Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities J. Albino / SLAC October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Conventional Facilities Major Developments New Staff Status of VE Design Status of Construction Construction Schedule CF Organization Chart 6 Month Look-ahead Summary October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Major Developments Strengthened CF Management APD Civil Construction CF Procurement Specialists On-site Design Liaison Structural Engineer UTR Executive Level CF Committee Active Participation in Int. Man. Team Developed Change Request Form Weekly LCLS / TCCo Exec. Meeting Notice to Proceed issued to TCCo Field Change Order Contract Mod October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Major Developments – cont’d Construction Underway Value Engineering Design Complete Research Yard turned over to TCCo Site Grading Underway Encountering Remnant Utilities Work Site Security October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu New Staff Jess Albino – Associate Project Director for Civil Construction James Dee – CF Procurement Specialist John Azevedo – CF Procurement Specialist Jim Cranston – Design Liaison Kenneth Yang – Structural Engineer (UTR) October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Value Engineering Jacobs Engineering Design SLAC/TCCO VE Recommendations Complete SLAC Beam Dump Modifications – in process Trade Contractor Concrete Mix – in process October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu CONSTRUCTION October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu SLAC Site Plan SLAC Main Gate Research Office Building Pep Ring Road Bldg #081 - MMF Sector 25 Sector 20 Upstream LCLS General Work Boundary Research Yard October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Completed Activities •SLAC Managed Projects •Demolition of Building #113, #102 A/B and SLC Gas Pad (Pep Ring Road) •Demolition completed •Beam Dump Spoils Analysis •Completed •FFTB Removal •Completed •ALL SLAC MANAGED ACTIVITIES MUST BE COMPLETED PRIOR TO JULY 21, 06 TO AVOID DELAY TO TCCO CONTRACT! (Actual Aug 21, 2006) October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Construction Projects to Date Sector 24 Equipment Enclosure FFTB Wall Magnet Measurement Facility Sector 20 Injector Facility MMF Electrical Feed FFTB Removal Research Yard Demolition Beam Dump Spoils Site Work (actual Sep 9, 2006) Utilities October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Status of CMGC TC is engaged in Phase 2 performing construction management and general contractor activities CM on-site staff includes Sr. PM, PM, Safety Rep., Proj. Eng., superintendent (2), safety coordinator, scheduler, etc Prepared and submitted Draft Baseline Schedule Manage and direct construction activities for site work and underground utilities Conducted subcontractor orientation and safety training Received bids on Groups 3 and 4 Coordinated weekly Owner/Architect/Contractor (OAC) meetings LCLS / TCCo Executive Meeting - weekly October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu SLAC Plans for Construction Use of Alpine Gate for all subcontractors Gate 17 will remain open 24/7 Implement an approved Tunnel Rescue Team prior to start of any tunneling late Oct, 06 Process Contractor Submittals, RFIs Assist with development of the project Baseline Schedule Continue coordinating with lab liaison (Steve Williams) for LCLS and SLAC interface issues October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Turner Plans for Construction Receive Authorization to Proceed Aug 01, 06 Mobilization and Site Work commences on Sep 11, 2006 Tunneling operations commence late Oct, 06 12 month duration, two shift operation RSY North Access driveway to be coordinated with tunneling and BTH activities BTH fencing to be coordinated with road closure CEH fencing installed by end of Oct. 06 October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu SCHEDULE October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu LCLS CF Construction Schedule Jan 07 Sep 07 Feb 08 Sep 07 Oct 07 Oct 07 Feb 08 Feb 08 Aug 08 October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu ORGANIZATION CHART October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu CF Construction Organization Project Director - John Galayda Deputy Proj. Director Mark Reichanadter Project Controls and Support Office Exec. CF Committee R. Claus, J. Jobe B. Miller M. Reichanadter SLAC Services Support Associate Project Director – Civil Construction Jess Albino Change Control Jim Dee John Azevedo Cost / Schedule Anita Malahowski Cost Account Manager – D. Saenz Deputy Manager - Dick McDonald Administrative Support Lee Anne De Wan Concepcion Zelaya University Technical Representative Manager CM/GC – Turner Tom Malloy – Sr. PM James Tubbs -PM MEP - Facilities Javier Sevilla Design Liaison Jim Cranston Bob Law SLAC ES&H Subject Matter Experts (SME) UTR – CM Jesse Saldivar UTR – Mechanical Javier Sevilla JE Design PM JE Walnut Creek UTR – Structural Ken Yang UTR – Electrical Lori Shewchuk JE Portland JE Boston UTR – CM Lam Chan Rutherford /Chekene Gyimah Kasali Electrical Lori Shewchuk Structural Ken Yang Construction Manager – Tunnels Patrick Doig - HMM Turner Procurement – Pre-purchased Equipment SubContractors Turner Project Office October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu 6 MONTH LOOK-AHEAD CONSTRUCTION Complete Site Grading Excavate UH tunnel Excavate NEH, Pour base slab Excavate and Pour CUP base slab Excavate and Pour FEE Form and Pour Beam Dump SOG October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu 6 MONTH LOOK-AHEAD (cont.) Construction (cont.) Form and Pour BTH SOG Begin Access Tunnel Administrative Delete CLOC Complete CF PM Documents Timely Submittal Processing Process Changes Enforce Safety Plan Enhance Coordination with Tech. Systems Monitor, Monitor, Monitor October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu Summary Good Progress on all fronts since last FAC. CF staff has been strengthened to ensure adequate experience is integrated in all requirements Continue to Value Engineer Interface with SLAC, Tech. Systems, CM/GC Support TCCo and Construction to prevent delays – keep to the schedule. Complete Development of tools for CF Staff Team is in place to safely construct the LCLS! October 12, 2006 Jess Albino FAC CF Overview albino@slac.stanford.edu