Report to the LCLS Facilities Advisory Committee LCLS Project Management M. Reichanadter / SLAC October 12-13, 2006 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu Outline Status of the LCLS Progress in the past six months Project Management Cost and Schedule Performance Contingency Allocation Organization and Integration Plans for the next six months Risks/challenges ahead October 12-13, 2006 LCLS FAC Meeting 2 Mark Reichanadter reich@slac.stanford.edu LCLS Status Cost Status CF subcontracts substantially over LCLS estimates Descope CLOC to stay within TPC Schedule Status Technical systems maintaining reasonable schedule progress Milestone performance ~OK, but installation activities are behind. Construction start delayed due to high subcontract bids Working new schedule & CP. New Co- and Beneficial milestones. Construction packages of LCLS beampath now awarded and construction is underway! Recent shutdown of Turner activities. Frequent cable discoveries. Management Status Procurements going reasonably well with the dedicated cell Consultants (Miller/Dee), expediter and BOA’s are on board Integration management team in place Manage the technical / CF interfaces and facilitate installation October 12-13, 2006 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu TEC Project Performance - July 2006 • LCLS showing steady progress overall. LCLS Project Performance (TEC = $315MAY)) 350,000 • 31% TEC comp • 28% TPC comp 300,000 BCWS (TEC) 250,000 AYK$ BCWP (TEC) ACWP (TEC) 200,000 BAC 150,000 BA OBL-S (TEC) 100,000 EAC 50,000 0 09 bFe 8 -0 ct O 08 nJu 08 bFe 7 -0 ct O 07 nJu 07 bFe 6 -0 ct O 06 nJu 06 bFe 5 -0 ct O 05 nJu 5 0 bFe 4 -0 ct O October 12-13, 2006 LCLS FAC Meeting 4 • SPI = 0.93 • CPI = 0.95 • $ burn rate ~$5-6M per/mo • Labor burn rate ~$2.5M/mo • At SLAC ~165 FTE’s ~350 heads on LCLS Mark Reichanadter reich@slac.stanford.edu LCLS Project Performance – July 2006 LCLS Cost/Schedule Performance - July 2006 (AYK$) Work Accomplished % Complete Total Budget at Completion 1.1 Project Management 16,428 65.8% 24,958 1.2 Injector 15,810 76.0% 20,795 1.3 Linac 7,912 32.1% 24,677 1.4 Undulator 16,719 40.7% 41,095 1.5 X-ray Transport 8,938 35.2% 25,367 1.6 X-ray Endstations 1,239 8.5% 14,555 1.9 Conventional Facilities 1 LCLS Total Base Cost 18,741 85,786 14.9% 30.9% 125,793 277,240 WBS 2 LCLS Other Project Cost LCLS Total Estimated Cost (TEC) 315,000 Available Contingency 37,760 % Contingency on ETC 19.7% 8,992 15.7% • Injector 95% complete in Jan07. 57,435 LCLS Total Other Project Costs (OPC) 64,000 Available Mgmt Reserve 6,565 % Mgmt Reserve on ETC 13.6% LCLS Total Obligations = $106,483.6K LCLS Total Project Cost (TPC) October 12-13, 2006 LCLS FAC Meeting 94,778 28.3% 5 379,000 Mark Reichanadter reich@slac.stanford.edu TEC Contingency Performance – July 2006 % Contingency AvaIlable (on remaining work) • ~$19M contingency allocated in July. •~$18M, CF Gp #1 •~$0.4M Linac ETC •~$1.2M, XTOD ETC •~$0.2M, XES ETC 40% 35% 30% 25% 20% % Complete BCWP/BAC Cont/(BACBCWP) • All ETC’s updated except CT & CF. • Aug Pending BCR’s; •CF ETC •CT ETC •Bid Group #2 15% 10% 5% 0% 6 06 nJu LCLS FAC Meeting 6 r- 0 Ap 06 bFe 05 cDe 5 -0 ct O 05 gAu 05 nJu 5 r- 0 Ap 05 bFe 04 cDe 4 -0 ct O October 12-13, 2006 • CLOC to be descoped to maintain adequate contingency. Mark Reichanadter reich@slac.stanford.edu Major Schedule Variances Linac System: SPI = 0.72, CPI = 1.09 Linac (and Injector) controls hardware current installation. Work behind schedule but recovering. Linac Controls work, RF waveguides and vacuum hardware for 2007 installation being deferred to support immediate needs. Undulator System: SPI = 0.85, CPI = 0.92 Single Undulator Test (SUT) system development at ANL developed into a larger test than anticipated. SUT is nearing completion. SLAC’s Magnetic Measurement Facility (MMF) is not yet prepared for undulator segment tuning. The Undulator alignment monitoring HLS behind on hardware procurements. Increased SLAC-LCLS oversight to recover schedule. XES Controls System: SPI = 0.72, CPI = 1.07 XES controls effort has been focused on preparations for Injector installation and commissioning period. Replan future XES controls work. October 12-13, 2006 LCLS FAC Meeting 7 Mark Reichanadter reich@slac.stanford.edu Schedule Status Old Schedule – Critical Path (CP) - Und B.O. – install – FEL commission. Total float 213d to CD-4. Near CP – Undulator vacuum system, Undulator testing, New Schedule – Updating project schedule and CP with Turner BO milestones. Provides “Co-occupancy” Target dates allow installation prior to BO. Estimate ~60 days loss of float resulting from evaluation of bids, additional value engineering effort and possible options. Near-term L3 milestone performance 6/2/06 – 1st Article Undulator 1 Rcvd @ SLAC. Done – 6/12/06 7/10/06 – Award CF subcontracts Done, Group #1 packages out, Group #2 ~ready, NTP to Turner on Aug 1 7/28/06 – MMF Qualified & Ready to Measure Prod Undulators ~Aug 28. Benches are installed and measuring the first magnets. 