June 2008 FAC Meeting LCLS Project Management 17 M. Reichanadter reich@slac.stanford.edu Project Management Risks & Mitigations Safety – Particularly construction and installation Fully staffed in ES&H, construction safety and oversight (UTR’s) Regular inspections, enforced procedures, stand-downs, daily tool box meetings Aligned DOE, SLAC, Turner, Jacobs, Subcontractors Cost – Contingency Perform monthly analysis on EAC and projected ‘burn rate’ Perform semi-annual contingency assessment & MC analysis Cost – Control (Owner-directed changes) Regular walk-arounds with IMT and LUSI teams Adhere to configuration controls (BCR, FCO and DCR) 16-18 June 2008 FAC Meeting LCLS Project Management 18 M. Reichanadter reich@slac.stanford.edu Project Management Risks & Mitigations Schedule – Installation Coordination IMT facilitates integration and identify gaps/conflicts Weekly install meetings (w/Turner) +readiness reviews Schedule – FY09 Continuing Resolution Request $8.1M ($5M above CR level) at beginning of FY09 Defer less critical work until later in FY09 Evaluate cost and contingency monthly Management – Transitions Actively manage organizational interfaces LCLS-LUSI, transition to Linac Ops, transition to LCLS Science Program Project transitions are high priority to DOE and SLAC Regular communication and access to key resources DOE-BES, DOE-SSO, SLAC Directorate • System Managers will address their risks and risk handling plans. • Full lists of active risks and mitigation actions are LCLS Risk Registry. 16-18 June 2008 FAC Meeting LCLS Project Management 19 M. Reichanadter reich@slac.stanford.edu Summary LCLS reporting on recently revised baseline Overall, earned value making steady progress Milestone performance good so far Cost and schedule contingencies adequate to address project risks Monitor and manage FY08 contingency allocation Request $8.1M in Oct08 ($5M above CR level) to maintain schedule to early science Challenges ahead: Close out (Turner) construction project Simultaneously manage install/commission activities Continue LUSI integration and transition to operations 16-18 June 2008 FAC Meeting LCLS Project Management 20 M. Reichanadter reich@slac.stanford.edu End of Presentation 16-18 June 2008 FAC Meeting LCLS Project Management 21 M. Reichanadter reich@slac.stanford.edu