Slac National Accelerator Laboratory Report to the LCLS Facilities Advisory Committee Mark Reichanadter LCLS Deputy Director Project Management Status Cost and Schedule Performance Funding, Obligations & Costs Milestones & Critical Path Procurement Status Risks & Mitigations Summary 11-13 November 2008 FAC Meeting LCLS Project Management M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Review Documentation LCLS Project Review information: http://www-ssrl.slac.stanford.edu/lcls/fac/2008november/index.html Back-up documentation Responses to June 2008 FAC Recommendations September 2008 Monthly Report Current LCLS Risk Registry Thumb-drives available Questions? Contact: Helen O’Donnell X3368, heleno@slac.stanford.edu Daphne Mitchell X5377, dmitchell@slac.stanford.edu 11-13 November 2008 FAC Meeting LCLS Project Management 2 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory LCLS Overview Focus is on three primary issues Safety – Construction and installation Construction nearly complete (Turner 98%) Installation safety management good so far. Endgame project planning Project 85% Complete, Line Item 88% Performance good so far, ~ on schedule Cost/Schedule contingency adequate Any upscopes need to be defined now. Transition into Operations/Science Mature commissioning plans. Ops is next. 11-13 November 2008 FAC Meeting LCLS Project Management 3 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Project Status LCLS performance is on track with baseline TPC = $420M (TEC = $352M, OPC = $68M) CD-4 = July 31, 2010 TPC >84% Complete, TEC >88% Complete Contingency on TEC = $17.7M 43% on remaining work Management Reserve on OPC = $8.9M 43% on remaining work LCLS received its full request under a CR TEC first five months FY09 funding + $5M OPC first five months FY09 funding 11-13 November 2008 FAC Meeting LCLS Project Management 4 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Project Performance LCLS Baseline Performance - September 2008 (AYK$) Work Accomplished % Complete Total Budget at Completion 1.1 Project Management 20,251 88.7% 22,822 1.2 Injector 20,239 100.0% 20,239 1.3 Linac 27,274 96.5% 28,257 1.4 Undulator 44,994 97.7% 46,065 1.5 X-ray Transport 22,372 79.5% 28,134 1.6 X-ray Endstations 3,407 35.9% 9,482 1.9 Conventional Facilities 121,374 88.0% 137,915 1.X Controls 1 LCLS Total Base Cost 33,382 293,293 80.7% 87.7% 41,362 334,277 WBS 2 LCLS Other Project Cost LCLS Total Project Cost (TPC) 11-13 November 2008 FAC Meeting LCLS Project Management LCLS Total Estimated Cost (TEC) 352,000 Available Contingency 17,723 % Contingency on ETC 43.2% 38,689 65.4% 59,123 LCLS Total Other Project Costs (OPC) 68,000 Available Mgmt Reserve 8,877 % Mgmt Reserve on ETC 43.4% 331,982 5 84.4% 420,000 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Project Performance (Sep08) TPC BCWS BCWP ACWP Obligations (cum) $336.4M $332.0M $330.9M $337.6M TEC (Line Item) Est at Complete (EAC) $338.1M Includes variances and Pending BCRs Includes upscopes for SXR Integr/Install and Hutch #6 EAC Cost to go contingency 30.7% Remaining Work (ETC) $ 45.3M ~$3M is under contract 11-13 November 2008 FAC Meeting LCLS Project Management 6 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Earned Value Indices LCLS Cost and Schedule Indices (TEC Only) 1.5 1.4 BCWP/BCWS (SPI) 1.3 BCWP/ACWP (CPI) 1.2 1.1 1.0 0.9 0.8 0.7 0.6 0.5 Rebaseline to address FY07 CR approved in Jan08. CPI & SPI performance steady 11-13 November 2008 FAC Meeting LCLS Project Management 7 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Cost and Schedule Variances LCLS TEC Cost and Schedule Variances 1,000 0 8 l-0 Ju 8 r- 0 Ap 08 nJa (1,000) AYK$ (2,000) (3,000) (4,000) (5,000) SV (6,000) CV (7,000) (8,000) SV due to delays in (Turner) construction and installation-related activities Recently improved, expected to continue 11-13 November 2008 FAC Meeting LCLS Project Management 8 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory TEC (Line Item) Performance 400000 ~$1.8M carry-forward 350000 300000 (AY$K) 250000 200000 150000 BCWS BCWP 100000 ACWP BA 50000 OBL 11-13 November 2008 FAC Meeting LCLS Project Management 9 FY 10 FY 09 FY 08 FY 07 FY 06 FY 05 FY 03 FY 04 0 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory DOE (Level 2) Milestone Performance LCLS DOE (Level 2) Milestones Delivery of Undulator 1st Articles to MMF Sector 20/Alcove Beneficial Occupancy MMF Qualified & Ready to Measure Prod Undulators Start Injector Commissioning (Drive Laser) Injector Accelerator Readiness Review (ARR) Comp Start Injector Commissioning(UV Beam to Cathode) Linac Water/Power Available Linac (Li20-Li30) Ready for Commissioning Start Installation of Undulator Facility BTH-UN-FEE-NEH-CUP Beneficial Occupancy Linac (Li20-Li30) Commissioning Complete Safety Analysis Document (SAD) Approved XT-FEH Beneficial Occupancy XT Start FEE Installation LCLS ARR Complete (BTH thru NEH) Start Linac-to-Undulator (LTU) Commissioning XT Start Tunnel Installation Start Undulator Commissioning (1st Light) 2-D Detector Shipped to SLAC Start FEE Commissioning with Beam First X-Rays into NEH - Initiate Early Ops XE Start Installation in FEH First X-Rays into FEH 11-13 November 2008 FAC Meeting LCLS Project Management 10 Baseline Date Actual 3-Jul-06 15-Jun-06 21-Jul-06 14-Apr-06 28-Aug-06 28-Aug-06 29-Jan-07 15-Dec-06 31-Jan-07 30-Mar-07 9-Apr-07 5-Apr-07 11-Jul-07 29-Mar-07 