8/21/06 – FY06 Shutdown: HW Reqd for Installation Aug 16 Conducted Hardware Installation Readiness Review Aug 30 Conducted Controls Installation Readiness Review 11/15/06 – Start Drive Laser Commissioning. On schedule October 12-13, 2006 LCLS FAC Meeting 8 Mark Reichanadter reich@slac.stanford.edu LCLS Organization Chart • Strengthened Senior Mgmt •APD-C •APD-E (TBD) •IMT • Procurement •Miller •Dee • Conv. Fac. •Turner •Jacobs T3 October 12-13, 2006 LCLS FAC Meeting 9 Mark Reichanadter reich@slac.stanford.edu LCLS Integration - IMT addresses the “5I’s” LCLS establishes IMT IMT under direction of RM Boyce Described under PMD 1.1-028 Integration management (gaps/conflicts) Review and ownership of Interfaces (ICD’s) CF-Tech leads identified for construction Installation readiness & planning Aug06 shutdown underway APD Engineer – To facilitate LCLS system engineering and inter-lab integration Interview process complete LCLS Design Reviews - ~35-40 have been conducted across the project to mature the design, validate progress and identify integration issues early. October 12-13, 2006 LCLS FAC Meeting 10 Mark Reichanadter reich@slac.stanford.edu LCLS design continues to mature Requirements Document Total No. Documents Number Approved Number in Sign-Off % Complete Global Requirements Document (GRD) 1 1 0 100 Physics Requirements Documents (PRDs) 79 61 0 77 Engineering Specification Documents (ESDs) 126 82 0 65 Management Physics Liaison Support Controls Injector Linac Undulator X-R Endstations Conventional Facilities XTOD 3 3 16 32 13 17 15 10 17 3 3 14 31 11 9 0 10 1 0 0 0 0 0 0 0 0 0 100 100 87 97 85 53 0 100 6 Room Data Sheets (RDSs) 51 51 0 100 Interface Control Documents (ICDs) 12 11 0 92 Injector Linac Undulator X-R TOD XES 3 4 1 2 2 3 4 1 2 1 0 0 0 0 0 100 100 100 100 50 269 206 0 ~76 Total October 12-13, 2006 LCLS FAC Meeting 11 Comments Complete LCLS Specs • 77% PRD’s • 65% ESD’s • Most open requirements are in photon area. Need to do better. Complete • 100% RDS’s • 92% ICD’s • IMT reviews ICD’s Mark Reichanadter reich@slac.stanford.edu LCLS Risk Registry Risk registry has been modified to provide a more tactical plan (FAC recommendation) System Managers identify and ‘own’ risk Improves consistency on risk characterization SM’s have authority and resources to prioritize risks. Risks reviewed each month at senior mgmt meeting Bulleted tasks identified to reduce risk Status punch list each month Avoid the broad, non-actionable risks October 12-13, 2006 LCLS FAC Meeting 12 Mark Reichanadter reich@slac.stanford.edu Near-Term Project Objectives Project Management Hire APD-Engineering Emphasize the IMT in resolving integration issues Cost Management Complete ETC’s and ensure remaining scope fits LCLS TPC Schedule Management Complete Injector / Linac shutdown effort safely Injector (RF Gun – BC1) Conduct Injector ARR and begin laser/injector commissioning Deliver 50% of undulators to MMF ~ Dec06 Monitor MMF measurement throughput Perform on civil construction, safe operations are a must to stay to cost/schedule. October 12-13, 2006 LCLS FAC Meeting 13 Mark Reichanadter reich@slac.stanford.edu Risks / Challenges Ahead Execution Phase – Safety is primary concern Fully staffed in ES&H, construction safety and oversight (UTR’s) Regular job site inspections, enforced procedures Aligned DOE, SLAC, Turner, Subcontractor team Technical / Quality – Missing scope/gaps are a risk Scrutinize ICD’s, LCLS / LUSI interface needs attention Improve technical specs, continue emphasis on design reviews Emphasize role and influence of IMT and APD-E Schedule - Installation activities and coordination IMT to facilitate installation planning Need to get APD-E on board Cost - Site conditions, field orders and staying to schedule CLOC descoped to maintain adequate contingency Recent bottoms-up ETC for the project Strong procurement and negotiating team in place October 12-13, 2006 LCLS FAC Meeting 14 Mark Reichanadter reich@slac.stanford.edu