Linac Coherent Light Source
Status Overview
John N. Galayda
Director of LCLS Construction
7 June 2006
LCLS Science Advisory Committee
1
John N. Galayda galayda@slac.stanford.edu
CD-3b Approved 28 March 2006
7 June 2006
LCLS Science Advisory Committee
2
John N. Galayda galayda@slac.stanford.edu
LCLS Cost/Schedule Status Report - Work Breakdown Structure
Cumulative to Date ($K)
1.1 Project Management
1.2 Injector
1.3 Linac
1.4 Undulator
1.5 X-ray Transport
1.6 X-ray Endstations
1.9 Conventional Facilities
1 LCLS Total Base Cost
WBS
Budgeted Cost
Work
Scheduled
14,521
15,331
8,094
15,706
8,063
1,321
17,247
80,284
Work
Performed
14,207
12,876
6,136
14,409
7,677
1,067
16,787
73,159
Actual Cost
Work
Performed
15,992
12,902
5,147
14,568
7,433
995
16,855
73,890
Variance
Schedule
Construction 26% complete
Contingency 29% of Estimate to Complete
-314
-2,455
-1,958
-1,298
-386
-254
-461
-7,125
Cost
-1,784
-26
989
-159
244
73
-68
-731
LCLS Total Estimated Cost
Avail. Contingency
Performance Indices
SPI
% Contingency / ETC
0.98
0.84
0.76
0.92
0.95
0.81
0.97
0.91
CPI
0.89
1.00
1.19
0.99
1.03
1.07
1.00
0.99
2.1 LCLS Project Mgmt, Planning & Admn (OPC)
2.2 Injector (OPC)
2.3 Linac (OPC)
2.4 Undulator (OPC)
2.5 X-ray Transport (OPC)
2.6 X-ray Endstations (OPC)
2.9 Conventional Facilities (OPC)
2 LCLS Total Other Project Cost
5,327
779
1
798
489
494
0
7,889
5,392
709
1
747
489
498
0
7,836
5,397
731
31
794
427
175
0
7,556
65
-70
0
-51
0
4
0
-53
% Complete LCLS Base Cost
-5
-22
-30
-47
62
322
0
280
1.01
0.99
1.01
0.91
1.00
0.94
1.00
1.00
0.97
0.04
0.94
1.14
2.84
1.04
LCLS Other Project Cost
LCLS Total Obligations = $97,316.4K
Avail. Management Reserve
% Management Reserve / ETC
LCLS Total Project Cost 88,173 80,995 81,446 -7,177
% Comp LCLS Other Project Cost
-451 0.92
% Complete LCLS TPC
*Management Estimate at Complete includes the Budget at Complete, a weighted CPI and SPI, proposed Baseline Change Requests and known risk contingencies.
0.99
7 June 2006
LCLS Science Advisory Committee
3
John N. Galayda galayda@slac.stanford.edu
30-Apr-06
Budgeted
At Completion ($K)
Management
Estimate at
Complete*
Variance
315,000
54,831
29.3%
28.1%
33,425
5,754
2,545
4,623
4,930
5,246
621
57,145
64,000
27,741
21,028
24,248
41,095
24,149
14,220
107,689
260,169
6,855
13.9%
13.7%
379,000
25.5%
315,000
34,417
16.6%
26.1%
33,540
5,807
2,575
1,672
4,878
4,932
621
54,026
64,000
32,189
22,156
23,517
42,516
26,960
16,021
117,224
280,583
9,974
21.6%
14.5%
379,000
24.2%
4,448
1,128
-731
1,421
2,811
1,801
9,535
20,414
-115
-52
-30
2,951
52
314
0
3,119
1%
0%
10%
Awarded Contracts
Total Estimated LCLS Contract Awards ~$175M (unesc)
• ~38% of LCLS contracts awarded.
9%
CF Subcontracts
37%
5%
PMCS, A/E, CM/GC,
S20/MMF, Undulator mat'ls & assembly, most of Injector/Linac
38%
Awards Under Contract
Conventional Facilities
Injector
Linac
Undulator
X-ray Transport
X-ray Endstations
• By end of FY06, 80% of contracts will be awarded.
•At that point, much more information & less risk
• Remaining contracts have some specialty components but most are commodities.
(vacuum, cabling, etc.)
• Cost Risks
•CF subcontracts
•Schedule performance
•System Integration
7 June 2006
LCLS Science Advisory Committee
4
John N. Galayda galayda@slac.stanford.edu
PROJECT INJURY EXPERIENCE TO DATE
SubContractors
29 K Hours worked
(03/31/2006)
Zero Injuries
2.5
Lost Time Injury Rate
2.1
2
Contractors
LCLS
Total Project
1.5
LCLS Collaboration
>460 K Hours worked
One shoulder strain
>250 Days Worked
Without Injuries
1
DOE
Construction
0.5
0.43 0.41
0
0
Project To Date
Note: Injury rates based on 200 K hours (100 manyears) of effort.
