Linac Coherent Light Source Overview

advertisement
Linac Coherent Light Source Overview
29 October 2007




Project status, effects of continuing resolution
Continuing resolution, revised estimate-to-complete
Organization
Preparation for experiment operations
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
LCLS Cost/Schedule Status Report
31-Aug-07
Cumulative to Date ($K)
WBS
Budgeted Cost
Work
Scheduled
Variance
Actual Cost
Work
Performed
Work
Performed
Schedule
Budget At
Complete
($K)
Performance Indices
Cost
SPI
CPI
% Complete
1.1 Project Management
16,203
16,203
17,264
0
-1,061
1.00
0.94
18,013
90%
1.2 Injector
16,722
16,615
20,083
-106
-3,467
0.99
0.83
16,760
99%
1.3 Linac
15,032
13,335
17,076
-1,698
-3,742
0.89
0.78
19,940
67%
1.4 Undulator
31,219
26,324
31,057
-4,895
-4,733
0.84
0.85
37,398
70%
1.5 X-ray Transport
19,231
13,125
15,579
-6,106
-2,454
0.68
0.84
22,803
58%
3,380
2,043
1,960
-1,337
83
0.60
1.04
8,735
23%
1.9 Conventional Facilities
79,453
70,328
68,607
-9,124
1,721
0.89
1.03
127,438
55%
1.X LCLS Controls
26,148
18,142
20,083
-8,006
-1,941
0.69
0.90
32,366
56%
207,387
176,114
191,709
-31,273
-15,594
0.85
0.92
283,453
62%
1.6 X-ray Endstations
1 LCLS Total Base Cost
LCLS Total Estimated Cost
315,000
Contingency
2.1 LCLS Project Mgmt, Planning & Admn (OPC)
31,547
11,730
12,145
11,476
415
669
1.04
1.06
30,195
40%
3,984
2,314
3,781
-1,670
-1,467
0.58
0.61
5,317
44%
742
318
488
-424
-170
0.43
0.65
3,232
10%
2.4 Undulator (OPC)
3,204
2,901
749
-303
2,152
0.91
3.87
6,852
42%
2.5 X-ray Transport (OPC)
1,156
1,099
1,010
-57
88
0.95
1.09
4,544
24%
2.6 X-ray Endstations (OPC)
1,971
1,698
1,009
-273
689
0.86
1.68
5,559
31%
2.2 Injector (OPC)
2.3 Linac (OPC)
2.9 Conventional Facilities (OPC)
292
0
0
-292
0
0
0
683
0%
2.X LCLS Controls (OPC)
650
68
114
-582
-46
0.10
0.60
1,129
6%
23,728
20,543
18,627
-3,185
1,917
0.87
1.10
57,511
36%
2 LCLS Total Other Project Cost
LCLS Other Project Cost
64,000
Management Reserve
LCLS Total Project Cost
231,115
29 October 2007
LCLS Facility Advisory Committee
196,658
210,335
-34,458
-13,678
6,489
0.85
John N. Galayda
galayda@slac.stanford.edu
0.93
379,000
58%
Project Baseline
May 2005
Proposed Baseline
Change September 2007
TEC $315M, TPC $379M
TEC $352M, TPC $420M
CD-4 3/09 Start of
Operations
Level 2 DOE milestone
7/09 Start Near Hall Ops
Characterize x-ray flux @ 1.5
Angstroms, in front end
enclosure (FEE)
Detect X-rays in the Far
Experiment Hall
29 October 2007
LCLS Facility Advisory Committee
Characterize x-ray flux at 1.5
Angstroms, in the Front-end
enclosure
CD-4 7/2010 Project
Complete
Detect X-rays in the Far
Experiment Hall
John N. Galayda
galayda@slac.stanford.edu
Status of Baseline Change
Lehman review 7/2007, follow-up 9/2007
EIR 10/2007
Draft report due 10/26/2007
Review went well
Approval of new baseline by 12/2007
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
FY2008 contingency risks and handling
Limited Budget Authority in FY2008
If contingency use in 2008 is too high:
Delay start of installation of undulator to “just in
time” with respect to schedule for x-ray flux
measurement in July 2009 - ~ $3M BA released
in FY2008
The risk handling plan reduces the available
commissioning time
CD-4 achievable on schedule (7/2010)
Reduced performance in early operations
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Contingency available by year
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Handling Plan
Delay installations to start of FY2009
Undulator
Beam Dump
Front End Enclosure
>$3M moved out of FY2008
Just-in-time for AMO installation
No FEL commissioning 10/2008-3/2009
Two-shift installation to reduce lost commissioning to
recover commissioning time
Decision Points for delay/go ahead:
12/2007 and thereafter