1-Dec-07 1-Dec-07 16-May-08 14-Aug-08 21-Jul-08 14-Aug-08 30-Jul-08 2-Apr-08 29-Aug-08 23-Sep-08 22-Oct-08 17-Nov-08 (P) 13-Jan-09 17-Apr-09 20-Apr-09 27-May-09 6-Jul-09 30-Jul-09 6-Aug-09 10-Sep-09 17-Sep-09 26-Feb-10 Variance -12 days -70 days 0 days -22 days 42 days -2 days -74 days 0 days 64 days 18 days -86 days 17 days 18 days (P) On Schedule Early Early On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule On Schedule M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Schedule Critical Path (CP) to CD-4 Undulator/FEE C.O. – install – FEL commission – Photons in FEH = ~108 working days Soft X-ray Mirror System = 109 days XE TUN/FEH PPS Shielding & Supports = 111 days Pop-Up Camera System = 113 days AMO readiness is tight for early science but not CD-4 Space Renovation B.O. = ~83 days Renovation of existing space has low technical risk Evaluating options to enhance the science program 11-13 November 2008 FAC Meeting LCLS Project Management 11 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Procurement Status Procurement and technical teams co-located 1 Manager, 1 Buyer (technical components) 1 Contract Administrator (A/E, CM/GC contracts) 1 Construction Buyer (Davis-Bacon contracts) Administer field changes and submittals 1 P/T Consultant (price and change negotiations) Weekly technical/procurement staff meetings Advance procurements monitored via APP’s LCLS <$10M procurement remain. ~$4.5M Space Renovation. ~$3-4M FEH Hutches. LUSI procurements will use same processes. SSO approval still required for >$500K. 11-13 November 2008 FAC Meeting LCLS Project Management 12 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Project Risks & Mitigating Actions Safety – Construction and Installation Fully staffed in ES&H, construction safety and oversight (UTR’s) Increased inspections, SLAC-enforced procedures, daily tool box meetings Hands-on safety management by LCLS, SLAC & DOE Recent performance improved, watch for complacency Cost / Contingency Analysis (End Game) Nov08 – Bottoms-up ETC on remaining work Monthly Estimate at Complete (EAC) analysis Construction claim set aside Looking at scope buy-backs to optimize science program CR – Does not appear to adversely impact on LCLS 11-13 November 2008 FAC Meeting LCLS Project Management 13 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory TEC Remaining Work PM 1% LN UN 0% 0% 0% XTOD 2% End Game Planning XES 2% CF 5% Remaining costs still dominated by CF CT 2% Hutches, Space Renovation Potential Claims Photon Systems Other Project Costs Re-estimate remaining costs Update schedule logic Resource rates Contingency estimates Upscopes to enhance science 88% Work Complete LCLS TEC Remaining Work (AYM$) 11-13 November 2008 FAC Meeting LCLS Project Management 14 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Project Risks & Mitigating Actions Transition from project to a science/user facility Reorganize LCLS Directorate Accelerator System Division Transition from PPA Directorate to LCLS Experimental Facilities Division Manage photon operations, User administration, outreach New Directorate – need to staff up. Strategic Projects Division LCLS/LUSI projects (focus is project delivery) Engineering and Physics Division Centralize technical staff for customer support (XFD, SPD, ASD) Common standards and configuration control Started to document LCLS “lessons learned’ Business Office Centralize business systems for ops and project management Scope-driven WBS for LCLS (to be SLAC-wide) 11-13 November 2008 FAC Meeting LCLS Project Management 15 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory LCLS Directorate Organization LCLS Directorate Define and deliver the transformational potential of Ultrafast photon science through efficient and effective operation of the Linac Coherent Light Source as a BES User facility Accelerator Systems Division Experimental Facilities Division Deliver the LCLS quality beam in a sustainable and efficient manner that meets the needs of the user program Deliver the instrument systems and user administration activities necessary for efficient performance of a user based research program Business Office Engineering Physics Division Strategic Projects Division Deliver the enabling Infrastructure necessary for efficient operation of LCLS Deliver the approach, resources, and standards, to optimize the configuration of LCLS in a reliable, available, and maintainable manner Deliver the planning and implementation of next generation upgrades and major modifications of LCLS 11-13 November 2008 FAC Meeting LCLS Project Management M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory Summary Overall, LCLS making steady progress Construction (Turner) phase near completion Cost and schedule performance good so far Contingencies adequate to address project risks Bottoms-up ETC for remaining work, add in any final upscopes Regular EAC and contingency calculations to manage endgame Challenges ahead: Safety management of (Turner) construction and installation activities Optimize LCLS science with endgame of TEC and OPC Transition of LCLS into science and operations. 11-13 November 2008 FAC Meeting LCLS Project Management 17 M. Reichanadter reich@slac.stanford.edu Slac National Accelerator Laboratory End of Presentation 11-13 November 2008 FAC Meeting LCLS Project Management 18 M. Reichanadter reich@slac.stanford.edu