7 June 2006
LCLS Science Advisory Committee
5
John N. Galayda galayda@slac.stanford.edu
LCLS Project Organization (Mar06)
• Feb06 Lehman committee recommended strengthening
Project Office
•APD – Engr
•APD – Civil
•Procurement
• Continued strengthening of
Conv Facilities
• LCLS PMOG functioning
7 June 2006
LCLS Science Advisory Committee
6
John N. Galayda galayda@slac.stanford.edu
Injector and Linac
Injector 61% complete
Gun fabrication at SLAC- Hot test at ASTA August
Laser delivery in July 2006
Linac BC-1
Articulated vacuum chamber received installation in Fall shutdown
Injector installation schedule runs into 2006/2007 shutdown
Shutdown schedule – 21 August 2006 to 5 January 2007
In-tunnel work (BC-1) must have priority
Pursue all prudent means to speed schedule and preemptively mitigate schedule problems
Add design staff
Off-site fabrication, sources for rigging etc.
Commissioning start – January 2007
Commissioning applications software will be rudimentary at start
7 June 2006
LCLS Science Advisory Committee
7
John N. Galayda galayda@slac.stanford.edu
Installation Schedule
6 MeV 135 MeV 250 MeV 4.30 GeV 13.6 GeV
Linac-0
L =6 m
Linac-X
L =0.6 m rf gun
Linac-1
L 9 m
Linac-2
L 330 m
Linac-3
L 550 m
...existing
linac
21-1 b,c,d
X
‘Wall region’
Injector, 2006 down
BC1
L 6 m
21-3b
24-6d
25-1a
30-8c
BC2
L 22 m
Linac, 2007 down
SLAC linac tunnel undulator
L =130 m
DL2
L =275 m research yard
7 June 2006
LCLS Science Advisory Committee
8
John N. Galayda galayda@slac.stanford.edu
Status of Gun Fabrication and Testing
Gun machining and brazing in progress
Gun will be furnace baked after final tuning
Final braze of power splitter this week
Gun solenoid received, magnetic measurement plan completed
Test plan reviewed
Mechanical design of gun & solenoid supports approved
Gun Solenoids
7 June 2006
LCLS Science Advisory Committee
Dual Feed Full-Cell
9
John N. Galayda galayda@slac.stanford.edu
Gun Fabrication in Progress
Cathode Plate (rear)
Dual-Feed Waveguide
Dual-Feed Full Cell
7 June 2006
LCLS Science Advisory Committee
Cathode Cell
10
Cathode Cell
John N. Galayda galayda@slac.stanford.edu
Readying Components for 2006 Down
Gun Solenoid
Injector Quadrupoles
7 June 2006
LCLS Science Advisory Committee
Shortened
Accelerator
Sections
11
John N. Galayda galayda@slac.stanford.edu
Commissioning
Begins after all components have previously been installed, aligned, connected, and verified by installers
Commissioning :
Pre-Beam Checkout
Final component verification, made mostly in tunnel by system physicist ( e.g.
, polarities, motion-control, etc.)
Systems validation ( e.g.
, power supplies, software applications, etc.)
Beam Commissioning
Component and system verification/calibration with beam
(hardware and software; e.g.
, BPM tests)
Optimization of beam transport and tuning ( e.g.
, steering)
Characterization of beam quality ( e.g.
, emittance meas.)
7 June 2006
LCLS Science Advisory Committee
12
John N. Galayda galayda@slac.stanford.edu
Commissioning Plans - Preparation
Plan development assigned to each system team:
Drive Laser (White, Gilevich)
Gun & Injector (Dowell, Limborg, Schmerge)
Linac (Emma, Wu)
Undulator (Nuhn, Welch)
FEL (Welch, Nuhn)
XTOD/XES (Arthur, M öller, Stefan, Tompkins)
Each developed an MS-Project file detailing both schedule and strategy
Goal was to force early development of tuning strategy
(what to measure, what to tune, in what order – simulations encouraged now)
Files now merged into master file and time-frame locked to project schedule (thanks to Jim Welch)
7 June 2006
LCLS Science Advisory Committee
13
John N. Galayda galayda@slac.stanford.edu
Schedule developed in MS-Project
One file/manager per system
Link to milestones and events in Master file
V:\LCLS\Group\Commissioning\Commissioning Schedule\Commissioning_Master.mpp
install Injector-BC1
Dec.
‘05
Aug.
‘06
7 June 2006
LCLS Science Advisory Committee
Dec.
‘06
14 install BC2 LTU-und.
Aug.