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Cost to Go, scheduled thru 2008
120,000
100,000
80,000
60,000
40,000
20,000
0
Jul-07
Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08
1.01 LCLS PROJECT MGMT, PLANNING & ADMN (TEC)
1.03 LINAC SYSTEM
1.05 X-RAY TRANSPORT & DIAGNOSTICS SYSTEMS
1.02 INJECTOR SYSTEM
1.04 UNDULATOR SYSTEM
1.06 X-RAY END STATION SYSTEMS
1.09 CONVENTIONAL FACILITIES
1.X CONTROLS
29 October 2007
LCLS Facility Advisory Committee
Jul-08
John N. Galayda
galayda@slac.stanford.edu
Aug-08 Sep-08
Contingency Mgmt: X-ray speedups
If more FY08 funds become available, one could:
Speed up controls and stands for FEE (1000k)
Speed up X-ray monitors in FEE (300k)
Speed up NEH controls and motors (450k)
Speed up XES laser system (340k)
Speed up AMO focusing mirrors (115k)
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Schedule Highlights
Early installation in new tunnels
December 2007
LCLS Linac installation complete
January 2008
Early start of Near Hall Operations
7/2009
End Station Systems delayed to preserve
contingency in FY2008
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Commissioning
Injector
All performance goals for the LCLS injector have been
met
Gun laser - 98% availability in over 3,000 hours of
operation in support of commissioning
Some work left on BC1, x-band cavity
Linac, BC2
Commissioning to begin in January
Faulty magnet coil may delay BC2 commissioning
Adequate commissioning time available in 2008
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Undulator vacuum chamber
Al extrusion design
Machining tests successful
Dimensional tolerance met
Internal polishing trials have yielded good results
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Undulator Magnetic Measurement
39 undulators are at SLAC.
The MMF is in production mode
15 undulators tuned/fiducialized
Girder/mover assembly underway at IL vendor
Undulator quadrupole accepted
Measurements indicate trim winding
is compatible with beam-based
alignment
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Photon Beam Systems
XTOD and XES affected significantly by the 2007 CR
New plan allows recovery with extended project, phased
completion
XTOD is in procurement phase, XES still in design
Manpower in controls area has been increased
Should be ready for early occupancy of expt’l areas
Coordination with LUSI is going well
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
XTOD Status
Procurements have begun
Most design reviews are done
Staying on new schedule
LLNL team is working well with SLAC
Award Low-Energy mirror PO
Award High-Energy mirror PO
7-2007
11-2007
Far Hall
First instrument ready to ship to SLAC 12-2007
Start FEE installation
29 October 2007
LCLS Facility Advisory Committee
8-2008
John N. Galayda
galayda@slac.stanford.edu
Recent ESS organizational progress
Added support in Controls/data acquisition
Added G. Haller as CAM for controls/data handling
effort for LCLS X-ray groups and for LUSI
Shifting people from Accelerator to X-ray area as work
progresses
Developed integrated installation/commissioning
plan
Under leadership of R.M. Boyce
Involves Accelerator, X-ray, Physics groups
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
XES Status
CR caused delays
Now in design phase
AMO instrument design going well
2-d detector development going well
Controls area was behind, catching up
Working with Radiation Physics on PPS
items
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
LUSI Project
Instrument scientists on board
Very successful DOE Conceptual Design Review
CD1 approved
Continuing Resolution affecting procurements
LUSI-LCLS Interface Working Group recent business:
Conventional facilities
Details of hutch design, rack placement, etc.
