Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz / SLAC April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu Agenda Scope Schedule Budget Safety April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu SLAC Site Plan SLAC Main Gate Research Office Building Pep Ring Road CEH Sector 25 Bldg #28 Sector 20 Upstream LCLS General Work Boundary Research Yard April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu Scope Systems Description remain unchanged Sector 20 Injector Facility – completed in May 2006 Magnetic Measurement Facility – completed in April 2006 Linac Improvements – to be completed in 07 shutdown Beam Transport Hall – in process ~ 15% complete Undulator Hall – in process ~ 5% complete Front End Enclosure – in process 5% complete Electron Beam Dump – in process ~ 5% complete Near Experimental Hall – in process ~ 35% complete X-Ray Transport & Diagnostics Tunnel – in process ~ 5% complete Far Experimental Hall – in process ~ 10% complete Lab infrastructure - design is imminent Any changes made to the CF scope resulting from VE adjustments have no impact the technical systems Modifications to the scope are coordinated with the Integration Management Team (CF direct liaison) Scope is well defined and understood by LCLS and the CMGC April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu Scope Systems Description Sector 20 Injector Facility – completed in May 2006 Magnetic Measurement Facility – completed in April 2006 Linac Improvements – to be completed in 07 shutdown Beam Transport Hall – in process ~ 15% complete Undulator Hall – in process ~ 5% complete Front End Enclosure – in process 5% complete Electron Beam Dump – in process ~ 5% complete Near Experimental Hall – in process ~ 35% complete X-Ray Transport & Diagnostics Tunnel – in process ~ 5% complete Far Experimental Hall – in process ~ 10% complete SLAC Space Renovations for LCLS Operations - design is imminent Any changes made to the CF scope resulting from VE adjustments have no impact the technical systems Modifications to the scope are coordinated with the Integration Management Team (CF direct liaison) Scope is well defined and understood by LCLS and the CMGC April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu SLAC Space Renovations for LCLS Operations Completion dates are compliant with LCLS mission objectives April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu Beam Transport Hall – 227m long above grade facility to transport the electron beam through the existing RSY Undulator Hall – 170m long underground tunnel housing undulators and ancillary equipment Near Experimental Hall – underground facility whose primary function is to house 3 experimental hutches, prep and shops Far Experimental Hall – underground single 46’ cavern to house 3 experimental hutches and prep space Electron Beam Dump – 40m long underground facility used to separate the electron and x-ray beams Front End Enclosure – 40m long underground facility to house various diagnostic equipment in support of the photon beam ~100’ location of tunneling to date in access tunnel X-Ray Transport & Diagnostics Tunnel – 200m long underground tunnel used to transport photon beams from NEH to FEH April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu Schedule Original LCLS CF schedule indicated 28 months for the entire scope (including the CLOC) Approved schedule (Jan 07) from CMGC for Beam-Path construction presented by TCCo and approved by LCLS (Aug 06 – June 08) indicates 22 months plus 2-3 months for close-out (as-builts, O&M manuals, etc) Concerns have developed with significant negative float being reported against Co-Occupancy milestones in monthly schedules within the initial 90 days of approved Baseline Schedule LCLS has made several requests for recovery plan schedule CMGC has suggested recovery options that are currently being reviewed and analyzed Beneficial Occupancy milestones are threatened April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu BTH Headhouse Rebar at Slab April 16, 2007 Status of Construction BTH Headhouse Slab Headwall # David Saenz saenzd@slac.stanford.edu Road header for UH April 16, 2007 Status of Construction UH initial penetration of portal # David Saenz saenzd@slac.stanford.edu Budget To Date For Civil Construction CMGC Fee - $12M Beam Path awarded to date totals $76.4M Bid Groups #1 and #2 (X bid packages) awarded to TCCo as contract modifications Remaining to be awarded $.2M - Pending Bid Packages Misc. accessories/toilet partitions, etc Awaiting LCLS CF technical direction Field Change Orders have been in low 6% range – see breakout session April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu Budget To Date For Civil Construction – cont’d Remaining to be negotiated CLOC descope Awaiting final pricing from TCCo for trade costs LCLS issued unilateral contract modification for CMGC credit of $1.4M (included in Beam Path cost to date) Addendum #2 Awaiting final pricing from TCCo for trade costs Addendums #3 and #4 to be submitted for pricing No current impact to schedule Several scope adjustments In process for submission to TCCo Major recent utility change order ~ $400K DW utility rupture ~ $200k April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu Summary Scope and schedule for CF WBS is well understood Budget is closer to being fully defined Construction activities in the field are demonstrating activities in parallel, slight gain to schedule Overall construction schedule requires immediate attention!! April 16, 2007 Status of Construction # David Saenz saenzd@slac.stanford.edu