‘07
Nov.
‘07
Mar.
‘08
John N. Galayda galayda@slac.stanford.edu
SLAC-Wide Effort on LCLS Safety Assessment
Document
7 June 2006
LCLS Science Advisory Committee
15
John N. Galayda galayda@slac.stanford.edu
Preparations for Accelerator Readiness Review
Integrated with design review process
Component and System PDRs and FDRs are being conducted following LCLS guidelines.
Safety aspects are a normal part of the technical requirements.
Working to report safety analyses in a uniform way to facilitate future assessments.
SLAC Citizen’s Committees participate in the review process, following normal SLAC practice.
Citizen’s Committees involvement specified through the SLAC
Safety Oversight Committee.
Need to ensure that all aspects of the project are reviewed, and that the completeness is presentable in a coherent way.
7 June 2006
LCLS Science Advisory Committee
16
John N. Galayda galayda@slac.stanford.edu
Accelerator Readiness Review
LCLS ARR for Injector Commissioning will take place Sept.- Nov. 2006, once Citizen Committees’ reviews are complete and the SOC is satisfied.
Working with the DOE SSO to ensure that the review process outlined here will be appropriate.
7 June 2006
LCLS Science Advisory Committee
17
John N. Galayda galayda@slac.stanford.edu
Undulator Systems
Undulator production underway
Prototype at SLAC for measurement
Chamber finish tests underway
Single Undulator Tests ongoing
RFBPM fabrication test encouraging
Undulator Measurements at SLAC
MMF startup in August
7 June 2006
LCLS Science Advisory Committee
18
John N. Galayda galayda@slac.stanford.edu
Photon Beam Systems
John Arthur is staffing up
Deputy – Hal Tompkins
X-ray Transport/Optics/Diagnostics
XTOD Liaison physicist- Peter Stefan
Prototype gas attenuator assembled, vac. tested
Design reviews for XRT vacuum, collimators
End Station Systems
Staffing up- Layout of experiments is settled down
AMO Liaison physicist – John Bozek
Detector Liaison physicist - Niels van Bakel
7 June 2006
LCLS Science Advisory Committee
19
John N. Galayda galayda@slac.stanford.edu
X-Ray Transport/Optics/Diagnostics
Prototype gas attenuator cell tested at LLNL
7 June 2006
LCLS Science Advisory Committee
20
John N. Galayda galayda@slac.stanford.edu
NEH
AMO SXR hard x-ray line
X-ray pumpprobe
Flipper Mirrors
7 June 2006
LCLS Science Advisory Committee
21
John N. Galayda galayda@slac.stanford.edu
FEH
XPCS
Coherent x-ray imaging
High energy density science
7 June 2006
LCLS Science Advisory Committee
22
John N. Galayda galayda@slac.stanford.edu
Beneficial Occupancy 21 April
Installation underway in vault tray supports floor
7 June 2006
LCLS Science Advisory Committee
23
John N. Galayda galayda@slac.stanford.edu
Magnet Measurement Facility Beneficial
Occupancy 14 April 2006
7 June 2006
LCLS Science Advisory Committee
24
John N. Galayda galayda@slac.stanford.edu
Final Focus Test Beam Cleanout
Phase 1 completed 28 April preservation of technical components
Phase 2 began 1 May completed 2 June removal of shielding blocks
Phase 3 started floor/soil excavation
7 June 2006
LCLS Science Advisory Committee
25
John N. Galayda galayda@slac.stanford.edu
Project Highlights and Key Considerations
Conventional Facilities
Architectural design @ 100%
Construction manager on board
Bids for first major packages in hand
Second group of bids due 14 June third group of bids (for CLOC) due in September
Beneficial occupancy of entire e-beam path and NEH by August 2007
7 June 2006
LCLS Science Advisory Committee
26
John N. Galayda galayda@slac.stanford.edu
First Bid Package – Entire Beam Path
Bids higher than estimates
Considerable draw on contingency required
Various alternatives under consideration
Changes to beam path, halls and FEL commissioning schedule are NOT under consideration
Economies required to deliver 2-floor CLOC
7 June 2006
LCLS Science Advisory Committee
27
John N. Galayda galayda@slac.stanford.edu
Summary
Injector and Bunch Compressor 1 will be ready for commissioning in January
Preparations for commissioning the injector
Address engineering, physics, operations, safety
Undulator Systems Coming Together
X-Ray Front End design maturing
End Station Systems layout maturing
Civil Construction organized, prepared to start
Civil Construction cost control an issue
LCLS is well on its way to groundbreaking science
7 June 2006
LCLS Science Advisory Committee
28
John N. Galayda galayda@slac.stanford.edu
7 June 2006
LCLS Science Advisory Committee
29
John N. Galayda galayda@slac.stanford.edu