Controls/Data acquisition
Details of data flow, storage, interface to detectors
Precisely defining LUSI/LCLS interfaces
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Conventional Facilities
Start-of-Installation Dates
Schedule performance has been good
Beam
Transfer
DEC07
Undulator
Hall
DEC07
Central Utility Plant
DEC07
Near Experimental Hall
DEC07
Beam Dump
DEC07
Front End Enclosure
DEC07
Xray/Diagnostics
JAN08
Far Experimental Hall
MAR08
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Construction Access, X-Ray Transport Tunnel
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Far Experiment Hall, Mid-Height Heading
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
LCLS
LCLS Scientific Expts
TBD
LUSI/LCLS
Instruments
Hastings
Hall Ops
John Arthur
Engineering
Fornek
User Program
ASD
John Seeman
Operations Group
Erickson
Laser Group
W. White
Beamline support
29 October 2007
LCLS Facility Advisory Committee
LCLS Accel Ops
Planning
Schultz
PEP-II/ESA/SABER
Test Beams
LCLS Accel Phys
Emma
A Very important
position to fill
ASAP
Maint/upgrade
planning
John N. Galayda
galayda@slac.stanford.edu
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Linac Operations Budget 2008
2/3 HEP – 1/3 BES in 2007
1/3 HEP – 2/3 BES ($65.5M) in 2008
3/3 BES ($96.7M) in 2009
Start LCLS transit to operations in 2008 for
Commissioning team
CF
Laser Group
Transit of ASD from PEP Operation to LCLS Operation
Begins modestly in 2008
100% in 2009
Persis Drell, Transition Working Group have prepared for
this transition throughout FY2007
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Instrument Commissioning
Responsibility of LCLS & LUSI Instrument
Scientists, Supported by Instrument Teams
Work to achieve performance requirements for first
approved experiments
Likely to reach soft x-ray capability first
First experiments scheduled thereafter
Judicious balance:
Operations time for experiments that are less demanding
of FEL performance (photons/pulse, timing, pulse
duration, etc)
Commissioning time for FEL improvement
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
First Experiments
Instruments will be operated by LCLS, in
support of approved experiments
“Facility” lasers operated/maintained by
SLAC
AMO and XR pump/probe available in 2009
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Summary
Performance of LCLS Injector meets
specification for 1.5 Angstrom SASE
A long way to go
Bunch Compression
Undulator tuning and alignment
Electron trajectory control
Looking forward to seeing the first LCLS
experimenters
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Summary
LCLS Turn-on has gone superbly
2008 is a narrow passage for the Project to pass through
Limited $ contingency
Scope contingency identified
Downstream to upstream
2009 first Near Hall Operations
2008 contingency control is crucial to this goal
Revised ETC puts the Project back on track for successful
completion
LCLS Project organization will transform to LCLS operating
organization
I will do my utmost to get this transition right
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Charge to FAC
Undulator system integration- FAC is asked
to list risks, with emphasis on
Girder setup and testing
Vacuum system design OTHER THAN extrusion
SLAC/ANL coordination
Diagnostics
Radiation protection
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Charge to FAC
LUSI, Photon Systems integration- FAC is
asked to list risks, with emphasis on
schedule pressure due to
Impacts of 2007 CR on LCLS
Impacts of 2008 CR on LUSI
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
Charge to FAC
Controls, Data Acquisition and Applications
software: identify risks with emphasis on
High-speed data acquisition
Schedule for development of data archiving
Conventional Facilities
Conditions at early occupancy
Safety on the construction site
Contingency burn rate
SLAC, Turner Const. Co roles/responsibilities
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu
End of Presentation
29 October 2007
LCLS Facility Advisory Committee
John N. Galayda
galayda@slac.stanford.edu