SLAC National Accelerator Laboratory
ES&H Status of Construction and
Technical System Installations
Mike Scharfenstein
Project ES&H Coordinator
12 November 2008
CF Breakout - ESH
1
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
Construction Safety
November 17, 2008 – Substantial Completion
146 Days without lost time incident - Major Milestone
60 days w/o recordable – Major Milestone
Safety in GC managed work a disappointment
Aggressive Management Steps
Weekly Senior Executive - Conference Calls & On-Site Meetings
Increased LCLS & TCCo field staff
Full-Time On-Site Nurse
Full time DOE field presence
Lessons Learned
12 November 2008
CF Breakout - ESH
2
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
TCCo Incident Distribution
12
10
8
Procedural
Injuries
Notices
6
4
2
0
1st
Qtr
12 November 2008
CF Breakout - ESH
2nd
Qtr
3rd
Qtr
4th
Qtr
5th
Qtr
3
6th
Qtr
7th
Qtr
8th
Qtr
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
12 November 2008
CF Breakout - ESH
4
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
Construction Development
Safety Stewardship Meeting – Weekly
Analyze emerging issues
Define action items (R&R, Nurse, Mgt Walks)
LCLS
Modified staffing
UTR Safety Observation Training
TCCo
Job Hazards Analysis Re-invigoration (WP&C)
LIFE Training
Bottom Line
Communicate to Hands-on Craft and Immediate Supervisors LCLS
emphasis on safety.
12 November 2008
CF Breakout - ESH
5
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
Leading & Lagging Indicators
Lagging Indicators
Leading Indicators
Incident/Injury
Lessons Learned from
incidents lead to
improvements
Indicator of Poor …
Opportunity to Learn
More oversight and
involvement with work
planning and execution
Added Field Personnel
Work Planning
Work Execution
Work Oversight
Field Work Assessments
Assessed past performance
Developed Corrective
Actions
ISM / WPC
12 November 2008
CF Breakout - ESH
6
Superintendents
Lab UTRs
Added Occupational Safety
Nurse
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
Lessons Learned
a little more detail
APPLY ISEMS !
7 Guiding Principles & 5 Core Functions
Good for All; staff and contractors
Work Planning & Control
Contractor Selection
Needs to be thorough
Meet the team / know the work
Recent jobs / EMR
Work Planning & Control
Site Specific Safety Plan
Detailed R2A2s
Personnel competencies, Know the work –
including hazards, Perform the work w/I
controls, Feedback & Improvement
12 November 2008
CF Breakout - ESH
7
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
Work Planning and Control
a little more detail
SLAC has undertaken a lab-wide initiative to consistently
assure that work is planned and controls identified before
work is authorized to begin…
2006 downtime WP&C strategy
2007 LCLS begins dialog w/ NIF
2008 LCLS participating/driving process
w/I Lab & w/ contractors
Lesson Learned - Active Participation in Oversight
Be a part of the major work packages
Collaborate for success
Firm and Fair
12 November 2008
CF Breakout - ESH
8
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
Work Goals
Subcontracted Work Goals
CF & Technical Systems Installation
APPLY Integrated Safety Management
Direct subcontractor management
Detailed work planning
The goal is to maintain exemplary safety record
GC managed
Current performance acceptable
Maintain engagement of GC and subs
<30 days of field work remaining
area to watch = demobilization
The goal remains Zero future incidents
12 November 2008
CF Breakout - ESH
9
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
Conclusion
Apply ISEM
Work Planning & Control
Maintain CF & Technical System direct
managed work performance
Continue close work with TCCo
LCLS / Lab / SSO involvement
Past 6 months = acceptable performance
The goal remains Zero!
12 November 2008
CF Breakout - ESH
10
Mike Scharfenstein
scharf@slac.stanford.edu
SLAC National Accelerator Laboratory
end of presentation