Undulator Long Lead Procurements Strategy Source Selection Plan Bid Lists

advertisement
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Undulator Long Lead Procurements
Glen Lawrence, ANL
November 15, 2004
Strategy
Requirements
Source Selection Plan
Bid Lists
Procurement
Quality Assurance
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Strategy
Define Requirements
Statements of Work
Engineering Drawings
Decide on a Source Selection Plan
Cost
Technical
Go-NoGo
Pre-qualified Bidders
Develop a Bid List
Procure Long Lead Items
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Defining Requirements –Current Status
Undulator Strongbacks
Drawings-Released
Statement of Work-Released
Undulator Magnet Poles
Drawing-Released
Statement of Work-Released
Undulator Magnets
Drawing-Released
Statement of Work - Routed for Signatures
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Statements of Work
Combined Business Requirements and Technical
Requirements
Business Requirements
Delivery Schedule
Planning Requirements
Reporting Requirements
Communication Requirements
Shipping Requirements
Technical Requirements
Enhancement of Drawing Requirements
Technical Requirements too Detailed for a Drawing
Testing Requirements
Certification Requirements
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Statement of Work - Initial Sections
Introduction -Section 1.0
The Introduction gives a brief view of the LCLS Project
Scope -Section 2.0
Scope of Work Section 2.1
How the current procurement fits into the LCLS Project
Delivery -Section 2.2
Defines the scope in time for fulfilling the procurement of each item
First Article -Section 2.3
Defines the requirement for a “First Article” in the scope of the
procurement
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Statement of Work - Technical Requirements
Typical Technical Requirements in Section 4.1
Material Requirements
Special Processes -Annealing
Special Properties –Magnetic Requirements
Marking for Identification
Packaging Requirements
Typical Technical Requirements in Section 4.5
Testing and Measurements
Data Reporting
Additional Technical Documents in Section 3.0
Drawings
Laboratory Technical Specifications
National Technical Specifications and Standards
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Statement of Work –Business Requirements
Typical Business Requirements – Sections 4.2 - 4.4
Program Plan
Program Meetings
Program Schedule
Typical Business Requirements – Sections 4.6 – 4.9
Special tooling
Quality Control
First Article Inspection
Contractor Proposed Changes
Proprietary Designs and Processes
Inspection and Test Plan
Quality Assurance
Quality Verification Program
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Statement of Work –Business Requirements
Typical Business Requirements – Sections 4.10 –4.15
Source Inspection
Testing Surveillance
Test Failures
Red Flag Notice
Nonconformance Reporting
Approvals
Reports, Data and Deliverables – Section 5.0
Progress Reports
Technical Data
Delivery
Other Special Considerations – Section 6.0
Sub-contractors, Publications, etc
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Source Selection
Best Price Selection
Does not Evaluate Vendor Capabilities thus Introduces Risk
Best Technical Proposal Selection
Weighed Evaluation of Technical Proposals
Introduces Subjective Judgments
Insufficient Technical Complexity to Warrant Required Effort
Go-NoGo Selection
Vendors Submit Qualifications with Bid on Specified Criteria
Vendor Responses judged “Go” or “NoGo”
One “NoGo” Rating Disqualifies a Vendor Proposal
Qualified Vendors’ Bids Compete on Price
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Source Selection
Pre-qualified Vendor Selection
Assess Potential Vendors with Specific Selection Criteria
Use Plant Visits to Clarify Vendor Capabilities
Offer Bid Package Only to Pre-Qualified Bidders
Bids Compete on Price
Similar to “GO-NoGo” Selection
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Developing Bid Lists
Look at Current ANL Vendors
Look for Vendors Recommended by Other National
Laboratories
Search Internet for Vendors with Required Expertise
Advertise in FedBizOpps and Let Vendors Express
Interest
Cull List for Best Potential Vendors
Proceed with Vendor Prequalification
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Procurement
Request for Proposals Will be Sent to Pre-qualified
Vendors
Documentation will include:
Drawings
Statement of Work
Any Special Documents Such As:
Special Bid Instructions
Interested Sub-Contractor Lists
Proposals Must Comply With All Requirements to be
Considered Valid
Contract will be awarded to the Vendor with the Best
Priced Valid Proposal
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Quality Assurance
What is Quality
Meeting Requirements
Define Requirements
Provide Proper Tools
Who is Responsible for Quality
We are, and Everyone Involved in the Process
How does Quality Assurance Apply
Control of Drawings via Checking, Review & Release
Control of Documents (SOW) Via Review & Release
Vendor Selection
Capacity
Tools
Quality Management System
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Vendor Quality Monitoring
Required Plans
Program Plan & Schedule
Inspection and Test Plan
Quality Verification Plan
Required Reports and Other Written Communications
Monthly Progress Reports
Red Flag Notices
Nonconformance Reports
Program Meeting Minutes
LCLS Undulator Design Review
Undulator Long Lead Procurements
Glen Lawrence, ANL
gsl@aps.anl.gov
Linac Coherent Light Source
Stanford Synchrotron Radiation Laboratory
Stanford Linear Accelerator Center
Vendor Quality Monitoring
Required Documentation
Test & Measurement Data
Certifications
Direct Monitoring
Program Meetings
At ANL
At Vendor Plant
Witness Testing
First Article Inspection
Post Delivery Inspection and Testing